CB 534 METHODS &EQUIPMENT FOR

CONSTRUCTION (II)

Lecture (1) EARTH MOVING MATERIALS AND OPERATIONS

Dr. El-Badr Osman

1
GRADE DISTRIBUTION
7 , , 30%
12 , , 20%
Class Performance / Attendance 10 %
Final Exam 40 %
Total 100%

2
CONTENTS
(1) INTRODUCTION TO ERTH MOVING
EARTHMOVING PROCESS
EQUIPMENT SLECTION
PRODUCTION OF EARTHMOVING EQUIPENT
PRODUCTION = VOLUMN PER CYCLE* CYCLES PER
Hour
COSTT PER UNIT OF PRODUCTION = (EQUIPMENT
COST
PER HOUR/ EQUIPEMNT PRODUCTION PER
HOUR)
(2) SOIL VOLUMN CHANGE.
SWELL – SHRINKAGE –LOAD AND SHRINKAGE
FACTORS.
(3) SPOIL PILES AND SPOIL BANKS

3
SHOVELS (EXCAVATE LOOSE SOIL ABOVE TRACK LEVEL)

4
HOES (EXCAVATE LOOSE SOIL BELOW TRACK LEVEL)

5
DRAGLINE (EXCAVATE LOOSE SOIL)

6
CLAMSHELLS (EXCAVATE LOOSE SOIL )

7
LOADER (EXCAVAT LOOSE SOIL – MOVE WITH SOIL
LOADING TRUCKS)

8
DOZER (DOZING LOOSE SOIL-RIPPING HARD SOILS)

9
WHEEL TYP DOZER TRACK TYPE DOZER

10
11
SCREPER (EXCAVAT LOOSE SOIL +FILL FOR LONG
DISTANCE)

12
TRUCKS (TRANSPORTING SOIL )

13
14
(2) VOLUMETRIC MEASURE

1 cubic meter (CM) in 1.25 cubic meter 0.90 cubic meter (CM)
natural condition (CM) after digging after compaction
(in-place meter) , (Loose meter) , (compacted meter) ,
BCM LCM CCM

15
1 cubic meter
1.25 cubic meter 0.90 cubic meter
(CM) in natural
(CM) after digging (CM) after
condition
(Loose meter) , compaction
(in-place meter) ,
LCM (compacted meter)
BCM
, CCM

16
1 cubic meter (CM) of
Bank cubic meter
material as it lies in
natural state , BCM

Loose cubic meter 1 (CM) of material after


it has been disturbed by
a loading process, LCM

1 (CM) of material in
the compacted state ,
Compacted cubic meter
also referred to as a net
in-place cubic meter,
CCM
17
18
19
Problem 1:
A soil weighs is 2,000 lb/cu yd (1187 kg/m3) loose and
2,500 1lb/cu yd (1483 kg/ m3) in- place. Find the swell
and load factor for the soil.

answer :

Swell % =( 1) 100 = 24.9 % 25 %

Load factor =( ) = 0.8


.
20
Problem 2:
A project requires that 100,000 BCY (76 460 BCM)
of the soil the swell = 25% and shrinkage =
15%excavated, hauled, and compacted in a fill. How
many loose cubic yards (meters) must be hauled. How
many compacted cubic yards (meters) of fill will the
excavation yield.
answer :
Loose volume (LCM) =Bank volume(BCM) x ( 1 + swe )
Loose volume (LCM) = 76460 x ( 1+ ) = 95575 LCM
volume (CCM) = Bank volume(BCM) x ( 1 shrinkage)
volume (CCM) =76460 x ( 1 0.15) = 64991 CCM

21
Problem 3:

A ditch having a cross-sectional area of 100 sq ft (9.3 m2) is being


excavated in clay. Find the height and width of the spoil bank which
will result. The soil’s angle of repose is 35 and its swell is 40%.

answer :

Volume = cross section x length assume length = 1 meter


Volume = 9.3 x 1 m = 9.3

.
B=( ) = 8.86 m
( )
. ( )
H=( ) = 2.09 m
22
Thank You for your attention