Professional Documents
Culture Documents
Story Point Estimation
Story Point Estimation
Story Points are a complex unit that includes three elements: risk, complexity and
repetition.
Risk – Unclear Demand, Dependency on 3rd party and uncertainty in the future
To find our Base Story, we search for one elementary task that corresponds to
internal standards of Definition of Done for User Stories and assign it one Story
Point. This will be our Base Story.
Step 2 — Create a Matrix for Estimation
To assign Story Points to each story, we have a meeting where all specialists
that will work on the project get together and play Planning Poker.
backlogs. It can be used with various estimating units, but we use Planning
2. All estimators select backlog items, discuss features, and ask questions;
3. When a feature has been fully discussed, each estimator privately (to
estimate;
4. When all estimators have made their estimates, they reveal their cards at
the same time. If all estimates match, estimators select another backlog
item and repeat the same process. When estimates differ, the estimators
5. By the end of Planning Poker, we’ve filled out the whole matrix. Our tasks
are divided into rows by the number of story points needed to implement
them. Finally, we place each backlog item in the appropriate row. There
sizes into man-hour estimates. Unfortunately, we can’t do this until the first sprint
is completed. While the first sprint is in progress we can track the team’s velocity.
As soon as the sprint is finished, we’ll know how many Story Points a team can
complete per sprint. We use these numbers to forecast the team's performance
When we have all backlog tasks estimated in terms of Story Points, we can
understand how many sprints we’re going to need to complete the project. And
finally, we can convert these abstract units into real calendar timelines.