Professional Documents
Culture Documents
February, 2021
Adama, Ethiopia
Contents LO #1- Supervise the administration of claims and payment
processes………………………………………………………………………4
Information Sheet 1- Preparing Contract payments accordance with the contract
allowance. ........................................................................................................... 5
Self-Check -1 ................................................................................................. 12
Information Sheet 2- Carrying out Drawings against allowances. ...................... 13
Self-Check -2 ................................................................................................. 15
Information Sheet 3. Authorizing Variations to contracts and Taking corrective
action. ............................................................................................................... 16
Self-Check 3................................................................................................... 19
Information Sheet 4- Apply Back-charges.......................................................... 20
Self-Check -4 ................................................................................................. 22
Information Sheet 5. Authorizing Payment of invoices for material supply. ........ 23
Self-Check 5................................................................................................... 24
Information Sheet 6. Completing and processing Insurance claims for site loss or
damage. ............................................................................................................ 25
Self-Check 6................................................................................................... 30
Information Sheet 7. Conducting and supervising Administrative processes with
reference to regulatory and organizational requirements. .................................. 31
Self-Check 7................................................................................................... 39
1.1. Contract
A contract is a mutual or legally binding agreement between two parties based on policies
and conditions recorded in document form. The two parties involved are one or more
property owners and one or more contractors. The owner, often referred to as the
'employer' or the 'client, has full authority to decide what type of contract should be used
for a specific development to be constructed and to set out the legally-binding terms and
conditions in a contractual agreement. A construction contract is an important document
as it outlines the scope of work, risks, duties and legal rights of both the contractor and
the owner.
There are three main types of construction contract, identified according to the
mechanism for calculating the sum due to be paid by the employer: lump sum contracts,
re-measurement contracts and cost-reimbursable contracts. The different types vary
primarily with regard to who takes the risks involved, which party has to pay for the cost
over runs, and which party can keep the savings if the project costs are less than the
estimated costs.
Commercial contract
Domestic building contract
Percentage rate contract
Item rate contract or Unit price contract
Lump sum and scheduled contract
Cost plus fixed fee contract
Cost plus percentage of cost contract
Subcontract agreement
Special contracts
Under a lump sum contract, an owner agrees to pay a contractor a specified lump sum
after the completion of work without a cost breakdown. After work is complete, no detailed
measurement is required.
In lump sum contract the complete work as per plan and specifications is carried out by
contractor for certain fixed amount as per agreement. The owner provides required
information and contractor charges certain amount.
This contract is suitable when the number of items are limited or when it is possible to
work out exact quantities of work to be executed.
The detailed specifications of all items of work, plans and detail drawings, security
deposit, penalty, progress and other condition of contract are included in agreement.
Though it is lump sum and scheduled contract, contractor will be paid at regular interval of
2–3 months as per progress of work on the basis of certificate issued by engineer in
charge. A scheduled of rate is included in agreement for making payment of extra items.
Under a lump sum contract, a “fixed price” for the work to be done is agreed upon by the
client and contractor before the work begins. This contract can also be applied to both
home building and commercial contracts. It can be more of a risk to the contractor as
there are fewer mechanisms to allow them to vary their price.
When the lowest rate and comparative position among the contractors are already
specified prior to the opening of the tender, then the percentage rate contract is used.
Percentage contract is a type of contract where there is no possibility of unbalanced
tender.
In cost plus fixed fee, the owner pays the contractor an agreed amount over and above
the documented cost of work.
This is a negotiated type of contract where actual and direct costs are paid for and
additional fee is given for overhead and profit is normally negotiated among parties. The
owner is in more control of the project; however, the risks are transferred to the owner.
In cost plus percentage, the owner pays greater than 100 percent of the documented
cost, usually requiring detailed expense accounting. In this type of contract, contractor is
paid the actual cost of work plus certain percentage as profit.
Various contract documents, drawing, specifications are not necessary at the time of
signing the agreement. The contractor has to keep all records for cost of material and
labour and contractor will be paid accordingly to engineer in charge. This type of contract
is suitable for emergency work like difficulties in foundation conditions, construction of
expensive structure etc.
Re-measurement contract
Under a re-measurement (or Re-measurement) contract, the price to be paid for the
whole work is to be ascertained by measurement in detail of the various parts of the work
and the valuation of the work done by reference to a schedule of prices included in the
contract.
Subcontract agreement
This contract is based on units put in place rather than a single price. The payment is
calculated at a specific rate for each item such as cubic yard for concrete times quantity
put in place. “The contractor quotes an owner a price for a particular task or scope of
work, though at the time of contracting the parties may not know the actual number of the
units of work to be completed.
Base date
A "base date" is a reference date from which changes in conditions can be assessed. In a
construction contract, the inclusion of a base date is generally used as a mechanism for
the allocation of risk between the owner and contractor for changes which might occur in
the period between the contractor pricing the tender and the signing of the contract. This
period can potentially be very long and changes that occur may have a significant impact
on the costs of the works.
Practical completion
Practical completion occurs when the contractor returns possession of the site to the
owner, usually at the time when the work has been completed and accepted by the client.
A certificate of practical completion usually confirms this acceptance. Typically half of the
retention monies are released, the contractor’s potential liability for liquidated damages
ends and the defects rectification period begins.
Retention
A retention is a sum of money withheld by the owner under the contract to act as security
against incomplete or defective works.
Sectional completion
Snagging
Snagging refers to a process where the owner or the owner's agent checks for any
defects, which the contractor needs to put right before the final payment is made. The UK
consumer organization which? States that the most common issues picked up by
snagging surveys for residential properties tend to be concerned with the completion of
plastering, tiling, skirting boards and external brickwork.
The types of conditions in a contract can vary, but common ones include:
1. Conditions precedent.
2. Conditions concurrent.
3. Conditions subsequent.
1. Condition Precedent
A condition precedent specifies an event that must happen before a person is obligated to
perform the duties specified in the contract. An example of this is if an employer tells an
employee they will receive a bonus of $600 if they complete an accounting course. Until
the employee completes the course, the employer is not liable to pay the employee.
However, once the employee completes the course, the employer has to pay up.
When put in the context of sale and purchase agreements, some condition precedents
might include:
You can also use condition precedents in real estate transactions. An example here
might include matters related to financing a mortgage or the physical condition of the
property being sold.
2. Condition Concurrent
A condition concurrent is required when the two parties in an agreement need to take
actions at the same time. Because of this, neither party is legally obligated to perform
their part of the contract until the other side starts performing their part of the contract.
3. Condition Subsequent
A condition subsequent always stipulates a condition that happens after the formation of a
contract. It relates to a specific incident that can release one party from the actions listed
in the contract. You might know it better as an escape clause, and it terminates the
contract if specific circumstances arise.
Condition subsequent can be used in deeds to real property. In this case, they might
describe an event which would terminate a person's interest in the property, such as a
divorce.
As a building contractor you will need to master contract administration. Not only do you
need a good understanding of contracts and the conditions that control the operation of
the project, you need to have or develop good interpersonal skills when interacting with
clients, architects, subcontractors, suppliers etc.
The contract between the client and building contractor is used as the ‘book of rules’ in
administering the work and working towards completing the contract by performance. By
‘performance’ we mean fulfilling your obligations under the contract conditions and
meeting or exceeding the expectations of the client or architect in respect of time, cost,
quality and customer service.
The preparation of forms can simplify the process. Examples of the more common forms
used in residential construction are included in this unit.
tender letter
variations
extensions of time
site instructions
progress payments
final account
Disputes with clients are often due to a need for better administration of the overall
contract as well as onsite activities. Small matters have a tendency to escalate in
importance if left unresolved. Good communication and interpersonal skills will develop
the trust shown by the client in awarding you construction of the project in the first place.
The job is made easier if you have good organizational skills and procedures in place to
properly document the project. Your project file should accurately record the history of the
job and should make your task of finalizing the project much easier.
communication
organization
procedures
supervision
quality
customer service
documentation
As-built drawings are documents that allow a compare and contrast between the
designed versus final specifications, and provide a detailed blueprint of the building and
the land around it as actually constructed in the end. Also known as record drawings and
red-line drawings.
As-built renderings should detail the shape, dimensions, and precise locations of any and
all elements within the scope of the project. Any modifications, whether minor or major,
should be included, along with a record of approvals to go along with the changes.
The final as-built drawings include any and all of the following, as well as every other
change made during the construction phase of a project:
Modifications
Field changes
Shop drawing changes
Design changes
Extra works
As-built drawings go hand-in-hand with as-built surveys, also called as-built maps. These
are used during the construction phase to continually track how the land and building is
changing as work progresses.
Typically, the architects or designers who originally designed the project will also create
the as-built. They are familiar with the original specifications and are therefore the most
qualified to reflect recorded changes.
As-built, in other words, ensure that as designers, architects and contracts move on from
the project and, a resource still exists beyond the original blueprints.
1. Assists the Facilities Team: With a full record of change, facility teams can meet
issues faster and owners can save money down the road due to improved operations and
speed
2. Improves the Renovation Process: With a full history of project changes, owners can
see exactly what has been built and do not have to invest heavily in learning about
existing conditions
Recording changes in scale, or ideally using the same scale as the original
drawings
Using clear labels and descriptions rather than vague phrases such as “similar” or
“equal to”
Including changes in sizing, materials, dimensions, location, installation, fabrication
and so on
Noting unexpected obstructions encountered, and the solutions decided upon
Noting dates when changes were made
Recording any changes made as a result of final inspection
Attaching all related shop drawings and appendices
TVET program title- On-site Building Version -1
Page 14 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
Self-Check -2 Written Test
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 1 point)
1. in project the drawings shouldn’t be used/kept by_________________
A. Site Office C. security guard
B. Supervisor D. All
2. before starting any project its possible to ensure that drawings are adequately detailed
and checked
A. False B. True C. None
3. The different means by which drawings could be produced to help building work
progress smoothly is________________
A. color coded C. large /small size
B. Laminated D. All
4. in Project careful attention must be paid as to how drawings are going to
be_____________
A. produced C. distributed
B. Checked D. All
Part II fill the blank space
1. What is As-built drawing? (3 point)
________________________________________________________
________________________________________________________
________________________________________________________
________________________________________________________
2. Write down the two main reasons which make as-built drawing important. . (4 point)
____________________________________________________________
_____________________________________________________________
______________________________________________________________
________ ______________________________________________________
When executing a variation it is important that any agency specific policy, procedure and
delegation is taken into consideration as there are usually only a limited number of
people, within an agency, who have the delegated authority to approve variations to
contracts (refer to your agency’s Procurement Delegation Schedule). Being aware of
agency and contractual requirements should help to minimize the risk of informal contract
variations. Refer also to the Contract Variation Flowchart.
When undertaking construction works there are often instances as a head contractor
when something on a client’s site might get damaged and needs to be repaired by the
owner of the property. In this situation and other similar situations it is clear there is a loss
to the owner.
There are ways in which the above scenarios can be resolved efficiently and quickly so
that it does not leave a bad taste in the mouth of the owner. Remember it is important to
keep up the reputation of the company even if it costs the company a little bit at that point
in time. The quick resolution of these issues can mean that the company’s reputation is
maintained.
For example if there is a trade that shows up late and the cleaners have been through
and they start making a mess after the cleaners have finished... WHO PAYS? Is it right
that the builder should pay again? Is it right that the client should pay again? However the
cleaner needs to be paid and the only person to blame is the contractor that did not show
up on time.
1. Communication
Best practice is to have any back charge notice requirements explicitly stated. Make sure
that the subcontract provides you with reasonable notice provisions. Meaning, if and
when you incur back charges, be sure you are notified of the charges and provided with
an ample amount of time to correct, repair, or clean up any issues caused by your team’s
work.
2. Documentation
Whether you are the General contractor (GC) or the sub contractor, proper and
meticulous documentation is key! For GC’s: include as much detail as possible when
sending notice of defective work. If the sub decides to take remedial action, take progress
photos for your records. If the back charges are challenged for any reason, it’s crucial to
have sufficient proof that it was caused or incurred directly by that specific sub.
Late payment of invoices is a problem for most suppliers of goods and services. In tough
economic times the problem gets worse as cash retention becomes a greater priority.
Materials and supplies being delivered to the site need to be paid for as soon as possible
often the materials are delivered by companies that have accounts with the Builder.
Money can easily be lost if deliveries are overpaid or time can be lost if accounts are not
paid on time.
The question that we are going to examine is how you account for deliveries and track
payments whilst ensuring companies are not overpaid.
There are a number of pieces of paper that are involved with any delivery of materials or
supplies to a building site.
Each of these papers is interrelated. These are:
1) Order form or Purchase order docket this is produced by the builder prior to
delivery to site.
2) Delivery docket this arrives with the delivery and is signed for by the site manager
or similar. This should be cross checked against the purchase order or Order form.
3) Invoice for payment this arrives at the company office as opposed to the building
site and relates directly to the delivery docket.
This should be cross checked with the delivery docket ensuring that everything charged
for has been signed off as delivered and the order form ensuring that what was delivered
was ordered.
Live wires
Active circuits
Specialized equipment
On top of any issues unique to your business, you can also face other common risks that
small business owners deal with, like property damage or losing important documents.
Electrician and electrical contractor insurance can help protect your business from these
risks.
Electrician insurance is business insurance for electrical contractors. It helps protect your
business from a wide range of risks.
Business Owner’s Policy (BOP) is a good place to start for your electrician insurance
plan, because it helps protect your electrician business the same way a homeowners
insurance policy helps protect your home and personal possessions.
BOP combines three coverage that are essential to many small business owners, so you
can save money on insurance rates while protecting your business with one policy.
Electrician liability insurance: This is also known as general liability insurance. It helps
protect your business from claims alleging bodily injury or property damage, like if a
customer gets hurt in your office or your employee damages their property while doing
electrical work at their home. General liability insurance for electrical contractors also
helps protect you from claims alleging libel and slander.
Business income insurance: This helps you recover your business’ lost income if you
can’t open because of covered property damage.
Insurance claims
Accidents occur on building sites and occasionally they damage materials or the fabric of
a building. Sometimes they are caused by malpractice or negligence and sometimes by
mistakes during construction. The main question when damage to property, building
fabric or product occurs on a building site is who pays?
The above is the reasons why we have insurance policies that cover every step of the
building process. The biggest question is how you make an insurance claim.
This is quite often undertaken by the insurance company. It should be noted however that
there are a number of things that you can do to help make an insurance claim.
1. Claims Adjudication
2. Explanation of Benefits (EOBs)
3. Claims Settlement
As soon as the damage theft accident or whatever the scenario occurs it is important to
document the situation clearly and logically so that the insurance company can see proof.
This proof can be shown through photos or evidence of delivery and the subsequent
value of the product. Details in site diaries are very important.
Calling the insurance company and stating that you would like to make a claim quoting
the policy number and you can start the process rolling to recover the loss that has
occurred.
If the damage was caused by vandals or there is theft it is essential that the police are
called and a police case report number is issued by the police and that this is given to the
insurance company.
Most personal injury claims are settled by the at-fault party’s insurance carrier. Your claim
begins with notifying the insurance company of your intent to seek compensation for your
injuries. To write an impressive letter your notification letter should be simple and stick to
the facts.
The at-fault party’s insurance policy number, if available Make a copy of the signed letter
for your records.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 2 point)
1. To be part of electrical business insurances because running an electrician business
means dealing with unique risks because you handle:
A. Live wires C. Specialized equipment
B. Active circuits D. All
2. Which of the following is the information to be included in claim notification letter.
A. A Letter date
B. Your full name and contact information
C. Injury date and location
D. The at-fault party’s name and contact information
E. All
3. In claim notification process, claims begin with notifying the police.
A. True B. False C. None
Building approvals are assessed against the Building Code of Australia and relevant state
plumbing and building regulations. These approvals are necessary to ensure and control
the safety of structures/electrical installation work.
Building approvals depend on the type of structure, for example a residential house will
look at different aspects compared to a multistory commercial of mixed used building.
Construction “Contract Documents” are the written documents that define the roles,
responsibilities, and “Work” under the construction Contract, and are legally-binding on
the parties (Owner and Contractor). Contract document is those items so designated in
the Agreement, and which together comprise the Contract.
Environmental standards are administrative regulations or civil law rules implemented for
the treatment and maintenance of the environment. Environmental standards are typically
set by government and can include prohibition of specific activities, mandating the
frequency and methods of monitoring, and requiring permits for the use of land or water.
Environmental standards may be used produce quantifiable and enforceable laws that
promote environmental protection.
Planning and scheduling are distinct but inseparable aspects of managing the successful
project. The process of planning primarily deals with selecting the appropriate policies
and procedures in order to achieve the objectives of the project. Scheduling converts the
project action plans for scope, time cost and quality into an operating timetable.
Plan and spec is a method of commercial construction project delivery where design
drawings (or plans) are created along with written specifications (or specs) to further
describe the equipment and parts shown in the drawings. One of the biggest reasons
Owners choose Plan & Spec is because construction costs are more defined. After the
design is completed, the Owner can send out the construction documents for bid.
The Safety Management Plan is a working document, which outlines all of the actions to
be carried out to ensure the safety and health at the work place. This document is
fundamental to the management of safety by the Health and Safety Committee and
Management. The sort of issues which should be addressed in the Safety Management
Plan include: -
The Consultation Program is a broad network of occupational safety and health services
funded primarily by federal OSHA. The Consultation Program exists to help you, the
employer.
A good tax system should meet five basic conditions: fairness, adequacy, simplicity,
transparency, and administrative ease.
Fairness, or equity, means that everybody should pay a fair share of taxes. There
are two important concepts of equity: horizontal equity and vertical equity.
Adequacy means that taxes must provide enough revenue to meet the basic needs
of society. A tax system meets the test of adequacy.
Because regulatory compliance is such a big deal, your business needs to take a
comprehensive, intentional approach to creating an effective regulatory compliance
program. Thorough training should accompany the program’s implementation to ensure
employees understand the importance of regulatory compliance and how it impacts their
day-to-day jobs.
Your first step to regulatory compliance starts with a comprehensive audit to determine a
compliance baseline and identify where any problem areas lie.
You’ll look at the strengths and weaknesses of everything from security policies to risk
management procedures. Assessing risks, for example, allows you to not only identify
them and their likelihood for occurring but also their potential impact on your business.
Once you identify your weaknesses, compliance gaps, or problem areas, then you can
put best practices in action.
If you don’t already, you should be reviewing and tracking how much compliance
violations have cost your business. Doing so can help when it comes time to ask for
TVET program title- On-site Building Version -1
Page 36 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
budget to mitigate these compliance issues. How? By enabling you to prove out how
much per year the violations are costing your company.
Compliance officer
It isn’t enough to simply have policies and procedures. They need to address the specific
compliance areas identified in the audit listed above. Plus, they need to be reviewed
regularly to stay current with the always-changing regulatory landscape. Again, that’s why
it’s helpful to designate a CCO.
In addition to having targeted policies and procedure tied to compliance, a key component
of policy management involves the need to track when employees have read and signed
your policies.
This plays a huge role in being able to prove compliance down the road, if necessary. If
you can show the employee knew the policy, read and acknowledged it, and violated it
anyway, then the company’s liability significantly decreases. This provides a much strong
position to take action against that employee.
Just like having your policies and procedures tied to compliance issues, you want to “train
to your policies.” If the policy is written to address specific compliance issues, then your
training should reinforce that behavior and ensure employees comprehend what they are
When you’re entire workforce understands the importance of compliance (and their role in
making it happen), it distributes the knowledge broadly. Compliance isn’t about a handful
of people who know the latest regulations and what that means for operations. Rather,
everybody is up to speed on the latest changes and they’ve been trained on how it
impacts them.
Continual improvement
It helps to automate this review process so nothing falls through the cracks. That’s one of
the powerful benefits of regulatory compliance software. It allows you to set workflows
and reminders to route it to the appropriate people who need to review and make
changes.
Now that you understand the critical importance of regulatory compliance (and the
challenges you might face), you can use the above guidelines as your action plan.
These steps will help you create an effective regulatory compliance program in your
business that protects your resources, your reputation, and your internal and external
audiences.
The site diary records the construction progress as well as various occurrences on the
construction site. This includes, for example, the occurrence of construction defects.
Thus, the documentation around a project is an important basis for clarifying any facts
and responsibilities.
Site diaries are the backbone of construction site reporting. They are used to document
daily site progress and ensure any project hiccups or claims can easily be traced back to
a site diary or other document to prove exactly what happened - along with supporting
evidence and signoff. Site diaries are often the final proof in small and large court cases
and claims.
A Site Diary is a document of "first record"; a site diary is where a competent site
supervisor initially records any occurrences on site.
Some items (example Variations) would then be further copied in to secondary
doucments (example Variation register Site diaries are also a place for supervisors to
record contact details and other items specifically related to a given project for quick
referencing. It is essential that a Site Diary MUST be filled out DAILY and as incidences
occur.
It is important to keep a construction site diary as construction logs are a great tool to
demonstrate what work was done, which tasks were completed, what problems were
solved and what issues were outstanding on specific days. Daily logs compound to an
archive of records that may be useful at any time. All verbal agreements and deals come
and go but recorded documents can always be retrieved.
Since the site diary is a formal record of your construction project’s worksite progress, it
should include all events that could affect the progress and your quality of finished work.
In the modern fast-paced construction world, document control and management is
imperative for every construction project. No matter what role you play in the project
manager, site manager, estimator, contracts manager everyone has the administrative
responsibility that is critical for your project’s success.
For the person in charge of the daily site activities, the daily construction log or site diary
is a very important administrative tool. Other than being an essential record of your
project’s development, your site diary also acts as substantial documentation for many
other construction contract aspects.
Usually, it’s the site foreman or inspector who records all the site information while the
site agent or contractor representative checks the data entries and signs the site diary.
The usual site diary usually includes, but is not limited to the following:-
The date and weather conditions
Site diary entries of dates and weather condition reports can help support your
requests for work extensions or provide evidence for work delays.
The number of workers in various trades
Keeping a record of the people on site (including subcontractor companies, their
workers and their hours) helps you organize appropriate worker amenities that are
specified by law (for example: commute, accommodations, toilets, showers, mess
hall, etc.).
1. You can use your site diary as documentary evidence in any case of construction
site disputes. It is always admissible in court.
2. Your construction logs will be requested in any accident investigation. Work covers
and insurance companies will need your site diary for their investigations.
3. Your site diary will be very handy in monitoring and maintaining your hire
equipment to avoid unnecessary multiple hiring.
4. Your site diary also records worker attendances for easy contractor invoicing and
charge outs.
In addition, depending on your role on site, you may be charged with completing more
information surrounding labor, plant, equipment, materials and expenses.
The most important part of your site diary etiquette is that you do it daily - and when
specific incidents occur. Your site diary is your document of first record - and it is the
reference point for many other important documents, such as variations.
The communication process is probably the single most important factor in the day to day
activities of a building supervisor.
All building organizations require essential communication links between the different
levels of the hierarchy. Communication has a direct association with performance i.e. the
better the communication process, the greater the performance. Because performance is
inextricably linked to profit, it is desirable for management to adopt sound communication
strategies from the outset; this becomes a major platform in on-site culture.
Effective communications will stop confusion occurring between the sender and receiver
of a message whether it is written or verbal. Communication is a two way process that
involves listening to the feedback supplied when instruction is given.
How well you perform your activities and how they are seen by workers will be
determined importantly by your communication skills. People do not communicate all their
thoughts and feelings. People commonly use poor communication techniques which can
lead to confusion.
Visitors
Plant Hire
Delays
Inspections
Accidents - Incidents
Where there is insufficient space to record information add Site Diary: Page 2 Notes
The problem arises when the resources are not handled properly and effectively. The
improper planning of resources and lack of coordination results in wastage of time.
Organizations would not be able to achieve their goals without using a resource allocation
software that helps in allocating & managing resources. The main motive of an
organization is to achieve targets.
To make use of your 100% of your resources, effective resource management should be
your first step.
2) Proposed regulation
The regulatory agency will draft the proposed regulations to fulfill the requirements of
the law upon which the regulation is based. For example, if a new law is passed by
Congress that limits water pollution produced by a business, the agency will develop
regulations that carefully outline the limits of pollution, how the limits are measured,
reporting requirements, enforcement powers vested in the agency, and penalties the
agency is entitled to impose under the law.
3) Public comments
The proposed regulations are published and the public is invited to comment. It's not
unusual for industry leaders and interest groups to comment in an attempt to modify
the rules to advance their particular interests.
4) Review of comments
The agency will review the public comments and may or may not make any changes
based upon them.
5) Final regulation
The completed regulation is published in the Federal Register and will eventually be
added to the Code of Federal Regulations, which is essentially a list of all the
federal regulations, broken up into titles and chapters.
6) Implementation
The regulation is implemented, or made effective, and enforcement commences.
The right piece of machinery for the job helps to ensure a safe working environment, as
well as protect the quality of the plant. Items that must be considered are: machine
capacity; horsepower; range and limit of machine in terms of what operating parameters
are safe, and when a change in these conditions can be potentially hazardous; safety
features and retrofits; and monitoring and maintenance equipment.
Plant Scheduling
This is a simple and easy to use, one-sheet worksheet that will allow you to monitor,
analyze and schedule the Property, Plant & Equipment (PP&E) of your business over a
5 year period. PP&E is made up of tangible capital assets.
To keep track of where plant items are being used on jobs, you can schedule them, or
alternatively, check out a plant item to an employee. Since you are not allowed to double-
book plant items, you always know where your plant items are and which ones are still
available.
You can check out plant items to employees when needed, then check them back in
when they are finished using them, so that you always know who is using what
equipment. You can also track when plant items are due to be serviced for maintenance.
The organization has a sound environmental policy that demonstrates their intent that
operations will be effectively managed, environmental impacts minimized and that the
operation of the business are continually improved. This policy, signed by members of the
board of directors and the company’s environmental manager is displayed on the staff
intranet, canteen, changing rooms, and offices.
It clearly states what the organization is committed to, their objectives and how they
intend to achieve these. Some of its key objectives include:
Undertaking all activities in an environmentally responsible manner
Fostering a pan-company environmentally responsible culture
Compliance with applicable environmental legislation
Continually striving to prevent pollution, reduce waste and energy use and limit the
use of non-sustainable natural resources
Prior to commencing work on any project the organization develops site environmental
management plans. Environmental aspects, impacts and the requirement for
environmental assessments are incorporated within these plans.
Environmental structure
The organization commits to collaborative working with other companies involved in this
management of this demolition project including environmental consultants. Integral to
this are the project and site managers. The project manager ensures all work is carried
out in compliance with legislation and contractual agreements.
TVET program title- On-site Building Version -1
Page 52 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
The site manager has responsibility for the management of health, safety and
environmental protection ensuring that all control measures are implemented including
the reporting of all health and safety and environmental incidents and near misses.
Holding meetings on site enables the stakeholders to see progress for themselves (rather
than relying on a report for another party), and to look at problem areas, discuss quality
issues, assess mock-ups, and so on.
Meeting minutes should be prepared, with a requirement that any disagreement with the
items recorded in the minutes is raised within a pre-defined period (perhaps one week).
Progress meetings may also result in the preparation of a construction progress report for
the client.
The request is a document which tells the purchasing department or manager exactly what
items and services are requested, the quantity, and source and associated costs.
Here are several ordering methods available to purchase products and services. The
primary ordering method Sourcing & Procurement manages and administers is the purchase
order method. Alternate ordering methods are available for specific types of purchases to
help expedite the purchasing process.
Procurement administrators work with suppliers to negotiate material and order costs, and
compile cost reports for invoices. In some cases, bargaining may be necessary to get the
best rates possible.
Prepare Purchase Orders
Procurement administrators prepare purchase orders and send order requests to suppliers.
They also update records and follow up with vendors to check if the order is being
processed.
Resolve Order Problems
If issues arise with shipments or orders are incorrect or late, procurement administrators
work with the supplier to resolve the issue. They build strong relationships with key contacts
within these companies, working with them closely to fix problems as quickly as possible.
Update and File Records
Procurement administrators perform inventory and administrative tasks like preparing and
forwarding invoices, updating databases, filing, and organizing documents for accounts.
They also provide additional administrative support for team members as needed.
Site instruction are very important for projects and companies in the industries.
Logistically, they are important to moving projects forward. A contractor who is largely
responsible for the safe delivery of the asset must have a mechanism for pushing
adjustments down through the chain of command. If a subcontractor is falling behind on
schedule or the client requests a change from the original plan, the contractor needs to
have a formal method for ensuring that other contractors and subcontractor are informed
and compensated for this change and execute the new instruction properly.
Because site instructions often fall outside the original scope of the contract, they aren't
necessarily 'covered' by the contract. When the builder queries a design detail, the client
often instructs he or she to do something that is not clear in the documentation. If this is
the case and the client does not provide written confirmation, you as the builder should
confirm the instruction in writing by use of a site instruction. If the instruction impacts on
your subcontractors, you should also provide them with a site instruction. A site
instruction is merely written confirmation of an instruction given to you by the client that is
not clear in, or contradicts, the contract documents.
For example: although the color of fencing specified on the drawings and in the
specifications is black, the client has changed their mind and wants the fence to be green.
They have advised you verbally but as it is considered a small change that has no
monetary impact (not a variation) the documents have not been changed.
TVET program title- On-site Building Version -1
Page 59 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
In this case, you need to confirm the request in writing and ask the client to sign it. Keep
a copy and distribute one to the client and to any subcontractors impacted upon by the
instruction.
When you receive an instruction from the client of the client’s representative that is not
considered a variation, and not confirmed in writing, you leave yourself open to dispute. It
is vital that any instructions given to you by a client is confirmed in writing and signed by
them.
Site Instruction Format
The communication between senior management and the supervisor requires a daily flow
of correspondence which must be quickly and effectively addressed by the supervisor.
Performance appraisal is one task frequently assigned to the supervisor and as such they
must closely follow company policies affecting the performance of subordinates; this
appraisal is considered one of the most important on-site reports. Any written formal or
informal communication is important. Many of these are in short report form and should
be recorded electronically or copies filed accordingly.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 3 point)
1. Site reports are frequently involved in activities such as______________
A. performance appraisal C. progress report
B. Site diary D. All
2. Which of the following is the categories of impact according to risk control and
management system.
A. low impact
B. moderate impact
C. high impact
D. very high impact
The first step is to identify whether the change in scope is in fact a 'variation' within
the meaning of the contract. When a contract refers to a 'variation', it typically
means a change in scope that has been directed by the principal or
superintendent.
Depending on the terms of your contract, there are a number of other events that
could give rise to an entitlement to claim an Extension of Time (EOT) or an
adjustment to the contract price. (Latent conditions, discrepancies between design
documents or changes in legislative requirements are examples). Although you
might think of these as a 'variation', they might not actually be a 'variation' for the
purposes of the contract. This distinction can be critical because there might be
different procedures for claiming different types of entitlement.
Once you have determined the nature of your entitlement (and therefore the type
of claim you need to make), you will need to look to the relevant clauses of the
contract to see what is required. It is important to consider all potentially relevant
clauses, noting that there may be more than one that applies to your situation.
For example: if you have been directed to perform a true 'variation', you will most
likely need to consider the clauses in your contract that deal with
variations, EOTs and delay costs (potentially 3 separate provisions). Often you will
be required to submit more than one notice in respect of the same entitlement.
If your contract includes time bars, you will need to comply with all relevant
timeframes. Otherwise you could potentially lose your entitlement to some or all of
your claim.
If different parts of your contract prescribe different timeframes for the same thing,
the safest course is to assume that the shortest timeframe applies.
3. Notify the client
The best way to avoid a dispute is to maintain transparency throughout the project.
Many contracts will expressly require you to notify the superintendent or principal
as soon as you become aware of anything that might constitute a variation
(including a direction received from the superintendent or principal, even if it is not
stated to be a variation).
This applies even where you might not have all of the information to provide the
complete picture. Particularly where your contract contains time bars, a failure to
provide a notice at all can put you in a much worse position than submitting a
notice which is qualified to reflect a lack of relevant information.
You must be able to substantiate your claim. The type and level of information that
will be required to achieve this will depend on the nature of the work and the
amount of time and cost involved. Some contracts will require this information to be
included in your initial notice (step 3 above). However, many will contemplate an
initial, abbreviated notice or estimate, with the detailed information to follow
separately. You will need to check your contract to see which applies.
When setting out your entitlements, think carefully about: all work that may be
required to effect the change; the impact (if any) this will have on the program, and
whether an EOT may be needed (and if so, whether delay costs may apply); and
your entitlements to claim additional preliminaries, overheads and/or margin.
These different entitlements should be addressed separately, so that the
superintendent or principal can understand the basis for your claims.
If you are submitting a claim for an EOT, you will need to be able to demonstrate
that the variation affects an item on the critical path of the current construction
program. An impacted program, based on an accurate baseline program, is
typically the best (and sometimes the only) way to demonstrate this.
Where you are claiming an EOT, the contract may require you to explain the steps
you have taken to minimize or mitigate it. Even if this is not a requirement under
the contract, including this additional information in your claim may improve your
chances of success.
Before commencing work on a variation, and subject to the terms of your contract,
you should wait to receive a written direction to proceed from the superintendent or
principal. It is critical that this direction is given after you have given them written
notice of the time and cost that will be involved (per the previous steps above).
The idea here is to ensure there is a clear paper trail to demonstrate that, when
they directed you to proceed with the work, they were on notice (in writing) of the
potential time and cost implications of the direction.
Once you have completed the work, you should claim payment for it. If your
variation involves a delay, make sure you have followed the process for claiming
an extension of time (EOT) and any delay costs (if applicable).
Once the work has been done, from a legal perspective, there is nothing to prevent
you from including the claim in your monthly payment claim.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 3 point)
1. _____ is an alteration to what has previously been agreed to in the building contract.
A. Contract C. Design
B. Variation D. All
2. which of the following is the common dispute occur due to Variation.
A. disagreement as to the nature and extent of the works that were to be completed
B. whether the variation works are included in the original contract price
C. disagreement as to the cost
D. All
3. In variation before the work commences on the variation, the builder should provide the
owner with:-
A. a written description of the work;
B. any plans or specifications for the work; and
C. The extra cost, and details of any extra time required to complete the work.
D. All E. A & C are correct
One acceptable grounds for the request of an extension includes legal issues or
problems. These issues can affect the project’s completion and the contractor’s
performance. An example of such a problem could be the delay in clearing inspections.
Reasons for Extensions That May Be Denied
Some problems causing delays may not gain approval. These include delays caused by
subcontractors such as not showing up for work or not having the necessary equipment.
Another contractor-based delay comes from an under-performing contractor, specifically if
bad management causes long-lead times in procuring items.
5.1.2. The Process to Request a Time Extension
When requesting a time extension, certain steps must be followed to ensure the
extension is approved. In a typical process, the contractor notifies the project manager
that an issue might affect the project schedule. A formal letter is addressed to the contract
administrator requesting the time extension and the reasons why those days should be
added to the construction schedule.
The contract administrator then remits the letter to the project manager for evaluation and
approval or rejection.
A time extension request letter should be concise and must reference the contract clause
that allows the request and provide proof of the delay reasons and a proposed recovery
plan. It should also include the damages (if any), the amount of calendar or working days
being requested, and the activities that are impacted by the changes.
Some builders will claim at every opportunity. Be aware that ridiculous claims can be
challenged and you may be required to justify it. If you cannot justify a claim, you may
damage the integrity of your organization. A claim should be backed up by evidence and
documentation (such as site diary entries).
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 3 point)
1. which of the following is additional consideration when making the request of time
extension
A. Calendar days are not the same as working days.
B. Insurances and bonds will need to be re-issued to cover extended periods.
C. Winter days are shorter and typically less productive than summer days.
D. No additional time will be granted for the same item once it has been approved.
E. All
2. Which of the following is the reason for time extension request may be denied
is_____
A. Delays caused by subcontractors such as not showing up for work or not having
the necessary equipment.
B. delay comes from an under-performing contractor
C. Bad management causes long-lead times in procuring items.
3. Which of the following is the reason for time extension request is acceptable
A. Legal issues or problems. C. when employees are absent
B. The delay in clearing inspections. D. A & B
4. The time taken to complete a project is all too often the cause of a dispute. This can
be the result of many factors including:
A. The original underestimated time
B. Unexpected delays
C. Bad weather
D. Lack of diligence by the builder
E. All
1. the creation of the potential for death or serious harm to a client, an employee, a
member of the public, or a person for whom the employee has responsibility, or
2. Loss of or damage to agency property or funds that has a serious impact on the
agency or its work.
Date:
We will have a follow up meeting on the [date] with you and [named employee] will
also attend to give their feedback.
I hope you will take this matter seriously as I am sure you have the capability to be a
valued member of the team if you really want to.
[your name]
[position]
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 3 point)
1. _______ is work-related performance that fails to satisfactorily meet job requirements
specified in the employee’s job description or work plan or as directed by the employee’s
supervisor.
A. Tiredness C. Unknown feeling
B. Unsatisfactory job performance D. All
2. Grossly inefficient job performance is unsatisfactory job performance that result in____
A. the creation of the potential for death or serious harm to a client, an employee, a
member of the public
B. Loss of or damage to agency property or funds that has a serious impact on the
agency or its work.
C. Good results
D. A & B are correct
3. Your notice for unsatisfactory job performance should include details of the contract
date____________
A. When the work was completed C. the faults in the work
B. The amount in question, D. All
4. It is important that all problems with unsatisfactory work are communicated directly to
the contractors involved in writing and that these are filed appropriately in hard copy or
electronic form.
A. True B. False C. None
The duty of an administrator depends on the company that the administrator works for.
The main job responsibility of an administrator is to ensure the efficient performance of all
departments in an organization. They act as a connecting link between the senior
management and the employees. They provide motivation to the work force and make
them realize the goals of the organization.
Administrative Procedures
Administrative procedures are a set or system of rules that govern the procedures for
managing an organization. These procedures are meant to establish efficiency,
consistency, responsibility, and accountability.
The Importance of Administrative Procedures
The project manager should ensure that a pre-start or “kick-off” meeting is held as there
are several benefits to site communication which may arise from such a meeting,
including the following:-
It allows people to get to know each other; this is likely to lead to better
communication and less confrontational attitudes as work progresses
It provides the opportunity to decide on how communications will operate
It provides the opportunity to define points of contact at each organization
It can be used to ensure that all people have the contact details for others working
on the project.
Ensure that all relevant people attend the kick-off meeting, this may include supervisors
and major suppliers.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 2 point)
1. ________ is a process of systematically arranging and coordinating the human and
material resources available to any organization for the main purpose of achieving
stipulated goals of that organization.
A. Administrator B. Administration. C. Leadership D. All
2. Administration systems is such a system which ensure that_____________________
A. all assets are safeguarded with limited access to each
B. business is conducted in an efficient and timely manner
C. staff are appropriately trained for the duties they perform
D. All
3. Which of the following is an ability of effective administrator.
A. To understand general concepts of Administration
B. File in the proper way and filing standard
C. Develop an appropriate office management strategy
D. All
4. Which of the following is the importance of administrative procedure.
A. They help ensure that managers are held accountable for decisions that deviate
from the procedures.
B. They provide an objective set of rules by which an organization is governed.
C. Establish the legitimacy of management action by ensuring the application of
management rules and decisions. D. All
Part II: fill the blank space
1. Write the four key features of good administrative control system. 4 point
________________________________________________________
________________________________________________________
________________________________________________________
________________________________________________________
Answer the following question!
Note: Satisfactory rating 12 points Unsatisfactory below 12 points
You can ask you teacher for the copy of the correct answers.
Score = ___________
Answer Sheet Rating: ____________
If there are issues with the product or project, it is on the subcontractor to fix the problem;
this is the main issue of inspection. At this level, the repairs are more expensive because
usually an entire section must be rebuilt. To prevent this, subcontractors should have
some inlet of a construction quality control plan or quality management plan in place.
Electrical Contractor Quality Control Plan
Want to know how to assure your client that your electrical project is safe and follows
contractual requirements? Incorporate an electrical contractor quality control plan into
your operations to ensure that your client can use the building. Businesses that use a
construction quality control plan for their projects can ensure that quality issues won’t
happen. There are some similar elements to every quality control plan, but many factors
are dependent upon the exact specifications of the individual project and trade.
In terms of quality control, electricians will use an electrical contractor quality control plan
to reduce the chances of injury in the field.
TVET program title- On-site Building Version -1
Page 86 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
Several locations contain all of the necessary information for construction industry quality
standards as well as applicable building codes. Using that information is an excellent
starting point for a construction quality control plan.
In this section, you will know the importance of a quality control plan and how to write one
for an electrical contractor to help outline ways to mitigate risk.
When starting a construction quality control plan, whoever writes it must have a section
for signatures of the participants. This shows that everyone read and agreed to the plan.
There should also be a space for information on the project; that way, it’s easier to ensure
it ends up in the right project folders.
The first part of a construction quality control plan will be an organizational chart. This
allows the company to determine who is responsible for what. Having a page that shows
the process and flow makes it easier to remember. It’s also a great reference page in
case anyone forgets who is in charge of different tasks. Work tasks are all quality
controlled, meaning each is subject to a number of inspections; before, during, and after
the project is over.
The next portion of a construction quality control plan should specify the work. Quality
control managers write all the defining features of the project. Contractors fill in how they
will complete the work as well as their primary point of contact. Now the quality control
manager can easily reach them if something is amiss.
The final section of the construction quality control plan has to cover a lot of ground. This
section overviews testing, verification, submittals, tracking, and weekly logs. It lays out the
tests that will be administered, the time frame the quality control manager must give
before the test, what happens when a test fails, how the records will be stored, and the
procedures around it. Additionally, it should also include a schedule of agencies that will
test and inspect the field. They will inspect the estimated date and the real date.
This section also informs people of the procedures for submittals. This helps determine
what should happen if the submittal isn’t approved, along with what happens if it is
approved. It should also include where submittals will be kept.
Your quality control procedure documents should contain information and guidelines as to
how total quality management will be maintained including:
Physical quality guidelines
Inspections, approvals and certifications
Inspection and test plans and certificates
Methods and sequence of tests
Acceptance and rejection criteria
Key control points
Performance specifications
Visual qualit
In order to get an accurate quote, make sure your specifications include all the relevant
information.
Initial Verification
An initial verification takes place upon completion of a new installation or upon completion
of additions or alterations to existing installations. The aim of the initial verification is to
determine whether the requirements of all the applicable prescriptions have been met.
This is achieved by inspection and testing.
good workmanship
separate circuits
adequate number of circuits
adequate number of socket-outlets
all circuits suitably identified
a suitable main switch provided
main breakers to interrupt all live conductors
main earthling terminal provided
correct fuses or circuit breakers installed
all connections secure
the installation earthed in accordance with national standards
primary equipotential bonding connects services and other extraneous conductive
parts to the primary earth facility
supplementary bonding has been provided in all bath and shower rooms
The following items must checked concerning protection against direct contact:
insulation of live parts
enclosures have a suitable degree of protection appropriate to external influences
enclosures have cable entries correctly sealed
enclosures have unused entries blanked off where necessary
After inspection, the following tests shall be carried out:
continuity of conductors
insulation resistance of the electrical installation
automatic disconnection of supply
measurement of the resistance of the earth electrode
measurement of the fault loop impedance
polarity, functional, and operational tests
voltage drop
It is true that electrical installations do not deteriorate quickly and therefore do not usually
require high levels of maintenance. However they do not retain their original condition:
damage, corrosion, degradation of material, and degradation of the insulation (the
insulation hardens and it can crack) all occur.
In addition, contacts can become loose as well as excessive electrical loading, ageing,
environmental influences, normal wear and tear, and other factors can affect the condition
of an installation. Apart from the deterioration over the years, the functioning of electrical
installations does not necessarily follow the changing needs of its users:
More power sockets are needed. (A recent survey in the UK reveals that two-thirds
of Britons say that they don’t’ have enough plug sockets in their homes!)
More lighting points are needed
There is an increased awareness of safety, therefore:
There is a need for an earthing arrangement
There is a need for RCDs (Residual Current Devices)
Electrical installations should be maintained in a good and safe condition to prevent
danger. Part of this maintenance should be a regular verification that includes appropriate
inspection and testing.
A periodic inspection is an inspection of the condition of an existing electrical installation
to identify – in order of priority – any deficiencies related to the safety standards for
electrical installations. Periodic inspections should comprise a detailed examination of the
installation. They can be carried out without dismantling or with partial dismantling of the
electrical installation.
A periodic inspection will reveal if any of the electrical circuits are overloaded as well as
other potential electrical shock risks and fire hazards in the electrical installation.
What grade of materials should be used, and what specific electrical equipment
requirements are there for lighting, power or distribution systems?
In many cases, you’ll find a conflict between the drawings and the specifications, some
examples include an electrical diagram that calls for one grade of wire while the
specifications call for another grade of wiring.
This is common and you’ll want to find a reference in the specification that clarifies what
supersedes the other. Generally, drawings will supersede the specifications about
quantity and location, while the specification will supersede the drawings on material type,
performance, and quality. Generally, the owner will include a clause that states in the
event of a conflict, use the option with the higher quantity and highest quality.
This covers the owner but puts you in a position of over bidding the project. In this case,
it’s best to submit a request for information (RFI) for clarification and always qualify your
bid confirming what was included and excluded in your bid price to avoid any confusion.
TVET program title- On-site Building Version -1
Page 99 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
Self-Check 1 Written Test
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 2point)
1. _____ensures that anything installed will be usable and safe for a client of the project.
A. Management B. Quality management C. manager D. A & C are correct
2. Which of the following is the items must checked concerning protection against direct
contact.
A. insulation of live parts
B. enclosures have cable entries correctly sealed
C. enclosures have unused entries blanked off where necessary
D. All
3. In building electrical installation work using quality material can prevent_______
A. Later rework C. appropriate standards
B. Can help ensure that the materials weren’t faulty D. A & B are correct
4. Your quality control procedure documents should contain information and guidelines as
to how total quality management will be maintained including:
A. Physical quality guidelines
B. Acceptance and rejection criteria
C. Inspections, approvals and certifications
D. Key control points
E. All
5. _________ the description of the Material, including requirements, tolerances, shelf
life, specifications, suppliers and safety data.
A. Material Specifications C. Material
B. Material quantity D. All
Part II: Fill the black space
1. Explain the five steps on writing an electrical quality control plan. 5 point
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________.
Answer the following question!
Note: Satisfactory rating 15 points Unsatisfactory below 15 points
You can ask you teacher for the copy of the correct answers.
Score = ___________
Rating: ____________
Answer Sheet
Name: _________________________ Date: ______________
TVET program title- On-site Building Version -1
Page 100 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
Information Sheet-2. Using and complete Site checklists detailing specific items.
2.1 Using and complete Site checklists detailing specific items
2.1.1. Site inspection checklist
Ref Criteria Observations
1. Administrative requirements
1.1 Signs have been installed that:
show the principal contractor’s name and telephone contact
numbers (including an after hours telephone number)
show the location of the site office for the project, if any
Are clearly visible from outside the workplace, or the work
area of the workplace, where the construction project is being
undertaken.
Work Health and Safety Regulation 2011 s.308
1.2 A written work health and safety management plan for the constr
uction project was prepared prior to work commencing.
Work Health and Safety Regulation 2011 s.309
1.3 So far as reasonably practicable, all workers carrying out constru
ction work on the project have been made aware of the content o
f the WHS management plan, including any updates, and their ri
ght to inspect the plan.
Work Health and Safety Regulation 2011 s.310 and s.311
1.4 The WHS management plan has been reviewed and, if necessar
y, revised to ensure it is up-to-date.
Work Health and Safety Regulation 2011 s.311
Ref Criteria Observations
2. Training, risk management, and general requirements
2.1 All workers carrying out construction work have received the general
construction induction training. Work Health and Safety Regulation 2011 s316
2.2 Workers have been informed of the site-specific health and safety rules.
Work Health and Safety Regulation 2011 s.310
2.3 Suitable and adequate information, training, and instruction has been
provided to workers in relation to work they are carrying out.
Work Health and Safety Regulation 2011 s.39
2.4 Control measures have been maintained and reviewed to ensure they remain
effective, fit for purpose, suitable, and set-up and used correctly.
Work Health and Safety Regulation 2011 s.37 and s.38
2.5 Personal protective equipment (PPE) has been provided to workers where it
is prescribed as a control measure. Work Health and Safety Regulation 2011 s.44
2.6 PPE is:
suitable for the relevant hazards
of suitable size and fit
Maintained such that it is clean and hygienic and in good working order.
Work Health and Safety Regulation 2011 s.44
7. Ladders
Ladders generally
Note: The criteria under this heading do not apply to trestle ladders.
7.1 Ladders have a load rating of at least 120kg and have been
manufactured for industrial use.
Work Health and Safety Regulation 2011 s.306M
7.2 Ladders are used only for the purpose for which they have been
designed. Work Health and Safety Regulation 2011 s.306M
7.3 Ladders are not used to support a weight greater than that for which
they have been designed.
Work Health and Safety Regulation 2011 s.306M
7.4 Note: This criterion does not apply to ladders used in confined
spaces.
Ladders are no longer than:
6.1m for single ladders
9.2m for extension ladders used to do electrical work within the
meaning of the Electrical Safety Act 2002
7.5m for other extension ladders.
Work Health and Safety Regulation 2011 s.306M
7.5 Ladders are used where the:
bottom of the ladder is on a stable surface
Rungs of the ladder are approximately level.
Work Health and Safety Regulation 2011 s.306M
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (3 point)
1. Which of the following criteria of site inspection check lists categorized under
administrative requirements.
A. Signs have been installed to show the principal contractor’s name and telephone
contact numbers
B. A written work health and safety management plan for the construction project was
prepared prior to work commencing.
C. All workers carrying out construction work on the project have been made aware of
the content of the WHS management plan.
D. All
2. Which of the following criteria of site inspection check lists categorized under Safe
work method statements
A. Each SWMS identifies the high risk construction work to which it applies
B. Each SWMS describes how control measures are to be implemented, monitored, a
nd reviewed.
C. Each SWMS states the hazards relating to the high risk construction work and
risks to health and safety associated with those hazards.
D. All
3. Which of the following criteria of site inspection check lists categorized under the work
environment
A. The workplace has sufficient ventilation to enable workers to carry out work without
risk to health and safety
B. Workers carrying out work in extremes of heat or cold are able to carry out work
without risk to health and safety.
C. Floors and other surfaces are designed, installed, and maintained to allow work to
be carried out without risk to health and safety.
D. All
4. Which of the following criteria of site inspection check lists categorized under electrical
A. Residual current devices are installed and tested regularly.
B. Work is conducted in a way that is electrically safe.
C. Electrical work is carried out by an appropriately licensed individual.
D. All
Answer the following question!
Note: Satisfactory rating 12 points Unsatisfactory below 12 points
You can ask you teacher for the copy of the correct answers.
Answer Sheet Score = ___________
Name: _________________________ Date: ______________ Rating: ____________
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (3 point)
1.________ is a document that states the company’s intentions for operating and
executing the processes within its quality management system.
A. Management system C. Procedure
B. Quality manual D. All
2. Quality manual can be used for several other important purposes such as___
A. To demonstrate the company’s plan to conform to the requirements of ISO
9001:2015
B. To provide a starting point for auditors, either internal, customer-affiliated, or the
ISO certification body.
C. To communicate management’s expectations to employees
D. All
3. Which of the following is the common topics included in quality manuals.
A. Quality policy
B. Explanation of the company’s documentation structure
C. Organizational chart
D. Reference to operating procedures
E. All
4. Quality manual sets the expectations for your team’s performance and for the caliber of
your deliverables.
A. True B. False C. None
You can ask you teacher for the copy of the correct answers.
Information Sheet 4. Arranging Local authority inspections.
You may make a Building Regulations application to your local authority building control
department if the electrician you employ to carry out notifiable work is not registered with one
of the relevant competent person schemes, or if you do the work yourself. You should
contact the local authority before you start the work and they will explain the requisite
procedures to you.
It is also best to discuss with the local authority how they wish to inspect and check the works
you are carrying out.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
A sample Specification for Electrical Construction Contract Works that describes General
Conditions and Requirements to accomplish electrical works all in conjunction with
Architectural, Civil, Mechanical and other services.
Codes and standards: All electrical equipment, materials, installation and workmanship
shall comply with the latest edition of the applicable codes and standards of any of these
organization listed below:
1. National Electric Code (NEC).
2. Underwriter laboratories (UL).
3. Institute of Electrical & Electronic Engineers (IEEE).
4. National Fire Protection Association (NFPA).
5. National Electrical Manufacturers Association (NEMA).
6. Insulated Power Cable Engineers Association (IPCEA).
7. American National Standards Institution (ANSI) and or BS code, IEE regulations or
any other approved equivalent standards.
2. Materials
All materials furnished under this specification shall be new and shall conform to any of
the standard such as Underwriters Laboratories, the American National Standards
Institute, the National Fire protection Association or BS or equivalent. Each major class of
equipment through out the installation shall be by a single manufacturer.
Catalogue and samples of all equipment and materials to be supplied under this
specification shall be submitted prior to installation for approval. Wherever applicable and
appropriate, the manufacturer’s test certificates shall be submitted for approval. The
contractor shall furnish all valid documents to show that the materials proposed to use in
the project are readily available, guaranteeing the availability of spare parts within the
Kingdom.
The drawings and specifications are intended to describe the work comprehensively, but
are not intended to be complete in every detail. Wherever reasonably implied by the
nature of the work, all materials shall be furnished and installed by the contractor as a
part of his contract work.
Any omissions from either the drawings or the specifications are unintentional and it shall
be the responsibility of the contractor to include all such items and to provide and install
all systems complete and in operable condition.
All contract drawings of any trade which may effect the location of any outlets, apparatus
& equipment shall be consulted to avoid possible interferences and permit full
coordination of all work.
All electrical equipment such as junction and pull boxes, panel boards, switches, controls
and such other apparatus as may require maintenance and operation periodically shall be
made easily accessible. Although the equipment may be shown on the drawings in
certain locations, the construction may disclose the fact that such locations do not make
its position readily accessible.
The contractor shall prepare detailed working drawings for approval to the Supervising
Engineer. These drawings shall comply with and complement the contract drawings to
the extent of showing the physical layout of all equipment, details of installations,
materials and methods. No changes shall be made without the prior approval of the
Supervising Engineer.
The contractor shall obtain manufacturers working drawings for all specialist items of
equipment such as distribution boards, panel boards etc. and submit them to the
Supervising Engineer for their approval before commencement of manufacture.
5. Record Drawings and Maintenance Manuals
On completion of the contract the contractor shall provide one set of record negatives on
heavy duty PVC reproducible film and three sets of dye line prints of the works as
installed. The drawings shall indicate the route and size of all conduits and cables
installed whether buried or surface fixed type and rating of luminaires, details of the
circuits used on all distribution board and the drawings showing all other services called
for, in the electrical section. Schematic contract drawings shall also be submitted
incorporating the details of any changes made during the contract.
The location and dimension of electrical equipment shown on plans shall be considered
as approximate and diagrammatic only. The contractor shall determine the exact location
to meet the field conditions, avoid interference with other equipment and services or for
other sufficient reasons.
The mounting heights of electrical equipment where not indicated or detailed on the
plans, shall be as noted below:
1. Convenience outlets, telephone outlets and television antenna outlets 300 mm
above finished floor to bottom of the box.
2. Light switches, push button station, selector switches and all other toggle or control
switches 1200 mm above finished floor to bottom of the box.
3. Panel boards for lighting, power, telephone and other auxiliary systems 2000 mm
above finished floor to top of panel.
4. Disconnect switches, service switches and individually mounted starters and
connector approximately 1500 mm above finished floor to center line.
5. Fire alarm pull station 1200 mm above finished floor to bottom of the box.
6. The mounting height for all equipment, except as noted shall be as recommended
by the equipment manufacturer.
7. All switches, socket outlets and any other power outlets in the kitchen and toilet
shall be mounted as 1200 mm above finished floor level.
TVET program title- On-site Building Version -1
Page 115 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
5.1.2. General Requirements for Electrical Earthling or Grounding System in
Building Construction
1. Earth electrode is to consist of one or more earth rods (also earth plate or earth
matt), interconnected by buried earthling tape or cable, which is to have a total
combined resistance value, during any season of the year and before
interconnection to other earthed systems or earthling means, not exceeding I ohm.
Distance between 2 rods is not to be less than 6 meters.
2. Main ring earthling resistance should not exceed 1 ohm.
3. Ring type earth electrode is to consist of earthling conductors, in a closed loop,
buried in exterior wall foundations underneath the water-proofing, or alternatively at
0.6 m around the perimeter of the building foundations, as shown on the Drawings.
Connect all earthling conductors to this ring. Insulated connection flags into the
building, of same material as earthling conductors, are to be located at positions of
service entrance and main switchboard rooms, terminating in bolt-type earth points
(studs) or test links for connection of main earth bar(s). Additional earth rods
connecting with the earth ring are to be provided, as necessary, to bring down
earth electrode resistance to an acceptable value.
4. Functional earth electrode is to be provided separately from, but interconnected
to, other earth electrode(s) through suitably rated (470 V) spark gap. Functional
earth electrodes are to be used for earthling electronic equipment (communication
equipment, digital processors, computers etc.) as required by the particular Section
of the Specification and recommendation of the manufacturer.
5. Alternative Earth Electrode: Other types of earth electrode may be used, after
approval, including:
1. Copper plate(s)
2. Tape mats (strips)
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (3 point)
1. Which of the following general requirement in electrical installation is about code and
standard that all electrical equipment, materials, installation and workmanship shall
comply with.
A. Requirements of regulatory C. Record Drawings and Maintenance Manuals
B. Manufacturer working drawing D. All
2. According to general requirement for electrical installation Light switches, push button
station, selector switches and all other toggle or control switches ____ mm above finished
floor to bottom of the box.
A. 1200 mm C. 1700 mm
B. 1500 mm D. 2000 mm
3. According to general requirement for electrical installation all switches, socket outlets
and any other power outlets in the kitchen and toilet shall be mounted as ____ mm above
finished floor level.
A. 2000 mm C. 1700 mm
B. 1500 mm D. 1200 mm
4. According to general requirement for electrical installation Convenience outlets,
telephone outlets and television antenna outlets _____ mm above finished floor to bottom
of the box.
A. 2000 mm C. 300 mm
B. 1500 mm D. 1200 mm
5. According to general requirement for electrical installation Panel boards for lighting,
power, telephone and other auxiliary systems____ mm above finished floor to top of
panel.
A. 2000 mm C. 300 mm
B. 1500 mm D. 1200 mm
TVET program title- On-site Building Version -1
Page 120 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
Part II: Fill the black space
1. Explain the seven Component parts of earthling system. (7 point)
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
____________________________________________________________________________.
You can ask you teacher for the copy of the correct answers.
Information Sheet 6. Processes on-site work supervises
It is not sufficient to stipulate that “supervision will be provided” without specifying the
detail of that provision. The client’s arrangements for managing the project and the risk
assessments for the project should stipulate the level and nature of the supervision
required.
Questions such as who will supervise, how supervision will take place, how much is
required and when need to be considered. Some workers and some activities will require
more supervision than others. For example:
young inexperienced workers may need very close and maybe constant
supervision
migrant workers with poor English language skills, or understanding of site safety
standards, may need additional supervision
High-risk activities will need to be closely monitored by supervisors.
Senior management must visibly support supervisors and their role. They must also show
positive commitment to site supervision through, for example, sufficient financial
investment in supervision.
Leadership
The Health and Safety Executive Research Report (RR) 367 concluded that there is a
positive correlation between attitudes and behaviors displayed by leaders and the
development of a safety culture and safety climate. Supervisors need to show leadership
and they need to set a good example to others in both their actions and attitudes.
Communication
Supervision can be important for achieving employee involvement, and often the
supervisor can be the link between workers and site management. This can lead to
improved health and safety standards on site.
Clear roles and responsibilities
If employees, supervisors and team leaders are not clear about their roles and
responsibilities this has the potential to adversely impact safety performance. The
supervisory arrangements therefore need to make these roles and responsibilities clear.
Supervisors need to be properly selected and, like all personnel on construction sites,
they need to be competent. This will involve some level of training. For example the
Construction Industry Training Board (CITB) offer a two-day training course for
construction site safety supervisors. The training needs to cover both the technical nature
of supervision and other skills such as leadership, communication and team working.
You can ask you teacher for the copy of the correct answers.
Information Sheet 7. Meet Contractual quality standards.
Contract quality requirements fall into four general categories, depending on the extent of
quality assurance needed by the Government for the acquisition involved.
1. Contracts for commercial items.
2. Government reliance on inspection by contractor.
3. Standard inspection requirements.
4. Higher-level contract quality requirements.
1. Contracts for commercial items.
When acquiring commercial items the Government shall rely on contractors’ existing
quality assurance systems as a substitute for Government inspection and testing before
tender for acceptance unless customary market practices for the commercial item being
acquired include in-process inspection. Any in-process inspection by the Government
shall be conducted in a manner consistent with commercial practice.
a. Except as specified in (b) of this section, the Government shall rely on the
contractor to accomplish all inspection and testing needed to ensure that supplies
or services acquired at or below the simplified acquisition threshold conform to
contract quality requirements before they are tendered to the Government .
b. The Government shall not rely on inspection by the contractor if the contracting
officer determines that the Government has a need to test the supplies or services
in advance of their tender for acceptance, or to pass judgment upon the adequacy
of the contractor’s internal work processes.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 2 point)
1. Requiring compliance with higher-level quality standards is necessary in solicitations
and contracts for complex or critical items or when the technical requirements of the
contract require:
A. Control of such things as design, work operations, in-process controls,
testing, and inspection; or
B. Attention to such factors as organization, planning, work instructions,
documentation control, and advanced metrology.
C. Management system standard
D. A & B are correct.
2. In higher level contract quality requirement Agencies shall establish procedures for
determining when higher-level contract quality requirements are necessary-
A. for determining the risk (both the likelihood and the impact) of nonconformance,
B. For removing quality.
C. For advising the contracting officer about which higher-level standards should be
applied and included in the solicitation and contract.
D. A & C are correct.
3. In making the determination for supply and services, the contracting officer shall
consider-
A. The nature of the supplies and services being purchased and their intended use
B. The potential losses in the event of defects
C. The likelihood of uncontested replacement or correction of defective work
D. The cost of detailed Government inspection
E. All F. B & D are correct
You can ask you teacher for the copy of the correct answers.
LG #58 LO #4. Complete project administration processes.
Instruction sheet
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics:
Carrying out Project administration processes and preparation for practical
completion.
Identify Practical completion inspection procedure.
Identify and carried out Handover procedures
Provide Certificates and appropriate client information at handover, including
Termite protection and appliance warranties.
Obtaining Defects liability items.
Rectifying Defects and obtaining client sign-off.
Conduct and supervise Administrative processes.
This guide will also assist you to attain the learning outcomes stated in the cover page.
Specifically, upon completion of this learning guide, you will be able to:
Carry out Project administration processes and prepare for practical completion in
accordance with the contract requirements and company policy.
Identify Practical completion inspection procedure, communicated to the client and
applied on site.
Identify Handover procedures and Carry out in accordance with organizational policy.
Provide Certificates and appropriate client information at handover, including termite
protection and appliance warranties.
Obtain Defects liability items from clients.
Obtain Defects are rectified and client sign-off.
Conduct Administrative processes and Supervise with reference to relevant
regulatory and organizational requirements.
Learning Instructions:
1. Read the specific objectives of this Learning Guide.
2. Follow the instructions described below.
3. Read the information written in the “Information Sheets”. Try to understand what are
being discussed. Ask your trainer for assistance if you have hard time understanding
them.
4. Accomplish the “Self-checks” which are placed following all information sheets.
5. Ask from your trainer the key to correction (key answers) or you can request your trainer
to correct your work. (You are to get the key answer only after you finished answering the
Self-checks).
6. If you earned a satisfactory evaluation proceed to the next “learning guide”.
7. If your performance is unsatisfactory, see your trainer for further instructions or go back to
Self-checks).
15) Backstabbed wires: The pushed wires at the back can be loose for new switches
than those anchored around screw terminals. This is not a code violation as it is allowed
for new constructions too. The risk occurs only when the loose wires are worst in case
otherwise it stops the switch from working. Check if your wires are backstabbed, if so,
release it and fix them to the respective screw terminals on the receptacle.
Switch is off
If the bulb is burned out
If RCCB (Residual Current Circuit Breaker) is tripped
In some situations, troubleshooting will be quite easy when it is the case of a switch or the
light bulb burned out. Many times, you may notice RCCB receptacle is tripped and the
tripped plug is behind a pile of boxes in a garage without even noticing that there is a plug
present there.
So let’s start troubleshooting
Be safe first
The project action items (PAI) list provides much more detailed information about what
you still need to do versus what you've actually done on a project. The bullet points below
describe how you might use a PAI form most effectively:
Job walks: Walk the job approximately every 200 man-hours, noting every detail you
can think of by room/area. Your primary tools should be a legal pad, clipboard, and
pen.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 2 point)
1. Project practical completion is reached when____
A. The building is usable for its intended purpose
B. All utilities(electrical, sanitary….etc.) are functioning
C. The project has achieved approval for use or occupancy
D. All
2. Once practical completion has been achieved, the contractor has no obligation to carry
out varied Work although an exception would be where the contract expressly provides
for issued variation after practical completion
A. True B. False C. None
3. Which of the following electrical problems occurred due to poor wiring in the house or
lightning strikes or faulty appliances or damaged power lines.
A. Electrical Surge C. Power sags and dips
B. Overloading D. All
4. Which of the following electrical problems occurred frequent burning out of light bulb
A. High wattage
B. Insulation is near to light
C. Poor wiring on circuit and mains
D. More wattage on a dimmer switch
E. All
5. It is very important to make sure of your safety while working with electrical problems
and solutions by applying_____
A. It is advisable not to work with energized wires or circuits.
B. Switch off the circuit and tag it to keep off so that other wont switch it on again
C. Before you test, insulate the wires with electrical tape if it is to be turned on.
D. All
1. Write down the things to be verify by carrying out initial inspection. . (4 point)
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________
2. Write down about eight items which must be covered in an inspection. (4 point)
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_____________________________________________________________________________
Where the installation cannot be isolated from the supply, the circuit protective
conductors and the equipotential bonding conductors must not be
disconnected from the main earthling terminal, as under fault conditions
extraneous metalwork could become live. Under these circumstances a
combination of inspection, continuity testing and earth loop impedance testing
should establish the integrity of the circuit protective conductors.
Polarity
Polarity tests should be carried out to check that:-
polarity is correct at the intake position and the consumer unit or distribution board
single pole switches or control devices are connected in the line conductor only
socket outlets and other accessories are connected correctly
center contact bayonet and Edison screw type lamp holders have their outer or
screwed contact connected to the neutral conductor
All multi-pole devices are correctly installed.
Where it is known that no alterations or additions have been made to the installation since
its last inspection and test, then the number of items to be tested can be reduced by
sampling.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 3 point)
1. A Practical Completion Inspection covers or deals with any evidence of the following at
the time of inspection
A. Safety hazards
B. Non-compliance building electrical work
C. Incomplete works
D. Substandard workmanship
E. All
2. It would not be practicable to inspect all parts of an installation; thus a random sample
should be inspected. This should include:
A. Checking that joints and connections are properly secured and that there is no sign
of overheating.
B. Checking switches for satisfactory electrical and mechanical conditions.
C. Checking that protective devices are of the correct rating and type; check for
accessibility and damage.
D. All
3. Which of the following tests can only be carried out where it is possible to safely isolate
the supply.
A. A. Continuity C. Polarity
B. Insulation resistance D. Earth fault loop impedance
4. A practical completion inspection also known as___________________
A. Start-up inspection C. Handover inspection
B. Resistance inspection D. A & B are correct
5. Earth-fault loop impedance tests should be carried out at:
A. the origin of each installation and at each distribution board
B. all socket outlets
C. At the furthest point of each radial circuit.
D. All
Answer the following question!
Note: Satisfactory rating 15 points Unsatisfactory below 15 points
You can ask you teacher for the copy of the correct answers.
Score = ___________
Rating: ____________
Answer Sheet
Name: _________________________ Date: ______________
TVET program title- On-site Building Version -1
Page 153 of 172 Federal TVET Agency
Electrical Installation -Level-IV
Author/Copyright February 2021
Information Sheet 3. Identifying and carried out Handover procedures
Warranty cover
The Supply of Extended Warranties on Domestic Electrical Goods Order requires traders
that supply extended warranties on domestic electrical goods to provide consumers with
certain information before the sale of an extended warranty.
A warranty provider may refuse to carry out repairs for a number of reasons – the most
obvious being that the warranty didn’t cover the particular problem in the first place.
Check the terms and conditions of the warranty carefully as these will show what is and
isn’t covered.
A common exclusion in a warranty document is for wear and tear, and a policy may or
may not cover accidental damage.
If a product fails prematurely it may not be covered if the failure is due to everyday wear
and tear.
What the law says about warranties
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 3 point)
1. According to building code of Australia requires that the following areas be treated
against termite infestation:
A. roof and floor framing (structural elements)
B. door jambs
C. window frames and reveals
D. All
2. Which of the following is the material that is termite resistant.
A. Treated timber C. Steel
B. Masonry D. Concrete E. All
3. ________is and agreement without any extra charge to repair, replace or offer a refund
on goods which do not meet the specifications in the guarantee.
A. Appliance C. Change
B. Guarantee D. Termite
4. A common exclusion in a warranty document is for wear and tear, and a policy may or
may not cover accidental damage.
A. True B. False C. None
When the electrical work (including new installation, addition, alteration and repair) is
completed, the qualified building services engineer and registered electrical contractor
should inspect and test the electrical installations and certify that the installations are safe
and comply with the safety requirements of the Electrical Ordinance stated in the Work
Completion Certificate.
Notice may be served for lack of repair, maintenance and test and to request an owner to
rectify any problem associated with an electrical installation in a building so as to ensure
electrical safety.
Client sign-off
Sign-offs are an indication that stakeholders agree with and approve the requirements that
have been elicited and documented. Though they provide a detailed view of requirements
and consistent expectations of what the final solution will deliver, obtaining formal sign-off
is important because it signifies the official end of a project or completion of a
deliverable and the acceptance of the product by the customer (internal or external).
While the process is not a complicated one, it is an essential step in ensuring customer
satisfaction. Sign-off sheets are one of those key pieces of documentation that are
essential to any Creative process for keeping a record of what’s been agreed upon,
where the project is in its course of development, and whether or not all parties are
in agreement with the final result.
2. Project Goal
Were project goals met?
3. Project Deliverables
5. Document Signatures
7.1 Conducting and supervising Administrative processes for project close out.
Project Closeout.
The project closeout process should include a combination of onsite and administrative
tasks. Site closeout is customarily coordinated by the general contractor (GC).
Onsite Project Closeout Checklist
Onsite Project Closeout Checklist should include the following tasks:-
Complete all punch list items. It is all-too-typical on most projects that the GC has to push
subcontractors to finalize their work in the field. Generally, punch list completion is verified
by the project architect.
Demobilize all contractors’ job storage/ trailers, temporary facilities and equipment
including temporary power poles and lavatory facilities from the work site.
Deliver, organize and store attic stock (contractually required surplus materials) such as
roofing, tile, HVAC filters, ceiling tile, etc.
Ensure that permanent utilities are installed, tested and working and all project-related
services and contracts, i.e., phone, water, power, gas and internet services are cancelled.
Ensure the site is completely clean and ready for occupancy.
Ensure all owner training of systems has been completed.
The goal of administrative closeout procedures and project contract management is to confirm
that all contractual terms have been satisfied, closeout documents provided and payments
have been made by the contractor to all the subcontractors and material suppliers. While
deliverables vary with each owner’s particular needs, the goal is to provide a transparent and
organized handoff of the project to the owner, including any information or documents they
may need in the future for reference.
A successful closeout process is not complete until final and complete payments are made,
final retainage is released, permits closed out and all parties are satisfied.
The project sponsor’s administrative procedures for retaining hard copy signatures or physical
stamps, as well as the handover of information to regional offices, should be considered at
this stage. In closing the project accounts (and all related financial cost centers), care must be
taken to store all financial records securely, as required by applicable financial management
procedures.
Generally at this stage, the project sponsor will release the final retention payment to the
contractor, in accordance with the contractual arrangements made without contention and
without opportunity for the client to delay payment by argument. No item of claim should be in
dispute at final account time.
This is also the time to ensure that all handover items such as warranties as-built, tagged
keys, and maintenance and operation manuals are completed and passed on to the client.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
Part I. Choose the best answer (each 3 point)
1. ________________should include a combination of onsite and administrative tasks.
A. Project start-up C. Project Close out
B. Checklists D. All
2. Which of the following is the task which included in on site project close out check list.
A. Complete all punch list items.
B. Demobilize all contractors’ job storage/ trailers, temporary facilities and equipment
C. Deliver, organize and store attic stock
D. Ensure the site is completely clean and ready for occupancy.
E. All
3. Which of following is a checklist of administrative tasks and documents to consider
during Project Closeout:
A. Review all contractual requirements and ensure that all terms have been met.
B. Review all change orders to ensure all have been accounted for and either voided,
rejected or completed.
C. Obtain any outstanding insurance and maintenance bonds, to the extent required
by contract.
D. All
4. A successful closeout process is not complete until__________,
A. final and complete payments are made
B. final retainage is released,
C. Permits closed out and all parties are satisfied.
D. All
5. Site closeout is customarily coordinated by the general contractor (GC).
A. False B. True C. None
Answer the following question!
Note: Satisfactory rating 15 points Unsatisfactory below 15 points
You can ask you teacher for the copy of the correct answers. Score = ___________
Rating: ____________
Answer Sheet
Name: _________________________ Date: ______________
1. https://www.powerdms.com/blog/regulatory-compliance-important/
2. https://www.ejcdc.org/construction-contract-documents/
3. https://www.betterteam.com/electrical-engineer-job-description
4. https://en.wikipedia.org/wiki/Environmental_standard
5. https://www.rwb.net/blog/plan-and-spec-explained/
6. https://www.osha.gov/Publications/consultation_kit/Prog_Ins.pdf
7. http://www.legalserviceindia.com/legal/article-1127-different-concepts-of-
wages.html
8. https://constructionblog.autodesk.com/as-built-drawings/
9. https://www.eresourcescheduler.com/blog/9-must-haves-for-project-managers
10. https://www.ecosys.net/knowledge/project-cost-management/
11. https://www.jobhero.com/job-description/examples/administrative/procurement-
administrator
12. https://en.wikiquote.org/wiki/Principles_of_administration
13. https://www.augustaga.gov/DocumentCenter/View/553/Article-4---Product-
Specifications?bidId=
14. https://electrical-engineering-portal.com/inspection-electrical-installations-home-1
15. https://whatis.techtarget.com/definition/quality-control-QC
16. https://www.qualityengineersguide.com/how-to-control-materials-and-delivery-to-
the-construction-site
17. https://prismic-io.s3.amazonaws.com/teachingesquemas/cd6d45fb-5525-40ec-
9d43-7c33a8369716_residential-electrical-inspection-checklist-template.pdf
18. https://www.togetherabroad.nl/electrical-instrumentation-QC-inspector-job-
description-template.html
19. https://stonemarkcm.com/blog/construction-management-closeout-procedures-
processes/
20. https://hbisw.com/practical-completion-inspection
21. Testing and Commissioning of electrical installation, NV03 electrical installation.
22. https://www.hpw.qld.gov.au/__data/assets/pdf_file/0009/3204/cwmfhandover.pdf
23. https://www.kenziegroup.co.uk/variation-after-practical-completion/
24. https://www.electricveda.com/building-services/general-conditions-and-
requirements-in-electrical-construction-contract