Professional Documents
Culture Documents
ADMINISTRATIOn
Project management
CHAPTER 1
THE CONCEPT OF PROJECT
CHAPTER 1
THE CONCEPT OF PROJECT
CHAPTER 1
THE CONCEPT OF PROJECT
CHAPTER 1
THE CONCEPT OF PROJECT
CHAPTER 1
THE CONCEPT OF PROJECT
There are three concepts that are part of any project no matter what
type of project is being worked on. These three concepts include:-
a) Project processes,
b) Project life cycles,
c) Project management systems.
CHAPTER 1
THE CONCEPT OF PROJECT
What are the key concepts in project management?
Process groups include
1) initiating,
2) planning,
3) executing,
4) monitoring and
5) controlling, and
6) closing.
Knowledge areas include integration, scope, time cost, quality, human
resources, communication, risk, procurement, and stakeholder management.
CHAPTER 1
THE Characteristics OF a PROJECT
A project has the following characteristics:
Objective
Each and every project needs to be guided to achieve an objective or a set of
objectives. It ceases to exist when the objective is achieved.
Life Span
A project has beginning and end. It cannot continue forever. Its life span can be
short or long depending on its nature and scope. It has a life cycle consisting of
formulation, planning, implementation and termination phases.
CHAPTER 1
THE Characteristics OF a PROJECT
Constraints
A project has a schedule. It operates within the constraints of time, cost and quality.
Every project requires certain investment of resources.
Unique
Every project is unique. No two projects are exactly similar. It consists of customized
non-repetitive activities
Teamwork
A project has many participants. It requires teamwork under the leadership of the
Project Manager. Team members are temporarily assigned from other functional
departments.
CHAPTER 1
THE Characteristics OF a PROJECT
CHAPTER 1
THE Characteristics OF a PROJECT
CHAPTER 1
phases in the life cycle OF a PROJECT
CHAPTER 1
phases in the life cycle OF a PROJECT
1) Initiating process group:-
Those processes performed to define a new project or a new phase of an
existing project by obtaining to start a project or phase
2) Planning process group:-
Those processes required to establish the scope of the project, refine the
objectives ,and define the course of action required to attain the
objectives that the was undertaken to achieve
3) Executing process group :-
Those processes performed to complete the work defined in the project
management plan to satisfy the project specifications.
CHAPTER 1
phases in the life cycle OF a PROJECT
4) Monitoring and controlling process group:-
Those processes required to track ,review and regulate the progress and
performance of the project; identify any areas in which changes to the
plan are required; and initiate the corresponding changes
Both Critical Path method CPM and Program Evaluation and Review Technique (PERT) provide tools to:
• 3. Calculate boundary times that define a time window for each task
• Boundaries include:
• earliest time for task to begin
• latest time for task to begin
• earliest completion time for task
• latest completion time for task
CHAPTER 3
time scheduling a project : PRELIMINARY WORK BREAKDOWN
STRUCTURE ( WBS) , LINEAR RESPONSILIBILITY CHART AND SCHedUlE
OF ACTIVITIES
Basics of Project Scheduling
• 1. Create deliverables-based project schedules
• 2. Determine the appropriate level of detail
• 3. Implement a regular status update and reporting process
• 4. Regularly review and update the schedule
CHAPTER 3
time scheduling a project : PRELIMINARY WORK BREAKDOWN
STRUCTURE ( WBS) , LINEAR RESPONSILIBILITY CHART AND SCHedUlE
OF ACTIVITIES
Work Breakdown Structure -WBS
A work breakdown structure (WBS) is essentially the scope statement reduced to
individual pieces of work.
Tasks - called work breakdown structure (WBS)
To project schedule, begin with set of tasks (WBS)
1. Effort, duration and start date are determined for each task
2. Assign tasks to project team member(s)
3. Develop a Gantt (timeline) chart
CHAPTER 3
time scheduling a project : PRELIMINARY WORK BREAKDOWN
STRUCTURE ( WBS) , LINEAR RESPONSILIBILITY CHART AND SCHedUlE
OF ACTIVITIES
The completed WBS will expose all the component parts of the project down
The WBS itself is not a schedule or cost estimate, but it provides the
scheduling
CHAPTER 4
gantt charts and lob
CHAPTER 4
gantt charts and lob
Creating a Gantt Chart:
There are two methods to creating a Gantt Chart (Maylor, 2005).
1. Using a Forward Schedule: starting with the list of activities and a
given start date (6th Sept in previous example) follow them forwards in
time until you hit given deadline.
2. Using a Backward Schedule: look at the deadline, from that date
work in the logical list of activities.
Both of these methods allow you to ensure that all necessary activities
can possibly be completed within the given project time frame.
CHAPTER 4
gantt charts and lob
Steps to Creating a Gantt Chart:
• 1. Determine Project start date and deadline.
• 2. Gather all information surrounding the list of activities within a project – the
Work Breakdown Structure may be useful for this.
• 3. Determine how long each activity will take
• 4. Evaluate what activities are dependent on others
• 5. Create Graph shell including the timeline and list of activities.
• 6. Using either Forward Scheduling or Backward Scheduling,Begin to add bars
ensuring to include dependencies and the full duration for each activity.
CHAPTER 4
gantt charts and lob
CHAPTER 4
gantt charts and lob
CHAPTER 4
gantt charts and lob
CHAPTER 4
gantt charts and lob
The Advantages:
• A useful tool for displaying time-based information within a project.
• Very simple to create
• They provide a useful overview of project activities, a good starting
point for project planning.
• The charts are widely used and understood.
• There exists several PC software packages that allow you to build
Gantt Charts.
CHAPTER 4
gantt charts and lob
Line of Balance (LOB)
Definition
• A simple diagram to show location and time at which a certain crew will be
working on a given operation.
• Focuses on balancing the time taken for individual activities by either re-
distribution of resource or by reducing process waste.
• LOB is a Planning methodology to optimize resources used
• LOB is a Good Visual tool that lets us see if a construction program can be
achieved with the minimum waiting time between tasks
• It is primarily used on projects that have repeated elements like Highways,
Pipelines, High-rise buildings, hotel bedrooms, bridge etc.
CHAPTER 4
gantt charts and lob
SCHEDULING WITH LOB
Prepare a logic diagram.
To complete each operation, calculate the estimate of man hours required.
Select a buffer time which will lookout against the risk of interference between
operations.
Calculate the equation outputs targets so as to meet a given project completion
date.
Complete the LOB schedule.
In order to bring more balance schedule, inspect the schedule and access possible
attentive.
CHAPTER 4
gantt charts and lob
Advantages
It allows a clear understanding of the amount of work taking place at a certain time in a specific
place.
It is relatively easier to modify , update and change the schedule.
if It allows the better management of sub contractor and resources.
It allows problems areas to be identified in advance
Disadvantages
LOB does not shows critical activities.
A monitoring device; not as easy to use as a planning device
Limited to production and assembly type processes.
It could be divided only by location.
It shows only where the problem is, it does not shows what actual problem is.
CHAPTER 4
gantt charts and lob
Faster planning process
Less tasks
Less links
Faster program creation
Less time to understand & interpret
Easy to try ‘what-if’ scenarios
Cont.
• Provides the basis for scheduling labor and equipment
• Provides an estimate of the project’s duration
• Provides a basis for budgeting cash flow
• Highlights activities that are “critical” and should not be delayed
• Help managers get and stay on plan
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
FROM WORK PACKAGE…
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
…NETWORK
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
CPM is a network diagramming technique used to predict total project duration.
CPM is an analysis technique with three main purposes:
• To calculate the project’s finish date
• To identify to what extent each activity in the schedule can slip(float) without delaying the project
• To identify the activities with highest risk that cannot slip without changing the project finish date
CPM
How does the Critical Path Method calculate the project’s finish date?
Forward pass calculation
• calculates Early Start and Early Finish dates
Backward pass calculation
• calculates Late Start and Late Finish dates
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
• Early Start (ES) is the earliest date a task can start
• Early Finish (EF) is the earliest date a task can be completed
• Late Start (LS) is the latest date a task can start without delaying the project and date
• Late Finish (LF) is the latest date a task can finish without delaying the project end date
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
CHAPTER 5
network techniques : concept of project network , construction
of project network, critical path method and free float
PERT deals with unpredictable activities, but CPM deals with predictable
activities. PERT is used where the nature of the job is non-repetitive. In contrast
to, CPM involves the job of repetitive nature. PERT is best for research and
development projects, but CPM is for non-research projects like construction
projects.
The advantages of PERT: It provides a graphical display of project activities that
helps the users understand the relationships among the activities. It is the ideal
technique for tactical level planning and operational level control of projects.
Chapter 6
PERT and its advantage over cpm . Probability of completing a
project in time
Chapter 6
PERT and its advantage over cpm . Probability of completing a
project in time
Crashing is the technique to use when fast tracking has not saved enough time on
the schedule. It is a technique in which resources are added to the project for the
least cost possible. Cost and schedule tradeoffs are analyzed to determine how to
obtain the greatest amount of compression for the least incremental cost.
Graph that plots project costs against time; includes direct, indirect,
and total costs for a project over relevant time range.
What are the 5 common reasons for crashing a project?
• Time to market pressures.
• Unforeseen delays.
• Incentives for early completion.
• Imposed deadlines.
• Pressures to move resources elsewhere.
Chapter 7
crashing a network and concept of pert cost
DIVISIONAL ORGANIZATION
• This structure is for HIGHLY DIVERSIFIED & DESPERSED firms in terms of geographical areas/
product/ market.
• A divisional organizational structure usually consists of several parallel teams focusing on a single
product or service line.
• In a divisional structure, an organization is divided into various divisions where people with diverse
skills are kept together in the form of groups by a similar product, service or geographic location,
and each division itself is capable of doing the task on its own. Each division has its own resources
required to function properly.
• The division can be based on product, service or the geographical area: e.g. :- ITC
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
MATRIX ORGANIZATION
• When it comes to matrix structure, the organization places the employees based on the function and the
product.
• The matrix structure gives the best of the both worlds of functional and divisional structures.
• The company uses teams to complete tasks
• The teams are formed based on the functions they belong to and product they are involved in
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
PROJECTIZED ORGANIZATION
• In projectized organizations, arrange their activities into programs or portfolios, and implement
them through the projects.
• Here, the project manager is in charge of his project, and he has full authority over it. Everyone in
his team reports to him. The projectized organization structure is opposite to the functional
organization structure. Here, either there will be no functional manager, or if he exists, he will have a
very limited role and authority.
• The project manager controls the budget, resource, and work assignment.
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Project planning
• Fulfills four distinct purpose, it determines:
• 1. The cost and duration of the project.
• 2. The level of resources needed.
• 3. Helps to allocate work and monitor progress.
• 4. Helps to assess the impact of changes to the project.
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Project control
• 1. Project monitoring: current expenditure to date, amount of
overtime authorized, inspection failure, progress of activities etc.
• 2. Assessing project performance: Compare planned and actual
expenditure
• 3. Intervene to change the project: when the project is out of control
in the sense of cost, quality levels or time, intervention is required.
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Introduction
• A successful execution of project requires satisfactory human relations system.
• Technical problems may be solved with additional input of resources, but peoples
problem is not readily resolved in short term.
• To achieve satisfactory human relations in project setting, project manager has to
handle successfully problems relating to:
1. Authority
2. Orientation
3. Motivation
4. Group Functioning
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Management Of Authority
A project manager usually receives very little formal authority between functional lines of command.
He has to co-ordinate the efforts of various functional groups consisting of professionals and
supervisory personnel.
In order to gain authority he should be able to:
1. Develop a rapport with the project personnel.
2. Resolve conflicts among various people working on the project.
3. Have good professional reputation and stature, good communication and persuasion skills.
4. Ability to act as buffer between technical, engineering, financial and commercial people.
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Management Of Orientation
The efficient achievement of project targets with in given time and budget requires
the project manager to strengthen his managerial orientation.
Usually a project manager is an engineer having technical knowledge and outlook
to problem handling, but for this he needs to become engineer-manager.
He needs to:
1. Perform tasks of planning, organizing, directing and controlling resources of the
firm.
2. Adopt a creative approach to unstructured problem solving.
3. Attach greater importance to efficient utilization of resources and resolution of
human relation problems.
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Management Of Motivation
The project manager while working within given sociotechnical system can influence the motivation
level of the project personnel.
For this he should remember that
1. Every human being has different needs with differing importance attached to them.
2. Behavioral research reveals that pressure to work is only functional to an extent.
3. Motivation level is strong with challenging, achievable goal setting.
4. Expectation of reward rather than fear of punishment has a greater bearing.
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Management Of Motivation
To motivate project personnel, project manager must:
1.Be a perceptive observer of human beings.
2.Have the ability to appreciate the variable needs of human beings.
3.Be sensitive to the reactions of people and act supportively rather than threatening
them.
4.Have the skill of several styles of management suitable to different situations.
Chapter 8
forms of project organization, project planning &control and
human aspects of project management
Factors affecting cost overruns were financial difficulty by client, delays in payments of completed
works, variations in designs, lack of communications plans, poor feasibility and project analysis,
poor financial management on site and material price fluctuations.
Check out the reasons for cost and time overruns in projects.
• Quoting in a hurry without having complete knowledge of the project details. Poor planning. ...
• Wrong assumptions on part of both the client and the vendor. ...
• Documentation
• Legal
• Cost
• Personnel
Chapter 11
project evaluation and control, project closeout and
termination
Why are Closeouts Difficult?
✓Project sign off can be a de-motivator
RISK MANAGEMENT
Risk Management is a logical and systematic method of identifying,
analyzing, treating and monitoring the risks involved in any activity or
process.
It includes maximizing the results of positive risks and minimizing the
consequences of negative events.
Chapter 12
project risk management , elements of project risk
management
To manage risk we use the six risk management processes
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
Chapter 12
project risk management , elements of project risk
management
WHY DO WE MANAGE RISK
Project problems can be reduced as much as 90% by using risk
analysis
Positives:
More info available during planning
Improved probability of success/optimum project
Negatives:
Project cut due to risk level
Chapter 12
project risk management , elements of project risk
management
RISK ANALYSIS
Risk analysis is a systematic process to estimate the level of risk for identified and approved risks.
This involves estimating the probability of occurrence and consequence of occurrence and converting
the results to a corresponding risk.
The approach used depends upon the data available and requirements levied on the project level.
The most common form of qualitative approach is the use of probability of occurrence and
consequence of occurrence scales together with a risk mapping matrix to convert the values to risk
levels.
Quantitative approaches include expected value, decision tree analysis, payoff matrices, and
modeling and simulation.
Chapter 12
project risk management , elements of project risk
management
Chapter 13
project PROCUREMENT MANAGEMENT
ELEMENTS OF PROJECT PROCUREMENT MANAGEMENT.
Project Procurement Management
The processes to purchase or acquire the products, services, or results needed from
outside the project team to perform the work
Why Procurement Management?
All projects will need to acquire some resources from outside. Not understanding the
different ways to contract could result in unnecessary risk for the project
Chapter 13
project PROCUREMENT MANAGEMENT
ELEMENTS OF PROJECT PROCUREMENT MANAGEMENT.
How Do We Manage Procurement?
Four processes
• – Plan Procurements
• – Conduct Procurements
• – Administer Procurements
• – Close Procurements
Chapter 13
project PROCUREMENT MANAGEMENT
ELEMENTS OF PROJECT PROCUREMENT MANAGEMENT.
Chapter 13
project PROCUREMENT MANAGEMENT
ELEMENTS OF PROJECT PROCUREMENT MANAGEMENT.
Chapter 13
project PROCUREMENT MANAGEMENT
ELEMENTS OF PROJECT PROCUREMENT MANAGEMENT.
Chapter 13
project PROCUREMENT MANAGEMENT
ELEMENTS OF PROJECT PROCUREMENT MANAGEMENT.
Chapter 14
ELEMENTS OF PROJECT QUALITY MANAGEMENT AND APPLY THEM TO THE
FINAL REPORT
Project Closure
This is the last of the project management stages, when
the final deliverables are handed over or go live. This stage provides
you, your team and stakeholders with an opportunity to evaluate how
successful the project was and what lessons were learned during
the process.