You are on page 1of 66

PIPING PRE-COMMISSIONING PROCEDURES

Joint Integrity Procedure

Joint Data:
ƒ Flange Data
ƒ Flange Type, Size and Class and Material
ƒ Joint and Gasket Type
ƒ Bolt and Nut size, material and grade
ƒ Bolt Data
ƒ Bolt Diameter;
ƒ Number of Bolts;
ƒ Thread Type, Imperial or Metric;
ƒ Bolt Material;
ƒ Lubricant
PIPING PRE-COMMISSIONING PROCEDURES

Joint Integrity Procedure

Joint Data - Continued:


ƒ Tightening Data
ƒ Torqueing:
ƒ Residual Bolt Stress,
ƒ Torque Value Required
ƒ Pump Pressure for specified tool.

ƒ Tensioning:
ƒ Residual Bolt Stress,
ƒ Tensioner 1st pass,
ƒ Tensioner Subsequent passes for specified tool
ƒ Thread Type
PIPING PRE-COMMISSIONING PROCEDURES

Joint Integrity Procedure

Tagging:
PIPING PRE-COMMISSIONING PROCEDURES

Joint Integrity Procedure

Flange Alignment:
If the bolts can be passed through the bolt holes of both flanges
without force, then this misalignment is acceptable.

Horizontal/vertical offset

Flange rotation
PIPING PRE-COMMISSIONING PROCEDURES

Joint Integrity Procedure

Flange Alignment:

Face separation
PIPING PRE-COMMISSIONING PROCEDURES

Joint Integrity Procedure

Flange Alignment:

Tools
PIPING PRE-COMMISSIONING PROCEDURES

Joint Integrity Procedure

Flange Face Defect


PIPING PRE-COMMISSIONING PROCEDURES

Flanged Joint Bolt Tightening

Hydraulic Torque Tightening


PIPING PRE-COMMISSIONING PROCEDURES

Flanged Joint Bolt Tightening

Hydraulic Torque Tightening

Criss-Cross Tightening Sequence Examples::


ƒ 4 Bolt Flange 1-3-2-4
ƒ 8 Bolt Flange 1-5-3-7-2-6-4-8
ƒ 12 Bolt Flange 1-7-4-10-2-8-5-11-3-9-6-12
ƒ 16 Bolt Flange 1-9-5-13-3-11-7-15-2-10-6-14-4-12-8-16
ƒ 20 Bolt Flange 1-11-6-16-3-13-8-18-5-15-10-20-2-12-7-17-4-
14-9-19
PIPING PRE-COMMISSIONING PROCEDURES

Flanged Joint Bolt Tightening

Manual Torque Tightening


PIPING PRE-COMMISSIONING PROCEDURES

Flanged Joint Bolt Tightening

Manual Torque Tightening

Criss-Cross Tightening Sequence Examples::


ƒ 4 Bolt Flange 1-3-2-4
ƒ 8 Bolt Flange 1-5-3-7-2-6-4-8
ƒ 12 Bolt Flange 1-7-4-10-2-8-5-11-3-9-6-12
ƒ 16 Bolt Flange 1-9-5-13-3-11-7-15-2-10-6-14-4-12-8-16
ƒ 20 Bolt Flange 1-11-6-16-3-13-8-18-5-15-10-20-2-12-7-17-4-
14-9-19
PIPING PRE-COMMISSIONING PROCEDURES

Flanged Joint Bolt Tightening

Bolt Tensioning

100% procedure 50% procedure 50% procedure


PIPING PRE-COMMISSIONING PROCEDURES

Cleaning and Flushing

Cleaning of lines after assembly and erection. After the completion


of erection, scale, dirt, welding electrodes, slag, and other foreign
material should be removed from the lines.

Flushing Media:
ƒ Flushing should be carried out using clean fresh water, potable
water, treated sea water, air or steam as appropriate.
ƒ For systems containing austenitic stainless steel piping and
fittings the chloride ion content of the water shall be less than
30ppm.
ƒ Carbon steel Pipe work flushed with sea water should be dried
immediately after flushing to prevent corrosion.
PIPING PRE-COMMISSIONING PROCEDURES

Cleaning and Flushing Certificate


PIPING PRE-COMMISSIONING PROCEDURES

Pressure Test

Each piping system shall be tested to ensure tightness prior to


initial operation and after completion of the applicable
examinations applies to quality control functions.

Testing must be carried out in accordance with the requirements


specified on the isometric drawing and piping line specification or
otherwise must take into account the duty of the system, namely
the process fluid and the operating pressures and temperatures.

Pressure test can be done with a several methods:


ƒ Hydrostatic test
ƒ Pneumatic test
ƒ Hydrostatic / pneumatic test
PIPING PRE-COMMISSIONING PROCEDURES

Hydrostatic Test

Test Media:
ƒ The fluid shall be water unless there is the possibility of damage
due to freezing or to adverse effects of water on the piping or
the process. In that case another suitable nontoxic liquid may
be used and you have to a make sure the test media will not
contaminate the final product.
ƒ For austenitic stainless steel piping the chloride ion content of
the water shall not be more than 30 ppm

Test Pressure:
ƒ The hydrostatic test pressure at any point in a piping system
shall be defined by the design documents and not less than 1.5
times the design pressure.
PIPING PRE-COMMISSIONING PROCEDURES

Hydrostatic Test

Test Records:
Records shall be made of each piping system during the testing,
including
ƒ Date of test
ƒ Identification of piping system tested
ƒ Test fluid
ƒ Test pressure
ƒ Certification of results by examiner
ƒ Pressure and temperature charts.
PIPING PRE-COMMISSIONING PROCEDURES

Hydrostatic Test

Pressure and temperature charts.


PIPING PRE-COMMISSIONING PROCEDURES

Hydrostatic Test Certificate


PIPING PRE-COMMISSIONING PROCEDURES

Steam Blowing For Piping Networks Procedure


PIPING PRE-COMMISSIONING PROCEDURES

Steam Blowing For Piping Networks Procedure

Reference to “Steam Blowing For Piping Networks Procedure”


“000470_DV_EX.DPM.0354.000_00”.

The purpose of blowing or cleaning the steam lines prior to


starting up a new unit is to remove any foreign matter remaining
in the equipment (i.e. superheater) and steam piping after
installation is completed.

The operational test package covers the pipework cleanness by


steam blowing method (Medium & Low Pressure Steam Headers
and sub-headers network).
PIPING PRE-COMMISSIONING PROCEDURES

Steam Blowing For Piping Networks Procedure

listed below are the systems and the loop numbers for the
following Systems:

Sub-System Description

525-BW01-01 Boiler Feed Water Generation package

525--BB01-01 Boiler Feed Water Distribution

525RG01-01 Boiler Blow Down

525-MS01-01 Medium Pressure Steam Generation

525-MS01-02 Medium Pressure Steam Distribution

525-LS01-01 Low Pressure Steam Generation

525-LS01-02 Low Pressure Steam Distribution


PIPING PRE-COMMISSIONING PROCEDURES

Steam Blowing For Piping Networks Procedure

TYPES OF STEAM BLOW METHODS:


Shock blow:
ƒ With shock blow, the pressure inside the steam generator is
raised to a certain maximum and reaching the required
pressure, a temporary sacrificial valve is opened quickly.

Continuous steam blow:


ƒ With continuous blow there is no pressure build up, but after
calculations, the K-factor is reached continuously. During the
continuous steam blow the target plates are checked on impacts
of particles.
PIPING PRE-COMMISSIONING PROCEDURES

Steam Blowing For Piping Networks Procedure

TARGET PLATE:
ƒ The results of steam blowing shall be checked by means of
target plate to consist of holding fixture to witch a mirror-
finished impingement plate of carbon steel with a brinell
hardness.

ƒ The possible locations of target plate are:


ƒ Installation of target plate in the inlet section of temporary
pipe network.
ƒ Installation of target plate in the outlet section of the steam
line.
ƒ Steam Blowing Results, Control, Evaluation and Records
PIPING PRE-COMMISSIONING PROCEDURES

Steam Blowing For Piping Networks Procedure

TARGET PLATE:
PIPING AND STATIC EQUIPMENT COMMISSIONING

Leak Testing

Reference to “Leak Test & N2 Purging Procedure for Systems


Commissioning” “000470_DV_EX.DPM.0361.000_00”.

Leak tests shall be carried out on entire systems, after flushing


and cleaning operations, and completion of the installation, to
prove the integrity of the following:
ƒ Gaskets and flanged joints in general;
ƒ Valve packing;
ƒ Miscellaneous connections such as vents, drains, safety
valves, instruments;
ƒ Connections between the system being tested and inter-
related systems.
PIPING AND STATIC EQUIPMENT COMMISSIONING

Leak Test Procedure

ƒ Systems test limits


ƒ Pressurization / De-Pressurizing Points.
ƒ Flange Taping in case complemented by HLD (Helium Leak
Detection) or Soap Testing.
ƒ Pressure recording
ƒ Relief systems
ƒ Issue a Witnessed Joint Register waiting Services Test
PIPING AND STATIC EQUIPMENT COMMISSIONING

Leak Test Report


PIPING AND STATIC EQUIPMENT COMMISSIONING

Witnessed Joint
PIPING AND STATIC EQUIPMENT COMMISSIONING

Inert Purging Of Process Piping General Conditions

It is the removal of oxygen from all pipework and vessels to


provide safe hydrocarbons introduction.

This operation is required only if the process system is filled with


air after leak testing (depending on leak testing methodology
adopted) which shall be decided by the Commissioning Team.

There are several gases which are considered as "inert" but for all
practical purposes only nitrogen is to be used.
PIPING AND STATIC EQUIPMENT COMMISSIONING

Purging Methods

Continuous flow or "sweeping“:


This method will generally be used for small, low-volume
systems such as piping systems up to 4" line diameter.
Continuous flow / sweeping of large diameter piping is
unsuitable due to the very high flow required to produce the
ideal velocity (3 m/s) to displace air.

Pressurization / depressurization:
This is the preferred method of inert gas or nitrogen purging
for reasons of economy and safety and is used for both vessels
and associated piping
PIPING AND STATIC EQUIPMENT COMMISSIONING

Inerting and Drying out Certificate


ROTATING EQUIPMENTS INSTALLATION

Storage and Preservation

Protecting project machinery from deterioration in the field.


Upon arrival of the machinery The following checks should tack
place:
ƒ Visually inspect components for physical damage or
contamination by opening packages and crates.
ƒ Ensure the equipment is received after the completion of all FAT
punch lists.
ƒ Verify that loose components and separate packages match the
packing lists.
ƒ Verify that special handling instructions are provided and carried
out etc.
ROTATING EQUIPMENTS INSTALLATION

Storage and Preservation Certification


ROTATING EQUIPMENTS INSTALLATION

Mechanical Installation Procedure

The following points are to be checked on all Machinery


equipment, static Equipment and Skid mounted unit:
ƒ Confirm that Storage and Preservation Protection Procedure was
applied
ƒ All installation activities will be according to vendor's manual.
ƒ Confirm proper foundation, levelling and position in accordance
with the mechanical drawings and vendor manual.
ƒ All drains and vents - including bedplate drains are fitted and
clear.
ƒ All mechanical seals are clean and completed
ƒ All pipe work is complete and correctly aligned, e.g. seal and
lube oil systems are flushed correctly (pickled where necessary)
and filled with the correct oil.
ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

ƒ Confirm that Jobsite Receiving and Protection Procedure was


applied.
ƒ Confirm that Generic Mechanical Installation procedure was
applied.
ƒ Mounting pads shall be provided for the pump and all drive train
components.
ƒ When the vendor mounts the components, a set of stainless
steel shims at least 3 mm (0.12 in.) thick shall be furnished.
ƒ When the vendor does not mount the components, the pads
shall not be drilled, and shims shall not be provided.
ƒ Level and properly grout the base-plate.
ƒ Remove jackscrews removed and tighten foundation bolts.
ƒ Flush and re-lubricate bearing housing.
ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

Surface to Be Rough Chipped


and Clean. The overhang of the base pad
allows levelling of the pads
Level baseplate using Jack without removal of the pump.
screws and levelling pads.
ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

Pump Feet with Dial Indicator:


ƒ The dial is attached with the button
on the top of the foot.
ƒ The hold down bolt is then
loosened.
ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

Align driver to pump:


ƒ This alignment is to ensure that
coupling alignment can be made
prior to grouting of the base.
ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

Grout Baseplate Install Main Piping


ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

Check for Pipe Strain


ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

Final Alignment
ROTATING EQUIPMENTS INSTALLATION

Pump Installation Procedure

Thermal Offset Map as


Supplied by OEM
ROTATING EQUIPMENTS INSTALLATION

Pump Installation Certificate


ROTATING EQUIPMENTS PRE-COMMISSIONING

Methods of Machinery Alignment

ƒ Reverse Alignment.
ƒ Face and Rim Alignment.
ƒ Optical Alignment .
ROTATING EQUIPMENTS PRE-COMMISSIONING

Machinery Alignment Procedure

The following Procedures are to be performed in conjunction with


the Machinery Alignment Certificate Form.
ƒ All machinery will have the alignment checked by one of the
following methods described below. Tolerances are to be within
the manufacturer's standard requirements.
ƒ Enter the type of Alignment Procedure to be used i.e.
Reverse/Optical/Face & Rim.
ƒ Enter the target alignment that is to be achieved in the required
Alignment section.
ROTATING EQUIPMENTS PRE-COMMISSIONING

Reverse Alignment

ƒ Reverse alignment is the measurement of the axis, or centerline


of one shaft to the relative position of an opposing shaft
centerline.
ƒ This measurement can be projected the full length of both
shafts for proper positioning if you need to allow for thermal
movement.
ƒ The measurement also shows the position of the shaft
centerlines at the coupling flex planes, for the purpose of
selecting an allowable tolerance.
ƒ The centerline measurements are taken in both horizontal and
vertical planes.
ROTATING EQUIPMENTS PRE-COMMISSIONING

Reverse Alignment Advantages

ƒ Very accurate especially for small diameter flanges


ƒ Not affected by axial float.
ƒ Can be used with a flexible coupling in place.
ƒ You have to rotate both shafts.
ROTATING EQUIPMENTS PRE-COMMISSIONING

Reverse Alignment

REVERSE INDICATOR

dF

DRIVER

dM
Inboard Outboard
ROTATING EQUIPMENTS PRE-COMMISSIONING

Reverse Alignment

HOW TO FIND THE SAG ?

BRACKET

STRAIGHT PIPE

STAND V BLOCK STAND V BLOCK


ROTATING EQUIPMENTS PRE-COMMISSIONING

Reverse Alignment
CHECK BASE FRAME & SOFT FOOT
ROTATING EQUIPMENTS PRE-COMMISSIONING

Reverse Alignment

CHECK RUN OUT BOTH OF COUPLINGS

DRIVER

Magnetic Dial
ROTATING EQUIPMENTS PRE-COMMISSIONING

Rim and Face Alignment

WHY USE THIS METHOD ?


ƒ Use this method if one of the shafts cannot be rotated.
ƒ An excellent method for large shaft diameters (8 inches or
200mm or greater) or if the diameters are equal to, or greater
than the span from the bracket location to the face and rim
location where the readings are to be taken.
ƒ Not too good a method if there is axial float from sleeve or
journal bearings.
ROTATING EQUIPMENTS PRE-COMMISSIONING

Rim and Face Alignment

dP

D dA DRIVER

L1

L2
ROTATING EQUIPMENTS PRE-COMMISSIONING

Rim and Face Alignment

Before Alignment Confirm????


ƒ A straight shaft that has been dynamically balanced.
ƒ Good wear rings with the proper clearance.
ƒ The correct impeller to volute, or back plate clearance.
ƒ The elimination of "soft foot".
ƒ Eliminate all pipe strain.
ƒ Good bearings installed on a shaft with the proper finish and
tolerances.
ƒ A good mechanical seal set at the proper face load. The closer
the seal is to the pump bearings the better off you are going to
be.
ROTATING EQUIPMENTS PRE-COMMISSIONING

Machinery Alignment Certificate


ROTATING EQUIPMENTS COMMISSIONING

Operational Test
ƒ This operational test consists of bringing the system equipment
into operation under conditions as close as possible to normal
operating conditions for a significant period of time.

ƒ Once the Operational Tests are complete, the system is “Ready


for Start-Up” or can be put under normal operation.

ƒ “Operational Test Certificate” will be issued to Company for


approval and for commencement of the associated start-up
activities as require.
ROTATING EQUIPMENTS COMMISSIONING

OTP Pumps Run-in Procedure

Preliminary Check:

Visual Inspection; Oil quality analysis;


Cleanliness; Coupling of driver and driven unit;
Removal of preservation; Filling of consumables;
Freedom of rotation; Filters and oil cartridge inspection;
Final alignment checks; Connection of temporary facilities;
Lubrication; Running and verification of all
Lube, seal and hydraulic oil filling auxiliaries
ROTATING EQUIPMENTS COMMISSIONING

OTP Pumps Run-in Procedure

OTP Execution:
Once the system is ready for its first start-up with the equipment
mechanically prepared and the system lined-up, it will be started
for two hours following a detailed step by step procedure as
recommended by the manufacturer (or under supervision by
Vendor’s representative).
The second phase of the operational test is essentially devised for
planning and resources purposes.
Actual dynamic verifications that all the sequences and interlocks
of the main equipment, its auxiliaries and of the whole
system/sub-system perform properly.
Actual verifications that the main equipment is mechanically
sound, by taking all the required reading during several hours
after stabilization.
ROTATING EQUIPMENTS COMMISSIONING

OTP Pumps Run-in Procedure

OTP Execution:

Once the system is ready for its first start-up with the equipment
mechanically prepared and the system lined-up, it will be started
for two hours following a detailed step by step procedure as
recommended by the manufacturer (or under supervision by
Vendor’s representative).

The second phase of the operational test is essentially devised for


planning and resources purposes.
ROTATING EQUIPMENTS COMMISSIONING

OTP Pumps Run-in Procedure

Actual dynamic verifications that all the sequences and interlocks


of the main equipment, its auxiliaries and of the whole
system/sub-system (or other system, if they are interlocked),
perform properly:

Start/stop normal sequences; Remote/local modes;


Hot/cold start; Duty/stand-by modes;
Emergency shutdown; Auxiliaries changeover;
Pneumatic/ Electric starts; Synchronisation.
Automatic/manual modes;
ROTATING EQUIPMENTS COMMISSIONING

OTP Pumps Run-in Procedure

Actual verifications that the main equipment is mechanically


sound, by taking all the required reading during several hours
after stabilization for:

Noise levels; Fuel and oil leaks;


Equipment, bearing, gearbox Piping vibrations;
vibrations; Strainers and filters differential
Lube oil/coolant flows, temperatures, pressures;
pressures Oil consumption;
Seals integrity; Signs of mechanical wear.
ROTATING EQUIPMENTS COMMISSIONING

OTP Pumps Run-in Procedure

Actual verification of the equipment performance:

ƒ By taking process or electrical readings during several hours


after stabilisation, at various loads;

ƒ By plotting the actual performance against theoretical


characteristics supplied by the manufacturer / vendor.
ROTATING EQUIPMENTS COMMISSIONING

OTP Pumps Run-in Procedure

Actual dynamic verifications as practicable that the key process


and equipment alarms and trips function properly:

ESD/Manual push-buttons; High/low flows;


F&G detection; High/low temperatures;
High/low pressures; Over speeds
ROTATING EQUIPMENTS COMMISSIONING

OTP Fan, Blower & Coolers Run-in Procedure

Run-in activities:

Review manufacturer operating Rotate group by hand, verifying that it


instructions. turns freely;
Check that installation is correct and Check that electric power is available
complete; from switchgear to starter of electric
Verify that equipment and driver are motor drivers;
correctly aligned; Close air inlet damper (if applicable)
Check belt tension of driven pulleys (if and start the blower(s);
applicable); Increase slowly air flow (as applicable);
Verify that bearings are properly Check for abnormal vibrations. Correct
lubricated and cooled (if applicable); as necessary;
Check control and monitory Measure bearing temperature and
instruments and safety devices vibrations;

You might also like