You are on page 1of 1

22/05/2023, 14:43 Network Charge Working Sheet

Solar Network and GST Details


Bill month : 05/2023
Tariff : LA1A
Consumption Period : 10/03/2023 To 11/05/2023
Network
CGST SGST IGST Total Amount
Charges
277.35 24.96 24.96 0 327.27

Standard Values
Capacity Utilization Factor(CUF) as stipulated by TNERC - 21%
Network Charge = Rs. 1.27 per unit generated (Before 10.09.2022) & Rs.1.48 (from
10.09.2022)
For Domestic upto 10KW - 20% of Network charges
Generated units (as per CUF) = PV capacity * 24 * CUF * No of days
Networking charges = Generated units * Network charge * Network charge percentage
GST on Networking charges = 18% CGST 9% and SGST 9%
Details of Calculation
Generated Unit Calculation = (3 * 24 * 0.21(CUF 21%) *62) = 937 units
Networking Charges = (937 * 1.48 * 20%) = Rs.277.35

tneb.tnebnet.org/newlt/sol_nwgst_charges.php?&url=MTEvMDUvMjAyMyMyNzcuMzUjMjQuOTYjMjQuOTYjTiMwIzEjMDE4MDA4Njk0IzEwLzAzL… 1/1