ACTIVITY PRECEDING TIME
A - 3
B - 4
C - 6
D A 2
E B 6
F C 3
G D,E,F 5

1 3
6
5

4
2

1 3
6
5

ACTIVITY DURATION TOTAL FLOAT FREE FLOAT

A 3 8–0–3=5 3–0–3=0

B 4 4–0–4=0 4–0–4=0

C 6 7–0–6=1 6–0–6=0

D 2 10 – 3 – 2 = 5 10 – 3 – 2 = 5

E 6 10 – 4 – 6 = 0 10 – 4 – 6 = 0

F 3 10 – 6 – 3 = 1 10 – 6 – 3 = 1

G 5 15 – 10 – 5 = 0 15 – 10 – 5 = 0
Critical Path = B-E-G

3
6
5
1

Project Duration = 4+6+5=15