You are on page 1of 12
Turner & Townsend HOME / PERSPECTIVES xX in B How data can improve pharmaceutical construction project performance 38 January 2021 Turner & Townsend Despite this, ‘big pharma’ companies have been unable to significantly increase new drug output over the past decade. Drug approval in the world’s largest pharmaceutical market, the USA, continues to average at around seven to 12 years, and the estimated average cost of taking a new drug from concept to market is about $1.3 billion USD. The momentous time and cost pressure within the pharmaceutical industry is putting project capital spend under the microscope, ‘There are growing calls from executives, shareholders and governments to drive greater efficiencies and savings which can be passed onto consumers through lower drug prices. However, increased pressure is not being met with improved construction pe-formance. Both from our own project experience and analysis of publicly reported projects, we estimate 70 percent of pharmaceutical construction projects miss their original budget target by around 15 percent on average, with delays of about four months on a typical three year project schedule. Finding answers in the data Data analysis enables us to diagnose the reasons why construction projects for pharmaceutical companies so often miss thelr mark ‘Through the benchmarking of pharmaceutical manufacturing projects we have supported across the US, Europe and Asia, we have grouped together where time, effort and capital's being expendes (see figures one and two below). What the dataset has illustrated is a broad range of results, exposing the lack of industry standardisation. os mutumernsoneandcoenprpaivenouci-an.npovegharraesis castro paomarce! ane Turner & Townsend Less haste, more speed Speed to market will always be the overriding driver for pharmaceutical companies which need to get a faciity into operation so they can start to manufacture products. This is especially true for our clients currently producing COVED-19 vaccines at an Unprecedented pace However, when it comes to the development of manufacturing space, the need for speed causes a propensity to rush through the early planning stages and an over reliance upon internal benchmarks of past project performance, ‘embark ont Issues typically start to arise during the conceptual phase of a project. At this stage, companies too ofte requesting capital funding while neglecting the importance of conceptual estimate validation, as well as comprehensive quantitative cost and schedule risk analysis. e process of ‘This means that well into the basis of the design phase, project teams find themselves measuring their performance on estimates and plans that reflect wreng assumptions, and inevitably result in an increase in engineering costs. Lack of intervention from project controls and proper benchmarking at an early stage of projects frequently leads to changes in scope during the design phases. Such changes make it dificult to determine @ procurement strategy reflective of the true project scope and the construction team is left to absorb project delays, causing sometimes severe cast overruns. os mutumernsoneandcoenprpaivenouci-an.npovegharraesis castro paomarce! ane Turner & Townsend Inthe Gataset provided, the schedule duration ranges are Drocen into the project phases wat we typrcaly see on medium ang farge~ scale pharmaceutical construction projects (see figure one). Typically, the consequences of poor-up front planning play out most strongly during the back end of the project, during the commissioning, qualification and validation phase (CQV). ur data Indleates the CQV phase typically ranges from three to ten percent of the project cost, but encompasses up to 40 percent of the schedule. This is particularly due to the operational qualification and validation stage, where there is extensive Interaction with organisations outside of the construction project team to coordinate approvals, tral runs and significant decumentation, causing @ drop in productivity. ‘Any schedule slippage in the early phases of the project typically resu in attempted acceleration of CQV, with significant additional resource added to the project. Extra resource doesn't necessarily save time, however, because more consideration needs to be given to the constraints of the equipment availability (i.e. equipment usage dictates speed more than extra people) Rather than trying to salvage a project schedule in its latter phases, investment should be weighted more heavily to pre~ planning and throughout the design and construction phases. os mutumernsoneandcoenprpaivenouci-an.npovegharraesis castro paomarce! ane eames ear naied up-front plannin Figure 1: Global schedule benchmarks os mutumerntonandcoenprpaivehouci-an.npovegharraeiis cata poe patomarce! sina Average 10% Basic design Aver 24%6 Detail design = Construction ss Startup and commissioning Average: 105% Qualification wera 4% Validation AAAAAA Minimising cost risks os nmutumernsonandcaenprpaivenoucis-an.npovegharrae is cat pospatomarce! oe Turner & Townsend Too often, more time and resources than anticipated end up being @ spent on the utility work to create the veins of the building. Any changes to an MEP system can have an adverse impact if it is not built into the risk-based contingency. This risk once again highlights the crucial need for proper planning and scope review during the early engineering phase. ‘Through the use of benchmarking and third party estimate reviews, we have created a robust package of data that enables leadership groups to determine if their business case and both the time and cast are worth the investment Figure 2: Global cast benchmarks os mutumerntonandcoenprpaivehouci-an.npovegharraeiis cata poe patomarce! na Turner & Townsend vera: 2% Engineering Construction management (Labour and fee) General conditions verge 205% Process equipment / process piping 2 verge 59% Clean / process utilities oe Avera 78% Mechanical, electrical and e- plumbing (MEP) nora 5% Givil structural architectural e Sos ‘VVVVVVV AAAAAAA os muturerntonaandconenprpaivenoucis-an.npovegharnace is castro pamare! ane Turner & Townsend average Commissioning and qualification > Qe em

You might also like