TOTAL AREA
TYPE OF RATE PER
SNO PLACE WORK INCHES SFT SFT VALUE
2 MASTER BEDROOM
Wardrobe (Deco) Box 84 x 84 49.00 200 9,800.00
Box 71 x 27 13.31 200 2,662.50
F/S 71 x 22 10.85 110 1,193.19
Pannel 71 x 21 10.35 90 931.88
Dressing (Deco) Box 79 x 36 19.75 200 3,950.00
F/S 36 x 23 5.75 110 632.50
F/S 16 x 23 2.56 110 281.11
F/S 25 x 73 12.67 110 1,394.10
Box 20 x 30 4.17 120 500.00
Partition (Veneer/Glass) F/S 24 x 83 13.83 150 2,075.00
TV Console Box (Deco) Box 60 x 30 12.50 200 2,500.00
Beeding Above Console
Beeding Behind Bed
MCB design 7,000.00
Ceiling Veneer F/S 148 x 42 43.17 150 6,475.00
Study (Deco/Veneer) Box 82 x 34 19.36 200 3,872.22
F/S 34 x 22 5.19 150 779.17
F/S 22 x 19 2.90 150 435.42
F/S 96 x 19 12.67 150 1,900.00
Draws Big 6.00 700 4,200.00
Draws Small 3.00 500 1,500.00
3 CHILD BEDROOM
Wardrobe (Acrylic) Box 119 x 104 85.94 120 10,313.33
Box 20 x 42 5.83 120 700.00
Window Plank pannel 20 x 42 5.83 90 525.00
Beside bed wooden beam F/S 26 x 94 16.97 150 2,545.83
Bed wall Design Pannel 101 x 24 16.83 110 1,851.67
Bed Side boxes (Duco) Box 44 x 23 7.03 200 1,405.56
WPVC box below window Box 35 x 18 4.38 200 875.00
Box 60 x 18 7.50 200 1,500.00
Draws 10.00 500 5,000.00
Dressing (Acrylic) Box 41 x 82 23.35 120 2,801.67
F/S 41 x 24 6.83 110 751.67
Box 41 x 90 25.63 200 5,125.00
Sub Total 85,476.81
4 GUEST BEDROOM
Wardrobe (Acrylic) Box 106 x 100 73.61 200 14,722.22
Bedside Boxes (Acrylic) Box 106 x 64 47.11 120 5,653.33
F/S 16 x 78 8.67 110 953.33
Pannel 12 x 78 6.50 90 585.00
Centre Ceiling (Veneer) F/S 48 x 48 16.00 150 2,400.00
Draws 6.00 500 3,000.00
NOTE: We Use
Wood: Gurjan 710 for internal structure,B W P Grade, Block board for Doors. Laminate/Veneer: should be selected by customer
from the catalogues provided by us. Hinges: Branded Soft close Stainless steel. Handles: should be selected by customer from the
catalogues provided by Us. Kitchen Accessories: Branded soft close channels
Any other extra work will be charged accordingly as per the above agreed price.
PAYMENT TERMS
First Payment: 50% of the quotation value to be transferred before the start of work. Second payment: 40% of the quotation value
should be paid before the dispatch of the doors from factory. Third Payment: Remaining 10% should be paid after completion of
work.
For
P Satyanarayana Raju
Mobile: 7989212112
Authorised Signature