You are on page 1of 27

CURRICULLUM VITAE

Ali. M
Electrical & Instrument
+6282174049940
alitopan9900@gmail.com
Batam, Indonesian

EDUCATION
 Senior High School ETIKA‐2 Pontianak

CERTIFICATED
 E & I Inspector : NO. OTI.EI.XXXI.05.15.666
 CABLE GLANDING and TERMINATION : NO. OTI.CBT‐IV.03.16.060
 TENISI K3 LISTRIK : NO.5/371/AS.02.04/XI/2021

SUMMARY JOB
More than 16 years extensive experienced in field of engineering, supervision, inspection,
fabrication, construction and installation of Electrical and instrumentation of offshore/onshore
in Oil & Gas platform such as platform utility module, Marine, Power Plant and Building. I have
ever been Work under Pressure. I like team work & have never leave a project under bad
condition. it gives a good sense of achievement and job satisfaction to have been a part of
team that gets the job done.

SKILL & ABILITY


 Contruction
 Cable Ladder/Tray Installation SS316, galvanize
 Installation Device Equipment like as F&G, JB, Lighting etc.
 Pulling Cable for Control, Electric, Instrument IS and ISE

 Install Glanding HAWK, CMP, and CAPRI product of Gland all Size
 Wiring Termination Control, Instrument, Lighting & small Power
 Inspection Equipment Installation, Cable Routing & Termination

Page 1 of 6
 Pre‐Comm and Commissioning
 Familiar with Instrument tools Multi Tester, Insulation Tester, Earthing Tester, Clamp
Meter
 Other system control I/O system list function test
 Hydraulic, Electrical pneumatic function test
 F&G, Instrument Device, HVAC, and sensor I/O function test
 Lighting system, Internal Communication system
 Cause and Effect general system testing
 Leak test, hydrotest of installation tubing instrument system

 Computer
 Microsoft Office (All Ver.)

 Understanding
 Ensure Contractor compliance with requirements of Inspection Test Plant & work
procedures.
 Monitor field construction activities to ensure requirements are meet in compliance
with drawings, specifications, and applicable codes.
 Issue Observation Report, Occurrence Report & NCR on Non‐complying products.
 Identify quality deficiencies and root causes at infancy to avoid substantial repetition
prior to discovery and minimize rework.
 Inspection equipment of Hazardous Area‐ensure equipment is suitable for the area in
which it is installed.
 Inspection all frame/support equipment electrical include installation for power
transformer, Main Switchboard, Emergency switchboard, Fixation Panels, Engine
Generators, etc.
 Familiar with electrical equipment inspection, installation, testing of electrical cable
LV/MV/HV, IPB/NPB, Substation Switchgear, Transformer, HV/LV motors, DCS, AC/DC
UPS‐Battery, Earthing systems, lightning arrester, Heat tracing system, etc.
 Prepared Check List & Datasheet of Electrical & Instrument Equipment.
 Witness and verify cable continuity test and insulation test or Insulation test including
the correct use and installation of cable glands.
 Squence Test Panel, Check Vibration, Temperature, RPM Motor.
 Check Earthing (proper electrical grounding) checks for continuity and resistance during
installation.
 Preparation of test records and reports.
 Completion of check sheet requirement and Planning of process to completion report.

Page 2 of 6
 Prepared Final Document dossier as Inspection Test Record include with incoming
material summary according ITP & requirement.
 Electrical Drawing, Symbol, Legend, Single Line Diagram, Layout Drawing, Cable
Schedule, and Detail Drawing.
 Learn about Hazardous Area Drawing.
 Material Specification, Standard Project / Specification. NEMA, NEC, IEC, IEEE, ANSI,
NFPA.
 Inspection Electrical work, Electrical Cabling, Cable Marking, Cable Glanding, Grounding
Cable and Pulling Cable, Connection and termination Cable, etc.
 Inspection Instrument work, Tubing Installation, Installation TT, FT, TE, LT, PDT, PDG, RTD.
 Pneumatic Testing Tubing.
 Electrical Equipment such as Panel Box, Junction Box, Marshalling Cabinet, Circuit
Breaker.
 Inspection of specification Installation Equipment.
 Cable Ladder and Cable Tray Installation and Inspection of Installation.
 Learn about Inspection, As built drawing, ITR, ITP, RFI, FIN, FIR, Material Control.
 Troubleshooting of control system.

Page 3 of 6
WORK EXPERIENCE

Name of Company : PT.DACHENG ENGINEERING


Work Location : TISSUE PROJECT APP.SINARMAS OKI PALEMBANG
Position : QA/QC Electrical & Instrument Inspector
Period : Feb”6, 2023 ‐ Present
Reason for Leaving :

Name of Company : PT. PP


Work Location : TIMOR‐1 C0AL FIRED STEAM POWER PLANT 2X50 MW
Position : Supervisor Electrical / Commissioning
Period : Okt”10 2022 – Jan” 28 2023
Reason for Leaving : Job Completed

Name of Company : PT. PP


Work Location : PLTMG 140.MW FREEPORT TIMIKA
Position : Supervisor Electrical
Period : Sept” 27 2021 – Sept“ 12 2022
Reason for Leaving : Job Completed

Name of Company : PT.TOSHIBA PLANT SYSTEM & SERVICE CORP ( TPSC )


Work Location : PLTU TANJUNG JATI B 2X1000 MW
Position : QA/QC Electrical Engineer
Period : Jun” 15 2019 – Augs“ 31 2021
Reason for Leaving : Job Completed

Page 4 of 6
Name of Company : PT.PP ( EPCC )
Work Location : PLTMG. MERAUKE 2X50 MW
Position : Supervisor Electrical
Period : Jan“ 11 2019 – Jul“ 11 2019
Reason for Leaving : Job Completed

`Name of Company : PT.INDO FUJI ENERGI


Work Location : PLTP EPCC KAMOJANG UNIT 1 1X50 MW
Position : Supervisor Instrument
Period : Agus” 14 2017 – Des” 15 2018
Reason for Leaving : Job Completed

Name of Company : PT.INDO FUJI ENERGI


Work Location : PLTMG PONTIANAK KALBAR 4X25 MW
Position : QA/QC Electrical & Instrument Inspector
Period : Jun” 01 2016 – Jan” 15 2017
Reason for Leaving : Job Completed

Name of Company : PT.TPE INDONESIA


Work Location : PLTU TANJUNG UNCANG BATAM 2X100 MW
Position : QA/QC Electrical & Instrument Inspector
Period : Augs” 01 2015 – Mar” 2016
Reason for Leaving : Job Completed

Name of Company : PT.TPE INDONESIA


Work Location : SIEMANS BATAM PROJEC YAMAL LNG
Position : QA/QC Electrical & Instrument Inspector
Periode : Jul” 01 2014 – Jun” 31 2015
Reason For Leaving : Job Completed

Page 5 of 6
Name of Company : PT.EIN INDONESIA
Work Location : PT.ASL MARINE BATAM
Position : Electrician Facillity Drydock
Period : Feb” 10 2008 – Sep” 2013
Reason for Leaving : Job Completed

Name of Company : PT.EIN INDONESIA


Work Location : PT.ASL SHIPYARD BATAM
Position : Electrical Technician Floating Dock
Period : Marc” 08.2005 – Febr” 06 2008
Reason for Leaving : Job Completed

Name of Company : CV.TENAGA SUKSES


Work Location : BATAM INDONESIA
Position : Electrical Technician Installation
Period : Augs” 02.1999 – July” 08.2005
Reason for Leaving : Job Completed

Page 6 of 6
PT PP (Persero) Tbk.
Plaza PP – Lantai 3
Jl. Letjend. TB. Simatupang No. 57
Pasar Rebo - Jakarta 13760
Telpon : (021) 840 3902
Fax : (021) 840 3992
epc@pt-pp.com

SURAT KETERANGAN KERJA


CERTIFICATE OF EMPLOYEMENT
No. 090/PSPP/EXT/EPC/IX/2022

Dengan in menerangkan bahwa


This Certify that

Nama : ALI M
Name

Tempat & Tanggal Lahir : Mempawah, 16 Februari 1977


Place & Date of Birth

Alamat : Pancur Tower RT 001/010 Duriangkang Sungai Beduk Batam,


Address Kepulauan Riau

Jabatan : Supervisor Electrical


Job Position Electrical Supervisor

Proyek : Portsite Dual Fuel Power Plant 140 MW, Freeport


Project Indonesia - Timika

Masa kerja : 27 September 2021 – 12 September 2022


Period of Service September 27, 2021 - September 12, 2022

Penilaian Umum : Baik / Good Manner


General Performance

Dengan ini perusahaan menyampaikan terima kasih atas jasa dan pengabdiannya
selama bekerja di proyek Portsite Dual Fuel Power Plant 140 MW , semoga
keberhasilan menyertainya dimasa mendatang.
_____________________________________________________________________
We highly appreciate for the good service, he rendered during the term of his working
period, and wish him to get success in the future.

Timika, 12 September 2022

Handoro Dewa Samodra


Construction Manager

You might also like