You are on page 1of 11

Available online at www.sciencedirect.

com

International Journal of Project Management 29 (2011) 604 – 614


www.elsevier.com/locate/ijproman

An empirical examination of project contractors' supply-chain cash flow


performance and owners' payment patterns
Hong Long Chen⁎
Department of Business and Management, National University of Tainan, No. 33, Sec. 2, Shu-Lin St., Tainan 700, Taiwan

Received 31 August 2009; received in revised form 31 March 2010; accepted 8 April 2010

Abstract

Supply-chain (SC) cash flow performance is an essential component of SC performance management. Despite the panoply of approaches to SC
cash flow modeling, relatively few published studies assess the effect of SC cash flow performance on a project contractor's financial
performance. Little research thus explores the behavioral patterns in the project owner–contractor dyad in the context of payment-term negotiation
for improving the SC cash flow performance of a project contractor. Using data from 42 Taiwanese construction project contracting corporations,
this paper systematically quantifies the effects of SC cash flow performance on the financial performance of construction project contractors.
Further analysis using data from 118 returned, usable surveys reveals important behavioral patterns of project owners regarding payment terms
with project contractors during the contracting phase of construction projects. These behavioral patterns provide project contractors with a base for
supporting implementation efforts for improving SC cash flow performance.
© 2010 Elsevier Ltd. and IPMA. All rights reserved.

Keywords: Project contractor; Supply-chain performance; Cash flows; Financial performance; Payment behavior

1. Introduction contracting industry. The first objective of this study, therefore,


is to examine and quantify systematically the effects of SC cash
Hendricks and Singhal (2003) herald supply-chain manage- flow performance on financial performance of construction
ment (SCM) as the next source of constructing, supporting, and project contractors so that stakeholders can better measure the
winning competitive advantage. Many studies focus on financial impact of improved SC cash flow performance.
improving supply-chain (SC) performance through synergistic The second objective of this study is to analyze how the project
integration of SC components (e.g., Andersen and Christensen, owner–contractor dyad behaves in the context of payment-term
2005; Dainty et al., 2001; Elmuti et al., 2008; Hill et al., 2009; negotiations for improving the SC cash flow performance of
Lee et al., 2007; Zailani and Rajagopal, 2005), but others claim construction project contractors. Such analysis especially benefits
that strong correlations exist between excellence in financial construction project contractors by providing appropriate strate-
performance and management of SC material, SC information, gies to negotiate with the owners regarding payment terms that
and SC cash flows (e.g., Christensen et al., 2007; Comelli et al., expedite cash inflows and improve SC cash flow performance.
2008; Ellram and Liu, 2002; Farris and Hutchinson, 2002; The rest of the paper is organized as follows. Section 2 reviews
Lanier et al., 2010; Fawcett et al., 2007). related studies. Section 3 presents the research questions and
Even though previous evidence supports most of those claims, methodology. Section 4 describes the collection of the samples.
little evidence exists that systematically links SC cash flow Section 5 presents a useful relationship between SC cash flows
performance to financial performance in the construction- and financial performance, followed by a robust regression-
modeling procedure. Section 6 presents the behavioral analysis of
⁎ Tel.: +886 6 260 6123x7741; fax: +886 6 260 6173. project owners' payment terms. Section 7 discusses the implica-
E-mail address: along314@mail.nutn.edu.tw. tions of the research results. Section 8 summarizes the paper.
0263-7863/$ - see front matter © 2010 Elsevier Ltd. and IPMA. All rights reserved.
doi:10.1016/j.ijproman.2010.04.001
H.L. Chen / International Journal of Project Management 29 (2011) 604–614 605

2. Background cash flows. They conclude that payment lags, components, and
frequency significantly affect cash flows from the test results of
A supply chain (SC) is an integrated process wherein raw three-way factorial experiments. More recently, Chen (2007)
materials are manufactured into final products, then delivered to models cash flows using the combined methods of transformed
customers through distribution, retail, or both (Cohen and Moon, time-series data, multivariate regression analysis, Yule–Walker
1990). Supply-chain management (SCM) is the process of estimates, and incomplete-principal component regression anal-
planning, executing, monitoring, and controlling the operations ysis. Recently, Görög (2009) develops a comprehensive model to
of the SC (Lee et al., 2007). Along this chain, three major flows allow contractors to plan and control project cash flows, as well as
exist, including material, information, and cash flows. These SC estimate the optimal competitive contract price of a project.
flows have drawn much attention from researchers and practi- Although a large number of studies acknowledge the
tioners alike because of their important impact on SC performance. importance of SC cash flow modeling (e.g., Hwee and Tiogn,
Despite the equivalent importance of these flows, most 2002; Kaka and Lewis, 2003; Motawa and Kaka, 2009), limited
published SC studies focus on material and/or information studies explore the relationship between cash flow and financial
flows (e.g., those published studies concerning information flows performance in SCM. Recent research performed by Ellram and
include Anand and Goyal (2009), Bayraktar et al. (2010), Chae Liu (2002), Lanier et al. (2010), Lo et al. (2009), and Tsai (2008)
et al. (2005), Fawcett et al. (2009), and Lin et al. (2002); those recognizes a trend in which more corporate executives are
concerning material flows include Richey et al. (2008), Arnold extending the SC manager's accountability from functional
et al. (2009), Sheu (2005), and Vachon and Klassen (2002); and efficiency to organizational efficiency such as financial
those concerning material and information flows include performance.
Baghdasaryan et al. (2010), Hill et al. (2009), and Naylor et al. As a result, understanding the relationship between SC cash
(1999)). Relatively few published studies address SC cash flows. flow and financial performance better is essential to SC and
Furthermore, most of the published studies that propose to financial managers. The establishment of such a relationship is
study cash flows in SCM focus on cash flow modeling (e.g., particularly important to construction contracting because the
Comelli et al., 2008; Kaka and Lewis, 2003; Tsai, 2008; Motawa industry not only has been characterized by low and unreliable
and Kaka, 2009), as reliable cash flow estimation provides the profitability, but has long been recognized as an industry with
groundwork for effective management of working capital. For more aggressive manipulation of cash flows in SCs (Chen, 2007;
example, Badell et al. (2005) develop a cash flow model to Chen et al., 2005; Kaka and Lewis, 2003; Sorrell, 2003). Thus, the
optimize cash flow and cash position in the end of each period first objective of this study is to systematically examine and
based on a mixed-integer linear program (MILP) scheduling quantify the effects of SC cash flow performance on the financial
algorithm for batch-chemical-process industries. performance of construction project contractors, enabling con-
More recently, Tsai (2008) uses an autoregression model to struction SC and financial managers to better measure the impact
develop a cash flow model that assesses the SC-related cash flow of improved SC cash flow performance on financial performance.
risks for a manufacturing firm measured by the standard The second objective of this study is to analyze the behavioral
deviations of cash inflows, outflows, and net flows of each patterns in the project owner–contractor dyad in the context of
period in a planning horizon. Comelli et al. (2008) estimate a payment-term negotiation for improving SC cash flow perfor-
multinational company's cash flows created by SC tactical- mance of construction project contractors.
production planning based on a combined Architecture of
Integrated Information Systems (ARIS) and Activity-Based 3. Research questions and methodology
Costing (ABC) modeling methodologies. Comelli et al. (2009)
further develop a mathematical model for optimizing cash flow To support the analysis of the relationship between SC cash
and value sharing in the context of SC planning. flow and financial performance, this study selects the cash
In particular, the construction-contracting industry is a project- conversion cycle (CCC) and the return on sales (ROS) metrics to
based industry where a product (project) represents a large measure their corresponding performance. Though ROS, return
proportion of a firm's total sales and expenses (Kaka and Lewis, on assets (ROA), and return on stockholders' equity (ROE) are
2003). This unique characteristic differentiates the industry from common measurements of financial performance (Wild, 2003;
manufacturing and service industries. One group of authors (e.g., Wild et al., 2004), this study uses ROS because ROA and ROE are
Chen et al., 2005; Cheng et al., 2009; Hwee and Tiogn, 2002; heavily subject to the manipulation of a company's total assets
Kaka and Lewis, 2003; Motawa and Kaka, 2009) thus proposes to and financial leverage, respectively, which could bias the research
model SC cash flows using S-curve models, which employ findings.
historical project data to determine the relationship between CCC is a composite metric that describes the average number
project construction time and project cumulative sales and/or cost of days required to turn a dollar invested in raw materials into a
in percentage, and therefore generate cash flows by combining dollar collected from a customer (Stewart, 1995). CCC comprises
that relationship with the project contract values. days-in-payable, days-in-inventory, and days-in-receivable,
For example, Kaka and Lewis (2003) devise a cash flow where days-in-payable is the number of days' credit before a
estimation model that accounts for both known and unknown firm pays its suppliers and subcontractors, days-in-inventory is
individual projects at the time of the forecast. Chen et al. (2005) the length of the manufacturing process and the number of days
investigate the influence of construction SC payment terms on that the finished goods remain in the firm before they are sold, and
606 H.L. Chen / International Journal of Project Management 29 (2011) 604–614

days-in-receivable is the average collection period from the firm's contractors would likely provide more effective and reliable
customers (Wild, 2003; Wild et al., 2004). results.
The CCC metric is a key performance indicator of SC cash The methodology to answer the research question is twofold.
flows because the metric not only bridges across inbound material First, this study develops a series of test hypotheses concerning
and service activities with suppliers and subcontractors, through the behavioral patterns of project owners negotiating payment
manufacturing operations, and to the outbound sales activities terms with contractors. Second, this study uses the combined
with customers, but the metric also indicates the value of net cash categorical experiments and Pearson's correlation tests to
flows (Farris and Hutchinson, 2002; Lanier et al., 2010; Lo et al., examine these hypotheses (Ott, 1993).
2009; Tsai, 2008).
Thus, in accordance with the first objective of this study, the 4. Data sources
first research question was posed:
This study carried out the data collection in two phases. In the
Research question 1: What percentage change in a first phase, the financial data collection focused on the publicly
construction project contractor's financial performance is owned construction-contracting companies listed on the con-
explained by a change in the contractor's SC cash flow struction sector of the Taiwan Stock Exchange, because the
performance? balance sheets and income statements of the private companies
were difficult to obtain. For each sample firm, the balance sheets
The performance of a firm's SC cash flows is measured by and income statements were hand-collected from 1999Q1 and
CCC, whereas ROS is used to measure the financial performance 2008Q4. Data was gathered using case-study research protocols
of that firm. The methodology to answer the research question is (Yin, 2003), including use of multiple data sources (where
threefold. First, after developing a test hypothesis, this study uses possible) to ensure quality of the data collected.
Pearson's correlation tests to examine the cross-sectional In total, 52 firms were listed on the construction sector of the
longitudinal relationships between the ROS and CCC metrics. Taiwan Stock Exchange between 1999Q1 and 2008Q4. Some of
Because CCC is expressed in a different unit of measurement these firms were excluded from the sample. Six firms were
than ROS, a common measure is needed to compare the two. excluded because their primary activity was consulting or agency
Because the basic rationale of this study is that changes in a rather than construction. Another four firms were excluded due to
contractor's ROS are correlated with changes in CCC, a change- missing or unavailable financial data. Hence, the sample for
ratio method is therefore used. The mathematical expression of analysis was reduced to 42. Because the disclosure of monthly
the change ratio and the test hypothesis are shown in the financial statements is not mandatory for public companies in
Hypothesis and results section. Taiwan, this study uses quarterly data as the basis for analysis.
Second, multivariate robust regression analysis is used for The search generated 40 observation data sets for each sample
initial model building, followed by heteroskedasticity and firm.
specification-error tests. Use of robust regression analysis not In the phase two, the data collection was by survey and focused
only dampens the influence of outlying observations but also on gathering information about the common payment terms
ensures that the forecasts and estimation of the model are unbiased construction project contracting firms had with project owners,
when the normality of the residuals is violated (Neter et al., 1996). especially regarding the payment lag, components, and frequency
Third, for the purposes of model restructuring due to variables of those payment terms, which significantly affect cash
autocorrelation and multicollinearity, the study uses a subsequent flows in a SC (Chen et al., 2005). Payment lag is defined as the
application of Yule–Walker estimates (Shumway and Stoffer, time between the approval of an application for payment and the
2000) and incomplete-principal component analysis (Littell and actual disbursement of funds; payment frequency is the number of
Freund, 2000). payments made per month; payment component is the proportion
To further investigate how project owners in construction of payment attributable to labor or materials. The payment lags for
SCs might respond to the negotiation of payment terms as a these percent-labor and percent-material variables are further
consequence of contractors' cash flow manipulation during the defined as labor time lags and material time lags, respectively.
contracting phase of projects, the second research question was
posed: 5. Relationship between SC cash flow performance and
financial performance
Research question 2: How do project owners behave
regarding payment terms with contractors during the 5.1. Hypothesis and results
contracting phase of projects?
The study uses the balance sheet and income statement data of
This study uses contractors rather than project owners as the the 42 firms collected from the Taiwan Stock Exchange to
basic unit of analysis because a contractor is likely to work for investigate and model the cross-sectional longitudinal relation-
several project owners. Each of these project owners typically has ships between the SC flow and financial performance. Before
payment terms specified in its contract with the contractor, building the model, developing a test hypothesis for statistically
creating a data set that contains a range of possible conditions verifying that changes in a firm's SC cash flows significantly
regarding payments from project owners. Thus, querying correlate with changes in the firm's financial performance is
H.L. Chen / International Journal of Project Management 29 (2011) 604–614 607

necessary. Derived from the change ratio defined in the previous the probability of an increase in ROS for time t is high. A
“Research questions and methodology” section, the change ratio significant negative correlation between ΔCR5t and ΔCR1t
that measures changes in the level of performance can be implies that as a contractor's CCC for time t decreases (that is,
mathematically expressed as the following: the contractor's CCC improves), the probability of an increase in
ROS for time t is high.
Vjt −Vjðt−1Þ
ΔCRjt = ð1Þ
jVjðt−1Þ j 5.2. Cross-sectional time-series regression model building
where Vjt and Vj(t − 1) denote the values of the tth and (t − 1)th time-
As suggested by the test result of the null hypothesis,
series observations of variable j, respectively, and jVj(t − 1)j is the
significant correlations exist between changes in contractors'
absolute value of Vj(t − 1). Together with the CCC and ROS metrics
financial performance at time t (ΔCR1t) and contractors' SC
shown in Table 1, the following null hypothesis was established.
cash flows at time t (ΔCR2t, ΔCR3t, ΔCR4t, and ΔCR5t) in the
Ho. Nonsignificant correlations exist between changes in the construction-contracting industry. The robust regression anal-
contractors' financial performance at time period t (ΔCRjt, ysis with a maximum R-squared improvement procedure was
where j = 1) and those of the contractors' SC cash flows at time further used to model these significant correlations, minimizing
period t in the construction-contracting industry (ΔCRjt, where the sum of the absolute deviations of the dependent variable's
j = 2, 3, 4, 5). observations from its mean and resulting in the maximum value
The left-hand side of Table 2 lists the results of Pearson's of R-squared. The right-hand side of Table 2 summarizes the
correlation tests of the null hypothesis. Correlation is judged to analysis results.
be significant when the probability value is smaller than the As seen in the table, the optimal cross-sectional model at step
threshold value of 0.05. As seen in the table, the Pearson 1 (Model 1) is the one with the ΔCR3t variable, where 2.03% of
correlation coefficients of ΔCR2t, ΔCR3t, ΔCR4t, and ΔCR5t are the variation in the ROS data is explained. At step 2, the optimal
− 0.16 with a p-value of b 0.01, − 0.16 with a p-value of b0.01, cross-sectional model (Model 2) is composed of ΔCR3t and
0.06 with a p-value of b 0.05, and − 0.10 with a p-value of ΔCR5t, capable of explaining 1.57% of the variation in the ROS
b 0.01, respectively. The null hypothesis is therefore rejected, data, which is 0.46% less than that of Model 1. The optimal
implying that significant correlations exist between changes in cross-sectional models at steps 3 and 4 (Models 3 and 4) are
contractors' financial performance and the contractors' SC cash composed of (ΔCR3t, ΔCR5t, and ΔCR2t), and (ΔCR3t, ΔCR5t,
flows. Specifically, a significant positive correlation between ΔCR2t, and ΔCR4t), respectively. The corresponding R-squares
ΔCR4t and ΔCR1t suggests that when a contractor's days-in- of Models 3 and 4 are 2.14% and 2.13%, suggesting that Model
payable for time t has increased (that is, the performance of the 3 is the optimal model.
contractor's days-in-payable has improved), the probability of The bottom of Table 2 shows the chi-square values of the
an increase in ROS for time t is high. White test (White, 1980) for Models 1 to 4. The White test
A significant negative correlation between ΔCR2t and ΔCR1t establishes whether the residual variance of a variable in a
suggests that when a contractor's days-in-receivable for time t regression model is constant (homoscedasticity) or not (hetero-
decreases (that is, the contractor's days-in-receivable improves), skedasticity). Diagnostics for heteroskedasticity in regression
the probability of an increase in ROS for time t is high. Likewise, a models are essential because heteroskedasticity leads to ineffi-
significant negative correlation between ΔCR3t and ΔCR1t cient parameter and covariance-matrix estimates. As seen in the
indicates that as a contractor's days-in-inventory for time t table, the chi-square value for the White test of Model 3 is 13.33,
decreases (that is, the contractor's days-in-inventory improves), and the associated p-value is larger than 0.05, suggesting the
acceptance of the null hypothesis of no heteroskedasticity in the
Table 1 residuals at the 0.05 level.
ROS and CCC metrics. Further, model-specification error often creates biased esti-
Variable Definition mates of parameters. This error occurs when the model is
V1t Return on sales for time t, where the return on sales = net income / net incorrectly specified; patterns involving groups of residuals
sales versus fitted values (Littell and Freund, 2000) usually reveal the
V2t Days-in-receivable for time t, where days-in-receivable = ending error. As seen in Fig. 1, the plot of the residuals versus predicted
accounts receivable / (net sales / 90), which is the average collection
values for Model 3 reveals an approximate linear pattern,
period from the firm's customers.
V3t Days-in-inventory for time t, where days-in-inventory = ending suggesting that specification errors are not present in the model.
inventory / (cost of goods sold / 90), which indicates the length of Consequently, the study selects Model 3 as the optimal cross-
the manufacturing process and the number of days that the finished sectional model for the construction-contracting industry.
goods remain in the firm before they are sold. Furthermore, aside from seasonal cycles (or autocorrelated
V4t Days-in-payable for time t, where days-in-payable = ending accounts
errors) that occur when a correlation exists between two or more
payable / (cost of goods sold / 90), which is the number of days' credit
before a firm pays its suppliers and subcontractors. consecutive error terms—which results in inefficient parameter
V5t Cash conversion cycle for time t, where cash conversion cycle = days- estimates (Belsley et al., 2004)—multicollinearity in which two
in-receivable + days-in-inventory − days-in-payable or more independent variables in a multivariate regression
Note: Vjt denotes the value of the tth time-series observation of variable j. The model are highly correlated may impair the usefulness of the
definitions of Vjt are based on Stewart (1995), Wild (2003), and Wild et al. (2004). model's estimated parameters by inflating their variances
608 H.L. Chen / International Journal of Project Management 29 (2011) 604–614

Table 2
Null hypothesis test and cross-sectional time-series regression model created with robust regression analysis using a maximum R-squared improvement.
Variables and Null hypothesis Cross-sectional time-series regression model
sources test
Mean Pearson's Dependent variable: ΔCR1t
correlation
Model 1 Model 2 Model 3 Model 4
with CR1t
Coefficient Chi-square Coefficient Chi-square Coefficient Chi-square Coefficient Chi-square
Step 1
Intercept 0.00 0.01 0.00 0.00 − 0.00 0.00 0.00 0.01
ΔCR3t 7.68 − 0.16 ⁎⁎ − 0.01 6152.48 ⁎⁎ − 0.01 1245.45 ⁎ − 0.01 8.65 ⁎⁎ − 0.01 8.68 ⁎⁎
Step 2
ΔCR5t 0.74 − 0.10 ⁎⁎ 0.02 32.17 ⁎⁎ − 0.01 256.33 ⁎⁎ 0.04 256.60 ⁎⁎
Step 3
ΔCR2t 7.41 − 0.16 ⁎⁎ 0.04 8.24 ⁎⁎ − 0.00 8.22 ⁎⁎
Step 4
ΔCR4t 0.11 0.06 ⁎ − 0.01 0.39
R2 (%) 2.03 1.57 2.14 2.13
Changes of R2 (%) − 0.46 0.57 − 0.01
The White test 6.08 ⁎ 8.33 13.33 15.97
Durbin–Watson statistic 2.04 2.04 2.04 2.04
Notes: The total observations are 1638 because the study contains 42 firms, each of which contributes 39 observations; decimal numbers are rounded to the nearest
hundredth.
⁎⁎ p b 0.01.
⁎ p b 0.05.

(Freund and Wilson, 1998). Hence, this study uses the Durbin– The right-hand side of Table 3 describes the result of the
Watson statistics (Vinod, 1973) and the eigenvalues (Freund incomplete-principal component regression analysis for Model 3,
and Wilson, 1998), the variance of principal component where the PCOMIT column specifies the number of deleted
regression analysis, to determine if the effects of seasonal principal components; the TYPE column provides information
cycles and multicollinearity are present in the model, about what the observation contains; PARMS and SEB identify
respectively. the ordinary least-square estimates and their standard errors; IPC
The Durbin–Watson statistic for Model 3, also in the bottom of provides parameters to the ordinary-least-squares method by the
Table 2, is 2.04 and the associated p-value is larger than 0.05, incomplete-principal analysis; and IPCSEB produces standard
implying no autocorrelation in Model 3. However, the multi- errors of the regression coefficients by the incomplete-principal
collinearity diagnostics, shown in the left-hand side of Table 3, analysis.
reveal that the third eigenvalue of Model 3 has a condition number As seen in the table, the residual standard deviation (Root
of 46.1952, and the ΔCR3t and ΔCR2t variables have variation MSE) decreases from 13.516 to 13.512 as one principal
proportions of 0.9986 and 0.9986, respectively. This result component is deleted, indicating that deleting one component
suggests that 99.86% of the variance of the ΔCR3t parameter may alleviate the multicollinearity. The result of further
estimate is associated with the third eigenvalue. Similarly, restructuring Model 3 is shown in row 3 of Table 3, where the
99.86% of ΔCR2t is associated with the third eigenvalue. R-square value improves from 2.14% (in Table 2) to 2.73%
Therefore, this study concludes that ΔCR3t and ΔCR2t are (shown in the notes to Table 3). This result suggests that 2.73% of
correlated. the improvement (change) in a contractor's financial performance
is explained by the improvement (change) in the contractor's SC
cash flow performance.

6. Behavioral analysis of project owners' payment terms

Following case research involving two construction project


contracting firms, which provides a basic understanding of
payment terms for formulating survey questions, a draft
questionnaire was devised using a combined open-end and
multiple-choice format.
Prior to data collection, the survey instrument was pretested for
content validity in three stages. First, several experienced
researchers and a panel of experts from Taiwan's Chinese
National Association of General Contractors (CNAGC), a
Fig. 1. Plot of the residuals versus fitted values of model 3. professional association in Taiwan with over 1000 members,
H.L. Chen / International Journal of Project Management 29 (2011) 604–614 609

Table 3
Multicollinearity diagnostics and incomplete-principal component regression analysis of model 3.
Multicollinearity diagnostics Incomplete-principal component regression analysis
Principal Eigenvalue Condition Variation proportion Observation PCOMIT TYPE Response Root Intercept ΔCR3t ΔCR5t ΔCR2t
component number variable MSE
ΔCR3t ΔCR5t ΔCR2t
1 2.6622 1.0000 0.0003 0.0480 0.0003 1 – PARMS ΔCR1t 13.516 1.0143 − 0.0070 0.0465 − 0.0116
2 0.3365 2.8126 0.0011 0.9509 0.0011 2 – SEB ΔCR1t 13.516 0.3347 0.0459 0.0357 0.0460
3 0.0013 46.1952 0.9986 0.0011 0.9986 3 1 IPC ΔCR1t 13.512 1.0149 − 1.0149 0.0465 − 0.0093
4 1 IPCSEB ΔCR1t 13.512 0.3344 0.0017 0.0356 0.0017
5 2 IPC ΔCR1t 13.539 1.0241 − 0.0052 − 0.0484 − 0.0052
6 2 IPCSEB ΔCR1t 13.539 0.3350 0.0008 0.0078 0.0008
Notes: Model 3 after restructuring: ΔCR1t = 1.01485 − 1.01485 ΔCR3t + 0.04654 ΔCR5t − 0.00931 ΔCR2t, where R-squared = 2.73%.

were asked to critique the questionnaire for structure, readability, lag (as low as one day and no more than 30 days) but payments for
clarity, and completeness. These researchers and experts were materials have a longer time lag (as low as 31 days and no more
also asked to appraise the extent to which the indicators than 121 days).
sufficiently addressed the subject area. Based on the feedback
from these researchers and experts, the instrument was then
modified to strengthen its validity. 6.1. Hypotheses
In the second stage, several contractors were contacted to help
pilot test the instrument. A contact person in each participating The variables associated with the project owners' payment
firm was asked to distribute the instrument to contract managers in terms (time lags, components, and frequency) typically display
their firms. Participants were asked to complete the instrument a range of values (Chen et al., 2005), suggesting that asking
and provide comments, particularly with regard to the under- respondents to indicate a point on a point scale would be more
standability and lack of ambiguity of the items (Kerlinger, 1986). appropriate. The categorical experiment was thus chosen for
The responses indicated only minor changes were required. data analysis, given that the categorical experiment investigates
In the third stage, following the minor changes, a second pilot the relations of variables whose levels are identified by name or
test was conducted involving a small sample of 20 contractors. rank (Ott, 1993). Because the objective of the experiment is to
The instrument was given to two contract managers in each identify the behavioral patterns of project owners through the
participating firm to test for response bias. A simple paired t-test payment lag, component, and frequency variables, the follow-
yielded no statistically significant differences between the two ing overall hypothesis was established: The variables of time
sets of scores, suggesting that response bias was not a problem. lags, components, and frequency of project owners to
The final version of the survey questionnaire comprises two contractors are independent.
sections based on the second research question posed. The first To determine the independence of variables, the experiment
section, comprised of open-end questions, seeks to identify the must indicate that the alternative hypotheses are unlikely. The study
common payment terms contractors have with project owners. uses the chi-squared statistic for independence in two-way
The second section examines how the payment variables contingency tables (Montgomery, 2001) to test the hypotheses.
interact with one another. Section 2 consists of multiple-choice Eight individual hypotheses were developed for testing the overall
questions in which respondents are asked to choose the likely hypothesis (shown in Table 5). All the responses to these individual
extent to which the payment variables had been used by hypotheses were statistically analyzed for independence, and
indicating a point on a five- or ten-point scale. Because of space
limitations, complete survey questionnaires are not presented
Table 4
here but are available from the author on request.
Survey results.
The sample population is limited to construction project
Response, revenue, and age of the firm Construction project contractors
contracting firms in Taiwan. Four hundred firms were randomly
selected and then contacted, and each received a copy of the Responses
questionnaire. Table 4 lists the results of the respondent Questionnaires issued 400
Questionnaires returned 118
contracting firms, along with their revenues and ages. In total, Questionnaire return rate (%) 30
118 usable returns were received, representing a response rate of Annual revenue (in US$ millions)
30%. Compared with similar surveys of the Taiwan construction Less than 1 30
industry, the response rate of 30% was considered good. 1–5 52
In summary, across all firms, a wide range of time lags from 5–10 14
Over 10 22
project owners exist (from a minimum of one day to a maximum Age of the firm (in years)
of 121 days). Though frequency of payments to the contractors Less than 5 39
varies between zero and twice monthly, the project owners 6–15 43
commonly either split payments or lump materials and labor 16–25 22
payments together. Notably, payments for labor have a short time Over 25 14
610 H.L. Chen / International Journal of Project Management 29 (2011) 604–614

Table 5
Test hypotheses and the results of chi-squared tests for the categorical experiment.
Overall hypothesis Individual hypothesis Chi- p- Test result
square value
OHo: The variables time lag, components, and frequency Ho1: The variables time lag and frequency of 22.21 0.01 Rejection
of project owners to contracting firms are independent. project owners to contracting firms are independent when NPSPO exists.
OHa: OHo1 is not all true. Ha1: Ho1 is not all true.
Ho2: The variables frequency and components of 12.48 0.13 Acceptance
project owners to contracting firms are independent when PSPO exists.
Ha2: Ho2 is not all true.
Ho3: The variables frequency and labor time lag of 1.51 0.83 Acceptance
project owners to contracting firms are independent when PSPO exists.
Ha3: Ho3 is not all true.
Ho4: The variables frequency and material time lag of 11.52 0.32 Acceptance
project owners to contracting firms are independent when PSPO exists.
Ha4: Ho4 is not all true.
Ho5: The variables percent labor and labor time lag of 8.43 0.39 Acceptance
project owners to contracting firms are independent when PSPO exists.
Ha5: Ho5 is not all true.
Ho6: The variables percent labor and material time lag of 64.09 b0.01 Rejection
project owners to contracting firms are independent when PSPO exists.
Ha6: Ho6 is not all true.
Ho7: The variables percent materials and material time lag of 95.41 b0.01 Rejection
project owners to contracting firms are independent when PSPO exists.
Ha7: Ho7 is not all true.
Ho8: The variables percent materials and labor time lag of 8.43 0.39 Acceptance
project owners to contracting firms are independent when PSPO exists.
Ha8: Ho8 is not all true.
Notes: OH = overall hypothesis; PSPO = payment split from project owners; NPSPO = no payment split from project owners.

respondents were asked to indicate the most likely level of payment As the bottom of Table 6 shows, the chi-squared value is 22.21
variables. The rating was based on scales of 1–5 or 1–10, measured and the associated p-value is 0.01, confirming a significant
in units of ten days, 20%, or one time per month. association. The null hypothesis is therefore rejected, implying
Table 5 lists the chi-squared test results of the eight that the variables time lags and frequency of payments to
individual hypotheses. A chi-squared value is significant if contractors are not independent when project owners do not split
the value exceeds Xα,df 2
, where α denotes the acceptable payments.
probability of incorrectly rejecting the null hypothesis, and df The study conducts similar analyses of rejected null
represents the degree of freedom for the factors. In this study, hypotheses for hypotheses 6 and 7 of the overall hypothesis.
the acceptable probability of incorrectly accepting the null Rejecting hypothesis 6 suggests that the variables percent labor
hypothesis is at the α = 0.05 level. This probability of 0.05 is a and material time lags are not independent when project owners
stringently accepted level, although some researchers prefer a split payments. Likewise, rejecting hypothesis 7 indicates that the
looser probability of 0.10 (Montgomery, 2001; Ott, 1993). variables percent materials and material time lags are not
independent. (Due to space limitations, only the data and result
6.2. Relationships between payment lags, components, and of the chi-squared test for hypothesis 1 of the overall hypothesis
frequency of project owners to contractors appears in this paper. The remaining test results of the hypotheses
are summarized in Table 5).
Table 6 shows the data and results of the chi-squared test for As a consequence of the rejection of hypotheses 1, 6, and 7,
hypothesis 1 of the overall hypothesis. The data are from 118 the overall hypothesis is rejected. This study concludes that the
usable survey responses and falls into LAG and FREQUENCY time lags, components, and frequency variables related to
groups, which represent the payment time lag and frequency payments from project owners to contracting firms are not
variables, respectively. Preliminary analysis reveals that independent. Specifically, when a project owner does not split
“FREQUENCY: (b 1)” (payment frequency is less than once a payments, the owner's decisions regarding time lags and
month) tends toward the “b21 days” subcategory of LAG. frequency related to the payments are interdependent (hypoth-
“FREQUENCY: (= 1)” (payment frequency is once a month) esis 1). When a project owner splits payments, the owner's
tends toward the “21–30 days” and “51–60 days” subcategories decisions regarding percent labor and material time lags related
of LAG, and “FREQUENCY: (= 2)” (payment frequency is to the payments for its contractors are interdependent
twice a month) tends toward the “31–40 days” subcategory of (hypothesis 6), and likewise the owner's decisions regarding
LAG. This study thus concludes that an association exists percent materials and material time lags related to the payments
between the LAG and FREQUENCY variables. for its contractors are interdependent (hypothesis 7).
H.L. Chen / International Journal of Project Management 29 (2011) 604–614 611

Table 6
Chi-squared test of independence for the variables time lag and frequency of project owners to contracting firms when NPSPO exists.
Source LAG
b21 daysa 21–30 days 31–40 days 41–50 days 51–60 days N61 days Total
FREQUENCY: (b1) 12.00 8.00 6.00 5.00 6.00 1.00 38.00
FREQUENCY: (=1) 7.00 18.00 3.00 8.00 18.00 4.00 58.00
FREQUENCY: (=2) 5.00 6.00 7.00 1.00 1.00 2.00 22.00
Total 24.00 32.0 26.00 14.00 25.00 7.00 118.00
Chi-square statistic Degree of freedom Value Probability
10.00 22.21 0.01
a
Considering the validation of the chi-squared tests, this study decided to combine some data points while running the chi-squared tests. For example, point scales 1 (1–
10 days) and 2 (10–20 days) are combined as b21.

Pearson's correlation tests are further performed to analyze simultaneously increase material time lags that result in a longer
the relationship between the variables in the rejected null days-in-receivable for the contractor.
hypotheses, shown in Table 7. As seen in the table, no
significant correlation exists (Pearson's correlation coefficient 7. Practical implications
0.13 with a p-value of 0.17) between the time-lag variable and
frequency variable (hypothesis 1). The lack of correlation Low and unreliably profitability characterize the construction-
suggests that these two variables affect each other; however, no contracting industry (Sorrell, 2003). Levy (2009) and Teerajetgul
clear behavioral patterns exist regarding how project owners et al. (2009) further note that contractors work on slim profit
determine one from the other while contracting with contrac- margins due to fierce competition. Though researchers continu-
tors. However, as seen in Table 7, a significant negative ally develop methods and approaches for reducing construction-
correlation (Pearson correlation coefficient − 0.24 with a p- contracting costs (e.g., Dainty et al., 2001; Humphreys et al.,
value of 0.01) exists between the percent-labor variable and 2003; Yeo and Ning, 2002), some authors (e.g., Hwee and Tiogn,
material time-lag variable (hypothesis 6). The negative 2002; Kaka and Lewis, 2003; Motawa and Kaka, 2009) have
correlation suggests that a trade-off relationship exists between focused on improving the profitability of construction contracting
the variables, implying that when a contractor bargains with the by improving the efficiency of SC cash flows.
project owner to increase the percent labor that accompanies Despite the panoply of approaches to modeling SC cash flows,
labor time lags (and results in a shorter days-in-receivable to the limited research exists that assesses the relationships between SC
contractor), the probability of having increased material time cash flow and financial performance. In this respect, this study
lags that results in longer days-in-receivable in return is high. poses a research question to investigate and model their
As also seen in Table 7, a significant positive correlation relationships statistically. A cross-sectional longitudinal analysis
exists between the percent-materials variable and the material of the Taiwanese construction-contracting industry suggests that
time-lag variable (hypothesis 7), where the Pearson correlation significant correlations exist between SC cash flow performance,
coefficient is 0.23 and the associated p-value is 0.01. This measured by CCC, and financial performance, measured by ROS.
correlation indicates that during the contracting phase of a Development of a cross-sectional time-series regression model on
project, as a project owner tries to increase percent materials that these correlations further implies that 2.73% of the variation in
accompany material time lags and result in longer days-in- contractors' ROS is explained by the contractors' SC cash flow
receivable for the contractor, the project owner is likely to performance. In other words, an important implication of this

Table 7
Descriptive statistics and correlations between the variables in the rejected hypotheses of the overall hypothesis.
Individual hypothesis Variable Mean Standard Correlation with the other Probability
deviation variable in the hypothesis (2-tailed)
Ho1: The variables time lag and frequency of project owners to contracting firms Time lag 3.0 1.61 0.13 0.17
are independent when NPSPO exists.
Ha1: Ho1 is not all true. Frequency 1.9 0.68 0.13 0.17
Ho6: The variables percent labor and material time lag of project owners to Percent 2.5 1.36 − 0.24 0.01
contracting firms are independent when PSPO exists. labor
Ha6: Ho6 is not all true. Material 4.1 1.66 − 0.24 0.01
time lag
Ho7: The variables percent materials and material time lag of project owners to Percent 3.5 1.36 0.23 0.01
contracting firms are independent when PSPO exists. materials
Ha7: Ho7 is not all true. Material 4.1 1.66 0.23 0.01
time lag
612 H.L. Chen / International Journal of Project Management 29 (2011) 604–614

model is that while a contractor is improving SC cash flows, the material time lags 1, 2, 3, 4, 5, and 6 represent b 21, 21–30, 31–
potential performance improvement of ROS in return is 2.73%. 40, 41–50, 51–60, and N 61 days, respectively, and those of
Although CCC can be improved by either increasing the percent labor 1, 2, 3, 4, and 5 represent 100%–81%, 80%–61%,
days-in-payable or reducing days-in-receivable or days-in- 60%–41%, 40%–21%, and 20%–0%, respectively. Thus, when
inventory, this study focuses on the potential improvement of a contractor bargains with a project owner to increase the
days-in-receivable by analyzing the behavioral patterns of percent labor that has shorter time lags to expedite its cash
project owners on the important variables of payment terms that inflows, the probability of having increased material time lags
affect cash flows. The results provide contractors with that slow down its cash inflows in return is high.
appropriate strategies for negotiating payment terms that A significant positive correlation exists between the percent-
expedite cash inflows and improve SC cash flow performance. material variable and material time-lag variable (hypothesis 7),
Using the combined categorical experiments and Pearson's implying a relationship of moving in the same direction
correlation tests, this study finds several important behavioral between the variables, shown in the right of Fig. 2, where the
patterns in the project owner–contractor dyad in the context of point scales of percent material 1, 2, 3, 4, and 5 represent
payment-term negotiation. These behavioral patterns have 100%–81%, 80%–61%, 60%–41%, 40%–21%, and 20%–0%,
implications for practitioners. Specifically, those accepted respectively. Namely, when a contractor bargains with a project
individual hypotheses of the overall hypothesis (Table 5) owner to decrease the percent material that has longer time lags
suggest that the paired variables in each of the hypotheses are to expedite its cash inflows, the probability of having increased
independent. This independency implies that while negotiating material time lags that slow down its cash inflows in return is
the value of one of the paired variables in each of the hypotheses high.
during the contracting phase of a project, the probability of the
other of the paired variables increasing or decreasing is low. For 8. Conclusions
example, as a contractor bargains with the project owner who
splits payments between labor and materials to increase Although SC cash flow management has been a key
payment frequency to expedite its cash inflows, the probability determinant of SC performance, little research assesses the
of having increased percent-material that has longer lags and impact of improvements in SC cash flows on financial
thus slows down its cash inflows in return is low (hypothesis 2 performance. Thus, this study investigates the relationship
shown in Table 5). between improving SC cash flow and financial performance,
Likewise, those rejected individual hypotheses imply that the which suggests that as a construction project contractor's SC
paired variables in each of the hypotheses significantly depend cash flows improve, the probability of the contractor's financial
on each other, suggesting an interpretation totally opposite from performance also improving is high. Development of a cross-
those accepted hypotheses. In particular, Pearson's correlation sectional time-series regression model on these correlations
tests of the paired variables in the rejected hypotheses 6 and 7 further reveals that 2.73% of the variation in financial
further indicate the paired variables (Table 7) move in the same performance is contributed by SC cash flow performance.
or opposite direction, revealing important behavioral patterns of This result in turn implies that as a contractor improves SC cash
the parties involved in the contracting phase. flows by reducing CCC, the potential improvement of ROS is
Specifically, a significant negative correlation exists between 2.73%.
the percent-labor variable and material time-lag variable To further support the implementation of improving SC
(hypothesis 6), suggesting a trade-off relationship between the cash flows by reducing the days-in-receivable variable of CCC,
variables. The left of Fig. 2 depicts this relationship, where error this study further analyzes the behavioral patterns of project
bars show 95% confidence interval of mean; the point scales of owners regarding payment terms. The combined categorical

Fig. 2. Plots of material time lags versus percent labor (left) and material time lags versus percent material (right).
H.L. Chen / International Journal of Project Management 29 (2011) 604–614 613

experiments and Pearson's correlation tests reveal several Cohen, M.A., Moon, S., 1990. Measuring supply chain performance. International
important behavioral patterns that provide contractors with an Journal of Operations & Production Management 19 (3), 275–292.
Comelli, M., Féniès, P., Tchernev, N., 2008. A combined financial and physical
ability to evaluate the potential responses of project owners to flows evaluation for logistic process and tactical production planning:
payment terms during the contracting phase of a project. More Application in a company supply chain. International Journal of Production
broadly, the research and methods of this paper not only provide Economics 112 (1), 77–95.
management with a practical means to measure the impact of Comelli, M., Féniès, P., Lemoine, D., 2009. Tactical planning for optimal cash
flow and value sharing in supply chain. International Journal of Logistics
the SC cash flows improvement on financial performance, but
Systems and Management 5 (3/4), 323–343.
contribute to a larger discussion about behavioral patterns of Dainty, A.R.J., Briscoe, G.H., Millett, S.J., 2001. New perspective on
payment terms in a SC. construction supply chain integration. Supply Chain Management: An
As an extension of this research, a study of the relationships International Journal 6 (3), 163–173.
between project contractors' annual sales and project owners' Ellram, M., Liu, B., 2002. The financial impact of supply management. Supply
payment patterns would be beneficial because incorporating Chain Management Review 6 (6), 30–37.
Elmuti, D., Minnis, W., Abebe, M., 2008. Longitudinal assessment of an
contractors' annual sales might significantly change the integrated industrial supply chain. Supply Chain Management: An
behavioral patterns of project owners regarding payment International Journal 13 (2), 151–159.
terms during the contracting phase of projects. Another Farris, M., Hutchinson, P., 2002. Cash-to-cash: the new supply chain
extension of the research in this paper to a broader evaluation management metric. International Journal of Physical Distribution &
of SC payment terms that includes suppliers and subcontractors Logistics Management 32 (4), 288–298.
Fawcett, S.E., Osterhaus, P., Magnan, G.M., Brau, J.C., McCarter, M.W., 2007.
will provide management a total picture of how the entire SC Information sharing and supply chain performance: the role of connectivity and
behaves under different conditions. willingness. Supply Chain Management: An International Journal 12 (5),
352–368.
Fawcett, S.E., Wallin, C., Allred, C., Magnan, G., 2009. Supply chain
Acknowledgment information-sharing: benchmarking a proven path. Management Science 16
(2), 222–246.
The author would like to thank the Taiwan National Science Freund, R.J., Wilson, W.J., 1998. Regression Analysis: Statistical Modeling of a
Council for financially supporting this research. Response Variable. Academic Press, CA.
Görög, M., 2009. A comprehensive model for planning and controlling
contractor cash-flow. International Journal of Project Management 27 (5),
References 481–492.
Hendricks, K.B., Singhal, V.R., 2003. The effect of supply chain glitches on
Anand, K.S., Goyal, M., 2009. Strategic information management under leakage shareholder wealth. Journal of Operations Management 21 (5), 501–522.
in a supply chain. Management Science 55 (3), 438–452. Hill, C.A., Zhang, G.P., Scudder, G.D., 2009. An empirical investigation of EDI
Andersen, P.H., Christensen, P.R., 2005. Bridges over troubled water: suppliers usage and performance improvement in food supply chains. IEEE
as connective nodes in global supply networks. Journal of Business Transactions on Engineering Management 56 (1), 61–75.
Research 58 (9), 1261–1273. Humphreys, P., Matthews, J., Kumaraswamy, M., 2003. Pre-construction
Arnold, J., Minner, S., Eidam, B., 2009. Raw material procurement with fluctuating project partnering: from adversarial to collaborative relationships. Supply
prices. International Journal of Production Economics 121 (2), 353–364. Chain Management: An International Journal 8 (2), 166–178.
Badell, M., Pomerom, J., Puigjaner, L., 2005. Optimal budgets and cash flow Hwee, N.G., Tiogn, R.L., 2002. Model on cash flow forecasting and risk
during retrofitting period in batch chemical industry. International Journal of analysis for contracting firms. International Journal of Project Management
Production Economics 95 (3), 359–372. 20 (5), 351–363.
Baghdasaryan, L., Darabi, H., Schuler, F., Schaller, A., 2010. A modelling and Kaka, A.P., Lewis, J., 2003. Development of a company-level dynamic cash flow
optimisation management tool for large-scale supply chain networks. forecasting model. Construction Management and Economics 21 (7), 693–705.
International Journal of Industrial and Systems Engineering 5 (1), 48–78. Kerlinger, F.N., 1986. Foundations of Behavioral Research. Harcourt Brace
Bayraktar, E., Gunasekaran, A., Koh, S.C.L., Tatoglu, E., Demirbag, M., Zaim, S., Jovanovich, New York.
2010. An efficiency comparison of supply chain management and information Lanier, D., Wempe, W., Zacharia, Z., 2010. Concentrated supply chain
systems practices: a study of Turkish and Bulgarian small- and medium-sized membership and financial performance: chain- and firm-level perspectives.
enterprises in food products and beverages. International Journal of Production Journal of Operations Management 28 (1), 1–16.
Research 48 (2), 425–451. Lee, C.W., Kwon, I.W.G., Severance, D., 2007. Relationship between supply
Belsley, D.A., Kuh, E., Welsch, R.E., 2004. Regression Diagnostics: Identifying chain performance and degree of linkage among supplier, internal
Influential Data and Sources of Collinearity. John Wiley & Son, New Jersey. integration, and customer. Supply Chain Management: An International
Chae, B., Yen, H.R., Sheu, C., 2005. Information technology and supply chain Journal 12 (6), 444–452.
collaboration: moderating effects of existing relationships between partners. Levy, S.M., 2009. Construction Process Planning and Management: An Owner's
IEEE Transactions on Engineering Management 52 (4), 440–448. Guide to Successful Projects. Butterworth-Heinemann, Oxford, UK.
Chen, H.L., 2007. Developing cost response models for company-level cost Lin, L.R., Huang, S.H., Lin, S.C., 2002. Effects of information sharing on
flow forecasting of project-based corporations. Journal of Management in supply chain performance in electronic commerce. IEEE Transactions on
Engineering 23 (4), 171–181. Engineering Management 49 (3), 258–268.
Chen, H.L., O'Brien, W.J., Herbsman, Z.J., 2005. Assessing the accuracy of cash Littell, R.C., Freund, R.J., 2000. SAS System for Regression. SAS Institute Inc.,
flow models: the significance of payment conditions. Journal of Construction Cary, NC.
Engineering and Management 131 (6), 669–676. Lo, C.K.Y., Yeung, A.C.L., Cheng, T.C.E., 2009. ISO 9000 and supply chain
Cheng, M.Y., Tsai, H.C., Liu, C.L., 2009. Artificial intelligence approaches to efficiency: empirical evidence on inventory and account receivable days.
achieve strategic control over project cash flows. Automation in Construction International Journal of Production Economics 118 (2), 367–374.
18 (4), 386–393. Montgomery, D.C., 2001. Design and Analysis of Experiments. John Wiley &
Christensen, W.J., Germain, R.N., Birou, L., 2007. Variance vs average: supply Sons, New York.
chain lead-time as a predictor of financial performance. Supply Chain Motawa, I., Kaka, A., 2009. Modelling payment mechanisms for supply chain in
Management: An International Journal 12 (5), 349–357. construction. Construction and Architectural Management 16 (4), 325–336.
614 H.L. Chen / International Journal of Project Management 29 (2011) 604–614

Naylor, J.B., Naim, M.M., Berry, D., 1999. Leagility: integrating the lean and Tsai, C.Y., 2008. On supply chain flow risks. Decision Support Systems 44 (4),
agile manufacturing paradigms in the total supply chain. International 1031–1042.
Journal of Production Economics 62 (1/2), 107–118. Vachon, S., Klassen, R.D., 2002. An exploratory investigation of the effects of
Neter, J., Kutner, M.H., Nachtsheim, C.J., Wasserman, W., 1996. Applied supply chain complexity on delivery performance. IEEE Transactions on
Linear Statistical Models. McGraw-Hill, MA. Engineering Management 49 (3), 218–230.
Ott, R.L., 1993. An Introduction to Statistical Methods and Data Analysis. Vinod, H.D., 1973. Generalization of the Durbin–Watson statistic for higher
Wadsworth Publishing Company, CA. order autoregressive process. Communications in Statistics 2 (2), 115–144.
Richey, R.G., Tokman, M., Skinner, L.R., 2008. Exploring collaborative White, H., 1980. A heteroskedasticity-consistent covariance matrix estimator
technology utilization in retailer–supplier performance. Journal of Business and a direct test for heteroskedasticity. Econometrica 48 (4), 817–838.
Research 61 (8), 842–849. Wild, J.J., 2003. Financial Accounting. Irwin McGraw-Hill, MA.
Sheu, J.B., 2005. A multi-layer demand-responsive logistics control method- Wild, J.J., Subramanyam, K.R., Halsey, R.F., 2004. Fundamentals of Financial
ology for alleviating the bullwhip effect of supply chains. European Journal Statement Analysis. MacGraw-Hill, New York.
of Operational Research 161 (3), 797–811. Yeo, K.T., Ning, J.H., 2002. Integrating supply chain and critical chain concepts
Shumway, R.H., Stoffer, D.S., 2000. Time Series Analysis and Its Application. in engineer-procure-construct (EPC) projects. International Journal of
Springer-Verlag, New York. Project Management 20 (4), 253–262.
Sorrell, S., 2003. Making the link: climate policy and the reform of the UK Yin, R.K., 2003. Case Study Research: Design and Methods. Sage Publications,
construction industry. Energy Policy 31 (9), 865–878. Inc., Thousand Oaks, CA.
Stewart, G., 1995. Supply chain performance benchmarking study reveals keys Zailani, S., Rajagopal, P., 2005. Supply chain integration and performance: US
to supply chain excellence. Logistics Information Management 7 (2), 38–45. versus East Asian companies. Supply Chain Management: An International
Teerajetgul, W., Chareonngam, C., Wethyavivorn, P., 2009. Key knowledge Journal 10 (5), 379–393.
factors in Thai construction practice. International Journal of Project
Management 27 (8), 833–839.

You might also like