Professional Documents
Culture Documents
Project Planning Methods
Project Planning Methods
Project Planning Methods
net/publication/338541301
CITATION READS
1 38,885
1 author:
SEE PROFILE
All content following this page was uploaded by Savo Kawa Abdulkareem on 12 January 2020.
Abstract
The objective of this research paper is to highlight and analyze the different types of
planning methods for construction projects in order to determine which one is the best method to
use before starting projects, such as multi-story buildings, houses, roads, highways, airports, and
so on. There are many strategies for scheduling construction projects; they include critical path
method, Gantt chart, Work Breakdown Structure, time-scaled arrow diagram, line of balance
chart, S-curve, activity on node diagram, resource allocation chart, and so on.
Each of these methods is used for work schedules; they could be different in the way of
giving less or more information, and selecting them would be based on the goal of our project and
project requirements. After all, the Gantt Chart method seemed to be the best option for project
scheduling of construction projects. In the Gantt Chart method, the cost estimates and the
progress of the work can be calculated, and also most significantly, the planned and actual work
can be realized on the chart clearly. Above all, the Gantt charts are usually easier to be read by
everyone since every single information or number has a caption explaining it.
1
Introduction
structure will tell you exactly when, where, how, and what activities should proceed first. Project
planning is arranged by project managers in order to find out the purpose, the cost, time duration,
and the procedure of the total project. Although project planning is taking some time to create, it
does worth it since it is going to save a lot of time later after starting the project. Due to the
absence of planning, sometimes, lots of issues will happen, such as delaying the material delivery,
machines, equipment, and project activities and as a result, wasting lots of time with losing a lot of
Obviously, there are notable benefits to create a simple schedule. Companies that are
able to successfully finish projects on time according to the planned schedule, therefore, will get
an advantage over the companies which fail in this regard. For better management, there are
some strategies. First, required tasks or activities have to be revised; Next, the available strategies
should be determined and analyzed to realize which one works best for a particular project; the
deciding on the project goals will ease the method selection, and lastly, the project network could
be develop (Gray, 102). In this stage, the engineer should have all the information about the
project, including size, topography, time required to finish, cost, resource availability, and so on.
2
Methods of Project Planning
Project managers use different methods of project scheduling in order to estimate the
time required for projects before starting. The period of working on a project can be divided into
three parts, which are before, during, and after completion of construction. The first part, before
planning, includes planning and estimation of the project duration, cost, materials, number of
workers, and sequence of activities. Project scheduling is important because once everything is
planned, everyone, including engineers, workers, contractors, and the owner of the project will
get an idea about when they have to start and finish constructing, how much the project costs,
what materials, machines, equipment are needed, how many workers and engineers are required,
what type of skills from the workers and engineers are sought, and so on (Planning). So during the
construction period, most of the issues and operations would be clear and understandable prior
to happening.
equipment, or any machine, which might be unavailable in the country, we can order them earlier,
so it will be ready to use when needed for a particular activity of the project . Otherwise, it may
delay the project for months or more. In the case of the unavailability of any type of machine or
materials during the construction process, everyone has to wait and delay their job, including
workers and engineers. So before starting any project, the project manager, engineers, and
Project planning and scheduling are used for the purpose of deciding project activities,
duration, money, required materials, and relations between each activity in order to finish a
particular work. There are many methods for scheduling. However, based on the project goal, one
3
of them has to be chosen and used to create a good plan before working on the project. There are
Critical Path method: was developed “in the late 1950s”, and since then, it is used widely for
scheduling projects, especially in construction, aerospace and defense, software development, IT,
etc; In this method, activities are connected by using dependencies in a network diagram and
forming paths, making forward and backward calculations (Kathy). The critical path of a project
can also be determined using a software, for instance, “Primavera P6 or Microsoft Project helps to
analyze the critical path of a project which consists of thousands of activities (Kathy).
In this method, activities should be listed according to which activity proceed and which
activity follows. Using this method will let us know after how many months, weeks, or days the
project will be completed and also clarifies the construction process for workers, contractors,
engineers, and supervisors to know the procedure and deadlines for each activity in the project.
In other words, this method tells the earliest starts (ES), earliest finishes(EF), latest starts (LS),
and latest finishes (LF) of each activity in the project. I believe this method is much more efficient
than other methods for scheduling because this method gives information about the duration,
earliest start, and the deadline, in which each activity should be completed.
Figure 1: ES, EF, LS, and LF in the Critical Path Method [4].
4
As shown in figure 1, each arrow is drowned with a letter on the top and a number
below the line. The letter represents the activity, and the number represents the time duration
that each activity takes. In the critical path method, the completion of each activity is followed by
an event number in a circle. Each circle has numbers written in both top and bottom. The number
below the circle represents the earliest start of the followed activity, the number over the circle
Gantt Chart is one of the easiest methods of the project schedule to prepare. Its activities are
represented as bars and the length of each bar represents the activity duration. The beginning and
the end of the bar show the start and end date of each activity. Depending on the project execution
plan and resource availability, these bars may be sequential or run in parallel (Kathy).
Preparing the Gantt Chart doesn't need a particular software; A simple Excel
Template can be used to make one and update it anytime. By using an excel template, Gantt
Chart can be made for scheduling and planning any types of construction projects. First, the
5
activities are listed in the first column and their durations in the second column. Then the
dates of starting and ending the project are filled up at the top in the first row. After that, a
horizontal bar is drowned for each activity according to its time required
The Gantt Chart is basically a diagram representation of the critical path method. The
advantage of a Gantt chart is that any information can be added by putting then in an extra
column. For example, the information, including the duration, cost, ES, EF, LS, and LF could be
represented in the chart, too. Same as the critical path method, we can easily figure out the ES, EF,
One thing that makes Gantt chart a better method than the critical path method is that
the bar graph can show the planned and actual scheduling dates of each activity as shown in
figure 4, and we can compare them right away to improve future scheduling. In this method, the
progress of work can be calculated each week according to the scheduled work. For instance, at
6
Cumulative Progress = ∑ activity Progress * Weight of each activity
Another advantage of the Gantt chart method is that columns can be added to determine the cost,
the total cost, or the weight of each activity as presented below in figure 4 and 5.
Figure 4: Actual and Planned Work and the Weight of Each Activity are sketched in the Gantt Chart [4].
Figure 5: Actual and Planned work period with the cost are sketched in the Gantt Chart [4].
7
Program Evaluation and Review Techniques (Pert): was developed by the “US Navy in the
late 1950’ s for Ballistic Missile Program” in order to find a simple system to organize complex
objectives and thousands of contractors (Kathy). In this method, the longest path can be identified
PERT method seems more difficult to use because it requires learning a software
program in order to make a schedule. In this method, the duration of each task is calculated by
three estimate techniques, which are most likely estimate, optimistic Estimate, and pessimistic
estimate. Optimistic estimate computes the shortest time period or earliest time required for
finishing a task, pessimistic estimate computes the latest time required for finishing a task, and
most likely estimate computes the most possible amount of time to finish the project (Kathy). In
Work Breakdown Structure: is an outline of the construction project with different levels of
detail. This method categorizes all the tasks of work project into subsections in a hierarchical
structure, and it shows their relationship with each other as shown in figure 6. This method also
serves as a framework for tracking cost, work performance, and progress (Gray, 108).
method is used mostly; In this method, each task will be presented in different shapes of boxes, in
which they are joined together by an arrow (Gray, 166). And, the arrows represent the relation
This method is similar to the critical path method. It presents the name, number, and
duration of each activity. However, it doesn't show the ES, EF, LS, and LF on the network diagram
as shown in figure 7 and 8. The difference between this method and the critical path method is
that in the activity on the Node Diagram method, the letter of each activity is written in the circle,
but in the critical path method, the letter of each activity is written over the arrow.
9
Resource Allocation Chart: used in projects where there is a competition between activities
for project resources. Resources could be considered as materials, specific labor types,
This method shows the starting, ending, and duration of each activity in a table.
However, this method doesn't give enough details similar to other methods. Resource Allocation
Chart method is very similar to the Gantt chart except that in the Gantt chart, both planned and
actual work are shown, but only the planned work is shown in the resource Allocation Chart
Time scaled arrow diagram: is one of the methods of project scheduling and
represents the preceding and proceeding activities by an arrow. In this method, it is much easier
to determine the float times, as shown in figure 10. However, this method only shows the
duration, starting, and finishing date of each activity without determining the ES, EF, LS, and LF.
Figure 10: Time Scaled Arrow Diagram for Scheduling Projects [4].
10
Line of balance chart (Linear Scheduling Method): is another method for project
scheduling. This method is mostly used for several repetitive tasks of a project. When a project
involves 3-5 tasks for a long-distance area, such as constructing roads, drilling, digging wells
and etc, then this method is the best option. For instance, figure 11 below shows a schedule,
using a linear scheduling method for a project with five repetitive activities, such as site
clearing, drainage, subgrade, base course, and paving for 50 stations. So each activity is done
Figure 11: Linear Scheduling Method, Used for Repetitive Work [4].
11
S-curve (cumulative progress chart): is a graphical representation of project progression in
percentage versus time. Same as the Gantt chart method, this method presents both the planned
and actual scheduling of the project. The purpose is to see the difference and progress of the work
and improve future scheduling. Similar to the time-scaled arrow diagram, this method only shows
the duration, starting, and finishing date of each activity without deciding on the earliest and
latest start with the earliest and latest finish. It is also called cumulative progress chart.
Figure 12: S- Curve Showing Work Progress, Actual, and Planned Work [4].
As a result, the best method to use for project scheduling and planning based on what
previously were mentioned could be the Gantt Chart Method. In the Gantt Chart method, the
weight of each activity is determined; the cost is calculated in a separate column; the planned and
12
Consequences of Delaying Construction Projects
Construction Projects are essential requirements and needed to be done to meet the
population demand and necessities. However, delaying construction projects is a common issue
around the world, especially when the projects are given to the central government. In Mumbai "4
out of 10 infrastructure projects are behind the scheduled deadline" (Pillay). One of the
consequences of project delay is the increase in the project cost like sometimes the cost increases
about 20 times the original cost (Pillay). For example, delaying a railway conversion project on
the Bankura-Damodar stretch in West Bengal the original caused the project to cost more than the
original price, which is from ₹ 111.9 crores to ₹ 2,371.85 crores (1 crore is 10 million) (Pillay).
So when a project is delayed, a huge amount of money is going to be spent and wasted,
however, that amount could be invested for other projects or used for buying new equipment.
There are many Data showing that the delay in construction projects causes time overrun and
cost overrun.
13
There are several other examples of project delay, such as from Western Australia, UAE,
Finland, and the USA. In each of these projects, the project delaying is between a year to 6 years.
In each of them, big differences between the original and final costs are recorded. As shown in
figure 13 below, as the projects are delayed, consequently their costs, which is called cost
50 final cost
Cost Overrun (Billions)
40 planned cost
30
20
10
0
18 Month 5 years 6 years 8 years
Delays of Projects
14
Conclusion
avoid project delays and cost overruns. So, the progress and completion of the construction
project during the whole period of working will depend on how effective is the manager's
schedule. The more detailed and clear the plan, the better and more understandable it will be.
There are many methods available for planning projects, including critical path method, Gantt
chart, time-scaled arrow diagram, line of balance chart, S-curve, activity on node diagram,
resource allocation chart, expanded node diagram, work breakdown structure, Program
After analyzing all of the techniques available, we have reached the conclusion that the
Gantt chart method is the best method to use in terms of giving most information required for the
contractors, workers, and everyone else working in the site during the construction work. This
method will allow determining the weight, progress, cost, actual and planned work, duration of
each activity, and also it is very understandable and clear. Planning reduces the amount of delays
15
References
[1] Gray, C. F., E. W. Larson, and McGraw-Hill. "Project Management: The Managerial Process."
Defining the Project Scope. 2005.
[2] Kathy. “Scheduling Techniques and Project Schedule Management.” Projectcubicle, 20 Mar.
2018. <www.projectcubicle.com/scheduling-techniques/>.
[3] Pillay, Amritha. “Delays, Cost Overruns Plague Infrastructure Projects.” livemint.com. 29 Mar.
2015. <www.livemint.com/Politics/tJkxdTZWlvS1kwNgJdbqII/Delays-cost-overruns-
plague-infrastructure-projects.html>.
[5] Ram, R. Sree. “Execution Delays and Low Tariffs Pose Double Trouble for NHPC.”
Https://Www.livemint.com, Livemint, 21 Nov. 2017,
<www.livemint.com/Money/T9za1CBZgaPw8YqzdsnYDI/Execution-delays-and-low-
tariffs-pose-double-trouble-for-NHP.html>.
[7] Usmani, Fahad. “Precedence Diagramming Method (Activity on Node Method) in Scheduling.”
Study Circle, 3 Feb. 2019..<https://pmstudycircle.com/2012/07/precedence-
diagramming-method-activity-on-node-method-scheduling/>.
[8] Viveka, Vinci. “Pert- Program Evaluation and Review Technique.” LinkedIn SlideShare, 11
Mar. 2013, <www.slideshare.net/vinciviveka/pert-17096780>.
[9] Wilks, Stuart. “The Century's Most Troublesome Construction Projects.” - GCR, 5 Oct. 2015,
<www.globalconstructionreview.com/perspectives/centurys-most-troublesome-
construction-pr8oje8ct8s/>.
16