WEEKLY REPORT ACTIVITY

TA / PLANT 1, 4 AND 5 HSC-PRODUKSI

Execution 15 february to 15 mart 2024


EQUIPMENT Work Description Main Qty REMARK
Power week 1 week 2 week 3 week 4
Start Finish
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 G -1 - 02A DESALTED WATER 4'' SET

2 G -1 - 02B DESALTED WATER 4'' SET

3 G -1 - 03A DESALTED CRUDE 14" SET

4 G -1 - 03B DESALTED CRUDE 14" SET

5 G -1 - 03C DESALTED CRUDE 14" SET

6 G -1 - 04A CIRCULATING NAPTHA 10" 1 SET 15/02/24 on progres

7 G -1 - 04B CIRCULATING NAPTHA 10" 1 SET 15/02/24 on progres


8 G -1 - 04C CIRCULATING NAPTHA 10" 1 SET 16/02/24 on progres
9 G -1 - 04D CIRCULATING NAPTHA 10" 1 SET 16/02/24 on progres
10 G -1 - 05A CIRCULATING KEROSIN 16" 1 SET 17/02/24 on progres
11 G -1 - 05B CIRCULATING KEROSIN 16" 1 SET 18/02/24 on progres
12 G -1 - 05C CIRCULATING KEROSIN 16" 1 SET 18/02/24 on progres
13 G -1 - 05D CIRCULATING KEROSIN 14" SET
14 G -1 - 06A CIRCULATING LGO PUMP 16" SET
15 G -1 - 06B CIRCULATING LGO PUMP 16" SET
16 G -1 - 06C CIRCULATING LGO PUMP 16" SET
17 G -1 - 07A CIRCULATING HGO PUMP 14" SET
18 G -1 - 07B CIRCULATING HGO PUMP 14" SET
19 G -1 - 08A CRUDE COLUMN NET O/H 10" SET
20 G -1 - 08B CRUDE COLUMN NET O/H 10" SET
21 G -1 - 08C CRUDE COLUMN NET O/H 10" SET
22 G -1 - 09A KEROSIN PRODUCT 10" SET
23 G -1 - 09B KEROSIN PRODUCT 10" SET
24 G -1 - 10A L G O PRODUCT 10" SET
25 G -1 - 10B L G O PRODUCT 10" SET
26 G -1 - 11A H G O PRODUCT 10" SET
27 G -1 - 11B H G O PRODUCT 10" SET
28 G -1 - 12A REDUCED CRUDE 14" SET
29 G -1 - 12B REDUCED CRUDE 14" SET
30 G -1 - 12C REDUCED CRUDE 14" SET
31 G -1 - 13A CRUDE COLUMN WATER 4" SET
32 G -1 - 13B CRUDE COLUMN WATER 4" SET
33 G -1 - 14A STABILIZER CHARGE 10" SET
34 G -1 - 14B STABILIZER CHARGE 10" SET
35 G -1 - 14C STABILIZER CHARGE 10" SET
36 G -1 - 15A STABILIZER REFLUX 10" SET
37 G -1 - 15B STABILIZER REFLUX PUMP 10" SET
38 G -1 - 16A LIGHT NAPTHA PRODUCT 6" SET
39 G -1 - 16B LIGHT NAPTHA PRODUCT 6" SET
40 G -1 - 17A HEAVY NAPTHA PRODUCT 10" SET
41 G -1 - 17B HEAVY NAPTHA PRODUCT 10" SET
42 G -1 - 18A H G O REFLUX 16" SET
43 G -1 - 18B H G O REFLUX 16" SET
44 G -1 - 19A L G O REFLUX 16" SET
45 G -1 - 19B L G O REFLUX 16" SET
46 G -1 - 20A KEROSINE REFLUK 14" SET
47 G -1 - 20B KEROSINE REFLUK 14" SET
48 G -1 - 21A CRUDE COLUMN REFLUX SET
49 G -1 - 21B CRUDE COLUMN REFLUX SET
50 G -1 - 22A STABILIZER O/H 4" SET
51 G -1 - 22B STABILIZER O/H 4" SET
52 G -1 - 24 CRUDE COLOM UNICOR SET
53 G -1 - 25 STABILIZER UNICOR SET
54 G -1 - 26A RELIEF BLOW DOWN 10" SET
55 G -1 - 26B RELIEF BLOW DOWN 10" SET
56 G -1 - 27A O/H RELIEF BLOW DOWN 4" SET
57 G -1 - 27B O/H RELIEF BLOW DOWN 4" SET
58 G -1 - 31B CONDENSATE GT-1-03A 2'' SET
59 G -1 - 32B CONDENSATE GT-1-03B 2" SET
60 G - 6 - 01A DEETHANIZER FERLUX 6" SET
61 G - 6 - 01B DEETHANIZER FERLUX 6" SET
62 G - 7 - 01A SOUR WATER CHARGER 6" SET
63 G - 7 - 01B SOUR WATER CHARGER 6" SET
64 G - 7 - 02A STRIPER P AROUND 10" SET
65 G - 7 - 02B STRIPER P AROUND 10" SET
66 G - 7 -03A STRIPER BOTTOM 6" SET
67 G - 7 -03B STRIPER BOTTOM 6" SET
68 G - 7 - 04 SLOP OIL 3" SET
69 G -1 - 06 RELIEF KO DRUM 6" SET

Page 1
WEEKLY REPORT ACTIVITY
TA / PLANT 1, 4 AND 5 HSC-PRODUKSI

Execution 15 february to 15 mart 2024


EQUIPMENT Work Description Main Qty REMARK
Power week 1 week 2 week 3 week 4
Start Finish
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 SOROK BLIND FLANK AND GASKATE VALVE 4" 1 SET 15/02/24 on progres
2 SOROK BLIND FLANK AND GASKATE VALVE 2" 1 SET 15/02/24 on progres
3 INSTALL SOROK AND GASKATE VALVE 6" 1 SET 15/02/24 on progres
4 INSTALL SOROK AND GASKATE VALVE 12" 1 SET 15/02/24 on progres
5 N33 /B2 160 SOROK BLIND FLANK AND GASKATE VALVE 10" 1 SET 15/02/24 on progres
6 N31 / STEB NET O/H SOROK BLIND FLANK AND GASKATE VALVE 3" 1 SET 15/02/24 on progres
7 N34 / BL HN TO STORAGE SOROK BLIND FLANK AND GASKATE VALVE 8" 1 SET 16/02/24 on progres
8 N33 / PLATFORMAT TO STORAGE SOROK BLIND FLANK AND GASKATE VALVE 4" 1 SET 16/02/24 on progres
9 BLH (LPG) SOROK BLIND FLANK AND GASKATE VALVE 4" 1 SET 16/02/24 on progres
10 BFW SUPPLAY SOROK BLIND FLANK AND GASKATE VALVE 4" 1 SET 16/02/24 on progres
11 N13 / NAPTHA FROM CDU IV SOROK BLIND FLANK AND GASKATE VALVE 6" 1 SET 16/02/24 on progres
12 N18 / NAPTHA FROM STORAGE SOROK BLIND FLANK AND GASKATE VALVE 6" 1 SET 17/02/24 on progres
13 N19 / NAPTHA FROM STORAGE SOROK BLIND FLANK AND GASKATE VALVE 6" 1 SET 17/02/24 on progres

14 N14 / NAPTHA FROM STORAGE SOROK BLIND FLANK AND GASKATE VALVE 6" 1 SET 17/02/24 on progres

15 N20 / NAPTHA FROM HCC N20 SOROK BLIND FLANK AND GASKATE VALVE 6" 1 SET 17/02/24 on progres
16 N27 / BL (BRINE WATER) SOROK BLIND FLANK AND GASKATE VALVE 3" 1 SET 18/02/24 on progres
17 N15 / BL SOROK BLIND FLANK AND GASKATE VALVE 3" 1 SET 18/02/24 on progres
18 N30 / BL SOROK BLIND FLANK AND GASKATE VALVE 10" 1 SET 18/02/24 on progres
19 N14 / BL /RAM OIL SUPPLAY SOROK BLIND FLANK AND GASKATE VALVE 2" 1 SET 18/02/24 on progres
20 N28 / BL SOROK BLIND FLANK AND GASKATE VALVE 12" 1 SET 18/02/24 on progres

Page 2
WEEKLY REPORT ACTIVITY
TA / PLANT 1, 4 AND 5 HSC-PRODUKSI

Execution 15 february to 15 mart 2024


EQUIPMENT Work Description Main Qty REMARK
Power week 1 week 2 week 3 week 4
Start Finish
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Note :
This schedule only a estimation, change can happened any times if this impossibility to provide inspection
All of tools and test equipment must be prepared on time.