DAILY REPORT

Format No: KPS-ALSO-AD-21(R0)

Date: 08. Jan. 2023 A ENGR SUPVR MGR


P
Department
P
Electrical Team
R
O
V
1. Manpower:
E

Identification Present Absent Leave W/off Total Remark


Korean 2 - - - 2
Engineers 4 - - - 4
Technicians 4 - - - 4
Electrician - - - - -
Total 10 - - - 10 See Note Below

2. WORK DESCRIPTION PERFORMED:


STATUS MAN
SYSTEM WORK DESCRIPTION
Percentage POWER
Completed
UPS - Performed weekly PM check for UPS system.
100%
Battery Completed
- Performed weekly PM check sheet for Battery charger system
charger 100%
Completed
Firefighting - Performed weekly PM check sheet for firefighting system.
100%
Completed
GPRS - Performed weekly PM check sheet for GPRS.
100%
SCR
[Req. No.: 19265] Found spare breaker in container and tested it, same problem In progress
compressor
happened, returned to BDP-902 until new breaker arrive.
904
UREA [Req. No.: 19308] found spare ventilation fan in container, swapped it with Completed Electrical
ventilation defective one and now working normally. 100% Team
- Checked crane in PH#3 area 1 for not working remotely, found loose connection Completed
Crane PH#3-1
on the remote receiver, rectified it and now working normally. 100%
- Following Wartsila and ABB email reply regarding REF615 for BAA-912
Common In progress
bootloader issue trouble shooting.
- Following and updating MR/IR status.
- Updating work permit list.
Office - Preparing weekly major jobs.
(Document/ In Progress
- Preparing 48K ERH PM report
EPMS/Meeting)
- Preparing Spare parts, consumables, tools and devices plan of 2023
- Clearing Completed T.M on EPMS (Performed work).

3. Holiday Schedule:
Day Staff Date
Friday 2023-01-06
Saturday 2023-01-07

4. Note
- N/A