Informe Semanal s13 Rev
Informe Semanal s13 Rev
FIMAR
CLIENTE
RESIDENTE
PIERO ORLANDO SÁNCHEZ PACORA
Sistema de
Contratación : SUMA ALZADA
Fecha de entrega
de terreno : 31 DE OCTUBRE DEL 2022
CURVA "S"
SEMANA 13
Cliente: FIMAR SA Obra: NUEVA SALA DE TRENZADO FIMAR
PROGRAMADO EJECUTADO
AVANCE
N° AVANCE PROGRAMADO SUB TOTAL AVANCE SUB TOTAL
FECHA SUB TOTAL ACUMULADO SUB TOTAL SITUACIÓN
SEMANA PROGRAMADO ACUMULADO ACUMULADO* EJECUTADO ACUMULADO
EJECUTADO
1y 2 14/11/22 5.74% 5.74% S/ 195,041.96 S/ 195,041.96 5.74% 5.74% S/ 249,138.89 S/ 249,138.89 ADELANTADO EN 0.00%
3y 4 2/12/22 7.86% 13.59% S/ 267,147.37 S/ 462,189.33 7.86% 13.59% S/ 145,887.09 S/ 395,025.98 ADELANTADO EN 0.00%
5y 6 15/12/22 7.33% 20.92% S/ 249,138.89 S/ 711,328.22 7.33% 20.92% S/ 217,047.18 S/ 612,073.16 ADELANTADO EN 0.00%
7 17/12/22 4.29% 25.21% S/ 145,887.09 S/ 857,215.31 4.38% 25.30% S/ 148,846.96 S/ 760,920.12 ADELANTADO EN 0.09%
8 24/12/22 6.38% 31.59% S/ 217,047.18 S/ 1,074,262.49 5.86% 31.16% S/ 199,407.44 S/ 960,327.56 ATRASADO EN 0.43%
9 31/12/22 13.51% 45.10% S/ 459,460.83 S/ 1,533,723.32 6.63% 37.79% S/ 225,532.03 S/ 1,185,859.59 ATRASADO EN 7.31%
10 7/01/23 14.68% 59.78% S/ 499,036.69 S/ 2,032,760.02 14.5% 52.29% S/ 492,995.00 S/ 1,678,854.59 ATRASADO EN 7.49%
11 14/01/23 9.50% 69.28% S/ 323,052.29 S/ 2,355,812.30 6.97% 59.27% S/ 237,153.39 S/ 1,916,007.98 ATRASADO EN 10.01%
12 21/01/23 11.86% 81.14% S/ 403,262.64 S/ 2,759,074.94 9.73% 69.00% S/ 331,031.56 S/ 2,247,039.54 ATRASADO EN 12.14%
13 28/01/23 9.19% 90.33% S/ 312,379.80 S/ 3,071,454.74 6.77% 75.77% S/ 230,197.81 S/ 2,477,237.35 ATRASADO EN 14.56%
14 4/02/23 4.09% 94.42% S/ 139,159.93 S/ 3,210,614.67
15 11/02/23 5.58% 100.00% S/ 189,812.29 S/ 3,400,426.96
L Y L CONTRATISTAS GENERALES
AV. CANAVAL Y MOREYRA Nº654 – 5to PISO – SAN ISIDRO - LIMA
CUMPLIDAS NO CUMPLIDAS
13 3
% DE CUMPLIMIENTO
81%
L Y L CONTRATISTAS GENERALES
AV. CANAVAL Y MOREYRA Nº654 – 5to PISO – SAN ISIDRO - LIMA
VACEADO DE CONCRETO EN LOSA MACIZA Coordinación de horarios con FIMAR para evitar cruces con fechas importandes. RESIDENTE - PIERO LYL/FIMAR X
VACEADO DE CONCRETO EN LOSA MACIZA Disponibilidad de la pluma para las fechas propuestas de vaceado RESIDENTE - PIERO LYL X
VACEADO DE CONCRETO EN LOSA MACIZA Libre acceso desde la entrada de FIMAR a la obra para el ingreso del mixer y pluma RESIDENTE - PIERO LYL/FIMAR X
HABILITACIÓN DE TUBOS PARA ARRIOSTRES Coordinación previa con proveedores para tener todo el material necesario en obra RESIDENTE - PIERO LYL X
ENCOFRADO DE LOSA MACIZA Correcto armado de andamios SSOMA - RONALD LYL X
SEMANA 14
L M M J V S D
Descripción Duración Comienzo Fin 30/01 31/01 1/02 2/02 3/02 4/02 5/02
SARDINELES
VACEADO DE SARDINEL 1° PISO 16 19/01/2023 3/02/2023 S4P1 S4P1 S5P1 S5P1 S5P1
VACEADO DE SARDINEL 2° PISO 13 26/01/2023 7/02/2023 S2P2 S2P2 S3P2 S3P2 S4P2 S4P2 S5P2
VACEADO DE SARDINEL 3° PISO 12 31/01/2023 11/02/2023 S1P3 S1P3 S1P3 S2P3 S2P3 S3P3
OBRAS METÁLICAS
ARRIOSTRES EN ELEVACIÓN
1° PISO CORTE Y PINTURA TUBO 10" X 10" X 10 A 53 23 28/12/2022 19/01/2023
1° PISO INSTALACIÓN DE TUBOS 16 18/01/2023 2/02/2023 S4P1 S5P1 S5P1 S5P1
2° PISO CORTE Y PINTURA TUBO 10" X 10" X 6 A 53 19 16/01/2023 3/02/2023 S4P2 S4P2 S5P2 S5P2 S5P2
2° PISO INSTALACIÓN DE TUBOS 11 27/01/2023 6/02/2023 S2P2 S2P2 S3P2 S3P2 S4P2 S4P2 S5P2
NAVE INDUSTRIAL
ARMADO DE PORTICOS 21 19/01/2023 8/02/2023 S3P3 S3P3 S4P3 S4P3 S4P3 S4P3 S4P3
AMARRE LATERAL 15 29/01/2023 12/02/2023 S1P3 S1P3 S2P3
CUBIERTA - TECHO 5 9/02/2023 13/02/2023
CERRAMIENTO LATERAL
CERRAMIENTO 1° PISO 10 29/01/2023 7/02/2023 S1P1 S2P1 S2P1 S3P1 S3P1 S4P1 S4P1
CERRAMIENTO 2° PISO 10 3/02/2023 12/02/2023 S1P2 S1P2 S2P2
CERRAMIENTO 3° PISO 10 8/02/2023 17/02/2023
ESCALERAS
ESCALERA 1 14 26/01/2023 8/02/2023 S1P1 S1P1 S1P1 S1P2 S1P2 S1P2 S1P2
ESCALERA 2 14 5/02/2023 18/02/2023 S4P1
L Y L CONTRATISTAS GENERALES
AV. CANAVAL Y MOREYRA Nº654 – 5to PISO – SAN ISIDRO - LIMA
SEGUIMIENTO DE RFI
Fecha 07.01.2023
Dias programados Fecha requerida Respuesta o Fecha Dentro del
Código Responsable Especialidad Fecha emisión Status OBSERVACIONES
de respuesta de respuesta comentarios respuesta plazo
RFI 01 PIERO/JOSE LUIS Estructuras 10/11/2022 5 15/11/2022 RESPONDIDO 22/11/2022 No
RFI 02 PIERO/JOSE LUIS Estructuras 10/11/2022 5 15/11/2022 RESPONDIDO 22/11/2022 No
RFI 03 JOSE LUIS Estructuras 10/11/2022 4 14/11/2022 RESPONDIDO 13/11/2022 Si
RFI 04 PIERO/JOSE LUIS Estructuras 10/11/2022 5 15/11/2022 RESPONDIDO 22/11/2022 No
RFI 05 PIERO/JOSE LUIS Estructuras 10/11/2022 5 15/11/2022 RESPONDIDO 22/11/2022 No
RFI 06 PIERO/JOSE LUIS Estructuras 13/11/2022 5 18/11/2022 RESPONDIDO 22/11/2022 No
RFI 07 PIERO/JOSE LUIS Estructuras 13/11/2022 5 18/11/2022 RESPONDIDO 22/11/2022 No
RFI 08 PIERO/JOSE LUIS Estructuras 13/11/2022 5 18/11/2022 RESPONDIDO 22/11/2022 No
RFI 09 PIERO/JOSE LUIS Estructuras 21/11/2022 5 26/11/2022 RESPONDIDO 22/11/2022 Si
RFI 10 PIERO/JOSE LUIS Estructuras 13/12/2022 3 16/12/2022 PENDIENTE
96 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038291 210 7.5 6 08:00 am 08:26 am 6
97 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038298 210 7.5 6 08:42 am 08:56 am 7 1
98 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038303 210 7.5 6 09: 15 am 09: 27 am 6
99 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038307 210 7.5 6 09: 42 am 09: 50 am 8 1
100 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038311 210 7.5 6 10: 05 am 10:13 am 6
101 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038315 210 7.5 6 10: 23 am 10:40 am 5 2
102 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038320 210 7.5 6 10: 54 am 11: 17 am 6
103 LOSA MACISA Y VIGAS 25/01/2023 LOTTY EJES: 8-10 T 258-0038322 210 7.5 6 11:22 am 11: 35 am 7 2
104 SARDINEL 25/01/2023 LOTTY EJES: 7-6 /D - 210 0.3 - 5:00 pm 5:30 pm
105 SARDINEL 26/01/2023 LOTTY EJES: 1-2/A - 210 0.3 - 4:00 pm 5:30 pm
106 SARDINEL 27/01/2023 LOTTY EJES: 1-2/D - 210 0.3 - 2:30 pm 4:00 pm
107 PARCHADO DE LOSA 28/01/2023 LOTTY EJES: 3-4/A - 210 0.9 - 3:00 pm 5:00 pm
L Y L CONTRATISTAS GENERALES
AV. CANAVAL Y MOREYRA Nº654 – 5to PISO – SAN ISIDRO - LIMA
f'c ROTURA
FECHA DE FECHA DE f'c ROTURA f'c ROTURA f'c ROTURA PORCENTAJE STATUS DE
ITEM SECTOR/NIVEL CÓDIGO PROBETAS ELEMENTO A VACEAR EDAD Promedio Nro. CERTIFICADO
MOLDEO ROTURA P-1 (kg/cm²) P-2 (kg/cm²) P-3 (kg/cm²) (%) RESULTADO
(kg/cm²)
1 ZAPATAS Z1-A,B,C ZAPATA 12/11/22 9 DIAS 21/11/22 204 201 227 212.0 100 22-2729 CONFORME
2 ZAPATAS Z1-A,B,C ZAPATA 12/11/22 16 DIAS 28/11/22 290 245 240 262.5 125 22-2790-1 CONFORME
3 ZAPATAS Z2-A,B,C ZAPATA 21/11/22 7 DIAS 28/11/22 215 200 ------ 207.5 99 22-2790-1 CONFORME
4 ZAPATAS Z2-A,B,C ZAPATA 21/11/22 14 DIAS 5/12/22 233 237 ------ 235.0 110 22-2876-1 CONFORME
5 ZAPATAS Z2-A,B,C ZAPATA 21/11/22 28 DIAS 19/12/22 268 262 273 267.7 127.5 223899 CONFORME
6 COLUMNA C: EJES B-C COLUMNA 22/11/22 7 DIAS 29/11/22 207 264 ------ 235.5 96 22-2790-2 CONFORME
7 COLUMNA C: EJES B-C COLUMNA 22/11/22 14 DIAS 06/12/22 243 277 ------ 260.0 121 22-2876-2 CONFORME
8 COLUMNA C: EJES B-C COLUMNA 22/11/22 28 DIAS 20/12/22 358 348 353 353.0 144 223954 CONFORME
9 COLUMNA EJES: C6 - C7 COLUMNA 26/11/22 9 DIAS 05/12/22 290 292 ------ 291.0 119 22-2857 CONFORME
10 VIGA EJES: 1-2-3 VIGA 01/12/22 4 DIAS 05/12/22 331 291 ------ 311.0 148 22-2876-1 CONFORME
11 VIGA EJES: 4-5-6 VIGA 05/12/22 7 DIAS 12/12/22 245 253 ------ 249.0 119 22-2891 CONFORME
12 VIGA EJES: 7-8 VIGA 12/12/22 3 DIAS 15/12/22 254 282 239 258.3 123 22-2959 CONFORME
13 ZAPATAS EJES: 9-10 ZAPATA 15/12/22 7 DIAS 23/12/22 190 ------ ------ 190.0 91 22-3042 CONFORME
14 LOSA MACISA EJES: 1-2 LOSA MACISA 17/12/22 6 DIAS 23/12/22 258 245 ------ 251.5 120 22-3042 CONFORME
15 LOSA COLABORANTE EJES: 3-4-5 LOSA COLABORANTE 17/12/22 6 DIAS 23/12/22 253 246 ------ 249.5 120 22-3042 CONFORME
16 LOSA EJES: 5-8 LOSA COLABORANTE 23/12/22 7 DIAS 30/12/22 238 247 242 242.3 98.9 225590 CONFORME
LOSA EJES: 5-8 LOSA COLABORANTE 23/12/22 28 DIAS 20/1/23 298 300 303 300.3 123 225590 CONFORME
17 VIGA EJES: 4-5 VIGA 31/12/22 7 DIAS 07/01/23 241.1 252.6 243.2 245.6 117 225977 CONFORME
18 VIGA EJES: 6-7 VIGA 03/01/23 7 DIAS 10/01/23 205.7 211.3 199.5 205.5 97.9 226073 CONFORME
19 LOSA MACIZA EJES:1-3 LOSA MACIZA 04/01/23 7 DIAS 10/01/23 182 206 ------ 194.0 80 23-0079 CONFORME
20 LOSA COLABORANTE EJES 3-5 LOSA COLABORANTE 05/01/23 3 DIAS 08/01/23 309 328 317 318.0 151 225981 CONFORME
21 VIGA EJES 7 VIGA 05/01/23 3 DIAS 08/01/23 327 343 338 336.0 137 226177 CONFORME
22 LOSA COLABORANTE EJES 5-9 LOSA COLABORANTE 10/01/23 3 DIAS 12/01/23 217 178 ------ 197.5 94 23-0115 CONFORME
23 VIGA EJE 9 VIGA 16/01/23 3 DIAS 19/01/23 349 355 341 348.3 142 226580 CONFORME
24 LOSA MACIZA EJES: 9-10 LOSA MACIZA 19/01/23 4 DIAS 23/01/23 253 ------ ------ 253.0 120 BORRADOR CONFORME
25 LOSA COLABORANTE EJES: 8-9 LOSA COLABORANTE 19/01/23 4 DIAS 23/01/23 310 ------ ------ 310.0 148 BORRADOR CONFORME
26 VIGA LOSA COLABORANTE EJES: 10 VIGA 19/01/23 4 DIAS 23/01/23 280 ------ ------ 280.0 134 BORRADOR CONFORME
27 COLUMNA EJES: 9-10 COLUMNA 20/01/23 10 DIAS 30/01/23
28 LOSA MACIZA EJES: 8-10 LOSA MACIZA 25/01/23 5 DIAS 30/01/23
29 VIGA EJES:10 VIGA 25/01/23 5 DIAS 30/01/23
3 ESTRUCTURA DEMOLICION
ZAPATAS DE ZAPATA SIN AUTORIZACION DEAbel
SUPERVISION
Aquino 13/12/22 16/12/22 19/12/22 en proceso en proceso NO EN PROCESO DE
0 ABSOLUCION
PRODUCTO TERMINADO EN PROCESO DE
4 ESTRUCTURA COLUMNAS Abel Aquino 22/12/22 26/12/22 27/12/22 en proceso en proceso NO
NO CONFORME 0 ABSOLUCION
PRODUCTO TERMINADO EN PROCESO DE
5 ESTRUCTURA COLUMNAS Abel Aquino 24/12/22 28/12/22 30/12/22 en proceso en proceso NO
NO CONFORME 0 ABSOLUCION
PRODUCTO TERMINADO EN PROCESO DE
6 ESTRUCTURA LOSAS Abel Aquino 26/12/22 30/12/22 02/01/22 en proceso en proceso NO
NO CONFORME 7 ABSOLUCION
PRODUCTO TERMINADO EN PROCESO DE
7 ESTRUCTURA LOSAS Tatiana 05/01/22 05/01/22 07/01/22 en proceso en proceso NO
NO CONFORME 2 ABSOLUCION
FALTO COLOCAR EL
8 ESTRUCTURA EJE A/8-9 NUMERO DE PASES Lotty Vega 25/01/23 28/01/23 30/01/23 en proceso en proceso SI EN PROCESO DE
INIDCADOS EN EL BAÑO 4 ABSOLUCION
PRODUCTO TERMINADO EN PROCESO DE
9 ESTRUCTURA LOSA Lotty Vega 25/01/23 28/01/23 30/01/23 en proceso en proceso SI
NO CONFORME 4 ABSOLUCION
L Y L CONTRATISTAS GENERALES
AV. CANAVAL Y MOREYRA Nº654 – 5to PISO – SAN ISIDRO - LIMA
RECEPCIÓN DE PROCURAS
FECHA FECHA DE
SEMANA DESCRIPCIÓN STATUS PROVEEDOR OBSERVACIONES
REQUERIDA RECEPCIÓN
10 Escalera de acceso al 2do nivel O/C Andamio Acrow 2/1/2023 2/1/2023
10 Volquete eliminacion O/C 2/1/2023 2/1/2023
10 Encofrado O/C 2/1/2023 2/1/2023
10 Concreto para vigas ejes 6 O/C Concremax 3/1/2023 3/1/2023
10 Tubos Metalicos para arriostres laterales O/C Tradisa 3/1/2023 5/1/2023
10 Concreto para techo 2° piso eje 1-3 O/C Concremax 4/1/2023 4/1/2023
10 Concreto para viga eje 7 O/C Concremax 4/1/2023 4/1/2023
10 Concreto para techo eje 3-5 O/C Concremax 5/1/2023 5/1/2023
10 Concreto para viga eje 8 O/C Concremax 5/1/2023 5/1/2023
11 Concreto para techo 2° piso eje 5-8 O/C Concremax 10/1/2023 10/1/2023
11 Perfiles para Nave Industrial columnas O/C Aceros Arequipa 10/1/2023 10/1/2023
11 Perfiles para Nave Industrial tubos O/C Aceros Arequipa 10/1/2023 12/1/2023
11 Concreto para zapatas O/C Concremax 12/1/2023 13/1/2023
11 Concreto para columnas O/C Concremax 13/1/2023 14/1/2023
12 Concreto para vigas O/C Concremax 16/1/2023 16/1/2023
12 Concreto para techo O/C Concremax 19/1/2023 19/1/2023
12 Concreto para columnas O/C Concremax 20/1/2023 20/1/2023
12 Placa colaborante O/C Aceros Deck 16/1/2023 16/1/2023
12 Fierro corrugado para piso terminado y resto de obra O/C Aceros Arequipa 23/1/2023 23/1/2023
12 Planchas para primer y segundo piso O/C Aceros Arequipa 16/1/2023 16/1/2023
13 Tubos Metalicos para escalera (columna) O/C Aceros Arequipa 24/1/2023 26/1/2023
13 Ángulos de cerramiento lateral O/C Aceros Arequipa 24/1/2023 26/1/2023
13 Pernos epoxicos para segundo nivel O/C HILTI 23/1/2023 24/1/2023
13 Cobertura lateral O/C ALUZIC 28/1/2023 26/1/2023
13 Cobertura liviana En Licitación ALUZIC 4/2/2023
13 Concreto para techo de segundo piso O/C Concremax 25/1/2023 25/1/2023
14 Tubos Metalicos para escalera (vigas) O/C Aceros Arequipa 31/1/2023
14 Tubos Metalicos para escalera 2 (columnas) O/C Aceros Arequipa 3/2/2023
14 Elementos para cerramiento lateral del 3° piso En Licitación TRADISA 4/2/2023
10.0 CONCLUSIONES
La curva “S” refleja un atraso de 14.56%, el control de calidad ha sido constante, se tiene topografía perenne en obra.