1- Fatek PLC (which contains all Control’s features of DTC and LG Master PLC)
2- Computer based Software (C# based, for Entering Recipe)
PROJECT DELIVERABLES:
1- Programmed Fatek PLC (containing control functions of DTC and Master PLC)
2- C# based Software for interfacing with 1 Nos. of Fatek (above mentioned) PLC for recipe and
other data entry.
PROJECT TIMELINE/PHASES:
1- Data collection and Requirement’s approval: Duration (60 Hours)
Phase 1.1 : Collection of Technical Data and requirements. (35 Hours)
Phase 1.2 : Finalization and written approval of requirements. (25 Hours)
NOTES:
During Phase 1 and Phase 3 ,following of teams are required from Candle/SWW:
1- Electrical
2- Mechanical
3- Operation/Production (Dyeing Depart)