Professional Documents
Culture Documents
MCQ Ie JD
MCQ Ie JD
2. CPM is
(A) Dummy
(B) Event
(C) Activity
(D) Contract
(A) An activity consumes time and resources whereas an event does not consume time or resources
(D) The turning of a job on lathe is an event whereas job turned is an activity
(B) A compact estimate of the handling which must be done between various work sections
(C) The information for changes required in rearranging material handling equipment
(D) An approximate estimate of the handling which must be done at a particular station
11. Which of the following organisation is preferred in automobile industry?
(A) Taylor
(B) Drucker
(C) McGregor
(D) Galileo
13. A company spends considerable amount on publicity to promote sales. This expenditure in break
even chart is shown below the
14. The mathematical technique for finding the best use of limited resources in an optimum manner
is known as
2. PERT
(B) Provides a way for management to require that planning be done on a uniform and logical basis
(C) Permits management to foresee quickly the impact of variations from the plan
(A) Normal
(B) Binomial
(C) Beta
(D) Exponential
7. Which of the following are the guidelines for the construction of a network diagram?
(A) Each activity is represented by one and only one arrow in the network
9. Breakeven analysis is a
(A) Management
(D) Function/cost
(C) Provides a standard method for communicating project plans schedules and to time and cost
performance
(B) To divert the resources from noncritical advanced activities to critical activities
(C) To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
(A) One-fourth
(B) One-half
(C) Equal to
(D) Twice
5. Which one of the following techniques is used for determining allowances in time study?
7. The most popular type of organisation used for Civil Engineering Constructions is
(A) A job
(D) Machine
11. The time required to complete a task is established and a bonus is paid to the worker for every
hour he saves from the established time required. This type of incentive plan is known as
12. Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is
paid for the fixed percentage of time saved?
(B) Workshop
(D) Stores
14. The production scheduling is simpler and high volume of output and high labour efficiency are
achieved in the case of
1. Answer: Option D 2. Answer: Option D 3. Answer: Option B 4. Answer: Option C 5. Answer: Option
D 6. Answer: Option B 7. Answer: Option A 8. Answer: Option C 9. Answer: Option B 10. Answer:
Option A 11. Answer: Option C 12. Answer: Option A 13. Answer: Option D 14. Answer: Option A 15.
Answer: Option A
(A) (F × V)/P
(B) (F × P)/V
(B) The time when unit can run without i loss and profit
(C) Major function of the item and accomplishing the same at least cost without change in quality
8. A-B-C analysis
(C) Does not depend upon the unit cost of the item but on its annual consumption
10. A big advantage of PERT over Gantt charts is that in the former case
(B) Early start and late finish of an activity are clearly marked
(A) An event
(B) An activity
(C) A duration
1. Answer: Option D 2. Answer: Option A 3. Answer: Option C 4. Answer: Option D 5. Answer: Option
C 6. Answer: Option A 7. Answer: Option C 8. Answer: Option D 9. Answer: Option A 10. Answer:
Option D 11. Answer: Option D 12. Answer: Option D 13. Answer: Option B 14. Answer: Option A 15.
Answer: Option B
Practice Test: Question Set - 05
1. Work sampling is applied for
(B) Estimating the percentage of the time consumed by various job activities
(C) Finding out time standards, specially where the job is not repetitive and where time study by
stop watch method is not possible
3. The unit cost in case of batch production is __________as compared to jobbing production.
(A) Same
(B) Low
(C) High
(A) Productivity
(A)Value analysis
(B)Operation research
(C)Linear programming
(D)Model analysis
11. The reasons which are basically responsible for the formation of a queue should be that
(A) The average service rate Hess than the average arrival rate
(C) Output rate is constant and the input varies in a random manner
13. The artificial activity, which indicates that an activity following it cannot be started unless, the
preceding activity is complete, is known as
(A) Event
(C) Artificial
(D) Dummy
14. Pick up the incorrect statement from the following. A critical ratio scheduling
(A) Establishes the relative priorities among various activities on a common basis
1. Answer: Option D 2. Answer: Option D 3. Answer: Option B 4. Answer: Option D 5. Answer: Option
A 6. Answer: Option B 7. Answer: Option D 8. Answer: Option C 9. Answer: Option C 10. Answer:
Option C 11. Answer: Option D 12. Answer: Option B 13. Answer: Option D 14. Answer: Option D 15.
Answer: Option B
(D) Guessed times are used in PERT and evaluated times in CPM
(A) Operation
(B) Inspection
(C) Transport
(A) Analysis of a man-work method by using a motion picture camera with a timing device in the
field of view
Correct Answer
1. Answer: Option D 2. Answer: Option C 3. Answer: Option B 4. Answer: Option D 5. Answer: Option
C 6. Answer: Option D 7. Answer: Option D 8. Answer: Option B 9. Answer: Option C 10. Answer:
Option D 11. Answer: Option A 12. Answer: Option C 13. Answer: Option A 14. Answer: Option A 15.
Answer: Option A
2. The amount deducted from the salary of workers towards employee’s provident fund is
7. For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs.
20 and sales price is Rs. 30 per piece. The break even production per month will be
(A) 300
(B) 460
(C) 500
(D) 1000
(A) A circle
(C) An arrow
(A) CPM
(B) PERT
5. Time study is carried out to determine the time required to complete job by
(D) An apprentice
8. The technique for establishing and maintaining priorities among the various jobs of any project is
known as
(A) Latest start time of succeeding event earliest finish time of preceding event activity time
(B) Latest start time of the event earliest start time of the event
(C) Latest finish time of event earliest finish time of the event
12. Which of the following organizations is best suited for steel plants
(A) Inspection
(B) Transport
(D) Departmentation
(C) Calculations are easier, method is economical and less time consuming
Correct Answer
4. The objective of time study is to determine the time required to complete a job by
A) If the float is positive and the activity is delayed by a period equal to its total float, the completion
of project in not delayed
(B) If the float of an activity is negative, delay in its performance is bound to delay the completion of
project
(C) If the float of an activity is zero, the activity is critical and any delay in its performance will delay
the whole project
(A) By finding all the significant informations regarding the job, work place and machine tool etc
(B) By breaking up each operation into small elements which are measurable with the help of the
measuring device accurately
(C) By observing and recording the time taken by the operator for an operation
4. Routing
5. Graphical method, simplex method, and transportation method are concerned with
6. If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual
time, then according to Halsey 50-50 plan, wages for the job will be
(A) TR
8. The most suitable incentive plan for the maintenance section of an industry will be
(D) Simplification
(A) Normal
(B) Binomial
(C) Exponential
(D) Gaussian
12. Critical path on PERT/CPM chart is obtained by joining the events having
(A) Maximum slack
(D) No slack
(A) 8
(B) 12
(C) 16
(D) 20
Correct Answer
All industries
(C) Volunteers
(B) Gantt
(C) Taylor
(D) Newton
5. In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his
efficiency reaches
(A) 50%
(B) 66.67%
(C) 75%
(D) 80%
(B) The tail of the arrow indicates the start of the activity
(C) The head of the arrow indicates the end of the activity
(D) The arrows are drawn (to scale from) left to right
(A) Standardization
15. The chart which gives an estimate about the amount of materials handling between various work
stations is known as (A) Flow chart
Answer: Option A
(C) All industries employing more than 100 workers have to recruit apprentices
(D) Only industries employing more than 500 workers have to recruit apprentices
7. In product layout
(B) Cost of project will always be more than the estimated cost, if no timely corrections are taken
(C) A project can be subdivided into a set of predictable, independent activities (D) Activities are
11. Which of the following wage incentive plan is applied to all workers?
(A) Halsey plan
12. According to MAPI formula, the old machine should be replaced by new one when
(A) Duration
7. The procedure of modifying work content to give more meaning and enjoyment to the job by
involving employees in planning, organisation and control of their work, is termed as
(D) Only one factor should change at a time, others remaining constant
(B) Lowest possible cost and shortest possible time for project
(B) Sales
13. Which of the following type of layout is suitable for automobile manufacturing concern?
(B) Critical path method provides a realistic approach to the daily problems
(C) Critical path method avoids delays which are very common in bar chart (D) All of the above
15. The most important function of inventory control is
1. Answer: Option C 2. Answer: Option C 3. Answer: Option D 4. Answer: Option B 5. Answer: Option
B 6. Answer: Option A 7. Answer: Option B 8. Answer: Option C 9. Answer: Option D 10. Answer:
Option B 11. Answer: Option C 12. Answer: Option D 13. Answer: Option A 14. Answer: Option D 15.
Answer: Option D