Control Project PO6
Control Project PO6
Prepared BY:
Eng. Amal Abd EL Hafeez Bakry
1/17
Table of Contents
Page
Item
no.
ـــــــــــــ 7. Project activities baseline list with resources / costs / duration loaded 9
2/17
1. Necessary Background
1.1 Background bout Telecom Egypt Company:
Telecom Egypt Company in the last 2 years have strategic project called MSAN
(Multi Service Access Node) Project. All Sectors inside Telecom Egypt Company like
(switching , transmission , Power , O&M …..etc.… ) are working in this project
Replace the old and exhausted copper network with fiber network. This will
lead to reduce the theft of copper cables in addition to unlimited bandwidth
of fiber cables.
Replace the Exchange Building with a cabinet and this lead to saving the cost
of constructing a new Exchange.
MSAN will work as a backhaul for the Telecom Egypt Mobile Network (which
is still under Negotiations with NTRA)
So for the above reasons MSAN Project is the most strategic project for Telecom
Egypt Company in the last 2 years and perhaps for the next 3 years.
In simple words deliver band width to MSAN Cabinet means installing Shelf
Equipment that contains GE (Giga Ethernet) Cards in the nearest exchange to
MSAN Cabinet to establish a connection between the MSAN Cabinet and the
Soft Switch where the subscribers exist through the backbone of Telecom
Egypt.
3/17
2. Project Description
This objective will achieved by installing and testing 1662 SDH Shelves
with GE Cards ) in sites (Kafr Agiba - Meet Habib - Qasaseen EL Azhar ).
4/17
3. WBS
The WBS (Work Break down Structure) of PO6 (Delta Mesh Network) project consists of the following
phases:
Phase Description
Project Milestones Contains two Activities which are (Start Project &End Project)
Sites Survey -Decide requirements for rooms preparations like (painting, false ceiling, raised floor ….etc.).
-Decide Requirements of both Power Needed to feed equipment and HVAC(Air Conditions).
Sites Preparations Perform all sites preparations needed according to signed survey report
Equipment Delivery Receive all the contracted requirements with check list approved
5/17
4. Activity List
6/17
5. Project Baseline Bar Chart
7/17
6. Project Precedence Diagram
8/17
7. Project activities baseline list with Resources / Costs /
Duration loaded
9/17
8. Project Time Phase Budget
10/17
1. Updated Schedule At DD : 30/9/2015
Updated Schedule At DD: 30/9/2015(Figure 1)
11/17
Updated Schedule At DD: 30/9/2015(Figure 2)
12/17
10. Project Status (DD: 30/9/2015) & Cost
Variance Analysis
PV=184066.67 EGP
EV=176800 EGP
AC=192525 EGP
EAC=234775
CV=EV-AC=176800-192525=-15725
SV=EV-PV=176800-184066.67=-7266.67 EGP
This means the project is Behind Schedule By Cost Equal to 7266.67 EGP
The increase in percentage of Project Progress by cost than by Time is due to high in increase
of cost of Tendering and Survey Activities
13/17
11. Earned Value Analysis
(Earned Value Analysis Figure 1)
14/17
(Earned Value Analysis Report Figure2 )
15/17
12. Earned Value Discussion
The above Earned Value analysis shows that:
The project is running over budget and behind Schedule (SPI =0.96 and
CPI=0.92).
First:
(SPI=0.96) because :
At DD: 30/9/2015 shows the project will be delayed for 6 days it will
finish on 4 November 2015 instead of 29 October 2015 and this
comes from that Custom Clearance of equipment Activity not
started yet and it was the responsibility of TE Company because
the delivery of Equipment was with FOB (Freight On Board).
2- In the next time Change the contract type to CIF (Cost, Insurance and
Freight-Shipping) instead of FOB.
16/17
Second:
I have to make Coordination at early time with the people living to insure
their agreement to install the MSAN_Cabinet.