Professional Documents
Culture Documents
សាយ ដាស៊ីន - I5EE - 2019-2020 - Dasin Say
សាយ ដាស៊ីន - I5EE - 2019-2020 - Dasin Say
វិទ្យាស្ថានបច្ចេរវិទ្យារម្ពជា
ុ
គ្ច្ក្ោងសញ្ញ
ា បក្តវិសរ
វ រ
ោរសិរាច្ល្ើខ្សែបណ្ដ
ា ញបញ្ជូ នតង់សយង់សពស១
់ ១៥គ្ីឡវ៉ា
ូ ុល្ពីអូច្ក្តេះច្ៅោន់
អនុស្ថានីយក្៍ ពេះសីហនុទ្យី២
MINISTERE DE L’EDUCATION,
DE LA JEUNESSE ET DES SPORTS
វិទ្យាស្ថានបច្ចេរវិទ្យារម្ពជា
ុ
គ្ច្ក្ោងសញ្ញ
ា បក្តវិសរ
វ រ
អនុញ្ញ
ា តឲ្យោរពារគ្ច្ក្ោង
នាយរវិទ្យាស្ថាន: _________________
ោរសិរាច្ល្ើខ្សែបណ្ដ
ា ញបញ្ជូ នតង់សយង់សពស១
់ ១៥គ្ីឡវ៉ា
ូ ុល្ពីអូច្ក្តេះច្ៅោន់អនុ
ស្ថានីយក្៍ ពេះសីហនុទ្យី២
ស្ថស្ត្ស្ថាចារយទ្យទ្យួល្បនទរ
ុ : បណ្ឌិត វវ៉ា វណ្ណៈ ___________
អនរទ្យទ្យួល្សុសក្តូវរនងសហក្ាស
ុ : ច្ោរ ឆុំ ច្ឆ្ម្វឌឍនា______
This thesis can be done successfully with the effort of everyone whom spent their time
to give extremely valuable advice and recommendation.
Moreover, I would like thank to Dr. CHRIN Phok, head of Department of Electrical
and Energy Engineering of ITC. Beneath his control, Department of Electrical and Energy
Engineering improves the quality of studying to the good position in the society that be
recognized by our nation and other nation in the globe.
Additionally, I would like thank to Dr. VAI Vannak, my thesis advisor. Below his
advices, my research can be finished on time in high quality and responsibility. During writing
thesis, he always gave me good ideas for considering and analyzing.
Furthermore, I would like thank to Mr. CHHOM CHHOUM Vathana, the Project
Manager of SCHNEITEC POWER CO., Ltd whom gave me the opportunity to intern in this
company. He spent his free time to discuss and consult me about my thesis and also trained me
the way of practical knowledge that are related to my topic of the thesis.
Finally, I would like to thank to all my lecturers and seniors of Electrical and Energy
Engineering Department of ITC who gave me the vital knowledge of method and concept for
considering.
i
សេចក្តេ
ី សខេប
បណ្ដ
ា ញបញ្ជន
ូ ថាមពលអគ្គិ សនីគ្ឺមានសារៈសំ ខាន់ ណ្ដស់ សម្រមាប់ ជីវត
ិ រស់ នៅម្របចំថ្ងៃក្នុងការ
ឆ្ងៃយៗ។
គ្ី ូវល
ុ ន្ដលអូ សនចញមក្ពីអនុសាានីយ៍អូ នម្រតេះនៅកាន់ អនុសាានីយ៍ម្រពេះសី ហនុទីពីរ។ ជាមួ យគ្ននននេះផង
ន្ដលបងកន ង
ើ នោយសារន្តវតត មានរបស់ គ្នម្រមាងមួ យននេះ។
ii
ABSTRACT
The transmission line is very essential for human lives to transmit power from one place
to other. In fact, for HV transmission line, it is used to deliver power electricity from the
generated source to GS to GS for long distance.
In this thesis, I focus on HV transmission line 115kV where is from OTres substation to
GIS2 in Sihanouk Ville. Additionally, there are three scopes of work in this thesis such as;
choosing the overhead conductor, choosing circuit breaker and studying on impact of
environment and society which are caused by this project.
iii
ABBREVIATIONS AND SYMBOLS
AC Alternating Current
CB Circuit Breaker
DC Direct Current
HV High Voltage
OH Overhead
SS Substation
UG Underground
iv
CONTENT
ACKNOWLEDGEMENTS ..................................................................................................... i
សេចក្តីេសខេប ...................................................................................................................... ii
v
2.11. Determine Tension of Conductor .............................................................................. 11
2.12. Determine Sag of Conductor ..................................................................................... 14
2.12.1. Determine Sag at Equal Level ....................................................................... 14
2.12.2. Determine Sag at Unequal Level ................................................................... 15
2.12.3. Clearance........................................................................................................ 15
2.13. Protective Device ....................................................................................................... 17
2.13.1. Arcing Horn ................................................................................................... 17
2.13.2. Amor Rod....................................................................................................... 18
2.13.3. Circuit Breaker ............................................................................................... 19
3. METHODOLOGY .............................................................................................................. 23
3.1. Flow Chart ................................................................................................................. 23
3.2. Data Gatheredtor ........................................................................................................ 25
3.3. Calculate Load Current .............................................................................................. 25
3.4. Calculate Current Carrying Capacity......................................................................... 25
3.4.1. Calculate AC Resistance at Operation Temperature ......................................... 26
3.4.2. Calculate Heat Loss by Convection .................................................................. 27
3.4.3. Calculate Heat Loss by Radiation ..................................................................... 28
3.4.4. Calculate Heat Gained by Solar Radiation........................................................ 28
3.5. Calculate Impedance .................................................................................................. 28
3.5.1. Calculate Impedance of Transmission Line ...................................................... 28
3.5.2. Calculate Impedance of HV Supply .................................................................. 31
3.6. Calculate Voltage Drop of Conductor ....................................................................... 32
3.7. Calculate Fault Current in System ............................................................................. 32
3.8. Calculate Cable Fault Rating ..................................................................................... 33
3.9. Calculate Tension and Sag of Conductor .................................................................. 34
3.10. Choosing Protective Device ...................................................................................... 36
4. RESULT AND DISCUSSION ........................................................................................... 37
4.1. Result ......................................................................................................................... 37
4.2. Discussion .................................................................................................................. 40
5. STUDYING ON IMPACT OF ENVIRONMENT AND SOCIETY ................................. 42
5.1. Condition of Construction of Transmission Line ...................................................... 42
5.2. Affection of Building Transmission Line on the Environment and Society ............. 42
5.3. The Solution of Solving the Problem ........................................................................ 43
6. CONCLUSION ................................................................................................................... 44
vi
REFERENCE
APPENDICE
vii
LIST OF FIGURES
viii
LIST OF TABLES
ix
1. INTRODUCTION
I started training at SchneiTec Power CO., LTD since 17, February, 2020 until 23,
May, 2020. During training, I really worked hard at there for writing this thesis and learning
something new more and more for expanding my knowledge. Actually, It made realize
better that otherwise technical knowledge, I have many things to learn more and more,
especially soft skill and communication. Being a good engineer must have both soft and
hard skill because all of developments or technologies always give both to humanity
positive and negative impact. So, we should try to find many ways to create something new
to complete the need of human and reduce the negative impact as much as our possible.
1
SchneiTec Co., Ltd is at #36, Street 352, Sangkat Boeng Keng Kang Ti Muoy,
Khan Chamkar Mon, Phnom Penh Capital, Cambodia.
1.3. Objective
The objective of this thesis, we study on the high voltage transmission line 115 kV
where is transferred from OTres to GIS 2 in Sihanouk Ville. Additionally, we will focus
on the process of designing transmission line and study on negative impact what will be
happened because of this building with giving proper solution.
2
2. LITERATURE REVIEW
a. Construction
Towers for support of the lines are mad by wood either grown or laminated, steel or
aluminum (either lattice structures or tubular poles), concrete, and occasionally reinforced
plastics. The bare wire conductors on the line are generally made of aluminum (either plain
or reinforced with steel or composite materials such as carbon and glass fiber), though
some copper wires are used in medium distribution and low voltage connections to
customer premises. A major goal of overhead power line design to maintain adequate
clearance between energized conductors and the ground so as to prevent dangerous contact
with the line, and to provide reliable support for the conductors, resilience to storm, ice
loads, earthquakes and other potential damage causes.
3
b. Classification
Overhead power transmission lines are classified in the electrical power industry by
the range of voltage [1]:
➢ Low Voltage (LV): It is less than 1000V, used for connection between a residential or
small commercial customer and the utility.
➢ Medium Voltage (MV): It is between 1000V (1kV) and 69kV, used for distribution in
urban and rural areas.
➢ High Voltage: It is used sub-transmission and transmission of bulk quantities of electric
power and connection to very large consumers.
➢ Extra High Voltage (EHV; Transmission): It is from 345kV, up to about 800kV,
used for long distance, very high power transmission.
➢ Ultra High Voltage (UHV): It is higher than 800 kV, it enables the transmission of
five times more power, over six times the distance.
The decision to build a transmission line results from system planning studies to
determine how best to meet the system requirements. At this stage, the following factors
need to be considered and established [2]:
➢ Voltage level
➢ Conductor type and size
➢ Line regulation and voltage control
➢ Corona and losses
➢ Proper load flow and system stability
➢ Grounding
➢ Insulation coordination
➢ Mechanical design
• Sag and stress calculation
• Conductor composition
• Conductor spacing
➢ Structural design
• Structure types
4
• Stress calculation
In general, the factors affecting a mechanical design of the overhead lines are [2]:
To choose the proper cross-sectional area (mm2), we should think of these first below
firstly [2].
➢ The maximum amount of allowed current in the conductor
➢ The maximum amount of power loss allowed in line
➢ The maximum amount of allowed short-circuit current of conductor
➢ Required span and sag between spans
➢ Tension of conductor and clearance
➢ Short-circuit current of conductor
➢ Climate condition at line location (the possibility of wind and ice loading)
➢ The possibility of having corrosive conductor
𝑆
𝐼𝐵 = (Eq. 2.1)
√3×𝑉𝐿
Where
5
𝐼𝐵 : Load Current (𝐴)
𝜇.𝑓
𝑋 = 0.063598√ (Eq. 2.4)
𝑅1 (1+𝛼(𝑡2 −𝑡1 ))
6
2.6.2. Determine Heat Loss by Convection
Where
𝐻𝑆 = 𝛼𝑆 𝑆𝑑 (Eq. 2.7)
Where
7
2.7. Determine Impedance of Conductor
Where
𝐺𝑀𝐷
𝐿 ∶ 0.2𝑙𝑛 ( ), Inductance of conductor (H/𝑘𝑚) (Eq. 2.9)
𝐺𝑀𝑅𝐿
Where
Where
8
1⁄
𝐷𝑠𝑏 = 𝑟𝑒 − 4 (Eq. 2.18)
Where
𝑐 : No-load factor
Where
𝑍𝑇 : Impedance of transformer (Ω)
𝑈𝑟𝑇 : Nominal voltage of transformer at secondary side (𝑘𝑉)
𝑈𝑘𝑟 : Short-circuit impedance of transformer (%)
𝑆𝑇𝑟 : Rated apparent power of transformer (𝑀𝑉𝐴)
❖ Find Short-circuit Impedance of Transformer
The formula of short-circuit impedance of transformer is expressed by [6]:
𝐼𝑛 ×100
𝑈𝑘𝑟 = (Eq. 2.22)
𝐼𝑆𝐶,𝑆𝑒𝑐𝑜𝑛𝑑
Where
9
𝐼𝑆𝐶,𝑆𝑒𝑐𝑜𝑛𝑑 : Short-circuit current at transformer (𝑘𝐴)
𝐼𝑛,𝑆𝑒𝑐𝑜𝑛𝑑 ∶ Rated current of transformer at secondary (𝑘𝐴)
❖ Find Load Current at Secondary Side of Transformer
The formula of load current at secondary side of transformer is expressed by [6]:
𝑆𝑟𝑇
𝐼𝑛,𝑆𝑒𝑐𝑜𝑛𝑑 = (Eq. 2.23)
√3𝑈𝑛,𝑆𝑒𝑐𝑜𝑛𝑑
Where
𝑆𝑟𝑇 : Rated operating power of transformer (𝑀𝑉𝐴)
𝑈𝑛,𝑆𝑒𝑐𝑜𝑛𝑑 : Rated voltage of transformer at secondary side (𝑘𝑉)
√3×|𝑍𝐿𝑖𝑛𝑒 |×𝐼𝐵
%𝑉𝑑 = (Eq. 2.24)
𝑉𝐿
Where
𝑐×𝑈𝑛
𝐼𝑓 = (Eq. 2.25)
√3×∑ 𝑍
Where
𝑐 : Voltage factor
10
2.10. Determine Cable Fault Rating
When selecting a cable, the performance of the cable under fault conditions is an
important consideration. It is important that calculations be carried out to ensure that any
cable is able to withstand the effects of any potential fault or short-circuit.
1
𝐼𝑆𝐶,𝑐𝑜𝑛 = 𝐴𝑘√ (𝑘𝐴) (Eq. 2.26)
𝑡
Where
𝐴 : Cross-sectional area of conductor (𝑚𝑚2 )
𝜃𝑓 −𝜃𝑖
𝑘 : 148√𝑙𝑛 (1 + ), for aluminum conductor Factor depends on cable
228+𝜃𝑖
𝑈𝑇𝑆
Working Tension (T) = (Eq. 2.28)
𝐹.𝑂.𝑆
Where
The maximum working tension means the maximum value of horizontal tension in
case of the worst condition which means a condition under strong wind.
11
The real maximum tension loaded on the conductor is the maximum tension TS,Max
on high-side supporting point and is larger than the maximum working tension TMax.
Therefore, safety factor of conductor needs some margin when the maximum tension is
calculated.
TUTS / safety factor (2.5) ≥ Tension of conductor (under the severest condition)
Where
12
𝐴 = Conductor cross-sectional area (m2)
𝑡1 = Initial temperature ℃
𝑡2 = Final temperature ℃
𝑊= Weight of conductor and may include wind and/or ice loading (𝑁/𝑚)
𝑆 = Sag (m)
13
2.12. Determine Sag of Conductor
To ensure adequate vertical and horizontal clearance under all weather and electrical
loadings, and to ensure that the breaking strength of the conductor is not exceeded, the
behavior of the conductor catenary under all conditions must be known before the line is
designed. The future behavior of the conductor is determined through calculations
commonly referred to as sag-tension calculation. And the result of calculation of sag
depends on both when supports are at equal level and when supports are at unequal level.
Where
𝑊 : Weight of conductor (𝑁/𝑚)
𝐿 : Length span between two support (𝑚)
𝑇 : Tension of conductor (𝑁)
Where
𝑇
𝑐 : , The ratio between tension of conductor
𝑊
2.12.3. Clearance
15
❖ Urban Area
Table 2.2: Clearance for Area where Third Person Difficult to Enter
16
❖ At the Road or Railway Station
Note: when the clearance of conductor of any between supports, we can adjust the sag
and tension of the conductor again until it reaches the Everyday Stress condition (𝑇𝐸𝐷𝑆 ).
And if the clearance still cannot be accepted after adjusting at that condition, we must
revise of the sizing of conductor again.
17
this purpose by providing a bypass flashover the high voltage across the insulator
using air as a conductive medium.
Arcing Horns bypasses the high voltage across the insulator using air as a
conductive medium between horns. The small gap between the horns ensures that
the air between them breaks down resulting in a flashover and conduct the voltage
surge rather than cause damage to the insulator.
Arcing Horn basically form a Spark Gap across the insulator with a lower
breakdown voltage than the air path along the insulator surface, so an overvoltage
will cause the air to break down and the arc to form between arcing horns, diverting
it away from surface of the insulator. An arc between the horns is more tolerable for
the equipment because it provides more time for the fault to be detected and the arc
to be safely cleared by remote circuit breaker.
18
Figure 2.9: Amor Rod
High voltage circuit breaker technology has changed radically in the last 15
years. Most utility systems utilize a combination of bulk oil, minimum oil, vacuum,
air blast, SF6 two-pressure, and SF6 single-pressure circuit breakers. The SF6
single-pressure system circuit breaker has become the current ‘state of the art’
technology at transmission voltages. Further improvements of this single-pressure
version are being introduced with thermal assisted arc quenching, in order to
facilitate reduction in operating energy requirements leading to cost reduction and
reliability improvement.
It is important that for the maintenance of SF6 gas equipment like circuit
breakers, the technical personnel involved should have a complete understanding of
the system. They should not only know how to perform maintenance tasks, but also
why and when these tasks should be performed. Condition-based maintenance
(CBM) and Reliability centered maintenance (RCM) are being proposed to replace
periodic maintenance of EHV circuit breakers, in order to minimize the maintenance
costs.
Circuit breaker can be arbitrarily classified using criteria such as; intended
voltage application, location of installation (i.e. outdoor, indoor), their external
19
design characteristics, or perhaps the most important, method and medium used for
the current interruption.
In the design of air blast circuit breakers, the interrupting process is initiated by
establishing an arc between two parting contacts and by simultaneously opening a
pneumatic valve. A blast of high pressure air is blown over the arc column, thereby
subjecting it to the intense cooling, and quenching the arc between the contacts when the
arc column ionization is least at current zero. Whenever current at higher voltages need
to be interrupted, more breaking units are used, in series. Dry and clean air supply is one
of the essential requirements for the operation of ABCBs.
20
b. Oil Circuit Breaker
Oil circuit breakers can be further classified with reference to the quantity of oil
used as; Bulk Oil Circuit Breaker (BOCBs) and Minimum Oil Circuit Breakers
(MOCBs).
In BOCBs, the interrupting unit is placed in a tank of oil at earth potential and the
incoming and outgoing conductors are connected through insulator bushings. In MOCBs
on the other hand, the oil requirement can be minimized by placing the interrupting units,
in insulating chambers at the live potential, on an insulator column.
21
Figure 2.12: Cross Section of Vacuum Interrupter
SF6 gas circuit breaker, are widely used for EHV applications today, as Sulphur
hexafluoride (SF6) gas is an electronegative such as compactness and less maintenance
of EHV circuit breakers.
The excellent insulating properties of SF6 gas make it possible to design circuit
breakers with smaller overall dimensions, shorter contact gaps, which help in the
construction of outdoor breaker with fewer interrupters, and evolution of metal enclosed
SF6 gas insulated switchgear (GIS).
22
3. METHODOLOGY
23
Figure 3.2: Process of Selecting Cross-sectional Area
24
3.2. Data Gatheredtor
The current rating of conductor based on the following operational condition in the
real place install that effected by environment surround it.
According to (Eq.2.1),
𝑆
𝐼𝐵 =
√3𝑉𝐿
75000
Thus, 𝐼𝐵 = = 376.352 𝐴
√3×115
25
3.4.1. Calculate AC Resistance at Operation Temperature
𝛼 = 0.00403
𝑡1 = 20 ℃
𝑡2 = 75 ℃
= 0.0924𝑘
= 0.0924𝑘
𝑓 = 50 𝐻𝑧
1×50
We obtain, 𝑋 = 0.063598√ = 1.479
0.0924
26
Table 3.3: Skin Effect Factor
𝐻𝐶 = 387(𝑉𝑑)0.448 𝜃
𝑑 = 27 mm
= 47167 W/km
27
3.4.3. Calculate Heat Loss by Radiation
𝑑 = 27 𝑚𝑚
𝜃 = 40 ℃
𝑡 = 35 ℃
= 22054 𝑊/km
𝑆 = 1000 𝑊/𝑚2
𝑑 = 27 𝑚𝑚
Thus, 𝐼𝑍 = 711𝐴
28
We have 𝑅𝐴𝐶,75℃ = 0.0942 Ω/𝑘𝑚
𝑓 = 50 𝐻𝑧
𝐺𝑀𝐷
𝐿 = 0.2𝑙𝑛 ( ) (Eq. 2.9)
𝐺𝑀𝑅𝐿
𝑙 = 6.4 𝑘𝑚
Where
4
We obtain, 𝐷𝐴𝐵 = √3850.7309 × 8743.8907 × 8853.0229 × 3835.2784
= 5814.8 𝑚𝑚
4
𝐷𝐵𝐶 = √3833.015 × 8705.1837 × 8869.2838 × 3850.5963
= 5810.1 𝑚𝑚
4
𝐷𝐴𝐶 = √7615.71 × 7209 × 7503 × 7615.71
= 7484 𝑚𝑚
29
3
Thus, 𝐺𝑀𝐷 = √5814.8 × 5810.1 × 7484 = 6317.9 𝑚𝑚
Where
𝐷𝑏1 𝑏2 = 8498 𝑚𝑚
𝐷𝑐1𝑐2 = 10600.5707 𝑚𝑚
1⁄
𝐷𝑠𝑏 = 𝑟𝑒 − 4 = 10.514 𝑚𝑚 , (𝑟 = 13.5 𝑚𝑚) (Eq. 2.18)
3
Thus, 𝐺𝑀𝑅𝐿 = √333.757 × 298.908 × 333.845 = 321.554 𝑚𝑚
6317.9
𝐿 = 0.2𝑙𝑛 ( ) = 0.596 × 10−3 𝐻/𝑘𝑚
321.554
30
3.5.2. Calculate Impedance of HV Supply
𝐼𝑛,𝑆𝑒𝑐𝑜𝑛𝑑 ×100
𝑈𝑘𝑟 =
𝐼𝑆𝐶,𝑆𝑒𝑐𝑜𝑛𝑑
𝑆𝑟𝑇
𝐼𝑛,𝑆𝑒𝑐𝑜𝑛𝑑 =
√3𝑈𝑛,𝑆𝑒𝑐𝑜𝑛𝑑
31
We have 𝑆𝑟𝑇 = 240 𝑀𝑉𝐴 (APPENDIX B)
240000
We obtain, 𝐼𝑛,𝑆𝑒𝑐𝑜𝑛𝑑 = = 1204.9 𝐴
√3×115
1204.9×100
And 𝑈𝑘𝑟 = = 3.012 %
40000
1152 3.012
Thus, 𝑍𝑇 = × = 1.659 Ω
240 100
√3×|𝑍𝐿𝑖𝑛𝑒 |×𝐼𝐵
%𝑉𝑑 =
𝑉𝐿
𝑐×𝑈𝑛
𝐼𝑓 =
√3×∑ 𝑍
𝑈𝑛 = 115 𝑘𝑉
∑ 𝑍 = 𝑍𝑄 + 𝑍𝑇
1.1×115
Thus, 𝐼𝑓,𝑑1 = = 28.396 𝑘𝐴
√3×2.572
𝑈𝑛 = 115 𝑘𝑉
∑ 𝑍 = 𝑍𝑄 + 𝑍𝑇 + 𝑍𝑙𝑖𝑛𝑒
= 2.572 + 1.339 = 3.911 Ω
1.1×115
Thus, 𝐼𝑓,𝑑2 = = 18.674 𝑘𝐴
√3×3.911
1
𝐼𝑆𝐶,𝐴𝐶𝑆𝑅 = 𝐴𝑘√
𝑡
𝜃𝑖 = 75 ℃
𝜃𝑓 = 200 ℃
33
200−75
We obtain, 𝑘 = 148√𝑙𝑛 (1 + ) = 86.979 (Eq. 2.27)
228+75
𝑇𝑈𝑇𝑆
At 𝑡1 = 13 ℃, 𝑇𝑀𝑊𝑇 = = 48364 𝑁 (𝑇𝑈𝑇𝑆 = 120910 𝑁)
2.5
We have:
𝑝 = 680 𝑁/𝑚2
𝑑 = 27 𝑚𝑚 = 0.027 𝑚
𝐿 = 129 𝑚
𝐸𝐴 𝐸𝐴
𝐸𝐴𝛼(𝑡1 − 𝑡2 ) + (𝑊12 . 𝐿2 . 2 2
2 ) − 𝑇1 = (𝑊2 . 𝐿 . ) − 𝑇2
24𝑇1 24𝑇22
34
2
67100 × 106 × 572.555 × 10−6
2
+ (23.213 × 129 × ) − 48364
24 × 483642
By Newton Raphson method, we obtain 𝑇2 = 35955 𝑁 > 𝑇𝐸𝐷𝑆 (we must calculate it
again)
❖ Find 𝑻𝟐,𝑵𝒆𝒘
We assume 𝑡1 = 27 ℃
𝑡2 = 13 ℃
𝑇𝐸𝐷𝑆 = 48364 𝑁
𝑊1 = 14.205 𝑁/𝑚
𝑊2 = 23.213 𝑁/𝑚
We obtain, 𝑇2,𝑁𝑒𝑤 = 41393 𝑁
Due to 𝑇2,𝑁𝑒𝑤 < 𝑇𝐸𝐷𝑆 , thus the tension of conductor can be accepted.
❖ Calculate Sag of Conductor
According to (Eq. 2.31),
𝐿 ℎ2
𝑆𝑎𝑔 = 𝑐 (𝑐𝑜𝑠ℎ ( ) − 1) √{1 + 𝐿 }
2𝑐 4𝑐 2 𝑠𝑖𝑛ℎ2 (2𝑐)
We have 𝐿 = 129 𝑚
ℎ = 0.5 𝑚
𝑇0 = 41393 𝑁
𝑊 = 14.205 𝑁/𝑚
𝑇0
𝑐= = 2913.973 𝑚
𝑊
129 0.52
Thus, 𝑆𝑎𝑔 = 2913.973 (𝑐𝑜𝑠ℎ ( ) − 1) √{1 + 129 }
2×2913.973 4×2913.9732 ×𝑠𝑖𝑛ℎ2 (2×2913.973)
= 0.714 𝑚
35
❖ Calculate Clearance between First and Second Support
We have 𝐼𝐵 = 376.532 𝐴
𝑈𝑆𝑦𝑠𝑡𝑒𝑚 = 115 𝑘𝑉
𝐼𝑆𝐶,𝑑1 = 28.396 𝑘𝐴
𝐼𝑆𝐶,𝑑2 = 18.693 𝑘𝐴
Thus, we choose the CB which has 𝐼𝐵 = 3150 𝐴 , 𝐼𝑆𝐶 = 40 𝑘𝐴 and rated voltage 115 𝑘𝑉
& maximum voltage 126 𝑘𝑉.
36
4. RESULT AND DISCUSSION
4.1. Result
Specification
Type of Conductor ACSR
Cross-section Area (𝑚𝑚2 ) 572.555
Current Carrying Capacity of Conductor (𝐴) 718
Voltage Drop (%) 0.76
Fault Current in System 𝐼𝑓,3𝑝ℎ (𝑘𝐴) 28.396
Short-circuit Current of Cable (𝑘𝐴) 49.8
Specification
Type SF6 Indoor
Rated Voltage (𝑘𝑉) 115
Maximum Voltage (𝑘𝑉) 126
Rated Frequency (𝐻𝑧) 50
Rated Normal Current (𝐴) 3150
Breaking Capacity (𝑘𝐴 𝑟𝑚𝑠) 40
37
Table 4.3: Tension Sag and Clearance of Conductor
38
Support L (𝑚) h (𝑚) T (𝑘𝑁) Sag (𝑚) C (𝑚) Crossing
30-31 181 3.75 42.487 1.37 16.88 MV Line
31-32 113 2.5 41.04 0.552 17.448
32-33 210 3.5 43.028 1.82 17.18
33-34 133 0.25 41.481 0.757 18.243
34-35 159 1.5 42.04 1.068 18.932 MV Line
35-36 180 2.5 42.467 1.355 17.645
36-37 199 0 42.83 1.642 16.858
37-38 199 0 42.83 1.642 16.858
38-39 94 1.5 40.627 0.386 16.614
Table 4.4: Tension Sag and Clearance of Conductor at Strong Wind Condition
39
16-17 218 4.25 48.364 1.745 16.755
17-18 87 7.5 48.364 0.278 20.722
18-19 181 1.5 48.364 1.201 21.8 MV Line
19-20 219 10 48.364 1.761 18.739
20-21 169 1.25 48.364 1.05 17.45
21-22 180 0.25 48.364 1.2 15.8
22-23 176 0.75 48.364 1.137 16.863
23-24 125 0.25 48.364 0.574 16
24-25 155 3 48.364 0.882 17.118
25-26 206 0.75 48.364 1.558 17.442
26-27 106 1.25 48.364 0.413 17.837
27-28 180 0 48.364 1.189 16.811
28-29 169 1 48.364 1.048 17.452
29-30 120 1.25 48.364 0.53 16.47
30-31 181 3.75 48.364 1.02 17.23 MV Line
31-32 113 2.5 48.364 0.47 17.53
32-33 210 3.5 48.364 1.62 17.38
33-34 133 0.25 48.364 0.65 18.35
34-35 159 1.5 48.364 0.93 19.. 07 MV Line
35-36 180 2.5 48.364 1.2 17.8
36-37 199 0 48.364 1.454 17.046
37-38 199 0 48.364 1.454 16.546
38-39 94 1.5 48.364 0.324 16.676
4.2. Discussion
Tension, sag and clearance are played important to determine the proper size of
conductor. While the sag of conductor is dipped over, we can increase the tension of
conductor to reduce the sag to get the acceptable clearance. But if we increase the tension
of conductor too much, it can cause to damage of conductor or damage the support
structure. And if we decrease the tension of conductor, it causes the conductor can swing
and causes dangerous to humanity or animal life whom are in its clearance.
40
The short-circuit of conductor is also important to determine the proper conductor.
And generally we should choose any conductor which has short-circuit value is greater
than or equal to short-circuit of breaker. To choose this, we can prevent the conductor from
damage when there is fault in system randomly (i.e. sometimes when there is fault in
system, the conductor can be broke before circuit breaker trip).
41
5. STUDYING ON IMPACT OF ENVIRONMENT AND SOCIETY
Due to the needing of electricity is increased day by day in Preah Sihanouk Vill and this
becomes a big concern that we are facing and should try to solve this problem on the time and
efficiently. So, EDC decided to develop this region by building of the transmission line more.
Although the transmission line can lead Cambodia to the modern life and development but
anyway it still gives many disadvantages to us also. Actually, there is no development without
affecting. Especially, for building transmission line. Because its line route cannot be changed
as what we want. So, it can effect on the properties of people, natural area, environment, etc.
Therefore, we always study on the impact of the environment and society firstly before building
this.
Due to the conductor of overhead transmission line has no the insulation, so we can
be shocked while we enter its field. Generally, its field is determined as below:
• Adequacy of clearance of trees, shrubs, bushes, etc. from the line conductor is checked.
All trees, shrubs, bushes etc. which infringe on the clearances are to be cut.
• Small bush growth, shrubs, trees and buildings whose height is grew than 3m, these
must be trimmed or not allow to build.
• Trees or bushes growing inside or very close to the legs of tower should be cut or
removed.
• The horizontal clearance of HV transmission 115kV is 7.5m for each side. So in this
field, we are not allowed to build or do anything.
Although building of the transmission line can bring Cambodia to the modern life and
development, but it also gives many disadvantage to us.
• People’s house can be moved to another place because of building transmission line.
• People’s farm or any properties can be damaged.
• The building of transmission line can destroy natural, fauna or bird’s home.
• The soil must be damaged.
• The water can be polluted.
42
• This building can affect the economic of people and their living.
• There can be argument between people and owner…etc.
43
6. CONCLUSION
Based on the result above, we can realize that to determine the proper sizing of conductor,
we should think of many factors firstly before starting design such as; the electrical and
mechanical design. For electrical, beyond the current carrying capacity of conductor and power
loss, the short-circuit current of conductor is the main role to select the right conductor. And
for mechanical, the environment (weather, vibration, etc.), the character of line route, right-of-
way and required clearance are also important to selection the cross-sectional.
Additionally, the studying on the affection to the environment and society should be done
firstly before building the transmission line. Because it can cause many problems to the
humanity and natural life although it can produce enough electricity power to us. Actually,
there is no development without broking. But anyways, as an being engineer, we should be
both inner and outer engineering whom always bring the society to the modern life and try to
decrease the risk or damaged as much as possible.
44
REFERENCE
[2] T. Gonen, Electric Power Transmission System Engineering Analysis and Design, France,
2009.
[3] H. Saadat, Power System and Analysis, New York: Kevin Kane, 1999.
[9] EDC, Electric Power Technical Standards of the Kingdom of Cambodia, Cambodia: EAC,
July 2004.
APPENDICE
APPENDIX A: Specification of ACSR
Specification
Type ACSR
Diameter (𝑚𝑚) 27
Weight (𝑘𝑔/km) 1448
𝑅𝐷𝐶,20℃ (Ω/km) 0.0757
Rated Strength (𝑘𝑁) 120.91
Modulus of Elasticity (𝑀𝑃𝑎) 67100
Coefficient of Linear Expansion per ℃ 19.3 × 10−6
APPENDIX B: Specification of Transformer
APPENDIX C: Type of Steel Pole
APPENDIX D: Method of Calculate Tension
Case A
%% Determine Tension
clear all;
clc;
t1 = 13; % Initial temperature (oC)
t2 = 27; % Final temperature (oC)
t = t2 - t1; % Temperature rise (oC)
% g = 9.81; % Gravitational constant (m/s2)
Ec =67100e6; % Modulus of elasticity (N/m2)
Alpha = 19.3e-6; % Coefficient of linear expansion (/oC) or (/k)
A = 572.55e-6; % Cross-sectional area (mm2)
d = 0.027; % Overall diameter of cable (m)
T = 120910; % Ultimate strength (N)
k1= 2.5;
T_MWT = T/k1; % Maximum Working Tension (N)
T_EDS = T*0.24 % Everyday stress (N)
L = input('Span length(m)= '); % Span length (m)
T1 = T_MWT;
p = 680; % Wind pressure (N/m2)
WL = p*d; % Wind load (N/m)
W2 = 1.448*9.81; % Final conductor unit effective weight (N/m)
W1 = sqrt(W2^2 + (WL^2)); % Initial conductor unit effective weight (N/m)
M = Ec*A*Alpha*t + ((W1*L)^2*Ec*A/(24*T1^2))-T1;
N = ((W2*L)^2*Ec*A/24);
%% Solve equation by Newton Raphson method
syms x
f = x^3+M*x^2-N; % Function f(x)
g = diff(f); % Derivative of funtion g=f'(x)
n = input('Enter the number of decimal places:');
epsilon = 5*10^-(n+1)
x0 = input('Enter the initial approximation:');
for i=1:100
f0=vpa(subs(f,x,x0)); % Calculate value f at x0
f0_der=vpa(subs(g,x,x0)); % Calculate value g at x0
y=x0-f0/f0_der; % Formula
err = abs(y-x0);
if err<epsilon % Checking amount of error at each iteration
break
end
x0=y;
end
T2 = x0
%% Determine T_min
T_min = min(T2,T_EDS)
Case B
%% Determine Tension
clear all;
clc;
t1_new = 27; % Initial temperature (oC)
t2_new = 13; % Final temperature (oC)
t_new= t2_new - t1_new; % Temperature rise (oC)
% g = 9.81; % Gravitational constant (m/s2)
Ec = 67100e6; % Modulus of elasticity (N/m2)
Alpha = 19.3e-6; % Coefficient of linear expansion (/oC)
A = 572.55e-6; % Cross-sectional area (mm2)
W1_new = 1.448*9.81; % Final conductor unit effective weight (N/m)
W2_new = 23.2135; % W2 new (N/m)
T1_new = 29018.4; % Ultimate strength (N)
L = input('Span length(m)= '); % Span length (m)
T2_new = 48364;
M = Ec*A*Alpha*t_new + ((W1_new*L)^2*Ec*A/(24*T1_new^2))-T1_new
N = ((W2_new*L)^2*Ec*A/24)
%
syms x
f = x^3+M*x^2-N; % Function f(x)
g = diff(f); % Derivative of funtion g=f'(x)
n = input('Enter the number of decimal places:');
epsilon = 5*10^-(n+1)
x0 = input('Enter the initial approximation:');
for i=1:100
f0=vpa(subs(f,x,x0)); % Calculate value f at x0
f0_der=vpa(subs(g,x,x0)); % Calculate value g at x0
y=x0-f0/f0_der; % Formula
err = abs(y-x0);
if err<epsilon % Checking amount of error at each iteration
break
end
x0=y;
end
T2 = x0
%% Determine T_min
T_min = min(T2,T2_new)
APPENDIX E: Detail Each Sag of Conductor