You are on page 1of 6

Project :

Package / Area :
Description :
Date :

NO. DESCRIPTION
UNIT

I. PRELIMINARIES
1. Mobilization of all personnel and manpower, provide skill and unskill
manpower for execution of work
(During construction, if any additional manpower required to meet
the construction schedule, the contractor shall mobilize and execute
the work without any additional cost to RAPP)
a) Project Manager Nos
b) Construction / Site Manager Nos
c) HSE Manager / QA&QC Manager Nos
c) Civil Superintendent, Civil Engineer, Civil Supervisor Nos
e) QA&QC, QS, Land Surveyor, Drafter, Scheduler Nos
f) HSE inspector / Safety Officer Nos
g) Back office management and staff Nos
h) Skilled and Unskilled manpower Nos
2. Demobilization of all personnel and manpower, upon completion of
the works, with the approval from the engineer
(During construction, if any additional manpower required to meet
the construction schedule, the contractor shall mobilize and execute
the work without any additional cost to RAPP)
a) Project Manager Nos
b) Construction / Site Manager Nos
c) HSE Manager / QA&QC Manager Nos
c) Civil Superintendent, Civil Engineer, Civil Supervisor Nos
e) QA&QC, QS, Land Surveyor, Drafter, Scheduler Nos
f) HSE inspector / Safety Officer Nos
g) Back office management and staff Nos
h) Skilled and Unskilled manpower Nos
3.
Mobilization of all required equipment, tools and materials to carry
out the work and to maintain them until job completion
(During construction, if any additional equipment and toolsrequired
to meet the construction schedule, the contractor shall mobilize and
execute the work without any additional cost to RAPP)

a) Service Crane upto 50 Ton Unit


b) Excavator Unit
c) Dump Truck Unit
d) Vibro Compactor Unit
e) Mini roller Compactor Unit
f) Mini Excavator Unit
g) Crane Truck / Foco Truck Unit
h) Generator Set Unit
4.
Demobilization of all required equipment, tools & materials upon
completion of the works, with the approval from the engineer
(During construction, if any additional equipment and toolsrequired
to meet the construction schedule, the contractor shall mobilize and
execute the work without any additional cost to RAPP)

a) Service Crane upto 50 Ton Unit


b) Excavator Unit
c) Dump Truck Unit
d) Vibro Compactor Unit
e) Mini roller Compactor Unit
f) Mini Excavator Unit
g) Crane Truck / Foco Truck Unit
h) Generator Set Unit
5. Provide all required tools & equipments such as forklift, scaffolding,
Lot
water pump, etc.
6. Establish and maintain during the entire period of stay at site
contractor's all temporary facilities such as oofice, workshop,
Lot
fabrication area, store, sanitary facilities, temporary water &
electrical supplies, etc.
7. Removal of all contractor's temporary facilities after completion of
the works and make the complete area clean before leaving the Lot
site, with the approval from the engineer
8. Site Office, Temporary Area Works / Material Storage Area
a) Site Office for Owner (Size = 4 x 6) M2 Unit
b) Contractor Site Office (Size = _ x _ ) M2 M2
c) Fabrication Workshop (Size = _ x _ ) M2 M2
d) Workers Rest Area (Size = _ x _ ) M2 M2
e) Sanitary Facilities such as Toilets Unit
f) Temporary Water source, & Electrical Power Tapping, area
Lot
cleaning and maintenance
g) Drainage Works Lot
9. Provision of site management & supervisory staff, as per
requirement of the services
a) Site management & supervisory staff Nos
b) Supervisors Nos
c) Operators Nos
d) QA & QC Staff, Safety Officers Nos
e) Skilled and Unskilled manpower Nos
10. Local Transport
a) Mini Bus Unit
b) Colt Diesel / Light Truck / Pick-up Unit
11. Loading and unloading of materials from logistic store to contractor's
Lot
fabrication workshop and to job site location
12. Provision & implementation of SMK3 Lot
- Contractor Safety Management System (CSMS)
- Proper Personal Protection Equipment (PPE)
- Security services for safekeeping & loss prevention of
equipment, tools and materials,
- Health insurances like Jamsostek during duration of contract
period, area cleaning & maintenance during and after completion
of the works
13.
Provide proper safety equipment & safety standard as necessary for
completion of the works as per directions of engineer

- safety helmet, safety shoes, helmet, gloves, mask Set


- safety body harness Set
- Others (as necessary for completion of the works as per
Lot
directions of engineer)
14.
Security of contractor's tools and equipment in scope contractor Lot

SUB TOTAL I. PRELIMINARIES


QTY Unit Rate Total Amount %

You might also like