Responsibles W14 W15

Phase 1
Customer milestones and quality plan (FOT / PPAP / SOP)
Customer requirements - received / defined
Team feasibility
Selection of material suppliers for production (BOM)
Selection of subsuppliers - external process
Phase 2
Proces Flow defined
Preliminary List of special characteristic defined
Tool design
Tool design verification + risk analysis (ex. Mold flow)
Proces FMEA
Pre-production Control Plan
Serial Control Plan
Instructions / Standard
Design of Indicators / Definition of measurement tools
Purchasing Tool Steel
Purchasing Standard Elements
Order PPAP from supplier (if necesary)
IMDS
Phase 3
CNC Programming
CNC Milling
HT
EE
Tool Assembly
First of tool
Tool Modification 1
Trials after TM1
Tool Modification 2
Trials after M2
MSA
Capability (process)
Tool validation
Phase 4
Training for operator
Production readiness audit
PPAP Part production
R&R (Run at rate)
PPAP Measurement
Laboratory test / Functional test
Supplier PPAP approval
Packaging trial and validation
PPAP completed
PPAP validation by customer
Phase 5
Serial Production Launch (SOP)
Feed back from Production
Continuous Improvement
W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36
5/15

FOT PPAP SOP


W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 Validation