Professional Documents
Culture Documents
Attachment
Attachment
Location:jijiga
client: Mr. omar feysel
consultant: Bright consultancy
3 2 *ditto forF2(1000mm-1000mm)
2
1.65
6.6m³
6 *ditto forF3(1200-1200mm)
2.2
2.2
1.65
7.95m³
5 2.4 *ditto for F4(1400mm-1400mm)
2.4
1.65
9.51m³
2 2.6 *dittoF5(1600mm-1600mm)
2.6
1.65
11.5m³ s
40.91m³ * total pit excavation
4 3.55 1.4 trench excavation
1.2 * inordinary soil upto 1m
1 *y-axis(y-o1-y-02,y-03,y-04)
17.04m³ *y between x(04)2x(03)
* L-3.55m *D-1.2m
*w-0.sm+0.25+0.25=1m
* working space 25cm
1.3stair
1 1.3 * concrete work in waist slab
2.8 height=3.06/1.53
0.15 width=8*0.03=2.4
0.55m³ by pythagoras theory
c²=a²+b²=1.53²+2.4²=2.84
thicknes=0.15
1 0.03 *concrete work in step
18 v=1/2*b*h*l=1/2*0.5*0.3*0.17=0.03
0.54m³ *raise to landing 1.53/0.17=9
number of step in 1 flight-9*2=18
1 1.3 *concrete work in landing
2.6
0.15
0.51m³
0.59m³ total volume
1.4 Concrete work for first floor beam
FFB.1
2 11.65 L=11.65
0.2 W=200=0.2
0.4 D=400=0.4
1.37m³
FFB.3
1 11.65 L=11.65
0.2 W=0.2
0.4 D=0.4
0.93m³
FFB.4
1 1.9 L=1.9
0.4 W=400=0.4
0.15 D=150=0.15
0.12m³
FFB.5
1 4.95 L=4.95
0.2 W=200=0.2
0.4 D=400=0.4
0.4m³
FFB.6
1 4.8 L=4.8
0.2 W=200=0.2
0.4 D=400=0.4
0.39m³
FFB.7
1 4.6 L=4.6
0.2 W=0.2
0.4 D=0.4
0.37m³
T L*W*H SQUARE DESCRIPTON
2.block work /HCB work
1 11.26 2.1 HCB20(B) for ground floor
2.9 axis x(01,02,03,04)
32.66m² ony(01)
1 4.5 axis x(01,02)on y(02)
2.9
13.03m²
1 8.2 axis x(01,02,03)on y(03)
2.9
23.18m²
1 11.26 axis x(01,02,03,04)ony(04)
2.9 ditto as(x01,02,03,04)ony(01)
32.66m²
1 11.65 axis y(01,02,03,04) onx(04)
2.9
33.79m²
1 4.95 axisy(01 and 02)onx(02)
2.9
14.36m²
1 4.8 axisy(03 and 04)onx(01)
2.9
13.92m²
164.22m² toal area of HCB20 work on GF
2.2 HCB 15(B)
2 4.95 axis y(01 and 02)onx(03)
2.9
28.91m²
1 6.8 axis y(02,03,04) onx(03)
2.9
19.72m²
1 2.95 axis x(03 and 04) ony(02)
2.9
8.56m²
56.99m² total area of HCB on GF
TIME L*W*H SQUARE DESCRIPTION
2.2 HCB 20(B) first floor
1 11.65 axis y(01,02,03,04)on x(04)
2.95
34.37m²
1 1.9 axis y(02 and 03) onx901)
2.95
5.61m²
1 1.97 axis y(03 and 03´) on x(03)
2.95
5.82m²
1 4.8 axis(03 and 04) on x(02)
2.95
14.16m²
1 4.8 axis y(03 and 04) onx(03)
2.95 ditto as y(03 and 04) 0nx(02)
14.16m²
1 11.25 axisX
2.95 x(01,02,03,04)on y(01)
33.18m²
y(01,02,03,04)on y(04)
ditto as x(01,02,03,04)on y(01)
32.9
1 4.5 HCB20
3.41 y(01,02)on y(01)
13.28m²
153.18m² Total area of HCB20 for FF
1 4.95 HCB25
2.95 y(01,03)on y(01)
14.61
2.95 HCB15
1 3.41 y(01,04)on y(01)
8.71m²
1 3.28 x(01,03)on y(03)
2.95
9.68m²
1 y(03-04)on y(03´)
ditto as x(03,04)on y(03)
9.68m²
1 0.1 x(01,03)on y(01´)
2.95
0.32m²
1 8.2 x(01,02,03)ony(03)
2.95
24.2m²
1 4.4 y(01 and 01´)onx(01´)
2.95
12.98m²
1 4.95 y(01 and 02)0nx(02)
2.95
14.61m²
1.9 y(02 and 03)onx(03)
2.95
5.61m²
2.53 y(03' and 04)onx(03)
2.95
7.5m²
93.3m² Total area of HCB15 for FF
TIME L*W*H SQUARE DESCRIPTION
2.3 HCB for service quartile
1 15.2 HCB20
2.6 y(05,06,07,08) onx(06)
39.52m²
1 1.51 y(05 and 05´)onx(05)
2.6
3.93m²
1 12.81 y(05´,06,07,08)onx(05)
2.6
33.3m²
1 2.6 x(05 and 06) on y(05)
2.6
6.76m²
x(05 and 06) on y(08)
6.76m² ditto as x(05 and 06)ony(05)
90.25m² total HCB20
4 2.6 HCB15 y(05,06,07,08)onx(05 and 06)
2.6
27.04m²
117.31m² total HCB
D=1.2m
24m³ W=0.5m+0.25+0.25=1m
127.03m³ total trench excavation for block 1
2 15 *block 2
0.5 depth 1.2
1.2 axis y width 0.5 or y05 to y08
18m³
2 3 axis x between x05 and 06
0.5
1.2
3.6m³
21.6m³ total volume for block 2
148.63m³ total trench excavation for block 1
1.5 back fill
*suitable material arising from
excavation and capable of being
compacted to form a stable filling side
145.2m³ * detto bulk excacation
40.91m³ * detto pit excavation
170.23m³ * detto of trench excavation
7m³ * total volume of concrete for pad
27.84m³ * total volume of concrete for footing
54.6m3 *total volume of masonary
266.9m3 BF=BE+PE+TE-(CP+CF)
1.6 cartaway
465.04m3 CA=total excavation+site clearance-(backfill)
TIME L*W*H SQUARE DESCRIPTIN
8 0.07 *C-4 |Circular column
1.35 depth 1600-250=1350=1.35m
0.76m³ Area detoo as C-1
2.21m³ *total foundation column block1
*block 2
8 0.08 circular column
2.66 area=∏r²
1.71m³ d=0.3 ,r=0.5 ,∏=3.14
3.92m³ *tota volume foundation column
* block 2
2.4 ground floor slab concrete block 1
1 35.43 along axis y(01,02,03,04) on x(04 and 03)
0.1 thickness=10cm=0.1
3.5m³
1 44.09 along axis y(01,02,03,04) on x(03 and 02)
0.1 thickness=10cm=0.1
4.41m³
1 53.59 along axis y(01,02,03,04) 0n x(02 and01)
0.1 thickness=10cm=0.1
5.4m³
1 3.23 for verenda on axis x(01and 01¯)
0.1 thickness=10cm=0.1
2.03m³
15.34m³ total volume floor slab for B1
* block 2
1 3.78 along axis y(y05,06,07,08) on x(06 and 05)
0.1
4.04m³
19.34m³ total volume floor slab for B1and B2
2.3 Ground floor Gread beam
2 14.2 GB1
0.2 y(05,06,07,08) on axis x(05,06)
0.4 w=200=0.2
2.28m³ d=400=0.4
4 2.6 GB2
0.2 X(05,06) on axis y(05,06,07,08)
0.4 w=200=0.2
o.84m³ d=400=0.4
3.12m³ total grade beam for block 2
9.06m³ total grade beam for block 1 and 2
concrete work for block 1
1 11.65 GB3
0.2 y(01,02,03,04) on axis x(01,04)
0.4 w=200=0.2
0.93m³ d=400=0.4
1 11.65 GB4
0.2 y(01,02,03,04) on axis x(02,03)
0.4 w=200=0.2
0.93m³ d=400=0.4
2 12.58 GB6
0.2 x(01,02,03,04) on axis y(01,02)
0.4 w=200=0.2
2.02m³ d=400=0.4
1 1.9 GB5(vertical)
0.2 y(01,02,03) on axis x(01)
0.4 w=200=0.2
0.16m³ d=400=0.4
5.94m³ total gread beam volume B1
12.45
6.6 c²=6.22²+2.22²
82.15m² 6.6
L=22.45
W=6.6
ceilling
12.25
12.05
147.62m² total area of ceilling
chimeny
9.58
1.2
11.49m² total area of chimeny
2 14.2
0.2
0.4
2.28m³
4 2.6
0.2
0.4
o.84m³
3.12m³
9.06m³
2.4 ground floor slab concrete block 1
1 35.43 along axis y(01,02,03,04) on x(04 and 03)
0.1 thickness=10cm=0.1
3.5m³
1 44.09 along axis y(01,02,03,04) on x(03 and 02)
0.1 thickness=10cm=0.1
4.41m³
1 53.59 along axis y(01,02,03,04) 0n x(02 and01)
0.1 thickness=10cm=0.1
5.4m³
1 3.23 for verenda on axis x(01and 01¯)
0.1 thickness=10cm=0.1
2.03m³
15.34m³ total volume floor slab for B1
* block 2
1 3.78 along axis y(y05,06,07,08) on x(06 and 05)
0.1
4.04m³
19.34m³ total volume floor slab for B1and B2
GB1
y(05,06,07,08) on axis x(05,06)
w=200=0.2
d=400=0.4
GB2
X(05,06) on axis y(05,06,07,08)
w=200=0.2
d=400=0.4
total grade beam for block 2
total grade beam for block 1 and 2
2.3 Ground floor Gread beam
concrete work for block 1
1 11.65 GB3
0.2 y(01,02,03,04) on axis x(01,04)
0.4 w=200=0.2
0.93m³ d=400=0.4
1 11.65 GB4
0.2 y(01,02,03,04) on axis x(02,03)
0.4 w=200=0.2
0.93m³ d=400=0.4
2 12.58 GB6
0.2 x(01,02,03,04) on axis y(01,02)
0.4 w=200=0.2
2.02m³ d=400=0.4
1 1.9 GB5(vertical)
0.2 y(01,02,03) on axis x(01)
0.4 w=200=0.2
0.16m³ d=400=0.4
5.94m³ total gread beam volume B1
super structure
item NO Description shape dia length(m) No of bar No of member
SERVICE QUARTILE sub structure
T 14 5.85 2 1
N
B 16 5.85 3 1
B 14 5.85 2 1
STIRRUP FFB7 for axis x(01,02)
on axis y(01)
T 16 5.65 3 1
N
B 16 5.65 3 1
STIRRUP FFB8 for axis x(03,04)
on axis y(01)
T 16 7.02 3 1
N
B 16 7.02 3 1
STIRRUP FFB9 for axis x(02,03)
on axis y(01'')
T 14 4.35 4 1
N
B 14 4.35 4 1
STIRRUP FFB10 for axis x(01',01,02,03
04) on axis y(02)
T 16 9.15 3 1
N
B 16 6.95 3 1
STIRRUP FFB11 for axis x(01',01,02,03
04) on axis Y(03)
T 16 9.15 3 1
N
B 16 6.95 3 1
STIRRUP FFB13 for axis x(01,02,03,04)
on axis y(04)
T 16 7.65 3 1
N
B 16 5.45 3 1
TOP TIE BEAM
SERVICE QUARTILE
TTB1 for axis y(05,06,07,08)
on axis x(05,06) service
T 12 8 3 2
N
B 12 9.8 3 2
STIRRUP for axis x(05,06)
on axis y(05,06,07,08) service
T 12 3.4 2 4
N
B 12 3.45 2 4
BLOCK 1
TTB3 for axis y(01,02,03) on
axis x(04)
T 14 6.95 3 1
N
B 14 5.7 3 1
STIRRUP TTB4 for axis y(01,02,03,04)
on axis x(02,03)
T 12 6.95 3 2
N
B 12 5.7 3 2
STIRRUP TTB5 for axis y(02,03)
on axis x(01')
T 14 2.7 3 1
N
B 14 2.7 3 1
STIRRUP TTB6 for axis y(01,02)
on axis x(01)
T 12 5.8 3 1
N
B 12 5.8 3 1
STIRRUP TTB7 for axis y(03,04)
on axis x(01)
T 12 5.65 3 1
N
B 12 5.65 3 1
STIRRUP TTB8 fo axis y(01,02)
on axis x(01')
T 14 5.8 3 1
N
B 14 5.8 3 1
STIRRUP TTB9 fo axis y(03,04)
on axis x(01')
T 14 5.65 3 1
N
B 14 5.65 3 1
STIRRUP TTB10 for axis x(01',01,02,
03,04) on axis y(01,02)
T 14 9.15 3 2
N 14 3.7 2 2
B 14 6.95 3 2
STIRRUP TTB11 for axis x(01',01,02
03,04) on axis y(03,04)
T 14 9.15 3 2
N 14 3.7 2 2
B 14 6.95 3 2
SECTION TTB
SEC A-A 8 1.01 1 1
SEC B-B 8 0.87 1 1
SEC C-C 8 0.47 1 1
FF SLAB
1 6 45.3 45.3
1 6 59.1 59.1
1 12 42 42
1 12 42 42
1 3 20.85 20.8
1 3 17.1 17.1
1 6 41.7 41.7
1 4 21.2 21.2
1 6 34.2 34.2
1 4 22.8 22.8
1 3 9.9 9.9
1 3 9.9 9.9
1 3 22.65 22.65
1 3 16.05 16.05
1 3 14.1 14.1
1 3 14.1 14.1
1 2 9.4 9.4
1 6 54.6 54.6
1 6 41.4 41.4
1 3 20.91 20.91
1 3 16.59 16.59
1 16 14.4 14.4
1 30 36 36
1 72 100.8 100.8
1 80 136 136
1 40 80 80
1 18 54 12 144
1 48 144 144
1 48 144 110.4
1 32 110.4
1 6 5.1 5.1
1 6 6 6
1 6 4.8 4.8
1 6 6 6
1 6 4.8 4.8
1 6 6 6
1 4 3.2 3.2
1 41 1943.4 1943.4
1 42 1957.2 1957.2
1 3 21 21
1 3 17.25 17.25
1 3 21 21
1 2 10.8 10.8
1 3 17.25 17.25
1 2 11.5 11.5
1 3 21 21
1 3 17.25 17.25
1 2 11.5 11.5
1 4 12.6 12.6
1 4 12.6 12.6
1 3 18 18
1 2 12 12
1 3 18 18
1 2 12 12
1 3 17.55 17.55
1 2 11.7 11.7
1 3 17.55 17.55
1 2 11.7 11.7
1 3 16.95 16.95
1 3 16.95 16.95
1 3 21.06 21.06
1 3 21.06 21.06
1 4 17.4 17.4
1 4 17.4 17.4
1 3 27.45 27.45
1 3 20.85 20.85
1 3 27.45 27.45
1 3 20.85 20.85
1 3 22.95 22.95
1 3 16.35 16.35
1 6 48 48
1 6 58.8 58.8
1 8 27.2 27.2
1 8 27.2 27.2
1 3 20.7 20.7
1 3 17.1 17.1
1 6 41.7 41.7
1 6 34.2 34.2
1 3 8.1 8.1
1 3 8.1 8.1
1 3 17.4 17.4
1 3 17.4 17.4
1 3 16.95 16.95
1 3 16.95 16.95
1 3 17.4 17.4
1 3 17.4 17.4
1 3 16.95 16.95
1 3 16.95 16.95
1 6 54.9 54.9
1 4 14.8 14.8
1 6 41.7 41.7
1 6 54.9 54.9
1 4 14.8 14.8
1 6 41.7 41.7
1 1 1.01 1.01
1 1 0.87 0.87
1 1 0.47 0.47
1 20 100 100
1 21 65.1 65.1
1 27 54 54
1 29 113.1 113.1
Total length 4325.15 194.4 884.3 945.8 632.37
unit ml/kg ml/kg ml/kg ml/kg ml/kg
Total weight 0.39kg 0.61kg 0.89kg 1.2kg 1.6kg
ELECTRICAL INSTALATION
Electrical fixture on ground floor
14 pc wall light point compact florencent
8 pc ceiling incondencent
4 pc wall incondencent
19 pc wall socket system
1 pc pole
1 pc TV outlet
3 pc tele intake
20 pc incondencent lamp
First floor fixture
13 pc socket system
4 pc double socket system
3 pc TV outlet
4 pc Tele intake
7 pc bell outlet
23 pc lighting system
10 pc doblelighting system
22 pc incondencent lamp
8 pcs florecent lamp
Wire for GF
size
2*2.5 lighting PVC pipe of Ø20 in main gate
3*6 stove
3*6 LPP-5Ø
3*6 LPP-IF
2*1 Bell cell
3*2.5 socket system
30ml TV outlet
40ml for telephone
Wire for service
size
2*2.6 lighiting
socket outlet
3*2.5 washing machine
3*6 electrical metal
wire for first floor
2*2.5 Ø20 in lighiting
3*2.5 heater
35ml TV outlet
2*1 bell cell
50ml tele
Distribution board
LLP-50ampere 1phase power source from ACB for GF
LPP-sq 32ampere 1phase power source from ACB for service quartiele
LPP- if 25ampere 1phase power source from ACB for FF
SANITORY INSTALATION
Wast water pipes
Ø300 waste water pipes
15ml for ground floor
10ml for first floor
Ø110 waste water pipes
10ml for ground floor
6ml for first floor
Ø50 and 65 waste water pipes
15ml forØ50 in GF
12ml for Ø65 in GF
17ml forØ50 in FF
14ml for Ø65 in FF
Water supply pipes
Ø20 water supply
23ml for ground floor
26ml for first floor
Ø15 water supply
30ml for ground floor
35ml for first floor
Fixture for ground and first floor
6 gate valve for 20mm diametr pipe
9 gate valve for 15mm diametr pipe
4 one way valv for 15
connector of pipe in pc
17 pc for 20mm
22 pc for 15 mm
Fixtures pipes
5 pc bond wash basin
3 pc shower basin
2 pc stove
4 pc water closer
2 pc kitchen sink
COST BREAK DOWN
Item no & activity: 1.10 site clearing with avg. depth of 20cm
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Project: 0.00
Item no & activity: 1.20 Bulk excavation to a 80 cm from the NGL
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
(birr) unit
D.labor 18 1.000
Const.
Forman 1 0.250
2.
Manpowe
r Total
1. Material Total "A" 0.00 "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 90.765
2. Profit and overhead cost (birr) = 25% 22.691
Total unit cost (birr) 113.46
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Const.
Forman 1 0.042
(birr) unit
Stone m 3
0.31 160.00 49.60 D.labor 4 1.000
Coarse
gravel m3 0.03 240.00 7.20 Mason 2 1.000
Const.
Forman 1 0.250
Total 'A' (birr) 56.80 Total 'B' (birr)
1. Material Total "A" 56.80 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 72.637
2. Profit and overhead cost (birr) = 25% 18.159
Total unit cost (birr) 90.80
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Cement qt 1.47 250.00 367.50 D.labor 12 1.000
Sand m 3
0.53 60.00 31.50 Mason 1 1.000
Const.
Gravel m3 0.74 240.00 177.60 Forman 1 1.000
Water m 3
0.22 20.00 4.40
Total 'A' (birr) 581.00 Total 'B' (birr)
1. Material Total "A" 581.00 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 727.738
2. Profit and overhead cost (birr) = 25% 181.934
Total unit cost (birr) 45.48
Project: concrete work
Item no & activity: 2.20 C-25 concrete cast into form work & vibrated in formwork (excl. form wo
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Cement qt 3.18 250.00 78.62 D.labor 8 1.000
Sand m 3
1.36 214.28 157.56 Mason 2 1.000
Const.
Gravel m3 0.68 714.28 1050.41 Forman 1 1.000
Water m 3
1.59 0.50 0.80
Total 'A' (birr) 1287.38 Total 'B' (birr)
1. Material Total "A" 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 216.133
2. Profit and overhead cost (birr) = 25% 54.033
Total unit cost (birr) 270.17
(birr) unit
2.0cm
thick
board m3 0.013 7165.00 93.15 D.laborer 8 1.000
diameter
6
eucalypt
us m 1.05 6.70 7.04
diameter
12eucaly Carpente
ptus m 1.05 14.20 14.91 r 4 1.000
Const.
Nail kg 0.30 25.10 7.53 Forman 1 0.668
Mould oil lit 0.60 3.50 2.10
Total 'A' (birr) 124.72 Total 'B' (birr)
1. Material Total "A" 124.72 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 172.931
2. Profit and overhead cost (birr) = 25% 43.233
Total unit cost (birr) 216.16
(birr) unit
2.0cm
thick
board m3 0.013 36.58 0.48 D.laborer 8 1.000
diameter
6
eucalypt
us m 1.05 10.00 10.50
diameter
12eucaly Carpente
ptus m 1.05 253.50 266.18 r 4 1.000
Const.
Nail kg 0.30 168.67 50.60 Forman 1 0.640
Mould oil lit 0.60 8.00 4.80
Total 'A' (birr) 332.55 Total 'B' (birr)
1. Material Total "A" 332.55 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 332.552
2. Profit and overhead cost (birr) = 25% 83.138
Total unit cost (birr) 415.69
Project: rieforcement bar
Item no & activity: 2.40 Cutting, bending, placing in position bar spacer & tying wire(8-20)
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Reinforc
ement
Bar kg 1.05 180.00 189.00 D.labor 4 1.000
Bar
tie wire kg 0.02 20.00 0.40 Bender 4 1.000
Const.
Forman 1 0.250
Item no & activity: 3.10 50cm thick stone masonry below NGL (cement sand mortar-1:4)
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Stone m 3
1.33 160.00 212.80 D.labor 12 1.000
Cement qt 1.50 251.50 377.25 Mason 3 1.000
Const.
Sand m3 0.40 60.00 24.00 Forman 1 0.501
Water m 3
0.20 20.00 4.00
Total 'A' (birr) 618.05 Total 'B' (birr)
1. Material Total "A" 618.05 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 745.672
2. Profit and overhead cost (birr) = 25% 186.418
Total unit cost (birr) 932.09
(birr) unit
20cm
HCB pcs 12.65 12.50 158.13 D.labor 6 1.000
Cement qt 0.10 251.50 24.40 Mason 3 1.000
Const.
Sand m3 0.03 60.00 1.68 Forman 1 0.375
Water m 3
0.20 20.00 4.00
Total 'A' (birr) 188.20 Total 'B' (birr)
1. Material Total "A" 188.20 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 218.420
2. Profit and overhead cost (birr) = 25% 54.605
Total unit cost (birr) 273.02
(birr) unit
10cm
HCB
(Class C) pcs 12.65 10.50 132.83 D.labor 4 1.000
Cement qt 0.10 251.50 24.40 Mason 2 1.000
Const.
Sand m3 0.03 60.00 1.68 Forman 1 0.250
Water m 3
0.20 20.00 4.00
Total 'A' (birr) 162.90 Total 'B' (birr)
1. Material Total "A" 162.90 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 193.364
2. Profit and overhead cost (birr) = 25% 48.341
Total unit cost (birr) 241.71
B.
A. Manpow
Material er
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
G - 32
corrugate
d iron
sheet m2 1.25 170.60 213.25 Helper 2 1.000
Decra tile Ml 0.12 452.00 54.24 carpenter 1 1.000
Roofing
nail Kg 0.08 25.10 2.01 Forman 1.00 0.125
Washer Pcs 4.20 0.80 3.36
1.
Material
Total "A" 272.86 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 279.505
2. Profit and overhead cost (birr) = 25% 69.876
Total unit cost (birr) 349.38
project ; SANITARY
Item no & activity: 3.20 100mm PVC down pipe with metal stirrups
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
PVC pipe
f
100mm m 1.05 20.50 21.53 D. labor 2 1.000
Metal
stirrup f
6mm pcs 1.00 45.50 45.50 plumber 1 1.000
Constr.
Forman 1 0.083
B.
A. Manpow
Material er
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Upper
and lower
chord Ø
10cm ml 1.10 23.00 25.30 DL 2 1.000
Carpente
Nail Kg 0.49 25.10 12.30 r 1 1.000
Construct
Fixing ion
band ,, 0.12 40.00 4.80 Forman 1 0.125
Anti
termite
paint Lit 0.06 4.84 0.29
Total 'B'
Total 'A' (birr) 42.69 (birr)
2.
1. Manpowe
Material r Total
Total "A" 42.69 "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 47.459
2. Profit and overhead cost (birr) = 25% 11.865
Total unit cost (birr) 59.32
B.
A. Manpow
Material er
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
chord Ø
8cm ml 1.10 8.95 9.85 D/L 2 1.000
Carpente
Nail Kg 0.49 25.10 12.30 r 1 1.000
Construct
Fixing ion
band ,, 0.12 40.00 4.80 Forman 1 0.125
Anti
termite
paint Lit 0.06 4.84 0.29
Total 'B'
Total 'A' (birr) 27.23 (birr)
1.
Material
Total "A" 27.23 2.Manpower Total B
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 31.844
2. Profit and overhead cost (birr) = 25% 7.961
Total unit cost (birr) 39.81
(birr) unit
Purling(7x
5cm) ml 1.10 10.67 11.73 D/L 2 1.000
Carpente
Nail Kg 0.49 25.10 12.30 r 1 1.000
Construct
Fixing ion
band ,, 0.12 40.00 4.80 Forman 1 0.125
Anti
termite
paint Lit 0.06 4.84 0.29
Total 'B'
Total 'A' (birr) 29.12 (birr)
1. 2.
Material Manpowe
Total "A" 29.12 r 2. Manpower Total B
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 33.097
2. Profit and overhead cost (birr) = 25% 8.274
Total unit cost (birr) 41.37
(birr) unit
Cement qt 0.02 600.00 11.40 D.labor 2 1.000
Sand m 3
0.003 500.00 1.50 Plasterer 2 1.000
Const.
Forman 1 0.250
Water m 3
0.09 30.00 2.55
Total 'A' (birr) 15.45 Total 'B' (birr)
1. Material Total "A" 15.45 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 36.933
2. Profit and overhead cost (birr) = 25% 9.233
Total unit cost (birr) 46.167
Total unit cost (birr) for three coat 138.50
Item no & activity: 8.50 Ceramic wall tiles stuck with cement mortar (150*150*6mm)
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Ceramic
tile-
150*150
*6mm M2 1.05 600.00 630.00 D.labor 2 1.000
Cement qt 0.06 600.00 36.00 Tiller 1 1.000
Const.For
Sand m3 0.01 500.00 5.00 man 1 0.167
white
cement
grout m3 0.001 150.00 0.15
Water m 3
0.09 24.00 2.04
Total 'A' (birr) 673.19 Total 'B' (birr)
1. Material Total "A" 673.19 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 708.786
2. Profit and overhead cost (birr) = 25% 177.197
Total unit cost (birr) 885.98
Project: 0.00
Item no & activity: 9.10 3 coats plastic emulsion paint to plastered wall & concrete surface
As per BDE
standard page 8
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Plastic
paint lit 0.25 350.00 86.10 Painter 2 1.000
stucco kg 0.15 200.00 30.00 D.labor 2 1.000
Animal
glue kg 0.03 200.00 6.00 Forman 1 0.167
sand
paper pcs 0.03 400.00 12.00
Brush pcs 0.01 50.00 0.50
Total 'A' (birr) 134.60 Total 'B' (birr)
1. Material Total "A" 134.60
2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 147.221
2. Profit and overhead cost (birr) = 25% 36.805
Total unit cost (birr) 184.03
Item no & activity: 9.10 3 coats plastic emulsion paint to plastered concrete surface(ceiling)
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Plastic
paint lit 0.25 600.00 147.60 Painter 2 1.000
stucco kg 0.15 200.00 30.00 D.labor 2 1.000
Animal
glue kg 0.03 200.00 6.00 Forman 1 0.167
sand
paper pcs 0.03 400.00 12.00
Brush pcs 0.01 50.00 0.50
Total 'A' (birr) 196.10 Total 'B' (birr)
1. Material Total "A" 196.10 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 211.245
2. Profit and overhead cost (birr) = 25% 52.811
Total unit cost (birr) 264.06
Project: finishing paint
Item no & activity: 9.10 one coat of varnish and two coats of anti - rust paint.
As per BDE
A . Material standard page 8 B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Varnish
paint lit 0.08 600.00 48.00 Painter 1 1.000
Anti -
rust Lit 0.16 55.25 8.84 D.labor 1 1.000
Brush pcs 0.01 50.00 0.50 Forman 1 0.167
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
4mm
thick
clear
glass m2 1.05 800.00 840.00 D.labor 2 1.000
putty kg 1.05 65.00 68.25 glazer 1 1.000
Constr.
Forman 1 0.063
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
PVC pipe
f
100mm m 1.05 30.00 31.50 D. labor 2 1.000
Metal
stirrup pHs 1.00 90.00 90.00 plumber 1 1.000
Constr.
Forman 1 0.083
(birr) unit
D.labor 1 1.000
Cement qt 0.22 600.00 132.30 Chiseler 1 1.000
Sand m3 0.07 500.00 35.00 Tiller 1 1.000
Constr.
Water m3 0.09 24.00 2.04 Forman 1 0.250
Total 'A' (birr) 169.34 Total 'B' (birr)
1. Material Total "A" 169.34 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 183.989
2. Profit and overhead cost (birr) = 25% 45.997
Total unit cost (birr) 229.99
A.
Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Door(70X2
10)CM M2 1.00 1500.00 1500.00
Paint 1.00 50.00 50.00 metal wor 2 0.250
Forman 1 0.125
A.
Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
A.
Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
GRILL kg 1.00 300.00 300.00
Total 'A' (birr) 300.00 Total 'B' (birr)
Item no
&
activity: 1.10 Angle iron 50x50x5mm L=50mm
B.
A. Manpow
Material er
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Daily
Angle Iron pHs 1.00 160.00 160.00 Laborer 1 1.000
Welder 1 1.000
Const.
Forman 1 0.083
1.
Material
Total "A" 160.00 2. Manpower Total "B"
Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 163.620
2. Profit and overhead cost (birr) = 25% 40.905
Total unit cost (birr) 204.000
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
Chip
wood
20mm m2 1.05 500.00 525.00 Forman 1 0.500
Carpente
r 1 1.000
Dl 2 1.000
A . Material B. Manpower
Type Unit Qty Rate Cost per Type # U.F.
(birr) unit
window
sill Ml 1.02 151.50 154.53 Forman 1 0.167
cement Qut 0.13 180.00 23.40 Mason 1 1.000
sand m3 0.03 90.00 2.70 Dl 2 1.000
chiseler 1 1.000
Manpower C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
dozer 1 1 1500.00 12000.00
Location: JIGJIGA
Daily out put: 280.00 m3
Manpower C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
dozer 1 1 1500.00 12000.00
Location: JIGJIGA
As per
BDE
standar
d
Page11
Daily out put: 14.08 m3 or 33
Manpower C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
65.00 1170.00 Tools 18 1 0.40 57.60
201.46 50.37
Location: JIGJIGA
Daily out put: 225.00 m3
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
0.00 Dozer D8N 1 8 1500.00 12000.00
0.00
r Total "B" 3.
0.00
Equipment Total "C" 53.33
Location: JIGJIGA
assumed from borrow to Daily out put: 164.95 m3
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
Loader 1 1 500.00 4000.00
Dump truck 2 1 900.00 14400.00
Location: JIGJIGA
m site & deposit within 2km from site Daily out put: 496.00 m3
Manpower C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
Loader 1 1 500.00 4000.00
Manpower C. Equipment
hourly Daily cost Type # U.F. Rental Daily cost
rate
costbrr (birr) (birr/hr) (birr)
31.20 124.80 Tools 4 8 0.40 12.80
120.00 240.00
200.00 50.00
Total 'B' (birr) 414.80 Total 'C' (birr) 12.80
r Total "B" 15.36 3. Equipment Total "C" 0.47
utput Daily output
Location: JIGJIGA
As per
BDE
standar
d Page
Daily out put: 12.00 m3 11
Manpower C. Equipment
hr (birr) hr cost Type # hr Rental Daily cost
rate
(birr) (birr/hr) (birr)
8.50 102.00 Mixer 1 8 187.00 1496.00
20.00 20.00
142.85 142.85
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
31.20 249.60 Mixer 1 8 188.00 1504.00
120.00 240.00 Vibrator 2 8 25.00 400.00
As per
BDE
standar
d page
Daily out p 16.00 m2 12
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
201.46 134.58
Location :JIGJIGA
Daily out put: 16.00
As per
BDE
standar
d page
0 16.00 m2 12
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
0.00 0.00
0.00 0.00
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
93.60 374.40
201.46 50.37
Location: JIGJIGA
As per
BDE
standar
d page
ment sand mortar-1:4) Daily out put: 6.00 m3 13
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
31.20 374.40 Tools 3 8 0.40 9.60
93.60 280.80
201.46 100.93
Location: JIGJIGA
cement mortar both sides As per
BDE
standar
d page
Daily out put: 18.00 m2 12
ring
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
201.46 75.55
Location: JIGJIGA
ent mortar both As per
BDE
standar
d page
Daily out put: 12.00 m2 12
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
Location: JIGJIGA
As per
DCEE
Daily out put: 34.00 m2 out put
C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
201.46 25.18
93.60 93.60
201.46 16.79
Location: JIGJIGA
hord Ø 10cm) Daily out put: 40.00 ml
C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
93.60 93.60
201.46 25.18
Location: JIGJIGA
diagonal Ø 8cm) Daily out put: 40.00 ml
C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
93.60 93.60
201.46 25.18
Location: JIGJIGA
Daily out put: 48.00 ml
C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
93.60 93.60
201.46 25.18
Location: JIGJIGA
1:3) for external wall, internal As per
BDE
standar
d page
urfaces Daily out put: 14.00 m2 14
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
31.20 62.40 Tools 2 1 0.40 0.80
93.60 187.20
201.46 50.37
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
201.46 33.58
Location: JIGJIGA
As per
BDE
standar
d page
wall & concrete surface Daily out put: 18.00 m2 14
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
Location: JIGJIGA
As per
BDE
standar
d page
concrete surface(ceiling) Daily out put: 15.00 m2 14
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
201.46 33.58
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
31.20 31.20
201.46 33.58
Location: JIGJIGA
glass Daily out put: 20.00 m2
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
201.46 12.59
Location: JIGJIGA
Daily out put: 40.00 m
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
201.46 16.79
Location: JIGJIGA
1:3 Daily out put: 17.50 m2
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
31.20 31.20 Tools 1 8 0.40 3.20
57.20 57.20
114.40 114.40
201.46 50.37
Total 'B' (birr) 253.17 Total 'C' (birr) 3.20
r Total "B" 14.47 3. Equipment Total "C" 0.18
utput Daily output
Location: JIGJIGA
C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
1.47 1920.32
C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
51.00 12.75 tools 2 8 0.40 6.40
201.46 25.18
C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
Total 'B' (birr) Total 'C' (birr)
C. Equipment
Daily rate Daily cost Type # U.F. Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
31.20 31.20
93.60 93.60
Tools 1 1 0.40 3.2
201.46 16.79
As per
BDE
standar
d page
Daily out put: 8.00 m2 13
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
1826.7286659
Location: JIGJIGA
As per
BDE
standar
d page
Daily out put: 20.00 m2 13
Manpower C. Equipment
Daily rate Daily cost Type # Daily hr Rental Daily cost
rate
(birr) (birr) (birr/hr) (birr)
Total cost=A+B
1,233,356.19