PRESENTADO POR EL CONTRATISTA

Item Descripción Und Metrado


01 ESTRUCTURA
01.01 MURO DE CONTENCION
01.01.01 MOVIMIENTO DE TIERRAS
01.01.01.01 EXCAVACIÓN PARA CIMIENTO CORRIDO m3 94.22
01.01.01.02 ELIMINACION DE MATERIAL EXCEDENTE m3 113.07
01.01.02 CORTES
01.01.02.01 CORTE MASIVO EN TERRENO C/MAQUINARIA m3 125.64
01.01.03 RELLENOS
0.01.03.01 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO m3 361.38
0.01.03.02 RELLENO COMPACTADO C/EQUIPO MAT/PRESTAMO AFIRMADO m3
01.01.04 OBRAS DE CONCRETO SIMPLE
01.01.04.01 SOLADOS
01.01.04.01.01 SOLADO DE CONCRETO FC= 100 Kg/cm2 m2 141.18
01.01.05 CONCRETO ARMADO
01.01.05.01 ZAPATAS
01.01.05.01.01 CONCRETO F'C = 210 Kg/cm2 m3 84.71
01.01.05.01.02 ACERO CORRUGADO fy=4200 Kg/cm2 kg 3299.64
01.01.05.02 PANTALLA DE M°C°
01.01.05.02.01 CONCRETO EN PANTALLA DE M°C°FC=210=KG/CM2 m3 75.76
01.01.05.02.02 ACERO CORRUGADO fy=4200 Kg/cm2 kg 5073.79
01.01.05.02.03 ENCOFRADO Y DESENCOFRADO NORMAL EN MURO DE CONTENCIÓN m2 421.05
01.02 SARDINEL DE CONCRETO ARMADO
01.02.01 EXCAVACIONES
01.02.01.01 EXCAVACION DE ZANJAS PARA SARDINELES m3 47.32
01.02.01.02 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. D = 20KM m3 54.41
01.02.02 CONCRETO ARMADO

01.02.02.01 SARDINEL DE CONCRETO DE F'C=175 KG/CM2 (Cem. Tip m3 26.04


01.02.02.02 SARDINEL ENCOFRADO y DESENCOFRADO m2 111.38
01.02.02.03 Sardinel - Acero F'y= 4200 Kg/cm2 kg 645.68
02 ARQUITECTURA
02.01 MURO DE CONTENCION
02.01.01 REVOQUES Y ENLUCIDOS

02.01.02 TARRAJEO DE MUROS DE CONCRETO (1:5 m2 205.39

02.01.03 VESTIDURA DE DERRAMES EN MURO DE CONTENCION (1:5) E=.15 m 156.97


02.01.04 SARDINEL DE CONCRETO ARMADO

02.01.04.01 BARANDA METALICA GALVANIZADO TUB. Ø 2" y 1"; H=1.0 m. (Segun Diseño) m 36.1
02.01.05 CERCO METALICO
02.01.05.01 CARPINTERIA METALICA

02.01.05.01.01 CERCO METALICO DE MALLA N°10 ELECTROSOLDADA m 101.47


02.01.06 CIELORASOS
02.01.06.01 CIELO RASO SUSPENDIDO CON PLANCHA DE FIBROCEMENTO DE 4MM m 259.7
02.01.07 PINTURAS
02.01.07.01 PINTURA ESMALTE EN ALERO m2 311.64
02.01.07.02 PINTURA ANTICORROSIVA EN ESTRUCTURAS METALICAS m2 65.24
02.01.08 JUNTAS
02.01.08.01 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1" m 35.7
COSTO DIRECTO
GASTOS GENERALES (9.10%)
UTILIDAD (6.79%)
SUB TOTAL
IGV (18%)
VALOR REFERENCIAL

* En los metrados están considerando partidas de tarrajeo en sardinel y pintura


* Ordenar los metrados de acuerdo a las partidas presentadas
ESENTADO POR EL CONTRATISTA COSTOS DEL EXP. TEC. REV 1 METRADOS
Precio S/ Parcial S/ Metrado Precio S/Parcial S/ Metrado Precio S/ Parcial S/
269,518.34 253,566.40 256,941.19
233,860.31 221,131.71 221,131.71
8,608.08 8,608.08 8,608.08
64.3 6,058.35 94.22 64.3 6,058.35 94.22 64.3 6,058.35
22.55 2,549.73 113.07 22.55 2,549.73 113.07 22.55 2,549.73
5,518.11 1,057.89 1,057.89
43.92 5,518.11 125.64 8.42 1,057.89 125.64 8.42 1,057.89
15,785.08 7,516.70 7,516.70
43.68 15,785.08 361.38 20.8 7,516.70 361.38 20.8 7,516.70

5,890.03 5,890.03 5,890.03


5,890.03 5,890.03 5,890.03
41.72 5,890.03 141.18 41.72 5,890.03 141.18 41.72 5,890.03
198,059.01 198,059.01 198,059.01
79,243.31 79,243.31 79,243.31
655.01 55,485.90 84.71 655.01 55,485.90 84.71 655.01 55,485.90
7.2 23,757.41 3299.64 7.2 23,757.41 3299.64 7.2 23,757.41
118,815.70 118,815.70 118,815.70
655.01 49,623.56 75.76 655.01 49,623.56 75.76 655.01 49,623.56
7.2 36,531.29 5073.79 7.2 36,531.29 5073.79 7.2 36,531.29
77.57 32,660.85 421.05 77.57 32,660.85 421.05 77.57 32,660.85
35,658.03 32,434.69 35,809.48
3,618.03 3,618.03 3,618.03
50.53 2,391.08 47.32 50.53 2,391.08 47.32 50.53 2,391.08
22.55 1,226.95 54.41 22.55 1,226.95 54.41 22.55 1,226.95
32,040.00 28,816.66 32,191.45

721.21 18,780.31 26.04 721.21 18,780.31 26.25 721.21 18,931.76


77.31 8,610.79 111.38 48.37 5,387.45 111.38 77.31 8,610.79
7.2 4,648.90 645.68 7.2 4,648.90 645.68 7.2 4,648.90
81,614.17 50,071.00 49,876.18
81,614.17 50,071.00 49,876.18
10,142.54 10,142.54 9,100.11

35.61 7,313.94 205.39 35.61 7,313.94 203.48 35.61 7,245.85

18.02 2,828.60 156.97 18.02 2,828.60 102.9 18.02 1,854.26


4,795.89 4,795.89 6,681.03

132.85 4,795.89 36.1 132.85 4,795.89 50.29 132.85 6,681.03


22,823.65 22,823.65 22,823.65
22,823.65 22,823.65 22,823.65

224.93 22,823.65 101.47 224.93 22,823.65 101.47 224.93 22,823.65


31,543.16 0.00 0.00
121.46 31,543.16 0 0 0.00 0 0 0.00
11,933.37 11,933.37 10,895.83
24.04 7,491.83 311.64 24.04 7,491.83 311.64 24.04 7,491.83
68.08 4,441.54 65.24 68.08 4,441.54 50 68.08 3,404.00
375.56 375.56 375.56
10.52 375.56 35.7 10.52 375.56 35.7 10.52 375.56
351,132.51 303,637.40 306,817.36
31,953.06 27,631.00 27,920.38
23,841.90 20,616.98 20,832.90
406,927.47 351,885.38 355,570.64
73,246.94 63,339.37 64,002.72
480,174.41 415,224.75 419,573.36

64,949.65
REV 1 PRESUPUESTO
Metrado Precio S/ Parcial S/
278,093.97
245,507.83
8,608.08
ok 94.22 64.3 6,058.35
ok 113.07 22.55 2,549.73
2,932.27
ok 348.25 8.42 2,932.27
15,785.08
ok 361.38 43.68 15,785.08
280.25 107.59 30,152.10
5,890.03
5,890.03
ok 141.18 41.72 5,890.03
212,292.37
92,533.46
ok 105 655.01 68,776.05
ok 3299.64 7.2 23,757.41
119,758.91
ok 77.2 655.01 50,566.77
ok 5073.79 7.2 36,531.29
ok 421.05 77.57 32,660.85
32,586.14
3,618.03
ok 47.32 50.53 2,391.08
ok 54.41 22.55 1,226.95
28,968.11
Es lo que indica en la hoja de metrados 26.25, pero no
coincide con el metrado inicial 26.25 721.21 18,931.76
ok 111.38 48.37 5,387.45
ok 645.68 7.2 4,648.90
51,087.33
51,087.33
10,142.54
En la hoja del metrado indica 203.478 pero en el resumen
han puesto 205.39 205.39 35.61 7,313.94
No figura el metrado de esta partida, sin embargo figura el
metrado de la partida tarrajeo en perapeto 156.97 18.02 2,828.60
5,033.69

No coincide con el metrado inicial, en el metrado nuevo


indica en la hoja de metrados 50.29, asi mismo ordenar el
metrado porque está todo confuso 37.89 132.85 5,033.69
23,673.88
23,673.88
No indica los tramos que sumo en el metrado para que salga
101.47, en el resumen del metrado considera 105.25 105.25 224.93 23,673.88
0.00
0 0 0.00
11,865.97
311.64 24.04 7,491.83
En la hoja de metrado indica 50 m2 es menor al metrado
inicial 64.25 68.08 4,374.14
371.25
ok 35.29 10.52 371.25
329,181.29
29,955.50
22,351.41
381,488.20
68,667.88
450,156.08
Actualizó el precio pero aumento el metrado, se reviso la hoja de metrados e indica 125.64 . Sustentar el metrado de 348.

Agrego está partida pero no están sus metrados, no indica el sustento

Aumento el metrado pero no coincide con la hoja de metrados presentado

Aumento el metrado pero no coincide con la hoja de metrados presentado

Aumento el metrado con respecto al metrado inicial

Aumento el metrado pero no coincide con la hoja de metrados presentado

Aumento el metrado pero no coincide con la hoja de metrados presentado

El metrado tiene un aumento con respecto al inicial, pero no coincide con la hoja de metrados inicial

Aumento el metrado pero no coincide con la hoja de metrados presentado


Coincide con el metrado inicial, pero no con la hoja de metrados presentada

Bajo el metrado pero no coincide con la hoja de metrados presentada


ustentar el metrado de 348.25