Professional Documents
Culture Documents
1 2 3 4
February 2009 6.03.09 4000 31500 31000
1 2 3 4
Nov2011 25.11.11 5500 43000 42000
1 2 3 4
July 2014 19.08.14 5600 46500 43500
Aug 2014 19.08.14 6000 48000 50000
Sep 2014 13.10.14 5800 42000 45000
Oct 2014 20.11.14 5900 44000 45000
Nov 2014 17.01.15 5500 43000 45000
Dec 2014 17.01.15 6000 43000 45000
Jan 2015 05.02.15 6800 43500 45000 45600
Feb 2015 11.03.15 6400 44000 46000 45600
Mar 2015 15.04.15 6200 43000 44000 45000
April 2015 05.05.15 6400 42000 44000 45000
May 2015 22.06.15 6400 42000 44000 45000
June 2015 22.07.15 5620 42000 44000 45000
July 2015 18.08.15 5620 41000 42000 42500
Aug 2015 16.09.15 5620 34000 41000 41500
Sep 2015 28.09.15 5620 34000 41000 41500
OCT 2015 17.10.15 5620 33000 39000 39000
Nov 2015 10.12.15 5620 32000 37000 34000
Dec2015 19.01.16 5620 32000 37000 34000
Jan 2016 15.02.16 5620 34000 38000 36000
Feb2016 08.03.16 5620 34000 38000 35000
Mar2016 20.04.16 5300 34000 37500 36000
Apr2016 04.05.16 5000 34000 37500 36000
May2016 29.06.16 5200 34000 37500 36000
June 2016 29.06.16 5700 34500 37500 36000
July 2016 17.08.16 5700 34500 37500 36000
Aug 2016 14.09.16 5700 34500 37000 36000
Sep 2016 22.09.16 6400 34500 37500 36000
Nov, Dec 2016 29.12.16 4800 34500 37500 36000
Jan2017 07.04.17 36000 38000 36500
Feb 2017 07.04.17 36000 38000 36500
23.03.17/13.0
Mar2017 37500 38000 36500
6.17
Apr2017
30.06.17 4800/5000 37500 40000 38000
May-17 30.06.17 37500 40000 38000
June2017 26.09.17 37500 40000 38000
STEEL ( HYSD bars avg, rate )
CEMENT in
MONTH Date 4800/5000
MT 8mm to 40mm MS Steel MS Rods
1 2 3 4
July 2017 26.09.17 38500 39000 39000
Aug2017 01.11.17 38500 40500 40200
Sep-17 04.12.17 32700 35000 35000
Oct-17 04.12.17 32100 35500 36000
Jan-18 03.03.18 Jan 41000 39000 41500
Feb-18 03.04.18 Feb 3750/3900 42500 39000 41500
Mar-18 03.04.18 March 41300 40000 41500
Apr-18 01.06.18 April 42000 41000 42000
05.07.18 May 42000 41300 43000
27.07.18 June 42000 41300 43000
20.08.18 July 42000 42000 43000
28.09.18 Aug 42000 42000 43000
06.11.18 Sep 42000 42000 44000
07.12.18 Oct 42000 42000 44000
20.12.18 Nov 43500 44000 44500
28.01.19 Dec 43500 44000 44500
25.01.19 Jan 43500 44000 44500
26.02.19 Feb 43500 45000 45000
27.03.19 43500 45000 45000
20.04.19 43500 45000 45000
12.06.19 May 38500 43500 44000
10.07.19 June 40500 43500 44000
30.07.19 July 40000 43000 43000
OPC 187.5
Hosing programme and CC
roads in Rural areasand angan
wadi PPC 185
PPC 187.5
194.1
3750
3680
CEMENT & STEEL
Mild steel,
STEEL ( HYSD bars
structural
avg, rate )
CEMENT 6mm MS Steel,
MONTH Date MS Flats
in MT Rods i.e. Angles,
FE 415 FE 500 Channels and
Isections
Jan 25.01.19 43500 44000 44500 44000 44000
Feb 26.02.19 43500 44000 45000 45000 45000
March 27.03.19 43500 44000 45000 45000 45000
April 20.04.19 43500 44000 45000 45000 45000
May 12.06.19 38500 39500 44000 44500 43500
June 10.07.19 40500 40900 44000 44500 43500
July 30.07.19 40000 40500 43000 44000 43000
August 28.08.19 36500 37000 43000 41000 40000
Septembe
26.09.19 36500 37000 37000 41000 39500
r
October 29.10.19 36500 37000 35000 40000 38000
November 18.12.19 36500 37000 35000 40000 38500
Jan-20 03.06.20 215 38500 39000 40000 40000 38500
Mar-20 27.11.20
1st Mar to
03.09.20 39000 40000 39000 39000 39000
31May20
Page 18
Blasting charges 70.00
Machine crushing charges 299.00
1565.00
(2) Add 25% extra per cum if the metal is obtained by machine
crushing excluding cost of blasting. 1 cum 25%
Page 19
Blasting charges 70.00
Machine crushing charges 273.00
1435.00
Page 20
MAT-00480 Clearing light Jungle 1 Sqm 2.80
Kadapa slab 40 mm thick and size not less than 0.457 M x 0.457
BMT-B.01 1 Sqm 125.00
M
Kadapa slab 50 mm thick and size not less than 0.457 M x 0.457
BMT-B.02 1 Sqm 145.00
M
Polished black Kadapa slabs minimum of 15 mm thick
BMT-B.06 10 Sqm 1750.00
(0.457x0.457M)
Polished Bethamcherla pure (marble type) white stone minimum
BMT-B.07 10 Sqm 4600.00
25 mm thick (0.254Mx0.254M)
Polished Bethamcherla coloured stone minimum 25 mm thick
BMT-B.08 10 Sqm 3200.00
(0.254M x0.254M)
High Polished Granite 16 to 18 mm thickup to2.43m other than
BMT-B.09 1 Sqm 2800.00
block/primium colours
High Polished Granite 16 to 18 mm thickup to2.43m other than
BMT-B.10 1 Sqm 2500.00
block/ regular colours
BMT-B.11 High Polished Granite 16 to 18 mm thickup to2.43m block 1 Sqm 2100.00
BMT-B.15 Polished Marble Tiles 8 mm thick of all sizes and varieties 1 sqm 510.00
BMT-B.16 Granitestonetiles8mmthick(mirrorpolished ofallshades)
Polished blackKadapaslabsof allsizes between 25 -30mm 1 Sqm 1100.00
thickness
BMT-B.17 10 sqm 1850.00
Page 21
Supply of glazed red or white full body ceramic wall tiles of Size
300 x 600 mmand thickness between 6-8 mm and 1st quality
BMT-C.23 1 sqm 550.00
conforming to IS:13711,IS:13712, IS:13630 (Parts 1 to 15) ofany
colour and finish in all shades and designs
Page 22
BMT-E.14 Assam Teak Wood scantlings: any length 1 Cum 72750.00
BMT-F.19 Stain less steel flyproof wire mesh of not less than 20guage 1Sqm 564.00
BMT-J.04 Supply of Zinc Chromate Yellow Oxide Primer paint for Iron works 1Litre 200.00
Page 23
BMT-J.08 White Lead 1 Kg 110.00
BMT-J.26 Supply of Paint grade White lime for wash 25Kg 490.00
BMS-W.20 Mastic pad 2'0 " x 4'0" (0.60M x 1.2M) of 1" (25.4 mm ) thick 1Sqm 923.00
BMS-W.21 Mastic pad 2'0 " x 4'0" (0.60M x 1.2M) of 1" (12.7 mm ) thick 1Sqm 529.00
Page 24
MAT-00536 Jute Rope 1Mt 8.35
BMM-V.13 Flat nosing to Kadapa/ Shahabad stoneslabs of any thick 1Rm 65.00
Page 25
Labour charges for fabricating all heavy steel works like Trusses,
BMM-V.16 Stanchions, Heavy Beams and Girders including cost of welding Kg 26.00
rods, power charges, etc excluding cost of fixing in position
Labour charges for Fabrication of stainless steel railing works
usingstainless steel welding rods includingbuffing, polishing,
BMM-V.18 Kg 144.00
lacquer finishing, topresent seamless finish
Drilling 130.00
Page 26
32mm Dia GI pipe 354.00
Page 27
Centring Unit of
NAME OF THE STRUCTURAL Material Hire
Sl Labour charges Charges for Measurem
MEMBER charges
2022-23 ent
1 2 3 4 5 6
B BEDBLOCKS BONDS Rs. 67.00 Rs. 363.00 Rs. 430.00 per 1 cum
D PLINTH BEAMS Rs. 1453.00 Rs. 1620.00 Rs. 3073.00 per 1 cum
Casuarinas Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc.,
F CHAJJAS - SUNSHADES Rs. 163.00 Rs. 204.00 Rs. 367.00 per 1 sqm
I SLABS - Up to 150 mm thick Rs. 165.00 Rs. 186.00 Rs. 351.00 per 1 sqm
J SLABS - above 150 mm - Up to 3 Rs. 170.00 Rs. 193.00 Rs. 363.00 per 1 sqm
K SLABS - above 300 mm thick Rs. 178.00 Rs. 201.00 Rs. 379.00 per 1 sqm
Q HELICAL STAIRCASES Rs. 205.00 Rs. 220.00 Rs. 425.00 per 1 sqm
HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casuarinas Ballies, Bamboos, Wooden Reapers,
Runners, Wood Posts, Wall Plates etc., for BRICK MASONRY/ STONE MASONRY/ WALL PUTTY/ TEXTURE PAINTS
etc - 1 sqm
A 1st - Floor Rs. 10.78 Rs. 84.62 Rs. 95.40 per 1 sqm
B 2nd - Floor Rs. 10.78 Rs. 121.18 Rs. 131.96 per 1 sqm
C 3rd - Floor Rs. 10.78 Rs. 157.72 Rs. 168.50 per 1 sqm
HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casuarinas Ballies, Bamboos, Wooden Reapers,
Runners, Wood Posts, Wall Plates etc., for PLASTERING to WALLS - 1 sqm
A 1st - Floor Rs. 1.08 Rs. 8.47 Rs. 9.55 per 1 sqm
B 2nd - Floor Rs. 1.08 Rs. 12.12 Rs. 13.20 per 1 sqm
C 3rd - Floor Rs. 1.08 Rs. 15.77 Rs. 16.85 per 1 sqm
HIRE CHARGES FOR STAGE SCAFFOLDING - up to 3.66 M using Casuarinas Ballies, Bamboos, Wooden Reapers,
Runners, Wood Posts, Wall Plates etc., for CEILING PLASTERING - 1 sqm
A 1st - Floor Rs. 2.57 Rs. 16.94 Rs. 19.51 per 1 sqm
B 2nd - Floor Rs. 2.57 Rs. 24.04 Rs. 26.61 per 1 sqm
C 3rd - Floor Rs. 2.57 Rs. 31.13 Rs. 33.70 per 1 sqm
HIRE CHARGES FOR CENTERING & SCAFFOLDING - Unsupported Height up to 3.66 M
Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates,etc.,
E CHAJJAS - SUNSHADES Rs. 243.00 Rs. 264.00 Rs. 507.00 per 1 sqm
H SLABS - Up to 150 mm thick Rs. 247.00 Rs. 241.00 Rs. 488.00 per 1 sqm
J SLABS - above 300 mm thick Rs. 265.00 Rs. 260.00 Rs. 525.00 per 1 sqm
ALLUMINIUM
BMT-G.06 75 MM Long Each 56.00
ALLUMINIUM
BMT-G.23 75 MM Long Each 82.00
ALLUMINIUM
BMT-G.40 200 mm long Each 265.00
5)FLAT LATCHES
BRASS
BMT-G.46 Door Stopers Each 185.00
ALLUMINIUM
BMT-G.48 200 mm long Each 117.00
Note : All the prices are ex-works. Excise duty, CST/VAT extra as applicable at the time of
supply. The above rates of RCC Plain ended pipes are based on the following raw materials
cost. Cement. Rs.3672/- per MT (including all taxes and freight). Steel (M.S. Rods) -
Rs.53000/- per MT. (including all taxes and freight). The revised cost of RCC pes due to
increase / decrease in the cost of raw materials shall be as per the following formula.
Sl.No. Description
1 2
MANUFACTURE, SUPPLY AND DELIVERY OF R.C.C. COLLARS CONFORMING
TO B.I.S. 458/2003 (RATE PER EACH COLLAR) SUITABLE FOR R.C.C.
PLAIN ENDED PIPES INCLUDING TRANSPORTATION BUT EXCLUDING
1 TAXES & DUTIES
Size Unit S S Rates for 2021-22
80 mm dia Each 46
100 mm dia Each 46
150 mm dia Each 47
200 mm dia Each 65
225 mm dia Each 69
250 mm dia Each 76
300 mm dia Each 99 141 141
350 mm dia Each 123 177 177
400 mm dia Each 135 202 202
450 mm dia Each 212 269 269
500 mm dia Each 341 321 321
600 mm dia Each 328 420 420
700 mm dia Each 527 567 567
800 mm dia Each 606 721 721
900 mm dia Each 723 839 839
1000 mm
Each 845 1050 1050
dia
1100 mm
Each 1034 1333 1333
dia
1200 mm
Each 1258 1668 1668
dia
1400 mm
Each 1620 2114 2114
dia
1600 mm
Each 2073 2709 2709
dia
1800 mm
Each 2127 3494 3494
dia
materials cost. Cement. Rs.3680/- per MT (including all taxes and freight).
Steel (M.S. Rods) - Rs.65000/- per MT. (including all taxes and freight).
The rates may be revised depending upon the increase/decrease in the cost of raw materials as
per the following method.
For every Rs.100/- per MT increase/decrease in the cost of cement, increase/decrease the rate by
0.79%.
For every Rs.1000/- per MT increase/decrease in the cost of steel, increase/decrease the rate by
1.495%.
3. S.S. RATES FOR CONVEYANCE OF R.C.C. PLAIN ENDED PIPES
1 2 3 4 5 6
CONVEYANCE OF R.C.C. PLAIN ENDED PIPES ON ALL WEATHER ROADS
1 INCLUDING LOADING, UNLOADING AND STACKING (per Meter) Sor
2021-22
NP - 2 Class NP - 3 Class & NP - 4 Class
1612.50 3214.69
12km
3262.50
83.45
83.2
1443.73
RATES FOR CONVEYANCE OF MATERIALS INCLUDING LOADING, UNLOADING AND STACKING ON METALLED ROAD FOR 2022-23
1 2 3 4 5 6 7 8
573.6
357.80
259.10
259.10
769.5
CONVEYANCE CHARGES - 2022-23
Earth, Earth,
Lead Cuddapah Lead in Cuddapah
Gravel, Metal Bricks Gravel, Metal Bricks
in Km slabs KM slabs
Sand Sand
1 36.00 34.70 51.00 57.80 36 528.00 509.50 747.90 847.40
Un
100 1296.00 1251.90 1835.90 2082.60 12.45 24.90 68.50
Loading
-
HIRE CHARGES OF PLANT & MACHINERY FOR THE YEAR : 2022-23
Hire Fuel Crew
Sl.
Description of machinery Unit charge charge Charge in Total in Rs
No
in Rs in Rs Rs.
1 2 3 4 5 6 7
1 Agitator car / Transit mixer 2 cum Hour 719.30 1508.60 391.60 2619.50
5 Air compressor 8.5 cmm ( diesel) Hour 254.90 1542.90 294.50 2092.30
6 Air compressor 8.5 cmm ( electric) Hour 156.40 475.90 230.10 862.40
9 Batching plant 0.5 cum ( 6 Cum/hr) Hour 106.90 126.90 473.50 707.30
10 Batching plant 2 x 1.00 cum ( 15 Cum/hr) Hour 378.20 380.70 473.50 1232.40
11 Batching plant 2 x 1.50 cum ( 50 Cum/hr) Hour 579.10 465.30 473.50 1517.90
13 Clamp shell and hoisting ropes Hour 5.70 0.00 0.00 5.70
16 Concrete mixer 300 / 200 ( diesel) Hour 51.00 137.10 306.80 494.90
17 Concrete mixer 300 / 200 ltr ( electric) Hour 49.60 42.30 306.80 398.70
18 Concrete mixer 600 / 400 ( diesel) Hour 86.40 274.30 306.80 667.50
19 Concrete mixer 600 / 400 ltr ( electric) Hour 84.60 84.60 306.80 476.00
38 Ice plant & accessories 30 t / day Hour 175.50 1205.50 184.10 1565.10
1 2 3 4 5
Spreading
1 Dozer( D 80 ) Cutting Per Hour 3031.80
Cleaning
Spreading
2 Dozer( D 50 ) Cutting Per Hour 1907.00
Cleaning
Clearing
Spreading
3 Mortor Grader Per Hour 3722.00
GSB
WMM
Soil Ordinary
Soil Marshy
4 Hydraulic Excavator Per Hour 3483.70
Soil unsuitable
Cranes
(a) 80 tonnes 1539.00
34
(b) 35 tonnes Lifting purpose Per Hour 1033.00
(c) 3 tonnes 501.00
(d)Crane with grab bucket 0.75 cum Well foundation Per Hour 2693.00
(e)Crane with grab bucket 1 cum Well foundation Per Hour 4403.00
Amarthaluru Bodapadu Vellaturu 29.00 Chandolu 12.00 Vejendala 26.00 Lam 43.50 Kollur 30.00 Tenali 21.00 20%
Amarthaluru Gowada Krishna River 20.00 Kavuru 10.00 Vejendala 32.00 Lam 52.00 Kollur 20.00 Tenali 20.00 20%
Amarthaluru Inturu Vellaturu 32.00 Chandolu 8.00 Vejendala 32.00 Lam 49.00 Kollur 32.00 Tenali 20.20 20%
Amarthaluru Korutadiparru Krishna River 24.50 Chandolu 15.50 Vejendala 25.50 Lam 43.50 Kollur 24.50 Tenali 14.50 20%
Krishna
Amarthaluru Kuchipudi 24.00 Krishna River 24.00 Vejendala 18.20 Lam 40.50 Kollur 24.00 Tenali 8.00 20%
River/Gaju
Amarthaluru Moparru Krishna River 28.00 Chandolu 17.00 Vejendala 24.00 Lam 42.00 Kollur 28.00 Tenali 16.50 20%
Amarthaluru Mulpur Juvvalapalem 25.00 Krishna River 25.00 Vejendala 23.00 Lam 47.00 Kollur 25.00 Tenali 11.00 20%
Amarthaluru Panchalavaram Krishna River 28.00 Gudavalli 7.00 Vejendala 31.00 Lam 51.00 Kollur 28.00 Tenali 19.00 0%
Amarthaluru Pedapudi Krishna River 20.00 Kavuru 16.50 Vejendala 23.00 Lam 43.50 Kollur 20.00 Tenali 11.00 20%
Amarthaluru Pyaparru Vellaturu 26.80 Chandolu 10.00 Vejendala 28.50 Lam 45.50 Kollur 28.00 Tenali 19.00 20%
Amarthaluru Thurumella 32Km Krishna River 26.00 Chandolu 15.00 Vejendala 25.50 Lam 44.00 Kollur 26.00 Tenali 13.50 20%
Amarthaluru Vamanaguntapalem Krishna River 26.50 Chandolu 17.50 Vejendala 27.50 Lam 45.50 Kollur 26.50 Tenali 16.50 20%
Amarthaluru Yadavaru Krishna River 15.50 Krishna River 15.50 Vejendala 18.50 Lam 39.50 Kollur 15.50 Tenali 7.50 20%
Amarthaluru Yalavarru Vellaturu 25.00 Chandolu 12.00 Vejendala 30.00 Lam 51.00 Kollur 22.00 Tenali 18.00 20%
373.8
21.9882
Pincodes
522325 27.20 Gajullanka
31.10 Gajullanka
30.00 Gajullanka
Chava vari Palem Kolluru 29.20 Kolluru 29.20 11.80 39.00 Kolluru 29.20 6.20
Eurukalapudi Kollipara 17.20 Kollipara 17.20 16.20 31.80 Kollipara 17.20 7.40
Gudiwada Kollipara 19.80 Kollipara 19.80 15.80 31.40 Kollipara 19.80 10.20
Half Peta Kollipara 23.00 Kollipara 23.00 17.40 24.00 Kollipara 23.00 13.20
JG Palem Kolluru 21.00 Kolluru 21.00 14.00 38.50 21.00 2.00
KancharlaPalem Kollipara 18.70 Kollipara 18.80 17.90 33.70 18.70 5.90
Kattevaram Kollipara 20.00 Kollipara 20.00 13.30 37.30 20.00 2.80
Kolakaluru Kollipara 18.50 Kollipara 18.50 12.90 28.50 18.50 8.60
Kopalle Kolluru 28.50 Kolluru 28.50 10.60 34.60 28.50 5.50
Mallepadu Kolluru 25.65 Kolluru 25.65 14.65 38.65 25.65 2.65
Nandivelugu Kollipara 15.60 Kollipara 15.60 15.80 31.40 15.60 6.60
Nelapadu Kolluru 30.00 Kolluru 30.00 19.00 43.00 30.00 7.00
Pedaravuru Kolluru 20.00 Kolluru 20.00 15.00 39.00 20.00 3.00
SJ Mudi Kolluru 30.00 Kolluru 30.00 5.00 29.00 30.00 7.00
SomasundaraPal
Kollipara 19.20 Kollipara 19.20 15.00 34.20 19.20 3.00
em
Telaprolu Kolluru 27.00 Kolluru 27.00 16.00 40.00 27.00 4.00
Village Sand for Mortor Sand for filling Gravel HBG Metal Bricks Cuddapah Slabs, Wood
Thotlapalem Kollipara 37.10 Kollipara 37.10 Vejendla 14.40 Lam 32.00 Kolluru 35.40 Tenali 14.90
UNIT -1 sqm
A) Material requirement as per India Gypsum
1219 mm x 1829 mm size Boards BMT M 53 sqm 1.03 441.00 454.23
GI Ceiling Angle - 25 mm x 10 mm x 0.55 mm BMT 47.36
RM 0.64 74.00
M 04
GI Ceiling section - 51.5 x 26 x 10.5 x 0.55 mm RM 0.84 85.00 71.40
BMT M 04
Intermediate channel - 45 x 15 x 15 x 0.9 mm RM 0.84 84.00 70.56
Perimeter Channel - 20 x 27 x 30 mm x 0.55 mm RM 0.4 74.00 29.60
Connecting clips Nos 1.84 2.00 3.68
Rawl Plug Nos 0.64 2.00 1.28
Soffit Cleats Nos 0.64 2.00 1.28
Drywall Screws - 25 mm Nos 18 2.00 36.00
Jointing compound Kgs 0.55 29.00 15.95
Jointing paper tape RM 1.46 5.00 7.30
Drywall Top Coat Liters 0.15 142.00 21.30
B) LABOUR CHARGES
1st Class Carpenter day 0.12 475.00 57.00
2nd Class Carpenter day 0.12 400.00 48.00
1st Class Painter day 0.024 510.00 12.24
2nd Class Painter day 0.024 400.00 9.60
Power Saw Cutter - Hand Operated - Operator day 0.012 400.00 4.80
Power Drill - Hand Operated - Operator day 0.024 400.00 9.60
Unskilled Mazdoor day 0.072 350.00 25.20
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 125.00 40.00
Power Drill - Hand Operated - Hire Charges Hrs 0.64 116.00 74.24
Scaffolding charges 1% 1040.62 10.41
D) Labour Allowance on B 166.44 41.61
E) Overheads and Contractor's Profit on A+B+C+D 1092.64
Page 55
2 Gypboard Fine line grid false ceiling
Supplying and fixing Gyp Board Fine Line Grid false ceiling (GS-FLC-4.6 as per India Gypsum) in size
600 mm x 600 mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet tiles of size 595 mm x 595 mm
or 595 mm x 1195 mm conforming to IS 2095 - 1982 fixing to Gyp steel Precoated GI wall angle of size
25 mm x 25 mm x of 0.70 mm thick along the perimeter of ceiling screw fixed to brick work/ partition at
610 mm c/c and suspending the frame work using pre-coated GI Tee section (24 mm x 38 mm x 0.7
mm) from soffit at 1220 mm c/c fixed with GI Soffit Cleat, rawl plugs and steel expansion fasteners &
connecting clip to the GI T section with 4 mm dia GI Rod with galvanized spring steel level clip of PVC
universal holding clips system at 1200 mm c/c and fixing the 12.5 mm / 9.5 mm Gypboard Sheet tiles
of size 595 mm x 595 mm or 595 mm x 1195 mm and finishing two coats of drywall topcoat complete
for finished item of work as per India Gypsum Ltd specification.
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 / 9.5 mm - Gypboard Tiles: 595 x 595 mm / 595
sqm 1.00 367.00 367.00
x 1195 mm BMT M 54
GI Precoated Angle - 25 mm x 25 mm x 0.7 mm RM 0.40 41.00 16.40
GI Precoated T Section: 24 mm x 38 mm x 0.7 mm RM 3.20 54.00 172.80
GI Rod - 4 mm Dia Connecting Rod RM 1.28 12.00 15.36
Rawl Plug Nos 1.28 2.00 2.56
Soffit Cleats Nos 1.28 2.00 2.56
Universal Holding Clips Nos 5.36 3.00 16.08
Drywall Top Coat Liters 0.15 142.00 21.30
B) LABOUR CHARGES
1st Class Carpenter day 0.12 475.00 57.00
2nd Class Carpenter day 0.12 400.00 48.00
1st Class Painter day 0.024 510.00 12.24
2nd Class Painter day 0.024 400.00 9.60
Power Saw Cutter - Hand Operated - Operator day 0.012 125.00 1.50
Power Drill - Hand Operated - Operator day 0.012 116.00 1.39
Unskilled Mazdoor day 0.072 350.00 25.20
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 125.00 40.00
Power Drill - Hand Operated - Hire Charges Hrs 0.32 116.00 37.12
Scaffolding charges 1% 846.11 8.46
D) Labour Allowance on B 154.93 38.73
E) Overheads and Contractor's Profit on A+B+C+D 893.31
3 Armstrong Fine line grid false ceiling
Providing and fixing in true horizontal level 600 mm x 600 mm 15 mm thick Arm strong false ceiling
system manufactured by M/s Arm strong world Industries using hot dipped Galvanized Steel section
exposed surface with pre-coated capping, main Tee of size 24 x 32 mm at every 1200 mm c/c
maximum and rotary stitched cross tee of size 24 x 27 mm at every 600 mm c/c and sub-cross tee of
size 24 mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall
and the above grid is suspended at every 1200 mm c/c in both directions using 2.0 mm thick pre-
straightened GI Wire laying fine fissured butt edge ceiling tiles of 15 mm thick mineral fiber Board
manufactured by M/s Arm Strong World Industries Ltd., having RH 99% and for finished of size 600 x
600 mm including Cost &conveyance of all materials and labour charges such as cutting , fixing of
standing of frame work exposing roof making complete for finished item of work
Page 56
UNIT -1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x 600 sqm 1
Precoated Hot dipped GI Angle Grid: 19 x 19 mm RM 0.4
Polyester painted GI - T Section: 24 x 32 mm and RM 1.6
24 x 25 mm (sub-cross Tee)
Polyester painted GI - T Section - 24 x 27 mm RM 1.6
GI pre-straightened - 2.0 mm dia Connecting Rod RM 1.28
6 mm Nylon Rawl Plug Nos 1.28
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter day 0.12
2nd Class Carpenter day 0.12
1st Class Painter day 0.024
2nd Class Painter day 0.024
Power Saw Cutter - Hand Operated - Operator day 0.012
Power Drill - Hand Operated - Operator day 0.012
Unskilled Mazdoor day 0.072
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32
Power Drill - Hand Operated - Hire Charges Hrs 0.32
Scaffolding charges 1%
D) Labour Allowance on B
E) Overheads and Contractor's Profit on A+B+C+D
4 Thermocole - Grid false ceiling
Providing and fixing Thermocole False ceiling in true horizontal level 600 mm x 600 mm using 15 mm/
19 mm thick Thermocole sheet anodized Aluminium Tee sections of size 24.50 mm x 24.0 mm x 2.4
mm in grid with cross tee of size 24 x 24.5 mm at every 600 mm c/c and anodized aluminium wall angle
of size 24 x 24 mm fixed to periphery of the wall and the above grid is suspended at every 1200 mm c/c
in both directions using 2.0 mm thick GI Wire for finished of size 600 x 600 mm including Cost
&conveyance of all materials and labour charges such as cutting , fixing of standing of frame work
exposing roof making complete for finished item of work
UNIT -1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600 sqm 1 46.00 46.00
Aluminium Angle : 24 mm x 24 mm RM 0.4 26.00 10.40
Anodized Aluminium T Section: 24 x 24.5 x 2.4 mm RM 3.2 34.00 108.80
GI Rod – pre-straightened - 2.0 mm dia - Nos 1.28 10.00 12.80
Connecting Rod
Rawl Plugs Nos 1.28 2.00 2.56
B) LABOUR CHARGES
1st Class Carpenter day 0.108 475.00 51.30
2nd Class Carpenter day 0.108 400.00 43.20
Power Saw Cutter - Hand Operated - Operator day 0.02 400.00 8.00
Page 57
Power Drill - Hand Operated - Operator day 0.04 400.00 16.00
Unskilled Mazdoor day 0.2 350.00 70.00
C) Machinery 0.00
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.16 125.00 20.00
Power Drill - Hand Operated - Hire Charges Hrs 0.32 116.00 37.12
Scaffolding charges 1% 37.7
D) Labour Allowance on B 463.88
E) Overheads and Contractor's Profit on A+B+C+D 46.39
5 S&F HYSD/TMT/MS bars (Lap splicing) 510.27
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel (MS)
steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works , including
labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying including sales and other taxes on all
materials etc., complete for finished item of work in all floors.( APSS No.126)
Unit = 1 MT
A) MATERIAL
HYSD/TMT/ MS bars including 5 per cent for MT 1.05
overlaps and wastage
Binding wire kg 6.00
B) LABOUR for cutting, bending, shifting to site,
tying, lap splicing and placing in position
Blacksmith / Bar bender day 10.00
Mazdoor (Unskilled) day 10.00
C) Labour Allowance on B
D) Overheads and Contractor's Profit on A+B+C
6 S&F HYSD/ TMT / MS bars (Welding)
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT)/ Mild Steel (MS)
steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) of different diameters for RCC works , including
labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and welding using electrodes, forming grills for
reinforcement work as per approved designs and drawings, including cost and conveyance of steel
bars, including all wastages such as overlaps, couplings, welding, chairs, spacer bars including cost
and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as
cutting, bending, placing in position, welding including sales and other taxes on all materials etc.,
complete for finished item of work in all floors.( APSS No.126)
Unit = 1 MT
A) MATERIALS
HYSD/ TMT/ MS bars including 2.5 per cent for MT 1.025
wastage
Welding Electrodes @ 5 per joint (14 joints / ton) each 70
Binding wire kg 3
B) Labour for cutting, bending, shifting to site,
welding and placing in position
Welder day 2.5
Blacksmith day 10
Mazdoor (Unskilled) day 10
C) Machinery
Page 58
Welding Charges (Hire charges of Welding Hr 10
Machine)
D) Labour Allowance on B
E) Overheads and Contractor's Profit on A+B+C+D
Page 59
7 Aluminium Fixed Glazing
Supply and fixing of aluminium fixed glazing as per drawing using standard powder coated/ anodized
aluminium section of 101.4 x 44.45 x of specified thickness fitted with 6.0mm thick / 4.0 mm thick plain
glass glazing fitted with suitable Aluminium glazing clips and approved brand silicon sealant including
cost and conveyance of all materials labour charges for manufacturing fixing in position using wooden
blocks and sheet metal screw etc. to complete for finished item of work as approved by Engineer-in-
charge
Unit - 1 sqm
A) Material requirement
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.351
2nd Class Carpenter day 0.429
Power Saw Cutter - Hand Operated - Operator day 0.039
Power Drill - Hand Operated - Operator day 0.078
Unskilled Mazdoor day 0.234
Non-technical work inspector Nos 0.078
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.312
Power Drill - Hand Operated - Hire Charges Hrs 0.624
D) Labour Allowance on B
Power charges for Motors 1%
E) Overheads and Contractor's Profit on A+B+C+D
8 Aluminium Partition partly glazed
Supply and fixing of aluminium Partition partly glazed as per drawing using standard powder coated/
anodized aluminium section of 101.4 x 44.45 of specified thickness fitted with 12.0mm thick Particle
Boards - Prelaminted up to 2.1 M height and balance height provided with 5.0 mm thick plain glass
glazing fitted with suitable Aluminium glazing clips and approved brand silicon sealant including cost
and conveyance of all materials labour charges for manufacturing fixing in position using wooden
blocks and sheet metal screw etc. to complete for finished item of work as approved by Engineer-in-
charge
Unit - 1 sqm
A) Material requirement
ALUMINIUM SECTION Kgs as per design
PARTICLE BOARD - Prelaminted sqm as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.434
2nd Class Carpenter day 0.434
Power Saw Cutter - Hand Operated - Operator day 0.043
Page 60
Power Drill - Hand Operated - Operator day 0.058
Unskilled Mazdoor day 0.145
Non-technical work inspector Nos 0.072
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.347
Power Drill - Hand Operated - Hire Charges Hrs 0.463
D) Labour Allowance on B
Power charges for Motors 1%
E) Overheads and Contractor's Profit on A+B+C+D
9 Aluminium Anodized Casement windows
Unit - 1 sqm
Supply and fixing Aluminium Anodized Casement windows as per approved drawing with aluminium
anodized sections of Series C Jindal or approved equivalent make Hollow sections and outer frame of
8804 of size 46 x 44 mm, Shutter frame of 8802 of size 44 mm x 46 mm and Mullion frame of 8803 of
size 59 x 38 and glazing section of 4433 with plain clear float glass 6 mm thick fixed including supply
and fixing aluminium powder coated 1 No. of casement friction stay hinges for each shutter, 1 Nos.
aluminium handles of 150 mm for each shutter and all labour charges for fixing the fixtures with
required no. of screws, bolts and nuts and including labour charges for fixing the frame in position,
fixing shutter to frame etc. completed for finished item of work
Unit - 1 sqm
A) Material requirement
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Alum Anodized PC Friction stay casement hinges Each as per design
Alum Anodized PC Handles Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.10
2nd Class Carpenter day 0.30
Power Saw Cutter - Hand Operated - Operator day 0.10
Power Drill - Hand Operated - Operator day 0.10
Unskilled Mazdoor day 0.30
Non-technical work inspector Nos 0.10
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.80
Power Drill - Hand Operated - Hire Charges Hrs 0.80
D) Labour Allowance on B
Power charges for Motors 1%
E) Overheads and Contractor's Profit on A+B+C+D
BASIC COST per 1 sqm
10 Aluminium Two/ Three Track Sliding Windows
Page 61
Supply and fixing Aluminium Anodized Two/ Three Track Sliding Windows as per approved drawing
with aluminium anodized sections of Series C Jindal or approved equivalent make sections and outer
frame top horizontals & both verticals of 8774 of size 62 x 29.5 mm and bottom horizontal - two track
frame of 8773 of size 62 x 29.5 mm, Shutter frame top, bottom and verticals of 8304 of size 50 mm x
20 mm and Weather interlocking frame of 8306 of size 50 x 20 with plain clear float glass 5 mm thick
fixed including supply and fixing aluminium handles of 100 mm for each shutter, nylon rollers assembly
and all labour charges for fixing the fixtures with required no. of screws, bolts and nuts and including
labour charges for fixing the frame in position, fixing shutter to frame etc. completed for finished item of
UNIT 1 sqm
A) Material requirement
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Aluminium Anodized PC Handles Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.096
2nd Class Carpenter day 0.289
Power Saw Cutter - Hand Operated - Operator day 0.096
Power Drill - Hand Operated - Operator day 0.096
Unskilled Mazdoor day 0.289
Non-technical work inspector Nos 0.096
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.771
Power Drill - Hand Operated - Hire Charges Hrs 0.771
D) Labour Allowance on B
Power charges for Motors 1%
E) Overheads and Contractor's Profit on A+B+C+D
11 Aluminium Anodized Doors - Single Shutter
Supply and fixing Aluminium Anodized Doors - Single Shutter as per approved drawing with aluminium
anodized sections of Jindal or approved equivalent make sections and outer frame top horizontals &
both verticals of 2408 of size 101.6 x 44.75 of specified thickness Shutter frame top, bottom and
verticals of 4504 of size 44.45 mm x 47.62 mm of specified thickness and Middle lock rail of 4621 of
size 49.91 x 44.45 x 3 mm with plain clear float glass 5 mm thick fixed including supply and fixing
aluminium handles of 100 mm for each shutter, floor springs/ hydraulic door closure assembly and all
labour charges for fixing the fixtures with required no. of screws, bolts and nuts and including labour
charges for fixing the frame in position, fixing shutter to frame etc. completed for finished item of work
UNIT 1 sqm
A) Material requirement
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Aluminium Anodized PC Handles Each as per design
Hydraulic Floor Spring/ Door Closure Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.099
Page 62
2nd Class Carpenter day 0.198
Power Saw Cutter - Hand Operated - Operator day 0.099
Power Drill - Hand Operated - Operator day 0.099
Unskilled Mazdoor day 0.297
Non-technical work inspector Nos 0.099
Page 63
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.793
Power Drill - Hand Operated - Hire Charges Hrs 0.793
D) Labour Allowance on B
Power charges for Motors 1%
E) Overheads and Contractor's Profit on A+B+C+D
12 Melamine polishing on wood work
Supply & applying Melamine Polish Glossy/ Matt finish to the wood works duly cleaning the surface and
applying emery paper, Sand the wood with 180 No., emery paper and then with 320 No., emery paper,
clean & wipe off loose dust, applying suitable knifing paste filler / wood filler by putty knife / muslin pad,
air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper, apply two component wood sealer, air
dry for 24 hrs, Sand with 320 No emery paper, applying one coat of approved spraying thinner (for
spraying)/ applying one coat of approved brushing thinner or general purpose thinner (for brushing) and
apply (either with spray or brush) two coats of approved brand melamine including cost & labour
charges, emery papers, cost of thinner & melamine polish of approved brands such as Jenson &
Nicholson, Asian Paints, Berger Paints or equivalent etc., complete for finished item of work
Unit = 1 SQM
A) MATERIALS :
Melamine polish L 0.065
Thinner for Melamine polish L 0.033
B) LABOUR
Painter day 0.8
Helper day 0.8
Sundries for Spraying Machine etc., LS
C) Labour Allowance on B
D) Overheads and Contractor's Profit on A+B+C
13 Poly-Urethane (PU)polishing on wood work
Supply & applying Poly-Urethane Water Proof Polish Glossy/ Matt finish to the wood works duly
cleaning the surface and applying emery paper, Sand the wood with 180 No., emery paper and then
with 320 No., emery paper, clean & wipe off loose dust, applying suitable knifing paste filler / wood filler
by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper, applying two
component wood sealer, after the surface preparation applying one coat of approved spraying PU
thinner (for spraying) / applying one coat of approved brushing PU thinner or general purpose thinner
(for brushing) and apply one coat of PU by brush or spray, air-dry overnight, Sand again with 180 No.
emery paper and removing dust, applying second coat of PU, air drying for 4 - 6 Hrs, Sand with 320 No
emery paper, and applying (either with spray or brush) two coats of approved brand PU including cost
& labour charges, emery papers, cost of thinner & PU of approved brands such as Jenson & Nicholson,
Asian Paints, Berger Paints or equivalent etc., complete for finished item
Unit = 1 SQM
A) MATERIALS :
Poly-Urethene Polish - Interior Grade L 0.065
Thinner for Polyurethane polish L 0.033
B) LABOUR
Painter day 0.80
Helper day 0.80
Sundries for Spraying Machine etc., LS
C) Labour Allowance on B
Page 64
D) Overheads and Contractor's Profit on A+B+C
14 Plastic Emulsion paint-1 coat-Internal Walls
Painting to new walls with 1 coat of plastic emulsion paint of approved brand and shade after
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including
cost and conveyance of all materials to work site and all operational, incidental, labour charges etc.
complete for finished item of work as per SS 911 for internal walls
B) LABOUR
Painter - 1st Class day 0.36
Painter - 2nd class day 0.84
Sundries for Spraying Machine etc., LS
C) Labour Allowance on B
D) Overheads and Contractor's Profit on A+B+C
16 Plastic Emulsion paint-1 coat-External Walls
Painting to new walls with 1 coat of plastic emulsion paint of approved brand and shade after
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including
cost and conveyance of all materials to work site and all operational, incidental, labour charges etc.
complete for finished item of work as per SS 911 for External walls
Page 65
D) Overheads and Contractor's Profit on A+B+C
Page 66
17 Plastic Emulsion paint-2 coats-External Walls
Painting to new walls with 2 coats of plastic emulsion paint of approved brand and shade after
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including
cost and conveyance of all materials to work site and all operational, incidental, labour charges etc.
complete for finished item of work as per SS 911 for external walls
Total cost for 10 sqm
A) MATERIALS :
Plastic Emulsion paint (at 20 sqm / liter as per
L 0.80 194.00 155.20
British Paints (I) Ltd.
B) LABOUR
Painter - 1st Class day 0.21 580.00 121.80
Painter - 2nd class day 0.49 460.00 225.40
Mazdoor day 1.5 420.00 630.00
Sundries for Spraying Machine etc., LS 195.44
C) Labour Allowance on B
D) Overheads and Contractor's Profit on A+B+C 1327.84
18 Providing Putty to internal walls
Providing and applying synthetic plaster putty or plaster of paris putty or lime punning of average 1 to 2
mm thickness over plastered surface to prepare the surface even and smooth after thoroughly brushing
the surface to remove all dirt and remains of loose powdered materials, applying emery paper, Sand
the surface, clean & wipe off loose dust, applying knifing paste filler by putty knife / muslin pad, air dry
for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the surface preparation including cost and
conveyance of all materials to work site and all operational, incidental, labour charges etc. complete for
finished item of work for Internal walls
Page 67
Mazdoor Day 1.82
Labour for access scaffold Sqm 10.00
C) Labour Allowance on B
Access scaffold as per Buildings SoR (Cumulative rates for Sqm 10.00
higher floors)
D) Overheads and Contractor's Profit on A+B+C
20 Boring for Cast-in-Situ piles
Augoring and boring of holes in site for Bored cast-in-situ R.C.C. Piles for building foundations in
loamy, clayey soils like Black cotton soils and ordinary soils without under reams as per IS 2911 - 1980
as per approved designs including all operations, incidental, labour charges, hire charges of
machinery, augur bore drill and shell equipment, etc, complete for all depths and for finished item of
work for piles of following diameters.
a up to 300 mm dia
Total cost for 1 RM
A. MATERIALS :
Nil
B. LABOUR
A. MATERIALS :
Nil
B. LABOUR
Mazdoor Day 0.631
C) Labour Allowance
D) Overheads and Contractor's Profit
Page 68
21 Under Reaming for Cast-in-Situ piles
Under-reaming for Bored cast-in-situ R.C.C. Piles for building foundations in loamy, clayey soils
like Black cotton soils and ordinary soils with Augoring and boring equipment in site as per IS 2911 -
1980 as per approved designs including all operations, incidental, labour charges, hire charges of
machinery, augur bore drill and shell equipment, etc, complete for all depths and for finished item of
work for piles of following diameters.
Page 69
Amount
Index-code S. No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
RBR-FNDN-1 1 Excavation for Structures
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable material as per Technical Specification 305
MORD / 304 MORTH
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and
301.2.1 of MORT&H
(I) Ordinary soil
(A) Manual Means
(i) Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64 250.00 910.00
Add 20% MA on Labour 182.00
Cost for 10 cum = a+b+c 1092.00
Rate per cum = (a+b+c)/10 109.20
2 Filling in foundation trenches as per drawing and technical specification Clause 305.3.9
RBR-FNDN-2
MORD & 304 MORTH
I Sand filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 250.00 77.50
b) Material
Sand cum 1.00
Water KL 0.10
I P.C.C grade M 10
(i) Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22
Coarse sand cum 0.45
40 mm aggregate cum 0.90
Water kl 1.20 90.00 108.00
(b) Labour
Mate day -
Mason (1st Class) day 0.10 315.00 31.50
Mazdoor (Unskilled) day 1.39 250.00 347.50
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity hour 0.40 200.80 80.32
fitted with water measuring device and preferably
also with load cell.
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
Mate day -
Mason (1st class) day 5.00 315.00 1575.00
Mason (2nd class) day 5.00 285.00 1425.00
Mazdoor (Unskilled) day 150.00 250.00 37500.00
Mazdoor (Skilled) day 6.00 250.00 1500.00
Surveyor day 2.00 600.00 1200.00
Mazdoor (Semi-Skilled) day 6.00 250.00 1500.00
Blacksmith for cutting of dowel bars including
removal of burrs, fabrications & fixing of dowel day 1.00 250.00 250.00
bars.
b) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 hour 36.00 281.70 10141.20
mixers) with weigh batcher and suitable
capacity calibrated water tank
Needle vibrator 40 mm ( petrol ) hour 9.00 132.70 1194.30
Screed vibrator hour 9.00 95.50 859.50
Plate shearing machine up to 12 mm hour 9.00 40.00 360.00
Concrete joint cutting machine for initial & final hour 4.00 0.00 0.00
cuts
Water tanker 8 kl capacity hour 3.75 1168.50 4381.88
Air Compressor (1 hour initial + 1 hour final) hour 2.00 277.85 555.70
c) Material
d) Formwork @ 3% of (a+b+c)
e&f) Overheads & Contractors Profit
Cost for 75 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/75
44.55
24.75
2.04
80 Flooring withParking Tiles 20mm thick ( medium Shade) set over base coat of cement
mortar (1:6), 12 mm thick over CC bed already laid or RCC roof slab, including neat
BLD- cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with
CSTN-7- white cement paste mixed with pigment of matching shade to full depth, including cost of
10 all materials like cement, sand water and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of work, but excluding the cost of conveyance of
all materials
Unit = 10 sqm
A. MATERIALS:
BMTC 08 Parking Tiles 20mm thick ( medium Shade) sqm 10.05 305.00 3065.25
Cement for CM (1:6) for base coat kg. 28.80 6400.00 184.32
White cement for jointing & pointing kg. 6.00 27.00 162.00
B. LABOUR 0.00
11.1.4 Supply and erecting approved make centrifugal water pump with impeller, priming funnel
cork, companion metallic flanges, with bolts and nuts and mounted on a common shaft of
high efficient squirrel cage Induction motor totally enclosed and fan cooled type suitable
Bldngs_E to operate on 230V, Single phase, 50Hz.. 1440 RPM A.C.Supply of 2.0 HP exculding
lec-11-1 suction / delivery pipe with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
ELEC 1HP Single Phase Monoblock each 1 7455.00 7455.00
5.4.41
Transportation Charges on Unit Cost 2% 149.1
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
ELEC 8.1.83 Skilled Fitter day 0.5 385.00 192.50
Helper day 1 345.00 345.00
Plumber day 0.5 440.00 220.00
Sundries and rounding off LS
Add MA @20% 151.50
8513.10
Add 13.615% 1159.059
9672.16
S/f of 40mm dia Nominal Bore GI Pipe Medium Grade properties &Weight asper IS 1239
ISI mark with GI fittings Incl the cost of pipe & Fittings & Labour charges
S/f of Gunmetal (GM) Ball valve with SS ball and SS Spindle as per IS Class I Indian
make heavy type 25mm NB Size incl cost of Pipe
Gunmetal (GM) Ball valve with SS ball and SS Spindle
as per IS Class I Indian make heavy type 25mm NB
BMW F59 Size 912
BMW F60 Labour charges 54.00
Add MA @20% 10.80
922.80
Andhra Pradesh Standard Data
Buildings
Amount
Index-code S No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
BLD-CSTN-1 MORTARS
BLD-CSTN-1-3 1 Cement Mortar (1 : 2)
Unit : 1cum
A. MATERIALS:
Cement kg. 720.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 215.00 43.00
Grand Total
BLD-CSTN-1-4 2 Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement kg. 480.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 215.00 43.00
Grand Total
BLD-CSTN-1-5 3 Cement Mortar (1 : 4)
Unit : 1cum
A. MATERIALS:
Cement kg. 360.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 215.00 43.00
Grand Total
BLD-CSTN-1-6 4 Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement kg. 288.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 215.00 43.00
Grand Total
BLD-CSTN-1-7 5 Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement kg. 240.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 215.00 43.00
Grand Total
BLD-CSTN-1-8 6 Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement kg. 180.00
Sand (including 5% wastage) cum 1.05
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 215.00 43.00
Grand Total
BLD-CSTN-2 CONCRETE, DAMP PROOF COURSE & REINFORCEMENT
BLD-CSTN-2-1 7 Plain Cement concrete Grade M20 - Nominal Mix
using 20mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement Kg 400.00
Coarse aggregate 20mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
B. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 2.36 215.00 507.40
Water (including for curing) kl 1.20 77.00 92.40
Grand Total
Note : For Nominal Mix : Considering table 9 IS 456 : 2000, the quantity of cement needed is 405 kgs
/ cum. Hence proposed 400 kgs of cement for cum of CC M20
BLD-CSTN-2-4 8 Plain Cement concrete (1:4:8) using 40 mm metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 4.70
Coarse aggregate 40 mm cum 0.90 1670.85
Fine aggregate (Sand) cum 0.45 775.90
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 88.00
B. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 2.36 215.00 507.40
Grand Total 535.90
9 Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture. All work upto plinth
BLD-CSTN-2-5 level.
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 4.70 761.40
Coarse aggregate 40 mm cum 0.90 1457.60 1311.84
Fine aggregate (Sand) cum 0.45 762.40 343.08
Seigniorage charges for C.A cum 0.90 0.00
Seigniorage charges for F.A cum 0.45 0.00
Water (including for curing) kl 1.20 88.00 105.60
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 626.60 626.60
C. LABOUR:
Mason 1st class day 0.10 585.00 58.50
Mazdoor (unskilled) day 1.39 490.00 681.10
Water Charges 1% -
Grand Total 3888.12
BLD-CSTN-3-13 10 R.C.C. M-20 Nominal Mix
NEW RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to Table 9 of IS
456 using 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication charges for finished item of work, but
excluding centering, shuttering.
BLD-CSTN-3-1 19 I Brick Masonry in CM (1:6) with 2nd class Bricks traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement kg 48.00
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
Mason 1st class day 0.24 550.00 132.00
Mason 2 class
nd day 0.56 500.00 280.00
Mazdoor (unskilled) day 1.89 460.00 869.40
Grand Total
20 11.5 cm wide Brick masonry for super-structure on ground floor in cm (1:3) using second class
traditional size bricks including cost of all materials, seigniorage charges, labour and all
BLD-CSTN-3-3 operations for constructing half brick masonry, mixing cement mortar, curing etc., complete for
finished item of work, but excluding conveyance charges of materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size nos 565.00
23x11x7cm
Cement kg. 106.00
Sand cum 0.22
Seigniorage charges for sand cum 0.22
B. LABOUR:
Mason 1st class day 0.60 224.00 134.40
Mason 2 class
nd day 0.60 206.00 123.60
Mazdoor (unskilled) day 2.75 170.00 467.50
Add water charges 1% 1.00%
Grand Total
BLD-CSTN-5 POINTING
BLD-CSTN-5-1 21 Flush Pointing with CM (1:3) to Brick / CRS Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40
Fine aggregate (Sand) cum 0.03
Seigniorage charges for F.A cum 0.03
B. LABOUR:
Mason 2nd class day 0.50 206.00 103.00
Mazdoor (unskilled) day 0.74 170.00 125.80
Grand Total
BLD-CSTN-6 PLASTERING
BLD-CSTN-6-1 22 Plastering with CM (1:3), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.45
Mason 2ndt class day 1.05
Mazdoor (unskilled) day 2.80
Grand Total
BLD-CSTN-6-2 23 Plastering with CM (1:4), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.15
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.45
Mason 2ndt class day 1.05
Mazdoor (unskilled) day 2.80
Grand Total
BLD-CSTN-6-3 24 Plastering with CM (1:5), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5) cum 0.150
Seigniorage charges for F.A cum 0.150
B. LABOUR:
Mason 1st class day 0.45
Mason 2nd class
t day 1.05
Mazdoor (unskilled) day 2.80
Grand Total
BLD-CSTN-6-8 25 Plastering with CM (1:3), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.210
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 1st class day 0.45
Mason 2ndt class day 1.05
Mazdoor (unskilled) day 2.80
Grand Total
Note : When Mortar mix is changed proportionate quantity of cement has to be substituted
26 RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh & nominal reinforcement as
directed by Engineer-in-charge with dubara sponge finishing, including cost & conveyance of all
materials to site, seigniorage charges, sales & other taxes on all materials, operational & incidental,
cost and conveyance of cement, wire mesh, water to work site, centering, scaffolding and form work,
BLD-CSTN-6-11 lift charges etc., complete for finished items of work but excluding cost of steel & its fabrication
charges, for finished item of work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop) sqm 13.30
Unit = 10 sqm
A. MATERIALS:
Polished Shabad Stone (White) (0.457 x 0.457m) sqm 11.00
SSR item No. (36)
Cement for CM (1:8) proportion for base coat kg. 21.60
Cement for slurry kg. 33.00
Cement for jointing kg. 20.00
Sand for CM (1:8) proportion cum 0.12
Seigniorage charges of sand cum 0.12
B. LABOUR:
Mason 1st class day 3.10 224.00 694.40
Mason 2nd class day 1.10 206.00 226.60
Mazdoor (unskilled) day 0.86 170.00 146.20
Add water charges 1%
Grand Total
28 Flooring with 40 mm thick Rough Cuddapah/Shabad stones, set over base coat of cement
mortar (1 : 8) 12 mm thick over CC bed already laid or RCC roof slab, including pointing with
cement mortar 1:3 duly filling joints nearly, including cost of all materials like flooring stone,
BLD-CSTN-7-2 cement, sand, and water etc., complete, including seigniorage charges, labour charges for
dressing of flooring stones etc., complete for finished item of work, but excluding the cost of
conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm thick) sqm 10.50
(0.457 x 0.457 m)
Cement for CM (1:8) proportion for base coat kg. 21.60
Cement for CM 1:3 proportion for pointing kg. 9.60
Sand for CM (1:8) proportion cum 0.12
Sand for CM (1:3) proportion cum 0.02
Seigniorage charges of sand cum 0.14
B. LABOUR:
Mason 1st class day 0.960 224.00 215.04
Mason 2nd class day 2.240 206.00 461.44
Mazdoor (unskilled) day 3.30 170.00 561.00
Add water charges 1%
Grand Total
29 Flooring with 100mm thick Cement Concrete 1:6:10, using 40mm metal, 100mm thick and 20 mm Cement
BLD-CSTN-7-14 Concrete surface (Ellis Pattern, 1st Sort)
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer cum 1.000
Stone Chippings 3.34 mm - 10 mm cum 0.250
Cement kg 120.000
B. LABOUR
Mason 1st class day 0.150 224.00 33.60
Mason 2nd class day 0.350 206.00 72.10
Mazdoor (unskiled) day 5.40 170.00 918.00
Add water charges 1% 1.00%
Grand Total
30 Flooring with Cement Concrete 1:6:10, using 40mm metal, 100mm thick and plastered over with
BLD-CSTN-7-15 12 mm thick in CM(1:3)
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer cum 1.00
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick sqm 10.00
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
White cement for jointing & pointing kgs 6.00 18.00 108.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason 1st class day 0.77 224.00 172.48
Mazdoor (unskiled) day 0.80 170.00 136.00
Grand Total
33 Providing skirting to internal walls to 15 cm height/risers of steps with 25 mm thick polished
Cuddapah stone length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick
with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed
with white cement paste mixed with pigment of matching shade to full depth, including cost of
BLD-CSTN-7-22 all materials like Cuddapah stone, cement, sand and water etc., complete including seigniorage
charges, etc., complete for finished item of work, but excluding the cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Cuddapah stone sqm 10.10
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 0.96 224.00 215.04
Mason 2nd class day 2.24 206.00 461.44
Mazdoor (unskiled) day 3.10 170.00 527.00
Add water charges 1% 1.00%
Grand Total
34 Flooring with Gravel 150 mm thick including cost of all materials, labour, watering etc.,
BLD-CSTN-7-25 complete
Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage) cum 1.53
B. LABOUR
Man mazdoor day 1.10 170.00 187.00
Woman mazdoor day 0.50 170.00 85.00
Grand Total
35 Reinforced cement Concrete Roofing 100 mm thick with CC (M 20) using 20 mm graded metal
BLD-CSTN-8-17 with Imprevious Coat with 12 mm thick Plastering in CM (1:3) with 1 kg. of Impermo Compound
or ACCO Proof per Bag of Cement and laid when slab is Green.
Unit = 10 sqm
Reinforced Concrete Roofing slab 100 mm thick 10 sqm 1.000
(for rate - vide relevant schedule item)
Centering Charges 10 sqm 1.000
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 cum 0.210
Water proof compound kg 2.000 24.00 48.00
B. LABOUR
Mason 1st class day 0.660 224.00 147.84
Mason 2nd class day 1.540 206.00 317.24
Mazdoor (unskiled) day 3.70 170.00 629.00
Grand Total 1142.08
BLD-CSTN-9 WHITE WASHING, COLOUR WASHING & DISTEMPERING
134 White washing two coats with whiting of approved quality to give an even shade after
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials
BLD-CSTN-9-5 including cost of all materials, labour charges and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / kg 2.00 490.00 39.20
Total 200.77
BLD-CSTN-9-8 137 Colour Washing, Two Coats
255 Unit: 10 sqm
Rate for "White Washing" two coats 10 sqm 1.00
Unit: 10 sqm
A. MATERIALS :
Distemper kg 1.34 53.00 71.02
B. LABOUR
Painter day 0.50 480.00 240.00
Mazdoor (unskilled) day 1.30 320.00 416.00
Sundries including brushes, ladders, etc., 0.01 7.27
Total cost for 10 sqm 734.29
139 Distempering, 2 Coats with Oil Bound
BLD-CSTN-9-10 257 Distemper
Unit: 10 sqm
A. MATERIALS :
Distemper kg 1.70 90.00 136.00
B. LABOUR
Painter day 1.20 480.00 576.00
Sundries including brushes, ladders, etc., 1.000% 7.12
Total cost for 10 sqm 719.12
BLD-CSTN-10 PAINTING & VARNISHING
142 Painting Walls with Snowcem or other equal and approved Water Proof Cement Paint over
BLD-CSTN-10-3 284 Priming Coat, One Coat (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg kg 2.000 42.68 85.36
B. LABOUR
Painter day 0.300 535.00 160.50
Mazdoor (unskilled) day 1.500 370.00 555.00
Sundries including brushes, etc., 1.000% 8.01
Total cost for 10 sqm 808.87
143 Painting Walls with Snowcem or other equal and approved Water Proof Cement Paint over
BLD-CSTN-10-4 285 Priming Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg kg 3.500 42.68 149.38
B. LABOUR
Painter day 0.500 535.00 267.50
Mazdoor (unskilled) day 1.500 370.00 555.00
164.50
Sundries including brushes, etc., 1.000% 9.72
Total cost for 10 sqm 1146.10
145 Painting, Priming Coat on New Wood Work
BLD-CSTN-10-6 268
Unit: 10 sqm
A. MATERIALS :
Wood Primer L 0.700 110.00 77.00
B. LABOUR
Painter day 0.700 224.00 156.80
Sundries including brushes, soap, putty etc., 1.000% 2.34
Total cost for 10 sqm 236.14
146 Painting, Priming Coat on New Iron Work
BLD-CSTN-10-7 269
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer L 0.70 100.00 70.00
B. LABOUR
Painter day 0.70 224.00 156.80
Sundries including brushes, soap, putty etc., 2.27
Total cost for 10 sqm 229.07
iii Painting with Synthetic Enamel paints - Two
BLD-CSTN-10-12 Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per L 1.200 180.00 216.00
British Paints (I) Ltd.
B. LABOUR
Painter day 1.200 224.00 268.80
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm 484.80
iv Painting with Synthetic Enamel paints - Two
Coats - For Old Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per L 1.100 180.00 198.00
British Paints (I) Ltd.
B. LABOUR
Painter day 1.100 224.00 246.40
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm 444.40
v Painting with Synthetic Enamel paints - Two
Coats - For New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per L 1.100 180.00 198.00
British Paints (I) Ltd.
B. LABOUR
Painter day 1.100 224.00 246.40
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm 444.40
BLD-CSTN-11 WOOD WORK, ALUMINUM DOORS, WINDOWS, VENTILATORS Etc.,
BLD-CSTN-11-1 155 Best Teak Wood wrought and put up to 2 meters (Schedule Item No 286)
Unit = 1 cum
Materials :—
Teak wood large scantlings upto 2 m cum 1.000 #REF! #REF!
Labour :—
Carpenter day 17.700 224.00 3964.80
Man Mazdoor day 8.800 170.00 1496.00
Add 20% MA 1092.16
6552.96
Sundries including nails, screws etc., LS 20.00
Cost per cum #REF!
156 Best Teak Wood wrought and put up over 2 metres and below 3 metres in length (Schedule Item
BLD-CSTN-11-2 No 287)
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and below 3 cum 1.000 #REF! #REF!
m in length
Labour :—
Carpenter day 17.700 224.00 3964.80
Man Mazdoor day 8.800 170.00 1496.00
Sundries including nails, screws etc., LS 20.00
Cost per cum #REF!
161 Furniture - Iron - for External doors (Schedule
BLD-CSTN-11-7 Item 292)
Top Tower bolts (Ave : Size) Nos 2 69.00 138.00
Bottom Tower bolts 150mm long Nos 2 27.00 54.00
Parliament hings with screws Nos 6 31.00 186.00
Oxidised aldrop with bolts Nos 1 124.00 124.00
Wind cleats with hings Nos 2 34.00 68.00
(Same for all doors) 570.00
162 Furniture - Iron - Internal doors (Schedule Item
BLD-CSTN-11-8 293)
Top Tower bolts (Ave : Size) Nos 1 69.00 69.00
Bottom Tower bolts 150mm long Nos 2 27.00 54.00
Butt hings with screws Nos 6 31.00 186.00
Wind cleats with hings Nos 2 34.00 68.00
(Same for all doors) 377.00
165 Framed and Planked Doors (Schedule Item No.
BLD-CSTN-11-11 296)
i 1000 x 2000 mm
*Teak wood cum 0.107 #REF! #REF!
Labour, wrought and putup in position frame & sqm 2.000 6552.96 1310.59
shutters
Sundries inclusive of putty, brads, hold fasts and LS 570.00
wind appliances and screws for planks (Vide
standard specification)
Total for each door #REF!
ii 1200 x 2100 mm
*Teak wood cum 0.127 #REF! #REF!
Labour, wrought and putup in position frame & sqm 2.520 6552.96 1651.35
shutters
Sundries inclusive of putty, brads, hold fasts and LS 570.00
wind appliances and screws for planks (Vide
standard specification)
Total for each door #REF!
* Note : Average rate for respective size
scantlings and rough planks.
BLD-CSTN-11-1 155 Best Sal Wood wrought and put up to 2 meters (Schedule Item No 286)
Unit = 1 cum
Materials :—
Sal wood large scantlings upto 2 m cum 1.000 44144.00 44144.00
Labour :—
Carpenter day 17.700 420.00 7434.00
Man Mazdoor day 8.800 320.00 2816.00
Add 20% MA 2562.50
12812.50
Sundries including nails, screws etc., LS 20.00
Cost per cum 56976.50
166 Country wood Framed and Planked Doors
BLD-CSTN-11-12 (Schedule Item No. 297)
Single Shutter :
i 1000 x 2000 mm
Country wood cum 0.107 56976.50 6096.49
Labour, wrought and putup in position frame & sqm 2.000 12812.50 2562.50
shutters
Sundries inclusive of putty, brads, hold fasts and LS 570.00
wind appliances and screws for planks (Vide
standard specification)
Total for each door 9228.99
ii 1200 x 2100 mm
Country wood cum 0.127 56976.50 7236.02
Labour, wrought and putup in position frame & sqm 2.520 12812.50 3228.75
shutters
Sundries inclusive of putty, brads, hold fasts and LS 570.00
wind appliances and screws for planks (Vide
standard specification)
Total for each door 11034.77
BLD-CSTN-11-21 175 Windows Panelled (Schedule Item No. 306)
B Double Shutter
i 800 x 1200 mm
*Sal wood cum 0.051 44144.00 2251.34
Labour, wrought and putup in position frame & sqm 0.960 12812.50 1230.00
shutters
Sundries inclusive of hold fasts and wind 212.07
appliances (Vide standard specification)
Total for each window 3693.41
ii 1000 x 1200 mm
*Sal wood cum 0.059 44144.00 2604.50
Labour, wrought and putup in position frame & sqm 1.200 12812.50 1537.50
shutters
Sundries inclusive of hold fasts and wind appliances 212.00
(Vide standard specification)
Total for each window 4354.00
iii 1200 x 1200 mm
*Sal wood cum 0.081 44144.00 3575.66
Labour, wrought and putup in position frame & sqm 1.440 12812.50 1845.00
shutters
Sundries inclusive of hold fasts and wind appliances 212.01
(Vide standard specification)
Total for each window 5632.67
*Note : Average rate for respective size
scantlings.
iv 900 x 1200 mm
**Teak wood cum 0.056 44144.00 2472.06
Labour, wrought and putup in position frame & sqm 1.080 12812.50 1383.75
shutters
Sundries inclusive of hold fasts and wind appliances 212.02
(Vide standard specification)
Total for each window 4067.83
**Note : Average rate for respective size
scantlings and rough planks.
176 Windows Panelled & Glazed (Schedule Item
BLD-CSTN-11-22 No. 307)
A Single Shutter
600 x 1200 mm
**Teak wood cum 0.036
Glass sqm 0.070
Labour, wrought and putup in position frame & sqm 0.720
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)
Total for each window
B Double Shutter
i 900 x 1200 mm
**Teak wood cum 0.052
Glass sqm 0.100
Labour, wrought and putup in position frame & sqm 1.080
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)
1 2 3 4 5 6 7
RBR-EECD-2 2 Preparation of Foundation for Embankment
i Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means
Scarifying the existing bituminous road surface to a
depth of 150 mm and disposal of scarified material with a
lift upto 3 m and lead upto 1000 m as per Technical
Specification Clause 301.4. MORD
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.260 170.00 44.20
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.250 345.00 86.25
Front end loader 1 cum bucket capacity @ 50 cum per hour 0.300 1320.00 396.00
hour
Tipper 5.5 cum capacity, 4 trips per hour hour 0.680 588.20 399.98
c&d) Overheads & Contractors Profit 115.80
Cost for 100 sqm = a+b+c+d 1042.23
Rate per sqm = (a+b+c+d)/100 10.42
ii Scarifying Existing Bituminous Surface to a Depth of 50 mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with
all lifts and lead upto 1000 m as per Technical Specification Clause 305.4.3 MORTH
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.260 170.00 44.20
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 345.00 27.60
Front end loader 1 cum bucket capacity @ 50 cum per hour 0.200 1320.00 264.00
hour
Tipper 5.5 cum capacity, 4 trips per hour hour 0.230 588.20 135.29
c&d) Overheads & Contractors Profit 58.89
Cost for 100 sqm = a+b+c+d 529.97
Rate per sqm = (a+b+c+d)/100 5.30
RBR-SBBS-10 9 II WBM Grading 2 (using Graded Metal)
(i) Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN
static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up
the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per
Technical Specification Clause 405 MORD / 404 MORTH.
1 2 3 4 5 6 7
RBR-SBBS-2 2 iii Gravel / Soil - Aggregate Base (Table 400.2) Grading C
a) Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader
on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100
kN static roller / Vibratory Roller 80-100 kN capacity to achieve the desired density, complete as per Technical
Specification Clause 402 MORD
Unit = cum
Taking output = 300 cum
a) Labour
Mate day -
Mazdoor (Skilled) day 2.40 224.00 537.60
Mazdoor (Unskilled) day 8.00 170.00 1360.00
b) Machinery
Motor grader 110 HP @ 50 cum per hour hour 6.00 2600.00 15600.00
Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00 686.84 20605.20
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.040
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400
Air compressor 210 cfm hour 1.400
Bitumen emulsion pressure distributor @ 1750 sqm/hour hour 1.000
Water tanker 6 kl capacity 1 trip per hour hour 0.500
c) Material
Bitumen emulsion (SS-1) @ 0.85 kg per sqm t 1.480
Water kl 3.000
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1750
RBR-BASC-2 2 Tack Coat
i Providing and applying tack coat with Bitumen emulsion (RS-1)
(Rapid Setting) using emulsion distributor at the rate of 0.20 to 0.25
kg per sqm on the prepared bituminous surface cleaned with
Hydraulic broom as per Technical Specification Clause 503 MORD.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.040
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400
Air compressor 210 cfm hour 1.400
Emulsion pressure distributor @1750 sqm per hour hour 1.000
c) Material
Bitumen emulsion (RS-1) @ 0.225 kg per sqm t 0.390
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
RBR-BASC-3 3 Bituminous Macadam
i Providing and laying bituminous macadam with 40-60 TPH
hot mix plant using crushed aggregates of grading as per
Table 500.4 premixed with bituminous binder, transported to
site upto a lead of 1000 m laid over a previously prepared
surface with paver finisher to the required grade, level and
alignment and rolled to achieved the desired compaction as
per Technical Specification Clause 504 MORD (using
vibratory Roller 80-100 KN for intermediate rolling and 3
wheel roller 80-100 KN for initial and final rolling).
Unit = cum
Taking output = 102.5 cum (225 t)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
Batch mix HMP 40-60 THP @ 40 t per hour actual output hour 6.000
Hydraulic broom @ 1250 sqm per hour hour 1.100
Air compressor 210 cfm hour 1.100
Paver finisher hour 6.000
Generator 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum, 10 t / 5-6 t capacity hour 6.210
Three wheel 80-100 kN static roller for initial break down hour 12.000
rolling, final and finishing rolling
Vibratory roller 80-100 kN for intermediate rolling hour 6.000
c) Material
(i) Bitumen @ 3.3 per cent of mix t 7.425
(Weight of mix = 102.5 x 2.2 = 225 t)
(ii) Aggregate
Total weight of mix = 225 t
Weight of bitumen = 7.425 t
Weight of aggregate = 225 – 7.425 = 217.575 t
Taking density of aggregate = 1.5 t/cum
Volume of aggregate = 145.05 cum
Grading (19 mm nominal size) :
25 -10 mm - 40 per cent cum 58.020
10– 5 mm - 40 per cent cum 58.020
5 mm and below - 20 per cent cum 29.010
d&e) Overheads & Contractors Profit
Cost for 102.5 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/102.5
Note : 1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the
output of 225 t considered in these analysis.
2. Quantity of bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site, including sundries have
been included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of Hydraulic broom and 2 mazdoor for the same
shall be deleted as the same has been included in the cost of tack coat.
5. Analysis is based on 1000 m lead of mixed material. Cost of additional cartage may be added as per
site requirements.
ii Providing and laying bituminous macadam with 100-120
TPH / 40-60 TPH hot mix plant producing an average
output of 75 tonnes/ 37.50 t per hour using crushed
aggregates of specified grading premixed with
bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired
compaction as per Tech. specification No. 504 MORTH.
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day -
Mazdoor working with HMP, mechanical broom, paver, roller, day 14.000
asphalt cutter and assistance for setting out lines, levels and
layout of construction
Skilled mazdoor for checking line & levels day 5.840
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour actual output hour 6.000
OR
HMP 40-60 TPH @ 17 cum (37.5 Tonnes) / hour hour 12.000
Air compressor 250 cfm hour 2.200
Paver finisher 100 TPH hour 6.000
Generator 250 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 3.900
Vibratory roller 8 tonnes for intermediate rolling. hour 3.900
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 3.900
c) Material
i) Bitumen@ 3.3 per cent of mix t 14.850
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510
25 - 10 mm 45 per cent cum 130.550
10 - 5 mm 25 per cent cum 72.530
5 mm and below15 per cent cum 43.510
or
Grading II (19 mm nominal size)
116.04 Cum of 25-10mm @ 40%
25 to 27mm IRC HBGM/C metal @ 40% cum 29.010
19 to 22mm IRC HBGM/C metal @ 10% cum 29.010
12 to 14mm IRC HBGM/C metal @ 10% cum 29.010
9.5 to 11.2mm IRC HBGM/C metal @ 10% cum 29.010
116.04 Cum of 10-5mm @ 40%
9.5 to 11.2mm IRC HBGM/C metal @ 20% cum 58.020
5 to 7mm IRC HBGM/C metal @ 20% cum 58.020
58.02 Cum of 5mm below @ 20%
5 to 7mm IRC HBGM/C metal @ 10% cum 29.010
2.36mm & below @ 10% cum 29.010
* Any one of the alternative may be adopted as per approved
design
(i) for Grading I ( 40 mm nominal size )
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
(ii) for Grading II (19 mm nominal size)
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
Note in MORTH : 1. Although the rollers are required only for 3 hours as per norms of output,
but the same have to be available at site for six hours as the hot mix plant and paver will take
six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater
for the idle period of these rollers, their usage rates have been multiplied by a factor of 0.65.
2. Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend
upon job mix formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including
sundries have been included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of Mechanical broom and 2
mazdoors for the same shall be deleted as the same has been included in the cost of tack
coat.
RBR-BASC-4 4 Built-Up Spray Grout
i Providing, laying and rolling of built-up spray grout layer over
prepared base consisting of a two layer composite
construction of crushed coarse aggregates using motor grader
for aggregates. Key stone chips spreader may be used with
application of bituminous binder after each layer, and with key
aggregates placed on top of the second layer to serve as a
base, conforming to the line, grades and cross-section
specified, the compacted layer thickness being 75 mm as per
Technical Specification Clause 505 MORD. (using Three
wheel 80-100 KN static Roller/ Vibratory Roller 80-100 kN).
A By Manual Means
Unit = sqm
Taking output = 800 sqm (60 cum)
(I) Bitumen (S-90)
a) Labour
Mate day -
Mazdoor (Unskilled) day 106.000
Chips spreader (Stone Packer) day 10.000
Bitumen Sprayer day 2.500
Mazdoor (Semi-Skilled) day 25.500
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set hour 6.000
A By Manual Means
Case – I: Using Nominal chipping size 13.2 mm
(I) Bitumen (S-90)
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate day -
Bitumen Sprayer day 1.000
Mazdoor (Unskilled) day 58.000
Mazdoor (Semi-Skilled) day 8.600
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set hour 2.250
Three wheel 80-100 kN static roller hour 2.250
Add: 0.5 per cent of (a) Labour for sundries L.S.
c) Material
Bitumen (S-90) @ 1.00 kg per sqm t 0.900
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum cum 9.000
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
(II) Bitumen (S-65)
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate day -
Bitumen Sprayer day 1.000
Mazdoor (Unskilled) day 58.000
Mazdoor (Semi-Skilled) day 8.600
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set hour 2.250
Mechanical Means
Unit = sqm
Taking output = 9000 sqm
Case 1 :-19 mm nominal chipping size
a) Labour
Mate day -
Mazdoor (Unskilled) day 9.000
Mazdoor skilled day 2.440
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200
Air compressor 250 cfm hour 7.200
Hydraulic self propelled chip spreader @ 1500 sqm/hour hour 6.000
Tipper 10 tonne capacity for carriage of stone chips from hour 6.000
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000
Bitumen pressure distributor hour 6.000
Smooth wheeled roller 8-10 tonne weight hour 6.000
c) Material
Bitumen@ 1.20 kg per sqm t 10.800
Crushed stone chipping, 19 mm nominal size @ 0.015 cum cum 135.000
per sqm
d&e) Overheads & Contractors Profit
Cost for 9000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/9000
Case 2 : 13 mm nominal size chipping
a) Labour
Mate day -
Mazdoor (Unskilled) day 9.000
Mazdoor skilled day 2.440
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200
Air compressor 250 cfm hour 7.200
Hydraulic self propelled chip spreader @ 1500 sqm per hour hour 6.000
Tipper 10 tonne capacity for carriage of stone chips from hour 6.000
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000
Vibratory roller 8-10 tonne weight hour 6.000
c) Material
Bitumen@ 1.00 kg per sqm t 9.000
Crushed stone chipping,13 mm nominal size @ 0.01 cum per cum 90.000
sqm
d&e) Overheads & Contractors Profit
Cost for 9000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/9000
Note : 1. Where the proposed aggregate fails to pass the stripping test, an approved adhesion agent may
be added to the binder as per clause 510.2.4. Alternatively, chips may be pre-coated as per clause 510.2.5
2. Input for the second coat, where required, will be the same as per the Ist coat mentioned above
Case 3 : Using 6 mm nominal size chipping
ii Providing and laying surface dressing in single coat
using 6 mm nominal size IRC HBG machine crushed
stone aggregates @ 0.004 cum / sqm on a layer of
bitumen binder of 80/100 grade @ 0.75 kg / sqm laid on
prepared surface and rolling with 8-10 T Power Road
Roller etc., complete for finished item of work as per
MoRT&H Specification 510 (4th Revision) and as directed
by the Engineer-in-charge.
Unit = sqm
Taking output = 9000 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 9.000
Mazdoor skilled day 2.440
b) Machinery
Mechanical broom @ 1250 sqm/hr. hour 7.200
Air compressor 250 cfm hour 7.200
Hydraulic self propelled chip spreader @ 1500 sqm/hr. hour 6.000
Tipper 10Tonne capacity for carriage of stone chips from hour 6.000
stock pile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000
Bitumen pressure distributor @1750 sqm/hr hour 6.000
Smooth wheeled roller 8 Ton hour 6.000
c) Material
Bitumen 80/100 @0.75 Kg/sqm MT 6.750
or
Bitumen 60/70 @0.75 Kg/sqm MT 6.750
Crushed stone chippings 6 mm nominal size @0.004 cum 36.000
cum/sqm
d&e) Overheads & Contractors Profit
Cost for 9000 sqm = a+b+c+d (80/100 BT)
Rate per sqm = (a+b+c+d)/9000
Cost for 9000 sqm = a+b+c+d (60/70 BT)
Rate per sqm = (a+b+c+d)/9000
RBR-BASC-12 12 Surface Dressing using Bitumen Emulsion
Providing and laying surface dressing as wearing course
consisting of a layer of bitumen emulsion laid on the prepared
surface, followed by a cover of crushed stone chippings of
specified size and rolling with 80-100 kN roller including
cleaning the road surface as per Technical Specification
Clause 507 MORD.
A By Manual Means
Case – I: Nominal aggregate size 13.2 mm
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate day -
Bitumen Emulsion Sprayer day 1.000
Mazdoor (Unskilled) day 60.360
b) Machinery
Emulsion sprayer, capacity 1000 litre fitted with spray set hour 2.250
Three wheel 80-100 kN static roller hour 2.250
Add: 0.5 per cent of (a) Labour for sundries L.S.
c) Material
Bitumen Emulsion (RS-1) @ 1.50 kg per sqm t 1.350
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum cum 9.000
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
Case – II: Nominal chipping size 9.5 mm
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate day -
Bitumen Sprayer day 1.000
Mazdoor (Unskilled) day 60.360
b) Machinery
Emulsion sprayer, capacity 1000 litre fitted with spray set hour 2.000
Three wheel 80-100 kN static roller hour 2.000
c) Material
Bitumen Emulsion (RS-1) @ 1.40 kg per sqm t 1.400
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum/ sqm cum 8.000
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
B By Mechanical Means
Case – I: Nominal chipping size 13.2 mm
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 9.000
Mazdoor (Skilled) day 2.440
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 6.000
Air compressor 210 cfm hour 6.000
Hydraulic self propelled chip spreader @ 1500 sqm / hour hour 6.000
Tipper 5.5 cum - 10 t capacity for carriage of stone chips from hour 6.000
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000
Bitumen Emulsion pressure distributor hour 6.000
Three wheel 80-100 kN static roller hour 18.750
c) Material
Bitumen Emulsion (RS-1) @ 1.50 kg per sqm t 11.250
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum/sqm cum 75.000
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
Case – II: Nominal chipping size 9.5 mm
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 9.000
Mazdoor (Skilled) day 2.440
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 6.000
Air compressor 210 cfm hour 6.000
Hydraulic self propelled chip spreader @1500 sqm per hour hour 6.000
Tipper 5.5 cum - 10 t capacity for carriage of stone chips from hour 6.000
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000
Bitumen Emulsion pressure distributor hour 6.000
Three wheel 80-100 kN static roller hour 15.000
c) Material
Bitumen Emulsion (RS-1) @ 1.40 kg per sqm t 10.500
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum/sqm cum 60.000
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
Note : Where the proposed aggregate fails to pass the stripping value test, an approved adhesion agent
may be added to the binder as per Clause 507.24. Alternatively, chips may be pre-coated as per Clause
507.25.
14 i 20mm thick Open-Graded Premix Carpet using
RBR-BASC-14 Bituminous (penetration grade/modified bitumen) Binder
Unit = sqm
Taking output = 10250 sqm (205 cum)
i Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less than
75 tonnes/hour .
a) Labour
Mate day -
Mazdoor (Unskilled) working with HMP, road sweeper, paver and day 16.000
roller
Skilled mazdoor for checking line & levels day 5.840
b) Machinery
i) Batch type HMP 75 tonne per hour hour 6.000
ii) Electric Generator Set 250 KVA hour 6.000
iii) Front end loader 1 cum bucket capacity hour 6.000
iv) Tipper 10 tonne capacity t.km 450 x L
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000
iv) Smooth wheeled/tandom roller 8-10 tonnes weight hour 6.000
c) Material
Bitumen@ 14.60 kg per 10 sqm t 14.970
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm cum 276.750
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Note : If a premix sand seal coat of 'B' type is proposed, the same is required to be provided over the open
graded premix carpet immediately on the same day. As the same HMP and other machines will be used
for laying of premix sand seal coat, out of 6 effective working hours, 4.00 hours may be utilised for laying of
premix carpet and balance 2.00 hours for the seal coat. The rate for the premix sand seal coat under
clause 513 (case II) has been worked out accordingly by utilising the HMP for 2.00 hours for the purpose of
seal coat. In case type 'A' seal coat is proposed, HMP can be worked for six hours for the premix carpet as
type 'A' seal coat does not require the use of HMP.
By Manual Means
Type A
(I) Bitumen (S-90)
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 litre capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Bitumen (S-90) @ 22 kg per 10 sqm t 1.100
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(II) Bitumen (S-65)
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 litre capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Bitumen (S-65) @ 22 kg per 10 sqm t 1.100
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 litre capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Polymer Modified Bitumen @ 22 kg per 10 sqm t 1.100
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 litre capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Crumb Rubber Modified Bitumen @ 22 kg per 10 sqm t 1.100
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Natural Rubber Modified Bitumen @ 22 kg per 10 sqm t 1.100
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Bitumen (S-90) @ 19 kg per 10 sqm t 0.950
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(II) Bitumen (S-65)
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Bitumen (S-65) @ 19 kg per 10 sqm t 0.950
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Polymer Modified Bitumen @ 19 kg per 10 sqm t 0.950
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Crumb Rubber Modified Bitumen @ 19 kg per 10 sqm t 0.950
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 21.000
Mazdoor (Skilled) day 8.400
b) Machinery
Mixall 6-10 t capacity hour 6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set hour 6.000
Three wheel 80-100 kN static roller hour 6.000
c) Material
Natural Rubber Modified Bitumen @ 19 kg per 10 sqm t 0.950
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum 13.500
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
By Mechanical Means
Type A
(I) Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Bitumen (S-90) @ 22 kg per 10 sqm t 8.800
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 108.000
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Bitumen (S-65) @ 22 kg per 10 sqm t 8.800
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 108.000
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Polymer Modified Bitumen @ 22 kg per 10 sqm t 8.800
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 108.000
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Crumb Rubber Modified Bitumen @ 22 kg per 10 sqm t 8.800
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 108.000
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Natural Rubber Modified Bitumen @ 22 kg per 10 sqm t 8.800
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum 108.000
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum - 10 t / 5-6 t capacity hour 3.600
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Bitumen (S-90) @ 19 kg per 10 sqm t 7.600
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum 108.000
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Bitumen (S-65) @ 19 kg per 10 sqm t 7.600
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum 108.000
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Polymer Modified Bitumen @ 19 kg per 10 sqm t 7.600
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.000
cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Crumb Rubber Modified Bitumen @ 19 kg per 10 sqm t 7.600
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.000
cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor (Skilled) day 3.520
b) Machinery
HMP of appropriate capacity hour 6.000
Electric generator set 125 KVA hour 6.000
Tipper 5.5 cum - 10 t capacity hour 3.600
Paver finisher hour 6.000
Three wheel 80-100 kN static roller hour 18.000
c) Material
Natural Rubber Modified Bitumen @ 19 kg per 10 sqm t 7.600
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.000
cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
ii Close Graded Premix Surfacing/Mixed Seal Surfacing
Case 1 : Mechanical means using HMP of appropriate capacity not
less than 75 tonnes/hour.
Providing, laying and rolling of close-graded premix surfacing material
of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or
13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade
bitumen to the required line, grade and level to serve as wearing
course on a previously prepared base, including mixing in a suitable
plant, laying and rolling with a Smooth wheeled roller 8-10 tonne
capacity, and finishing to required level and grade as per Tech.
Specification No 512 MORTH.
A Type - A
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) working with HMP, road sweeper, paver and day 16.000
roller
Skilled mazdoor for checking line & levels day 5.840
b) Machinery
i) HMP of appropriate capacity. hour 6.000
ii) Electric Generator Set 250 KVA hour 6.000
iii) Front end loader 1 cum bucket capacity hour 6.000
iv) Tipper 10 tonne capacity t.km 450 x L
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000
iv) Smooth wheeled8-10 tonnes weight hour 6.000
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm t 22.500
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum per cum 276.750
10 sqm
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
B Type - B
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) working with HMP, road sweeper, paver and day 16.000
roller
Skilled mazdoor for checking line & levels day 5.840
b) Machinery
i) HMP of appropriate capacity. Not less than 75 t / hour hour 6.000
ii) Electric Generator Set 250 KVA hour 6.000
iii) Front end loader 1 cum bucket capacity hour 6.000
iv) Tipper 10 tonne capacity tkm 450 x L
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000
iv) Smooth wheeled8-10 tonnes weight hour 6.000
c) Material
Type - B
Bitumen @ 19 kg per 10 sqm t 19.480
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum 276.750
per 10 sqm
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
RBR-BASC-17 17 Seal Coat
i Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A, Type B and Type C as per Technical
Specification Clause 510 MORD. (using Three wheel 80-100
kN static roller)
A By Manual Means
Case - I : Type A
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate day -
Bitumen Sprayer day 1.000
Mazdoor (Unskilled) day 22.000
Mazdoor (Semi-Skilled) day 7.150
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set hour 2.200
c) Material
Natural Rubber Modified Bitumen @ 6.80 kg per 10 sqm t 0.850
Crushed sand or grit as passing 2.36 mm sieve and retained cum 7.500
on 180 micron sieve applied @ 0.06 cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250
Case - III : Type C (510 - MORD)
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate day -
Bitumen Sprayer day 1.000
Mazdoor (Unskilled) for carrying of chips & spraying day 22.000
Mazdoor (Semi-Skilled) day 6.150
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set hour 2.200
Three wheel 80-100 kN static roller hour 2.200
c) Material
Bitumen (S-90) @ 6.50 kg per 10 sqm t 0.715
Crushed stone chipping of 6.7 mm size defined as 100% cum 9.900
passing 9.5 mm sieve and retained on 2.36 mm sieve applied
@ 0.09 cum.
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(II) Bitumen (S-65)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate day -
Bitumen Sprayer day 1.000
Mazdoor (Unskilled) day 22.000
Mazdoor (Semi-Skilled) day 6.150
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set hour 2.200
Three wheel 80-100 kN static roller hour 2.200
c) Material
Bitumen (S-65) @ 6.50 kg per 10 sqm t 0.715
Crushed stone chipping of 6.7 mm size defined as 100% passing 9.5 cum 9.900
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 4.160
b) Machinery
HMP of 75 tonnes/hour. hour 2.000
Electric Generator Set 250 KVA hour 2.000
Front end loader 1 cum bucket capacity hour 2.000
Tipper 10 tonne capacity t.km 104 x 'L'
Add 10 per cent of cost of carriage to cover cost of loading and
unloading
Paver finisher hydrostatic with sensor attachment hour 2.000
Smooth wheeled 8-10 tonnes capacity hour 2.000
c) Material
Bitumen@ 6.80 kg per 10 sqm t 5.340
Crushed stone chipping of 6.7 mm size defined as passing 11.2 mm sieve 47.160
and retained on 2.36 mm sieve applied @ 0.06 cum per 10 sqm
Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor skilled day 1.440
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060
Air compressor 250 cfm hour 0.060
Mastic cooker 1 tonne capacity hour 6.000
Bitumen boiler 1500 litres capacity hour 6.000
Tractor for towing and positioning of mastic cooker and hour 1.000
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)
I) Bitumen 80 / 100 or 30/40 @ 10.2 per cent by weight of t 0.204
mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on 0.075mm cum 0.390
sieve @ 31.9 per cent by weight of mix = 2 x 31.9/100 =
0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less than 80 t 0.360
per cent by weight @ 17.92 per cent by weight of mix = 2 x
17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cent by cum 0.550
weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for skid cum 0.018
resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight = kg 0.500
0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
d&e) Overheads & Contractors Profit
Cost for 35.00 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/35
Note : 1.The rates for 50 mm & 40 mm thick layers may be worked out on pro-rata basis.
2. Where tack coat is required to be provided before laying mastic asphalt, the same is
required to be measured and paid separately.
3. The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities
shall be as per mix design.
4. This rate analysis is based on design made by CRRI for a specific case and is meant for
estimating purposes only. Actual design is required to be done for each case.
(i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day -
Mazdoor (Unskilled) day 6.240
b) Machinery
Mechanical broom hour 6.000
Air compressor 250 cfm hour 6.000
Mobile slurry seal equipment hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000
stockpile on road side to slurry equipment, bitumen emulsion
and filler.
Pneumatic tyred roller with individual wheel load not exceeding 1.5 hour 6.000
tonnes
Water tanker6 KL capacity hour 2.000
c) Material
Residual Binder (BT Emulsion - medium setting) @ 11 per t 19.360
cent of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 per cent of total cum 102.080
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5, =
153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 (Cement) t 3.520
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.000
Mazdoor skilled day 2.480
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000
Mechanical broom @ 1250 sqm per hour hour 1.280
Air compressor 250 cfm hour 1.280
Bitumen pressure distributor @ 1750 sqm per hour hour 0.910
Hot mix plant 100-120 TPH producing an average of 75 tonnes per hour 3.000
hour
Electric generator set 250 KVA hour 3.000
Front end loader 1.00 cum bucket capacity hour 3.000
Tipper 5.5 cum capacity hour 18.000
Smooth wheeled roller 8-10 tonnes hour 1.950
Vibratory roller 8 tonnes hour 1.950
Smooth wheeled tandem roller 6-8 tonnes hour 1.950
c) Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the extent of 60
per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance 193.2
tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 per t 1.987
cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x 0.04 t 7.728
= 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47 tonne
Taking average density of 1.5 tonnes/cum, total volume of
aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent cum 28.440
25 - 10 mm @ 15 per cent cum 18.550
10- 5 mm @ 20 per cent cum 24.730
Below 5 mm @40 per cent cum 49.460
Filler (cement) @ 2 % of 276 tonne = 5.52 tonnes t 5.520
d&e) Overheads & Contractors Profit
Cost for 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
Note : Although the total rolling time is only 4 hours as per norms, all the
three rollers have to be available at site for 3 hours each to match with the
output of re-cycling plant. To cater for their idling time, these have been
multiplied with a factor of 0.65.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.120
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000
Air compressor 250 cfm hour 6.000
Bitumen emulsion pressure distributor @ 1750 sqm per hour hour 6.000
c) Material
Bitumen emulsion (Medium setting) @ 0.75 kg/sqm t 7.880
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160
Mazdoor (Unskilled) for precoating of grit day 4.000
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250
Bitumen emulsion for precoating grit @ 2 per cent of t 0.790
grit,39.38 x 0.02
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b
Rate per sqm = (a+b)/10500
RBR-BASC-23 23 Bituminous Cold Mix ( Including Gravel Emulsion)
Providing, laying and rolling of bituminous cold mix on prepared base
consisting of a mixture of unheated mineral aggregate and emulsified
or cutback bitumen, including mixing in a plant of suitable type and
capacity, transporting, laying, compacting and finishing to specified
grades and levels as per Tech. Specification 519 MORTH.
Unit = cum
Taking output = 205 cum (450 tonne)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as under:-
Bitumen Emulsion 8 per cent by weight of Total Mixture
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day -
Mazdoor (Unskilled) day 16.000
Mazdoor skilled day 5.840
b) Machinery
Drum mix plant for cold mixes of appropriate capacity but not hour 6.000
less than 75 tonnes/hour.
Electric generator 125 KVA hour 6.000
Front end loader 1 cum bucket capacity hour 6.000
Tipper 10 tonne capacity t.km 450 x L
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher hour 6.000
Pneumatic tyred roller 12-15 tonnes hour 3.900
Smooth wheeled steel tandem roller 6-8 tonnes hour 3.900
c) Material
Bitumen emulsion (Medium setting) @ 8 per cent t 36.000
Filler (lime)@ 2 per cent t 9.000
Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5 cum 75.000
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
(Applicable to cases I to IV)
Note : 1. Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid separately.
3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to
be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and
paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate day -
Mazdoor (Unskilled) day 16.000
Mazdoor skilled day 5.840
b) Machinery
Hot Mix Plant of appropriate capacity but not less than 75 tonnes/hour hour 6.000
Unit = tonne
The use of modified binder is expected to result in an extended service life of bituminous
pavements subject to heavy traffic loads in extreme climatic conditions, thus justifying the
entire cost of adding modifiers/fibers. Other advantages include lower temperature
susceptibility, higher resistance to aging, higher fatigue life, higher resistance to cracking and
better adhesion between aggregates and binder.
Detailed information and inductive dose level on the use of polymer modified binder is
available in IRC : SP-53 / 2002. A number of proprietary products are now available in the
market. For such proprietary products, test reports and cost effectiveness should be the basis
for their selection in road works.
The modifier, in the required quantity shall be blended at the refinery or at central unit with all
facilities by proper industrial process, is essential. If supplied in drums it shall be agitated in
melted condition with suitable device for achieving homogeneity
Proposals to use glass fiber, polypropylene fibers or any other similar material in a bituminous
mixture should be substantiated, complete with all details including test results, manufacturer's
recommendations for addition or means of incorporating the fibers, homogeneously, without
segregation, into the mixture.
Before agreeing to the use of a fiber, it should have been proved to be satisfactory in use
under circumstances, similar to the work, elsewhere or it would have under gone appropriate
performance trials. Documented evidence of use and trials of the fiber, in any country having
conditions similar to Indian will be acceptable.
where information on use of trials is inadequate or lacking, trials may be required to be under
taken before agreeing to the use of the fiber.
Note : 1. The modified binder is usually manufactured by specialised firms as a proprietary product. The
rate for this product is required to be as certained from the market.
2.The specifications for various item of road works using polymer/rubber modified bitumens are same as
those for penetration grade bitumen except those for any special conditions which the manufacturer may
indicate
3.The other controls during mixing, laying shall be same as specified in IRC - 14, 29, 94 and 95 for open
graded premix carpet, bituminous concrete, DBM and SDBC respectively
4.The temperature of mixing and rolling will be slightly higher than conventional bituminous mixes as
indicated in Table 8 of IRC: SP: 53 - 2002
RBR-BASC-26 26 Crack Prevention Courses
i Stress absorbing membrane (SAM) crack width less than
6 mm
Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width below 6 mm after cleaning with a
mechanical broom, using modified binder complying with clause 521,
sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed
stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip
spreader, sweeping the surface for uniform spread of aggregates and
surface finished to conform to clause 902. Tech. Specification 522
MORTH.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 6.240
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000
Air compressor 250 cfm hour 6.000
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000
Hydraulic Chip spreader hour 6.000
Smooth wheeled road roller 8-10 tonne hour 6.000
c) Material
Modified binder t 9.450
Crushed stone aggregates 5.6 mm size cum 105.000
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
(ii) Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width 6 to 9 mm after cleaning with a
mechanical broom, using modified binder complying with clause 521,
sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface finished to
conform to clause 902, Tech. Specification 522 MORTH.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 6.240
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000
Air compressor 250 cfm capacity hour 6.000
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000
Hydraulic Chip spreader hour 6.000
Smooth wheeled road roller 8-10 tonne hour 6.000
c) Material
Modified binder t 11.550
Crushed stone chipping 11.2 mm size cum 105.000
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
(iii) Stress absorbing membrane (SAM) crack width above 9
mm and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing membrane
over a cracked road surface, with crack width above 9 mm and
cracked area above 50 per cent after cleaning with a mechanical
broom, using modified binder complying with clause 521, sprayed at
the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to clause 902,
Tech. Specification 522 MORTH.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 6.000
Mazdoor skilled day 2.240
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000
Air compressor 250 cfm capacity hour 6.000
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000
Hydraulic Chip spreader hour 6.000
Smooth wheeled road roller 8-10 tonne hour 6.000
c) Material
Modified binder t 15.750
Crushed stone aggregates 11.2 mm size cum 126.000
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
Note : In case 2nd coat is also required to be provided, material provided for the 2nd coat
shall be as per table 500-47.
(iv) Case-IV : Bitumen impregnated geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration and
constructed to the requirement of clause 703.4.5, Tech.
Specification 522 MORTH.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 12.000
Mazdoor skilled day 2.560
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800
Air compressor 250 cfm capacity hour 2.800
Bitumen pressure distributor @ 1750 sqm per hour t 2.000
Pneumatic roller hour 2.000
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg per sqm t 3.680
Geotextile including 10 per cent for overlaps sqm 3850.000
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note : As bitumen overlay construction shall follow closely the fabric
placement on the same day, an output of 3500 sqm only has been
considered for the analysis which will cover a length of 500 m, of 7 m wide
carriageway. This can be conveniently overlaid by a bituminous course in a
day
Unit = cum
Taking output = 205 sqm (450 tonnes)
(i) 75 mm thickness
a) Labour
Mate day -
Mazdoor (Unskilled) day 12.000
Mazdoor skilled day 6.000
b) Machinery
Drum mix plant for cold mixes 40 / 60 tonne per hour hour 9.000
producing output of 50 tonnes per hour
Electric generator 125 KVA hour 6.000
Front end loader 1 cum capacity hour 6.000
Paver finisher hydrostatic with sensor control @ 75 cum/ hour hour 6.000
Tipper 10 tonne capacity t.km 450 x L
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Pneumatic tyred roller12-15 tonnes. hour 3.900
Smooth wheeled steel roller6-8 tonnes. hour 3.900
Water tanker6 KL capacity hour 1.000
c) Material
Bitumen emulsion (MS) @ 45 litres per tonne t 20.250
Crushed stone aggregates 40 mm nominal size cum 297.000
Cost of water KL 6.000
d&e) Overheads & Contractors Profit
Cost for 205 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/205
ii 40 mm thickness
a) Labour
Mate day -
Mazdoor (Unskilled) day 12.000
Mazdoor skilled day 6.000
b) Machinery
Batch type cold mixing plant100-120 TPH capacity producing an hour -
average output of 75 tonne per hour
Drum mix plant for cold mixes 40 / 60 tonne per hour hour 9.000
producing output of 50 tonnes per hour
Electric generator 125 KVA hour 6.000
Front end loader 1 cum capacity hour 6.000
Paver finisher hydrostatic with sensor control @ 75 cum per hour 6.000
hour
Tipper 10 tonne capacity t.km 450 x L
Add 10 per cent of cost of carriage to cover cost of loading and
unloading
Pneumatic tyred roller 12-15 tonnes. hour 3.900
Smooth wheeled steel roller 6-8 tonnes. hour 3.900
Water tanker6 KL capacity hour 1.000
c) Material
Bitumen emulsion (MS) @ 70 litres per tonne t 31.500
Crushed stone aggregates 14 mm nominal size cum 287.000
Cost of water KL 6.000
d&e) Overheads & Contractors Profit
Cost for 205 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/205
iii 25 mm thickness
a) Labour
Mate day -
Mazdoor (Unskilled) day 12.000
Mazdoor skilled day 6.000
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity producing hour -
an average output of 75 tonne per hour
Drum mix plant for cold mixes 40 / 60 tonne per hour hour 9.000
producing output of 50 tonnes per hour
Electric generator 125 KVA hour 6.000
Front end loader 1 cum capacity hour 6.000
Paver finisher hydrostatic with sensor control @ 75 cum per hour 6.000
hour
Tipper 10 tonne capacity t.km 450 x L
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Pneumatic tyred roller hour 3.900
Smooth wheeled steel roller hour 3.900
Water tanker6 KL capacity hour 1.000
c) Material
Bitumen emulsion (MS) @ 85 litres per tonne t 38.250
Crushed stone aggregates 6 mm nominal size cum 270.000
Cost of water KL 6.000
d&e) Overheads & Contractors Profit
Cost for 205 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/205
Note : (Case I to III)
1. These mixes are considered suitable for minor repair work and temporary road surface
improvement.
2. In case concrete mixtures are required to be used for mixing, a number of these will be
needed to match the capacity of road rollers.
3. Tack coat, where provided, will be measured and paid separately.
4. Both the rollers have to be available at site to match with the output of batch mixing plant
and paver finisher. A multiplying factor of 0.65 has been adopted to cater for the idling period
of road rollers.
General Note :
1. The provisions towards Mate is included in the provision towards unskilled
Mazdoor upto item 2.
2. The provisions towards Mate is included in the provision towards skilled Mazdoor
from item 3.
RBR-BASC-1 Prime Coat
i Low porosity
a Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base
including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical
means as per Technical Specification Clause 502 MORD (for use on Wet mix macadam & WBM)
Unit = sqm
Taking
output
a) Labour=
1750
Mate sqm day -
Mazdoor day 1.040
(Unskilled)
b)
Machinery
Hydraulic hour 1.400
broom @
Air hour 1.400
1250
Bitumensqm
compresso hour 1.000
rper
210hour
cfm
emulsion
Water hour 0.500
pressure
tanker 6 kl
c) Material
distributor
capacity 1
trip per
Bitumen t 1.480
emulsion
(SS-1) @
0.85 kg per
sqm
Water kl 3.000
d&e)
Overheads
&
Contractor
s Profit
Cost of
1750 sqm
=
a+b+c+d+e
Rate per
sqm =
(a+b+c+d+
e)/1750
Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine
crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 80/100 grade @ 0.75 kg /
1 sqm including cost, seigniorage and conveyance of all materials to work site and laid on prepared surface
and rolling with 8-10 T Power Road Roller etc., complete for finished item of work as per MoRT&H
Specification 510 (4th Revision) and as directed by the Engineer-in-charge.
(A) Labour
Total 2040.56
(B) Machinery
7.20 hr Mechanical broom @ 1250 sqm/hr. 290.00 hr 2088.00
6.00 hr Hydraulic self propelled chip spreader @ 1500 sqm/hr. 2070.00 hr 12420.00
Tipper 10Tonne capacity for carriage of stone chips
6.00 hr from stock pile on road side to chip spreader 588.17 hr 3529.02
(Rate of Tipper 5 cum
6.00 hr Front end loader 1 cum bucket capacity 1320.00 hr 7920.00
Total 37718.58
(C) Material
(A) Labour
(C) Material
Total 13816.18
1 Sqm
Providing 20mm thick Open Geaded Bituminious Premix using 0.18Cum of 13.20mm and 0.09mm of
1.20mm IRC size HBG machine crushed Granite chips for 10Sqm premixed with bitumen of 80/100grade
at the rate of 14.60Kg/ sqm of area laid over a tack coat including cost and seigniorage of all materials and
conveyance of all materials to the site with all leads and lifts and stacking the metal to department guage
for premeasurementa and labour charges for cleaning, brushing the road surface and mechanically heating
3
the bitumen and aggregate to proper temperture and mixing the bitumen and aggregate in a mini hot mix
plant of 6-10T capacity including spreading the premix to camber consolidation with 8-10T power road
roller including all labour charges hire and operational charges of all machinery T&P barricading diversion
of traffic providing caution boards and banner flags during day time and danger lights during night time
VAT @4% etc complete for 10Sqm
Unit = sqm
Taking output = 500 sqm
(A) Labour
1.35 nos. Male 188.00 day 253.80
21.00 nos. Mazdoor 146.00 day 3066.00
6.00 nos. Hot Mazdoor 146.00 day 876.00
Total A 4195.80
(B) Machinary
4.00 hr Mini Hot mix plant 6 to 10T 279.23 hr 1116.92
3.00 hr Bitumen boiler 1.5 T oil fired 170.00 hr 510.00
6.00 hr Power roller 8-10T 540.00 hr 3240.00
Total 4866.92
Sundries such as maintanance of diversion traffic
4386.92*
control sign boards etc., and for quality control on B 24.33
0.50/100
above @ 0.50%
Misllaneous items such as spray nozzle tarring outfit,
Ls 25.00
joint paper, burnal, soap, coconut oil, wheel borrow
Total B 4916.25
Total A +B 9112.05
(C) Material
0.09 Cum Cost of 11.20mm HBG chips including conveyance 914.20 1Cum 82.28
0.18 Cum Cost of 13.20mm HBG chips including conveyance 1039.20 1Cum 187.06
14.60 Kg Bitumen 80/100 Grade 22483.90 MT 328.26
10.00 Sqm Labour & Machinery power roller hire charges (A+B) 9112.05 500Sqm 182.24
779.85
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C) 46.79
(E) Total of (A) + (B)+( C)+(D) 826.64
(F) Add Contractors Profit at 10% on (E) 82.66
Cost per 10 Sqm (E) + (F) 909.30
Rate per 1 sqm 90.93
Rate to be adopted 91.00
1 sqm
Providng and laying bituminious liquid Seal Coat (Type A) comprising of a layer of bituminious binder
followed by a cover of stone chipping of grading as defined in table 500-16 of MORT &H at 0.09 Cum/
10Sqm of chips to be laid simultaneously along with the botuminious course using 9.80Kgs of bitumen
80/100grade for 10Sqm and rolling with power roller including of required line, level, and grades serve as
wearing course on previously prepared surface and finishing to required level and grades including cost,
4
and conveyance of all materials from approved sources and stacking the metal at site to departmental
gauge for premeasurements and labour charges, hire and operational charges of power road rleer 80 to
10 T capacity and all other machinery tools and plants providing barricading for diversion of traffic,
errecting red flags other incidential and operational charges etc., complete for finished item of work as per
MORT &H specification No. 513
Unit = sqm
Taking output = 10250 sqm ( 92.25 Cum )
(A) Labour
0.24 nos. Male 188.00 day 45.12
6.00 nos. Mazdoor 146.00 day 876.00
Total A 921.12
(B) Machinary
6.00 hr Hydraulic self propelled chip spreader @ 1500 sqm/hr. 2070.00 hr 12420.00
6.00 hr Front end loader 1 cum bucket capacity 1320.00 hr 7920.00
6.00 hr Tipper 10Tonne capacity 5.5Cum 575.00 hr 3450.00
6.00 hr Bitumen pressure distributer @1750 Sqm per hour 940.00 hr 5640.00
6.00 hr Power roller 8-10T 540.00 hr 3240.00
Total B 32670.00
(C) Material
Cost of 6-7mm size defined as 100% passing through
92.25 Cum 11.20mm seive and retained om 2.36mm sieve applied 789.20 1Cum 72803.70
@0.09Cum per 10Sqm including conveyance
Bitumen 80/100 Grade @ 9.80 Kg per 10Sqm
10.05 T 22483.90 MT 225963.20
including conveyance
Total C 298766.90
Rate per 10250 Sqm ( A+B+C ) 332358.02
Rate per 10Sqm = (A+B+C )/10250 324.25
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C) 19.46
(E) Total of (A) + (B)+( C)+(D) 343.71
(F) Add Contractors Profit at 10% on (E) 34.37
Cost per 10 Sqm (E) + (F) 378.08
Rate per 1 sqm 37.81
Rate to be adopted 38.00
1 sqm
Supply and fixing of 1.05m x2.10m size teak wood framed, Bottom teak wood planked and top Photogray
1
glass Single Door Shutters
6"x 11/2 "
Requirment of Teak wood
for Middle 1x0.95x 0.20x 0.0375 0.00710 Cum 5"x 11/2 "
0.04045 Cum
for Plank 1x0.95x 0.75x 0.0375 0.0267 Cum
Requirement of 5mm thick
0.75x0.95 0.7125 Sqm 6"x 11/2 "
1.05m
Sundries 0.02
13017.80
Rate per 1Sqm 13017.80/2.205 5903.76
or Say 5904.00
Labour charges for Drilling of Bores 20% MA
STEEL WEIGHTS
Page 141
RR Masonary CM (1:8) Dry Packing Gravel Backing
Observed Data for Cup board of Size 3' 0" x 6' 0"
Frames Verticals 2x 0' 8" x 0' 4" x 0' 1" 0.368 Cft
Horizantals 2x3' 8" x 0' 4" x 0' 1" 0.202 Cft
Shutters Verticals 2x2x 6' 0" x 0' 3" x 0' 1" 0.480 Cft
Horizantals 2x7x 1' 6" x 0' 3" x 0' 1" 0.420 Cft
Planks 2x6x 1' 2" x 0' 9" x 0' 1" 0.870 Cft
2.34 Cft
or 0.066 Cum
1.67 Sqm Labour charges
Horiz 2x5' 0''x 0' 21/2'' x 0' 3'' 0.52 Hor 3x2x 0'16''x 0' 21/2'' x 0' 11/2'' =0.05
Vert 4x4' 6''x 0' 21/2'' x 0' 3'' 0.90 6x1x3 ' 6''x 0' 21/2'' x 0' 11/2'' =0.55
1.42
Page 142
25% MA
1509.38
1940.63
1832.81
2228.13
2012.50 3.50
2803.13
3665.63 6.375
0.040781
0.17651
0.075048 1.9812
0.033418 0.032002
0.060718
0.035
Page 143
0.333333
0.083333
0.364835
0.44
Page 144
20mm,40mm ,1
Sand Countr
S. Distanc Sand for 2 mm,6mmHBG Distanc Dista Gravel and Distan Rough Dista
Name for Distance y MA
No e Mortor Metal,Stone e nce Quarry Rubbish ce Stone nce
filling Bricks
dust
10 Medikonduru Local 5.00 Amaravathi 41.00 Perecherla 9.00 Kollur 69.00 Perecherla 10.00 Perecherla 9.00 25.00
DATA SHEET
Painting with Synthatic enamil paint two coats of approved colour 10Sqm to new wood work ---
10.00Sqm
1.20 Litres Cost of Synthetic paint 180.00 1Lit 216.00
0.36 Nos Paint 1st class 224.00 1Nos 80.64
0.84Nos Paint 2nd class 206.00 1Nos 173.04
Sundries for brushes 0.80
470.48
Painting with Synthatic enamil paint two coats of approved colour 10Sqm to Old wood work ---
10.00Sqm
1.10 Litres Cost of Synthetic paint 180.00 1Lit 198.00
0.36 Nos Paint 1st class 224.00 1Nos 80.64
0.84Nos Paint 2nd class 206.00 1Nos 173.04
Sundries for brushes 0.80
452.48
Painting with Synthatic enamil paint one coat of approved colour 10Sqm to Old wood work ---
10.00Sqm
0.70 Litres Cost of Synthetic paint 180.00 1Lit 126.00
0.21 Nos Paint 1st class 224.00 1Nos 47.04
0.49Nos Paint 2nd class 206.00 1Nos 100.94
Sundries for brushes 1.00
274.98
Painting with water bound Distemper two coats with oilbound distemper --- 10.00Sqm
1.70 Litres Cost of Distemper 80.00 1Lit 136.00
0.36 Nos Paint 1st class 224.00 1Nos 80.64
0.84Nos Paint 2nd class 206.00 1Nos 173.04
Sundries for brushes 0.62
390.30
Painting walls with Snowcem other equal approved waterproof cement over primary coat-- one
coat --- 10.00Sqm
2.00Kg Cost of Snowcem paint 950.00 25Kg 76.00
0.09 Nos Paint 1st class 224.00 1Nos 20.16
0.21Nos Paint 2nd class 206.00 1Nos 43.26
0.50Nos Man Mazdoor 170.00 1Nos 85.00
1.00Nos Women Mazdoor 170.00 1Nos 170.00
Sundries for brushes 1.28
395.70
Painting walls with Snowcem other equal approved waterproof cement over primary coat-- two
coats --- 10.00Sqm
3.50Kg Cost of Snowcem paint 950.00 25Kg 133.00
0.15 Nos Paint 1st class 224.00 1Nos 33.60
0.35Nos Paint 2nd class 206.00 1Nos 72.10
0.50Nos Man Mazdoor 170.00 1Nos 85.00
1.00Nos Women Mazdoor 170.00 1Nos 170.00
Sundries for brushes 1.30
495.00
RCM facia work 50mm thick in CM (1:3) using Rabit wire mesh including cost conveyance of all
materials and labour charges etc
0.50Cum Cost of CM (1:3)
10.00Sqm Rabit wire mesh 12.00 1Sqm
10.00Sqm Centering Charges 102.00 1Sqm
10.00Sqm Labour charges 180.00 1Sqm
C/s of fixing Aluminium partion wallsmade up of 63.50mmx38.10mmx 1.50mm thick including fixing
navapan12mm thick including cost conveyance of all materials and labour charges etc
Section 63.50mmx38.10mmx 1.50mm
1x1x3.37 3.37
1x1x3.60 3.60
1x8x0.85 6.80
13.77 0.90 12.393 Kg
12.393Kg cost of Aluminium 250.00 Kg 3098.25
1.15x0.85
Sqm Cost of Navapan 1587.00 1Sqm 9307.76
5.865
5.865Sqm Labour charges 322.80 1Sqm 1893.22
14299.23
14299.23/5.865 2438.06
Add Vat 2.80% 68.27
2506.33
153.00
172.80
315.00
97.56
738.36
GOODS AND SERVICE TAXES
S.No Category Tax in %
1 Red Bricks 5
3 M sand 5
4 River Sand 5
7 TMY Steel 18
9 GI Fittings 18
10 Cement 28
11 Concrete Blocks 28
12 Glass 28
15 28
16 Wall Papers 28
19 Tiles 18-28