Casual Furniture WS
Casual Furniture WS
1 2 3 4 5 6
MPS 70 70 80 90 60 80
Scheduled Receipts
Available Inventory 0 0 0 0 0 0
Net Requirements 70 70 80 90 60 80
Planned Order Receipts 70 70 80 90 60 80
Planned Order Releases 70 70 80 90 60 80
LEVEL 1
Cabinet
Lead Time 2 weeks 1 2 3 4 5 6
Gross Requirements 70 70 80 90 60 80
Scheduled Receipts
Available Inventory 120 50 0 0 0 0 0
Net Requirements 0 20 80 90 60 80
Planned Order Receipts 0 20 80 90 60 80
Planned Order Releases 80 90 60 80 80 70
Shelf (3/bookshelf)
Lead time 1 week 1 2 3 4 5 6
Lot Size: FOQ = 500
Gross Requirements 210 210 240 270 180 240
Scheduled Receipts
Available Inventory 300 90 380 140 370 190 450
Net Requirements 0 120 0 130 0 50
Planned Order Receipts 0 500 0 500 0 500
Planned Order Releases 500 0 500 0 500 0
Bracket (4/bookshelf)
Lead time: 1 week 1 2 3 4 5 6
Lot Size: FOQ = 600
Gross Requirements 280 280 320 360 240 320
Scheduled Receipts 600
Available Inventory 320 40 320 560 320 0
Net Requirements 0 0 280 40 0 0
Planned Order Receipts 0 0 600 600 0 0
Planned Order Releases 0 600 600 0 0 600
7 8
80 70
0 0
80 70
80 70
80 70
LEVEL 2
Back
7 8 Lead Time 1 week 1 2 3 4
80 70 Gross Requirements 80 90 60 80
Scheduled Receipts
0 0 Available Inventory 100 20 0 0 0
80 70 Net Requirements 0 70 60 80
80 70 Planned Order Receipts 0 70 60 80
Planned Order Releases 70 60 80 80
Slide
7 8 Lead Time 1 week 1 2 3 4
Gross Requirements 160 180 120 160
240 210 Scheduled Receipts
Available Inventory 200 40 0 0 0
210 0 Net Requirements 0 140 120 160
0 0 Planned Order Receipts 0 140 120 160
0 0 Planned Order Releases 140 120 160 160
0 0
End
7 8 Lead Time 1 week 1 2 3 4
Gross Requirements 160 180 120 160
320 280 Scheduled Receipts
Available Inventory 200 40 0 0 0
280 0 Net Requirements 0 140 120 160
320 0 Planned Order Receipts 0 140 120 160
600 0 Planned Order Releases 140 120 160 160
0 0
Safety Stock 30
LEVEL 3
Oaksheets
5 6 7 8 Lead Time 1 week 1 2
80 70 0 0 Gross Requirements 850 300
Scheduled Receipts 1000
0 0 0 0 Available Inventory 500 650 350
80 70 0 0 Net Requirements 0 0
80 70 0 0 Planned Order Receipts 0 0
70 0 0 0 Planned Order Releases 0 1000
5 6 7 8
160 140 0 0
0 0 0 0
160 140 0 0
160 140 0 0
140 0 0 0
5 6 7 8
160 140 0 0
0 0 0 0
160 140 0 0
160 140 0 0
140 0 0 0
3 4 5 6 7 8
900 400 850 0 0 0
End
Lead Time 1 week 1 2 3 4 5 6 7
Gross Requirements 160 180 120 160 160 140 0
Scheduled Receipts
Available Inventory 40 0 0 0 0 0 0
Net Requirements 0 140 120 160 160 140 0
Planned Order Receipts 0 140 120 160 160 140 0
Planned Order Releases 140 120 160 160 140 0 0
8
0
0
0
0
0
200
6 7 8
0 0 0
Processing Time
Component (no. of minutes) Week 1 Week 2 Week 3 Week 4
Back 10 70 60 80 80
Processing Time required 700 600 800 800
Side 8 140 120 160 160
Processing Time required 1120 960 1280 1280
End 5 140 120 160 160
Processing Time required 700 600 800 800
Shelf 7 500 0 500 0
Processing Time required 3500 0 3500 0
TOTAL PROCESSING TIME (in minutes) 6020 2160 6380 2880
TOTAL PROCESSING TIME (in hours) 100.33 36 106.33 48