SCOPE OF WORK :
The Project has been planned to draw 259.88 Cumecs (9,000 Cusecs) of water from
Godavari River at El. +45.00 M for a length of 10.50Km. Thereafter water will be lifted
at BG Kotturu village from EL. +43.60 M to EL. +67.10 M and then water will be flowing
through a gravity canal of 29.20 Km. Then, the water will be lifted at Koyagutta from
EL +63.00 M to +110.00 M and then water will be flowing through a gravity canal of 21
Km. The water then will be lifted at Kamalapuram from EL. +108 m to EL. +160 m and
EL. +200 m, where the canal at RL.+160 m is bifurcated in to two branches.
The first branch will cover Rajiv Sagar area and the second branch will cover Indira
Saga area. The gravity canal at EL. +200 m (Right) after lift from Kamalapuram will
cover area of Indira Sagar ayacut. Under this scheme it is also proposed to stabilize the
ayacut of about 80,000 Acres under DBM 60 of SRSP Stage-II Command through
Bayyaram Tank.
It is also proposed to improve the capacities of
1) Rollapadu tank from existing capacity of 0.175 TMC to 10.61 TMC,
The alignment of Sita Rama Lift Irrigation Project (SRLIP) avoids Kinnerasani
Wild Life Sanctuary and its eco sensitive zone.
The alignment of SRLIP will cross railway lines at very few places against too
many railway crossings in earlier RDLIS alignment.
The alignment of SRLIP is not interfering with Ash pond area of KTPS and runs
away from Palvoncha town, where as the alignment of RDLIS running very close
to Palvoncha Town and interfering with Ash pond area of KTPS.
The alignment of SRLIP runs in Telangana state only avoiding interstate issues
with state of Andhra Pradesh as was the case in ISRLIS where in the head works
of ISRLIS located in the administrative boundary of the residual Andhra
Pradesh.
While designing SRLIP, due care has been taken to utilize the expenditure
incurred on RDLIS & ISRLIS to the maximum extent possible
The length of pressure main is restricted to 10.50 Kms. against the pressure
main length of 77.00 Kms in the earlier projects i.e., RDLIS & ISRLIS.
The new alignment of project will irrigate the upland areas viz.,
Tirumalayapalem (M), Kusumanchi (M), Nelekondapally and Mudigonda (M)
which are not covered in earlier projects. The number of pump houses
proposed in SRLIP are only 5 No’s against 10 No’s in earlier projects and reduce
post project maintenance problems.
In case of availability of additional water during a good year, the SRLIP will also
serve/ supplement several existing medium irrigation projects such as Paleru,
Wyra and Lanka Sagar Projects.
The storage facilities provided in the RDLIS & ISRLI schemes is about 1.00 TMC
where as in SRLIP, the storage capacity of Tanks are increased to 12.38 TMC
which will be a cushion in case of any break downs in the lifting system.
Meet the requirement of water for both domestic and industrial growth due to
creation of new districts.
The water allocated to Palair and Wyra reservoirs under Mission Bhagiratha can
be fed from SRLIP, as these reservoirs are not receiving sufficient inflows even
to satisfy their own ayacut at present.