ASUMSI VOLUME Stn
Emin (dy terpasang x jam nyala /1000) 348,000,000 Jt
daya terpasang 1,000,000 VA
jam nyala 1 bln 240 jam
EMIN 1 Thn 4,176,000,000 Jt
SPJBTL 10 th
BP 1,250 VA
UJL 250 VA
TARIF TUNGGAL 1,450 kWh
INVESTASI PLN 2,500,000,000 M
PERKIRAAN BPP 975 kWh
BIAYA OPERASIONAL TETAP 10,000,000 BULAN
BIAYA DEPRESIASI 187,000,000 TH
WACC 10%
PAJAK PENGHASILAN 25 %
BPP 234,000,000 Jt
BPP 1 Thn 2,808,000,000 Jt
biaya depresiasi 187,000,000 per tahun
biaya tetap 120,000,000 per tahun
PAJAK PENGHASILAN 265,250,000
MAKA HITUNGLAH
PBP ?
NPV ? APAKAH PROYEK TSB LAYAK
IRR ?
ROI ?
Thn
Rp 1,250,000,000
Rp 250,000,000
Thn
732% 733%
SELISIH ARUS SELISIH ARUS
KAS (PV) I KAS (PV) II
- 1,250,000,000 - 1,250,000,000
95,643,029 95,528,211
11,495,556 11,467,973
1,381,677 1,376,707
166,067 165,271
19,960 19,840
2,399 2,382
288 286
35 34
4 4
1 0