Shortage of Material
Dear Sir,
We noticed we have continually received shortage notifications from key raw material supplies and
carriers. As per warehouse records, for three months in a row, we received a material shortage from
January 2024 to March 2024 under PO -2043-20, PO-2064-20, PO-2077-20, and PO-2085-20.
The total we received in raw materials is 168,000 kgs which is equal to 240 bulks. For every bulk, the
material average shortage is 5 kg per bulk. The kg needs to be refunded which is 240 bulk x 5kg =
1,200 kgs. As per calculation 1,200 kgs x RM 3.90 = RM 4,680.00 needs to be refunded to Roflex Pipe
Sdn Bhd.
Here are the details of the company bank account for your reference.
We regret to inform you that we do not expect a supply shortage situation. Kindly improve the
situation in the future.
Thank you.
Yours faithfully,
_______________
FW Wong