You are on page 1of 14

492

(昭和57年11月 日本 造 船 学 会 秋 季 講 演 会 に お い て講 演)

Application of New Construction Method to


Aluminum Spherical Tanks for LNGC

by Hiromasa Kawai*, Member Jinzo Nozaki**, Member


Kengo Nakayama**, Member Masataro Mitani**, Member
MasanoriKobayashi**,Member Hideo Takecia** Member

Summary
Thispaperpresentsan outlineof newconstructionmethodof 125,000 M3Moss
Rosenbergtype LNGCaluminumsphericaltanks whichwestartedbuildingin 1981.
Thisconstructionmethodhas manycharacteristicpointsand employsmoreadvanced
techniquesand has producedthe expectedresultsin savingson specialfacilitiesand
laborand in achievement
ofa highqualitylevel.

Rosenberg Verft, which has been adopted by


1. Introduction request of the users and the shipowners.
In our Nagasaki Shipyard & Engine Works of In regard to the construction method of alu-
Mitsubishi Heavy Industries, the aluminum minum spherical tanks, new techniques have
spherical tanks for the ship have been completed been developed and applied on the basis of the
and the ship is now under outfitting work. Sub- latest design in order to improve work efficiency
sequent to this ship, we received an order for two and achieve improvement and stabilization of
additional LNG carriers, which will be put in quality. In determining the tank construction
service in a project to import liquefied natural method, considerations were given to full utiliza-
gas from Arun in North Sumatra, and are build- tion of the existing facilities and application of
ing the aluminum spherical tanks for the third the latest techniques, with the top priority given
ship. to 100% trouble-free work.
We have energetically made various studies The features of the construction method of
for the past ten-odd years to prepare ourselves aluminum spherical tanks can be summed up as
for construction of LNG carriers. We have follows.
conducted various fundamental researches on (1) Adoption of three-sections tank construc-
materials, structure, element processing tech- tion method
niques and special outfitting, making the most (2) Assembly stage work done indoors instead
of the potentials of our laboratories, and at the of outdoors
same time, have continued studies on the opti- (3) Integrated production in our own ship-
mum construction method and construction yard from material forming to completion
facilities as well, so that we can build any type (4) Development and application of latest
of LNG tanks. element techniques
At present we are not only putting the abund- This paper reports on the features of the tank
ant results of the series of these researches and construction method and the results of tank
studies into practical use but also making vari- construction, focusing on the aluminum spherical
ous improvements including those in element tank construction method which is one of a few
techniques on the basis of our experience. All key points in the construction of LNGC.
three ships we are building at present are of the
2. Basic Construction Method
aluminum spherical tank type developed by Moss
2.1 Spherical Tank Construction Method
* Shimonoseki Shipyard & Engine Works, Needless to say, the key points in building an
Mitsubishi Heavy Industries, Ltd. LNG carrier are :
**
Nagasaki Shipyard & Engine Works, Mitsu- Construction of aluminum spherical tanks,
bishi Heavy Industries, Ltd. and
Application of New Construction Method to Aluminum Spherical Tanks for LNGC 493

*
A B C D MHZ

Fig. 1 Comparison of production procedure of spherical tank

Special outfitting related to handling of to be received steadily. From the standpoint of


LNG construction capacity, construction of two ships
Spherical tank construction methods can largely per year seems adequate for the time being. On
be classified into the following three categories the other hand, C and D companies have been
as is clear from Fig. 1. effectively using the existing facilities for con
One-block construction method struction of tanks.
Two-segment subassembly There is a view that tanks should be built
grand assembly to sphere indoors in order to achieve the required quality .
(A company) However, several shipyards make it a rule to
Two-segment subassembly—ring assembly- construct tanks outdoors, and the grounds for
-tank assembly thinking that indoor work is absolutely neces-
(B company) sary from the standpoint of quality are not
Ring assembly method completely clear. Examining the effects of exter-
1/2-ring fit-up-1/4-ring subassembly nal environmental conditions upon assembly
ring assembly-ank assembly and welding, we judged it is feasible to construct
(C company) tanks outdoors if necessary countermeasures were
Three-sections construction method taken. We studied what effects an extensive
1/4-ring subassembly-ring assembly facility investment will have at the present stage
three-sections assembly upon construction efficiency and the quality level
(D company) to be achieved, and reached a conclusion that it
Four-segment subassembly was the best to make the effective use of the
three-sections assembly existing modern facilities of our Koyagi Works.
(Mitsubishi Heavy Industries) We made a comparative study in respect of
Each of these methods has its own unique quality and construction efficiency as to whether
characteristics. The main factors which influenc- to construct spherical tanks in one piece or in
ed out decision on the construction method are sections in Koyagi Works, and found it desirable
quality, investment in facilities, construction to construct them in three sections. When the
efficiency, number of ships on order and construc- three-sections construction method is adopted ,
tion capacity. each section must be welded together on board
As regards construction facilities, the one- the ship, but we arranged to perform the master
block construction method as used by A com- seam welding, which is only less than 10% of
pany required a enormous facility investment the total welding length, in exactly the same
including construction of new housing, and poses environmental conditions as indoors by schedul-
a high risk unless orders for ships are expected ing it after installation of the tank cover. The:
494 日本 造 船 学 会 論 文 集 第 152 号

Fig. 2 Production tolerances for LNG tank (Example)

three sections construction method made it As regards the accuracy of tank volume, the
possible to construct tanks without any modifi- required accuracy level of each tank must be of
cation to the existing facilities of Koyagi Works. an extremely severe value in order to attain the
The points to be considered in constructing guaranteed cargo carrying capacity while minimiz-
spherical tanks are the accuracy control of the ing an surplus tank volume. Incidentally, when
spherical tanks and quality of welding joints the tank girth length is 30 mm shorter uniformly,
(welding quality). The accuracy of tanks is there will be a shortage of 20 m3 in a 25,000 m3
twofold ; accuracy of tank volume and accuracy tank. In the case of Al 5083-0 material used for
of tank form which is important by strength the tanks as shown in Table 1, the 10-meter
reason. girth length varies by 2.6 mm in every tempera-
Application of New Construction Method to Aluminum Spherical Tanks for LNGC 495

ture change of 10•Ž. Therefore, what accuracy ed.


control method is to be developed is an important The most important points in element tech-
task as well as establishment of the measuring niques are bending and bevelling techniques.
technique. As regards the amount of deformation We succeeded in raising the accuracy level con-
allowable from the viewpoint of tank strength, siderably by developing the NC press bender and
relatively many factors have been published, and the NC bevelling machine. As for the quality of
they are considered reasonable when various welding joints, we achieved nearly perfect weld-
elements in construction are taken into account. ing edges and thorough going advanced training
We established the accuracy standards as shown and individual control of more than 100 qualified
in Fig. 2 taking into account our strength calcula- welders. The problems and remedies related to
tion results and the construction accuracy level welding will be reported briefly in a later sec-
achieved in tests. What effects will these ac- tion.
curacy standards have on the construction effici- In constructing spherical tanks, the accuracy
ency ? Needless to say, a high accuracy of seg- of segments was achieved with the NC bevelling
ments and assembly make it possible to reduce machine, and in the assembly stage, three- and
unnecessary time for repairs and so on, and in four-segment assembly was performed, using a
view of the quality level required of the spherical simple assembly method with the tilting assembly
tank, it is necessary to achieve a much higher pedestal as the dimensional standard. In assembl-
accuracy standard one level above the accuracy ing the ring and the sections, we adhered to an
standards for the conventional hull construction ; assembly method using the accuracy of the
therefore, it must be said that a decrease in ac- assembly pedestal as the standard, making
curacy level will have an extremely great effect. adjustment for effects of temperature change
In order to attain with ease the accuracy level and assembly welding. This made it possible to
required of the spherical tank construction, it is reduce unnecessary work during assembly work.
evident that the accuracy of each segment (petal) As regards the quality control system during
is more important than anything else. the tank construction, we throughly implemented
In one shipyard, the accuracy level of each the quality assurance system, and took extra
segment is less than 2 mm in length, and in other precautions for verification of work. The quality
respects, error ranges exceeding 3 mm are the control system used this time is a piece-by-piece
standard ranges. What consequences does this control, and integrated stage-by-stage control
have in the assembly and welding stages ? As and also the vertical control from the material
seem from a comparison of spherical tank con- forming stage to the completion of tanks.
struction methods adopted by various ship- 2.2 Block Division
yards in Fig. 1, assembly and welding work on Aluminum was chosen as the material of
the ground, indoor work and the size of blocks spherical tanks at the wishes of the users and the
are limited. This is not desirable from the stand- ship owners. We had compared it with 9% Ni
point of the efficient construction method used steel, studied in detail which may be advantage-
in the conventional shipbuilding process. An ous in cost and construction method, and made
increase in volume of work on the ground will it clear that there is no problem with either
necessarily improve construction efficiency and material as far as the construction method is
lead to stabilized quality. Therefore, an increase concerned. Table I shows the chemical composi-
in the accuracy of every segment (petal) will tions and mechanical properties of Aluminum
necessarily improve the conditions of segment 5083-O.
joints and the efficiency of welding, which will What is essential from the viewpoint of con-
lead to facilitation of ring assembly and grand struction efficiency is a small number of seg-
assembly in the subsequent processes. Con- ments of spherical tanks, a small plate thickness,
sidering assembly efficiency and facility utiliza- and a small number of tanks. The number of
tion rate, we made it a standard to use three- segments is limited by the manufacturing capa-
segment and four-segment subassemblies. This city of the material suppliers and the processing
was expected to increase the application ratio of capacity of our shipyard. Major manufactures
the high current MIG welding method in flat of thick aluminum plates are major U.S. com-
position and improve the work efficiency and panies and several Japanese companies, and the
quality. Our detailed research shows that in materials made by the former were found superior
applying the high current MIG welding method, by a test we conducted around 1970. However,
it is desirable to maintain the welding joint gap we newly conducted market research this time,
within 1 mm. Therefore, we established element and found that the materials made in Japan
techniques so that the target of the work ac- were very good in quality and cleanliness and
curacy standards shown in Fig. 2 will be achiev- were more advantageous when economy and
496 日本 造 船 学会 論 文 集 第 152 号

Table 1 Chemical compositions and mechanical properties of Aluminum 5083- O

level of segments and forming capacity outside


our shipyard, we reached a conclusion that it was
advisable to buy flat plates and form them by
ourselves.
Fig. 4 shows the above-mentioned basic con-
struction method developc-d by stage.

3. Development of Construction
Method by Stage

3.1 Forming Stage


Fig. 5 shows a comparison of different com-
panies' methods of forming segments of spherical
tanks. As seen from this figure, some U.S. ship-
yards purchase trapezoidal plates and hot-form
them. For welding edge preparation, they adopt
a method using portable bevelling machines and
guide rails. Another U.S. supplier performs cold
forming with a 3,000 ton press, and make edge
preparations with NC plasma cutting machines
and portable bevelling machines. As the forming
method which is an important point in building
spherical tanks, the hot forming seems advantage-
ous from the standpoint of accuracy, but it
should be evaluated in relation to the invest-
ment in facilities. Although cold forming is a
standard method, it is not easy to cold form
wide and thick plates within a strict accuracy
range in a short time, and it would be necessary
to accumulate techniques and knowhow to do it
successfully. An ideal forming method would
be to cut flat plates, bevel and then form them,
Fig. 3 Tank division but since the amount of spring back and elonga
tion and contraction due to forming operations
are not constant, there is no alternative but to
steady supply was taken into account. Con- make edge preparations after forming plates.
sidering the maximum width of plates produced Therefore, we conducted systematic experi-
in Japan and our processing capacity, we decided ments to find how to improve forming accuracy
to divide spherical tanks into blocks as shown in and keep the accuracy of segment dimensions
Fig. 3. As compared with some U.S. shipyard, within the allowable range, and as a result,
the number of segments is greater, which is developed and put into practical use the NC
because there is a limit to the size of Japanese press bender :Mitsubishi type three-line press;
plates and tapered plates are not used. One of for bending operation and the NC bevelling
the points in purchasing plates is whether to buy machine for bevelling operation. With these
flat plates or formed plates. After making a study machines we could achieve an accuracy higher
with priority given on improvement in accuracy than the target value.
Application of New Construction Method to Aluminum Sphericaf Tanks for LNGC 497

Fig. 4 Production procedure of spherical tank (No. 1)

As shown in Fig. 5, we purchased trapezoidal The Mitsubishi type three-line press machine
plates mainly to minimize scrappage and cut has three lines of press heads, with ten pairs
them into the specified shapes with NC plasma of heads, at top and bottom, on each line, and
cutting machines. The plasma cutting machines can be set at any desired radius of carvature.
are of the air plasma type which had previously The machine has an arithmetric formula built in,
been used for cutting steel plates. The plasma which is preprogrammed to be obtained the desir-
cutting machines were also used for marking of ed radius of carvature, so that bending operation
various lines, which were kept to the required can be performed by feeding initial values cor-
minimum. responding to the shape and thickness of seg
498 日本 造 船 学 会 論 文 集 第 152 号

Fig. 4 Production procedure of spherical tank (No. 2)

ments. Plates to be bent are checked for dimen- that the curvature of segments is not 100% ac-
sional accuracy on the accuracy measuring curate, the machine is provided, on the support
device, and are finished to the final dimensions bed, with the vacuum support stand to maintain
with the NC bevelling machine. The machine the curvature radius of spherical tanks. NC
has two sets of bevelling heads which can be put control is performed on the plane (x, y axes)
to work simultaneously. In order to shorten only, and the copying system is used for the verti-
loading and unloading time and thereby increase cal control (z axis). The bevelling accuracy was
the bevelling time ratio, the machine is provided held within 0.25 mm in dimensional error and 2°

with bevelling heads in two stages. Considering degree in angle; as a result, the gap at the joint
Application of New Construction Mlethod to Aluminum Spherical Tanl, T.NGC 499

A B C MHI

Fig. 5 Fabrication methods Of segments

Fig. 6 NC press bender F g. 7 NC bevelling machine

between two plates was kept less than 0.5 mm. tion of welding distortion, but the high curreilt
and the segments for spherical tanks for two MIG welding method was developed which was
ships have already been processed to the aimed capable of keeping welding distortion withIl
accuracy. Fig. 6 shows the NC press bender an allowable limit, and a procedure for correctinh.,.
welding distortiom was established in case weld-
(Mitsubishi type three-line press), and Fig. 7
the NC bevelling machine (Mitsubishi planoma). ing distortion should occur.
3.2 Assembly Stage The aPpllcation ratio of the high current MIG

The decisive factor of the spherical tank as- welding niethod reached about 56% of all weld-
sembly method would be to increase the ratio of ing length of about 2,000 m/sphere, thcreby
work to be done in the assembly stage as much achieving a remarkable reduction in the spherical

as possible within the range in which ring assem- tank assembly time while achieving nearly 100%

bly and block assembly can be carried out perfect welding quality. Figs. 8 and 9 show a
smoothly. We reviewed two-segment (petal) comparison of the application ratio and welding

subassembly method which had been com- efficiency by welding method. It can be seen

monly used in the past, compared and analyzed from the figures that the increase in the ratio of

the possibility of three- or four-segment sub- work on the ground and the increase in the size

assembly through an improvement in accuracy of block made a great contribution. Assembly

level, and reached a conclusion that they were and welding were performed on positioners

practicable from the standpoints of accuracy and shown in Fig. 10. The positioners which we made

quality. An increase in the number of segments and used this time can be operated with single-

in subassembly is liable to cause difficulty in. shaft control and can be held at any desired

adjustment of dimensional accuracy and correc- inclination angle within 6•} 1 degrees when weld
500 日本 造 船 学会 論 文 集 第 152 号

Fig. 10 Positioning pedestal for assembly


stage

the inaccuracy of welding edges was less than

1 mm, and variations of girth length and other

dimensions were less than 1.5 nun. The effect on

welding quality of coexistance of work on steel

and on aluminum had qualitatively been discus-

sed but its quantitative effect was not clear.

We made various experimental studies of this

matter to work out countermeasures for practical

application, and found that the effect of simul-

taneous work on steel and aluminum was much

smaller than expected. We allocated an area

Fig. 8 Application of welding method exclusively for work to be done on aluminum

after bevelling process to prevent unnecessary

troubles, and established the allowable limit

values for practical application, quantitatively

examining the effect of steel particles and other

foreign substances on the high current MIG

welding.

Development and practical use of jigs contrib-

uted to smooth execution of work in subassem-

bly, ring assembly and grand assembly stages.

In cutting, bevelling and grinding operations,

portable jigs played a great role in production


schedule, quality and efficiency.

3.3 Ring Assembly and Grand Assembly

After three-segment subassembly and four-

segment subassembly were finished, the equa-

torial ring, northern and southern hemisphere

sections were assembled in the grand assembly

shop. As shown in Fig. 4, the equational section

requires the most work, with the equatorial ring

of 156 mm thick plates, and is connected to the

hull structure through the skirt. Therefore

the accuracy of the equatorial ring is not only

the most important point in the construction of


Fig. 9 Comparison of welding efficiency
spherical tanks but also needs to be finished to

the severest level at the joint with the hull

ing operations are carried out. Each kind of structure.

As shown in Fig. 2, the actual deformation of


positioners was made separately for two-segment
subassembly, four-segment subassembly and the assembled ring was less than •}20 mm on

poler segment subassembly. At the time of set-up, diameter in the standard range. One of the
ApplicnLtioll of New Construction Method to Aluminum Spherical Tamks for LNGC 501

It goes without saying that minute care is mces-


sary taking into account the effects of tempera-
ture changes, error of measuring equipment and
welding contraction, etc.
Welding in this stage involves difficult elements
especially, the accuracy of welding joints have
a great effect in horizontal welding. Therefore.
adjustments were made to minimize errors of
girth length, offset, etc., and satisfactory welds
were obtained. Fig. 11 shows the assembly pedes-
tal.
4. Welding Technique
Fig. 11 Grand assembly pedestal 4.1 Selection of Welding Method
The MIG welding method is generally used
to weld Al 5083 material. We used a high
reasons why this figure was aimed at was to current AEG welding method in the assembly
prevent problems from arising at the joint be- stage, three- and four-plate subassembly. In the
tween the reinforced part of the hall structure final assembly and the skirt assembly stages, we
and the skirt of the aluminum spherical tank. used the narrow-groove MIG welding method we
For this purpose, in the equatorial ring assembly developed as well as the ordinary MIG welding
too, each segment was fully checked for accuracy method, as shown in Fig. 8. A comparison of
and was finished taking into account welding the mechanical efficiencies (excluding set-up) of
deformation and contraction. As the result, these methods is shown in Fig. 9. This figure
errors of girth length were less than 30 mm. reveals what a great effect the extended applica-
For other petals than equatorial itself, adjusting tion of the high current MEG-welding method had
plates were provided so that final adjustment of upon the improvement of welding efficiency. The
girth length could be made in the final assembly application of the narrow-groove MIG welding
stage but such -measure performed their func- method contributed to the improvement in
tion in the first spherical tank only and were efficiency of vertical and horizontal welding. The
almost unnecessary to the second and subsequent ratio of automatic welding methods applied to
spherical tanks. An assembly method using an the spherical tanks proper was 97% and the
grand assembly pedestal as the reference was ratio of the high current MIG welding method
adopted because the most important control reached 56%. As for the welding quality, we
point in the final assembly of spherical tanks is first anticipated repair welding of several percent,
girth length accuracy, and the spherical tanks but thanks to improvement in welding equip-
are of the skin structure. With this method, ment and in accuracy of welding edges and to
nearly exact shape and girth length were obtain- advanced training of welders, welding defects
ed, but it is no easy job to keep the error of girth which actually occurred were less than one
length within 30 mm in such a. large structure. percent in terms of the number of X-ray films

Table 2 Example of welding condition


502 日本 造 船 学 会論 文 集 第 152 号

taken. Defects were all blowholes, which were from designing, material inspection, transport
repaired by welding to the perfect quality. Table storage, forming, assembly, measurement, inspec-
2 shows an example of typical welding condi- tion, etc., a fine mesh of quality assurance system
tions. was set up, so that anything which did not con-
4.2 Problems and Remedies in Welding form to the standards in one stage would not
It is known from various literatures that the move to the next stage, which is, as it were,
working environments have a great effect on 100% check system. To carry out this system
welding of aluminum materials. We conducted smoothly, necessary measures were taken such
a thorough investigation into all factors which as development and application of element
seemed to have an effect on welding quality. techniques.
Since the details of this investigation will be Figs. 12 shows an example of studies on surface
reported at another opportunity, only the con- protection of aluminum tank by FTA.
clusion is briefly mentioned below. First, high 5.2 Accuracy Standards and Results
temperature and humidity of the atmosphere had Fig 2 shows the accuracy standards for tank
little effect upon the high current NHGwelding, conLtiuction and the results 'the accmacy
and tended to cause blow-holesin the ordinary standards w ere set up taking into account all
MIG welding, especially in the horizontal weld- deformations anticipated donut; the construc-
ing. To prevent them, it was necessary to heat tion process and the standard \allies w hick could
cooling water (torch), pre-flow shield gas, and be permitted from the standpoint of design The
dehumidity of wires. There is a literature which accuracy standards is ere developed from the
reports that a humidity of 85% is the upper final process back to the preceding processes,
limit permissible for welding, but according to and the accuracy le\ el to be achievel in each
our experiments, the upper limit varies with stage was determined. The target shown in
temperature and absolute humidity. Fig. 2 is what we set up as the standard range.
In regard to the effect of various kinds of dust The target values for the diameter errors of the
and dirt, the degree of effects of iron dust and three tank blocks were severe, which were dictat-
welding fumes was examined since aluminum ed by the tolerances for STJ (structural transi-
materials were worked on in the shop previously tion joint), that is, the joint bete cen steel and
used for work on iron and steel materials, and aluminum skirt structures, and the earlier the
as a result, it was found out that there was no construction process, the severer the accuracy.
problem if welding conditions (protection of Thus, it can be recognized how important the
temporary parts, etc.) were selected in a proper accuracy of each petal is. The errors of the girth
range. As a matter of course, cleaning of petals length of spherical tanks were us the range of
and welding edges was carried out as part of 10-20 mm, so it can be said that there was
the established work system. Grooves for the vintually no error in the tank diameter. The
high current MIG welding need sti act checking accuracy of tank joalt, with the hull structure
since foreign matter is liable to fail into them. is as also satisfactory
As regards the effect of wind, the level which 5.3 NDI Standards and Results
had no effect on welding quality was about 0.5 m/s As the NDI standards for s erilying the quality
although it had relation to the constinetion of of welds, the NV rules were generally used in
tin. welding torch and gas flow. the past This time, however, we conducted
many tests and as a result, adopted an inspec-
5. Quality Control tion method mainly using VT as shown in Table
5.1 Control Method 3. The inspection standanls were approved by
The objectives of quality control in spherical NK. and the ship-owners. In the case of the NV
tank construction are, needless to say, to secure rules calling for an mspecirm method mainly
the required tank volume, prevent tank deform- using RT, cracks and insufficient fusion are
ation for s*rength reason and prevent foreign difficeilt to detect with RT; therefore, we decided
matter from entering the tanks. We thoroughly to use an inspection method mainly using UT
conducted quality assurance programs for ac- combned with RI whick is superior in detecting
curacy, welding quality and surface cleanliness, spherical defects such as blownoles Details of
etc. Besides the stage-by-stage control by the the applicat ion standards of the inspection
exclusive line organization for aluminum spherical method will be reported separately
tank construction, a direct staff responcsibleto The ratio of welds winch passed the initial
accuracy and welding was assigned, and every inspection reached 99% (the first ship), and al-
piece and part were thoroughly followed up in though blow holes are liable to occur in the
all stages from the start of marking to comple- horizontal automatic welding and semi-automatic
tion of spherical tanks. Therefore, in all stages welding, cracks or insunicient fusion did not
503
Application of New Construction Method to Aluminum Spherical Tanks for LNGC
504 日本 造 船 学会 論 文 集 第 152 号

Table 3 Non-destructive test plan and inspection result

In addition to visual inspection, the followings are to be applied

Inspection result (Initial data)

Total 99.0%

occur at all. Table 3 shows non-destructive test standing problems were solved by thorough
plan and inspection result. advanced verification. In order to achieve further
improvement in construction efficiency and
6. Concluding Remark
stabilized quality, we will continue to make
This paper has presented an outline of the con- various technical improvements. Since there
struction method of spherical tanks. The con- are many things to do including expanded ap-
struction method has been determined through plication of the narrow-groove welding method,
the earnest efforts of our naval architects exerted we intend to steadily accumulate technical im-
over many years, and the construction of the provements. Though the brief description, we
tanks has been progressing very smoothly. In hope that this paper would be helpful in the
implementing this construction method, out- field of aluminum tank construction.
Application of New Construction Method to Aluminum Spherical Tanks for NLGC 505

Acknowledgements CATION OF 41/2 PERCENT Mg-ALUMI-


The study of the construction method was NUM ALLOY-WELDING AND INSPEC-
conducted with the assistance and cooperation of TION, IIW,1976, MTC.
many people, and the authors wish to express 7) Y. Murata, I. Yonekura, S. Minahata:
their appreciation to Mr. M. Kanayama. Director, Non-destructive Test of Welding Joints in
General Manager of Nagasaki Shipyard & Engine Al-Alloy LNG Spherical Tanks, Kawaju
Works, Mitsubishi Heavy Industries, Ltd. (M.H. Giho, No. 64, August, 1976.
I.), Dr. R. Nagamoto of Nagasaki Shipyard & En- 8) A Gromholt : Fertigung und Montage
gine Works, Mr. M. Ono and Mr. N. Ito- groBer Kugelformiger Tanks fur den Schiffs
-transport verflussigter Erdgase ,Vorget-
yama of Ship Engineering Dept., M.H.I. of our
Head Office for their kind assistance and advice. ragen auf der GroBen SchweiBtechnischen
Tagung 1977 des Deutschen Verbandes
References fur SchweiBtechnik (DVS) Essen, Septem
1) P. Takis Veliotis : A Solution to the Series ber, 1977.
Production of Aluminum LNG Spheres, 9) J. Nozaki, K. Nagamoto, M. Kurokawa,
The Society of Naval Architects and Marine K. Iwamoto, Y. Ito: Non-destructive
Engineers, November, 1977. inspection of welding joints in Aluminum
2) Kawasaki Heavy Industries, Ltd. : LNG Spherical tanks, Presented in the autumn
Carrier by Kawasaki, September, 1978. meeting of The West-JAPAN SOCIETY
3) The special issue of LNG ships, Bulletin OF NAVAL ARCHITECTS,1982.
of The Society of Naval Architects of Japan, 10) R.Nagamoto, E. Sakai, H. Takeda, S.Oba:
Vol. 631, Jan., 1982. Prevention of packling Phenomina Gccur-
4) M. Mizuno, K. Minoda, A. Sakaguchi : ring to Aluminum Alloy thicker plate
Welding of Aluminum and Aluminum welding loints by using High current MIG
Alloy, Yosetsuzensho No. 13 by Sanpo weldillg method, Presented in the autmmn
in 1979. lneeting of Japan Nvelding society,1982.
5) BERG A-FINSNES O. F.:Quality As- 11) H. Nito, E. Sakai, T. Hayashida, S. Mori-
surance inthe buildingof welded Aluminum uchi : Prevention of blow hole in the con-
Tanks for Shipboard Transportation of ventional MIG weldillg joints of Aluminum
LiquefiedNatural Gas, Technical paper by Alloy thicker plate. Presented in the
DET NORSKE VERITAS, Norwav. Autum meeting of Japan Welding society,
6) H. Wintermark CRYOGENIC APPLI- 1982.

You might also like