Professional Documents
Culture Documents
ABSTRACT: The North West Rail is Australia’s biggest public transport infrastructure project and
includes 15.5km of twin running tunnels and eight new railway stations, five of which are below
ground. Solutions developed during the reference design have enabled a significant reduction in both
the extent of tunnels in the project, and the depth of underground stations. These amendments to the
business case design, along with the adoption of an undrained tunnel solution, have contributed to
significant improvements for the project including a better customer experience and reductions in
maintenance requirements. This paper outlines the approaches taken to capitalise on opportunities for
an optimum project outcome in regards to the tunnel form, the tunnel alignment and the design
interfaces for the delivery contracts.
1 INTRODUCTION
The North West Rail Link (NWRL) is an AECOM and Parsons Brinckerhoff have been
$AUS 8.3 billion dollar project which is engaged as technical advisors to Transport for
currently under construction in Sydney, New South Wales (TfNSW) for the planning,
Australia. When complete in 2019, the project design and construction of NWRL, including
will connect Sydney’s North West growth the development of a reference design and
region to major business districts using contract documentation for the three major
Sydney’s first rapid transit rail system. Among contracts required to deliver the project. Two of
other works, the project will deliver 23km of the contracts involve the design and
new rail corridor, including 15.5km of twin tube construction (D&C) of major civil infrastructure
rail tunnels and 5 underground rail stations. (tunnels, viaducts and surface structures), whilst
These will be the longest rail tunnels in the third contract involves the design and
Australia. construction of the stations and rail systems,
provision of the rolling stock and operation of
the rail line under a Private Public Partnership
(PPP) contract. This procurement strategy was
adopted to comply with New South Wales
Government requirement to commence
tunnelling by late 2014 and to remove tunnel
construction risks from the PPP process.
The PPP contract will be awarded after the
commencement of construction for the two
D&C contracts. As such the project required
key design decisions to be made during the
reference design and captured in the contract
documentation to provide surety of delivery
across the contract interfaces, and to provide
Figure 1. Breakthrough of a Sydney Tunnel Boring confidence in the planning approvals process.
Machine (TBM) similar to the future NWRL TBM’s.
1
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
This paper discusses the approach taken with a pH above 5 produces ferric hydroxide
during the development of the reference design deposits in the form of a gelatinous, iron stained
and contract documentation to deliver a sludge similar to that pictured in Figure 2. This
successful whole of life cost solution for the reaction occurs naturally and cannot be con-
NWRL project. The paper focuses on three key trolled or stopped. The problem is a function of
areas where this was achieved; specification of the groundwater chemistry, and the scale of the
the running tunnel form, capitalising on tunnel problem is a function of the amount of ground-
alignment opportunities, and de-risking the
water inflow into the tunnels.
design interfaces between delivery contracts.
2 PROJECT SETTING
Recorded groundwater inflows into drained form part of the broader NWRL, and it was a
rail and road tunnels in Sydney are typically in condition of the emergency services to provide a
the order of 0.5 to 1.0 l/s/km of tunnel. consistent approach to fire life safety throughout
the system wherever reasonably practicable.
Other configuration options that were
3 TUNNELS considered included the following:
Single tube (single, twin track tunnel
Key decisions for the running tunnel with internal fire separation wall)
specification were made during the reference Single tube-stacked (single, twin track
design phase to inform the planning approvals tunnel with internal fire separation
process. These decisions were also made to slab)
provide surety in delivery and risk mitigation Triple tube (two, single track tunnels
across the three interfacing contracts. They with an additional services tunnel)
concerned tunnel configuration and form,
groundwater control requirements, and the
space proofing of the running tunnels.
Safety was a key consideration from the start
and formed a guide to the strategy from the
outset. An early safety in design review
concluded that a key risk in tunnelling
operations would be "rock fall" and that this
could be eliminated through the use of TBM
with segmental lining. The strategy was Figure 3. NWRL running tunnels and cross passage
developed around considering a So Far As Is Tunnel space proofing for the twin tube running
Reasonably Practical (SFAIRP) argument that tunnel configuration revealed that a circular
TBM tunnelling should be used wherever profile with an internal diameter of 6m
reasonable and practical. All options noted (excluding construction tolerances) was optimal
below were considered in the light of this to accommodate the train structure gauge, rail
argument. systems and services, emergency egress
walkways, and other necessary infrastructure.
3.1 Tunnel configuration and form The other tunnel forms considered, such as
the horse-shoe profiles, were found to be more
Several tunnel configuration options were suited to drained tunnel options excavated in
compared and assessed during the reference poor quality rock. Flat roof profiles were, again,
design. These broadly assumed either bored, found to be more suited to drained conditions
circular TBM excavation profiles or mined, but where the main tunnelling medium was
horse-shoe/flat roof sequential excavation competent sandstone. These profiles were
profiles. These were measured in terms of their assessed in respect of their ability to introduce
whole-of-life cost benefits and their ability to efficiencies to the running tunnel cross sectional
meet project requirements. A qualitative area in comparison to a circular profile. Once a
comparison was also completed that considered circular profile was decided upon the further
the compatibility of each option with the question as to whether the tunnels should be
proposed station arrangements, geotechnical and drained or undrained required consideration.
construction risk, fire and life safety and
ventilation, environmental impacts and
operational and maintenance requirements. 3.2 Drained or undrained tunnels
A twin tube (two adjacent, single track The decision to adopt a ‘drained’ (inclusion of a
tunnels) running tunnel configuration shown in tunnel groundwater pressure relief system) or
Figure 3 below was eventually selected based ‘undrained/tanked’ (incorporation of
on the results of both the comparative cost and waterproofing to prevent water inflow) tunnel
qualitative assessments. Furthermore, this system is a key decision which can influence the
configuration is consistent with the existing construction method, operational environment
ECRL tunnel configuration, which the new and maintenance requirements for the project.
tunnels connect to. The existing tunnels will
3
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
For many projects this decision is driven by 150mm was required irrespective of the whether
external constraints such as a requirement to the tunnel was designed to be drained or
limit changes to the existing groundwater undrained. The main options considered are as
regime that can cause consolidation of overlying follows:
soils. In the majority of locations within the Drained options:
Sydney Basin, overlying soils are comparatively TBM (main beam) and roadheader
thin and incompressible and so in most cases the driven tunnels both of which include
risks associated with groundwater table an allowance for temporary pattern
drawdown are minor. The main risks associated rockbolt support and a permanent cast
with the construction of drained tunnels within in-situ concrete linings (nominally
the Sydney Basin concerns the management of 200mm in thickness)
the groundwater that travels into the tunnels Undrained options:
during their operation. Historically this TBM (single/double shielded) driven
groundwater has been found to be corrosive and tunnels with a 275 mm thick precast
the cause of iron sludge deposits within the steel fibre reinforced concrete
tunnel drainage systems. For this reason drained segmental lining; and
tunnels in Sydney can be susceptible to the TBM (main beam) and roadheader
accelerated deterioration of some internal tunnel driven tunnels both of which include
components, necessitating relatively frequent an allowance for temporary pattern
treatment or early replacement. Also the rockbolt support and a permanent cast
management of iron sludge deposition requires in-situ concrete lining (nominally
frequent treatment/management of tunnel 200mm to 300mm in thickness).
drainage and pumping systems. In both cases, Advance rates and casting rates adopted in
these risks translate into increased whole of life costings were based largely on past experience
costs for the project. of tunnel construction within Sydney as sourced
The main advantage of drained tunnel from specialist constructability advisors.
solutions is that the resulting support structure Importantly the rates were assessed for their
can be designed to have reduced structural sensitivity on the costs.
capacity as compared with the undrained The outcome of this assessment revealed that
alternative. This can offer reduced lining a tanked TBM (double shielded) option was
thickness and reduced excavation cross section. likely to be the most cost effective solution in
In addition, drained tunnel solutions reduce the terms of capital costs, with a drained TBM
need for waterproofing/management activities (main beam) option being the second least
which can have a significant impact on both expensive approach. A key differentiator
construction cost and program. An important between these two options was the efficiency in
consideration for any drained tunnel solution is tunnel production for the tanked, single pass
that a robust and easily accessible and segmental lining (as built behind the double
maintainable groundwater pressure relief system shielded TBM) when compared with a double
is required. pass, drained tunnel lining system that is built
In broad terms, the main advantages of tanked some distance behind the main beam TBM. The
tunnel solutions are that there is limited latter option required the installation of
environmental impact to local groundwater temporary support followed by drainage layer
regimes and operational requirements/costs are and final cast in place lining. In addition, it was
reduced in terms of the management of the found that the lining thickness required to resist
quantity of groundwater entering the tunnel groundwater pressure for an undrained running
system. tunnel with a circular profile and small cross
sectional area was only marginally greater than
3.2.1 Capital cost assessment that required for the drained alternative.
A comparative capital cost assessment was Generally, given the long length of the tunnel
completed for drained and tanked tunnel alignment and the large distances between
options. This assessment incorporated the construction access points, the roadheader
project requirement for provision of a tunnel constructed options were assessed to be less
lining to which the PPP Contractor can fix rail efficient for the NWRL project in comparison to
systems. This requirement meant that a concrete TBM options given their significantly slower
tunnel lining with a minimum thickness of rates of advance
4
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
3.2.2 Operational cost assessment tunnels discussed above. The main benefits that
In addition to the capital cost comparison, an this option has over other drained solutions can
assessment was completed to determine the be summarized as follows:
direct operational costs that would be incurred Protection of railway infrastructure,
to collect, convey and treat groundwater inflow fixtures and equipment on the inside
resulting from drained tunnel options. These from corrosion;
costs were assessed to be significant and Assistance with long term durability of
supported the decision to adopt an undrained structures;
tunnel solution. Provides a clean and dry environment
The operational cost assessment did not allow for maintenance within the tunnels;
for the indirect costs associated with potential Removes the risk of having to deal
problems from reduced asset lives and increased with any potentially contaminated
maintenance requirements which commonly water; and
arise from the corrosive groundwater chemistry Removes the need to deal with iron
and iron oxide sludge deposition within drained sludge.
tunnels in Sydney. Several operators of drained
road, rail and utility tunnels within Sydney were
consulted for feedback on the performance of 3.3 Tunnel Specification
tunnel assets and fixtures and the maintenance To ensure certainty in achieving the project
issues associated with groundwater ingress and objectives and securing the optimum whole-of-
drainage and pumping systems. This feedback life cost solutions for the project, the tunnel
indicated that in most cases steel assets of low configuration/form and water control
to medium grade or low durability protection requirements were mandated in the contract
(such as galvanized steel) experience high rates documentation. A circular running tunnel
of corrosion when exposed to groundwater. In profile with a 6 m diameter clear opening, and a
addition, some pumping systems needed concrete lining capable of meeting groundwater
frequent maintenance and replacement, whilst seepage limits of 2 ml/hr per m2 of concrete
some drainage systems (including groundwater lining and 5 ml/hr per m2 over any 10 m length
pressure relief systems) experienced frequent of the lining was specified in the NWRL
iron sludge blockages affecting drainage contract documentation.
channels, sumps and treatment plants. Of
particular concern to drained rail tunnels in
Sydney is the durability of overhead wiring 4 ALIGNMENT
systems and the steel rail tracks. These rail
components cannot be easily protected or 4.1 Capitalising on opportunities
treated for corrosion if exposed to groundwater.
The original rail alignment adopted for the
Drained road, rail and utility tunnels in NWRL business case was a product of previous
Sydney have now been operational for 15 years
studies conducted over a decade ago. The
(with some rail tunnels being older) so good
designs were based on the conventional
asset management information is available. This approach of open face excavations supported by
information has enabled a better understanding
rock bolts and sprayed concrete temporary
of appropriate M&E specification,
support and cast in situ permanent support. The
waterproofing and drainage design requirements
use of TBM and segmental lining provided the
and maintenance needs to adequately address
opportunity to adjust the original alignment and
the above issues. It is considered that by
capitalise on potential cost savings. In addition,
applying these lessons at the design stage,
significant improvements to customer
drained tunnels of the future which are assessed
experience and operational performance were
to offer reasonable capital cost savings can be
achieved; Raising the vertical alignment would
maintained at relatively modest operational
result in shallower stations and reduced tunnel
costs.
extents.
In the case of NWRL, a tanked TBM driven
The final NWRL alignment that emerged
tunnel solution was assessed to have the least
from this value engineering process offered new
capital and operational costs, even without
and improved station locations, removal of all
consideration of the potential durability and
cavern stations, removal of approximately 2.5
maintenance issues associated with drained
5
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
7
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
6 CONCLUSIONS
ACKNOWLEDGEMENTS