You are on page 1of 50

FIDIC

FIDIC

1913
1949
60

1996 FIDIC
FIDIC

FIDIC 1 1957 2
1963 3 1977 1988 1992
1988 4 1999

FIDC
FIDIC
2002 5 FIDIC 1
FIDIC
EPC/
FIDIC

FIDIC

1
2
3
4
5
6
7
8
9
10
11
12

FIDIC



ICE FIDIC

EDF
ACP OCT
1.
FIDIC
110
1889 1961

2.

AIA
A101-1987 A101-1977
A111-1978

AGC500-1980
ICE51973
ICE61991ICE MW1988
JCT63
JCT80
1991

1991

1990

1976
1986

EDF ACP
EDF FIDIC
1987 4
3.

2
3

FIDIC

Price Risks

B.Q.
B.Q. Bill of Quantities BOQ
"" Price Schedules
B.Q.

B.Q.

B.Q.

B.Q.

FIDIC
B.Q.

55
B.Q.

FIDIC

B.Q.

B.Q.
"Looking for the gaps in the B.Q."

FIDIC
FIDIC "" B.Q.
"
"

B.Q.

B.Q. ICE
FIDIC
FIDIC 60
""
B.Q.

B.Q.

B.Q.
1
2

B.Q.

B.Q.
B.Q.

FIDIC
B.Q.

B.Q.
B.Q. FIDIC

B.Q.

FIDIC

"
"Cost plus Benefit Contract

FIDIC "
"""Remeasurement
Contract B.Q.

""

Site Record

""
""


""
""

B.Q.

FIDIC 56

B.Q.

""Front
Loading


"
" FIDIC 65
66 69

B.Q.

1000
500
20-30%

B.Q.

""
Active Cost
Driver Apportionment

100 /m3 10000m3


15000m3 B.Q.
130 /m3 130
/m310000m3 130
/m315000m3 100 /m3

"
"
50%

Price Risks

FIDIC

FIDIC
FIDIC
FederationInte.nationaledesln nieurs-Conseils
,, FIDIC
,FIDIC
,

()FIDIC
FIDIC :
,
(Conditions Of ContraCt for works of Civil Engineering
ConstruCtion),.
,,
(Conditions Df ContraCt for E LeCtrieal and
MeenaniCal Works),,
,
(Client/(Consultantmodel ServiCe Agreement),
,
;,
>Conditions of Con-traCt for Design-Build
and Turnkey ,1995),,
,

BOT , FIDIC 1999 EPC


,<(Conditions of
ContraCt for EngineCring,Pro-Curementand
ConstruCtion),,

(The Short Form ofContraCT), FIDIC


,
,
() FIDIC
FIDIC ,
;,
FIDIC ,

, EIDIC
,,

FIDIC ,
60 FIDIC
,
,FIDIC ,
,,
15%,
, 20%
, 25%,FIDIC
,
,FIDIC
,
, 80%
FIDIC
()
FIDIC ,,
FIDIC
,,
,,

FIDIC ,
,
,
,
,
,
,,
,
,,

,
()
,
,,
,

,,;
,
,Q.S()
,,
,,
,,

,,

()
FIDIC , 1977 ,
1988 , 1999
FIDIC
1977 ,:
,FIDIC
, windows,
, 1977

,,
FIDIC
,
()

,,,
,,
,
,
FIDIC :,

,,
, FIDIC (
),,
, FIDIC ,

FIDIC , ICE
( LCE ),LCE The
Institution Of Civil En neers ,ICE
FIDIC , FIDIC ICE ,

ICE ,
ICE
,
, FIDIC ICE
, FIDIC ,
,,

,,,
Know the ContraCt,Use the
ContraCt(,)
() ICE FIDIC
, ICE FIDIC
( 72 ),
:ICE ,; FIDIC
,
:
FIDIC ,, ICE

,,
,( ICE
),,
FIDIC , ICE ,
EIDIC (,
FIDIC Conditions Of SubContraCt for Works of
GvilEngineering ConstruCtion,1994)
,
,
ICE ,

FIDIC ICE ,
,, FIDIC
,FIDIC ICE (Common Law)
,,,
(Continentallaw)
,,,
,,()

,,,
,,,
,
,(Rules Of
Equity) 50 ,
20 ,,
,,
,
,, 3
, 27 ,
, 40 ,
23 , 17 ,

FIDIC ICE ,
,

,,
(),

()
, FIDIC
:,(The
ContraCtor gets paid for the work heoor-fonns and the
Employer gets the work he is paying for)

FIDIC 60 69 ,

,
,,,
,,,
,,
,,
,, FIDIC
69 ,
,,

,,
,
, 800 ,

,
, B.Q.
,,
,
()
,
, 24
,,
,
,
,, 10%
5%( 2.5%, 2.5%
),,
,,,
,,

FIDIC ,
,
;,,
,
FIDIC ,
"",
,
"",
""
,
, B.O.

,,/,
,,,
,:,
,,
;,
, FIDIC 63
69 ,,
63 , 69 ,
,, 69
66 ,, 63 69


() FIDIC
FIDIC ,
,,

B.Q.,
FIDIC 5.2
,
, FIDIC ,
,,

FIDIC ,
,, FIDIC ""
(,
FIDIC );,
,
,
,,
,
, FIDIC ""
,,
?
FIDIC ,
(Pan I),(Pan II),
,,

FIDIC ,""
,,
,
,

()
,,;
,,,
,
,
, FTDIC 60 ,
,

,
,,,
,,,,
,
,,
,
()
FIDIC
,,
,,,
()
FIDIC ,

,
,
:,
,,
,,,

,"(Contra Proferentum Rule)",


,

FIDIC ,, 67
,
, notiCe OfdeCision By the
Engineer,
,,,
:
()
,,
,
FIDIC
"",,
,,
,"
"(Business Engineer),
,

:
,,
,,
,
,,
,
FIDIC 7.2 ,
(ConstruCtion Drawings)(Shop
Drawings),
,?,
,,
FIDIC 7.3 ,
,
,
, FIDIC
"",
(ioint and severa liabilities)
, 8.2
,
(fessional Tndenmity In SuranCe)
,
FIDIC 13 49.4 ,

, FIDIC ,
,
,(
),
10%
1%-4%

FIDIC

FIDIC

FIDIC
FIDIC 1999

1Conditions of Contract for


Construction""

building or engineering
works

Conditions
of Contract for Works of Civil Engineering Construction
""

engineering civil engineering

2Conditions of
Contract for Plant and Design-Build"
"
/

/
Conditions
of Contract for Electrical and Mechanical Works"
"
""""
Plant
""

3EPC Conditions of Contract for


EPC Turnkey Projects""

i
ii

""

Conditions of Contract for Design-Build and Turnkey


"" FIDIC ""
"" EPC Engineering
Procurement and Construction EngineerProcure and
Construct Engineering
Design

4Short Form of Contract

/
FIDIC
FIDIC1999 "
"""""
1
20 70

FIDIC
"
"1995 1994
AIA JCT

FIDIC 1999 ""


10 EPC
EPC
EPC
FIDIC FIDIC

2
FIDIC
"" 25 72 194 "
" 32 51 197 "" 20 160

FIDIC1999
"" 20 "
"160

""
""
""
""

""""""
""
"" 3 """" 3
""""
""

14

3
5

5
4
24

5
4
8
8
6
11

7
8

8
12

9
4

10
4

11
11

12
4
4
4
13
8

14
15

15
5

16
4

17
6

18
4

19
7

20
8

""""
"""" 4.5 "
""""" 5 4.5
""

""

FIDIC1999
FIDIC """"""
FIDIC

FIDIC1999

FIDIC

1 FIDIC
FIDIC (Fdration
Internationale Des Ingnieurs-Conseils) 1913
FIDIC
60 1996
FIDIC

FIDIC 2 FIDIC
(ASPAC)FIDIC (CAMA) FIDIC
/
(CCRC)(CC)(EC)
(ENVC) (QMC)21 (Task
Force 21)FIDIC (FIDIC POBox
861000 Lausanne 12Switerland)
2 FIDIC
FIDIC
FIDIC FIDIC

FIDIC

(Conditionsof Contract for Work


Of Civil Engineering Construction FIDIC)
(Conditions of Contractfor
Electrical and Mechanical Works FIDIC)
/(Client/Consulant Model
Services Agreement FIDIC)
(Conditions of Contract for
DesignBuild and Turnkey FIDIC)
FIDIC

1957
196319771987 19881992

2 1996
1999 FIDIC 2
FIDIC
21 (Condition of Contract for
Construction)

(BuildingWorks)
(Engi- neeringWorks)
22 (Conditions of
Contract for Plantand DesignBuild)

23 EPC (Conditions of Contract for


EPC Turnkey Projects)

24 (Short Form of Contract)

FIDIC

3 FIDIC
FIDIC

FIDIC
(General Conditions)
(Conditions of Particular Application)
(
)

FIDIC
31

FIDIC
FIDIC

32
FIDIC

FIDIC
FIDIC

FIDIC

33
FIDIC

34
FIDIC

FIDIC

FIDIC

4
FIDIC

FIDIC

FIDIC

FIDIC

FIDIC 99

FIDIC
1957 FIDIC [
FIEC]ACE

1
FIDIC

1963

1969

1977 FIDIC FIEC


Federation Internationale Europeenne de la
Construction()
1980
1987 9


1988

1995 -
198719871995
-
/
FIDIC

1999 9 FIDIC 4

Conditions of Contract for


Consrtuction for Building and Engineering Works Designed
by the Employer
-

Conditions of Contract forPlant and Designed-Build for


Electrlcal and Mechanical Plant and Building and
Engineering Works Designed by the Contractor
EPC/
Conditions of Contract for
EPC/TurnkeySilver Book
FIDIC
Short Form of contractGreen Book
FIDIC
FIDIC

FIDIC
/
/

15 52
1

--
Design-Bid-Construction

1
1995 20

4
3

2-
--

Design-Construction

2-

3
4

1 1995

2
7

4 DAB

3EPC/

EPC/

EPC/

1
2
3
4
EPC/
EPC

EPC/
1
PFIPrivate Finance Initiate/
PPPPublic/Private Partnership BOTBuilt
Operate Transfer2
3

1EPC

EPC

EPC
4

FIDIC

1 500000 6
2
3
4

FIDIC

FIDIC FIDIC

--
FIDIC
1999 4 26

""
-14 1999
1 6
"" 20
""""
""""
""
FIDIC common law
statute law

FIDIC

FIDIC

FIDIC

FIDIC
FIDIC

FIDIC
1


8.2
13.1

53.1~53.5


3 FIDIC ICE

FIDIC

FIDIC
FIDIC
1991 12 21
1992 1

FIDIC

FIDIC

1.
1Conditions of Contract for Works of
Civil Engineering Construction, Part I General Conditions
2Conditions of Contract for Works of
Civil Engineering Construction, Part II Conditions of
Particular Application with Guidelines for Preparation of
Part II Clauses
3Tender, Appendix to
Tender and Tender security
4Agreement
5Specifications
6Drawings
7Priced Bills of
Quantities
8Letter of Acceptance
9

2.

2Contract Price
3

FIDIC
FIDIC

Our Ref: 94083/SPC/01 BY FAX & POST

26th February 1998


New Construction Co., Ltd.
Flat 2,3/F, Honor Hall
437-441 Hudson Road
Kowloon, Hong Kong, China
Attn: Mr. Zhang Desheng
Dear Sirs:
Letter of Acceptance Main Contract for Proposed
Multi-Service Centre on SLNK 6517 L/M King Luo Street/Hong
Bao Road, Kowloon
We refer to your submission of tender for the captioned
works on 21st July 1997 and the following post-tender
correspondences:
1. Letter dated 23rd August 1997 from Levett to New
Construction Co., Ltd.
2. Letter dated 25th August 1997 from New Construction Co.,
Ltd. to Levett.
3. Letter dated 5th September 1997 from New Construction
Co., Ltd. to Design 2.
4. Fax transmittal dated 15th November 1997 from Design 2
to New Construction Co., Ltd.
5. Letter dated 16th November 1997 from New Construction
Co., Ltd. to Design 2.
6. Letter dated 22nd January 1998 from New Construction
Co., Ltd. to Design 2.
On behalf of the Mental Health Association of Hong
Kong, we are pleased to advise that your tender in the
amount of HK$32,677,269.00(including a contingency sum of
HK$1,000,000.00) has been ccepted. The contract period is
320 calendar days from the Date for possession that will
not be later than 31st March 1998.
Unless and until a formal agreement is prepared and
executed, your submitted tender together with this letter
shall constitute a binding contract between you and the
Employer.
Contract documents are being prepared and you will be
notified when they are ready for execution. All post-tender

correspondence above-mentioned shall form part of the


contract documents.
Please acknowledge your receipt of this letter of
Acceptance by countersigning and returning the duplicate
copy of this letter.
Yours faithfully,
John C.D. Yeung
Authorized person
JK/as
Cc: MHA Miss Marry Kong
L Mr. Smith David

Dear Sir or Madam:


Re: Employers intention to enter into a contract with us
for Good Luck Plaza
Thank you for your letter of 7 May 1999 informing us
of the Employers intention to enter into a contract with
us for this project on the basis of our tender of 5 January
1999.
You request us to start the access to the site in
anticipation of the contract. However, before undertaking
this preparatory work we would like to have an express
undertaking from the Employer to reimburse the cost of any

work so undertaken, together with a reasonable allowance


for overhead and profit, should the contract not proceed
for any reason.
On receipt of this undertaking, we shall proceed
immediately in accordance with your request.
Yours sincerely,
3.

FIDIC

FIDIC

FIDIC FIDIC .

. FIDIC 5.5
.FIDIC

.
FIDIC
.

. FIDIC
FIDIC
?.
2

FIDIC

FIDIC .FIDIC
.
(FIEG)(FIIC) FIDIC
.FIDIC

.
FIDIC
.
FIDIC .FIDIC
()
()(
). FIDIC
.FIDIC
.FIDIC

.
FIDIC
()

.
FIDIC .
FIDIC
AIA . FIDIC
FIDIC .
3

FIDIC

FIDIC
..
FIDIC
(1)
(2)
(3).
FIDIC
FIDIC .

.FIDIC
.
FIDIC
.
.
FIDIC .

.
FIDIC
.

.
50
FIDIC . FIDIC

.
.
FIDIC
.

.
.()

.
.
.
FIDIC
.

FIDIC

1 Invitation for Bids


2 Instructions to Bidders
3 General Conditions of Contract Part I (Conditions
of Contract for Works of Civil Engineering Construction,
Part I General Conditions)
4 Special Conditions of Contract (Conditions of
Contract for Works of Civil Engineering Construction, Part
II Conditions of Particular Application with Guidelines
for Preparation of Part II Clauses)
5 Technical Specifications
6 Forms of Tender, Appendix to Tender and Tender
Security
7 Bills of Quantities
8 Form of Agreement
9 Forms of Securities, Performance Bank Guarantee
10 Drawings

1.Instructions to Bidders

FIDIC
1
2
3
4
5
6
7

8
9
10
11
12
1993 5

A.
1.
2.
3.
4.
5.
6.
7.
8.
B.
1.
2.
3.
C.
1.

2.
3.
4.
5.
6.
7.
8.
9.
D.
1.
2.
3.
4.
E.
1.
2.
3.
4.
5.
6.
7.
8.

F.
1.
2.
3.
4.
5.
2.Conditions of Contract
FIDIC

Establish a
common basis
Operational clauses, protective clauses,
variations and remedies

Follow
the structure of the general conditions; modify the general
conditions by clarifying existing clauses, deleting the
inapplicable clauses and adding requirements. Prevail over
the general conditions.
25 72 192
FIDIC
1 5 ,
1 5 , 2 6 ,
2 4 , 3.1
4.14.2 , 3 4.1~4.5 ,
5~7 , 5~9 , 8~33 ,
10~37 , 3435 , 38~41
, 36~39 , 42~46
, 40 , 5455 ,
41~48 , 47~53 ,
4950 , 56~58 ,
5152 , 59~64 ,

53 , 54 ,
71~77 , 55~57 ,
58 ,
65~70 , 59 , 60 10
~ 62 , 78~80 , 63
64 , 81~83 , 65
8 , 84~85 , 66 ,
67 , 86 , 68
, 87 , 69 5 ,
88 , 70 , 89
, 7172 , 90
FIDIC

"

FIDIC
12.1 "

"
12.1


"

"
"

FIDIC
3. Specifications

4. Drawings

5. Bills of Quantities

FIDIC

6. Tender, Bid

FIDIC