02.01.04.01 BARANDA METALICA GALVANIZADO TUB. Ø 2" y 1"; H=1.0 m. (Segun Diseño) m 36.1
02.01.05 CERCO METALICO
02.01.05.01 CARPINTERIA METALICA
64,949.65
REV 1 PRESUPUESTO
Metrado Precio S/ Parcial S/
278,093.97
245,507.83
8,608.08
ok 94.22 64.3 6,058.35
ok 113.07 22.55 2,549.73
2,932.27
ok 348.25 8.42 2,932.27
15,785.08
ok 361.38 43.68 15,785.08
280.25 107.59 30,152.10
5,890.03
5,890.03
ok 141.18 41.72 5,890.03
212,292.37
92,533.46
ok 105 655.01 68,776.05
ok 3299.64 7.2 23,757.41
119,758.91
ok 77.2 655.01 50,566.77
ok 5073.79 7.2 36,531.29
ok 421.05 77.57 32,660.85
32,586.14
3,618.03
ok 47.32 50.53 2,391.08
ok 54.41 22.55 1,226.95
28,968.11
Es lo que indica en la hoja de metrados 26.25, pero no
coincide con el metrado inicial 26.25 721.21 18,931.76
ok 111.38 48.37 5,387.45
ok 645.68 7.2 4,648.90
51,087.33
51,087.33
10,142.54
En la hoja del metrado indica 203.478 pero en el resumen
han puesto 205.39 205.39 35.61 7,313.94
No figura el metrado de esta partida, sin embargo figura el
metrado de la partida tarrajeo en perapeto 156.97 18.02 2,828.60
5,033.69
El metrado tiene un aumento con respecto al inicial, pero no coincide con la hoja de metrados inicial