HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. SKETSA PERHITUNGAN
pas. Batu
m3
RABAT BETON
p0 0.830 + 0.700 x 0.1 = 0.077
2
p1 0.830 + 0.700 x 0.1 = 0.077
2
Volume Profil P 0 - P1
V = 0.077 + 0.077 x 50.00 = 3.825 m3 3.825
2
P2 0.830 + 0.700 x 0.1 = 0.077
2
Volume Profil P 1 - P2
V = 0.077 + 0.077 x 50.00 = 3.825 m3 3.825
2
P3 0.830 + 0.700 x 0.1 = 0.077
2
Volume Profil P 2 - P3 3.825
V = 0.077 + 0.077 x 50.00 = 3.825 m3
2

Volume Profil P 3 - P4
V = 0.077 + m3 x 50.00 = #VALUE! m3 #VALUE!
2
Volume Profil P4- P5
V = m3 + m3 x 50.00 = #VALUE! m3 #VALUE!
2
Volume Profil P5- P6 #VALUE!
Volume Profil P6- P7 #VALUE!
Volume Profil P7- P8 #VALUE!
Volume Profil P8- P9 #VALUE!
Volume Profil P5- P10 #VALUE!
Volume Profil P5- P11 #VALUE!
Volume Profil P5- P12 #VALUE!
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. SKETSA PERHITUNGAN
pas. Batu
m3
Volume Profil P5- P13 #VALUE!
Volume Profil P5- P14 #VALUE!
Volume Profil P5- P15 #VALUE!
Volume Profil P5- P16 #VALUE!
Volume Profil P5- P17 #VALUE!
Volume Profil P5- P18 #VALUE!
Volume Profil P5- P19 #VALUE!
Volume Profil P5- P20 #VALUE!
Volume Profil P5- P21 #VALUE!
Volume Profil P5- P22 #VALUE!
Volume Profil P5- P23 #VALUE!
Volume Profil P5- P24 #VALUE!
Volume Profil P5- P25 #VALUE!
Volume Profil P5- P26 #VALUE!
Volume Profil P5- P27 #VALUE!
Volume Profil P5- P28 #VALUE!
Volume Profil P5- P29 #VALUE!
Volume Profil P5- P30 #VALUE!
Volume Profil P5- P31 #VALUE!
Volume Profil P5- P32 0.000
Volume Profil P5- P33 0.000
Volume Profil P5- P34 0.000

#VALUE!
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
1 97 - 98 KANAN Pas. Batu Gunung
Struktur
0.30 + 0.90 x 0.93 x 0.00 x 1.00 = 0.00 m3
2.00
Pengurangan Batu Muka
0.93 x 0.00 x 0.10 x 1.00 = 0.00 m3
0.00 m3 0.000
Pas. Batu Muka
0.93 x 0.00 x 0.10 = 0.00 m2 0.000 0.000
Plesteran
0.40 x 0.00 = 0.00 m2 0.000

2 205 -215 KANAN Pas. Batu Gunung


250-252 KANAN Struktur
0.30 + 0.90 x 1.09 x 12.00 x 1.00 = 7.81 m3
2.00
Pengurangan Batu Muka
1.09 x 12.00 x 0.10 x 1.00 = 1.30 m3
6.51 m3 6.510
Pas. Batu Muka
1.09 x 12.00 x 0.10 = 1.30 m2 1.302 1.302
Plesteran
0.40 x 12.00 = 4.80 m2 4.800

272-275 KIRI Pas. Batu Gunung


Struktur
0.30 + 0.90 x 1.09 x 3.00 x 1.00 = 1.95 m3
2.00
Parapet
0.30 x 0.36 x 3.00 x 1.00 = 0.32 m3
2.28 1.843
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
Pengurangan Batu Muka
1.09 x 3.00 x 0.10 x 1.00 = 0.33 m3
0.36 x 0.10 x 3.00 x 1.00 0.11
0.43 m3
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
Pas. Batu Muka
1.09 x 3.00 x 0.10 = 0.33 m2
0.36 x 0.10 x 3.00 = 0.11 m2
0.43 0.434 0.434
Plesteran
0.40 x 3.00 = 1.20 m2 1.200

3 426 - 433 kanan Pas. Batu Gunung


Struktur
0.30 + 1.00 x 0.34 x 7.00 x 1.00 = 1.55 m3
2.00
Pengurangan Batu Muka
0.34 x 7.00 x 0.10 x 1.00 = 0.24 m3
1.31 m3 1.309
Pas. Batu Muka
0.34 x 7.00 x 0.10 = 0.24 m2 0.238 0.238
Plesteran
0.40 x 7.00 = 2.80 m2 2.800
426 - 433 KIRI Pas. Batu Gunung
Struktur
0.30 + 1.00 x 0.78 x 7.00 x 1.00 = 3.55 m3
2.00
Pengurangan Batu Muka
0.78 x 0.10 x 7.00 x 1.00 = 0.55 m3
3.00 m3 3.003
Pas. Batu Muka
0.78 x 0.10 x 7.00 = 0.55 m2 0.546 0.546
Plesteran
0.40 x 7.00 = 2.80 m2 2.800
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
4 640 - 643 KIRI Pas. Batu Gunung
697 - 698 KIRI Struktur
0.30 + 0.60 x 0.65 x 0.00 x 1.00 = 0.00 m3
2.00
Pengurangan Batu Muka
0.65 x 0.00 x 0.10 x 1.00 = 0.00 m3
0.00 m3 0.000
Pas. Batu Muka
0.65 x 0.00 x 0.10 = 0.00 m2 0.000 0.000
Plesteran
0.40 x 0.00 = 0.00 m2 0.000

5 748 - 749 KIRI Pas. Batu Gunung


Struktur
0.30 + 0.70 x 0.79 x 0.00 x 1.00 = 0.00 m3
2.00
Parapet
0.30 x 0.70 x 0.00 x 1.00 = 0.00 m3
0.00 0.000
Pengurangan Batu Muka
0.79 x 0.00 x 0.10 x 1.00 = 0.00 m3
0.70 x 0.10 x 0.00 x 1.00 0.00
0.00 m3
Pas. Batu Muka
0.79 x 0.00 x 0.10 = 0.00 m2
0.70 x 0.10 x 0.00 = 0.00 m2
0.00 0.000 0.000
Plesteran
0.40 x 0.00 = 0.00 m2 0.000
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
780 - 787 KANAN Pas. Batu Gunung
Struktur
0.30 + 0.50 x 0.66 x 0.00 x 1.00 = 0.00 m3
2.00
Pengurangan Batu Muka
0.66 x 0.00 x 0.10 x 1.00 = 0.00 m3
0.00 m3 0.000
Pas. Batu Muka
0.66 x 0.00 x 0.10 = 0.00 m2 0.000 0.000
Plesteran
0.40 x 0.00 = 0.00 m2 0.000

6 977 - 980 KIRI Pas. Batu Gunung


Struktur
0.30 + 1.00 x 0.86 x 3.00 x 1.00 = 1.67 m3
2.00
Pengurangan Batu Muka
0.86 x 3.00 x 0.10 x 1.00 = 0.26 m3
1.41 m3 1.411
Pas. Batu Muka
0.86 x 3.00 x 0.10 = 0.26 m2 0.257 0.257
Plesteran
0.40 x 3.00 = 1.20 m2 1.200

Pas. Batu Gunung


7 1004 - 1030 KIRI Struktur
1060 - 1077 KIRI 0.30 + 1.05 x 0.67 x 43.00 x 1.00 = 19.45 m3
2.00
Parapet
0.30 x 0.56 x 43.00 x 1.00 = 7.22 m3
26.67 21.382
Pengurangan Batu Muka
0.67 x 0.10 x 43.00 x 1.00 = 2.88 m3
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
0.56 x 0.10 x 43.00 x 1.00 2.41
5.29 m3
Pas. Batu Muka
0.67 x 0.10 x 43.00 = 2.88 m2
0.56 x 0.10 x 43.00 = 2.41 m2
5.29 5.289 5.289
Plesteran
0.40 x 43.00 = 17.20 m2 17.200
1010 - 1015 KANAN Pas. Batu Gunung
1038 - 1045 KANAN Struktur
0.30 + 1.05 x 0.88 x 12.00 x 1.00 = 7.09 m3
2.00
Pengurangan Batu Muka
0.88 x 12.00 x 0.10 x 1.00 = 1.05 m3
6.04 m3 6.038
Pas. Batu Muka
0.88 x 12.00 x 0.10 = 1.05 m2 1.050 1.050
Plesteran
0.40 x 12.00 = 4.80 m2 4.800

Pas. Batu Gunung


8 1182 - 1185 KIRI Struktur
1196 - 1205 KIRI 0.30 + 1.05 x 0.85 x 12.00 x 1.00 = 6.84 m3
2.00
Parapet
0.30 x 0.56 x 12.00 x 1.00 = 2.02 m3
8.86 7.175
Pengurangan Batu Muka
0.85 x 0.10 x 12.00 x 1.00 = 1.01 m3
0.56 x 0.10 x 12.00 x 1.00 0.67
1.69 m3
Pas. Batu Muka
0.85 x 0.10 x 12.00 = 1.01 m2
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
0.56 x 0.10 x 12.00 = 0.67 m2
1.69 1.686 1.686
Plesteran
0.40 x 12.00 = 4.80 m2 4.800

Pas. Batu Gunung


9 1285.5 - 1290.5 KIRI Struktur
1290.5 - 1300 KIRI 0.30 + 0.95 x 0.68 x 8.50 x 1.00 = 3.61 m3
2.00
Parapet
0.30 x 0.56 x 8.50 x 1.00 = 1.43 m3
5.04 3.987
Pengurangan Batu Muka
0.68 x 0.10 x 8.50 x 1.00 = 0.58 m3
0.56 x 0.10 x 8.50 x 1.00 0.48
1.05 m3
Pas. Batu Muka
0.68 x 0.10 x 8.50 = 0.58 m2
0.56 x 0.10 x 8.50 = 0.48 m2
1.05 1.054 1.054
Plesteran
0.40 x 8.50 = 3.40 m2 3.400

10 1340 - 1350 KIRI Plesteran


1350 - 1360 KIRI 0.60 x 0.00 = 0.00 m2 0.000
Pas. Batu Gunung
1312 - 1315 KANAN Struktur
0.30 + 0.95 x 0.64 x 0.00 x 1.00 = 0.00 m3
2.00
Parapet
0.30 x 0.80 x 0.00 x 1.00 = 0.00 m3
0.00
Pengurangan Batu Muka
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
0.64 x 0.10 x 0.00 x 1.00 = 0.00 m3
0.80 x 0.10 x 0.00 x 1.00 0.00
0.00 m3 0.000
Pas. Batu Muka
0.64 x 0.10 x 0.00 = 0.00 m2
0.80 x 0.10 x 0.00 = 0.00 m2
0.00 0.000 0.000
Plesteran
0.40 x 0.00 = 0.00 m2 0.000

11 1403 - 1404 KANAN Pas. Batu Gunung


1406 - 1420 KANAN Struktur
0.30 + 0.95 x 0.59 x 15.00 x 1.00 = 5.48 m3
2.00
Parapet
0.30 x 0.68 x 15.00 x 1.00 = 3.06 m3
8.54 6.647
Pengurangan Batu Muka
0.59 x 0.10 x 15.00 x 1.00 = 0.88 m3
0.68 x 0.10 x 15.00 x 1.00 1.02
1.90 m3
Pas. Batu Muka
0.59 x 0.10 x 15.00 = 0.88 m2
0.68 x 0.10 x 15.00 = 1.02 m2
1.90 1.898 1.898
Plesteran
0.40 x 15.00 = 6.00 m2 6.000

12 1502 - 1504.5 KIRI Pas. Batu Gunung


1506 - 1508 KIRI Struktur
1562 - 1564 KIRI 0.30 + 0.95 x 0.69 x 6.00 x 1.00 = 2.57 m3
2.00
Parapet
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
0.30 x 0.43 x 6.00 x 1.00 = 0.77 m3
3.34 2.674
Pengurangan Batu Muka
0.69 x 0.10 x 6.00 x 1.00 = 0.41 m3
0.43 x 0.10 x 6.00 x 1.00 0.26
0.67 m3
Pas. Batu Muka
0.69 x 0.10 x 6.00 = 0.41 m2
0.43 x 0.10 x 6.00 = 0.26 m2
0.67 0.669 0.669
Plesteran
0.40 x 6.00 = 2.40 m2 2.400
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. STA KANAN KIRI PERHITUNGAN
Pas. Batu Plesteran Siaran BT. Muka
m3 m2 m2 m2
13 1686 - 1688,9 KIRI Pas. Batu Gunung
Struktur
0.30 + 0.95 x 0.66 x 2.90 x 1.00 = 1.20 m3
2.00
Parapet
0.30 x 0.49 x 2.90 x 1.00 = 0.42 m3
1.62 1.286
Pengurangan Batu Muka
0.66 x 0.10 x 2.90 x 1.00 = 0.19 m3
0.49 x 0.10 x 2.90 x 1.00 0.14
0.33 m3
Pas. Batu Muka
0.66 x 0.10 x 2.90 = 0.19 m2
0.49 x 0.10 x 2.90 = 0.14 m2
0.33 0.332 0.332
Plesteran
0.40 x 2.90 = 1.16 m2 1.160

14 1736 - 1750 KANAN Pas. Batu Gunung


Struktur
0.30 + 1.20 x 0.90 x 14.00 x 1.00 = 9.40 m3
2.00
Pengurangan Batu Muka
0.90 x 14.00 x 0.10 x 1.00 = 1.25 m3
8.14 m3 8.145
Pas. Batu Muka
0.90 x 14.00 x 0.10 = 1.25 m2 1.253 1.253
Plesteran
0.40 x 14.00 = 5.60 m2 5.600

71.408 58.160 16.007 16.007


PERHITUNGAN BOQ SALURAN
LUAS VOLUME
Patok Jarak
Timbunan Galian Rabat Timbunan Galian Rabat
M2 M2 M2 M3 M3 M3

P. 0 0.14 0.193 0.076


50 7.625 9.650 3.800
P.1 0.165 0.193 0.076
50 7.675 9.650 3.800
P.2 0.142 0.193 0.076
50 7.125 9.650 3.800
P.3 0.143 0.193 0.076
50 6.925 7.200 3.525
P.4 0.134 0.095 0.065
50 6.700 4.725 3.250
P.5 0.134 0.094 0.065
50 6.700 4.725 3.250
P.6 0.134 0.095 0.065
50 6.700 4.750 3.250
P.7 0.134 0.095 0.065
50 6.700 4.750 3.250
P.8 0.134 0.095 0.065
50 6.700 4.750 3.250
P.9 0.134 0.095 0.065
50 6.700 4.750 3.250
P.10 0.134 0.095 0.065
50 6.700 4.750 3.250
P.11 0.134 0.095 0.065
50 6.700 4.750 3.250
P.12 0.134 0.095 0.065
50 6.700 4.750 0.260
P.13 0.134 0.095 0.065
50 6.700 4.750
P.14 0.134 0.095 0.065
50 6.700 4.750
P.15 0.134 0.095 0.065
50 6.700 4.750
P.16 0.134 0.095 0.065
50 6.700 4.750
P.17 0.134 0.095 0.065
50 6.700 4.750
P.18 0.134 0.095 0.065
50 6.700 4.750
P.19 0.134 0.095 0.065
50 6.700 4.750
P.20 0.134 0.095 0.065
50 6.700 4.750
P.21 0.134 0.095 0.065
50 6.700 4.750
P.22 0.134 0.095 0.065
50 6.700 4.750
P.23 0.134 0.095 0.065
50 6.700 4.750
P.24 0.134 0.095 0.065

1200 Juml 163.35 131.10 41.18


PERHITUNGAN PELAT JEMBATAN
DIMENSI (M) LUAS VOLUME TULANGAN
Titik Sta. Owner
lebar panjang Tebal (M2) (M3) (KG)
120
1 SALURAN 1.5 4.00 0.12 6 0.72 86.4
6 0.72 86.4
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
ENGINEERING ESTIMATE (EE)

Kegiatan : Pembangunan Saluran/Drainanse Lingkungan


Pekerjaan : Pembangunan Saluran/Drainanse Lingkungan, Desa Garu
Lokasi : Desa Garu Kec. Baron, Kab. Nganjuk
Kabupaten : Nganjuk
Tahun Anggaran : 2023
Tolak Ukur :
- 126.00 M

JUMLAH HARGA
NO. JENIS PEKERJAAN
( Rp )
I PEKERJAAN PERSIAPAN Rp 1,764,000.00
II PEKERJAAN TANAH Rp 2,041,200.00
III PEKERJAAN PASANGAN Rp 142,792,608.00
JUMLAH TOTAL Rp 146,597,808.00
JUMLAH TOTAL PEMBULATAN Rp 146,597,000.00

Terbilang : Seratus Juta Rupiah

Nganjuk, 2023
DIBUAT OLEH
KETUA POKMAS
BAROKAH

MOHAMAD ANWAR
ketua
RENCANA KUANTITAS DAN HARGA
ENGINEERING ESTIMATE (EE)

Kegiatan : Pembangunan Saluran/Drainanse Lingkungan


Pekerjaan : Pembangunan Saluran/Drainanse Lingkungan, Desa Garu
Lokasi : Desa Garu Kec. Baron, Kab. Nganjuk
Kabupaten : Nganjuk
Tahun Anggaran : 2023
Tolak Ukur :
- 126.00 m

HARGA HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME SATUAN PEKERJAAN
Rp Rp

I PEKERJAAN PERSIAPAN
1 Pembersihan sebelum dan sesudah proyek Ls 1.00 1,264,000.00 1,264,000.00
2 Pemasangan papan nama dan prasasti bh 1.00 500,000.00 500,000.00

Jumlah Harga Pekerjaan Persiapan 1,764,000.00

II PEKERJAAN TANAH
1 Galian tanah biasa m3 30.24 67,500.00 2,041,200.00

Jumlah Harga Pekerjaan Tanah 2,041,200.00

III PEKERJAAN PASANGAN


1 Pasangan batu kali/gunung dengan campuran 1 Pc:4 Ps m3 134.40 876,100.00 117,747,840.00
2 Plesteran 1 pc : 3 psr m2 254.52 63,400.00 16,136,568.00
3 Acian m3 254.52 35,000.00 8,908,200.00

Jumlah Harga Pekerjaan Pasangan 142,792,608.00

IV PEKERJAAN BETON
1 Rabat Beton m3 4.41 822,900.00 3,628,989.00
Jumlah Harga Pekerjaan Beton 3,628,989.00
Jumlah Total ( I+II+III+IV) 150,226,797.00
Jumlah Toptal Pembulatan 150,226,000.00

Nganjuk, 2023
DIBUAT OLEH
KETUA POKMAS
BAROKAH

MOHAMAD ANWAR
ketua
PERHITUNGAN VOLUME

KEGIATAN : Pembangunan Saluran/Drainanse Lingkungan


PEKERJAAN : Pembangunan Saluran/Drainanse Lingkungan, Desa Garu
LOKASI : Desa Garu Kec. Baron, Kab. Nganjuk
TA. ANGGARAN : 2023
NO NAMA BAGIAN PEKERJAAN DAN
GALIAN TNH PASIR URUG PASANGAN RABAT BETON PLESTRAN
PERINCIAN PERHITUNGAN VOLUME
MANUAL BATU GUNUNG 1:3
GBR GAMBAR POTONGAN / PERSPEKTIF
(M2) (m3) ( m3 ) ( m2 )
25
0,35 25
0,35
GALIAN
F1 = 42.00 x 0.40 x 0.30 x 1.00 = 5.04
F2 = 105.00 x 0.40 x 0.30 x 2.00 = 25.20
0,70
60

å F 30.24 30.24

80
PAS. BATU GUNUNG
= 0.30 + 0.40 x 0.70 x 42.00 x 1.00 = 10.29
F1
20

0,30 2
= 0.30 + 0.40 x 0.70 x 105.00 x 2.00 = 51.45
35
0,40 0,60 35
0,40 F2
2
F3 = 0.40 x 0.30 x 42.00 x 1.00 = 5.04
F4 = 0.40 x 0.30 x 105.00 x 2.00 = 25.20
25
0,35 0,70 25
0,35 å F = 91.98 91.98

BETON
F1 = 0.60 x 0.05 x 147.00 = 4.41 4.41
0,70
60

PLESTERAN
80

F1 = 1.01 x 42.00 x 1.00 = 42.42 254.52


F2 = 1.01 x 105.00 x 2.00 = 212.10
20

0,30
Acian
35
0,40 0,60 35
0,40 F1 = 1.01 x 42.00 x 1.00 = 42.42 254.52
F2 = 1.01 x 105.00 x 2.00 = 212.10

30.24 254.52 134.400 4.410 254.520 ###


HARGA SATUAN UPAK TENAGA KERJA, BAHAN DAN ALAT
Zona C

NO NAMA BAHAN SATUAN


ZONA B
1 2 4 7
1 Batu Gunung/Kali m³ 227,000
2 Batu Pecah 2/3 mesin m³ 296,000
3 Pasir Hitam Cor / Pasir Beton m³ 357,000
4 Semen Portland kg 1,550
5 Kayu Begesting m3 3,916,000
6 Kayu Gelam m3 5,641,000
7 Besi Beton 16,000
8 Kawat Bendrat kaku kg 25,000
9 Paku 2"-5" kg 24,000
10 pasir pasang m3 347,500
11 Minyak Bekisting kg 32,000
STANDAR HARGA SATUAN UPAH TENAGA KERJA DAN BAHAN
TAHUN ANGGARAN 2023
Zona C
NO SPESIFIKASI SATUAN HARGA SATUAN
1 Kepala Tukang Batu hari 135,000
2 Kepala Tukang Besi hari 135,000
3 Kepala Tukang Kayu hari 135,000
4 Tukang Batu hari 125,000
5 Tukang Besi hari 125,000
6 Tukang Kayu hari 125,000
7 Juru ukur hari 135,000
8 Pekerja Tak Terampil / Kuli hari 110,000
ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2023

HARGA SAT JUMLAH


NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)

B. PEKERJAAN TANAH
B.001 Menggali 1 m³ tanah biasa sedalam 1 meter
A Tenaga
Pekerja 0.7500 OH 110,000.00 82,500.00
Mandor 0.0250 OH - -
JUMLAH TENAGA KERJA 82,500.00
B Bahan -
JUMLAH HARGA BAHAN -
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 82,500.00
E Harga Satuan Pekerjaan 82,500.00

B.002 Menggali 1 m3 tanah cadas sedalam 1 m


A Tenaga
Pekerja 1.5000 OH 110,000.00 165,000.00
Mandor 0.0600 OH - -
JUMLAH TENAGA KERJA 165,000.00
B Bahan -
JUMLAH HARGA BAHAN -
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 165,000.00
E Harga Satuan Pekerjaan 165,000.00

Mengurug kembali 1 m³ galian dihitung dari 1/3 x dari koefisien pekerjaan galian
A Tenaga
Pekerja 0.5000 OH 110,000.00 55,000.00
Mandor 0.0500 OH - -
JUMLAH TENAGA KERJA 55,000.00
B Bahan
JUMLAH HARGA BAHAN -
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 55,000.00
E Harga Satuan Pekerjaan 55,000.00

Memasang 1 m³ pondasi batu gunung; campuran 1 PC : 4 PP


A Tenaga
Pekerja 1.5000 OH 110,000.00 165,000.00
Tukang Batu 0.7500 OH 125,000.00 93,750.00
Kepala Tukang 0.0750 OH 135,000.00 10,125.00
Mandor 0.0750 OH - -
JUMLAH TENAGA KERJA 268,875.00
B Bahan
Batu Gunung 15/20 1.2000 m³ 227,000.00 272,400.00
Portland Cement (PC) 163.0000 kg 1,550.00 252,650.00
Pasir Pasang (PH) 0.5200 m³ 357,000.00 185,640.00
JUMLAH HARGA BAHAN 710,690.00
C Peralatan
JUMLAH HARGA ALAT -
Analisa Pekerjaan 21 dari 63
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
D Jumlah (A+B+C) 979,565.00
E Harga Satuan Pekerjaan 979,560.00

C. PEKERJAAN PLESTERAN
C.001 Memasang 1 m² plesteran 1 Pc : 3 Ps; tebal 15 mm
A Tenaga
Pekerja 0.2000 OH 110,000.00 22,000.00
Tukang Batu 0.1500 OH 125,000.00 18,750.00
Kepala Tukang 0.0150 OH 135,000.00 2,025.00
Mandor 0.0100 OH - -
JUMLAH TENAGA KERJA 42,775.00
B Bahan
Portland Cement (PC) 7.7760 kg 1,550.00 12,052.80
Pasir Hitam 0.0230 m³ 357,000.00 8,211.00
JUMLAH HARGA BAHAN 20,263.80
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 63,038.80
E Harga Satuan Pekerjaan 63,030.00

D.01 Membuat 1 m³ beton mutu f'c=21,75 Mpa (K 225); slump (12 ± 2) cm; w/c = 0,66
A Tenaga
Pekerja 1.6500 OH 110,000.00 181,500.00
Tukang Batu 0.2750 OH 125,000.00 34,375.00
Kepala Tukang 0.0280 OH 135,000.00 3,780.00
Mandor 0.0830 OH - -
JUMLAH TENAGA KERJA 219,655.00
B Bahan
Portland Cement (PC) 371.0000 kg 1,550.00 575,050.00
Pasir Beton (PB) 0.4986 m³ 357,000.00 177,990.00
Koral Beton (maksimum 30 mm) 0.7756 m³ 296,000.00 229,564.44
Air 0.2150 m³ 1,500.00 322.50
JUMLAH HARGA BAHAN 982,926.94
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,202,581.94
E Harga Satuan Pekerjaan (D+E) 1,202,580.00

D.01 Membuat 1 m³ beton mutu f'c=9,8 Mpa (K 125); slump (12 ± 2) cm; w/c = 0,78
A Tenaga
Pekerja 1.6500 OH 110,000.00 181,500.00
Tukang Batu 0.2750 OH 125,000.00 34,375.00
Kepala Tukang 0.0280 OH 135,000.00 3,780.00
Mandor 0.1650 OH - -
JUMLAH TENAGA KERJA 219,655.00
B Bahan
Portland Cement (PC) 276.0000 kg 1,550.00 427,800.00
Pasir Beton (PB) 0.6210 m³ 357,000.00 221,697.00
Koral Beton (maksimum 30 mm) 0.7400 m³ 296,000.00 219,040.00
Air 0.2150 m³ 1,500.00 322.50
JUMLAH HARGA BAHAN 868,859.50
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,088,514.50
E Harga Satuan Pekerjaan (D+E) 1,088,510.00

Analisa Pekerjaan 22 dari 63


HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)

1 kg, Besi beton


Tenaga
Pekerja 0.0077 OH 110,000.00 847.00
Tukang Besi 0.0077 OH 125,000.00 962.50
Kepala Tukang 0.0008 OH 135,000.00 103.95
Mandor 0.0003 OH - -
JUMLAH TENAGA KERJA 1,913.45
Bahan 0.0000
Besi Beton (polos/ulir) 1.0500 kg 16,000.00 16,800.00
Kawat Beton 0.0150 kg 25,000.00 375.00
JUMLAH HARGA BAHAN 17,175.00
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 19,088.45
E Harga Satuan Pekerjaan (D+E) 19,080.00

Memasang 1 m² bekisting dinding beton


A Tenaga
Pekerja 0.3600 OH 110,000.00 39,600.00
Tukang Kayu 0.1800 OH 125,000.00 22,500.00
Kepala Tukang 0.0180 OH 135,000.00 2,430.00
Mandor 0.0360 OH - -
JUMLAH TENAGA KERJA 64,530.00
B Bahan
Kayu Bekisting 0.0140 m³ 3,916,000.00 54,824.00
kaso 5/7 0.0050 m³ 5,641,000.00 28,205.00
Paku Biasa 2"-5" 0.3000 kg 24,000.00 7,200.00
Minyak Bekisting 0.2000 liter 32,000.00 6,400.00
JUMLAH HARGA BAHAN 96,629.00
C Peralatan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 161,159.00
E Harga Satuan Pekerjaan 161,150.00

1 m3 Pengurugan dengan pasir urug


A Tenaga
Pekerja 0.3000 OH 110,000.00 33,000.00
Mandor 0.0100 OH - -
JUMLAH TENAGA KERJA 33,000.00
C pasir urug 1.2000 m3 347,500.00 417,000.00
JUMLAH HARGA ALAT 417,000.00
D Jumlah (A+B+C) 450,000.00
E Harga Satuan Pekerjaan 450,000.00

Analisa Pekerjaan 23 dari 63


ANALISA HARGA SATUAN PEKERJAAN

1 m³ Pekerjaan Galian Tanah Biasa Sedalam 1 m


1.7.1.a Analisa PUPR 2022 Bidang Umum Hal. 183

Harga Satuan (Rp)


No. Uraian Satuan Koefisien Jumlah Harga (Rp)

A. TENAGA
1 Pekerja O.H 0.7500 90,000.00 67,500.00
Jumlah 67,500.00
Total Dibulatkan 67,500.00

1 m³ Pekerjaan Pasangan Batu Gunung 1PC : 4 PP


An. 2.1.2.a.3.a.(a) Analisa PUPR Bidang Umum Hal. 249

Harga Satuan (Rp)


No. Uraian Satuan Koefisien Jumlah Harga (Rp)

A. TENAGA
1 Pekerja O.H 1.5000 90,000.00 135,000.00
2 Tukang Batu O.H 0.7500 110,000.00 82,500.00
3 Kepala Tukang Batu O.H 0.0750 120,000.00 9,000.00
Jumlah 226,500.00
B. BAHAN
1 Batu gunung m3 1.2000 215,000.00 258,000.00
2 Pasir pasang m3 0.5200 283,000.00 147,160.00
3 Portland Cement kg 163.0000 1,500.00 244,500.00
Jumlah 649,660.00
C. ALAT
-
Jumlah -
Total 876,160.00
Nilai HSPK 876,100.00

1 m² Pekerjaan Plesteran 1 PC : 3 PP tebal 1,5 cm


An. 2.1.2.a.3.a.(a) Analisa PUPR Bidang Umum Hal. 297

Harga Satuan (Rp)


No. Uraian Satuan Koefisien Jumlah Harga (Rp)

A. TENAGA
1 Pekerja O.H 0.3000 90,000.00 27,000.00
2 Tukang Batu O.H 0.1500 110,000.00 16,500.00
3 Kepala Tukang Batu O.H 0.0150 120,000.00 1,800.00
Jumlah 45,300.00
B. BAHAN
1 Pasir Pasang m3 0.0230 283,000.00 6,509.00
2 Portland Cement kg 7.7760 1,500.00 11,664.00
Jumlah 18,173.00
Total 63,473.00
Nilai HSPK 63,400.00
1 m² Pekerjaan Acian
An. 3.2.2.(c) Analisa PUPR Bidang Umum Hal. 299

Harga Satuan (Rp)


No. Uraian Satuan Koefisien Jumlah Harga (Rp)

A. TENAGA
1 Pekerja O.H 0.2000 90,000.00 18,000.00
2 Tukang Batu O.H 0.1000 110,000.00 11,000.00
3 Kepala Tukang Batu O.H 0.0100 120,000.00 1,200.00
Jumlah 30,200.00
B. BAHAN
2 Portland Cement kg 3.2500 1,500.00 4,875.00
Jumlah 4,875.00
Total 35,075.00
Nilai HSPK 35,000.00
1 m³ P1 m3 Pekerjaan beton untuk lantai kerja (K.100 s/d K.125)
An. 2.2.1.1.a.(a) Analisa PUPR Bidang
Umum Hal. 264

No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja O.H 1.2000 90,000.00 108,000.00
2 Tukang Batu O.H 0.2000 110,000.00 22,000.00
3 Kepala Tukang O.H 0.0200 120,000.00 2,400.00
Jumlah 132,400.00
B. BAHAN
1 pc kg 227.0000 1,500.00 340,500.00
2 pb m3 0.6437 283,000.00 182,168.15
3 kr m3 0.7143 220,000.00 157,142.86
4 air L 215.0000 50.00 10,750.00
Jumlah 690,561.01
C. ALAT

Jumlah -
Total 822,961.01
Nilai HSPK 822,900.00
TIME SCHEDULE
Kegiatan : Pembangunan Saluran/Drainanse Lingkungan
Pekerjaan : Pembangunan Saluran/Drainanse Lingkungan, Desa Garu
Lokasi : Desa Garu Kec. Baron, Kab. Nganjuk
Kabupaten : Nganjuk
Tahun Anggaran : 2023
Volume pekerjaan :

No Nama Pekerjaan Jumlah Harga Bobot Time Schedule


(%) Ket.
Bulan ke - 1 Bulan ke - 2 Bulan ke - 3
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M - 10 M - 11 M - 12

1 PEKERJAAN PERSIAPAN Rp 1,764,000.00 1.20 0.60 0.60 `


`
2 PEKERJAAN TANAH Rp 2,041,200.00 1.39 1.00 2.00 -1.61
`

3 PEKERJAAN PASANGAN Rp 142,792,608.00 97.40 4.00 7.00 9.00 14.00 14.00 16.00 15.00 18.40 `
`
Jumlah Rp 146,597,808.00 100.00

Progres Rencana 1.60 2.00 2.39 7.00 9.00 14.00 14.00 16.00 15.00 18.40 0.00 0.60
Kumulatif Rencana ###
1.60 3.60 5.99 12.99 21.99 35.99 49.99 65.99 80.99 99.40 99.40 100.00
Realisasi Pekerjaan
Komulatif Ralisasi Pekerjaan ###
Deviasi

Nganjuk, 2023
DIBUAT OLEH
KETUA POKMAS
BAROKAH

MOHAMAD ANWAR
ketua
DAFTAR UPAH PEKERJA
KECAMATAN NGANJUK

NO JENIS KEGIATAN PERORANGAN SATUAN UPAH

1 Tukang Batu 1 Hr Rp 110,000


2 Tukang Kayu 1 Hr Rp 110,000
3 Tukang Besi 1 Hr Rp 110,000
4 Tukang Aspal 1 Hr Rp 110,000
5 Tukang Cat 1 Hr Rp 110,000
6 Tukang pipa 1 Hr Rp 110,000
7 Tukang las konstruksi 1 Hr Rp 110,000
8 Tukang Listrik 1 Hr Rp 110,000
9 Kepala Tukang 1 Hr Rp 120,000
10 Pekerja 1 Hr Rp 90,000
11 Mandor 1 Hr Rp -

DAFTAR HARGA SEWA ALAT


KECAMATAN NGANJUK

NO JENIS KEGIATAN PERORANGAN SATUAN UPAH

1 Molen/concret mixer kapasitas 0,3 m3 1 Hr Rp 30,000


2 Excavator 1 jam Rp 450,000
3 Tripod 1 Hr Rp -
4 Jack Hammer 1 Hr Rp -
5 palu/godam bh Rp -
6 pahat beton bh Rp -
7 Water tanker bh Rp 75,000
7 Pompa air diesel 5 KW 1 jam Rp 20,000
DAFTAR HARGA BAHAN

No. Uraian Satuan harga (Rp)

1 Semen (PC) kg 1,500.00


2 Besi Beton kg 12,000.00
3 Besi Beton Ulir kg 12,500.00
4 Bendrat/Kawat Ikat kg 21,000.00
5 Paku 5 cm dan 7 cm kg 21,000.00
6 Batu Pecah 5-7 cm m3 220,000.00
7 Batu Belah 15-20 cm m3 215,000.00
8 Pasir Urug m3 100,000.00
9 Pasir Pasang/Cor m3 283,000.00
10 Pasir Pasang/Cor kg 176.88
11 Agregat Kasar m3 225,000.00
12 Agregat Kasar kg 136.36
13 Tanah Urug m3 65,000.00
14 Kaso 5/7 cm m3 3,000,000.00
15 Minyak bekisting m3 10,000.00
16 Multiplex 12 mm Lembar 120,000.00
17 Multiplex 18 mm m2 125,000.00
18 Air Liter 50.00
18 Cat kayu kg 60,000.00
GAMBAR
Pembangunan Saluran/Drainase Lingkungan
POKMAS
BAROKAH
KEGIATAN

PEKERJAAN

25
0,35 25
0,35
Pembangunan Saluran/Drainase
Lingkungan
LOKASI
KABUPATEN NGANJUK
REVISI TANGGAL T. TANGAN
60

0,70

80
MENGETAHUI,
KETUA POKMAS
BAROKAH
20

0,30
MOHAMAD ANWAR

350,40
35
0,40
Mengetahui,
Kepala Desa Pandiyang

YUSRO

Judul Gambar Skala


Detail saluran
ANALISIS PRODUKTIVITAS ALAT BERAT PENGGALIAN TANAH DI SALURAN PEMBUANG

KOEFISI
No. URAIAN KODE SATUAN KETERANGAN
EN
I. ASUMSI
1. Jam kerja efektif per hari Tk 7.00 jam
2. Faktor pengembangan tanah Fk 1.20
3. Faktor tanah lepas Fk1 1.00
4 Tahapan kerja
a. Posisi Excavator di darat / dia atas tanggul
b. Excavator mengeruk / menggali tanah
kemudian di letakkan di tanggul sungai
Untuk kemudian diratakan.

II. ALAT
a. Excavator E.11.C
Kapasitas Bucket v 0.70 m3 Daya 138Hp, Berat
operasi 13 ton
Faktor Bucket (Tabel 9) Fb 1.00 Operasi sedang, ta
nah biasa
Faktor Efisiensi Alat (Tabel 4) Fa 0.71 Pemeliharaan mesin
sedang
Waktu Siklus Ts1 menit

Menggali kedalaman 0 - 2m, Memuati bucket, mengayun Sedang (sudut buang 90


T.1 0.31 menit
bermuatan, membuang muatan 6+6,5+6) detik
(Tabel 6.3)
Swing kembali dan lain-lain T.2 0.33 menit waktu putar 180(derajat)
Ts1 0.64 menit

Kap. Produksi/jam = ( V x Fb x Fa x 60 ) / ( Ts.1 x Fk ) Q.1 38.73 m3/jam

Koefisien Alat / m3 = 1 / Q.1 0.025 jam


ANALISIS PRODUKTIVITAS ALAT BERAT PENGGALIAN TANAH +URUGAN DAN PERATAAN TANGGUL LOKASI SEDANG

KOEFISI
No. URAIAN KODE SATUAN KETERANGAN
EN
I. ASUMSI
1. Jam kerja efektif per hari Tk 7.00 jam
2. Faktor pengembangan tanah Fk 1.20
3. Faktor tanah lepas Fk1 1.00
4 Tahapan kerja
a. Posisi Excavator di darat
b. Excavator mengeruk / menggali tanah
kemudian di tuang ke dalam DT.
c. Exavator meratakan dan merapikan hasil galian

II. ALAT
a. Excavator E.11.C
Kapasitas Bucket v 0.50 m3 Daya 138Hp, Berat
operasi 13 ton
Faktor Bucket (Tabel II.2) Fb 0.80 Operasi sedang, ta
nah liat basah
Faktor Efisiensi Alat (Tabel 4) Fa 0.71 Pemeliharaan mesin
sedang
Waktu Siklus Ts1 menit

Menggali kedalaman 0 - 2m, Memuati bucket, mengayun Sedang (sudut buang 90


T.1 0.37 menit
bermuatan, membuang muatan 9+6,5+6,5) detik
(Tabel 6.3)
Swing kembali, meratakan, memadatkan dan lain-lain T.2 0.33 menit waktu putar 180(derajat)
Ts1 0.70 menit

Kap. Produksi/jam = ( V x Fb x Fa x 60 ) / ( Ts.1 x Fk ) Q.1 20.29 m3/jam

Koefisien Alat / m3 = 1 / Q.1 0.049 jam


ANALISIS BIAYA OPERASI ALAT BERAT EXCAVATOR
UNTUK PENGGALIAN TANAH DI SUNGAI

PERHITUNGAN BIAYA
NO. URAIAN KODE SATUAN KETERANGAN
OPERASI PERALATAN
A. URAIAN PERALATAN
1 Jenis Peralatan - - Excavator
2 Merk/Tipe - - 80-140HP
3 Tenaga Pw HP 138.00
4 Kapasitas Cp - 0.50
5 Umur Ekonomis A Tahun 10.00
6 Jam Operasi Dalam 1 Tahun W Jam 2,000.00
7 Harga Alat B Rp. 1,077,500,000

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat C Rp. 107,750,000.00 Suku Bunga
I= 10%
1 x (1+i)A
Faktor Angsuran Modal = D - 0.16275
(1+I)A-1
2 Biaya Pasti Per Jam :
a. Biaya Pengembalian (B - C) x D
= E Rp/Jam 78,911.17
Modal W

B Asuransi
b. Asuransi, dll. = P x F Rp/Jam 1,077.50
W P= 0.2%

Biaya Pasti per Jam G = (E+F) G Rp/Jam 79,988.67

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12%-15%) x Pw x Ms H Rp/Jam 184,437.00 13.50%

2 Pelumas = (2,5%-3%) x Pw x Mp I Rp/Jam 154,560.00 2.80%

B 43,100.00 8.00%
Biaya Bengkel = (6,25% - 8,75%) x J Rp/Jam
W

Perawatan dan B 83,506.25 15.50%


3 = (12,5% - 17,5%) x K Rp/Jam
Perbaikan W

4 Operator = (m orang/jam) x U1 M Rp/Jam 24,000.00

5 Pembantu Operator = (n orang/jam) x U2 L Rp/Jam 20,000.00

Biaya Operasi (per jam) P Rp/Jam 509,603.25

D. BIAYA OPERASI ALAT / JAM = (G+P) S Rp/Jam 589,591.92

E. LAIN - LAIN
1 Bahan Bakar Premium (non subsidi) Mb Liter 8,150.00
2 Bahan Bakar Solar (non subsidi) Ms Liter 9,900.00
3 Minyak Pelumas Mp Liter 40,000.00

ANALISIS BIAYA OPERASI ALAT DUMP TRUCK


UNTUK PENGGALIAN DARAT

PERHITUNGAN BIAYA
NO. URAIAN KODE SATUAN KETERANGAN
OPERASI PERALATAN
A. URAIAN PERALATAN
1 Jenis Peralatan - - Excavator
2 Merk/Tipe - - 3 - 4 M3
3 Tenaga Pw HP 100.00
4 Kapasitas Cp - 3.50
5 Umur Ekonomis A Tahun 10.00
6 Jam Operasi Dalam 1 Tahun W Jam 2,000.00
7 Harga Alat B Rp. 368,750,000

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat C Rp. 36,875,000.00 Suku Bunga
I= 10%
1 x (1+i)A
Faktor Angsuran Modal = D - 0.16275
(1+I)A-1
2 Biaya Pasti Per Jam :
a. Biaya Pengembalian (B - C) x D
= E Rp/Jam 27,005.56
Modal W

B Asuransi
b. Asuransi, dll. = P x F Rp/Jam 368.75
W P= 0.2%

Biaya Pasti per Jam G = (E+F) G Rp/Jam 27,374.31

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12%-15%) x Pw x Ms H Rp/Jam 118,800.00 12.00%

2 Pelumas = (2,5%-3%) x Pw x Mp I Rp/Jam 100,000.00 2.50%

B 14,750.00 6.25%
Biaya Bengkel = (6,25% - 8,75%) x J Rp/Jam
W

Perawatan dan B 28,578.13 12.50%


3 = (12,5% - 17,5%) x K Rp/Jam
Perbaikan W

4 Operator = (m orang/jam) x U1 M Rp/Jam #NAME?

5 Pembantu Operator = (n orang/jam) x U2 L Rp/Jam #NAME?

Biaya Operasi (per jam) P Rp/Jam #NAME?

D. BIAYA OPERASI ALAT / JAM = (G+P) S Rp/Jam #NAME?


E. LAIN - LAIN
1 Bahan Bakar Premium (non subsidi) Mb Liter 8,150.00
2 Bahan Bakar Solar (non subsidi) Ms Liter 9,900.00
3 Minyak Pelumas Mp Liter 40,000.00
TM.02.a Menggali dengan Excavator 1
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A. Tenaga Kerja
1 Pekerja L.01 jam #NAME? #NAME?
2 Mandor L.04 jam - -
Jumlah Harga Tenaga Kerja #NAME?
B Bahan
1 -
Jumlah Harga Bahan -

C Peralatan
1 Excavator E.11.c jam 0.0490 589,591.92 28,890.00
Jumlah Harga Peralatan 28,890.00

D Jumlah Harga Tenaga, Bahan, dan Peralatan (A+B+C) #NAME?


E Harga Satuan Pekerjaan per - m3 (D+E) #NAME?

TM.02.a Menggali dengan Excavator 2


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A. Tenaga Kerja
1 Pekerja L.01 jam #NAME? #NAME?
2 Mandor L.04 jam - -
Jumlah Harga Tenaga Kerja #NAME?
B Bahan
1 -
Jumlah Harga Bahan -

C Peralatan
1 Excavator E.11.c jam 0.0250 589,591.92 14,739.80
Jumlah Harga Peralatan 14,739.80

D Jumlah Harga Tenaga, Bahan, dan Peralatan (A+B+C) #NAME?


E Harga Satuan Pekerjaan per - m3 (D+E) #NAME?

TM.02.B.2 Mengangkut Hasil galian Material Jarak 5 Km


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A. Tenaga Kerja
1 Pekerja L.01 jam -
2 Mandor L.04 jam - -
Jumlah Harga Tenaga Kerja -
B Bahan
1 -
Jumlah Harga Bahan -

C Peralatan
1 Dumptruck E.08.b jam 0.2114 #NAME? #NAME?
Jumlah Harga Peralatan #NAME?

D Jumlah Harga Tenaga, Bahan, dan Peralatan (A+B+C) #NAME?


E Harga Satuan Pekerjaan per - m3 (D+E) #NAME?

TM.02.B.2 Mengangkut Hasil galian Material Jarak 3 Km


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A. Tenaga Kerja
1 Pekerja L.01 jam -
2 Mandor L.04 jam - -
Jumlah Harga Tenaga Kerja -
B Bahan
1 -
Jumlah Harga Bahan -

C Peralatan
1 Dumptruck E.08.b jam 0.1489 #NAME? #NAME?
Jumlah Harga Peralatan #NAME?

D Jumlah Harga Tenaga, Bahan, dan Peralatan (A+B+C) #NAME?


E Harga Satuan Pekerjaan per - m3 (D+E) #NAME?
HITUNGAN VOLUME BANGUNAN

NAMA : PERENCANAAN DRAINASE SALURAN PEMBUANG GUNGGUNG


VOLUME
No. SKETSA PERHITUNGAN
pas. Batu BT. Muka
m3 m2
Pas. Batu Gunung

Pondasi:
0.40 x 0.30 x 262.50 x 2.00 = 63.00 m3
Struktur
0.30 + 0.40 x 1.00 x 262.50 x 2.00 = 183.75 m3
2.00
Pengurangan Batu Muka
1.00 x 262.50 x 0.10 x 2.00 = 52.50 m3
299.25 m3

Pasangan Ex.Bongkaran = 299.25 x 0.50 = 149.63 m3 149.625

Pas. Batu Muka

0.80 x 262.50 x 2.00 = 420.00 m2

Pasangan Ex.Bongkaran = 420.00 x 0.50 = 210.00 m3 210.000

149.625 210.000
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM : B.0 41.139 7.7914 0 0 0 0 0 8.812 459.3 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
1 Beton tor setempat di hilir Patok B.0
Panjang rata - rata
>> 0.5 x ( 2.8 + 6.58 ) = 4.69 m
Galian Tanah h = 2.92 m
>> 0.5 x ( 2.42 + 3.59 ) x 2.92 x 4.69 41.14
Timbunan
>> 41.14 - ( ( 2.42 x 2.42 ) x 4.69 ) +( 7.79
Konstruksi Pengaspalan ))
Beton bertulang U
>> 0.21 x 2.21 x 2 x 4.69 4.35
>> 0.21 x 2.00 x 1 x 4.69 1.97
>> 0.15 x 0.15 x 4.69 0.11
Beton Cover
>> 0.21 x 2.42 x 1 x 4.69 2.38

Tulangan U_dicth L = 4.69 m


No L Dia Jrk Jum BD Berat
1 3.58 D-13- 250 20 0.995 71.242 71.24
2 2.17 D-13- 125 39 0.995 84.207 84.21
3 1.94 f 10- 125 77 0.620 92.616 92.62
4 2.41 f 12- 125 77 0.887 164.6 164.60
5 6.73 D-13- 250 20 0.995 133.93 133.93
Bagi 4.69 f 8 - 120 112 0.393 206.44 206.44

Cover
No L Dia Jrk Jum BD Berat
6 2.36 D-19- 150 32 2.25 169.92 169.92
7 2.36 f 12- 125 39 0.887 81.639 81.64
Bagi 4.69 f 8- 125 40 0.393 73.727 73.73
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM : B.0 41.139 7.7914 0 0 0 0 0 8.812 459.3 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
2
Begesting
>> 2.21 x 4.69 x 4 41.46
1 D13-250 1.79x2 5x2
>> 2.00 x 4.69 9.38

Lebar = 3.42 m
2 D13-125 2.17 11

Agregat B =
3 Ø10-125 0.97x2 11x2
>> 0.30 x 0.76 x 4.69 = 1.07 m3
Agregrat A
>> 0.20 x 3.42 x 4.69 = 3.21 m3
AC-BC,t=6 cm
4
Ø10-125 2.41 11x2
>> 0.06 x 3.42 x 4.69 = 0.96 m3
AC-WC,t=4 cm
3 >> 0.04 x 3.42 x 4.69 = 0.64 m3
Konstruksi Peng Aspalan 5.88 m3

D13-250 6.73 6

U-Dictk ukuran 100 , 100 , 120 cm


Panjang = 8.4 m >> 6 buah
6 D19-150 2.36 9
Tinggi :
7 Ø12-10 2.36 13 Galian tanah : 1.54 m
>> 0.5 x ( 1.20 + 1.82 ) x 1.54 x 8.40 19.51
U_ditch
>> Ukuran 100,100,120 = 6 buah
>> Cover 100,0.12 x 120 = 6 buah
AC-BC,t=6 cm
>> 0.06 x 1.50 x 8.40 = 0.76 m3
AC-WC,t=4 cm
>> 0.04 x 1.50 x 8.40 = 0.50 m3
Konstruksi Peng Aspalan 1.26 m3
Jumlah 60.65 7.79 0.00 0.00 0.00 0.00 0.00 8.81 619.02 459.30 50.84
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM : P.14 + 24 m 49.87 11.6301 0 0 0 0 0 9.2628 532.23 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
1 Beton tor setempat di hilir Patok P.14 + 24

Panjang rata - rata = 4.00 m


Galian Tanah h = 3.24 m
>> 0.5 x ( 3.20 + 4.50 ) x 3.24 x 4.00 49.87
Timbunan
>> 49.87 - ( ( 3.00 x 2.92 ) x 4.00 ) +( 11.63
Konstruksi Pengaspalan ))
Beton bertulang U
>> 0.21 x 2.71 x 2 x 4.00 4.55
>> 0.21 x 2.50 x 1 x 4.00 2.10
>> 0.15 x 0.15 x 4.00 0.09
Beton Cover
>> 0.21 x 3.00 x 1 x 4.00 2.52

Tulangan U_dicth L = 4.00 m


No L Dia Jrk Jum BD Berat
1 4.2 D-13- 250 17 0.995 71.043 71.04
2 3.48 D-13- 125 33 0.995 114.27 114.27
3 1.92 f 10- 125 66 0.620 78.566 78.57
4 5.82 f 12- 125 66 0.887 340.71 340.71
5 8.07 D-13- 250 17 0.995 136.5 136.50
Bagi 4.00 f 8 - 120 140 0.393 220.08 220.08

Cover
No L Dia Jrk Jum BD Berat
6 3.34 D-19- 150 28 2.25 210.42 210.42
7 3.34 f 12- 125 33 0.887 97.765 97.77
Bagi 4.00 f 8- 125 48 0.393 75.456 75.46
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM : P.14 + 24 m 49.87 11.6301 0 0 0 0 0 9.2628 532.23 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
2
Begesting
>> 2.5 x 4.00 x 4 40.00
1 D13-250 1.79x2 5x2
>> 3.00 x 4.00 12.00

Lebar = 4 m
2 D13-125 2.17 11

Agregat B =
3 Ø10-125 0.97x2 11x2
>> 0.30 x 0.80 x 4.00 = 0.96 m3
Agregrat A
>> 0.20 x 0.80 x 4.00 = 0.64 m3
AC-BC,t=6 cm
4
Ø10-125 2.41 11x2
>> 0.06 x 4.00 x 4.00 = 0.96 m3
AC-WC,t=4 cm
3 >> 0.04 x 4.00 x 4.00 = 0.64 m3
Konstruksi Peng Aspalan 3.20 m3

D13-250 6.73 6

5
U-Dictk ukuran 100 , 100 , 120 cm
Panjang = 10.8 m >> 9 buah
Tinggi :
6 D19-150 2.36 9
Galian tanah : 1.54 m
7 Ø12-10 2.36 13 >> 0.5 x ( 1.20 + 1.82 ) x 1.54 x 10.80 25.08
U_ditch
>> Ukuran 100,100,120 = 9 buah
>> Cover 100,0.12 x 120 = 9 buah
AC-BC,t=6 cm
>> 0.06 x 1.50 x 8.40 = 0.76 m3
AC-WC,t=4 cm
>> 0.04 x 1.50 x 8.40 = 0.50 m3
Konstruksi Peng Aspalan 1.26 m3
Timbunan tanah
>> 25.08 -( 1.24 x 1.24 x 10.8 ) +(1.26 ) = 7.21498
Jumlah 74.95 18.85 0.00 0.00 0.00 0.00 0.00 9.26 812.58 532.23 52.00
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM P.12 + 19 m 8.3763 1.59024 0 0 0 0 0 1.719 99.729 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
1 Beton tor setempat di hilir Patok P.14 + 12 m
Panjang rata - rata
>> 0.5 x ( 1.3 + 0.80 ) = 1.03 m
Galian Tanah h = 2.74 m
>> 0.5 x ( 2.42 + 3.52 ) x 2.74 x 1.03 8.38
Timbunan
>> 8.38 - ( ( 2.42 x 2.42 ) x 1.03 ) +( 1.59
Konstruksi Pengaspalan ))
Beton bertulang U
>> 0.21 x 2.21 x 2 x 1.03 0.96
>> 0.21 x 1.50 x 1 x 1.03 0.32
>> 0.15 x 0.15 x 1.03 0.02
Beton Cover
>> 0.21 x 1.92 x 1 x 1.03 0.42

Tulangan U_dicth L = 1.03 m


No L Dia Jrk Jum BD Berat
1 4.08 D-13- 250 5 0.995 20.298 20.30
2 1.98 D-13- 125 9 0.995 17.731 17.73
3 1.92 f 10- 125 18 0.620 21.427 21.43
4 4.38 f 12- 125 18 0.887 69.931 69.93
5 5.6 D-13- 250 5 0.995 27.86 27.86
Bagi 1.03 f 8 - 120 99 0.393 40.074 40.07

Cover
No L Dia Jrk Jum BD Berat
6 1.88 D-19- 150 8 2.25 33.84 33.84
7 1.88 f 12- 125 9 0.887 15.008 15.01
Bagi 1.03 f 8- 125 31 0.393 12.548 12.55
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM P.12 + 19 m 8.3763 1.59024 0 0 0 0 0 1.719 99.729 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
2
Begesting
>> 2.21 x 1.03 x 4 9.11
1 D13-250 1.79x2 5x2
>> 2.00 x 1.03 2.06

Lebar = 3.52 m
2 D13-125 2.17 11

Agregat B =
3 Ø10-125 0.97x2 11x2
>> 0.30 x 0.76 x 1.03 = 0.23 m3
Agregrat A
>> 0.20 x 0.76 x 1.03 = 0.16 m3
AC-BC,t=6 cm
4
Ø10-125 2.41 11x2
>> 0.06 x 3.52 x 1.03 = 0.22 m3
AC-WC,t=4 cm
3 >> 0.04 x 3.52 x 1.03 = 0.15 m3
Konstruksi Peng Aspalan 0.75 m3

D13-250 6.73 6

6 D19-150 2.36 9

7 Ø12-10 2.36 13

Jumlah 8.38 1.59 0.00 0.00 0.00 0.00 0.00 1.72 158.99 99.73 11.17
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM P.3 + 14 m 18.298 3.47382 0 0 0 0 0 3.755 201.43 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
1 Beton tor setempat di hilir Patok P.3 + 14 m
Panjang rata - rata
>> 0.5 x ( 1.5 + 3.00 ) = 2.25 m
Galian Tanah h = 2.74 m
>> 0.5 x ( 2.42 + 3.52 ) x 2.74 x 2.25 18.30
Timbunan
>> 18.30 - ( ( 2.42 x 2.42 ) x 2.25 ) +( 3.47
Konstruksi Pengaspalan ))
Beton bertulang U
>> 0.21 x 2.21 x 2 x 2.25 2.09
>> 0.21 x 1.50 x 1 x 2.25 0.71
>> 0.15 x 0.15 x 2.25 0.05
Beton Cover
>> 0.21 x 1.92 x 1 x 2.25 0.91

Tulangan U_dicth L = 2.25 m


No L Dia Jrk Jum BD Berat
1 4.08 D-13- 250 10 0.995 40.596 40.60
2 1.98 D-13- 125 19 0.995 37.432 37.43
3 1.92 f 10- 125 38 0.620 45.235 45.24
4 4.38 f 12- 125 38 0.887 147.63 147.63
5 5.6 D-13- 250 10 0.995 55.72 55.72
Bagi 2.25 f 8 - 120 99 0.393 87.541 87.54

Cover
No L Dia Jrk Jum BD Berat
6 1.88 D-19- 150 16 2.25 67.68 67.68
7 1.88 f 12- 125 19 0.887 31.684 31.68
Bagi 2.25 f 8- 125 31 0.393 27.412 27.41
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM P.3 + 14 m 18.298 3.47382 0 0 0 0 0 3.755 201.43 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
2
Begesting
>> 2.21 x 2.25 x 4 19.89
1 D13-250 1.79x2 5x2
>> 2.00 x 2.25 4.50

Lebar = 3.52 m
2 D13-125 2.17 11

Agregat B =
3 Ø10-125 0.97x2 11x2
>> 0.30 x 0.76 x 2.25 = 0.51 m3
Agregrat A
>> 0.20 x 0.76 x 2.25 = 0.34 m3
AC-BC,t=6 cm
4
Ø10-125 2.41 11x2
>> 0.06 x 3.52 x 2.25 = 0.48 m3
AC-WC,t=4 cm
3 >> 0.04 x 3.52 x 2.25 = 0.32 m3
Konstruksi Peng Aspalan 1.65 m3

D13-250 6.73 6

6 D19-150 2.36 9

7 Ø12-10 2.36 13

Jumlah 18.30 3.47 0.00 0.00 0.00 0.00 0.00 3.76 339.50 201.43 24.39
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM P.2 + 37 m 9.2708 1.76007 0 0 0 0 0 1.9025 115.56 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
1 Beton tor setempat di hilir Patok P.2 + 37 m
Panjang rata - rata
>> 0.5 x ( 1.8 + 0.50 ) = 1.14 m
Galian Tanah h = 2.74 m
>> 0.5 x ( 2.42 + 3.52 ) x 2.74 x 1.14 9.27
Timbunan
>> 9.27 - ( ( 2.42 x 2.42 ) x 1.14 ) +( 1.76
Konstruksi Pengaspalan ))
Beton bertulang U
>> 0.21 x 2.21 x 2 x 1.14 1.06
>> 0.21 x 1.50 x 1 x 1.14 0.36
>> 0.15 x 0.15 x 1.14 0.03
Beton Cover
>> 0.21 x 1.92 x 1 x 1.14 0.46

Tulangan U_dicth L = 1.14 m


No L Dia Jrk Jum BD Berat
1 4.08 D-13- 250 6 0.995 24.358 24.36
2 1.98 D-13- 125 10 0.995 19.701 19.70
3 1.92 f 10- 125 20 0.620 23.808 23.81
4 4.38 f 12- 125 20 0.887 77.701 77.70
5 5.6 D-13- 250 6 0.995 33.432 33.43
Bagi 1.14 f 8 - 120 99 0.393 44.354 44.35

Cover
No L Dia Jrk Jum BD Berat
6 1.88 D-19- 150 9 2.25 38.07 38.07
7 1.88 f 12- 125 10 0.887 16.676 16.68
Bagi 1.14 f 8- 125 31 0.393 13.889 13.89
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM P.2 + 37 m 9.2708 1.76007 0 0 0 0 0 1.9025 115.56 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Begesting
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
2
Begesting
>> 2.21 x 1.14 x 4 10.08
1 D13-250 1.79x2 5x2
>> 2.00 x 1.14 2.28

Lebar = 3.52 m
2 D13-125 2.17 11

Agregat B =
3 Ø10-125 0.97x2 11x2
>> 0.30 x 0.76 x 1.14 = 0.26 m3
Agregrat A
>> 0.20 x 0.76 x 1.14 = 0.17 m3
AC-BC,t=6 cm
4
Ø10-125 2.41 11x2
>> 0.06 x 3.52 x 1.14 = 0.24 m3
AC-WC,t=4 cm
3 >> 0.04 x 3.52 x 1.14 = 0.16 m3
Konstruksi Peng Aspalan 0.83 m3

D13-250 6.73 6

6 D19-150 2.36 9

7 Ø12-10 2.36 13

Jumlah 9.27 1.76 0.00 0.00 0.00 0.00 0.00 1.90 176.43 115.56 12.36
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM U-Dicth yang melewati sal.Primer 136.62 41.4611 0 0 0 0 15.04 12.5 0 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Bt muka
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2

Galian tanah untuk U-Dicth = 16.8 m= 14 bh

Galian Tanah h = 2.74 m


>> 0.5 x ( 2.42 + 3.52 ) x 2.74 x 16.80 136.62
Timbunan kembali
>> 136.6 - ( 2.38 x 2.38 x 16.8 ) 41.46

Lantai dasar saluran


Lebar saluran = 5 m
Panjang Lantai = 25 m m
Tebal lantai = 10 cm

Volume beton = 5.00 x 25 x 0.10 12.50


Dipakai tulangan praktis
f 10 - 125 >> tiap m3 memerlukan = 110.9 kg
>> 12.50 x 110.92 = 1387 kg 1387

Bongkaran pasangan lama : L= 16.00 m


>> 0.94 x 16.00 = 15.04 15.04
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM U-Dicth yang melewati sal.Primer 136.62 41.4611 0 0 0 0 15.04 12.5 0 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Bt muka
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2

Pasangan baru 1 : 4
>> 0.78 x 16.00 = 12.48 12.48
Pasangan Batu Muka
>> (1.28 + 0.86 + 0.66) x 16.00 = 41.6 41.6
Siaran 41.6 41.6
Pleateran :
>> (0.1+0.5+0.1) x 16.00 = 11.2 11.20

Jumlah 136.62 41.46 0.00 12.48 11.20 41.60 15.04 12.50 1386.50 0.00 41.60
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM U-Dicth yang melewati sal.Primer 0 0 0 0 0 0 0 0 0 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Bt muka
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2
HITUNGAN VOLUME BANGUNAN

NAMA : KEGIATAN PERENCANAAN DRAINASE PERKOTAAN


NAMA BANGUNAN / KM U-Dicth yang melewati sal.Primer 0 0 0 0 0 0 0 0 0 0
VOLUME
No. SKETSA PERHITUNGAN
Galian Timb. Geb. Pas. Plest. Siar. Bongk. Bt. Bert. Besi f Besi D Bt muka
m3 m3 m2 m3 m2 m2 m3 m3 Kg kg m2

Jumlah 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
HARGA SATUAN (Rp)
NO NAMA BAHAN MERK / SPESIFIKASI SATUAN
ZONA C
1 2 3 4 5

2. BIAYA BAHAN DAN PERALATAN

2.2. BIAYA BAHAN DAN PERALATAN ZONA C

2.2.1. BAHAN DAN PERALATAN BIDANG PEKERJAAN UMUM

2.2.1.1. BAHAN MENGGUNAKAN BATU, PASIR DAN SEMEN

2.2.1.2. BAHAN BETON CETAKAN


3 Buis Beton Bulat (Riool) 20 x 100 cm buah 55,000
4 Buis Beton Bulat (Riool) 30 x 100 cm buah 65,000
5 Buis Beton Bulat (Riool) 40 x 100 cm buah 75,000
2.2.1.3. BAHAN UNTUK DINDING DAN LANTAI
2.2.1.4. BAHAN MENGGUNAKAN KAYU
1 Kayu Sengon/ Tahun m³ 2,150,000
2 Kayu Gelam / Dolken Panjang 4 meter m³ 5,175,000
2.2.1.5. BAHAN MENGGUNAKAN BESI, BAJA DAN ALUMINIUM
1 Besi Beton Polos 6 mm x 12 m batang 4,887
2 Besi Beton Polos 8 mm x 12 m batang 4,008
3 Besi Beton Polos 10 mm x 12 m batang 3,784
4 Besi Beton Polos 12 mm x 12 m batang 7,036
5 Besi Beton Polos 16 mm x 12 m batang 66,700
6 Besi Beton Polos 19 mm x 12 m batang 76,475
7 Besi Beton Polos 22 mm x 12 m batang 70,150
2.2.1.6. BAHAN JENIS PAKU, MUR DAN BAUT
2.2.1.7. BAHAN UNTUK INSTALASI AIR NON BESI
2.2.1.8. BAHAN UNTUK PENGECATAN
2.2.1.9. BAHAN PENGGANTUNG DAN PENGUNCI
2.2.1.10. BAHAN UNTUK KAMAR MANDI DAN WC/URINOIR
2.2.1.11. BAHAN UNTUK INSTALASI LISTRIK
2.2.1.12. BAHAN UNTUK PENUTUP ATAP DAN PLAFOND
2.2.1.13. BAHAN MENGGUNAKAN KACA
2.2.1.14. BAHAN FURNISHING INTERIOR DECORATION
2.2.1.15. BAHAN UNTUK JALAN
1 Paving Block Straight/Bata Abu-abu 6 cm ( 1m² = 44 pcs ) m² 58,000
2 Paving Block Straight/Bata Atas Merah 6 cm (1m²=44 pcs) m² 103,500
3 Paving Block Straight/Bata Full Merah 6 cm (1m² =44 pcs ) m² 115,000
2.2.1.16. BAHAN DAN PERALATAN LAIN UNTUK BIDANG PEKERJAAN
UMUM
1 Air Tawar Terjangkau PDAM m³ 28,175
2 Air Tawar Tidak Terjangkau PDAM m³ 62,450
HARGA SATUAN (Rp)
NO NAMA BAHAN MERK / SPESIFIKASI SATUAN
ZONA D
1 2 3 4 5
2. BIAYA BAHAN DAN PERALATAN

2.3. BIAYA BAHAN DAN PERALATAN ZONA D


2.3.1. BAHAN DAN PERALATAN BIDANG
PEKERJAAN UMUM
2.3.1.1. BAHAN MENGGUNAKAN BATU, PASIR DAN
SEMEN
1 Batu Gunung/Kali m³ 218,500
2 Batu Putih Besar/Batu Kapur m³ 207,000
3 Pasir Pasang Tegal m³ 253,000
4 Roster 20/20 bata pres buah 11,500
4 Roster Keramik Trisensa, Standart 20x20 buah 40,250

4 Roster Keramik Trisensa, Standart 30x30 buah 51,750


5 Semen Portland Gresik / 40 kg sak 70,725
6 Semen Putih Tiga Roda / 40 kg sak 112,125
7 Semen Warna Khusus keramik kg 12,075
2.3.1.2. BAHAN UNTUK DINDING DAN LANTAI
1 Nat Sriti sachet 9,200
2.3.1.3. BAHAN MENGGUNAKAN KAYU
1 Triplek Tebal 3 mm ( 1.22 x 2.44 m¹ ) lbr 71,300
2 Triplek Tebal 6 mm ( 1.22 x 2.44 m¹ ) lbr 94,900
3 Triplek Tebal 9 mm ( 1.22 x 2.44 m¹ ) lbr 138,000
2.3.1.4. BAHAN MENGGUNAKAN BESI, BAJA DAN
ALUMINIUM
1 Besi Beton Polos 6 mm x 12 m batang 29,900
2 Besi Beton Polos 8 mm x 12 m batang 42,550
3 Besi Beton Polos 10 mm x 12 m batang 56,350
4 Besi Beton Polos 12 mm x 12 m batang 79,350
5 Kawat Bendrat Lemas kg 20,700
2.3.1.5. BAHAN JENIS PAKU, MUR DAN BAUT
1 Paku 2 cm kg 17,250
2 Paku 2.5 cm kg 17,250
3 Paku 3 cm kg 17,250
4 Paku 4 cm kg 17,250
5 Paku 5 cm kg 17,250
6 Paku 6 cm kg 17,250
7 Paku 7 cm kg 17,250
8 Paku 10 cm kg 17,250
9 Paku 12 cm kg 17,250
2.3.1.6.
BAHAN UNTUK INSTALASI AIR NON BESI

1 Knee PVC Maspion, TS Ø 3/4" buah 8,050


2 Pipa PVC Maspion, AW-MOF Ø1/2" Outside buah 17,250
22mm, panjang 6 m
3 Pipa PVC Maspion, AW-MOF Ø 3/4" Outside buah 23,000
26mm, panjang 6 m
4 Pipa PVC Maspion, AW-MOF Ø 1" Outside buah 17,250
32mm, panjang 6 m
5 Pipa PVC Maspion, AW-MOF Ø 3" Outside buah 13,250
89mm, panjang 6 m
6 Pipa PVC Maspion, AW-MOF Ø 4" Outside buah 218,500
114mm, panjang 6 m
2.3.1.7. BAHAN UNTUK PENGECATAN
1 Cat Kayu/Besi Emco-Segitiga 1 kg kg 67,850
2 Cat Kayu/Besi Emco-Bintang 1 kg kg 79,350
3 Cat Tembok Altex khusus / 5kg galon 14,750
4 Cat Tembok Altex biasa / 5 kg galon 97,750
5 Kertas Gosok No. 360 lbr 6,325
6 Kertas Gosok No. 100 lbr 6,325
7 Kertas Gosok No. 150 lbr 6,325
8 Kertas Gosok No. 280 lbr 6,325
9 Kol - Ter kg 28,750
10 Lapisan Anti Bocor Aqua Proof 4 kg galon 239,200
11 Plamur Cap Pedang kg 29,900
12 Plamur Kayu Cap Pedang kg 31,625
13 Spiritus liter 16,700
2.3.1.8.
BAHAN PENGGANTUNG DAN PENGUNCI

1 Gerendel Bossini ukuran 3 buah 14,950


2 Gerendel Bossini ukuran 2 buah 11,500
3 Gembok Dior 20 mm buah 8,050
4 Gembok Dior 30 mm buah 13,800
5 Gembok Besar Merk Globe buah 26,450
6 Kunci 2x putar Kodai buah 43,700
7 Kunci 2x putar buah 43,700
2.3.1.9. BAHAN UNTUK KAMAR MANDI DAN
WC/URINOIR
1 Kloset Jongkok Porselint Setara INA (Warna muda) buah 166,750
2 Kloset Jongkok Porselint Setara INA (Warna tua) buah 161,000
2.3.1.10. BAHAN UNTUK PENUTUP ATAP DAN
PLAFOND

1 Asbes Gelombang Besar Tebal 5 mm (3.05x1.05) lbr 92,000


2 Asbes Gelombang Kecil Uk : 1.1x2.05 lbr 71,300
3 Nok Setel Gelombang besar m¹ 74,750
4 Nok Setel Gelombang kecil m¹ 40,250
5 Talang Seng Lebar 60 cm m¹ 7,475
6 Talang Seng Lebar 50 cm m¹ 8,625
7 Seng BJLS 30 lebar 60 cm m¹ 19,550
8 Seng BJLS 30 lebar 90 cm m¹ 27,600
2.3.1.11. BAHAN FURNISHING INTERIOR
DECORATION
1 Karpet Hitam Lebar 110 m 11,500
2 Karpet Hitam Lebar 90 m 9,200
3 Karpet Hitam Lebar 60 m 6,900
4 Karpet Hitam Lebar 50 m 5,750
2.3.1.12. BAHAN DAN PERALATAN LAIN UNTUK
BIDANG PEKERJAAN UMUM
1 Kuas 3 dim buah 14,950
2 Kuas 4 dim buah 19,550
3 Kuas 5 dim buah 25,300
4 Lem FOX Bungkusan 350 gr sachet 8,050
5 Lem Rajawali kg 14,375
6 Meteran Tovo, 5m buah 17,250
7 Meteran Tovo, 3m buah 11,500
8 Selang Timbangan m 5,750
9 Skraper (Kapi) Plastik buah 9,200
10 Timba Cor buah 7,750
HARGA SATUAN (Rp)
NO NAMA BAHAN MERK / SPESIFIKASI SATUAN
ZONA E
1 2 3 4 5

2. BIAYA BAHAN DAN PERALATAN

2.4. BIAYA BAHAN DAN PERALATAN ZONA E


2.4.1. BAHAN DAN PERALATAN BIDANG
PEKERJAAN UMUM
2.4.1.1. BAHAN MENGGUNAKAN BATU, PASIR DAN
SEMEN

1 Batu Bata Putih buah 1,150


2 Batu Belah 15/20 cm m³ 172,500
3 Batu Belah 10/15 cm m³ 172,500
4 Batu Pecah 5/7 cm m³ 230,000
5 Batu Pecah 3/5 cm m³ 287,500
6 Batu Pecah 2/3 cm m³ 316,250
7 Batu Pecah Mesin 0/1 cm m³ 460,000

8 Batu Pecah Mesin 1/2 cm m³ 402,500

9 Batu Pecah Mesin 1/1.5 cm m³ 402,500

10 Batu Pecah Mesin 2/3 cm m³ 402,500


11 Batu Pecah Mesin (3/5 cm) dan (4/6 cm) m³ 402,500
12 Batu Pecah Mesin 5/7 cm m³ 402,500
13 Batu Pecah Mesin 0.5 / 1 cm m³ 402,500
14 Batu Pecah Mesin 1/1 cm m³ 402,500
15 Batu Pecah Mesin 1-2 cm m³ 402,500
16 Batu Putih Besar/Batu Kapur buah 1,150
17 Kapur Bubuk m³ 460,000
18 Pasir Hitam Cor / Pasir Beton m³ 460,000
19 Pasir Halus m³ 460,000

20 Pasir Lokal Untuk wil. Kec. Ra'as, Pulau Sepudi m³ 172,500

21 Pasir Sawur m³ 172,500


22 Sirtu/Tasirtu m³ 230,000
23 Semen Portland Gresik / 40 kg sak 80,500

24 Semen Portland Tiga Roda / 40 kg sak 74,750

25 Tanah Urug/Pasir Urug (Umum) m³ 172,500


2.4.1.2.
BAHAN UNTUK KAMAR MANDI DAN
WC/URINOIR

1 Kloset Jongkok Porselint Setara INA (Warna Putih) buah 402,500

2.4.1.3. BAHAN UNTUK PENUTUP ATAP DAN


PLAFOND

1 Asbes Plat Gresik Uk : 90 cm x 180 cm lbr 46,000


2 Fiber Gelombang Tebal Uk : 1.10 x 1.80 lbr 57,500
3 Fiber Gelombang Tebal Uk : 1.10 x 2.10 lbr 63,250
4 Talang Karet Lebar 50 cm m¹ 20,125
5 Talang Karet Hitam Lebar 60 cm m¹ 23,000
2.4.1.4. BAHAN UNTUK JALAN
1 Air Tawar Tidak Terjangkau PDAM m³ 69,000
2 Timba Cor buah 8,050
HARGA SATUAN (Rp)
NO NAMA BAHAN MERK / SPESIFIKASI SATUAN
ZONA F
1 2 3 4

2. BIAYA BAHAN DAN PERALATAN

2.5 BIAYA BAHAN DAN PERALATAN ZONA F


2.5.1. BAHAN DAN PERALATAN BIDANG PEKERJAAN
UMUM

2.5.1.1. BAHAN MENGGUNAKAN BATU, PASIR DAN


SEMEN

1 Batu Bata Merah kelas 2 buah 1,150


2 Batu Gunung/Kali m³ 230,000
3 Batu Gunung/Kali Wil. Kepulauan Sapeken m³ 287,500
4 Batu Belah 2/3 cm m³ 431,250
5 Batu Belah 3/5 cm m³ 345,000
6 Batu Belah 4/7 cm m³ 345,000
7 Batu Belah 10/15 cm m³ 230,000
8 Batu Pecah Mesin 0/1 cm m³ 575,000
9 Batu Pecah Mesin 1/2 cm m³ 575,000
10 Batu Pecah Mesin 1/1.5 cm m³ 575,000
11 Batu Pecah Mesin 2/3 cm m³ 575,000
12 Batu Pecah Mesin (3/5 cm) dan (4/6 cm) m³ 575,000
13 Batu Pecah Mesin 5/7 cm m³ 575,000
14 Batu Pecah Mesin 0.5 / 1 cm m³ 575,000
15 Batu Pecah Mesin 1/1 cm m³ 575,000
16 Batu Pecah Mesin 1-2 cm m³ 575,000
17 Batu Putih Besar/Batu Kapur buah 230,000
18 Batu Putih Besar untuk wil.Kec. Masalembu, Arjasa, buah 230,000
Kangayan & Sapeken
19 Kapur Bubuk m³ 40,250
20 Pasir Hitam Cor / Pasir Beton m³ 287,500
21 Pasir Lokal untuk wil.Kec. Kangayan & Sapeken m³ 287,500

22 Pasir Pasang Tegal m³ 149,500


23 Pasir Sawur m³ 287,500
24 Semen Portland Gresik / 40 kg sak 86,250
25 Semen Warna Khusus keramik kg 11,500
26 Serbuk Batu Putih m³ 287,500
27 Tanah Urug/Pasir Urug (Umum) m³ 287,500
2.5.1.2. BAHAN MENGGUNAKAN KAYU

1 Kayu Jati Kangean m³ 2,300,000


2 Triplek Tebal 3 mm ( 1.20 x 2.40 m¹ ) lbr 69,000
3 Triplek Tebal 4 mm ( 0.90 x 2.10 m¹ ) lbr 80,500
4 Triplek Tebal 6 mm ( 1.20 x 2.40 m¹ ) lbr 103,500
5 Triplek Tebal 9 mm ( 1.20 x 2.40 m¹ ) lbr 155,250
2.5.1.3. BAHAN MENGGUNAKAN BESI, BAJA DAN
ALUMINIUM
1 Kran Air SAN EI, PSN34-85 buah 40,250
2 Kran Air Wina Kuningan Ø 1/2" buah 17,250
3 Kran Air Wina Kuningan Ø 3/4" buah 17,250
2.5.1.4. BAHAN JENIS PAKU, MUR DAN BAUT

1 Paku 2 cm kg 17,250
2 Paku 2.5 cm kg 17,250
3 Paku 3 cm kg 17,250
4 Paku 4 cm kg 17,250
5 Paku 5 cm kg 17,250
6 Paku 6 cm kg 17,250
7 Paku 7 cm kg 17,250
8 Paku 10 cm kg 17,250
9 Paku 12 cm kg 17,250
2.5.1.5.
BAHAN UNTUK INSTALASI AIR NON BESI
1 Pipa PVC Maspion, AW Ø 1/2" Outside 22mm, buah 28,750
panjang 4 m
2 Pipa PVC Maspion, AW Ø 3/4" Outside 26mm, buah 31,050
panjang 4 m
3 Pipa PVC Maspion, AW Ø 1" Outside 32mm, buah 34,500
panjang 4 m

4 Pipa PVC Maspion, AW Ø 3" Outside 89mm, buah 57,500


panjang 4 m
5 Pipa PVC Maspion, AW Ø 4" Outside 114mm, buah 74,750
panjang 4 m

6 Tandon Air Plastik Model TDA/Profil Tank 650 liter buah 1,063,750

2.5.1.6. BAHAN UNTUK PENGECATAN

1 Cat Kayu/Besi Emco-Standart 1 kg kg 74,750

2 Lapisan Anti Bocor Aqua Proof 4 kg galon 86,250

3 Minyak Cat / Afduner Thiner B liter 28,750

4 Plamur Kayu Cap Pedang kg 34,500

5 Spiritus liter 19,550


2.5.1.7.
BAHAN PENGGANTUNG DAN PENGUNCI
1 Gembok Besar Merk Globe buah 34,500
2.5.1.8. BAHAN UNTUK KAMAR MANDI DAN
WC/URINOIR

1 Bak Mandi Oval, Fiber, 55 cm unit 517,500


2
Bak Mandi Kotak, Fiber, 53 cm unit 402,500
3
Kloset Jongkok Porselint Setara INA (Warna muda) buah 172,500

2.5.1.9. BAHAN UNTUK PENUTUP ATAP DAN


PLAFOND

1 Lis Plafond Gips m¹ 51,750

2 Talang Karet Merah Lebar 60 cm m¹ 11,500

3 Talang Karet Hitam Lebar 60 cm m¹ 13,800

4 Tepung Gypsum SGP kg 69,000

5 Kaca Polos Tebal 3 mm m² 112,700

6 Kaca Polos Tebal 5 mm m² 132,250

7 Kaca Rayband Tebal 5 mm m² 127,075


2.5.1.10. BAHAN UNTUK JALAN

1 Aspal Drum 2,070,000


2.5.1.11.
BAHAN DAN PERALATAN LAIN UNTUK
BIDANG PEKERJAAN UMUM

1 Kuas 2 dim buah 8,050

2 Kuas 2.5 dim buah 11,500

3 Lem Isarplas lem pipa 45 gram buah 9,200


URAIAN ANALISA ALAT
ANALISA PERMEN PU NO. 28 TH. 2016

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3,5M3 E08
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 3.5 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 138,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 13,800,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 18,525.40 Rupiah
W

b. Asuransi, dll = 0.002 x B F 138.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 18,663.40 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 102,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 100,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 6,038


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 8,625.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L #NAME? Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M #NAME? Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P #NAME? Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S #NAME? Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 #NAME? Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 #NAME? Rp./Jam
4. Bahan Bakar Bensin Mb 8,150.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
ANALISA PERMEN PU NO. 28 TH. 2016

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 133.0 HP
3. Kapasitas Cp 0.93 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 977,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 97,750,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 131,221.55 Rupiah
W

b. Asuransi, dll = 0.002 x B F 977.50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 132,199.05 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 135,660.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 133,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 42,766 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 61,093.75 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L #NAME? Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M #NAME? Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P #NAME? Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S #NAME? Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 #NAME? Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 #NAME? Rp./Jam
4. Bahan Bakar Bensin Mb 8,150.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Analisa : EI-31 1a
Jenis Pekerjaan : Galian biasa
Satuan : M3
ANALISA PERMEN PU NO. 28 TH. 2016 URAIAN ANALISA HARGA SATUAN

NO. URAIAN KODE KOEF SATUAN KET

I ASUMSI
1. Menggunakan alat berat (cara mekanik)
2. Lokasi Pekerjaan : sepanjang saluran dan bosem
3. Kondisi exesting jalan : sedang / baik
4. Jam kerja efektif per-hari Tk 7.00 Jam
5. Faktor pengembangan bahan Fk 1.20 -
6. Berat Volume Tanah (lepas) D 1.60 ton/m3 1,4-1,8

II METHODE PELAKSANAAN
1. Tanah yang dipotong umumnya berada disisi jalan
2. Penggalian dilakukan dng. menggunakan excavator
3. Selanjutnya Excavator menuangkan meterial hasil
galian ke dalam Dump Truck
4. Dump Truck membuang material hasil galian
disekitar lokasi pekerjaan sejauh L 0.75 Km

III PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
Tidak ada bahan yang diperlukan

2 ALAT
2a. EXCAVATOR
Kapasitas bucket V 0.93 M3
Faktor bucket Fb 1.00 -
Faktor efisiensi alat Fa 0.83 -
Waktu Siklus Ts1
- Menggali / Muat T1 1.32 menit
- Lain - lain T2 0.10 menit
Ts1 1.42 menit
VxFaxFbx60xFk
Kap. Prod./jam = ------------------ Q1 32.615 M3/Jam
Ts1xFk

Koefisien Alat/M3 = 1 : Q1 (E10) 0.0307 Jam

2 DUM TRUCK (E 08)


Kapasitas bak V 3.5000 ton
Faktor efisiensi alat Fa 0.8300
Kecepatan rata-rata bermuatan V1 20.0000 KM/jam
Kecepatan rata-rata kosong V2 30.0000 KM/jam
Waktu Siklus Ts2 Menit
- Muat tempuh isi = (V x 60) (D x Q1) T1 4.0242 Menit
- Waktu tempuh isi = (L : V1) x 60 T2 2.2500 Menit
- Waktu tempuh kosong = (L : V2) x 60 T3 1.5000 Menit
- Lain-lain T4 2.0000 Menit
TS 2 9.7742 Menit

Kapasitas Produksi /Jam = V x Fa x 60 Q2 9.2879 M3/ Jam


D x Fk x Ts2

Koefisien alat M3 = 1 : Q2 (E08) 0.1077 Jam

3 TENAGA
Produksi menentukan : EXCAVATOR Q4 32.62 M3/Jam
Produksi Galian/hari = TkxQ1 Qt 228.31 M3
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang

Koefisien tenaga /M3


- Pekerja = (Tk x P) : Qt (L01) 0.06132 Jam
- Mandor = (Tk x M) : Qt (L03) 0.03066 Jam
Analisa : EI-31 1a
Jenis Pekerjaan : Galian biasa
Satuan : M3
ANALISA PERMEN PU NO. 28 TH. 2016 URAIAN ANALISA HARGA SATUAN

NO. URAIAN KODE KOEF SATUAN KET

I ASUMSI
1. Menggunakan alat berat (cara mekanik)
2. Lokasi Pekerjaan : sepanjang saluran dan bosem
3. Kondisi exesting jalan : sedang / baik
4. Jam kerja efektif per-hari Tk 7.00 Jam
5. Faktor pengembangan bahan Fk 1.20 -
6. Berat Volume Tanah (lepas) D 1.60 ton/m3 1,4-1,8

II METHODE PELAKSANAAN
1. Tanah yang dipotong umumnya berada disisi jalan
2. Penggalian dilakukan dng. menggunakan excavator
3. Selanjutnya Excavator menuangkan meterial hasil
galian ke dalam Dump Truck
4. Dump Truck membuang material hasil galian
disekitar lokasi pekerjaan sejauh L 0.00 Km

III PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
Tidak ada bahan yang diperlukan

2 ALAT
2a. EXCAVATOR
Kapasitas bucket V 0.93 M3
Faktor bucket Fb 1.00 -
Faktor efisiensi alat Fa 0.83 -
Waktu Siklus Ts1
- Menggali / Muat T1 1.32 menit
- Lain - lain T2 0.10 menit
Ts1 1.42 menit
VxFaxFbx60xFk
Kap. Prod./jam = ------------------ Q1 32.615 M3/Jam
Ts1xFk

Koefisien Alat/M3 = 1 : Q1 (E10) 0.0307 Jam

2 DUM TRUCK (E 08)


Kapasitas bak V 3.5000 ton
Faktor efisiensi alat Fa 0.8300
Kecepatan rata-rata bermuatan V1 20.0000 KM/jam
Kecepatan rata-rata kosong V2 30.0000 KM/jam
Waktu Siklus Ts2 Menit
- Muat tempuh isi = (V x 60) (D x Q1) T1 4.0242 Menit
- Waktu tempuh isi = (L : V1) x 60 T2 0.0000 Menit
- Waktu tempuh kosong = (L : V2) x 60 T3 0.0000 Menit
- Lain-lain T4 2.0000 Menit
TS 2 6.0242 Menit

Kapasitas Produksi /Jam = V x Fa x 60 Q2 15.0695 M3/ Jam


D x Fk x Ts2

Koefisien alat M3 = 1 : Q2 (E08) 0.0664 Jam

3 TENAGA
Produksi menentukan : EXCAVATOR Q4 32.62 M3/Jam
Produksi Galian/hari = TkxQ1 Qt 228.31 M3
Kebutuhan tenaga :
- Pekerja P 1.00 orang
- Mandor M 0.20 orang

Koefisien tenaga /M3


- Pekerja = (Tk x P) : Qt (L01) 0.03066 Jam
- Mandor = (Tk x M) : Qt (L03) 0.00613 Jam