Appendix A Solutions to Self-Test Questions and Problems A-15
CHAPTER 12
ST-2 a. Estimated investment requirements:
Price ($55,000) Installation (10,000) Change in net operating working capital (2,000) Total investment ($67,000) b. Depreciation schedule: Equipment cost $65,000; MACRS 3-year class YEARS 1 2 3 MACRS depreciation rates 33% 45% 15% Equipment depreciation expense $21,450 $29,250 $9,750 Note that the remaining book value of the equipment at the end of the project’s life is 0.07 $65,000 $4,550. c. Terminal cash flow: Salvage value $10,000 Tax on salvage valuea (2,180) Net operating working capital recovery 2,000 Termination cash flow $ 9,820 a Sales price $10,000 Less book value 4,550 Taxable income $ 5,450 Tax at 40% $ 2,180 Book value Depreciable basis Accumulated depreciation $65,000 $60,450 $4,550 d. Net operating cash flows: Year 1 Year 2 Year 3 Revenues (4,000 $50) $200,000 $200,000 $200,000 Variable costs (70%) 140,000 140,000 140,000 Fixed costs 30,000 30,000 30,000 Depreciation 21,450 29,250 9,750 EBIT $ 8,550 $ 750 $ 20,250 Taxes (40%) 3,420 300 8,100 NOPAT $ 5,130 $ 450 $ 12,150 Add back: Depreciation 21,450 29,250 9,750 Operating cash flow $ 26,580 $ 29,700 $ 21,900 e. Project cash flows: 0 11% 1 2 3
Operating cash flows 67,000 26,580 29,700 21,900
Terminal cash flow 9,820 Project cash flows 67,000 26,580 29,700 31,720 f. From the time line shown in part e, the project’s NPV can be calculated as follows: NPV $67,000 $26,580/(1.11)1 $29,700/(1.11)2 $31,720/(1.11)3 $4,245 Alternatively, using a financial calculator, you would enter the following data: CF0 67000; CF1 26580; CF2 29700; CF3 31720; I/YR 11; and then solve for NPV $4,245. Since the NPV is positive, the project should be accepted. g. Project analysis if unit sales turned out to be 20 percent below forecast: Initial projection 4,000 units; however, if unit sales turn out to be only 80 percent of forecast then unit sales 3,200. A-16 Appendix A Solutions to Self-Test Questions and Problems
$13,350 Alternatively, using a financial calculator, you would enter the following data: CF0 67000; CF1 19380; CF2 22500; CF3 24520; I/YR 11; and then solve for NPV $13,350. Since the NPV is negative, the project should not be accepted. If unit sales were 20 percent below the forecasted level, the project would no longer be accepted. h. Best-case scenario: Unit sales 4,800, Variable cost % 65%.
$39,434 Alternatively, using a financial calculator, you would enter the following data: CF0 67000; CF1 40980; CF2 44100; CF3 46120; I/YR 11; and then solve for NPV $39,434. Base-case scenario: The NPV was calculated in part f as $4,245. Worst-case scenario: Unit sales 3,200; Variable cost % 75%.