BALUWATAR APARTMENT REMAINING WORK ESTIMATE

SN DESCRIPTION OF WORK UNIT NO.S LENGTH BREADTH HEIGHT


A CIVIL WORKS
i BRICKWORK SQFT

9" thick wall


[Ground Floor] 1 14.17 1.00 10.00
1 4.00 1.00 10.00
1 4.08 1.00 10.00
1 4.83 1.00 10.00
1 4.67 1.00 10.00
1 9.33 1.00 10.00
1 2.58 1.00 10.00
1 1.17 1.00 10.00
1 9.25 1.00 10.00
1 4.48 1.00 10.00
1 2.33 1.00 10.00
1 3.50 1.00 10.00
1 2.17 1.00 10.00
1 9.33 1.00 10.00
1 10.67 1.00 10.00
1 3.17 1.00 10.00
1 1.67 1.00 10.00
1 6.00 1.00 10.00
deduct w3 -1 6.00 1.00 4.50
1 6.00 1.00 10.00
deduct w3 -1 6.00 1.00 4.50
1 3.00 1.00 10.00
deduct w5 -1 3.00 1.00 6.00
1 6.00 1.00 10.00
deduct w3 -1 6.00 1.00 4.50
1 3.00 1.00 10.00
deduct w5 -1 3.00 1.00 6.00
1 6.00 1.00 10.00
w3 -1 6.00 1.00 4.50
1 5.00 1.00 10.00
MD -1 5.00 1.00 7.00
2 10.58 1.00 10.00
1 8.67 1.00 10.00
d1 -1 3.00 1.00 7.00
2 6.58 1.00 10.00
1 4.25 1.00 10.00
d2 -1 2.50 1.00 7.00
1 10.58 1.00 10.00
1 8.67 1.00 10.00
d1 -1 3.00 1.00 7.00
1 5.25 1.00 10.00
d2 -1 2.50 1.00 7.00
1 10.58 1.00 10.00
1 11.00 1.00 10.00
d1 -1 3.00 1.00 7.00
1 11.00 1.00 10.00
d1 -1 3.00 1.00 7.00
1 3.33 1.00 10.00
1 1.48 1.00 10.00
TOTAL
[1st/2nd/3rd/4th floor]
bedroom
(16'9"*11'2") 1 17.00 1.00 10.00
deduct (w4) -2 4.00 1.00 6.00
1 14.17 1.00 10.00
deduct sd2 -1 7.00 1.00 6.00
1 10.75 1.00 10.00
deduct w2 -1 7.00 1.00 3.00
1 14.50 1.00 10.00
deduct sd1 -1 10.00 1.00 6.00
1 23.92 1.00 10.00
deduct w4 -2 4.00 1.00 6.00
deduct w5 -1 3.00 1.00 6.00
1 9.92 1.00 10.00
deduct w5 -2 3.00 1.00 6.00
1 11.33 1.00 10.00
deduct w4 -1 4.00 1.00 6.00
1 10.25 1.00 10.00
deduct w1 -1 7.00 1.00 6.00
1 3.17 1.00 10.00
deduct w7 -1 1.75 1.00 8.92
1 9.42 1.00 10.00
1 5.75 1.00 10.00
deduct w7 -1 1.75 1.00 8.92
1 4.08 1.00 10.00
deduct w5 -1 3.00 1.00 6.00
1 10.75 1.00 10.00
1 3.50 1.00 10.00
1 5.50 1.00 50.00

TOTAL
4" thick wall
1 6.00 1.00 10.00
deduct d1 -1 3.00 1.00 7.00
1 7.42 1.00 10.00
2 5.42 1.00 10.00
deduct d2 -1 2.50 1.00 7.00
1 6.75 1.00 10.00
1 4.42 1.00 10.00
1 2.17 1.00 10.00
1 2.33 1.00 10.00
1 6.00 1.00 10.00
1 9.17 1.00 10.00
1 9.25 1.00 10.00
deduct w5 -1 3.00 1.00 6.00
deduct w6 -1 2.00 1.00 6.00
1 12.50 1.00 10.00
1 8.58 1.00 10.00
2 6.33 1.00 10.00
1 1.83 1.00 10.00
deduct d2 -1 2.50 1.00 7.00
1 2.08 1.00 10.00
1 6.83 1.00 10.00
1 14.50 1.00 10.00
1 3.92 1.00 10.00
1 3.42 1.00 10.00
1 7.92 1.00 10.00
1 15.75 1.00 10.00
1 8.58 1.00 10.00
1 4.50 1.00 10.00
deduct d2 -1 2.50 1.00 7.00
1 10.25 1.00 10.00
deduct d1 -1 3.00 1.00 7.00
1 4.50 1.00 10.00
deduct d2 -1 2.50 1.00 7.00
1 37.92 1.00 3.33
1 56.75 1.00 3.33
1 33.08 1.00 3.33
1 23.17 1.00 3.33
1 18.08 1.00 3.33

TOTAL
ii WATERPROOFING WORK SQFT
BASEMENT
FLOORING 1 1189.39 1.00 1.00
WALL 1 25.00 10.67 1.00
1 20.08 10.67 1.00
1 3.17 10.67 1.00
1 14.67 10.67 1.00
1 5.08 10.67 1.00
1 27.00 10.67 1.00
1 15.33 10.67 1.00

TOTAL

TOILET-1 1 7.00 5.00 1.00


POWDER ROOM 1 7.75 5.00 1.00
TOILET-2 1 8.17 5.50 1.00
TOILET-3 1 8.00 6.00 1.00
BALCONY-1 1 9.08 5.25 1.00
BALCONY-2 1 4.17 16.17 1.00
BALCONY-3 1 15.83 4.50 1.00

TOILET-1 WALL 1 7.00 7.00 1.00


POWDER ROOM WALL 1 7.75 7.00 1.00
TOILET-2 WALL 1 8.17 7.00 1.00
TOILET-3 WALL 1 8.00 7.00 1.00
BALCONY-1 WALL 1 9.08 7.00 1.00
BALCONY-2 WALL 1 4.17 7.00 1.00
BALCONY-3 WALL 1 15.83 7.00 1.00

TOTAL

PARAPHET WALL 1 37.92 2.00 1.00


1 56.75 2.00 1.00
1 33.08 2.00 1.00
1 23.17 2.00 1.00
1 18.08 2.00 1.00

RCC WORK FOR SILL AND LINTEL BAND 1 169.00 0.33 0.25

TERRACE FLOORING 1 1694.22 1.00 1.00

TOTAL

iii PLASTER WORK SQFT


Basement 2 29.00 1.00 10.67
2 22.25 1.00 10.67
2 4.83 1.00 10.67
2 6.25 1.00 10.67
2 5.08 1.00 10.67
2 10.92 1.00 10.67
2 28.68 1.00 10.67
2 11.33 1.00 10.67
2 16.17 1.00 10.67
TOTAL
[1st/2nd/3rd/4th floor]
bedroom
(16'9"*11'2") 2 17.00 1.00 10.00
deduct (w4) -2 4.00 1.00 6.00
2 14.17 1.00 10.00
deduct sd2 -2 7.00 1.00 6.00
2 10.75 1.00 10.00
deduct w2 -2 7.00 1.00 3.00
2 14.50 1.00 10.00
deduct sd1 -2 10.00 1.00 6.00
2 23.92 1.00 10.00
deduct w4 -2 4.00 1.00 6.00
deduct w5 -2 3.00 1.00 6.00
2 9.92 1.00 10.00
deduct w5 -2 3.00 1.00 6.00
2 11.33 1.00 10.00
deduct w4 -2 4.00 1.00 6.00
2 10.25 1.00 10.00
deduct w1 -2 7.00 1.00 6.00
2 3.17 1.00 10.00
deduct w7 -2 1.75 1.00 8.92
2 9.42 1.00 10.00
2 5.75 1.00 10.00
deduct w7 -2 1.75 1.00 8.92
2 4.08 1.00 10.00
deduct w5 -2 3.00 1.00 6.00
2 10.75 1.00 10.00
2 3.50 1.00 10.00
2 5.50 1.00 50.00
2 6.00 1.00 10.00
deduct d1 -2 3.00 1.00 7.00
2 7.42 1.00 10.00
2 5.42 1.00 10.00
deduct d2 -2 2.50 1.00 7.00
2 6.75 1.00 10.00
2 4.42 1.00 10.00
2 2.17 1.00 10.00
2 2.33 1.00 10.00
2 6.00 1.00 10.00
2 9.17 1.00 10.00
2 9.25 1.00 10.00
deduct w5 -2 3.00 1.00 6.00
deduct w6 -2 2.00 1.00 6.00
2 12.50 1.00 10.00
2 8.58 1.00 10.00
2 6.33 1.00 10.00
2 1.83 1.00 10.00
deduct d2 -2 2.50 1.00 7.00
2 2.08 1.00 10.00
2 6.83 1.00 10.00
2 14.50 1.00 10.00
2 3.92 1.00 10.00
2 3.42 1.00 10.00
2 7.92 1.00 10.00
2 15.75 1.00 10.00
2 8.58 1.00 10.00
2 4.50 1.00 10.00
deduct d2 -2 2.50 1.00 7.00
2 10.25 1.00 10.00
deduct d1 -2 3.00 1.00 7.00
2 4.50 1.00 10.00
deduct d2 -2 2.50 1.00 7.00
2 37.92 1.00 3.33
2 56.75 1.00 3.33
2 33.08 1.00 3.33
2 23.17 1.00 3.33
2 18.08 1.00 3.33
TOTAL

iv SCREEDING WORK SQFT


BASEMENT 1 1443.60 1.00 1.00

1ST FLOOR 1 154.95 1.00 1.00


1 678.59 1.00 1.00
1 446.41 1.00 1.00
1 406.29 1.00 1.00
1 80.19 1.00 1.00

TOTAL

ROOF 1 1795.77 1.00 1.00

v PUNNING WORK SQFT


Basement 1 1443.60 1.00 1.00
4 417.68 1.00 10.00
TOTAL
vi RCC WORK SILL AND LINTEL CFT 1 1670.72 0.75 0.25

vii FLOORING SQFT


TILES
FLOORING TILES 1 1738.77 1.00 1.00
TOILET FLOOR 1 7.00 5.00 1.00
1 8.00 6.00 1.00
1 7.75 5.00 1.00
1 8.17 5.50 1.00
TOTAL
WALL TILES
WALL 1 8.17 5.50 1.00
DEDUCT D2 -1 2.50 7.00 1.00
W5 -1 3.00 6.00 1.00
1 7.75 5.00 1.00
W6 -1 2.00 6.00 1.00
D3 -1 2.50 7.00 1.00
1 8.00 6.00 1.00
D2 -1 2.50 7.00 1.00
W6 -1 2.00 6.00 1.00
1 7.00 5.00 1.00
W5 -1 3.00 6.00 1.00
D2 -1 2.50 7.00 1.00

TOTAL
GRAND TOTAL FLOORING TILES
KITCHEN GRANITE 1 34.79 1.00 1.00
WOODEN FLOORING

TOTAL
GRANITE IN WINDOW SILL
D1 17 3.00 0.58 1.00
D2 26 2.50 0.58 1.00
W1 4 7.00 0.58 1.00
W2 4 7.00 0.58 1.00
W3 4 6.00 0.58 1.00
W4 21 4.00 0.58 1.00
W5 22 3.00 0.58 1.00
W6 4 2.00 0.58 1.00
W7 10 1.75 0.58 1.00
SD1 4 10.00 0.58 1.00
SD2 4 7.00 0.58 1.00

TOTAL

DOORS AND WINDOWS


MAIN DOOR FRAME CFT 1 5.00 7.00 0.42
DOOR CFT
D1 17 3.00 7.00 0.42
D2 26 2.50 7.00 0.42
TOTAL
UPVC WINDOWS SQFT
D1 17 3.00 7.00 1.00
D2 26 2.50 7.00 1.00
W1 4 7.00 6.00 1.00
W2 4 7.00 3.00 1.00
W3 4 6.00 4.00 1.00
W4 21 4.00 6.00 1.00
W5 22 3.00 6.00 1.00
W6 4 2.00 6.00 1.00
W7 10 1.75 8.98 1.00
TOTAL
UPVC SLIDING DOOR SQFT
SD1 4 10.00 6.00 1.00
SD2 4 7.00 6.00 1.00
TOTAL

METAL WORK
TRUSS WORK RFT
3"*3" SQ. HOLLOW PIPE 4 23.98 1.00 1.00
3"*1.5" SQ. HOLLOW PIPE 7 29.00 1.00 1.00
3"*3" SQ. PIPE FOR POST 10 8.00 1.00 1.00
TOTAL

TOUGHEN GLASS SQFT 1 23.98 29.00 1.00


TOUGHEN GLASS IN STAIRCASE SQFT 4 7.00 3.33 1.00
4 7.00 3.33 1.00
4 0.50 3.33 1.00
TOTAL

METAL GATE SQFT 1 14.00 8.00 1.00

BOUNDARY WALL
BRICKWORK SQFT 1 35.25 6.00 1.00
1 11.68 6.00 1.00
1 12.68 6.00 1.00
1 4.08 6.00 1.00
1 2.68 6.00 1.00
1 36.75 6.00 1.00
1 41.00 6.00 1.00
1 28.33 6.00 1.00
1 19.08 6.00 1.00
1 15.00 6.00 1.00
1 55.00 6.00 1.00
1 5.67 6.00 1.00
TOTAL 267.20

RCC WORK FOR SILL AND LINTEL BANDS CFT 2 267.20 0.75 0.25

RAILING WORKS SQFT


PARAPET WALL RAILING 1 37.92 3.33 1.00
1 56.75 3.33 1.00
1 33.08 3.33 1.00
1 23.17 3.33 1.00
1 18.08 3.33 1.00
BALCONY RAILINGS 4 9.08 3.33 1.00
4 16.17 3.33 1.00
4 15.67 3.33 1.00
1 37.98 3.33 1.00
1 56.75 3.33 1.00
1 18.08 3.33 1.00
1 23.98 3.33 1.00
1 29.00 3.33 1.00
8 7.00 3.33 1.00
8 4.50 3.33 1.00
8 4.17 3.33 1.00

TOTAL

SEPTIC TANK 1 14.75 6.50 6.00


2 6.50 6.00 1.00
TOTAL
SOAK PIT 1 9.67 1.00 9.00
WATER PROOFING IN SEPTIC TANK 1 14.75 6.50 1.00
2 14.75 6.50 1.00
2 6.50 6.50 1.00

UNDERGROUND WATER TANK CFT 2 10.00 10.00 5.00


(10'*10'*5')
BRICKWORK SQFT 1 10.00 10.00 5.00
PLASTERWORK SQFT 1 10.00 10.00 5.00
PUNNING WORK SQFT 1 10.00 10.00 5.00

MANHOLE
BRICKWORK SQFT 4 1.50 1.50 1.50

SOAKPIT L.S 2

RCC WORK CFT


Columns
Top Floor 14 1.67 1.67 10.50
6 1.67 1.67 10.50
Beams 2 31.33 0.75 1.42
1 15.17 0.75 1.42
1 31.84 0.75 1.42
1 29.00 0.75 1.42
3 52.17 0.75 1.42
1 30.25 0.75 1.42
Slab 1 1970.78 1.00 0.42

Reinforcement For concrete Kgs. 1 1.00 1.00 1.00


STIMATE
QUANTITY REMARKS

141.70 [Ground Floor] 2 14.17 10 1 283.40


40.00 2 4.00 10 1 80.00
40.80 2 4.08 10 1 81.60
48.33 2 4.83 10 1 96.67
46.67 2 4.67 10 1 93.33
93.30 2 9.33 10 1 186.60
25.83 2 2.58 10 1 51.67
11.70 2 1.17 10 1 23.40
92.50 2 9.25 10 1 185.00
44.80 2 4.48 10 1 89.60
23.30 2 2.33 10 1 46.60
35.00 2 3.50 10 1 70.00
21.70 2 2.17 10 1 43.40
93.30 2 9.33 10 1 186.60
106.67 2 10.67 10 1 213.33
31.70 2 3.17 10 1 63.40
16.70 2 1.67 10 1 33.40
60.00 2 6.00 10 1 120.00
-27.00 deduct w3 -2 6.00 10 1 -120.00
60.00 2 6.00 10 1 120.00
-27.00 deduct w3 -2 6.00 10 1 -120.00
30.00 2 3.00 10 1 60.00
-18.00 deduct w5 -2 3.00 10 1 -60.00
60.00 2 6.00 10 1 120.00
-27.00 deduct w3 -2 6.00 10 1 -120.00
30.00 2 3.00 10 1 60.00
-18.00 deduct w5 -2 3.00 10 1 -60.00
60.00 2 6.00 10 1 120.00
-27.00 w3 -2 6.00 10 1 -120.00
50.00 2 5.00 10 1 100.00
-35.00 MD -2 5.00 10 1 -100.00
211.67 4 10.58 10 1 423.33
86.70 2 8.67 10 1 173.40
-21.00 d1 -2 3.00 10 1 -60.00
131.60 4 6.58 10 1 263.20
42.50 2 4.25 10 1 85.00
-17.50 d2 -2 2.50 10 1 -50.00
105.80 2 10.58 10 1 211.60
86.70 2 8.67 10 1 173.40
-21.00 d1 -2 3.00 10 1 -60.00
52.50 2 5.25 10 1 105.00
-17.50 d2 -2 2.50 10 1 -50.00
105.80 2 10.58 10 1 211.60
110.00 2 11.00 10 1 220.00
-21.00 d1 -2 3.00 10 1 -60.00
110.00 2 11.00 10 1 220.00
-21.00 d1 -2 3.00 10 1 -60.00
33.30 2 3.33 10 1 66.60
14.80 2 1.48 10 1 29.60
2057.37 3670.73

170.00
-48.00
141.70
-42.00
107.50
-21.00
145.00
-60.00
239.20
-48.00
-18.00
99.20
-36.00
113.30
-24.00
102.50
-42.00
31.70
-15.61
94.20
57.50
-15.61
40.80
-18.00
107.50
35.00
275.00

1371.88

60.00
-21.00
74.20
108.40
-17.50
67.50
44.20
21.70
23.30
60.00
91.70
92.50
-18.00
-12.00
125.00
85.80
126.60
18.30
-17.50
20.80
68.30
145.00
39.20
34.20
79.20
157.50
85.80
45.00
-17.50
102.50
-21.00
45.00
-17.50
126.40
188.98
110.16
77.16
60.21

2242.60

1189.39
266.75
214.25
33.82
156.53
54.20
288.09
163.57

2366.61

35.00
38.75
44.94
48.00
47.67
67.43
71.25

49.00
54.25
57.19
56.00
63.56
29.19
110.83

773.06

75.84
113.50
66.16
46.34
36.16

14.08

1694.22

338.00

618.86
474.82
103.14
133.38
108.41
233.03
612.03
241.78
345.07
2870.51

340.00
-48.00
283.40
-84.00
215.00
-42.00
290.00
-120.00
478.40
-48.00
-36.00
198.40
-36.00
226.60
-48.00
205.00
-84.00
63.40
-31.22
188.40
115.00
-31.22
81.60
-36.00
215.00
70.00
550.00
120.00
-42.00
148.40
108.40
-35.00
135.00
88.40
43.40
46.60
120.00
183.40
185.00
-36.00
-24.00
250.00
171.60
126.60
36.60
-35.00
41.60
136.60
290.00
78.40
68.40
158.40
315.00
171.60
90.00
-35.00
205.00
-42.00
90.00
-35.00
252.80
377.96
220.31
154.31
120.41
7125.95

1443.60

154.95
678.59
446.41
406.29
80.19

1766.43

1795.77

1443.60
16707.20
18150.80
313.26

1738.77
35.00
48.00
38.75
44.94
166.69

164.04
-17.50
-18.00
153.00
-12.00
-17.50
168.00
-17.50
-12.00
210.00
-18.00
-17.50

565.04
1572.09
34.79
34.79

29.75
37.92
16.33
16.33
14.00
49.00
38.50
4.67
10.21
23.33
16.33

256.38

14.58

149.94
191.10
355.62

357.00
455.00
168.00
84.00
96.00
504.00
396.00
48.00
157.15
2265.15

240.00
168.00
408.00

95.92
203.00
80.00
378.92

695.42
93.33
93.33
6.67
193.33

112.00

211.50 1 35.25 2 70.5


70.08 1 11.68 2 23.36
76.08 1 12.68 2 25.36
24.48 1 4.08 2 8.16
16.08 1 2.68 2 5.36
220.50 1 36.75 2 73.5
246.00 1 41.00 2 82
169.98 1 28.33 2 56.66
114.48 1 19.08 2 38.16
90.00 1 15.00 2 30
330.00 1 55.00 2 110
34.00 1 5.67 2 11.333333333
1603.18
534.3933333
100.20

126.27
188.98
110.16
77.16
60.21
121.07
215.60
208.93
126.47
188.98
60.21
79.85
96.57
186.67
119.88
111.09

2078.09

255.00 95.875
78.00
333.00
273.89
30.43
30.43
30.43
91.30

1000.00

200.00
300.00
300.00

13.50

409.97
175.70
66.58
16.16
33.91
30.88
166.68
32.22
821.16
1753.25
9682.37
BALUWATAR APARTMENT REMAINING WORK ESTIMATE
SN DESCRIPTION OF WORK UNIT QUANTITY RATE
A CIVIL WORKS
i RCC Work CFT
Columns 585.67 570
Beams 1167.58 570
Slab 821.16 570

ii Reinforcement bar Kgs. 9682.37 175

i BRICKWORK SQFT
9" THICK WALL 7544.89 465
4" THICK WALL 8970.39 325

ii WATERPROOFING WORK SQFT 7491.06 550

iii PLASTER WORK SQFT 35045.06 60

iv PAINT WORK SQFT 35045.06 60

v SCREEDING WORK SQFT 10305.09

vi PUNNING WORK SQFT 18150.80

vii SILL AND LINTEL BAND CFT 427.54 550

viii REBAR KGS. 2361.11 135

viii FLOORING SQFT


a. TILES EXCEPT TOILETS 6288.34
b. TILES IN TOILETS 666.74
c. WALL TILES IN TOILET 2260.16
d. KITCHEN GRANITE WORK 139.16
e. GRANITE IN WINDOWS SILL 256.38
f. WOODEN FLOORING

B DOORS AND WINDOWS


i WOODEN DOOR FRAME CFT 355.62
ii UPVC WINDOW SQFT 2265.15
iii UPVC SLIDING DOOR SQFT 408.00

C METAL WORKS
i TRUSS RFT
a. 3"*3" SQ PIPE 175.92
b. 3"*1.5" SQ PIPE 203.00
ii. TOUGHEN GLASS IN PERGOLA DESIGN TRUSS SQFT 695.42
iii. TOUGHEN GLASS FOR STAIRCASE SQFT 193.33
iv. METAL GATE SQFT 112.00
v. RAILING WORK SQFT 2345.28
vi. TANK STAND LADDER LS 1.00

D SANITARY AND ELECTRICAL


1 SANITARY LS
i PIPE LAYOUT LS
ii OVERHEAD WATER TANK-1000 Ltr. LS 1.00
2 SOLAR HEATER 24 TUBE

E WASTE MANAGEMENT
a. SEPTIC TANK
i. BRICKWORK SQFT 333.00
ii PLASTERWORK SQFT 333.00
iii PUNNING WORK SQFT 350.88
iv WATER PROOFING SQFT 91.30
b. SOAK PIT SQFT 273.89
c. MANHOLE SQFT
d. SEWER LINE
e. GREASE TRAPS
f. SUMP PUMP

F ELECTRICAL
i POWER DISTRIBUTION SYSTEM
ii WIRING AND CONDUITS
iii ELECTRICAL OUTLETS AND SWITCHES

G BOUNDARY WALL AND UNDERGROUND WATER TANK


i Brickwork SQFT 1603.18
ii Fencing SQFT 534.39
iii Plaster work SQFT 1603.18

UNDERGROUND WATER TANK-28300 LITRE 1000CFT


Brickwork SQFT 200.00
Plasterwork SQFT 300.00
Punning SQFT 300.00
Waterproofing SQFT 300.00
RK ESTIMATE
AMOUNT REMARKS

333831.33
665523.24
468060.25

1694414.62

3508372.30
2915375.32

4120083.02

2102703.54

2102703.54

10305.09

18150.80

235148.15

318749.51

6288.34
666.74
2260.16
139.16
256.38

355.62
2265.15
408.00
0.00
0.00
0.00
175.92
203.00
695.42
193.33
112.00 `
2345.28
1.00
0.00
0.00
0.00
0.00
0.00
0.00
1.00
0.00
0.00
0.00
0.00
333.00
333.00
350.88
91.30
273.89
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1603.18
534.39
1603.18
0.00
0.00
200.00
300.00
300.00
300.00
0.00
0.00
0.00
0.00
0.00