Project Implementation Manual Component A
Project Implementation Manual Component A
March 2008
1
ABBREVIATIONS AND ACRONYMS
4
Table of Contents
Appendices
ANNEX: 1
Guidelines for Identification, Sub-Project Prioritization, Feasibility Study, Social and
Environmental Management Plan, Appraisal, Detail Design And Approval For
Implementation of The Sub Project
ANNEX: 2
Memorandum of Agreement
ANNEX: 3
Terms of Reference for NGOs
ANNEX: 4
Implementation Timeframe
ANNEX: 5
Results Framework and Monitoring
5
1 PROJECT OBJECTIVES
2 PROJECT COMPONENTS
Though there are four different components of IWRMP, this manual deals
with component A only. The scope and activities of component A are:
6
the following issues: (a) structural and operational weaknesses in the
traditional FMIS, with consequent low water efficiency and low agricultural
productivity; and (b) low exploitation of the excellent groundwater potential
of the Terai and lack of an appropriate plan for systematic development of
groundwater irrigation.
The output of this component will be better irrigation services from existing
and /or new schemes in the Western regions, both in the Hills and Terai,
which are or will be managed by farmers (FMIS). It involves four sub-
components (i) physical rehabilitation and modernization of small and
medium FMIS in the mountains, hills and Terai; (ii) Capacity Building of
WUAs and DOI as appropriate; (iii) development and improvement of sixty
DTW groundwater schemes; (iv) supporting, through electrification, ten
groundwater irrigation schemes; and (v) preparation of a groundwater
irrigation development plan. Under component A, support will be provided
for improved irrigation water delivery on about 26,392 ha through
rehabilitation and improvement of 168 FMIS spread over forty districts Of
this 50 are to be taken up in the first year.
With regard to groundwater, the project will directly support DTW ground
water schemes covering an estimated area of 2,100 ha. It will also support
indirectly, to ten groundwater irrigation schemes with a total command area
of 3000 ha through electrification (provisioning of electricity distribution
lines from the nearest grid) over the life of this project.
The following selection criteria and project preparation guidelines are used
for surface irrigation schemes
Selection Criteria
(a) Poverty pocket areas: According to the Nepal Poverty Map developed
by WFP, CBS and WB, high concentrations are found in Terai due to a
much higher population density, Poverty line is established by CBS in 2003
that represents the level of per capita expenditure required to meet basic
needs. In case of Nepal the Poverty line is Rs. 7,696 per person per year at
2003 commodities price index level. The direct calorie intake method
provides an alternative measurement of poverty and is based on the number
of people that consume less than an established minimum calorie
requirement. For Nepal, this requirement is set at 2144 kilocalorie per person
per day (CBS, 2005)
7
Maps for both measurement of poverty were prepared at subdistrict
(ILAKA) level. A cluster of poorest Ilaka can be observed in the Hills and
Terai of the Far and Mid Western Development Regions.
(b) Water availability to meet the crop water requirement in the potential
area.
A rapid appraisal of 50 surface schemes and 3 DTW proposed for the first
year was done through field offices located in different parts of the project
area including some remote areas. The prioritization of selected project can
be done based on the form 4 in annex-1. The IDD/IDSD would prioritize for
feasibility study of each sub-project according to the main components
influencing the potential development with support of DADO.
The project design has also considered the nature and extent of arsenic
contamination in groundwater in Terai and the actions proposed in the study
“Arsenic Testing and Finalization of Groundwater Legislation” conducted
by the DoI with the Bank’s support in 2003-04. Actions proposed in the
study such as detailed monitoring, the design of an arsenic management
framework in the Terai and related institutional and legal modifications have
been incorporated. The selection of groundwater sub-projects has been made
by avoiding districts affected by arsenic contamination.
The irrigation schemes in hills and mountains are liable to face severe
damages due to natural calamity or fragile geological environment, which
needs assistances from the government for its revival and to bring it in an
operational condition. Likewise, in Terai also the schemes are frequently
10
damaged due to floods. During such natural disasters, the repair works
certified by the concerned IDD/IDSD/GFO beyond the capacity of WUAs
will be supported by DoI to maintain irrigation systems in participation of
users as per irrigation policy.
At the regional level, a Regional Project Support Unit (RPSU) will be placed
in each Regional Irrigation Directorates (RID) of DOI, with assigned staff
from RID and Regional Agriculture Directorate (RAD). The director of RID
will head the RPSU as project manager for the concerned region. It would
have the SDE from RID, the subject matter specialists (SMS) from RAD,
sociologist and geologist as members and the representative from
implementation consultants as adviser. The Groundwater Field Offices
would also work under the guidance and supervisions of the RID and
maintain close link with GWRDP. The RPSU will review in detail the
subproject appraisal documents submitted by IDD/IDSD/GFO, verify if
11
necessary at field level and would recommend to the RAC (Regional
Appraisal Committee) the approval of the sub-project implementation.
Detailed cost estimates would be approved by the authorized officer. The
RPSU will be responsible ensuring the technical and economic viability of
the sub-projects.
13
ORGANIZATION STRUCTURE AND RESPONSIBILITIES
14
Figure 1: Implementation Set up for Component A-IWRMP
Programme
Coordinator
Technical Project Director (WECS)
Assistance (DoI)
Programme
Coordinator
(DoA)
Process and formats required for different stages of project preparation such
as the Project Identification, Prioritization, Feasibility study and Detail
Engineering Phase of surface and groundwater sub projects and Appraisal is
given in Annex -1.
15
4. OPERATION MANUAL FOR COMPONENT A
16
ad-hoc WUA committee and then collectively complete an application form.
The application is to be signed by all beneficiaries households before
submission through the nearest ASC/ASSC to the IDD/IDSD, along with an
upfront cash deposit of NRs 50 per ha for surface irrigation.
Step 7: Feasibility Study: The RID & OPD would undertake the
feasibility study. If the sub-project is large or potentially challenging a local
consultant could be deployed. The mobile irrigation team (MIT) and RAD
staff would extend technical support to the study team as required. The
WUA or beneficiary group would be closely involved in the fieldwork and
discuss the scope of works and preliminary cost estimates. To ensure
uniformity in the feasibility study and its report presentation, the approach
detailed in the procedural guidelines would be strictly followed. The report
would include screening of alternatives as well as describing the optimum
17
solution; realistic construction cost and benefits estimation for performing an
economic analysis and environmental assessment of the sub-projects. SEMP
would be carried out according to the guidelines on environmental
considerations in the detailed Procedural Guidelines.
Step 10: Approval and Tender Document Preparation: All the sub-projects
in IWRMP will need appraisal and recommendations from SAC and RAC,
and then only it will be approved for implementation by PICC through the
OPD review. In the case of approval of the cost estimate the financial rules
and regulations will prevail.
At this stage the WUA would be required to deposit balance of upfront cash
to make up 0.5% of the investment cost, otherwise no further works would
be undertaken by DOI.
Step 13: Construction: Tenders would be floated for the SMU parts, and
contract awarded as per Govt. of Nepal financial rules keeping transparency
with the WUA. A construction committee would be formed by the WUA to
supervise and monitor the quality of works being carried out both by SMU
contract as well as by WUA according to the work breakdown agreement.
Training would be conducted by IDD/ RID staff or NGO (if engaged) for
construction committee members on quality control and supervision of
works. WUA would be encouraged to take part in the final measurement of
contract works. WUA part of works would also be recorded and evaluated
19
by SMU. If during construction, variation in the scope of works demands a
cost overrun of more than 10% from the original estimate, then the works
would be suspended until the WUA contributes in cash or labor, on a pro-
rata basis, their share of the cost over-run. MIT would check on construction
progress and quality of works.
Contract Commissioning: Any piece of contract, when completed should be
commissioned by IDD/ IDSD technical staff in association with WUA and
contractor within the liability period of contractor. Contractors would rectify
the defects noticed duly.
Step 15: Operation and Maintenance: After completion, the WUA would
receive back the O.5% upfront cash deposit from SMU as potential seed
money for future O&M of the system. Thereafter, the DADO/ASC/NGO,
the WUA and farmers would strengthen their linkages with other support
agencies. SMU/RID or NGO would carry out O&M and water management
trainings to WUA members as needed. NGO would provide to the WUA
continuing advice to ensure future sustainable agriculture practices. RID
would make provision for budgetary support to completed Sub-Projects in
case of natural unforeseen disasters for the stabilization period, whereas
WUA will be responsible for carrying out regular operation and maintenance
and resource collection in terms of ISF to meet the O&M expenditure.
Step 16: Result Framework and Monitoring: The Result framework and
monitoring of component A (Surface) defining project development Object
(PDO), Outcome indicators, Baseline survey, Target values, Data collection
and reporting and use of intermediate Outcome Monitoring to verify the
timely and satisfactory completion of component A. The responsibility for
data collection and reporting will be done by IDD/IDSD and WUA.
Monitoring and Evaluation system shall comply participatory methods
leading to participatory monitoring and evaluation.
20
Figure A.1: Procedural Guidelines Steps for Sub-project Implementation
of Surface water Schemes
Feasibility Study
Step-7
Legalization of WUA
21
Step-13 Construction
Step-14 Commissioning
22
b) Based on the available data on arsenic testing in groundwater
(Report on 'Sate of Arsenic in Nepal, 2003' and other recent data),
Village Development Committees (VDCs), where shallow aquifers
are free from arsenic contamination problem (i.e. arsenic content
level below 50 ppb limit – the interim national standard for
drinking water in Nepal), have been identified as the potential
areas for groundwater sub-project development, both STW and
DTW schemes.
c) Because of the low capital and operating costs, the project has
emphasized on developing STW sub-projects (clusters), where the
tube wells will be operated by electric motor operated pumping
sets. Therefore, priority will be given to those VDCs, where
electricity supply system already has a full coverage, followed by
those VDCs where this facility is available in parts of the VDC
area.
24
Step 3 APPLICATION: Farmers hold discussions among themselves,
assisted by NGOs, and organize into groups (for each
DTW/STW cluster) and form an ad- hoc WUA Committee for
each cluster (i.e. sub-project). The WUA together with the GFO
will delineate the cluster area, whose sizes will be 300 ha each.
The size of the area may be compromised if there are genuine
constraints from physical, technical and social aspects. The
WUA prepares its program, completes the APPLICATION
FORM and submit it along with the up-front cash deposit to the
GFO. The first installment of (Rs.200 per hectare) up-front cash
will be 0.5% of the total cost of the DTW/STW system. The
sub-project will provide 11 KV Rural Electrification and Access
Road Improvement in 3000 ha STW cluster area at project cost
whereas WUA will drill STW, install 4 inch casing pipe along
with, filter, pump, motor and 440 volt LT line from II KW HT
line at their own cost. The GFO assists the sub-project area
farmers in this process. The GFO receives the APPLICATION
FORM along with the up-front cash, and screens all the forms
thus received to verify that they meet the requirements of
selection criteria for identification study. The GFO, with
assistance of the DADO, selects the clusters for sub-project
identification studies, and informs SAC/DDC of the selection
list.
Step 4 SUBPROJECT IDENTIFICATION: The GFO, the DADO/ASC and
Sub-project staff visit the cluster sites, collect the relevant data
and prepare IDENTIFICATION REPORT for each cluster. The
GFO discusses the Identification Reports in the Sub-project
Appraisal Committee (SAC), and prioritizes the clusters for
further studies. The MIT provides assistance, if necessary. The
respective WUA ad-hoc committee liaises with the sub-project
identification team and discusses the project proposals during
this stage. NGOs/CBOs will facilitate the GFO and farmers in
the identification activities.
Step 5 FEASIBILITY STUDY: The GFO/RID prepares Feasibility Study
programs for the prioritized clusters, and conducts detailed
feasibility study after obtaining approval from the RID. This
may be conducted by the GFO itself or may use the service of
the local consultant. The WUA Ad-hoc committee members and
25
the farmers are actively involved with the feasibility study team
in collecting data, conducting surveys, and in designing and
estimating the cost of the sub-project. All the pre-existing
irrigation and drinking water ground water schemes will be
tested for arsenic content in their groundwater and will be an
integral part of the feasibility report. The feasibility report will
contain a detailed project design, including the design and cost
for electricity supply network in the ground water development
sub-project area. The feasibility study will be supported by
lithologic investigation by investigative slim hole in the sub-
project area. In case of the DTW sub-projects, this investigation
should indicate good potential of deep aquifers, but not the
shallow aquifers. IEE/EIA assessment would be carried out
according to the prevailing guidelines mentioned as per
integrated social environmental management framework
(ISEMF). The MIT and RAD staff will provide technical
support and assistance to the feasibility study team of the GFO
or the consultant. Prepares the Integrated Social Environmental
Management Plan in consultation with the ad-hoc WUAs and
NGOs to find the social and environment dimensions of the sub-
project areas defining marginal, subsistence farmers,
disadvantaged groups, gender issues and environment problems.
Step 6 APPRAISAL: SAC appraises the Feasibility Study Reports and
recommends to the RAC for approval. The MIT/RID team
appraises the feasibility report by checking the detailed designs,
drawings, and cost estimates, supported by site verification. The
WUA and the farmers assist the field survey team and confirm
the proposed project design, and the project sites. If found
necessary, the MIT/RID may suggest for additional surveys and
for upgrading the feasibility study report. The TA team
undertakes technical review of the sub-project feasibility report
and endorses it. With the endorsement of the TA Team and the
recommendation of the MIT/RID, the SAC submits the sub-
project report to the RAC. The appraisal document from RAC
shall be sent to GWRDP for review before approval by PICC
through OPD.
Step 7 INTENSIVE INFORMATION DISSEMINATION, FARMERS'
MOBILIZATION & ORGANIZATION: Once the sub-project is
approved by the PICC, the GFO mobilizes the NGO for
26
intensive information dissemination to the beneficiary farmers
in the sub-project area. The WUA plays an active role in this
activity, and it is the main responsibility of the NGO that they
provide full details about the project and mobilize the farmers
into forming the WUGs. The farmers obtain all the information
about the project and its implementation procedures and
organize themselves into the Water User Groups (WUGs). The
GFO approves the groups after field verification.
Step 8 RESOURCE MOBILIZATION: In case of DTW, the WUA deposits
the balance amount of the up-front cash to make deposit of
0.5% of the total cost of the DTW system, whereas in case of
the other ground water development schemes, the full cost of
well drilling,, installation of well with pipe, filter and the LT
440 V electricity connection and electric pumping set, will be
born by WUA where the project will provide11 KV HT rural
transmission line and rural access road to these cluster area of
about 300 ha at project cost. The GFO prepares sub-project
implementation plan, together with the WUA, DADO, NGO
and other stakeholders. The RID approves the implementation
plan and includes in the annual work plan.
Step 9 FORMALIZE FARMERS' ORGANIZATION AND PARTICIPATION:
The NGO sees that the WUA finalizes its constitution by the
general assembly of all the members, and that the WUA is
registered. In this process, the TA team, GFO and DADO/ASC
also provide necessary technical and advisory assistance. The
WUA then signs a memorandum of understanding with the
GFO in front of the general assembly for the implementation of
the sub-project in the area.
Step 10 COST ESTIMATION, APPROVAL AND TENDER DOCUMENT
PREPARATION: After RAC and PICC approval, GFO informs
the RAD, DADO, DDC and the WUA about the approval of the
sub-projects. The GFO then discusses the final cost estimate,
including the cost sharing arrangements, with the WUA, to
which, the WUA and its members agrees. The invitation of
tender bid, their evaluation and award of contract will be carried
out as per the rules and regulations of the government of Nepal.
Step 11 CONSTRUCTION: The GFO starts the construction works
only after ensuring that the WUA has deposited a total of 15%
of the total cost, cash and kind combined, in case of DTW
subproject, while in the case of other ground water subproject,
27
full cost of drill, installation of casing pipe filter pipe line with
centrifugal electric pumps, LT electricity connection, will be
born by WUGs through WUA. The project will provide full cost
of HT transmission line and access rural road to cluster area.
The up-front cash will be collected from WUG and deposited in
the joint account of GFO and WUA. The civil construction
work may be contracted out or may be done by force account.
The GFO staff supervises the drilling works; tube well testing,
pump installation, power supply line and other civil works. The
WUA also forms a construction supervision committee, which
supervises all tube well and civil work construction, pumping
set and electric fittings suppliers, and ensures their quality
before the payment to the contractor or the suppliers. In case of
the ground water development schemes, the respective water
user groups (WUGs) will drill well, install casing pipe, filter
and purchase the pumping set and install LT electricity
connection at their cost.
Contract Commissioning: Any piece of contract, when
completed should be commissioned by GFO technical staff in
association with WUA and contractor within the liability period
of contractor. Contractors would rectify the defects noticed
duly.
29
Figure A.2: Procedural Guidelines Steps for Sub-project Implementation
of Ground water Schemes
Sub-project Approval
for Implementation.
Legalization of WUA
Commissioning
Step-12
30
4.3 Time frame of subprojects implementation (SW &GW)
under component A
Any unsustainable human intervention into natural regime of soil and water
resources can cause instability and threat to equilibrium of nature and impact
the livelihood of the local communities. For example, unplanned excavation
of canal can pose instability and undue extraction of natural resources (Earth
materials viz. Soil, Sand, and Boulder including surface or Ground Water)
can cause major or minor social and environmental disturbances. Depending
on the scale of intervention and sustainable capability of the nature, the
social and environmental effects may be local, regional and sometimes
national. Therefore, all irrigation sub-projects proposed to be included under
IWRMP are required to be screened against the prevailing legal regulations
criteria and the Social and Environmental Framework (SEMF) of IWRMP
and agreed with the World Bank and complying with its Social and
Environmental Safeguard Policies. However, in case of environmental
aspects in addition to SEMF, depending on the scale of intervention at the
31
subproject level may be subjected to Environmental Impact Assessment
(EIA) or Initial Environmental Examination (IEE) in accordance with the
Environmental Protection Rules (EPR 1997 amended in 1999) of
Government of Nepal (GoN). In sub-projects which do not require EIA/IEE,
social assessment should be undertaken to assess whether the project
activities have any adverse social impacts and accordingly determine
whether a social management plan is required, specifically the need for a
resettlement plan (RAP), indigenous peoples development plan (IPDP),
gender action plan (GAP), etc.
The SEMF is designed to provide a guideline at the sectoral level for Social
and Environmental Assessment (SEA) of irrigation sub-projects proposed
for implementation under IWRMP and incorporates all the essential policy
and regulatory features of the GoN's social and environmental policy
regime.
32
project planning and implementation so that their genuine voices and
demands are not left unheard.
33
Steps in Social and Environmental Assessment Process vis-à-vis the Sub-
Project Cycle
34
strategy suggested should also be incorporated during
this process.
10. ISEA Report Preparation: Summary of all
information obtained, analyzed and interpreted in a
report form; also include a non-technical summary
including methods used, results, interpretations and
conclusions made. GON’s EPA and EPR do not
demand for ISEA report. Rather IEE/EIA is sufficient
for EA process but it should incorporate physical,
chemical, biological, social, economic and cultural
aspects/environment as these are considered to be the
inseparable parameters of the existing environment as
a whole.
Project 11. Review and Approval of ISEA Report: Review
Appraisal/Approval of report to assess if all possible issues have been
adequately addressed and to facilitate the decision-
making process; decide if project should proceed, or if
further alternatives must be examined or totally
abandoned.
12. Public Hearing: As per the EPR, project related
details including the impacts and their mitigation
measures should be disseminated to the public and
their involvement process during the implementation
should be discussed. The representatives related with
local governance, project affected people and other
stakeholders are invited during the process.
Implementation 13. Preparation of Social and Environmental
Plan, Engineering Management Plan (SEMP): Determination of
Design specific actions to take during engineering design and
construction stages to minimize negative impacts and
enhance the positive impacts. Formulation of
Resettlement Action Plan and/or Women, Indigenous
and Disadvantaged/ Vulnerable (Dalits, Land less)
Groups Development Plan, if required.
Engineering 14. Social and Environmental Monitoring:
Design & Determination of compliance with SEMP and social
Construction mitigation plans (Resettlement and other plans)
Works
Post-Construction 15. Environmental Audit : Commission the audit two
years after the sub-project completion
35
Applicable Bank Social and Environmental Policies: Following Table
summarizes the Bank safeguards operational policies that are applicable to
the project and how they will be addressed under IWRMP
39
common community) constructing lost community resources,
properties facilities such as religious and cultural
structures or providing alternatives in
consultation with affected communities.
4.2 Titleholders Cash compensation/transition allowance.
Temporary
Losses
In addition, the affected people will be provided counseling services to find
suitable lands for resettlements.
Strategy for Indigenous People Development: The indigenous peoples
(referred as janajatis ) and other vulnerable groups (including dalits) in
Nepal are normally characterized by marginal and small land holding size,
land mostly in the tail end of the command area, mostly practice traditional
agricultural practices with limited benefits from irrigated agriculture, limited
exposure to emerging market, limited access to institutional credit, farm
inputs and agricultural extension, lack or poor leadership, marginalization in
the decision making process, inadequate participation in decision-making in
WUA functioning; lack of consultation regarding water management
practices etc. In order these issues, a strategy for indigenous peoples’
development has been prepared for the project and included as part of
ESMF. This strategy is based on GON’s specific policies and programs
being implemented for development of these groups and is aimed at helping
them access project benefits and improve their participation in the planning
and implementation of the project activities at the sub-project level.
43
6. MONITORING AND EVALUATION OF OUTCOMES/RESULTS
The OPD will have overall responsibility for planning and coordinating
M&E activities. In this role, the OPD will coordinate M&E activities of the
three sets of entities that will be involved with data collection and analysis:
(i) the implementing departments/agencies, including at the regional and
district levels; (ii) an external M&E agency (to be engaged for baseline
survey and pre-MTR and pre-ICR impact assessments); and (iii) beneficiary
WUAs and other relevant stakeholders. The PICC will function as an
oversight body to monitor overall project implementation on a quarterly
basis.
There will be a dedicated M&E unit in the OPD headed by the Project
Director. The unit will have lead responsibility for ensuring that relevant
entities involved in project M&E use appropriate data collection, analysis
and reporting methods and instruments and have appropriate procedures for
ensuring quality and reliability of data (such as the use of “without project”
reference sites – or “control” sites – and “triangulation” with other available
data where feasible). In particular, it will oversee development of the
relevant formats and software data collection, compilation, analysis and
reporting at various levels on a periodic basis. In this regard, it will
coordinate with the M&E unit in WECS, project M&E units at regional and
sub-regional levels, the external M&E agency, and NGOs facilitating data
collection at the WUA level. It will report on a quarterly basis on project
implementation progress to PICC.
At the regional level, each RID and RAD will have M&E units responsible
for coordinating activities in the concerned districts/ divisions/ Ground
Water Field Offices (GFOs). At the district level Irrigation Development
Division (IDDs)/GFOs/District Agriculture Development Offices (DADOs)
shall be the coordinating agencies for the M&E activities. The process of
participatory M&E undertaken by the beneficiary WUAs will be facilitated
by local NGOs and by the local level project implementing agencies as
44
appropriate. The data collected will be filled in standard formats at the
IDD/GFO/DADO level and forwarded to M&E units at the RD levels. At the
RD level, all the data received from lower levels will be complied and
forwarded to central M&E units. The M&E unit under the OPD will analyze
the date and produce simplified informative formats for distribution to the
PICC, World Bank, NPC, WECS and other concerned agencies for their
review and timely feedback.
Overall, the M&E activities undertaken within the project would include:
baseline study; regular performance tracking of inputs and outputs by
concerned implementing agencies; participatory M&E by beneficiary
WUAs; and pre-MTR and pre-ICR performance assessment and impact
evaluation surveys. The results framework and monitoring of Component A
and component B is shown in Annex 5.
Both IDA and GoN will carry out a formal six-monthly review of project
implementation progress and achievement of project development objective.
This will allow for necessary mid-course corrections in response to changing
local conditions, including with respect to the security situation.
7. PROCUREMENT ARRANGEMENT
Under this project procurement will be required for the rehabilitation of
existing irrigation schemes, construction of small tertiary canals and other
minor construction works. Most of these works would be of medium or
small value and shall be procured through National Competitive Bidding
(NCB) using national procedures and model documents agreed with or
satisfactory to the Bank or when appropriate, through quotations. Small
works in secondary and tertiary canals in transferred irrigation systems will
be contracted out to respective WUAs up to 3.5 million as per clause 97 of
procurement regulation.. The procurement for works will be done through
National Competitive Bidding (NCB)/ Local Competitive Bidding (LCB) as
per process set out in regulation’s chapter 5 of Public procurement
regulation 2064 using national SBD agreed with or satisfactory to the Bank.
The threshold value of NCB and LCB will be as agreed with World Bank.
Assignments that require the services of firms or individual consultants
include studies and assessments, development of a national water resources
database, and training will be procured as per process agreed with WB. The
threshold value will be also agreed with Bank.
45
8 FINANCIAL MANAGEMENT
46
contain details of how users’ contribution will be accounted and other
reporting formats.
8.2 Funds Flow Arrangements
GON releases the budget as per the approved work programs to respective
departments (DOI, WECS and DOA) in three tranches as per its fund release
procedures. The budget approved by GON will be indicated in the
government’s budget (Red Book) under separate budget heads under each
implementing agency. Prior to the approval of the work program and
budget, one-third release of the previous year expenditures or projected
expenditures for the first trimester, whichever is greater, will be made to the
respective agency through the concerned DTCO. Fund release for IDA’s
share of expenditures will be pre-financed through GON’s consolidated
fund. Upon approval of the work program and budget, appropriate
adjustment will be made against the advance for the first trimester release.
Subsequent second and third trimester releases are based on performance
reflected by the physical progress reports as required by Schedule 2 of the
FAR.
47
component, and the other for the agriculture component. Each component
implementing agency will compile the monthly statement of expenditures
(SOE) within seven days following the end of each month. WECS will send
its statement of expenditures to the OPD which will be consolidated in the
report to be prepared by DOI. Both DOI and DOA will be adequately
strengthened to maintain accounting information using spreadsheet or
appropriate software.
48
Team will comprise of a Project Coordinator, the Accounts Officer and the
Accountant. Similarly, in DOA, for implementation of Component D, the
Project Management Team will have one Project Coordinator, one Agro-
Economist, one overseer, two Agriculture Extension Officers, one Accounts
Officer, one Accountant and one Computer Assistant. Teams at WECS and
DOA will closely coordinate with the OPD Team.
8.5 Internal Audit
District Treasury Controller Offices (DTCOs) in districts are responsible to
carry out the internal audits of all cost centers operating in the districts.
Internal audits are carried out on a trimester basis. Divisional Irrigation
Offices and District Agriculture Development Offices are responsible to
maintain district level accounts by budget heads. These offices forward the
monthly expenditure statements to their respective departments, which then
will prepare their consolidated expenditure statements. For technical audits
of civil works, an arrangement will be made through the National Vigilance
Center (NVC).
8.6 Implementation Progress Reports (IPRs)
Total project costs are estimated around US$65.0 million of which IDA
contribution is US$50.0 million, government counterpart contribution is
US$10.0 million, and users contribution (in kind or cash) is about US$5.0
million (only for irrigation sub-projects). While developing annual work
programs and budgets, each implementing agency will formulate programs
to be separated by activity or work program fully funded by IDA or GON.
For irrigation sub-projects, proposed Implementation Manual will contain
details of accounting users’ contribution in the books of accounts and how
they should be reported.
49
a trimester basis and submitted within 45 days from the end of the preceding
trimester.
8.7 External Audit
The following is the audit1 requirements under the Project:
1
Terms of reference acceptable to IDA need to be discussed and agreed with OAG.
50
List of References (IWRMP)
51