ID Task Task Name Duration Start Jun 23, '19 Jun 30, '19 Jul 7, '19 Jul 14,

Jun 23, '19 Jun 30, '19 Jul 7, '19 Jul 14, '19 Jul 21, '19 Jul 28, '19
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 HD 8094 SENDERO ACTUALIZACION TECNOLOGICA 30 days Mon 6/24/19
2 PRE ACTIVIDADES TENCO 6 days Fri 7/12/19
3 LLEGADA DE CABLE 2 days Mon 7/15/19
4 LLEGADA DE EQUIPOS 1 day Fri 7/12/19
5 CONFIGURACION DE EQUIPOS LABORATORIO 3 days Mon 7/15/19
6 ENVIO EQUIPO CONFIGURADO A OBRA 2 days Thu 7/18/19
7 ACTIVIDADES HOME DEPOT 1 day Mon 6/24/19
8 INSTALACION SWITCHS 1 day? Mon 6/24/19
9 DIRECCIONAMIENTO IP 1 day? Mon 6/24/19
10 ACTIVIDADES CONSTRUCTIVAS 13 days Wed 7/17/19
11 INSTALACION CABLEADO 5 days Wed 7/17/19
12 INSTALACION DE EQUIPOS 3 days Wed 7/24/19
13 PUESTA EN MARCHA 2 days Mon 7/29/19
14 AJUSTES FINALES 2 days Wed 7/31/19
15 CAPACITACIÓN 0.5 days Fri 8/2/19
16 ENTREGA DE SISTEMA 0.5 days Fri 8/2/19

Task Project Summary Manual Task Start-only Deadline

Project: 19BD081 HD 8094 SEN Split Inactive Task Duration-only Finish-only Progress
Date: Mon 6/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone