REKAPITULASI

Pekerjaan : MESS PEKERJA


Lokasi : MESUJI
Tahun : 2024

HARGA MATRIAL HARGA UPAH


NO URAIAN PEKERJAAN JUMLAH (Rp)
(Rp) (Rp)
I PEKERJAAN PERSIAPAN 10.500.000.00 8.250.000.00 18.750.000.00
II PEKERJAAN GALIAN - 3.081.712.50 3.081.712.50
III PEKERJAAN TIMBUNAN 1.475.000.00 1.998.000.00 3.473.000.00
IV PEKERJAAN STRUKTUR 68.558.905.00 20.702.400.00 89.261.305.00
V PEKERJAAN ARSITEKTUR 137.757.950.00 82.195.000.00 219.952.950.00
VI PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING(MEP) 30.945.000.00 3.867.000.00 34.812.000.00
JUMLAH 249.236.855.00 120.094.112.50 369.330.967.50
PPN 11% 27.416.054.05 13.210.352.38 40.626.406.43
TOTAL 276.652.909.05 133.304.464.88 409.957.373.93
PEMBULATAN 276.650.000.00 133.300.000.00 409.950.000.00

TERBILANG: Empat Ratus Sembilan Juta Sembilan Ratus Lima Puluh Ribu Rupiah
Harga Permeter material : 2.459.111.11 include PPN
Jasa : 1.184.888.89 include PPN
Matrial + jasa : 3.346.530.61 include PPN

Catatan: Luas bangunan 112.5m2


RENCANA ANGGARAN BIAYA

Pekerjaan : MESS PEKERJA


Lokasi : MESUJI
Tahun : 2024

HARGA
HARGA JASA TOTAL MATERIAL TOTAL UPAH
NO URAIAN PEKERJAAN VOL SAT MATERIAL
(Rp) (Rp) (Rp)
(Rp)
A B C D E F G H
I PEKERJAAN PERSIAPAN
1 Pembersihan lahan 1.00 Ls - 5.000.000.00 5.000.000.00
2 Pemasangan Bowplank 1.00 Ls 2.500.000.00 750.000.00 2.500.000.00 750.000.00
3 Pemagaran Area Kerja 1.00 Ls 7.500.000.00 2.500.000.00 7.500.000.00 2.500.000.00
4 Biaya K3 1.00 Ls 500.000.00 500.000.00 -
SUB TOTAL 10.500.000.00 8.250.000.00
II PEKERJAAN GALIAN
1 Galian pondasi Footplat 80x80 16.64 M3 135.000.00 - 2.246.400.00
2 Galian Saluran Buang Parit 3.19 M3 135.000.00 - 430.312.50
3 Pekerjaan galian septictank 3.00 M3 135.000.00 - 405.000.00
SUB TOTAL - 3.081.712.50
III PEKERJAAN TIMBUNAN -
1 Urugan pasir kerja 5cm 1.00 M3 275.000.00 135.000.00 275.000.00 135.000.00
2 Floor Lantai Kerja 5cm 1.00 M3 1.200.000.00 135.000.00 1.200.000.00 135.000.00
3 Urugan Tanah Kembali Pondasi 12.80 M3 - 135.000.00 - 1.728.000.00
SUB TOTAL 1.475.000.00 1.998.000.00
IV PEKERJAAN STRUKTUR -
1 Pasangan Sloof 15x30
Bakisting 60.60 M2 115.000.00 12.500.00 6.969.000.00 757.500.00
Pembesian 474.40 Kg 15.450.00 12.500.00 7.329.480.00 5.930.000.00
Beton k225 4.50 M3 1.200.000.00 195.000.00 5.400.000.00 877.500.00
2 Pasangan Kolom 15x15 -
Bakisting 12.60 M2 115.000.00 12.500.00 1.449.000.00 157.500.00
Pembesian 292.00 Kg 15.450.00 12.500.00 4.511.400.00 3.650.000.00
Beton k225 1.89 M3 1.200.000.00 195.000.00 2.268.000.00 368.550.00
3 Pasangan Ring Balok 10x20 -
Bakisting 39.20 M2 115.000.00 12.500.00 4.508.000.00 490.000.00
Pembesian 397.50 Kg 15.450.00 12.500.00 6.141.375.00 4.968.750.00
Beton k225 1.98 M3 1.200.000.00 195.000.00 2.376.000.00 386.100.00
4 Pasangan Balok Latei Atas Kusen -
Bakisting 6.00 M2 115.000.00 12.500.00 690.000.00 75.000.00
Pembesian 62.00 Kg 15.450.00 12.500.00 957.900.00 775.000.00
Beton k225 0.45 M3 1.200.000.00 195.000.00 540.000.00 87.750.00
5 Pasangan floor lantai finishing semen 145.25 M2 175.000.00 15.000.00 25.418.750.00 2.178.750.00
SUB TOTAL 68.558.905.00 20.702.400.00
V PEKERJAAN ARSITEKTUR -
A BANGUNAN UTAMA -
1 pasangan Dinding Batako 1/2 Bata 198.00 M2 55.800.00 50.000.00 11.048.400.00 9.900.000.00
2 Pasangan Plesteran 396.00 M2 25.700.00 47.500.00 10.177.200.00 18.810.000.00
3 Pasangan Acian 396.00 M2 26.700.00 47.500.00 10.573.200.00 18.810.000.00
4 pengecatan Dinding 3 lapis 396.00 M2 22.500.00 20.000.00 8.910.000.00 7.920.000.00
5 Pasangan rangka Hollow 150.00 M2 22.755.00 15.000.00 3.413.250.00 2.250.000.00
6 Pasangan plafon gypsum 113.00 M2 39.700.00 15.000.00 4.486.100.00 1.695.000.00
7 Pasangan plafon gypsum luar 9.00 M2 39.700.00 15.000.00 357.300.00 135.000.00
8 Pengecatan plafon 159.00 M2 22.500.00 15.000.00 3.577.500.00 2.385.000.00
9 Pasangan keramik tile 40x40 36.00 M2 145.000.00 45.000.00 5.220.000.00 1.620.000.00
10 Pasangan keramik Lantai motif kasar 40x40 4.50 M2 145.000.00 45.000.00 652.500.00 202.500.00
11 Pasangan keramik Dinding 40X40 21.50 M2 145.000.00 45.000.00 3.117.500.00 967.500.00
12 pasangan rangka Atap baja ringan 300.00 M2 65.000.00 25.000.00 19.500.000.00 7.500.000.00
13 Pasangan Atap Genting metal 300.00 M2 125.000.00 25.000.00 37.500.000.00 7.500.000.00
14 Pasangan Lisplank GRC 70.00 M1 37.500.00 10.000.00 2.625.000.00 700.000.00
HARGA
HARGA JASA TOTAL MATERIAL TOTAL UPAH
NO URAIAN PEKERJAAN VOL SAT MATERIAL
(Rp) (Rp) (Rp)
(Rp)
15 pasangan Pintu 1 (P1) 2.00 Unit 2.400.000.00 200.000.00 4.800.000.00 400.000.00
16 Pasangan Pintu 2 (P2) 2.00 Unit 2.300.000.00 200.000.00 4.600.000.00 400.000.00
17 Pasangan Pintu 3 (P3) 2.00 Unit 975.000.00 150.000.00 1.950.000.00 300.000.00
18 Pasangan Jendela 1 (J1) 2.00 Unit 1.650.000.00 200.000.00 3.300.000.00 400.000.00
19 Psangan Jendela 2 (J2) 2.00 Unit 975.000.00 150.000.00 1.950.000.00 300.000.00
SUB TOTAL 137.757.950.00 82.195.000.00
VI PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING(MEP) -
A ELEKTRIKAL -
1 Instalasi titik elektrikal Kabel NYA 30.00 titik 97.500.00 22.500.00 2.925.000.00 675.000.00
2 Instalasi Lampu LED 13 Watt 16.00 titik 195.000.00 22.500.00 3.120.000.00 360.000.00
3 Instalasi Kipas 2.00 titik 1.250.000.00 48.500.00 2.500.000.00 97.000.00
4 Instalasi Stop Kontak 10.00 titik 77.500.00 22.500.00 775.000.00 225.000.00
5 Intalasi saklar single 6.00 titik 125.000.00 22.500.00 750.000.00 135.000.00
6 Intalasi saklar Double 4.00 titik 125.000.00 22.500.00 500.000.00 90.000.00
7 Intalasi MCB 2.00 titik 475.000.00 55.000.00 950.000.00 110.000.00
SUB TOTAL 11.520.000.00 1.582.000.00
B PLUMBING -
1 Instalasi Pipa Induk Distribusi 2" Air Bersih 1.00 Ls 1.250.000.00 150.000.00 1.250.000.00 150.000.00
2 Instalasi Pipa 3/4" pembagi kran air 1.00 Ls 750.000.00 150.000.00 750.000.00 150.000.00
3 Instalasi Pipa 3" Air bekas 1.00 Ls 2.750.000.00 150.000.00 2.750.000.00 150.000.00
4 Instalasi Pipa 4" Air Kotor 1.00 Ls 1.875.000.00 150.000.00 1.875.000.00 150.000.00
5 Pengadaan Toren air kapasitas 1000 Liter 1.00 Unit 2.000.000.00 250.000.00 2.000.000.00 250.000.00
6 Pengadaan Closed jongkok Toto 2.00 Unit 1.050.000.00 75.000.00 2.100.000.00 150.000.00
7 Pemasangan Stop Kran 4.00 Unit 175.000.00 37.500.00 700.000.00 150.000.00
8 Pasangan Wastafel Steinlis 2.00 Unit 1.050.000.00 100.000.00 2.100.000.00 200.000.00
9 Pasangan Floor drain 2.00 Unit 175.000.00 37.500.00 350.000.00 75.000.00
10 Pengadaan Kran Wastafel 2.00 Unit 275.000.00 30.000.00 550.000.00 60.000.00
11 Biotank 2.00 Unit 2.500.000.00 400.000.00 5.000.000.00 800.000.00
SUB TOTAL 19.425.000.00 2.285.000.00
TOTAL A+B 30.945.000.00 3.867.000.00
SUB TOTAL 249.236.855.00 120.094.112.50