Professional Documents
Culture Documents
Joint Data:
Flange Data
Flange Type, Size and Class and Material
Joint and Gasket Type
Bolt and Nut size, material and grade
Bolt Data
Bolt Diameter;
Number of Bolts;
Thread Type, Imperial or Metric;
Bolt Material;
Lubricant
PIPING PRE-COMMISSIONING PROCEDURES
Tensioning:
Residual Bolt Stress,
Tensioner 1st pass,
Tensioner Subsequent passes for specified tool
Thread Type
PIPING PRE-COMMISSIONING PROCEDURES
Tagging:
PIPING PRE-COMMISSIONING PROCEDURES
Flange Alignment:
If the bolts can be passed through the bolt holes of both flanges
without force, then this misalignment is acceptable.
Horizontal/vertical offset
Flange rotation
PIPING PRE-COMMISSIONING PROCEDURES
Flange Alignment:
Face separation
PIPING PRE-COMMISSIONING PROCEDURES
Flange Alignment:
Tools
PIPING PRE-COMMISSIONING PROCEDURES
Bolt Tensioning
Flushing Media:
Flushing should be carried out using clean fresh water, potable
water, treated sea water, air or steam as appropriate.
For systems containing austenitic stainless steel piping and
fittings the chloride ion content of the water shall be less than
30ppm.
Carbon steel Pipe work flushed with sea water should be dried
immediately after flushing to prevent corrosion.
PIPING PRE-COMMISSIONING PROCEDURES
Pressure Test
Hydrostatic Test
Test Media:
The fluid shall be water unless there is the possibility of damage
due to freezing or to adverse effects of water on the piping or
the process. In that case another suitable nontoxic liquid may
be used and you have to a make sure the test media will not
contaminate the final product.
For austenitic stainless steel piping the chloride ion content of
the water shall not be more than 30 ppm
Test Pressure:
The hydrostatic test pressure at any point in a piping system
shall be defined by the design documents and not less than 1.5
times the design pressure.
PIPING PRE-COMMISSIONING PROCEDURES
Hydrostatic Test
Test Records:
Records shall be made of each piping system during the testing,
including
Date of test
Identification of piping system tested
Test fluid
Test pressure
Certification of results by examiner
Pressure and temperature charts.
PIPING PRE-COMMISSIONING PROCEDURES
Hydrostatic Test
listed below are the systems and the loop numbers for the
following Systems:
Sub-System Description
TARGET PLATE:
The results of steam blowing shall be checked by means of
target plate to consist of holding fixture to witch a mirror-
finished impingement plate of carbon steel with a brinell
hardness.
TARGET PLATE:
PIPING AND STATIC EQUIPMENT COMMISSIONING
Leak Testing
Witnessed Joint
PIPING AND STATIC EQUIPMENT COMMISSIONING
There are several gases which are considered as "inert" but for all
practical purposes only nitrogen is to be used.
PIPING AND STATIC EQUIPMENT COMMISSIONING
Purging Methods
Pressurization / depressurization:
This is the preferred method of inert gas or nitrogen purging
for reasons of economy and safety and is used for both vessels
and associated piping
PIPING AND STATIC EQUIPMENT COMMISSIONING
Final Alignment
ROTATING EQUIPMENTS INSTALLATION
Reverse Alignment.
Face and Rim Alignment.
Optical Alignment .
ROTATING EQUIPMENTS PRE-COMMISSIONING
Reverse Alignment
Reverse Alignment
REVERSE INDICATOR
dF
DRIVER
dM
Inboard Outboard
ROTATING EQUIPMENTS PRE-COMMISSIONING
Reverse Alignment
BRACKET
STRAIGHT PIPE
Reverse Alignment
CHECK BASE FRAME & SOFT FOOT
ROTATING EQUIPMENTS PRE-COMMISSIONING
Reverse Alignment
DRIVER
Magnetic Dial
ROTATING EQUIPMENTS PRE-COMMISSIONING
dP
D dA DRIVER
L1
L2
ROTATING EQUIPMENTS PRE-COMMISSIONING
Operational Test
This operational test consists of bringing the system equipment
into operation under conditions as close as possible to normal
operating conditions for a significant period of time.
Preliminary Check:
OTP Execution:
Once the system is ready for its first start-up with the equipment
mechanically prepared and the system lined-up, it will be started
for two hours following a detailed step by step procedure as
recommended by the manufacturer (or under supervision by
Vendor’s representative).
The second phase of the operational test is essentially devised for
planning and resources purposes.
Actual dynamic verifications that all the sequences and interlocks
of the main equipment, its auxiliaries and of the whole
system/sub-system perform properly.
Actual verifications that the main equipment is mechanically
sound, by taking all the required reading during several hours
after stabilization.
ROTATING EQUIPMENTS COMMISSIONING
OTP Execution:
Once the system is ready for its first start-up with the equipment
mechanically prepared and the system lined-up, it will be started
for two hours following a detailed step by step procedure as
recommended by the manufacturer (or under supervision by
Vendor’s representative).
Run-in activities: