Professional Documents
Culture Documents
Phase 1 Program
Operations and Maintenance
Report
March 2016
TRANSBAY TRANSIT CENTER PROGRAM
March 2016
Prepared by
ISES Corporation
for the
Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
CONTENTS PAGE
1 Introduction ........................................................................................................................... 1
1.1 Phase 1 Program Description .......................................................................................... 2
1.2 Objective ........................................................................................................................ 3
1.3 General Assumptions and Limitations ............................................................................ 3
Figures
1-1 Project Area with Program Components ................................................................................... 1
Tables
1-1 Program Components ............................................................................................................... 2
2-1 Transbay Transit Center Tenants & Stakeholders...................................................................... 5
2-2 Insurance Coverages ................................................................................................................ 6
3-1 Maintenance Staffing Summary ................................................................................................ 9
3-2 Groundskeeping Estimate Summary ....................................................................................... 10
3-3 Janitorial Estimate Summary .................................................................................................. 11
3-4 Utility Consumption Estimates ............................................................................................... 13
3-5 Service Contracts Costs .......................................................................................................... 14
3-6 Service Contracts Costs Years 1-2 .......................................................................................... 14
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page iii of v Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
Appendices
A.1 Maintenance Estimate – Phase 1 .......................................................................... A.1-1
A.2 Maintenance Estimate – Phase 1 Transit Center .................................................. A.2-1
A.3 Maintenance Estimate – Phase 1 Bus Ramp ........................................................ A.3-1
A.4 Maintenance Estimate – Phase 1 Rooftop Park .................................................... A.4-1
A.5 Maintenance Estimate – Phase 1 Bus Storage Facility ......................................... A.5-1
A.6 Preventive Maintenance Estimate ........................................................................ A.6-1
A.7 Preventive Maintenance Instructions ................................................................... A.7-1
A.8 Corrective Maintenance Estimate ........................................................................ A.8-1
B.1 Groundskeeping Estimate – Phase 1 .................................................................... B.1-1
B.2 Groundskeeping Estimate – Phase 1 Transit Center ............................................. B.2-1
B.3 Groundskeeping Estimate – Phase 1 Bus Ramp ................................................... B.3-1
B.4 Groundskeeping Estimate – Phase 1 Rooftop Park .............................................. B.4-1
B.5 Groundskeeping Estimate – Phase 1 Bus Storage Facility ................................... B.5-1
C.1 Janitorial Daily Task Estimate ............................................................................. C.1-1
C.2 Janitorial Projects Estimate – Phase 1 .................................................................. C.2-1
C.3 Janitorial Projects Estimate – Phase 1 Transit Center .......................................... C.3-1
C.4 Janitorial Projects Estimate – Phase 1 Rooftop Park ............................................ C.4-1
C.5 Janitorial Projects Estimate – Phase 1 Bus Storage Facility ................................. C.5-1
D Phase 1 Facilities Renewal Needs Estimates........................................................... D-1
E Uniformat II Elements ............................................................................................ E-1
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page iv of v Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
Executive Summary
This document is an excerpt from the Operations & Maintenance study for the Transbay Transit Center
Program (Program) prepared by ISES Corporation in cooperation with the Program
Management/Program Controls Consultant for the Transbay Joint Powers Authority (TJPA). This
excerpt focuses on projected operations tasks, service levels, and staffing requirements for Phase 1
operations.
The report includes many assumptions necessary to estimate the level of care likely to coincide with the
facilities’ expected use as they relate to the TJPA’s desired level of performance, reliability or
cleanliness. Many of these assumptions are shown in Section 3 of this report. Overall, it is envisioned
that a systematic, continuous improvement process based on tracked performance will be in place.
Performance is envisioned to be relatively good to excellent in most areas, and data is to be collected
systematically, where applicable, to support management decisions. Following are brief descriptions of
performance in relevant facets of operations.
Maintenance services have been estimated to optimize purchased utilities, maintenance labor and
materials, component renewal or replacement cycles, and component up-time. Lower costs for all of
these facets are desirable; this can be accomplished through a comprehensive preventive maintenance
program consisting of largely routine maintenance activities as well as inspection activities that
proactively yield corrective maintenance work orders. Such a program envisions that all completed
work orders be associated with a building component or asset. Through diligent maintenance and
tracking processes, the need for costly emergency maintenance can be mitigated, component
replacement cycles maximized, utility consumption optimized, and component down-time minimized.
Janitorial services are expected to require a high level of staffing due to the Transit Center’s function
as a passenger terminal situated in a major employment center in downtown San Francisco. In addition
to transit services, the facility will host offices, retail space, and a 5.4-acre park with event space. The
janitorial approach includes daily services to the common areas as well as bus and program spaces that
are accessed by the public. The common areas include public restrooms, stairwells, lobbies, alleys, and
retail concourses. In short, the level of appearance sought by the estimate in this report is orderly and
tidy.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page v of v Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
1 Introduction
The Transbay Transit Center Program (Program) is a $4.5 billion program to replace the former
Transbay Terminal at First and Mission streets in San Francisco with a modern regional transit hub that
will connect eight Bay Area counties and the State of California through eleven transit systems:
Alameda–Contra Costa Transit, BART (Bay Area Rapid Transit), Caltrain, Golden Gate Transit,
Greyhound, Muni (San Francisco municipal bus lines), SamTrans (San Mateo County Transit),
WestCAT (Western Contra Costa Transit) Lynx, Amtrak, Paratransit, and high-speed rail from San
Francisco to Los Angeles/Anaheim.
The Program will be constructed in two phases. Phase 1 includes design and construction of the above-
grade portion of the Transit Center including the Rooftop Park, the structure and core of the two below-
grade levels of the train station, Bus Ramp, and Bus Storage Facility. The Downtown Rail Extension
(DTX) tunnel, the build-out of the below-grade train station facilities at the Transit Center, the Fourth
and Townsend Street Station, and an Intercity Bus Facility will follow as Phase 2 of the Program. Each
of these components is described further in Section 1.1. This excerpt focuses on Phase 1 operations.
Completion of Phase 1 is planned for late 2017.
Figure 1-1 shows the Transbay Transit Center with respect to other elements of the Program.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 1 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
The Transbay Joint Powers Authority (TJPA) oversees the design, construction and operations of all
Program components. ISES Corporation, as part of the TJPA’s Program Management/Program
Controls team, undertook this Operations & Maintenance study to provide the TJPA with a
comprehensive task-level assessment of operations and maintenance activities.
Table 1-1 outlines the analyzed components of Phase 1 of the Program as well as the associated
enclosed areas.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 2 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
The Bus Deck directly above the Second Level will serve AC Transit, Muni, and WestCAT
Lynx bus services, as well as Greyhound and Amtrak until the completion of an intercity bus
facility in Phase 2. The Bus Deck will connect directly to the new bus ramp that will lead to
the San Francisco–Oakland Bay Bridge and an off-site Bus Storage Facility
The Rooftop Park—over five acres of landscaped outdoor space atop the Transit Center—will
contain a variety of recreational spaces and amenities including a café, a restaurant, a
children’s play area, and an amphitheater.
The Train Box—the core and structure of the Lower Concourse and Train Platform levels,
will be constructed in Phase 1; this work includes the fit-out of some operation spaces on
those levels.
Bus Ramp
The Bus Ramp is a series of aerial structures and at-grade roadway that will connect the Bay Bridge to
the Transit Center and the Bus Storage. The Bus Ramp will be used only by bus transit agencies
operating service across the bay. Inbound buses will exit the Bay Bridge at the Fremont Street Off
Ramp, merge onto the Bus Ramp at a point near Harrison Street, and enter the Transit Center at the
elevated Bus Deck level. In the outbound direction, the alignment will bifurcate so that one ramp leads
to the Bus Storage Facility via a bus link ramp, and the other to the eastbound deck of the Bay Bridge.
A turnaround in the inbound direction provides direct access to the bus link ramp and Bus Storage
Facility.
1.2 Objective
This study provides some guidance regarding level of service and maintenance procedures that can be
adopted as part of the future operations plan for the facility. Finally, the information presented herein
will aid the TJPA in the selection and refinement of a future management strategy for the facility
commensurate with its role as a future civic and neighborhood landmark.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 3 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
This study estimates annual staffing needs attributable to a baseline level of performance for the future
Transit Center and its related infrastructure. The baseline condition has been characterized as the
ordinary servicing requirements for all public spaces and transit tenant uses of the completed facility,
including use by the TJPA; this includes upkeep and maintenance of all the building’s functional
elements intended to serve these uses.
Because the future Transit Center will be put into operation in phases, the estimates for future operation
and maintenance needs have been differentiated by phase. This excerpt focuses on Phase 1 operations.
The procedure used to prepare the estimates presented in this study follows the task approach. For all
activity-based maintenance, janitorial and groundskeeping efforts, design documents and reference
materials were used to assemble an itemized task-level model for the facility under programmed use.
Supporting the task level approach, each activity has been paired with a labor classification needed to
perform the task and rates of completion for similarly performed work. Except where specifically
developed or adapted to conditions unique to the Transit Center's design or use, activity data has been
gathered and applied from industry resources and publications. Activity data includes labor
classifications, trade, materials and equipment needed to perform the maintenance task.
Several other updated resources provided by the TJPA were consulted for the development of certain
estimates. In many instances, multiple sources were used to evaluate the various functional areas of the
design.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 4 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
TENANT ABBREVIATION
Amtrak AMTRAK
Greyhound GREYHOUND
Operation of the Rooftop Park, excluding insurance, will be partially funded by the Greater Rincon Hill
Community Benefit District (CBD), which was established in 2015. The Greater Rincon Hill CBD will
provide nearly 80 percent of the funding required for operation and maintenance of the Rooftop Park.
The Greater Rincon Hill CBD Owners’ Non-Profit Association Board of Directors will review the
operations and maintenance budget for the Rooftop Park and the calendar of events held on the Rooftop
Park. Specific information about the Greater Rincon Hill CBD can be found in the Greater Rincon Hill
Community Benefit District Management Plan and Engineer’s Report at www.rinconhillcbd.org.
2.3 Insurance
During the course of this study, estimates were obtained to reflect the likely annual costs to insure the
TJPA for property loss or damage, general liability, and loss or damage and liability extending from a
terrorism event. These estimates were provided following consultation with Alliant Insurance Services
and R. K. Harrison Insurance Brokers, Ltd. These estimates provide a very rough indication of the cost
to secure the stated coverage on an annual basis, under current conditions in the market for similar
protections. It should be noted that actual costs may be different, owing to year-to-year volatility in the
availability of insurance products and assumed market capacity at a future date.
All-risk property insurance for the full phase-completion replacement cost, less the $1,000,000
deductible, has been quoted. The estimated insurance products and coverages are listed in Table 2.2.
Premiums have been estimated based on construction cost estimates prepared for the TJPA by Pelli
Clarke Pelli Architects.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 5 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
All-risk and terrorism coverage reflect recommended basic insurance against damage and loss of use
resulting from most insurable events, with the exception of flood and earthquake. Market capacity for
terrorism coverage may be limited or unavailable at the time the policy is requested, and the estimates
represented herein reflect current market conditions. These estimates are a non-binding baseline
reference prepared by Lloyd’s of London reflecting the future Transit Center’s likely attraction to
terrorism events and recommended level of coverage from a range of protections currently offered.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 6 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
3 Staffing Analysis
3.1 Maintenance
Appendix A contains the counts, measurements and calculations utilized to develop the maintenance
staffing estimate. Appendix A.1 contains a summary of the estimates by trade for Phase 1. Appendices
A.2 through A.5 contain summaries of the estimates by Program component. Appendix A.6 outlines the
preventive and routine maintenance portion of the estimate. Appendix A.7 details the scheduled
preventive and routine maintenance activities. Appendix A.8 shows the corrective or unscheduled
maintenance component of the estimate. The preventive and corrective maintenance estimates are
organized using the ASTM Uniformat II taxonomy. Appendix E contains an outline of pertinent
Uniformat II elements.
All maintenance estimates are broken out by the structure outlined in Table 1-1. Notable systems
designed into the Program facilities are as follows:
Perforated metal awning surrounding the Bus Deck level of the facility – this is essentially a
screen wall. It is, however, a low maintenance application.
Graywater Reuse System, which includes water treatment, filtration, pumps, tanks, piping,
etc.
Geothermal HVAC system that utilizes underground temperatures to chill condenser water
for the building cooling medium in the warm months and heat the condenser water for
building heating in the cold months. This process is facilitated by water-to-water condensers,
heat exchangers and water-source heat pumps. There are no boilers or chillers serving this
facility.
High capacity diesel-fired emergency generators with fuel delivery systems
Public Art displays that will require maintenance include an LED display exhibit, Shaw Alley
lighting, Rooftop Park fountain, Mission Square sculpture installation, and the Grand Hall
terrazzo floor.
Wayfinding signage
Digital signage and scheduling board
Electrified bird control systems
Bus Ramp traffic signaling and lighting systems
For the purposes of developing this report, it is envisioned that a level of service will be provided in
which maintenance activities are organized and strategically managed. Equipment and building
components are typically observed to be in good working order. The organization is responsive to
customer calls per the vision outlined in the stationary staff responsibilities. Building components are
upgraded when economically feasible, which, in effect, increases the effectiveness of the maintenance
organization.
The building maintenance estimate presented in this report envisions a single maintenance shop located
on the grounds of the Transit Center. This shop will be managed via the aforementioned fixed-term,
qualifications-based competitive solicitation. The shop is envisioned to consist of the following trades:
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 7 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
The contracted stationary maintenance organization is envisioned to make their stationary maintenance
staff responsible for the following:
Periodic operational tours and checks
Administration of applicable service contracts
Response to emergency requests and conditions (within thirty minutes)
Response to urgent requests (within four hours)
Response to routine service requests (within twenty-four hours)
Completion of all work orders within five work days, except when waiting on materials (most
work orders will take less than four hours to complete)
Completion of minor projects, depending on scope, required expertise, labor availability and
other factors
Preventive maintenance tasks
Work orders that will require more than four hours to complete, although the maintenance
staff may complete maintenance projects that are longer that four hours in duration
Specialty trades will also be required to apply service at the Transit Center. Trades estimated to be
needed but not necessarily stationed at the Transit Center include the following:
Carpenter – responsible for carpentry projects beyond the scope of the stationary Generalist
but not full renovation efforts
Fire Alarm Technician – responsible for maintenance of fire alarm and security systems
Fire Protection Plumber – responsible for maintenance of fire suppression systems
Generator Mechanic – responsible for maintenance of emergency generators and associated
appurtenances, such as diesel fuel storage and delivery systems and automatic transfer
switches
Glazier – responsible for repair or replacement of interior and exterior glass finishes
Mason – Responsible for projects pertaining to brick or other masonry finish systems
Painter – responsible for painting projects beyond the scope of the stationary Generalist but
not full renovation efforts
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 8 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
Preventive and corrective maintenance tasks and time estimates (Appendix A.6 through A.8) are based
on time standards applied to a building-specific component list, modified for size or difficulty of work.
Each preventive maintenance task has an assigned shop.
The standards for maintenance materials and supplies include daily operational, preventive and repair
maintenance. The standards include all aspects of maintenance (i.e., mechanical, structural, building
systems, exterior and roofs). The standards include locks, cores, key materials and similar items for the
locksmith function but do not include major rekeying or replacement of cylinders or cores. The
standards are intended to provide a budgeting figure for daily, routine operational and repair
maintenance.
Daily maintenance staffing needs are estimated for Phase 1 of the Program as outlined in Table 3-1.
Please see Appendix A for more detail.
TOTALS 10.3
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 9 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
It is estimated that the Transit Center will be operated 24 hours a day, 7 days a week. There are three
available shifts during each day. A potential distribution for these shifts is:
Day Shift 7 am to 3 pm
Evening Shift 3 pm to 11 pm
Night Shift 11 pm to 7 am
Over the course of the year, a full time equivalent employee (FTE) averages being available for four 8-
hour shifts per week. In this case, 5 to 6 FTEs are needed in a single craft position to have full coverage
for 24/7 operation. The transient staff craft positions are not needed on a shift basis since they are
performing specialized and mostly scheduled work; they are not typically located onsite but rather at a
central location or are mobile. Some of the transient staff craft positions show 0.0 FTE needs. Work
will be required of such crafts. However, the projected annual hours are so few that they result in a
negligible FTE count.
The only stationary craft position where 100% coverage will be available is in the Generalist position.
The Generalist should be available for 24/7 coverage beginning in Phase 1. It is recommended that the
Generalist position be staffed such that a Generalist is capable of being a first responder in case of
emergency during the night shift. At most, there would be 2 Generalists on site during each day and
evening shift, and 1 on the night shift.
The remaining stationary positions do not need to be available for 24/7 coverage. The remaining
potentially stationary staff positions total around 1 FTE each. The HVAC Technician and the Mechanic
can be combined into 1 FTE and the Plumber and Electrician positions equate to a need for
approximately 1 FTE; this would indicate that, during most weeks, these positions would only be
present during the day shift.
In summation, a typical day shift at the Transit Center at full operation would consist of 1 electrician, 1
to 2 Generalists, 1 HVAC/Mechanic and 1 Plumber, in addition to transient positions responding to
specialized emergency calls and performing regular testing and maintenance of specialized systems.
It should be noted that the retail tenant space identified as shell space in the current design is not
included in this report.
3.2 Groundskeeping
Appendix B contains the calculations incorporated into the groundskeeping staffing estimates. Table 3-
2 summarizes the groundskeeping estimates:
Appendix B.1 outlines the Phase 1 activities and associated time estimates. Appendices B.2 through
B.5 contain summaries of the estimates by Program component.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 10 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
The Rooftop Park represents the largest groundskeeping load within the Program. The Transit Center
ground level landscaping is limited to maintenance of planters, including associated irrigation services.
Time has been included to pressure wash or otherwise clean the sculpture in Mission Square. There is
also minimal landscaping and low-maintenance landscaping at the Bus Storage Facility. For all areas,
exterior graffiti removal has been assigned to the groundskeeping entity.
Roadway (Bus Plaza, Deck and Ramp paving) sweeping is envisioned to be managed by the Master
Lessee such that this task is performed during off hours on a daily basis. Other paving surfaces are
assumed to be periodically either brushed or pressure washed manually per the detailed estimate.
The service level envisioned in this groundskeeping estimate is similar to that which is typically
applied to well-developed public areas such as malls, government grounds or college/university
campuses. Turf grass is cut roughly once per week during the growing season. Weeding, fertilization
and aeration are periodically performed on turf. Environmentally friendly fertilizer is periodically
applied to all plantings such that they are healthy and growing vigorously. Fertilization schedules
should be applied per plant needs. Soils should be amended periodically per local needs. Disease and
insect issues should be mitigated and/or eliminated promptly upon first observation in an
environmentally friendly manner. Irrigation systems should be diligently managed and maintained. The
maintenance needs are estimated in the maintenance section of this report. Public exterior spaces
should be policed regularly, and litter diligently controlled. Benches, tables, etc., should be refinished
and repaired periodically.
Note that a service contract has been secured for the first two years of Rooftop Park groundskeeping.
ROOFTOP PH1
PH1 TTC PARK BSF SUBTOTAL
Net Cleanable SF 189,176 1,904 1,460 192,540
Appendix C contains the counts, measurements, and calculations utilized to develop the janitorial
staffing estimates. Appendix C.1 shows the daily routine cleaning estimate based on the finish
materials designed or anticipated to be designed into the facility. Appendix C.2 outlines Phase 1
cleaning projects. The floor cleaning project is based on the projected floor coverings. Other cleaning
projects are also listed and include the annual and semi-annual project applications for the terrazzo
floor in the Grand Hall. Window and skylight washing is also included in these projects. Appendices
C.3 through C.5 contain summaries of the estimates by Program component. For all estimates, interior
graffiti removal has been assigned to the janitors.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 11 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
The service level envisioned in the janitorial service estimate provides for spaces that regularly appear
orderly and clean. Floors and base moldings appear bright and clean. There is no buildup in corners or
along walls. All vertical and horizontal surfaces are clean, but marks, dust, smudges and fingerprints
may be noticeable upon close observation. Interior lights are operable, and associated fixtures are clean.
Washroom fixtures and tile gleam and are odor-free. Washroom supplies are regularly replenished.
The janitorial hours estimate comprises routine cleaning, policing and project hours. The routine
cleaning hours are the hours required to keep the interior spaces orderly and clean, which includes the
daily cleaning and policing activities estimated in Appendix C.1. The project hours (Appendices C.2 to
C.5) are based upon completing certain cleaning projects, including:
Annual stripping and refinishing of floors coated with floor finish
Annual water extraction cleaning of carpeted floors
Annual machine scrubbing of non-coated floors
Quarterly machine scrubbing of restroom floors
Annual cleaning of ceiling
Annual wall washing as needed
Annual window washing of exterior windows
An allotment of hours for miscellaneous cleaning projects
Annual resurfacing and semi-annual refinishing of terrazzo floor in Grand Hall
The total required janitorial labor hours are calculated based upon the routine cleaning of the majority
of the program components seven times per week. It is optimal that this routine cleaning be scheduled
during off-hours. Provision has been made in the required labor hours for daily “policing” of the
facilities during the day or evenings to replenish restroom supplies, remove spills, and keep entrances
and lobbies clean and litter-free.
The standards for janitorial materials and supplies are based upon benchmarks incorporating the tasks
and frequencies. Janitorial materials would include “consumable” items, such as general cleaning
detergent, cleaner-disinfectants, glass cleaner, crème cleanser, bowl cleaner, furniture polish, hand
tools, and specialized products required by the facilities.
3.4 Utilities
Consumption of electricity and potable water has been modeled by the TJPA for the Program
components. The potable water consumption model considered the captured graywater that is to be
utilized to partially satisfy non-potable water needs, such as for a subsurface wetland and toilet
flushing. The consumption estimates were broken out among the Program components based on the
proportions developed in a previous study. The electricity loads for the Bus Storage Facility were
extrapolated from the model. Natural gas consumption was excluded from the calculation since gas
service is sub-metered and to be a direct cost to applicable tenants. Electrical costs for tenant spaces
were also excluded due to their being a direct cost to tenant by way of sub-metering. Utility
consumption estimates are summarized in Table 3-4.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 12 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
BUS RAMP
Electricity 1,057,070 KWH
ROOFTOP PARK
Potable Water 296,470 GAL
Sewer 296,470 GAL
Electricity 1,057,070 KWH
Garbage/Recycling 1 MONTH
Elevator and Escalator Maintenance: The TJPA has secured multi-year maintenance contracts for the
elevators (10 years) and escalators (11 years) with a not-to-exceed amount for the Phase 1 systems.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 13 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
These elevator and escalator maintenance contracts cover all testing, preventive maintenance, and
corrective maintenance activities.
Five-Year Mission Square Sculpture Installation Stress Test & Reporting (Annualized): Stress testing
of installation with reporting to include annotated photographs of the locations and extent of surface
cracks or hollow sounding areas; reporting to include comparisons to previous tests and predictions
of further deterioration.
The service contracts projected to be required at the Transit Center during normal operations are
outlined in Table 3-5.
Grounds Maintenance for the Rooftop Park is projected to be outsourced for the first two years. After
the two-year period, it is envisioned that this service will be provided by the property manager . Table
3-6 outlines the Year 1-2 projected service contracts.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 14 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report
Revolving projects to maintain interior and exterior finishes at a desirable level . Such
activities would include periodically renewing a painted concrete floor, refinishing walls, and
refurbishing ceilings in a public lobby to preserve the aesthetics of the space.
Recurring renewals that are intended to keep the facility operating as close to original design
specifications as possible, reduce frequent and costly maintenance activities, or improve
energy efficiency (for instance, replacing functional air distribution networks and HVAC
controls due to favorable payback through reduced maintenance and energy consumption
over an acceptable period of time).
Other tasks associated with facilities operation, such as the provision of central utilities, preventive and
corrective maintenance, janitorial services, grounds services or waste management, are not included in
this definition of Facilities Renewal Reserve projects. Adequate reinvestment in the facility will serve
to optimize the maintenance organization and the consumption of purchased utilities but will not
necessarily affect the cost of such services.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page 15 of 15 Rev.0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.1
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.1-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.2
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.2-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.3
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.3-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.4
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.4-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.5
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.5-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.6
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.6-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 TTC PH1 B203902 DOOR, SWINGING, POWERED AC 2 EA PM0008 1.25 DOOR, SWINGING, POWERED ‐ QUARTERLY 4.00 10.00 GENERALIST
1 TTC PH1 B203902 DOOR, SWINGING, POWERED DC 31 EA PM0008 1.25 DOOR, SWINGING, POWERED ‐ QUARTERLY 4.00 155.00 GENERALIST
1 TTC PH1 C102105 DOOR, SLIDING, POWERED DC 14 EA PM0016 1.224 DOOR, SLIDING, POWERED ‐ ANNUAL 1.00 17.14 GENERALIST
1 TTC PH1 C102105 DOOR, SLIDING, POWERED DORMA ESA300 5 EA PM0016 1.224 DOOR, SLIDING, POWERED ‐ ANNUAL 1.00 6.12 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED 40 EA PM0012 0.1 DOOR, FIRE‐RATED ‐ QUARTERLY 4.00 16.00 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED AC 128 EA PM0012 0.1 DOOR, FIRE‐RATED ‐ QUARTERLY 4.00 51.20 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED DC 79 EA PM0012 0.1 DOOR, FIRE‐RATED ‐ QUARTERLY 4.00 31.60 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED DOOR CONTACT 4 EA PM0012 0.1 DOOR, FIRE‐RATED ‐ QUARTERLY 4.00 1.60 GENERALIST
1 TTC PH1 D201101 TOILET PHASE 1 35 EA PM0046 0.15 TOILET ‐ ANNUAL 1.00 5.25 PLUMBER
1 TTC PH1 D201201 URINAL PHASE 1 7 EA PM0047 0.15 URINAL ‐ ANNUAL 1.00 1.05 PLUMBER
1 TTC PH1 D201301 LAVATORY PHASE 1 38 EA PM0048 0.15 LAVATORY ‐ ANNUAL 1.00 5.70 PLUMBER
1 TTC PH1 D201301 LAVATORY PHASE 1 39 EA PM0048 0.15 LAVATORY ‐ ANNUAL 1.00 5.85 PLUMBER
1 TTC PH1 D201701 SHOWER PHASE 1 2 EA PM0049 0.15 SHOWER ‐ ANNUAL 1.00 0.30 PLUMBER
1 TTC PH1 D201801 DRINKING FOUNTAINS PHASE 1 12 EA PM0050 0.6 DRINKING FOUNTAINS ‐ ANNUAL 1.00 7.20 HVAC TECHNICIAN
EMERGENCY EYE WASH, SHOWER, AND COMBO EMERGENCY EYE WASH, SHOWER, AND
1 TTC PH1 D201901 PHASE 1 8 EA PM0051 1.4 2.00 22.40 PLUMBER
STATIONS COMBO STATIONS ‐ SEMIANNUAL
EMERGENCY EYE WASH, SHOWER, AND COMBO EMERGENCY EYE WASH, SHOWER, AND
1 TTC PH1 D201901 PHASE 1 1 EA PM0051 1.4 2.00 2.80 PLUMBER
STATIONS COMBO STATIONS ‐ SEMIANNUAL
BACKFLOW PREVENTER ‐ DOMESTIC COLD
1 TTC PH1 D202101 BFP‐3‐A‐1 1 EA PM0058 0.5 BACKFLOW PREVENTER ‐ SEMIANNUAL 1.00 0.50 PLUMBER
WATER
1 TTC PH1 1 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 0.50 PLUMBER
1 TTC PH1 1 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 0.50 PLUMBER
Page A-6.3
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 TTC PH1 1 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 0.50 PLUMBER
1 TTC PH1 1 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 0.50 PLUMBER
1 TTC PH1 1 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 0.50 PLUMBER
1 TTC PH1 1 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 0.50 PLUMBER
1 TTC PH1 1 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 0.50 PLUMBER
1 TTC PH1 D202201 DOUBLE CHECK VALVE ‐ FIRE SUPPRESSION 5 EA PM0062 0.3 VALVE, HOT WATER MIXING ‐ QUARTERLY 4.00 6.00 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐1‐A‐1 1 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 0.60 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐1‐B‐1 1 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 0.60 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐1‐D‐1T4 4 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 2.40 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐3‐A‐2 1 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 0.60 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐3‐D‐1T3 3 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 1.80 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B1‐A‐1 1 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 0.60 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B1‐C‐1 1 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 0.60 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B1‐D‐1 1 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 0.60 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B2‐A‐1 1 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 0.60 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐1‐A‐2 1 EA PM0065 0.75 WATER HEATER, NATURAL GAS ‐ ANNUAL 1.00 0.75 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐2‐A‐1 2 EA PM0065 0.75 WATER HEATER, NATURAL GAS ‐ ANNUAL 1.00 1.50 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐3‐A‐1 1 EA PM0065 0.75 WATER HEATER, NATURAL GAS ‐ ANNUAL 1.00 0.75 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐3‐B‐1 1 EA PM0065 0.75 WATER HEATER, NATURAL GAS ‐ ANNUAL 1.00 0.75 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐4‐C‐1 1 EA PM0065 0.75 WATER HEATER, NATURAL GAS ‐ ANNUAL 1.00 0.75 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐5‐A‐1 1 EA PM0065 0.75 WATER HEATER, NATURAL GAS ‐ ANNUAL 1.00 0.75 PLUMBER
1 TTC PH1 D202301 PUMP, DOMESTIC WATER DWP‐B2‐A‐1T3 3 EA PM0068 0.75 PUMP, DOMESTIC WATER ‐ QUARTERLY 3.00 6.75 PLUMBER
1 TTC PH1 3 EA PM0069 0.75 PUMP, DOMESTIC WATER ‐ ANNUAL 1.00 2.25 PLUMBER
1 TTC PH1 D202301 PUMP, DOMESTIC WATER IRP‐B2‐A‐1,IRP‐B2‐A‐2 2 EA PM0068 0.75 PUMP, DOMESTIC WATER ‐ QUARTERLY 3.00 4.50 PLUMBER
1 TTC PH1 2 EA PM0069 0.75 PUMP, DOMESTIC WATER ‐ ANNUAL 1.00 1.50 PLUMBER
1 TTC PH1 D203401 GREASE TRAP FUEL OIL SAND INTERCEPTOR 7 EA PM0070 0.75 GREASE TRAP ‐ MONTHLY 12.00 63.00 PLUMBER
SE‐B2‐A‐1&2,SE‐B2‐B‐1T4,SE‐B2‐C‐1T4,SE‐
1 TTC PH1 D203402 PUMP, SEWAGE EJECTION 14 EA PM0071 1 PUMP, SEWAGE EJECTION ‐ SEMIANNUAL 1.00 14.00 PLUMBER
B2‐D‐1T4
1 TTC PH1 14 EA PM0072 3.75 PUMP, SEWAGE EJECTION ‐ ANNUAL 1.00 52.50 PLUMBER
1 TTC PH1 D204302 PUMP, SUMP ALL GWP & OFP 14 EA PM0076 1 PUMP, SUMP ‐ SEMIANNUAL 1.00 14.00 PLUMBER
Page A-6.4
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 TTC PH1 14 EA PM0077 3.75 PUMP, SUMP ‐ ANNUAL 1.00 52.50 PLUMBER
1 TTC PH1 D204302 PUMP, SUMP ALL GWP/OZ 6 EA PM0076 1 PUMP, SUMP ‐ SEMIANNUAL 1.00 6.00 PLUMBER
1 TTC PH1 6 EA PM0077 3.75 PUMP, SUMP ‐ ANNUAL 1.00 22.50 PLUMBER
1 TTC PH1 D204302 PUMP, SUMP ALL SPG 8 EA PM0076 1 PUMP, SUMP ‐ SEMIANNUAL 1.00 8.00 PLUMBER
1 TTC PH1 8 EA PM0077 3.75 PUMP, SUMP ‐ ANNUAL 1.00 30.00 PLUMBER
1 TTC PH1 D204302 PUMP, SUMP SP‐B1‐A‐1&2,SP‐B1‐B‐1&2,SP‐B1‐C‐1&2 6 EA PM0076 1 PUMP, SUMP ‐ SEMIANNUAL 1.00 6.00 PLUMBER
1 TTC PH1 6 EA PM0077 3.75 PUMP, SUMP ‐ ANNUAL 1.00 22.50 PLUMBER
SP‐B2‐A‐1T6,SP‐B2‐B‐1T6,SP‐B2‐C‐1T6,SP‐B2‐
1 TTC PH1 D204302 PUMP, SUMP 24 EA PM0076 1 PUMP, SUMP ‐ SEMIANNUAL 1.00 24.00 PLUMBER
D‐1T6
1 TTC PH1 24 EA PM0077 3.75 PUMP, SUMP ‐ ANNUAL 1.00 90.00 PLUMBER
1 TTC PH1 D301101 TANK, FUEL OIL 2 EA PM0087 0.549 TANK, FUEL OIL ‐ ANNUAL 1.00 1.10 GENERATOR MECHANIC
1 TTC PH1 2 EA PM0088 8 TANK, FUEL OIL ‐ 4 YEARS 0.25 4.00 GENERATOR MECHANIC
1 TTC PH1 D301102 PUMP, FUEL OIL DIESEL PUMPS (DFP) 4 EA PM0484 0.33 PUMP, FUEL OIL ‐ MONTHLY 10.00 13.20 GENERATOR MECHANIC
1 TTC PH1 4 EA PM0089 1.2 PUMP, FUEL OIL ‐ SEMIANNUAL 2.00 9.60 GENERATOR MECHANIC
1 TTC PH1 D301103 FILTER, FUEL OIL 2 EA PM0091 0.5 FILTER, FUEL OIL ‐ ANNUAL 1.00 1.00 GENERATOR MECHANIC
1 TTC PH1 D303110 COOLING TOWER CT‐B1‐A‐1 1 EA PM0125 20 COOLING TOWER ‐ QUARTERLY 4.00 80.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0126 1.5 COOLING TOWER ‐ QUARTERLY 2.00 3.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0127 12.38 COOLING TOWER ‐ SEMIANNUAL 1.00 12.38 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0128 12.86 COOLING TOWER ‐ ANNUAL 1.00 12.86 HVAC TECHNICIAN
1 TTC PH1 D303110 COOLING TOWER CT‐B1‐A‐2 1 EA PM0125 20 COOLING TOWER ‐ QUARTERLY 4.00 80.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0126 1.5 COOLING TOWER ‐ QUARTERLY 2.00 3.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0127 12.38 COOLING TOWER ‐ SEMIANNUAL 1.00 12.38 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0128 12.86 COOLING TOWER ‐ ANNUAL 1.00 12.86 HVAC TECHNICIAN
1 TTC PH1 D303110 COOLING TOWER WHP‐B1‐A‐1 1 EA PM0125 20 COOLING TOWER ‐ QUARTERLY 4.00 80.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0126 1.5 COOLING TOWER ‐ QUARTERLY 2.00 3.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0127 12.38 COOLING TOWER ‐ SEMIANNUAL 1.00 12.38 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0128 12.86 COOLING TOWER ‐ ANNUAL 1.00 12.86 HVAC TECHNICIAN
1 TTC PH1 D303110 COOLING TOWER WHP‐B1‐C‐1 1 EA PM0125 20 COOLING TOWER ‐ QUARTERLY 4.00 80.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0126 1.5 COOLING TOWER ‐ QUARTERLY 2.00 3.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0127 12.38 COOLING TOWER ‐ SEMIANNUAL 1.00 12.38 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0128 12.86 COOLING TOWER ‐ ANNUAL 1.00 12.86 HVAC TECHNICIAN
1 TTC PH1 D303110 COOLING TOWER WHP‐B1‐C‐2 1 EA PM0125 20 COOLING TOWER ‐ QUARTERLY 4.00 80.00 HVAC TECHNICIAN
Page A-6.5
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 TTC PH1 1 EA PM0126 1.5 COOLING TOWER ‐ QUARTERLY 2.00 3.00 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0127 12.38 COOLING TOWER ‐ SEMIANNUAL 1.00 12.38 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0128 12.86 COOLING TOWER ‐ ANNUAL 1.00 12.86 HVAC TECHNICIAN
1 TTC PH1 D303201 CONDENSING UNIT ACC‐B2‐A‐1&2,ACC‐B2‐D‐1&2 4 EA PM0133 0.299 CONDENSING UNIT ‐ QUARTERLY 3.00 3.59 HVAC TECHNICIAN
1 TTC PH1 4 EA PM0134 0.861 CONDENSING UNIT ‐ ANNUAL 1.00 3.44 HVAC TECHNICIAN
1 TTC PH1 D304003 EXPANSION TANK 8 EA PM0146 0.75 EXPANSION TANK ‐ ANNUAL 1.00 6.00 MECHANIC
1 TTC PH1 D304101 AIR HANDLING UNIT AHU‐B1‐A‐1 1 EA PM0149 0.75 AIR HANDLING UNIT ‐ QUARTERLY 3.00 2.25 HVAC TECHNICIAN
1 TTC PH1 1 EA PM0150 8.25 AIR HANDLING UNIT ‐ ANNUAL 1.00 8.25 HVAC TECHNICIAN
1 TTC PH1 D304109 DAMPER, FIRE OR SMOKE 311 EA PM0164 0.23 DAMPER, FIRE OR SMOKE ‐ 5 YEARS 0.20 14.31 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL SF‐B1‐C‐3,SF‐B1‐C‐4 2 EA PM0168 0.62 FAN, AXIAL ‐ SEMIANNUAL 2.00 2.48 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL SF‐B2‐A‐1,STP‐2‐A‐1 2 EA PM0168 0.62 FAN, AXIAL ‐ SEMIANNUAL 2.00 2.48 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL SF‐B2‐B‐1,SF‐B2‐B‐2 2 EA PM0168 0.62 FAN, AXIAL ‐ SEMIANNUAL 2.00 2.48 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL STP‐1‐A‐1,STP‐1‐A‐2,STP‐2‐D‐1 3 EA PM0168 0.62 FAN, AXIAL ‐ SEMIANNUAL 2.00 3.72 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL STP‐2‐B‐1 1 EA PM0168 0.62 FAN, AXIAL ‐ SEMIANNUAL 2.00 1.24 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL STP‐B1‐C‐1,STP‐1‐B‐1 2 EA PM0168 0.62 FAN, AXIAL ‐ SEMIANNUAL 2.00 2.48 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL (16) EF FANS 16 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 12.00 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL (27) CF FANS 27 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 20.25 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐1‐A‐1 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐1‐A‐4,EF‐B1‐A‐2 2 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 1.50 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐1‐B‐1,EF‐B1‐A‐3 2 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 1.50 MECHANIC
EF‐1‐B‐2,EF‐1‐D‐1&2,EF‐2‐A‐3,EF‐2‐D‐1,EF‐3‐
1 TTC PH1 D304112 FAN, CENTRIFUGAL 6 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 4.50 MECHANIC
D‐3
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐2‐B‐2,EF‐B1‐A‐6 2 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 1.50 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐B1‐A‐4 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐B1‐A‐5 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐B1‐B‐1,EF‐B2‐A‐2 2 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 1.50 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐1‐A‐1,SF‐1‐A‐2,SF‐1‐B‐1,SF‐3‐A‐1 4 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 3.00 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐2‐D‐1 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐A‐1T2,SF‐B1‐B‐2,SF‐B1‐C‐1&2 5 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 3.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐A‐3 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐A‐4 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐B‐1 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐B‐3 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐D‐1 1 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 0.75 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL TRANSFER FANS (TF) 19 EA PM0169 0.75 FAN, CENTRIFUGAL ‐ ANNUAL 1.00 14.25 MECHANIC
Page A-6.6
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 TTC PH1 D304113 FAN, MIXED FLOW EF‐B1‐D‐1 1 EA PM0170 0.5 FAN, MIXED FLOW ‐ QUARTERLY 4.00 2.00 MECHANIC
1 TTC PH1 D304113 FAN, MIXED FLOW EF‐B2‐A‐1 1 EA PM0170 0.5 FAN, MIXED FLOW ‐ QUARTERLY 4.00 2.00 MECHANIC
1 TTC PH1 D304118 VAV BOX 9 EA PM0177 1.25 VAV BOX ‐ ANNUAL 1.00 11.25 MECHANIC
1 TTC PH1 D304405 PUMP, HEATING HOT WATER HWP‐B1‐A‐1 1 EA PM0175 0.15 PUMP, HEATING HOT WATER ‐ SEMIANNUAL 1.00 0.15 MECHANIC
1 TTC PH1 1 EA PM0176 2.5 PUMP, HEATING HOT WATER ‐ ANNUAL 1.00 2.50 MECHANIC
1 TTC PH1 D304405 PUMP, HEATING HOT WATER RFP‐B1‐C‐1 1 EA PM0175 0.15 PUMP, HEATING HOT WATER ‐ SEMIANNUAL 1.00 0.15 MECHANIC
1 TTC PH1 1 EA PM0176 2.5 PUMP, HEATING HOT WATER ‐ ANNUAL 1.00 2.50 MECHANIC
1 TTC PH1 D304405 PUMP, HEATING HOT WATER RFP‐B1‐C‐2 3 EA PM0175 0.15 PUMP, HEATING HOT WATER ‐ SEMIANNUAL 1.00 0.45 MECHANIC
1 TTC PH1 3 EA PM0176 2.5 PUMP, HEATING HOT WATER ‐ ANNUAL 1.00 7.50 MECHANIC
CHEMICAL FEEDER, CHILLED / CONDENSER CHEMICAL FEEDER, CHILLED / CONDENSER WATER TREATMENT
1 TTC PH1 D304502 1 EA PM0193 1 2.00 2.00
WATER WATER ‐ SEMIANNUAL TECHNICIAN
HEAT EXCHANGER, PLATE AND FRAME ‐
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B1‐A‐2 1 EA PM0196 0.9 1.00 0.90 MECHANIC
ANNUAL
HEAT EXCHANGER, PLATE AND FRAME ‐
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B2‐C‐1 1 EA PM0196 0.9 1.00 0.90 MECHANIC
ANNUAL
HEAT EXCHANGER, PLATE AND FRAME ‐
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B1‐A‐1 1 EA PM0196 0.9 1.00 0.90 MECHANIC
ANNUAL
HEAT EXCHANGER, PLATE AND FRAME ‐
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B2‐A‐1 1 EA PM0196 0.9 1.00 0.90 MECHANIC
ANNUAL
HEAT EXCHANGER, PLATE AND FRAME ‐
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B2‐D‐1 1 EA PM0196 0.9 1.00 0.90 MECHANIC
ANNUAL
1 TTC PH1 D304506 PUMP, CONDENSER WATER CWP‐B1‐A‐1T3 1 EA PM0483 0.33 PUMP, CONDENSER WATER ‐ MONTHLY 10.00 3.30 MECHANIC
1 TTC PH1 1 EA PM0198 0.75 PUMP, CONDENSER WATER ‐ SEMIANNUAL 2.00 1.50 MECHANIC
1 TTC PH1 D304506 PUMP, CONDENSER WATER CWP‐B1‐A‐4T6 1 EA PM0483 0.33 PUMP, CONDENSER WATER ‐ MONTHLY 10.00 3.30 MECHANIC
1 TTC PH1 1 EA PM0198 0.75 PUMP, CONDENSER WATER ‐ SEMIANNUAL 2.00 1.50 MECHANIC
1 TTC PH1 D304506 PUMP, CONDENSER WATER CWP‐B1‐C‐1,CWP‐B1‐D‐1 2 EA PM0483 0.33 PUMP, CONDENSER WATER ‐ MONTHLY 10.00 6.60 MECHANIC
1 TTC PH1 2 EA PM0198 0.75 PUMP, CONDENSER WATER ‐ SEMIANNUAL 2.00 3.00 MECHANIC
1 TTC PH1 D304507 VALVE, HVAC PIPING 127 EA PM0199 0.5 VALVE, CHILLED WATER ‐ ANNUAL 1.00 63.50 MECHANIC
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (12) 1‐2 MBH UNITS 12 EA PM0206 1 FAN COIL UNIT, CEILING‐MOUNTED ‐ ANNUAL 1.00 12.00 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (14) 13‐15 MBH UNITS 14 EA PM0206 1 FAN COIL UNIT, CEILING‐MOUNTED ‐ ANNUAL 1.00 14.00 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (2) 10‐12 MBH UNITS 2 EA PM0206 1 FAN COIL UNIT, CEILING‐MOUNTED ‐ ANNUAL 1.00 2.00 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (2) 16‐18 MBH UNITS 2 EA PM0206 1 FAN COIL UNIT, CEILING‐MOUNTED ‐ ANNUAL 1.00 2.00 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (20) 7‐9 MBH UNITS 20 EA PM0206 1 FAN COIL UNIT, CEILING‐MOUNTED ‐ ANNUAL 1.00 20.00 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (44) 4‐6 MBH UNITS 44 EA PM0206 1 FAN COIL UNIT, CEILING‐MOUNTED ‐ ANNUAL 1.00 44.00 HVAC TECHNICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE CF‐3‐A‐1,CF‐3‐A‐2,CF‐3‐B‐1,CF‐3‐B‐10 4 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.00 ELECTRICIAN
CF‐3‐B‐11,CF‐3‐B‐2,CF‐3‐B‐3,CF‐3‐B‐4,CF‐3‐B‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 5 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.50 ELECTRICIAN
5
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE CF‐3‐B‐6,CF‐3‐B‐7,CF‐3‐B‐8,CF‐3‐B‐9 4 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.00 ELECTRICIAN
Page A-6.7
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
CF‐3‐C‐1,CF‐3‐C‐2,CF‐3‐C‐3,CF‐3‐C‐4,CF‐3‐C‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 5 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.50 ELECTRICIAN
5
CF‐3‐C‐6,CF‐3‐C‐7,CF‐3‐C‐8,CF‐3‐C‐9,CF‐3‐C‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 5 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.50 ELECTRICIAN
10
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE CF‐3‐D‐1,CF‐3‐D‐2,CF‐3‐D‐3,CF‐3‐D‐4 4 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.00 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE CWP‐B1‐A‐1,CWP‐B1‐A‐2,CWP‐B1‐A‐3 3 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 1.50 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE CWP‐B1‐A‐4,CWP‐B1‐A‐5,CWP‐B1‐A‐6 3 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 1.50 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE EF‐1‐A‐1,EF‐1‐A‐4,EF‐1‐B‐1 3 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 1.50 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE EF‐B1‐A‐4,EF‐B1‐A‐5,EF‐B1‐A‐6 3 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 1.50 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE RFP‐B1‐C‐1,RFP‐B1‐C‐2 2 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 1.00 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE SF‐1‐A‐2,SF‐2‐D‐1,SF‐B1‐A‐1,SF‐B1‐A‐2 4 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.00 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE SF‐B1‐B‐1,SF‐B1‐B‐2,SF‐B1‐C‐1,SF‐B1‐C‐2 4 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.00 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE STP‐2‐A‐1,STP‐2‐B‐1,ATP‐2‐D‐1 3 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 1.50 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE STP‐B1‐C‐1,STP‐1‐A‐1,STP‐1‐A‐2,STP‐1‐B‐1 4 EA PM0234 0.5 VARIABLE FREQUENCY DRIVE ‐ ANNUAL 1.00 2.00 ELECTRICIAN
1 TTC PH1 D403101 FIRE EXTINGUISHER 448 EA PM0273 0.15 FIRE EXTINGUISHER ‐ MONTHLY 12.00 806.40 GENERALIST
1 TTC PH1 D501201 BREAKER, MOLDED CASE 146 EA PM0289 1.5 BREAKER, MOLDED CASE ‐ ANNUAL 1.00 219.00 ELECTRICIAN
1 TTC PH1 D501203 DISTRIBUTION PANEL 271 EA PM0291 0.5 DISTRIBUTION PANEL ‐ ANNUAL 1.00 135.50 ELECTRICIAN
Page A-6.8
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC ATS‐B1‐A‐SOC 1 EA PM0299 0.25 TRANSFER SWITCH, AUTOMATIC ‐ ANNUAL 1.00 0.25 GENERATOR MECHANIC
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC ATS‐B1‐B‐LRS,ATS‐B1‐C‐LRS 2 EA PM0299 0.25 TRANSFER SWITCH, AUTOMATIC ‐ ANNUAL 1.00 0.50 GENERATOR MECHANIC
ATS‐B2‐A‐EMG,ATS‐B1‐B‐EMG,ATS‐B1‐C‐
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC 3 EA PM0299 0.25 TRANSFER SWITCH, AUTOMATIC ‐ ANNUAL 1.00 0.75 GENERATOR MECHANIC
EMG
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC ATS‐B2‐A‐LRS,ATS‐B1‐B‐OPT,ATS‐B1‐D‐OPT 3 EA PM0299 0.25 TRANSFER SWITCH, AUTOMATIC ‐ ANNUAL 1.00 0.75 GENERATOR MECHANIC
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC ATS‐B2‐FP1,ATS‐B2‐FP2 2 EA PM0299 0.25 TRANSFER SWITCH, AUTOMATIC ‐ ANNUAL 1.00 0.50 GENERATOR MECHANIC
1 TTC PH1 D501212 TRANSFER SWITCH, MANUAL 9 EA PM0300 0.25 TRANSFER SWITCH, MANUAL ‐ SEMIANNUAL 2.00 4.50 ELECTRICIAN
1 TTC PH1 D501215 TRANSFORMER, SECONDARY 52 EA PM0303 1 TRANSFORMER, SECONDARY ‐ ANNUAL 1.00 52.00 ELECTRICIAN
1 TTC PH1 D502202 LIGHTING, EXTERIOR PHASE 1 605 EA PM0305 1 LIGHTING, EXTERIOR ‐ ANNUAL 1.00 605.00 GENERALIST
1 TTC PH1 D502202 LIGHTING, EXTERIOR PHASE 1 3 EA PM0305 1 LIGHTING, EXTERIOR ‐ ANNUAL 1.00 3.00 GENERALIST
1 TTC PH1 D502203 LIGHTING, INTERIOR, FLUORESCENT PHASE 1 4121 EA PM0306 0.25 LIGHTING, INTERIOR, FLUORESCENT ‐ 5 YEARS 0.20 206.05 ELECTRICIAN
1 TTC PH1 E102502 ILLUMINATION, SHAW ALLEY PUBLIC ART SHAW ALLEY 1 EA PM0506 1 ILLUMINATION, SHAW ALLEY ‐ BIWEEKLY 26.00 26.00 GENERALIST
1 TTC PH1 E102502 ILLUMINATION, SHAW ALLEY PUBLIC ART SHAW ALLEY 1 EA PM0507 96 ILLUMINATION, SHAW ALLEY ‐ ANNUAL 1.00 96.00 GENERALIST
1 TTC PH1 D502204 SPOTLIGHTS PHASE 1 282 EA PM0308 1.5 SPOTLIGHTS ‐ MONTHLY 12.00 5076.00 GENERALIST
1 TTC PH1 D503704 FIRE ALARM CONTROL PANEL 1 EA PM0317 2.25 FIRE ALARM CONTROL PANEL ‐ ANNUAL 1.00 2.25 FIRE ALARM TECHNICIAN
1 TTC PH1 D503708 HORN STROBE DEVICE 1058 EA PM0321 0.15 HORN STROBE DEVICE ‐ ANNUAL 1.00 158.70 FIRE ALARM TECHNICIAN
1 TTC PH1 D503709 MANUAL PULL STATION 76 EA PM0322 0.13 MANUAL PULL STATION ‐ ANNUAL 1.00 9.88 FIRE ALARM TECHNICIAN
1 TTC PH1 D503711 SMOKE DETECTOR 1296 EA PM0324 0.13 SMOKE DETECTOR ‐ ANNUAL 1.00 168.48 FIRE ALARM TECHNICIAN
1 TTC PH1 D503804 CAMERA, CCTV 70 EA PM0503 0.15 CAMERA, CCTV ‐ QUARTERLY 4.00 42.00 GENERALIST
1 TTC PH1 D509208 EMERGENCY GENERATOR CTR‐GEN GENERATOR 1 EA PM0336 1 EMERGENCY GENERATOR ‐ WEEKLY 26.00 26.00 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0337 0.75 EMERGENCY GENERATOR ‐ BIWEEKLY 14.00 10.50 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0338 5.5 EMERGENCY GENERATOR ‐ MONTHLY 8.00 44.00 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0339 1.15 EMERGENCY GENERATOR ‐ QUARTERLY 2.00 2.30 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0340 1.5 EMERGENCY GENERATOR ‐ SEMIANNUAL 1.00 1.50 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0341 1.5 EMERGENCY GENERATOR ‐ ANNUAL 1.00 1.50 GENERATOR MECHANIC
1 TTC PH1 D509208 EMERGENCY GENERATOR WEST GENERATOR 1 EA PM0336 1 EMERGENCY GENERATOR ‐ WEEKLY 26.00 26.00 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0337 0.75 EMERGENCY GENERATOR ‐ BIWEEKLY 14.00 10.50 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0338 5.5 EMERGENCY GENERATOR ‐ MONTHLY 8.00 44.00 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0339 1.15 EMERGENCY GENERATOR ‐ QUARTERLY 2.00 2.30 GENERATOR MECHANIC
1 TTC PH1 1 EA PM0340 1.5 EMERGENCY GENERATOR ‐ SEMIANNUAL 1.00 1.50 GENERATOR MECHANIC
Page A-6.9
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 TTC PH1 1 EA PM0341 1.5 EMERGENCY GENERATOR ‐ ANNUAL 1.00 1.50 GENERATOR MECHANIC
1 TTC PH1 D509210 EXIT SIGN PHASE 1 323 EA PM0343 0.02 EXIT SIGN ‐ SEMIANNUAL 2.00 12.92 FIRE ALARM TECHNICIAN
1 TTC PH1 D509213 UNINTERRUPTIBLE POWER SUPPLY UPS‐B1‐A‐SOC,UPS‐B1‐B,UPS‐B1‐D 3 EA PM0346 0.5 UNINTERRUPTIBLE POWER SUPPLY ‐ ANNUAL 1.00 1.50 ELECTRICIAN
1 TTC PH1 E102501 DISPLAY, LED PUBLIC ART LED DISPLAY 1 EA PM0504 96 DISPLAY, LED ‐ ANNUAL 1.00 96.00 GENERALIST
1 TTC PH1 E102501 DISPLAY, LED PUBLIC ART LED DISPLAY 1 EA PM0508 0.5 DISPLAY, LED ‐ BIWEEKLY 26.00 13.00 GENERALIST
1 TTC PH1 E103302 DOCK LEVELER 8 EA PM0488 0.82 DOCK LEVELER ‐ SEMIANNUAL 4.00 26.24 GENERALIST
1 TTC PH1 E109903 SIGNAGE, WAYFINDING 1 EA N/A 1 SIGNAGE, WAYFINDING ‐ WEEKLY INSPECTION 52.00 52.00 GENERALIST
1 BUS RAMP D501203 DISTRIBUTION PANEL BUS RAMP 1 EA PM0291 0.5 DISTRIBUTION PANEL ‐ ANNUAL 1.00 0.50 ELECTRICIAN
1 BUS RAMP D501215 TRANSFORMER, SECONDARY BUS RAMP 1 EA PM0303 1 TRANSFORMER, SECONDARY ‐ ANNUAL 1.00 1.00 ELECTRICIAN
1 BUS RAMP D502201 LIGHTING DIMMER PANEL BUS RAMP 1 EA PM0304 4.5 LIGHTING DIMMER PANEL ‐ QUARTERLY 4.00 18.00 ELECTRICIAN
1 BUS RAMP D502202 LIGHTING, EXTERIOR BUS RAMP 18 EA PM0305 1 LIGHTING, EXTERIOR ‐ ANNUAL 1.00 18.00 GENERALIST
1 BUS RAMP D502204 SPOTLIGHTS BUS RAMP 15 EA PM0308 1.5 SPOTLIGHTS ‐ MONTHLY 12.00 270.00 GENERALIST
1 BUS RAMP D502204 SPOTLIGHTS BUS RAMP 12 EA PM0308 1.5 SPOTLIGHTS ‐ MONTHLY 12.00 216.00 GENERALIST
1 BUS RAMP D503804 CAMERA, CCTV 37 EA PM0503 0.15 CAMERA, CCTV ‐ QUARTERLY 4.00 22.20 GENERALIST
1 BUS RAMP G201601 TRAFFIC LIGHT 5 EA PM0404 0.513 TRAFFIC LIGHT ‐ QUARTERLY 3.00 7.70 GENERALIST
1 BUS RAMP 5 EA PM0405 0.742 TRAFFIC LIGHT ‐ ANNUAL 1.00 3.71 GENERALIST
1 ROOF PARK B102001 ROOF (PER 100 SF) ROOF PARK BUS FOUNTAIN 120 100 SF PM0003 0.03 ROOF (PER 100 SF) ‐ SEMIANNUAL 2.00 7.20 ROOFER
1 ROOF PARK B102001 ROOF (PER 100 SF) ROOF PARK MEP ROOMS 50 100 SF PM0003 0.03 ROOF (PER 100 SF) ‐ SEMIANNUAL 2.00 3.00 ROOFER
1 ROOF PARK D201101 TOILET PHASE 1 15 EA PM0046 0.15 TOILET ‐ ANNUAL 1.00 2.25 PLUMBER
1 ROOF PARK D201201 URINAL PHASE 1 3 EA PM0047 0.15 URINAL ‐ ANNUAL 1.00 0.45 PLUMBER
1 ROOF PARK D201301 LAVATORY PHASE 1 9 EA PM0048 0.15 LAVATORY ‐ ANNUAL 1.00 1.35 PLUMBER
1 ROOF PARK D209401 WATER TREATMENT, FOUNTAIN ROOF PARK 2 EA PM0081 0.917 WATER TREATMENT, FOUNTAIN ‐ WEEKLY 40.00 73.36 PLUMBER
1 ROOF PARK 2 EA PM0082 1.917 WATER TREATMENT, FOUNTAIN ‐ MONTHLY 12.00 46.01 PLUMBER
Page A-6.10
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 ROOF PARK D209905 PUMP, GENERAL‐USE BUS FOUNTAIN P201 2 EA PM0461 0.15 PUMP, GENERAL‐USE ‐ SEMIANNUAL 1.00 0.30 PLUMBER
1 ROOF PARK 2 EA PM0462 0.15 PUMP, GENERAL‐USE ‐ ANNUAL 1.00 0.30 PLUMBER
1 ROOF PARK D209905 PUMP, GENERAL‐USE BUS FOUNTAIN P301 2 EA PM0461 0.15 PUMP, GENERAL‐USE ‐ SEMIANNUAL 1.00 0.30 PLUMBER
1 ROOF PARK 2 EA PM0462 0.15 PUMP, GENERAL‐USE ‐ ANNUAL 1.00 0.30 PLUMBER
1 ROOF PARK G204601 FOUNTAIN ROOF PARK 1 EA PM0411 4 FOUNTAIN ‐ ANNUAL 1.00 4.00 PLUMBER
1 ROOF PARK G205702 IRRIGATION ZONE ROOF PARK, GROUND LEVEL 65 EA PM0414 0.5 IRRIGATION ZONE ‐ SEMIANNUAL 2.00 65.00 PLUMBER
1 ROOF PARK G205703 BACKFLOW PREVENTER ‐ IRRIGATION M101,M201 2 EA PM0058 0.5 BACKFLOW PREVENTER ‐ SEMIANNUAL 1.00 1.00 PLUMBER
1 ROOF PARK 2 EA PM0059 0.5 BACKFLOW PREVENTER ‐ ANNUAL 1.00 1.00 PLUMBER
1 BSF B102001 ROOF (PER 100 SF) BSF ADMIN BLDG 165 100 SF PM0003 0.03 ROOF (PER 100 SF) ‐ SEMIANNUAL 2.00 9.90 ROOFER
1 BSF B102001 ROOF (PER 100 SF) BSF GUARD SHACKS 0.5 100 SF PM0003 0.03 ROOF (PER 100 SF) ‐ SEMIANNUAL 2.00 0.03 ROOFER
1 BSF B102001 ROOF (PER 100 SF) BSF SUPPORT BLDG 9 100 SF PM0003 0.03 ROOF (PER 100 SF) ‐ SEMIANNUAL 2.00 0.54 ROOFER
1 BSF D201101 TOILET BSF ADMIN BLDG 5 EA PM0046 0.15 TOILET ‐ ANNUAL 1.00 0.75 PLUMBER
1 BSF D201201 URINAL BSF ADMIN BLDG 2 EA PM0047 0.15 URINAL ‐ ANNUAL 1.00 0.30 PLUMBER
1 BSF D201301 LAVATORY BSF ADMIN BLDG 4 EA PM0048 0.15 LAVATORY ‐ ANNUAL 1.00 0.60 PLUMBER
1 BSF D202202 WATER HEATER, ELECTRIC BSF ADMIN BLDG 3 EA PM0063 0.6 WATER HEATER, ELECTRIC ‐ ANNUAL 1.00 1.80 PLUMBER
1 BSF D403101 FIRE EXTINGUISHER 6 EA PM0273 0.15 FIRE EXTINGUISHER ‐ MONTHLY 12.00 10.80 GENERALIST
1 BSF D501203 DISTRIBUTION PANEL 3 EA PM0291 0.5 DISTRIBUTION PANEL ‐ ANNUAL 1.00 1.50 ELECTRICIAN
1 BSF D502201 LIGHTING DIMMER PANEL 3 EA PM0304 4.5 LIGHTING DIMMER PANEL ‐ QUARTERLY 4.00 54.00 ELECTRICIAN
1 BSF D502202 LIGHTING, EXTERIOR BSF 10 EA PM0305 1 LIGHTING, EXTERIOR ‐ ANNUAL 1.00 10.00 GENERALIST
1 BSF D502202 LIGHTING, EXTERIOR BSF 7 EA PM0305 1 LIGHTING, EXTERIOR ‐ ANNUAL 1.00 7.00 GENERALIST
1 BSF D502203 LIGHTING, INTERIOR, FLUORESCENT BSF ADMIN BLDG 20 EA PM0306 0.25 LIGHTING, INTERIOR, FLUORESCENT ‐ 5 YEARS 0.20 1.00 ELECTRICIAN
1 BSF D502203 LIGHTING, INTERIOR, FLUORESCENT BSF GUARD SHACKS 2 EA PM0306 0.25 LIGHTING, INTERIOR, FLUORESCENT ‐ 5 YEARS 0.20 0.10 ELECTRICIAN
1 BSF D502203 LIGHTING, INTERIOR, FLUORESCENT BSF SUPPORT BLDG 12 EA PM0306 0.25 LIGHTING, INTERIOR, FLUORESCENT ‐ 5 YEARS 0.20 0.60 ELECTRICIAN
Page A-6.11
Program UNIFORMAT PM TIME PM FREQUENCY TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY PM NUMBER PM TITLE SHOP
Component II STANDARD COUNT PM HOURS
1 BSF D502204 SPOTLIGHTS BSF ADMIN BLDG 7 EA PM0308 1.5 SPOTLIGHTS ‐ MONTHLY 12.00 126.00 GENERALIST
1 BSF D503804 CAMERA, CCTV 6 EA PM0503 0.15 CAMERA, CCTV ‐ QUARTERLY 4.00 3.60 GENERALIST
1 BSF D509210 EXIT SIGN BSF ADMIN BLDG 2 EA PM0343 0.02 EXIT SIGN ‐ SEMIANNUAL 2.00 0.08 FIRE ALARM TECHNICIAN
1 BSF G205702 IRRIGATION ZONE 2 EA PM0414 0.5 IRRIGATION ZONE ‐ SEMIANNUAL 2.00 2.00 PLUMBER
Page A-6.12
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Check ceilings and the underside of the deck for signs of water entry such as stained ceiling tiles,
dry rot in a wooden deck, or rust in a steel deck. Note all deteriorated areas on your roof plan
for comparison later on the roof.
2. Walk around the perimeter of the building.
3. Check for cracks and signs of water entry into the walls and examine exterior drainage
accessories such as downspout, scupper heads and gutters for signs of leakage.
4. Mark the deficiencies on the roof plan and proceed to the roof.
5. Check for ponding and plant growth (roof should drain within 48 hours of a rain fall.) Any
accumulation of water (ponding) should be noted on the roof plan. Pay particular attention to
areas near building air intakes.
6. Check for physical damage such as punctures, note location of patches, repairs and
accumulation of debris especially near drains.
7. Check for wrinkles, buckles, bubbles and sponginess. Note exposure of bituminous coating due
to loose or missing gravel.
8. Check all flashing for wind damage, caulking and curling, and exposed edges.
9. Check flashing fasteners for looseness and deterioration.
10. Check any fibrous material that might be asbestos for deterioration.
11. Report information on any asbestos material to the asbestos program.
12. Check the condition of any joints, roof to wall joint in particular. Check the termination of
roofing expansion joints at parapet walls. Be sure that water drains off the top of the coping and
that it is well attached.
13. Check coping for deterioration, especially rusting, punctures and open seams in metal coping,
and spalling or cracking in masonry coping.
14. Check whether walkways are in logical locations and in good condition with no blistering below
them.
15. Check that any installed equipment such as antennas, HVAC equipment and flagpoles are
properly installed according to building codes, including necessary I-beam supports for heavy AC
equipment, and are flashed and secured to the building.
16. Refill pitch pockets.
17. Check ballast (rock) for even spread; remove any with very sharp edges.
18. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
19. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
20. If any corrections or repairs are necessary submit a request for work order.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-2 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
9. On pneumatic or hydraulically operated door operators, check for correct operating pressures
per manufacturer's instructions.
10. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
11. If any corrections or repairs submit a request for work order.
12. Clean up area and dispose of trash properly.
13. Review with customer for operational problems and trends. Identify customer contacted.
14. Log all items shown above on inspection sheet.
1. With the exception of electromagnetic hold-open devices, remove all hold-open devices such as
fusible links.
2. Inspect the door for damage.
3. Check hang and swing of door for close fit. Doors must latch on a normal closing cycle and have
a neat fit.
4. Remove any obstructions that retard full swing or movement of the door.
5. Test the operation of the panic hardware.
6. Inspect door coordinates on double doors. Make sure the coordinates on double doors are
securely attached and adjusted properly to allow the first leaf (inactive leaf) to close before the
second leaf (active leaf). Check this by completely opening both doors and simultaneously
releasing them.
7. Check the operation of any special devices such as smoke detectors or electromagnetic door
releases.
8. Check for breaks in the face covering of the door.
9. Inspect all other hardware for damage or wear.
10. Lubricate the hinges of the door.
11. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
12. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
13. If any corrections or repairs are necessary submit a request for work order.
14. Clean up area and dispose of trash properly.
15. Review with customer for operational problems and trends.
16. Identify customer contacted
17. Log all items shown above on inspection sheet.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-3 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
TOILET ANNUAL
PM0046 0.15
1. Vacuum breaker-type:
A. Flush and adjust water flow if required.
B. Inspect for missing or damaged parts/caps, seat supports, and replace.
C. Fill out maintenance checklist and report deficiencies.
2. Tank-type:
A. Clean flapper seat if leaking, adjust fill level if required.
B. Inspect for missing or damaged parts/caps, seat supports, and replace.
C. Fill out maintenance checklist and report deficiencies.
3. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
4. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
5. If any corrections or repairs are necessary submit a request for work order.
6. Clean up area and dispose of trash properly.
7. Review with customer for operational problems and trends. Identify customer contacted.
URINAL ANNUAL
PM0047 0.15
LAVATORY ANNUAL
PM0048 0.15
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-4 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
SHOWER ANNUAL
PM0049 0.15
1. Activate the unit to flush the line and verify proper operation.
2. Assure that area is free of obstructions, that activation mechanisms are accessible to personnel
in a distressed condition.
3. Operate valve in full open and close position. Loss of ability to close tightly will require
inspection of valve seals and discs for wear and contaminate build-up.
4. Check systems for cleanliness and clean if necessary.
5. Safety shower:
A. Place trash can under shower.
B. Hold butterfly net around shower and place bottom of net into trash can.
C. Pull handle to turn on water.
D. Let water run for 5 - 10 seconds.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-5 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Test and calibrate check valve operation of backflow prevention device with test set.
2. Inspect for leaks under pressure.
3. Clean backflow preventer and surrounding area.
4. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
5. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
6. If any corrections or repairs are necessary submit a request for work order.
7. Clean up area and dispose of trash properly.
8. Review with customer for operational problems and trends. Identify customer contacted.
9. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-6 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-7 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-8 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
8. Check electrical wiring for fraying and loose connections on oil burner.
9. Check for proper water temperature setting; adjust as required.
10. Check condition of flue pipe, and chimney.
11. Drain sediment from tank.
12. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
13. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
14. If any corrections or repairs are necessary submit a request for work order.
15. Clean up area and dispose of trash properly.
16. Review with customer for operational problems and trends. Identify customer contacted.
17. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-9 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-10 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-11 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-12 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-13 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Prior to end of heating season, adjust oil deliveries so oil will be nearly consumed.
2. Remove manhole.
3. Pump oil tank down to within 6" of bottom of tank.
4. Pump sludge from bottom of tank and flush. Dispose of appropriately. If the material removed
from the tank is hazardous waste, contact the regional S&EM office for instructions.
5. Disconnect heating coil, remove from tank and clean.
6. Examine tank for leaks, condition of piping connections.
7. Inspect tank for corrosion.
8. Inspect floating tank roof, lifter or cone, and automatic float gauge, if applicable
9. Check for leaks on suction and discharge piping, seals, packing, etc.
10. Make minor adjustments as required.
11. Check pumps and motors operation for excessive vibration, noise, and overheating.
12. Check pump controller for proper operation.
13. Lubricate pumps and motors.
14. Clean and adjust oil transfer pumps (oil or steam driven).
15. Examine, clean, and adjust operation of strainers, traps, control valves, oil flow meter, oil
temperature and pressure gauges.
16. Check floats and leveling devices in tank. Check float adjustment with depth level indicators.
17. Clean breather vents, conservation vents, and flame arrestors where appropriate.
18. Clean condensate return unit and surrounding area.
19. Log all items shown above on inspection sheet.
20. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
21. If any corrections or repairs submit a request for work order.
22. Clean up area and dispose of trash properly.
23. Review with customer for operational problems and trends. Identify customer contacted.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-14 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Close building air intake vents within the vicinity of the cooling tower until the cleaning
procedure is complete.
2. Shut down, drain, and flush the cooling tower with water:
A. Check with state to determine if there are any restrictions on discharging the water.
B. Isolate the cooling tower from the rest of the condenser water system where applicable.
3. Clean the wet deck, remove all debris, and dispose of properly. If the wet deck panels contains
asbestos, follow the asbestos management plan for isolation, notification, work practice, and
waste disposal.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-15 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
4. Inspect the tower, the tower basin and holding tank for sediment and sludge, and any biological
growth.
5. Using low pressure water hose or brushes, clean the tower, floor, sump, fill, spray pans and
nozzles and removable components such as access hatches, ball float, and other fittings until all
surfaces are clean and free of loose material. Porous surfaces such as wooden and ceramic tile
towers will require additional cleaning and brushing.
6. Clean cracks and crevices where buildup is not reached by water treatment.
7. Clean all system strainers and strainer housings.
8. Remove drift eliminators and clean thoroughly using a hose, steam, or chemical cleanser.
9. Check fan and air inlet screens and remove any dirt or debris.
10. Reassemble components, and fill tower and cooling system with water.
11. Monitor the water ph and maintain ph within a range of 7.5 to 8.0. The ph can be monitored
with litmus paper or a ph meter.
12. If a more thorough disinfectant cleaning is needed; perform the following:
A. Add a silicate-based low or non-foaming detergent as a dispersant at a dosage of 10-25
pounds per thousand gallons of water in the system. Use a silicate-based low or non-
foaming detergent such as cascade®, calgonite®, or equivalent product.
B. If the total volume of water in the system is not known, it can be estimated to be ten
(10) times the recirculating rate (gallons per minute) or 30 gallons per ton of
refrigeration capacity.
C. The dispersant is best added by first dissolving it in water and adding the solution to a
turbulent generalist in the water system, such as the cooling tower basin near the pump
suction.
D. Contact a professional water treatment specialist for a dispersant which may be safely
used without interfering with the operation of the system.
13. Add chlorine disinfectant to achieve 25 parts per million (ppm) of free residual chlorine:
A. Maintain 10 ppm of free residual chlorine in water returning to the cooling tower for 24
hours.
B. A swimming pool test kit may be used to monitor the chlorine.
C. Follow the manufacturer's instructions.
D. Test papers such as those used to monitor
E. Restaurant sanitizing tanks may also be used.
F. Monitor every 15 minutes for two hours to maintain the 10 ppm level. Add chlorine as
needed to maintain this level.
G. Two hours after the slug dose or after three measurements are stable at 10 ppm of free
residual chlorine, monitor at two hour intervals to maintain the 10 ppm of free residual
chlorine.
H. Some kits cannot measure 10 ppm. In this case dilute the test sample with distilled
water to bring it within the test set range.
14. After 24 hours, drain the system (check with state to determine if there are any restrictions on
discharging the water).
15. Adjust bleed, float, central valve for desired water level.
16. Open any building air vents that were closed prior to the cleaning of the cooling tower.
17. Implement an effective routine treatment program for microbial control.
18. Document all maintenance and cleaning procedures by date and time. Record the brand name
and the volume or weight of chemicals used.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-16 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-17 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-18 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
E. Some kits cannot measure 10 ppm. In this case dilute the test sample with distilled
water to bring it within the test set range.
32. After 24 hours, drain the system (check with state to determine if there are any restrictions on
discharging the water).
33. Adjust bleed, float, and central valve for desired water level.
34. Open any building air vents that were closed prior to the cleaning of the cooling tower.
35. Implement an effective routine treatment program for microbial control.
36. Document all maintenance and cleaning procedures by date and time.
37. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
38. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
39. If any corrections or repairs are necessary submit a request for work order.
40. Clean up area and dispose of trash properly.
41. Review with customer for operational problems and trends. Identify customer contacted.
42. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-19 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-20 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-21 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Make sure the access door is reasonably air tight and latches properly.
2. If the damper is closed, check for a ruptured fusible link, broken attachment or hinges,
corrosion, or damage.
3. Remove the fusible link and operate the damper to verify that it is self-closing and fully closes
and latches.
4. Operate damper with normal system airflow to assure that they are not held open by the air
stream.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-22 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-23 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
12. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
13. If any corrections or repairs are necessary submit a request for work order.
14. Clean up area and dispose of trash properly.
15. Review with customer for operational problems and trends. Identify customer contacted.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-24 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-25 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
13. Close discharge valve. Bleed off pressure but do not drain pump. Observe pressure gauges for
signs that the discharge and suction valves are not closing tightly.
14. Lubricate pump and motor bearings. Do not over-lubricate.
15. Use a torque wrench to check the tightness of all bolts, especially the bolts of cast iron pumps.
16. Closely inspect the pump-motor coupling.
17. Check motor and pump alignment.
18. Inspect and clean suction strainers and blowdown valves.
19. Clean pump and casing surfaces.
20. Check that base bolts are securely fastened.
21. After shut-down, drain pump housing, check suction, discharge and check valve for holding.
22. Remove cover gland and packing.
23. Remove corrosion from impeller shaft and housing cover.
24. On pumps with oil ring lubricated bearings, drain oil, flush, and fill to proper oil level with new
approved type oil.
25. Inspect water rings, seals, and impeller.
26. Clean pump suction strainers, and pump packing water seal filter/strainer.
27. Replace packing, and reassemble.
28. Start and stop pump, noting vibration, pressure, and action of check valve.
29. Adjust packing.
30. Lubricate impeller shaft bearings. Do not over lubricate.
31. Check motor and pump alignment.
32. Check drive shaft coupling.
33. Clean up work area and remove all debris.
34. Addendum: centrifugal pump HVAC technician packing:
A. Disconnect and remove pump/motor coupling from pump shaft.
B. Clean external pump housing and shaft, remove flange on pump housing to remove
pump HVAC technician seal assembly while noting how the seal is assembled on the
shaft and in the pump housing.
C. After old seal has been removed, clean surfaces of shaft sleeve. If this sleeve is galled or
damaged, a new seal will not hold for long. It is best to replace the shaft sleeve at this
time. If the shaft sleeve is not damaged, follow seal manufacturer's instructions and
install new HVAC technician seal. Install new pump housing O-ring or gasket, reinstall
pump housing. Slowly open discharge and suction valve, then rotate pump shaft to
assist in setting HVAC technician seal.
D. Check alignment of pump and motor couplings. The use of shims may be necessary
under the motor or pump to align the pump coupling with the motor coupling.
E. Examine both suction and discharge pressure gauges if they are not registering 0 psig.
Replace one or both gauges if defective. Open pump suction and discharge valves, vent
air out of pump housing. Log static pressure, if any, from pump suction gauge.
F. Start pump motor, record pump operating suction and discharge pressures. Any unusual
noises should be investigated and corrected before allowing pump to be put back in
service. Record pump motor voltage and operating amps.
G. Restore pump to service, remove tag.
35. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
36. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
37. If any corrections or repairs are necessary submit a request for work order.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-26 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Check to see that operating control stat activates damper per design specifications. Replace if
malfunctioning.
2. Check damper linkage for tightness or damage. Lightly oil moving parts.
3. Inspect dampers for free movement in duct or mixing box. Replace felt or other type seals as
required.
4. Inspect mixing box and connecting ducts for air leaks. Correct leaks with duct tape or tighten
connections as required.
5. Inspect damper activators for tightness to mounting brackets.
6. Tighten electrical connections to servomotors. Clean vent ports.
7. If pneumatic actuator does not stroke properly, correct sticking valve stem or binding linkage.
8. Replace diaphragm if necessary.
9. Inspect for air leaks around actuator and in air line between controller and actuator.
10. Check unit for noise and vibration.
11. Check v-belt condition and tension. Adjust or replace as necessary.
12. Clean and wash permanent filters.
13. Recharge wire mesh filters with oil.
14. Replace disposable filters.
15. Lubricate fan shaft bearings if not sealed.
16. Lubricate motor bearings sparingly, using SAE 10w motor oil if not sealed.
17. Clean coils by vacuuming or brushing.
18. Clean fan blades and interior surfaces of unit to remove soil.
19. Damp wipe exterior surfaces.
20. Clean up work area.
1. Check with operating or area personnel for deficiencies before shutting off units.
2. Lockout exhaust fan at disconnect and hang "lockout" sign.
3. Hang "out of service" sign on fume hood(s).
4. Check v belt if applicable.
A. Check belts for cracks, fraying, and other signs of wear, replace as needed.
B. With a straight edge, check for belt alignment by putting a straight edge on sheaves.
C. Check the belt tension. The proper "feel" is when the belt has a "springy" action when
struck with the hand. If there is insufficient tension the belt will feel loose or dead when
struck. Too much tension will cause the belts to feel taut.
5. Check the sheaves:
A. Look for a dished condition in the groove or shoulders on the side wall of the groove. If
any of these conditions are found, excessive wear has taken place.
B. If the sheave isn't replaced the shoulders will quickly chew off the bottom corners of the
new belt.
6. Lubricate the fan bearing.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-27 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-28 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-29 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-30 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-31 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-32 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
33. If any corrections or repairs are necessary submit a request for work order.
34. Clean up area and dispose of trash properly.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-33 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-34 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
4. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
5. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
6. If any corrections or repairs are necessary submit a request for work order.
7. Clean up area and dispose of trash properly.
8. Review with customer for operational problems and trends. Identify customer contacted.
9. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-35 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
9. Drain and clean humidifier drip pan, if applicable. Remove corrosion; prime, and paint as
needed.
10. Lubricate motor and fan bearings, if not sealed.
11. Check alignment of motor and fan.
12. Replace prefilters if needed.
13. Replace final filters if needed.
14. Check compressor oil level, if compressor has an oil sight glass.
15. Remove lockout tag and start unit.
16. Run machine, check action of controls, relays, switches, etc., to see that:
A. Compressor runs at proper settings.
B. Reheat coils activate properly.
C. Humidistat activates humidifier.
D. Suction and discharge pressures are proper.
E. Discharge air pressure is set properly.
17. Check and tighten any loose unit electrical terminals, disconnect switches, or connectors.
18. Check and adjust vibration eliminators. Replace if required.
19. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
20. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
21. If any corrections or repairs are necessary submit a request for work order.
22. Clean up area and dispose of trash properly.
23. Review with customer for operational problems and trends. Identify customer contacted.
24. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-36 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Clean, lubricate and adjust all electro-HVAC technician components (printers, relays, graphic
projectors, command buttons and switches).
2. Test data transmission to and from remote panels and input/output devices. Recalibrate and/or
repair.
3. Verify command functions by observing resultant action (on-off, open-close, etc.).
4. Test alarm report devices and subsystems and analyze visual, audible and printed annunciation.
Clean, recalibrate, repair or replace defective components.
5. Test scanning system. Repair if necessary. Note: systems incorporating open type relays should
be cleaned.
6. Check operating data. Analyze for accuracy.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-37 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
11. Check & tighten all connectors at disconnect switches and motor connector.
12. Record VFD at normal performance:
Speed: __________; load: __________; volts: _________.
13. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
14. If any corrections or repairs are necessary submit a request for work order.
15. Clean up area and dispose of trash properly.
16. Review with customer for operational problems and trends. Identify customer contacted.
17. Log all items shown above on inspection sheet.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-38 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Disarm the fire bells at the fire control panel. Fire doors and flashing lights will still operate.
2. Using the radio, inform the engineer at the fire control panel of your location, and then activate
the tamper switch valve.
3. Turn valve to fully closed and then to fully open.
4. The engineer at the fire control panel will then verify by radio that the audio and light alarms are
working properly, then silence and reset the panel and inform the roving engineer by radio that
the panel has been reset.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-39 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
5. The roving engineer will then activate the water flow switch at the same location by opening the
test valve.
6. Note: the water flow alarm may not activate immediately. Wait up to one minute for the alarm
to activate. If it does, continue testing. If the alarm does not activate, note the location and
inform tele-fire of same.
7. The engineer at the fire control panel will then verify by radio that the audio and light alarms are
working properly, then silence and reset the panel and inform the roving engineer by radio that
the panel has been reset.
8. Continue testing at each location systematically, indicating location, tamper switch, water flow.
9. Notify building operator and energy management that testing is completed.
10. Have CBX announce that testing is completed.
11. For additional guidance on performing tests, see NFPA 72,1999 edition (table 7-3.2)
12. Make sure all data is correct on work order (location, make, model #, size, hp, serial number,
installation date, outlet pipe size).
13. If any corrections or repairs submit a request for work order.
14. Clean up area and dispose of trash properly.
15. Review with customer for operational problems and trends. Identify customer contacted.
16. Log all items shown above on inspection sheet.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-40 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
19. The pressure relief valve shall be inspected so as to ensure that the pressure downstream of the
relief valve fittings in the fire pump does not exceed the pressure for which the system
components are rated.
20. Check oil level in vertical motor sight glass (bearings).
21. Clean up area and dispose of trash properly.
22. Review with customer for operational problems and trends. Identify customer contacted.
23. Log all items shown above on inspection sheet.
24. For additional guidance on performing tests, see NFPA 25, 1998 edition.
25. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
26. Report deficiencies to all inspections, samples, disposal, cleanups or decontamination
27. If any corrections or repairs are necessary submit a request for work order
28. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-41 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-42 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
12. Check and inspect pneumatic system for physical damage and proper operation. Make minor
adjustments as required.
13. Trip test deluge system (control valve closed); make minor adjustments as necessary
14. Restore system to fully operational condition.
15. Inspect OS&Y and PIV cut-off valves for open position.
16. Clean area around system components.
17. Ensure that system is restored to proper operating condition.
18. Fill out maintenance checklist and report deficiencies.
1. Check nozzles for damage; that nozzle caps (if installed) are in place, and that nozzles are
properly aligned for the hazard being protected.
2. Check for signs of physical damage to all system components. Have damaged components
checked and replaced or repaired accordingly.
3. Check entire piping systems and cylinders for signs of leakage and adequate support.
4. Check cylinder pressures, if provided, for proper pressure. Service system if pressures are
outside of operable range.
5. Check for grease accumulation on the fusible links and nozzles on systems protecting cooking
equipment.
6. Check that manual system actuators are not obstructed.
7. Check that seals or tamper indicators are intact.
8. Verify that any detection system(s) used to activate the extinguishing system is operational.
9. Verify that there are no changes in the size or type of hazard being protected and that no
alterations have been made to the equipment or room being protected.
10. Where total flooding extinguishing systems protect space, verify that all doors are not blocked
and will be free to close with system activation.
11. Initial and date inspection tag.
12. Clean up area and dispose of trash properly.
13. Review with customer for operational problems and trends. Identify customer contacted.
14. Log all items shown above on inspection sheet.
15. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
16. Report deficiencies to all inspections, samples, disposal, cleanups or decontamination.
17. If any corrections or repairs are necessary submit a request for work order.
18. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-43 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-44 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-45 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-46 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-47 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-48 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-49 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Disassemble fixture. Wash all removable parts with warm water and a mild detergent. Rinse and
allow to drip-dry.
2. Damp wipe remaining body of fixture in place.
3. Remove old fluorescent lamps and install new lamps.
4. Test light fixture. Replace starters, where necessary. Note and report any needed electrical
repairs.
5. Reassemble all removable parts to fixture.
6. Clean up area and remove any trash.
SPOTLIGHTS MONTHLY
PM0308 1.50
1. Inspect the cabinet for damage (exterior and interior) including locks, door hinges, and plastic
covers.
2. Check all lamps/LEDs (including remote annunciators).
3. Check all fuses.
4. Check power supply output voltage in normal and under load conditions.
5. Check standby battery voltage under load for a minimum of 5 minutes (if applicable).
6. Check battery charge current (be sure it is within manufacturer's limits).
7. Verify trouble signals by opening all supervised circuits one at a time (Class A circuits open two
return wires; Class B circuits open end of the line device).
8. Verify ring back feature for systems using a trouble silencing switch which requires resetting.
9. When panel has disconnect and isolating switches, verify that each switch performs its intended
function and a trouble signal is received when a supervised function is disconnected.
10. Check for proper alarm on all input circuits.
11. Verify return to normal operation after each alarm circuit input.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-50 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
12. Verify for proper reset (either automatic or manual) of the trouble signal when the circuits are
closed.
13. Verify for proper contact closure and signal transmission for all panel modes of operation
(trouble, alarm, ground, etc.).
14. When system has ground detection feature, verify that a ground fault indication is given
whenever any installation conductor is grounded.
15. Verify transmission of signals to main fire alarm control panel:
A. Actuate an appropriate initiating device and verify that alarm signal is received at the
main fire alarm control panel.
B. Create a trouble condition and verify that a trouble signal is received at the main fire
alarm control panel.
C. Actuate a supervisory device and verify that a supervisory signal is received at the main
fire alarm control panel.
D. If transmission carrier is capable of operation under a single or multiple fault condition,
activate an initiating device during such fault condition and verify that a trouble signal is
received at the main fire alarm control panel in addition to the alarm signal.
16. Verify for proper operation and confirm proper identification for all remote annunciators. When
provided, verify proper operation under a fault condition.
17. Test electrically operated release devices (control heads).
18. Test manual overrides electrically to cause direct actuation of release devices.
19. Test cross-generalist systems by operating one sensor or detector on each generalist. Verify that
correct sequence of alarms, release devices, and auxiliary functions occurs with operation of
first generalist and then with operation of second generalist.
20. Test abort feature by operating the abort approximately in the middle of the time interval.
Verify correct sequence and operation. At the end of the time interval, confirm that the aborted
functions did not occur.
21. Test the manual override device over the abort feature.
22. Test matrix type circuit by operating all sensors in system. Verify correct matrix develops with
each sensor operated.
23. Test verified, sequential, or counting generalist type circuits by operating required sensors at a
minimum of four locations in circuit. Verify correct sequence with both the first and second
detector in alarm.
24. Verify operation of solenoid release circuits.
25. Test squib release circuits by using AGI flashbulb or other test light acceptable to the
manufacturer. Verify operation of flashbulb or light.
26. Check all meters in panel for proper operation and deflection.
27. Check modules in panel for signs of heat or deterioration.
28. Check standby batteries (if located in the panel) for signs of overcharging, heat, and leakage.
29. Clean interior of panel.
30. Return all circuits and subsystems to normal. Leave panel in normal operating condition with
door locked.
31. Inform involved personnel that testing is complete.
32. Clean up area and dispose of trash properly.
33. Review with customer for operational problems and trends.
34. Identify customer contacted.
35. Log all items shown above on inspection sheet.
36. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-51 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
37. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
38. If any corrections or repairs are necessary submit a request for work order.
39. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
1. Travel to site.
2. Present yourself to the customer. Let them know you will be interrupting the phone line their
security alarm seizes.
3. ID the phone line for the customer.
4. Test all generalists for communications to the police department.
5. Check prints for accuracy.
6. Modify system programs to current update status.
7. Check for loose connections.
8. Check battery condition.
9. Check with central station for proper reporting
10. Check for proper signage & alarm decals.
11. Communicate alarm system condition to customer.
12. For additional guidance on performing tests, see NFPA 72,1999 edition (table 7-3.2)
13. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
14. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
15. If any corrections or repairs are necessary submit a request for work order.
16. Clean up area and dispose of trash properly.
17. Review with customer for operational problems and trends. Identify customer contacted.
18. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
1. Notify building personnel and energy management that fire pull stations pm will be taking place.
Have them announce the test.
2. Call notified fire monitor station to put system on test.
3. At the fire control panel, disable audible & flashing light on all floors.
4. Using the radio, inform the engineer at the fire control panel of your location. Then using the
fire control panel key, activate the fire pull station by opening the cover. The engineer at the fire
control panel will verify by radio that the audio and light alarms are working properly, then
silence and reset the panel and inform the roving engineer by radio that the panel has been
reset.
5. Close and lock the fire pull station and continue testing.
6. At the completion of the test, put all disable floor audible & light back to service, and call
monitor station to back on normal services.
7. Notify building tenants and energy management that testing is completed. Have them announce
that testing is completed.
8. Log any discrepancies under comments and notify foreman of same.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-52 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-53 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
9. Review with customer for operational problems and trends. Identify customer contacted.
10. Log all items shown above on inspection sheet.
11. For additional guidance on performing tests, see NFPA 72,1999 edition (Table 7-3.2)
12. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
13. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
14. If any corrections or repairs are necessary submit a request for work order.
15. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
1. Check to make sure that there are no obstructions that could block the flow of air.
2. Also make sure that the area is clean and that rags etc. Are not left on or near the generator set.
3. Add coolant as necessary to bring level up to within about 1/2" of the filler neck.
4. Remove dirt and debris from radiator fins, and check for leaks.
5. Make visual check of radiator fan, and water pump drive belts to ensure they are tight and in
good condition.
6. Record fuel reading prior to test.
7. Check "open" the fuel shutoff valve.
8. Ensure fuel solenoid disconnect switch is in the "on" position.
9. Observe air cleaner components to make sure they are tight and in proper position to prevent
unfiltered air from entering engine.
10. Inspect battery cables for cracking and loose connections.
11. Keep electrolyte at the proper level above the plates by adding distilled water.
12. Check battery charger switch in the on position.
13. Record battery voltage.
14. Check and add oil as necessary to bring the level up to the full mark on the dip stick.
15. Press lamp test button and check to make sure lamps provided on the panel are operational.
16. Record registered running hours.
17. Check generator main circuit breaker closed.
18. Note: before proceeding to run test, the electrical shop may need to conduct their monthly PM
of transferring their emergency lighting loads to the generator.
19. If generator has an automatic start control, start the generator by shutting off power to the
sensor -or- for generators without auto start, place the start switch in the "on" or "run" position.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-54 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Check to make sure that there are no obstructions that could block the flow of air.
2. Make sure the area is clean and that rags, etc., are not left on or near the generator set.
3. Add coolant as necessary to bring level up to within about 1/2 inch of the filler neck.
4. Remove dirt and debris from radiator fins, and check for leaks.
5. Make visual check of radiator fan, and water pump drive belts to ensure they are tight and in
good condition.
6. Record fuel reading prior to test. Fuel level: _________.
7. Check 'open' the fuel shutoff valve.
8. Ensure fuel solenoid disconnect switch is in the "on" position.
9. Observe air cleaner components to make sure they are tight and in proper position to prevent
unfiltered air from entering engine.
10. Inspect battery cables for cracking and loose connections.
11. Keep electrolyte at the proper level above the plates by adding distilled water.
12. Check battery charger switch in the on position.
13. Record battery voltage.
14. Check and add oil as necessary to bring the level up to the full mark on the dip stick
15. Press lamp test button and check to make sure lamps provided on the panel are operational.
16. Record registered running hours
17. Check generator main circuit breaker closed.
18. Record cranking time.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-55 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-56 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
G. Amps C phase.
H. Hertz.
I. Engine oil pressure.
J. Engine cooling temperature.
4. End of test:
A. Transfer time emergency to normal.
B. Engine cool down time (minutes).
C. Run engine at no load.
D. Test engine over speed.
E. Test engine high temperature safety.
F. Test engine low oil pressure.
5. Check diesel fuel level.
6. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
7. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
8. If any corrections or repairs are necessary submit a request for work order.
9. Clean up area and dispose of trash properly.
10. Review with customer for operational problems and trends. Identify customer contacted.
11. Notify your supervisor of any deficiencies that need to be scheduled for repairs.
1. Check to make sure that there are no obstructions that could block the flow of air.
2. Make sure that the area is clean and that rags etc. Are not left on or near the generator set.
3. Add coolant as necessary to bring level up to within about 1/2" of the filler neck.
4. Remove dirt and debris from radiator fins; check for leaks.
5. Make visual check of radiator fan, and water pump drive belts to ensure they are tight and in
good condition.
6. Record fuel reading prior to test ___________.
7. Check "open" the fuel shutoff valve.
8. Ensure fuel solenoid disconnect switch is in the "on" position.
9. Observe air cleaner components to make sure they are tight and in proper position to prevent
unfiltered air from entering engine.
10. Inspect cables for cracking and loose connections.
11. Keep electrolyte at the proper level above the plates by adding distilled water.
12. Battery charger switch in "on" position.
13. Record battery voltage___________.
14. Check and add oil as necessary to bring the level up to the full mark on the dipstick.
15. Press lamp test button and check to make sure lamps provided on the panel are operational.
16. Record registered running hours.
17. Check generator main circuit breaker closed.
18. Note: before proceeding to run tests, the electrical shop may need to conduct their monthly PM
of transferring their emergency lighting loads to the generator.
19. If generator has an automatic start control, start the generator by shutting off power to the
sensor. For generators without auto start, place start switch in the "on" or "run" position.
A. Record cranking time.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-57 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Check to make sure that there are no obstructions that could block the flow of air.
2. Also make sure that the area is clean and that rags, etc. are not left on or near the generator set.
3. Add coolant as necessary to bring level up to within about 1/2" of the filler neck.
4. Remove dirt and debris from radiator fins; check for leaks.
5. Make visual check of radiator fan, and water pump drive belts to ensure they are tight and in
good condition.
6. Record fuel reading prior to test.
7. Check "open" the fuel shutoff valve.
8. Ensure fuel solenoid disconnect switch is in the "on" position.
9. Observe components to make sure they are tight and in proper position to prevent unfiltered air
from entering engine.
10. Inspect cables for cracking and loose connections.
11. Keep electrolyte at the proper level about the plates by adding distilled water.
12. Battery chargers switch in “on” position.
13. Record battery voltage.
14. Check and add oil as necessary to bring the level up to the full mark on the dipstick.
15. Press lamp test button and check to make sure lamps provided on the panel are operational.
16. Record registered running hours.
17. Check generator main circuit breaker closed.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-58 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
18. Note: before proceeding to run test the electrical shop may need to conduct their monthly PM
of transferring their emergency lighting loads to the generator.
19. If generator has an automatic start control, start the generator by shutting off power to the
sensor. For generators without auto start, place start switch in the "on" or "run" position:
A. Record cranking time.
B. Record starting time.
C. Record the unloaded frequency.
20. When the generator is loaded record the following:
A. Oil pressure (when generator is loaded).
B. Water temperature (when generator is loaded).
C. Volts (when generator is loaded).
D. Amps (when generator is loaded).
E. Frequency (when generator is loaded).
F. Ammeter for battery charging rate (when generator is loaded).
21. Record running time with loads (25 minutes min)
22. Allow internal engine temperatures to equalize by idling the engine for at least 7 minutes.
23. Turn the start switch to off. Place switch in "ready" status.
24. Record time after test.
25. Record new running hours.
26. Fuel reading after test.
27. Quantity of fuel used.
28. Upon completion of test, double check all equipment such as switches, air compressor, indicator
lights, fuel level and fuel stop valve to ensure that the emergency generator is in a "ready"
status.
29. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
30. If any corrections or repairs submit a request for work order.
31. Clean up area and dispose of trash properly.
32. Review with customer for operational problems and trends. Identify customer contacted.
33. Log all items shown above on inspection sheet.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-59 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
D. Procedure used to inspect and adjust ignition timing. Record on attached template.
E. Name of certified mechanic. Record on attached template.
F. Check to make sure that there are no obstructions that could block the flow of air.
3. Also make sure that the area is clean and that rags, etc. are not left on or near the generator set.
4. Coolant level - add coolant as necessary to bring level up to within about 1/2" of the filler neck.
5. Remove dirt and debris from radiator fins; check for leaks.
6. Make visual check of radiator fan, and water pump drive belts to ensure they are tight and in
good condition.
7. Record reading prior to test.
8. Check "open" the fuel shutoff valve.
9. Ensure fuel solenoid disconnect switch is in the "on" position.
10. Air cleaner - observe components to make sure they are tight and in proper position to prevent
unfiltered air from entering engine.
11. Inspect cables for cracking and loose connections.
12. Keep electrolyte at the proper level above the plates by adding distilled water.
13. Battery charger switch in “on” position.
14. Record battery voltage.
15. Check and add oil as necessary to bring the level up to the full mark on the dipstick.
16. Press lamp test button and check to make sure lamps provided on the panel are operational.
17. Record registered running hours.
18. Check generators main circuit breaker closed.
19. If generator has an automatic start control, start the generator by shutting off power to the
sensor. For generators without auto start, place start switch in the "on" or "run" position.
20. Record cranking time.
21. Record starting time.
22. Record the unloaded frequency.
23. When the generator is loaded record the following:
A. Oil pressure
B. Water temperature
C. Volts
D. Amps
E. Frequency
F. Ammeter for battery charging rate
24. Record running time with loads (25 minutes min)
25. Allow internal engine temperatures to equalize by idling the engine for at least 7 minutes.
26. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
27. If any corrections or repairs submit a request for work order.
28. Clean up area and dispose of trash properly.
29. Review with customer for operational problems and trends. Identify customer contacted.
30. Log all items shown above on inspection sheet.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-60 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
4. Relamp as necessary.
5. If exit sign does not work correctly, replace it with a new one.
6. Dispose of lamps in proper waste receptacles.
7. Check all emergency lighting. Pull plug – check to see if light comes on.
8. Plug unit back in and push test button to see if light comes on.
9. Replace battery if necessary.
10. Replace lamp if necessary.
11. Dispose of battery properly as hazmat material.
12. Clean up area and dispose of trash properly.
13. Review with customer for operational problems and trends. Identify customer contacted.
14. Log all items shown above on inspection sheet.
1. Check monitor/mimic display to ensure UPS is configured for normal operation: all breakers
closed.
2. Press the “select” button to reach main menu
3. Scroll using “up” and “down “buttons to get the status reports and select.
4. Scroll to present status and select.
5. Take readings on attached log sheet.
6. Exit present status and scroll to event history and select.
7. Scroll through the last month and record all events that occurred.
8. “SR” supervisor review logs prior to scanning.
9. At the battery string for each UPS, use a clamp-on ammeter to verify AC trickle current of 10 –
12a. Absence of current flow may indicate an open cell.
10. Make sure all nameplate data is correct on work order (location, make, model #, size, serial
number, installation date, etc.).
11. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
12. If any corrections or repairs are necessary submit a request for work order.
13. Clean up area and dispose of debris properly.
14. Review with customer for operational problems and trends. Identify customer contacted.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-61 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
GATE SEMIANNUAL
PM0408 2.00
1. Gates:
A. Inspect all pivot points, hinges, latches, etc.
B. Apply lubricant where needed, wiping off excess.
C. Check all locking devices. Lubricate as required.
D. Inspect center gate support rollers and lubricate as required.
E. Clean roller track of any debris.
F. Check bolts, fasteners, and mounting hardware; tighten or adjust as necessary.
G. Check for any obstructions that retard full swing or movement of the gate.
H. Check hold-open devices for proper operation. Lubricate as required.
2. Fences:
A. Check posts and corner posts, support guys, and horizontal bars between each support
post.
B. Check wire and anchor point; re-stretch and re-anchor if necessary.
C. Inspect fence anchors along the bottom of the fence at the point where the fence is
connected to the post.
D. Treat with galvanized protectant where rust has developed.
E. Apply weed control along entire base of fence. Consult the material safety data sheets
(MSDS) for hazardous ingredients and proper personal protective equipment (PPE).
FOUNTAIN ANNUAL
PM0411 4.00
1. Fall:
A. Drain fountain.
B. Remove fountain head(s).
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-62 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
C. Clean scale from head(s) after removing and install cover plate.
D. Clean bolts and spacers. Replace defective bolts as needed.
E. Check and clean fill tube, remove spacer pipe and cap fill tube.
F. Clean overflows and strainers.
2. Spring:
A. Remove fill tube cap, install spacer pipe and install fill tube.
B. Remove fountain head cover(s), if applicable, and install fountain head.
C. Clean basins.
D. Remove tags from valves and fill fountain.
E. Remove tags from pump and put into service.
F. Clean up area and dispose of trash properly.
3. Review with customer for operational problems and trends. Identify customer contacted.
4. Log all items shown above on inspection sheet.
1. Zone valves:
A. Check for proper operation.
B. Check for leakage.
2. Sprinkler heads:
A. Check nozzle and remove corrosion/encrustation.
B. Replace washers and/or O-rings if required.
C. Clean unit thoroughly and inspect for freedom of operation.
3. Rotating types:
A. Check throw regulator and spring assembly for tightness.
B. Lightly lubricate pivot arm and guide bushings.
C. Check adjustment screw and retaining spring.
4. Clean up work area on lawn; remove any debris around sprinkler heads.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-63 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-64 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-65 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-66 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
35. Make sure all nameplate data is correct on work order (location, make, model #, size, hp, serial
number, installation date, outlet pipe size, etc.).
36. Report deficiencies found during inspection, sampling, disposal, cleanup, or decontamination
activities to management.
37. If any corrections or repairs are necessary submit a request for work order.
38. Clean up area and dispose of trash properly.
39. Review with customer for operational problems and trends. Identify customer contacted.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-67 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-68 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
A. Pressure monitoring test: semiannually, after notification of the fire alarm monitoring
company, test the low pressure monitoring switch to verify that a supervisory signal is
transmitted.
B. Records of testing and maintenance, including laboratory reports shall be sent to the
inspector for the building immediately upon receipt. Additionally, copies of all records
shall be maintained in the building and shall be available upon request of the fire
department.
C. Fill out maintenance checklist and report deficiencies.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-69 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.7
1. Inspect bi-weekly for obvious signs of evenness of lighting, vandalism, surface dirt, or staining.
1. Inspect annually for signs of deterioration, cracks, separation of sealants or laminates, etc.
Document annual inspections with photographs and text.
2. Maintain a maintenance log.
3. Surface cleaning: for most surfaces, a mild, pH neutral soap in water with a potable water rinse
will remove most soiling. High pressure water sprayers are probably not necessary for regular
cleanings and can sometimes cause further damage to materials or assemblies. Low pressure
sprayers (less than 400 psi) or garden type hose nozzles are safer. Hot water cleaners may be
more effective in removing stubborn surface grime.
1. Inspect for extinguished LEDs, consistent brightness or flicker, smooth play of animations.
2. Document location of diode performance and replacement to determine any repeat problem
areas using a pre-designed documentation checklist.
3. Replace LED bars as needed. Bars will snap in place.
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.7-70 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix A.8
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page A.8-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 TTC PH1 B201102 WALL, EXTERIOR, PANEL W‐16A 2600 SF REPAIR 0.0078 0.0400 0.81 CARPENTER
1 TTC PH1 B201102 WALL, EXTERIOR, PANEL W‐18 GLASS REINF CONC PNL 92250 SF REPAIR 0.0078 0.0400 28.78 CARPENTER
1 TTC PH1 B201301 AWNING, EXTERIOR, PERFORATED METAL PANEL W‐1 PERF MTL PNLS 158000 SF REPAIR 0.0087 0.0400 54.98 CARPENTER
1 TTC PH1 B201501 HANDRAILS ‐ EXTERIOR 6500 LF REFINISH 0.0165 0.1000 10.73 PAINTER
1 TTC PH1 B202201 GLASS, CURTAIN WALL W‐2 22350 SF REPAIR 0.0015 0.2000 6.71 GLAZIER
1 TTC PH1 B202201 GLASS, CURTAIN WALL W‐3 19200 SF REPAIR 0.0015 0.2000 5.76 GLAZIER
1 TTC PH1 B202201 GLASS, CURTAIN WALL W‐4 5000 SF REPAIR 0.0015 0.2000 1.50 GLAZIER
1 TTC PH1 B203402 DOOR, OVERHEAD ROLL‐UP, POWERED 1 EA REPAIR 0.7900 0.1000 0.08 GENERALIST
1 TTC PH1 B203402 DOOR, OVERHEAD ROLL‐UP, POWERED DC 1 EA REPAIR 0.7900 0.1000 0.08 GENERALIST
1 TTC PH1 B203402 DOOR, OVERHEAD ROLL‐UP, POWERED RETAIL/LOADING 9 EA REPAIR 0.7900 0.1000 0.71 GENERALIST
1 TTC PH1 B203402 DOOR, OVERHEAD ROLL‐UP, POWERED RETAIL/LOADING 6 EA REPAIR 0.7900 0.1000 0.47 GENERALIST
1 TTC PH1 B203402 DOOR, OVERHEAD ROLL‐UP, POWERED RETAIL/LOADING 9 EA REPAIR 0.7900 0.1000 0.71 GENERALIST
1 TTC PH1 B203402 DOOR, OVERHEAD ROLL‐UP, POWERED RETAIL/LOADING 6 EA REPAIR 0.7900 0.1000 0.47 GENERALIST
1 TTC PH1 B203902 DOOR, SWINGING, POWERED AC 2 EA REPAIR 0.8400 0.1000 0.17 GENERALIST
1 TTC PH1 B203902 DOOR, SWINGING, POWERED DC 31 EA REPAIR 0.8400 0.1000 2.60 GENERALIST
1 TTC PH1 B302101 ROOF SKYLIGHT PARK LEVEL SKYLIGHT 354 20 SF REPAIR 0.5700 0.1667 33.64 GLAZIER
Page A-8.3
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 TTC PH1 C101401 PARTITIONS, TOILET BSF ADMIN BLDG 50 EA REPAIR 0.8400 0.2500 10.50 CARPENTER
1 TTC PH1 C102107 DOOR, SWINGING, INTERIOR, MANUAL 66 EA REPAIR 0.8400 0.1000 5.54 GENERALIST
1 TTC PH1 C102107 DOOR, SWINGING, INTERIOR, MANUAL AC 2 EA REPAIR 0.8400 0.1000 0.17 GENERALIST
1 TTC PH1 C102107 DOOR, SWINGING, INTERIOR, MANUAL AC 29 EA REPAIR 0.8400 0.1000 2.44 GENERALIST
1 TTC PH1 C102107 DOOR, SWINGING, INTERIOR, MANUAL DC 10 EA REPAIR 0.8400 0.1000 0.84 GENERALIST
1 TTC PH1 C102107 DOOR, SWINGING, INTERIOR, MANUAL DC 31 EA REPAIR 0.8400 0.1000 2.60 GENERALIST
1 TTC PH1 C102107 DOOR, SWINGING, INTERIOR, MANUAL RAMP MAIN 1 EA REPAIR 0.8400 0.1000 0.08 GENERALIST
1 TTC PH1 C102107 DOOR, SWINGING, INTERIOR, MANUAL SEALED DOOR 16 EA REPAIR 0.8400 0.1000 1.34 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED 40 EA REPAIR 0.8400 0.1000 3.36 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED AC 128 EA REPAIR 0.8400 0.1000 10.75 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED DC 79 EA REPAIR 0.8400 0.1000 6.64 GENERALIST
1 TTC PH1 C102108 DOOR, FIRE‐RATED DOOR CONTACT 4 EA REPAIR 0.8400 0.1000 0.34 GENERALIST
1 TTC PH1 C201401 HANDRAILS ‐ INTERIOR 6500 LF REFINISH 0.0165 0.2500 26.81 PAINTER
1 TTC PH1 C301101 WALL FINISH ‐ PAINT COMMON/BOH 324023 SF REPAIR 0.0006 0.0500 9.72 PAINTER
1 TTC PH1 C301101 WALL FINISH ‐ PAINT COMMON/BOH 10259 SF REPAIR 0.0006 0.0500 0.31 PAINTER
1 TTC PH1 C301103 WALL FINISH ‐ TILE, CERAMIC / STONE TRANSIT 4805 SF REPAIR 0.0031 0.1000 1.49 CARPENTER
1 TTC PH1 C301103 WALL FINISH ‐ TILE, CERAMIC / STONE COMMON/BOH 8810 SF REPAIR 0.0031 0.1000 2.73 CARPENTER
1 TTC PH1 C301103 WALL FINISH ‐ TILE, CERAMIC / STONE COMMON/BOH 6139 SF REPAIR 0.0031 0.1000 1.90 CARPENTER
1 TTC PH1 C301104 WALL FINISH ‐ GLASS TRANSIT 25932 SF REPAIR 0.0088 0.0400 9.13 GLAZIER
1 TTC PH1 C301104 WALL FINISH ‐ GLASS TRANSIT 1204 SF REPAIR 0.0088 0.0400 0.42 GLAZIER
1 TTC PH1 C301104 WALL FINISH ‐ GLASS COMMON/BOH 6368 SF REPAIR 0.0088 0.0400 2.24 GLAZIER
1 TTC PH1 C301104 WALL FINISH ‐ GLASS COMMON/BOH 12153 SF REPAIR 0.0088 0.0400 4.28 GLAZIER
1 TTC PH1 C301104 WALL FINISH ‐ GLASS COMMON/BOH 12853 SF REPAIR 0.0088 0.0400 4.52 GLAZIER
1 TTC PH1 C301104 WALL FINISH ‐ GLASS COMMON/BOH 8729 SF REPAIR 0.0088 0.0400 3.07 GLAZIER
Page A-8.4
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
FLOORING ‐ FLUID APPLIED, EPOXY / ACRYLIC /
1 TTC PH1 C302301 COMMON/BOH 8969 SF REPAIR 0.0011 0.0667 0.66 PAINTER
POLYURETHANE
FLOORING ‐ FLUID APPLIED, EPOXY / ACRYLIC /
1 TTC PH1 C302301 COMMON/BOH 88548 SF REPAIR 0.0011 0.0667 6.50 PAINTER
POLYURETHANE
1 TTC PH1 C302302 FLOORING ‐ FLUID APPLIED, PAINT OR CLEAR SEAL COMMON/BOH 43571 SF REPAIR 0.0015 0.0667 4.36 PAINTER
1 TTC PH1 C302401 FLOORING ‐ TERRAZZO/POLISHED CONCRETE COMMON/BOH 28556 SF REPAIR 0.0043 0.0667 8.19 CARPENTER
1 TTC PH1 C302401 FLOORING ‐ TERRAZZO/POLISHED CONCRETE BUS DECK WAITING 67247 SF REPAIR 0.0043 0.0667 19.29 CARPENTER
1 TTC PH1 C302402 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY DRIVER SUPPORT 622 SF REPAIR 0.0041 0.0667 0.17 CARPENTER
1 TTC PH1 C302402 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY DRIVER SUPPORT 202 SF REPAIR 0.0041 0.0667 0.06 CARPENTER
1 TTC PH1 C302402 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY COMMON/BOH 3446 SF REPAIR 0.0041 0.0667 0.94 CARPENTER
1 TTC PH1 C302402 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY COMMON/BOH 1144 SF REPAIR 0.0041 0.0667 0.31 CARPENTER
1 TTC PH1 C302403 FLOORING ‐ VINYL COMPOSITION TILE SECURITY 5772 SF REPAIR 0.0005 0.1111 0.32 CARPENTER
1 TTC PH1 C302501 FLOORING ‐ CARPET, TILE OR ROLL COMMON/BOH 8351 SF REPAIR 0.0008 0.2500 1.67 CARPENTER
1 TTC PH1 C303101 CEILING FINISH ‐ METAL OR SPECIALTY TILE COMMON/BOH 398 SF REPAIR 0.0066 0.1250 0.33 CARPENTER
1 TTC PH1 C303102 CEILING FINISH ‐ PAINTED OR STAINED COMMON/BOH 622 SF REPAIR 0.0015 0.0400 0.04 CARPENTER
1 TTC PH1 C303102 CEILING FINISH ‐ PAINTED OR STAINED COMMON/BOH 67247 SF REPAIR 0.0015 0.0400 4.03 CARPENTER
1 TTC PH1 C303102 CEILING FINISH ‐ PAINTED OR STAINED COMMON/BOH 30365 SF REPAIR 0.0015 0.0400 1.82 CARPENTER
1 TTC PH1 C303102 CEILING FINISH ‐ PAINTED OR STAINED COMMON/BOH 3628 SF REPAIR 0.0015 0.0400 0.22 CARPENTER
1 TTC PH1 C303102 CEILING FINISH ‐ PAINTED OR STAINED COMMON/BOH 34776 SF REPAIR 0.0015 0.0400 2.09 CARPENTER
1 TTC PH1 C303201 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE COMMON/BOH 202 SF REPAIR 0.0004 0.1111 0.01 CARPENTER
1 TTC PH1 C303201 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE COMMON/BOH 14612 SF REPAIR 0.0004 0.1111 0.65 CARPENTER
1 TTC PH1 C303201 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE COMMON/BOH 193 SF REPAIR 0.0004 0.1111 0.01 CARPENTER
1 TTC PH1 D201101 TOILET PHASE 1 35 EA REPLACE FLUSH VALVE 0.3300 0.1000 1.16 PLUMBER
1 TTC PH1 D201201 URINAL PHASE 1 7 EA REPLACE FLUSH VALVE 0.9000 0.1429 0.90 PLUMBER
1 TTC PH1 D201301 LAVATORY PHASE 1 38 EA VALVE SET 0.6400 0.1000 2.43 PLUMBER
Page A-8.5
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 TTC PH1 D201301 LAVATORY PHASE 1 39 EA VALVE SET 0.6400 0.1000 2.50 PLUMBER
1 TTC PH1 D201701 SHOWER PHASE 1 2 EA VALVE SET 0.6400 0.1000 0.13 PLUMBER
1 TTC PH1 D202102 PIPING, DOMESTIC COLD WATER PHASE 1 3.145 KLF RESOLDER JOINT 5.6800 0.1000 1.79 PLUMBER
1 TTC PH1 3.145 KLF REPLACE 10' SECT. 2.0999 0.0500 0.33 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐1‐A‐1 1 EA DRAIN & FLUSH 2.6700 0.1429 0.38 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐1‐B‐1 1 EA DRAIN & FLUSH 2.6700 0.1429 0.38 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐1‐D‐1T4 4 EA DRAIN & FLUSH 2.6700 0.1429 1.53 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐3‐A‐2 1 EA DRAIN & FLUSH 2.6700 0.1429 0.38 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐3‐D‐1T3 3 EA DRAIN & FLUSH 2.6700 0.1429 1.14 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B1‐A‐1 1 EA DRAIN & FLUSH 2.6700 0.1429 0.38 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B1‐C‐1 1 EA DRAIN & FLUSH 2.6700 0.1429 0.38 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B1‐D‐1 1 EA DRAIN & FLUSH 2.6700 0.1429 0.38 PLUMBER
1 TTC PH1 D202202 WATER HEATER, ELECTRIC EWH‐B2‐A‐1 1 EA DRAIN & FLUSH 2.6700 0.1429 0.38 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐1‐A‐2 1 EA DRAIN & FLUSH 4.0000 0.1429 0.57 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐2‐A‐1 2 EA DRAIN & FLUSH 4.0000 0.1429 1.14 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐3‐A‐1 1 EA DRAIN & FLUSH 4.0000 0.1429 0.57 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐3‐B‐1 1 EA DRAIN & FLUSH 4.0000 0.1429 0.57 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐4‐C‐1 1 EA DRAIN & FLUSH 4.0000 0.1429 0.57 PLUMBER
1 TTC PH1 D202204 WATER HEATER, NATURAL GAS EWH‐5‐A‐1 1 EA DRAIN & FLUSH 4.0000 0.1429 0.57 PLUMBER
1 TTC PH1 D202209 PIPING, DOMESTIC HOT WATER PHASE 1 0.51 KLF RESOLDER JOINT 5.6800 0.1000 0.29 PLUMBER
1 TTC PH1 D202209 PIPING, DOMESTIC HOT WATER PHASE 1 0.51 KLF REPLACE 10' SECT. 2.0999 0.0500 0.05 PLUMBER
1 TTC PH1 D202301 PUMP, DOMESTIC WATER DWP‐B2‐A‐1T3 3 EA OVERHAUL 0.6800 0.2000 0.41 PLUMBER
1 TTC PH1 D202301 PUMP, DOMESTIC WATER IRP‐B2‐A‐1,IRP‐B2‐A‐2 2 EA OVERHAUL 0.6800 0.2000 0.27 PLUMBER
1 TTC PH1 D203001 PIPING, SANITARY AND STORM PHASE 1 26.7 KLF REPLACE 10' SECT. 5.6700 0.0833 12.61 PLUMBER
1 TTC PH1 26.7 KLF GASKET & BOLTS 2.5999 0.0400 2.78 PLUMBER
SE‐B2‐A‐1&2,SE‐B2‐B‐1T4,SE‐
1 TTC PH1 D203402 PUMP, SEWAGE EJECTION 14 EA REPAIR 10.0000 0.2500 35.00 PLUMBER
B2‐C‐1T4,SE‐B2‐D‐1T4
1 TTC PH1 D204302 PUMP, SUMP ALL GWP & OFP 14 EA REPAIR 10.0000 0.2500 35.00 PLUMBER
Page A-8.6
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 TTC PH1 D204302 PUMP, SUMP ALL GWP/OZ 6 EA REPAIR 10.0000 0.2500 15.00 PLUMBER
1 TTC PH1 D204302 PUMP, SUMP ALL SPG 8 EA REPAIR 10.0000 0.2500 20.00 PLUMBER
SP‐B1‐A‐1&2,SP‐B1‐B‐1&2,SP‐
1 TTC PH1 D204302 PUMP, SUMP 6 EA REPAIR 10.0000 0.2500 15.00 PLUMBER
B1‐C‐1&2
SP‐B2‐A‐1T6,SP‐B2‐B‐1T6,SP‐
1 TTC PH1 D204302 PUMP, SUMP 24 EA REPAIR 10.0000 0.2500 60.00 PLUMBER
B2‐C‐1T6,SP‐B2‐D‐1T6
1 TTC PH1 D209101 PIPING, NATURAL GAS PHASE 1 3.5 KLF REPLACE 10' SECT. 2.3191 0.0833 0.68 PLUMBER
1 TTC PH1 3.5 KLF GASKET & BOLTS 1.6540 0.0400 0.23 PLUMBER
1 TTC PH1 D209907 PIPING, GRAY WATER PHASE 1 4.25 KLF RESOLDER JOINT 5.6800 0.1000 2.41 PLUMBER
1 TTC PH1 4.25 KLF REPLACE 10' SECT. 2.0999 0.0500 0.45 PLUMBER
1 TTC PH1 D301102 PUMP, FUEL OIL DIESEL PUMPS (DFP) 4 EA REPAIR 3.5300 0.1000 1.41 GENERATOR MECHANIC
1 TTC PH1 D301104 PIPING, FUEL PHASE 1 1.1 KLF RESOLDER JOINT 5.6800 0.1000 0.62 PLUMBER
1 TTC PH1 1.1 KLF REPLACE 10' SECT. 3.8999 0.0500 0.21 PLUMBER
1 TTC PH1 D303201 CONDENSING UNIT ACC‐B2‐A‐1&2,ACC‐B2‐D‐1&2 4 EA REPAIR 5.0000 0.1000 2.00 HVAC TECHNICIAN
1 TTC PH1 D304101 AIR HANDLING UNIT AHU‐B1‐A‐1 1 EA REPAIR 21.8200 0.1000 2.18 HVAC TECHNICIAN
1 TTC PH1 D304111 FAN, AXIAL SF‐B1‐C‐3,SF‐B1‐C‐4 2 EA REPAIR 4.0000 0.1000 0.80 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL SF‐B2‐A‐1,STP‐2‐A‐1 2 EA REPAIR 4.0000 0.1000 0.80 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL SF‐B2‐B‐1,SF‐B2‐B‐2 2 EA REPAIR 4.0000 0.1000 0.80 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL STP‐1‐A‐1,STP‐1‐A‐2,STP‐2‐D‐1 3 EA REPAIR 4.0000 0.1000 1.20 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL STP‐2‐B‐1 1 EA REPAIR 4.0000 0.1000 0.40 MECHANIC
1 TTC PH1 D304111 FAN, AXIAL STP‐B1‐C‐1,STP‐1‐B‐1 2 EA REPAIR 4.0000 0.1000 0.80 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL (16) EF FANS 16 EA REPAIR 2.4000 0.1000 3.84 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL (27) CF FANS 27 EA REPAIR 2.4000 0.1000 6.48 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐1‐A‐1 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐1‐A‐4,EF‐B1‐A‐2 2 EA REPAIR 2.4000 0.1000 0.48 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐1‐B‐1,EF‐B1‐A‐3 2 EA REPAIR 2.4000 0.1000 0.48 MECHANIC
EF‐1‐B‐2,EF‐1‐D‐1&2,EF‐2‐A‐
1 TTC PH1 D304112 FAN, CENTRIFUGAL 6 EA REPAIR 2.4000 0.1000 1.44 MECHANIC
3,EF‐2‐D‐1,EF‐3‐D‐3
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐2‐B‐2,EF‐B1‐A‐6 2 EA REPAIR 2.4000 0.1000 0.48 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐B1‐A‐4 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐B1‐A‐5 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL EF‐B1‐B‐1,EF‐B2‐A‐2 2 EA REPAIR 2.4000 0.1000 0.48 MECHANIC
Page A-8.7
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
SF‐1‐A‐1,SF‐1‐A‐2,SF‐1‐B‐1,SF‐3‐
1 TTC PH1 D304112 FAN, CENTRIFUGAL 4 EA REPAIR 2.4000 0.1000 0.96 MECHANIC
A‐1
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐2‐D‐1 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
SF‐B1‐A‐1T2,SF‐B1‐B‐2,SF‐B1‐C‐
1 TTC PH1 D304112 FAN, CENTRIFUGAL 5 EA REPAIR 2.4000 0.1000 1.20 MECHANIC
1&2
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐A‐3 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐A‐4 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐B‐1 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐B‐3 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL SF‐B1‐D‐1 1 EA REPAIR 2.4000 0.1000 0.24 MECHANIC
1 TTC PH1 D304112 FAN, CENTRIFUGAL TRANSFER FANS (TF) 19 EA REPAIR 2.4000 0.1000 4.56 MECHANIC
1 TTC PH1 D304113 FAN, MIXED FLOW EF‐B1‐D‐1 1 EA REPAIR 4.7000 0.1000 0.47 MECHANIC
1 TTC PH1 D304113 FAN, MIXED FLOW EF‐B2‐A‐1 1 EA REPAIR 4.7000 0.1000 0.47 MECHANIC
1 TTC PH1 D304118 VAV BOX 9 EA REPAIR 1.5500 0.1000 1.40 MECHANIC
1 TTC PH1 D304405 PUMP, HEATING HOT WATER HWP‐B1‐A‐1 1 EA REPAIR 0.6500 0.2000 0.13 MECHANIC
1 TTC PH1 D304405 PUMP, HEATING HOT WATER RFP‐B1‐C‐1 1 EA REPAIR 0.6500 0.2000 0.13 MECHANIC
1 TTC PH1 D304405 PUMP, HEATING HOT WATER RFP‐B1‐C‐2 3 EA REPAIR 0.6500 0.2000 0.39 MECHANIC
1 TTC PH1 D304411 PIPING, HEATING HOT WATER PHASE 1 10 KLF RESOLDER JOINT 5.6800 0.1000 5.68 PLUMBER
1 TTC PH1 10 KLF REPLACE 10' SECT. 3.8999 0.0500 1.95 PLUMBER
1 TTC PH1 D304501 PIPING, CHILLED OR CONDENSER WATER PHASE 1 82.624 KLF RESOLDER JOINT 5.6800 0.1000 46.93 PLUMBER
1 TTC PH1 82.624 KLF REPLACE 10' SECT. 3.8999 0.0500 16.11 PLUMBER
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B1‐A‐2 1 EA REPAIR 8.3300 0.1429 1.19 MECHANIC
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B2‐C‐1 1 EA REPAIR 8.3300 0.1429 1.19 MECHANIC
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B1‐A‐1 1 EA REPAIR 8.3300 0.1429 1.19 MECHANIC
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B2‐A‐1 1 EA REPAIR 8.3300 0.1429 1.19 MECHANIC
1 TTC PH1 D304504 HEAT EXCHANGER, PLATE AND FRAME HX‐B2‐D‐1 1 EA REPAIR 8.3300 0.1429 1.19 MECHANIC
1 TTC PH1 D304506 PUMP, CONDENSER WATER CWP‐B1‐A‐1T3 1 EA REPAIR 1.1400 0.2000 0.23 MECHANIC
1 TTC PH1 D304506 PUMP, CONDENSER WATER CWP‐B1‐A‐4T6 1 EA REPAIR 1.1400 0.2000 0.23 MECHANIC
1 TTC PH1 D304506 PUMP, CONDENSER WATER CWP‐B1‐C‐1,CWP‐B1‐D‐1 2 EA REPAIR 1.1400 0.2000 0.46 MECHANIC
1 TTC PH1 D304507 VALVE, HVAC PIPING 127 EA REPACK GLAND 0.4500 0.1000 5.72 MECHANIC
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (12) 1‐2 MBH UNITS 12 EA REPAIR 3.1600 0.1000 3.79 HVAC TECHNICIAN
Page A-8.8
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (14) 13‐15 MBH UNITS 14 EA REPAIR 3.1600 0.1000 4.42 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (2) 10‐12 MBH UNITS 2 EA REPAIR 3.1600 0.1000 0.63 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (2) 16‐18 MBH UNITS 2 EA REPAIR 3.1600 0.1000 0.63 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (20) 7‐9 MBH UNITS 20 EA REPAIR 3.1600 0.1000 6.32 HVAC TECHNICIAN
1 TTC PH1 D305104 FAN COIL UNIT, CEILING‐MOUNTED (44) 4‐6 MBH UNITS 44 EA REPAIR 3.1600 0.1000 13.90 HVAC TECHNICIAN
1 TTC PH1 D305201 AIR CONDITIONER, PACKAGE, COMPUTER AC‐B1‐A‐1,AC‐B1‐A‐2 2 EA REPAIR 57.6000 0.1000 11.52 HVAC TECHNICIAN
1 TTC PH1 D305201 AIR CONDITIONER, PACKAGE, COMPUTER AC‐B1‐B‐1T3,AC‐B1‐D‐1T3 6 EA REPAIR 57.6000 0.1000 34.56 HVAC TECHNICIAN
1 TTC PH1 D306301 HVAC CONTROLS, CONTROLLER PHASE 1 8 EA REPAIR 1.2900 0.2000 2.06 HVAC TECHNICIAN
CF‐3‐A‐1,CF‐3‐A‐2,CF‐3‐B‐1,CF‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 4 EA REPLACE COIL 1.5000 0.2000 1.20 ELECTRICIAN
3‐B‐10
CF‐3‐B‐11,CF‐3‐B‐2,CF‐3‐B‐3,CF‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 5 EA REPLACE COIL 1.5000 0.2000 1.50 ELECTRICIAN
3‐B‐4,CF‐3‐B‐5
CF‐3‐B‐6,CF‐3‐B‐7,CF‐3‐B‐8,CF‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 4 EA REPLACE COIL 1.5000 0.2000 1.20 ELECTRICIAN
3‐B‐9
CF‐3‐C‐1,CF‐3‐C‐2,CF‐3‐C‐3,CF‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 5 EA REPLACE COIL 1.5000 0.2000 1.50 ELECTRICIAN
3‐C‐4,CF‐3‐C‐5
CF‐3‐C‐6,CF‐3‐C‐7,CF‐3‐C‐8,CF‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 5 EA REPLACE COIL 1.5000 0.2000 1.50 ELECTRICIAN
3‐C‐9,CF‐3‐C‐10
CF‐3‐D‐1,CF‐3‐D‐2,CF‐3‐D‐3,CF‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 4 EA REPLACE COIL 1.5000 0.2000 1.20 ELECTRICIAN
3‐D‐4
CWP‐B1‐A‐1,CWP‐B1‐A‐2,CWP‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 3 EA REPLACE COIL 1.5000 0.2000 0.90 ELECTRICIAN
B1‐A‐3
CWP‐B1‐A‐4,CWP‐B1‐A‐5,CWP‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 3 EA REPLACE COIL 1.5000 0.2000 0.90 ELECTRICIAN
B1‐A‐6
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE EF‐1‐A‐1,EF‐1‐A‐4,EF‐1‐B‐1 3 EA REPLACE COIL 1.5000 0.2000 0.90 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE EF‐B1‐A‐4,EF‐B1‐A‐5,EF‐B1‐A‐6 3 EA REPLACE COIL 1.5000 0.2000 0.90 ELECTRICIAN
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE RFP‐B1‐C‐1,RFP‐B1‐C‐2 2 EA REPLACE COIL 1.5000 0.2000 0.60 ELECTRICIAN
SF‐1‐A‐2,SF‐2‐D‐1,SF‐B1‐A‐1,SF‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 4 EA REPLACE COIL 1.5000 0.2000 1.20 ELECTRICIAN
B1‐A‐2
SF‐B1‐B‐1,SF‐B1‐B‐2,SF‐B1‐C‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 4 EA REPLACE COIL 1.5000 0.2000 1.20 ELECTRICIAN
1,SF‐B1‐C‐2
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE STP‐2‐A‐1,STP‐2‐B‐1,ATP‐2‐D‐1 3 EA REPLACE COIL 1.5000 0.2000 0.90 ELECTRICIAN
STP‐B1‐C‐1,STP‐1‐A‐1,STP‐1‐A‐
1 TTC PH1 D306701 VARIABLE FREQUENCY DRIVE 4 EA REPLACE COIL 1.5000 0.2000 1.20 ELECTRICIAN
2,STP‐1‐B‐1
1 TTC PH1 D501201 BREAKER, MOLDED CASE 146 EA REPAIR 2.1000 0.1000 30.66 ELECTRICIAN
Page A-8.9
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
SWITCHGEAR AND DISTRIBUTION ASSEMBLY, MS‐B1‐A‐1,MS‐B1‐A‐2,MS‐B1‐
1 TTC PH1 D501210 5 EA REPAIR 16.0000 0.2000 16.00 ELECTRICIAN
MAIN B,MS‐B1‐C,MS‐B1‐D
SWITCHGEAR AND DISTRIBUTION ASSEMBLY,
1 TTC PH1 D501210 MS‐FP‐B1 1 EA REPAIR 16.0000 0.2000 3.20 ELECTRICIAN
MAIN
SWITCHGEAR AND DISTRIBUTION ASSEMBLY,
1 TTC PH1 D501210 RMS‐B1‐A,RMS‐B1‐B,RMS‐B1‐C 3 EA REPAIR 16.0000 0.2000 9.60 ELECTRICIAN
MAIN
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC ATS‐B1‐A‐SOC 1 EA REPAIR 2.0000 0.2000 0.40 GENERATOR MECHANIC
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC ATS‐B1‐B‐LRS,ATS‐B1‐C‐LRS 2 EA REPAIR 2.0000 0.2000 0.80 GENERATOR MECHANIC
ATS‐B2‐A‐EMG,ATS‐B1‐B‐
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC 3 EA REPAIR 2.0000 0.2000 1.20 GENERATOR MECHANIC
EMG,ATS‐B1‐C‐EMG
ATS‐B2‐A‐LRS,ATS‐B1‐B‐
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC 3 EA REPAIR 2.0000 0.2000 1.20 GENERATOR MECHANIC
OPT,ATS‐B1‐D‐OPT
1 TTC PH1 D501211 TRANSFER SWITCH, AUTOMATIC ATS‐B2‐FP1,ATS‐B2‐FP2 2 EA REPAIR 2.0000 0.2000 0.80 GENERATOR MECHANIC
1 TTC PH1 D501212 TRANSFER SWITCH, MANUAL 9 EA REPAIR 2.0000 0.2000 3.60 ELECTRICIAN
1 TTC PH1 D501215 TRANSFORMER, SECONDARY 52 EA REPAIR 1.5000 0.1000 7.80 ELECTRICIAN
1 TTC PH1 D502202 LIGHTING, EXTERIOR PHASE 1 605 EA REPLACE BALLAST 0.4600 0.1000 27.83 GENERALIST
1 TTC PH1 D502202 LIGHTING, EXTERIOR PHASE 1 3 EA REPLACE BALLAST 0.4600 0.1000 0.14 GENERALIST
1 TTC PH1 D502203 LIGHTING, INTERIOR, FLUORESCENT PHASE 1 4121 SF REPLACE BALLAST & LAMPS 0.4400 0.1000 181.32 ELECTRICIAN
1 TTC PH1 D503103 DIGITAL SIGNAGE, TTC AV COMMUNICATIONS PHASE 1 527490 EA REPAIR 0.0015 0.2000 162.46 ELECTRICIAN
1 TTC PH1 D503704 FIRE ALARM CONTROL PANEL 1 EA REPAIR 1.2900 0.2000 0.26 FIRE ALARM TECHNICIAN
1 TTC PH1 D503711 SMOKE DETECTOR 1296 EA REPAIR 0.6000 0.1000 77.76 FIRE ALARM TECHNICIAN
UPS‐B1‐A‐SOC,UPS‐B1‐B,UPS‐
1 TTC PH1 D509213 UNINTERRUPTIBLE POWER SUPPLY 3 EA REPLACE BATTERY 0.3300 0.1000 0.10 ELECTRICIAN
B1‐D
1 TTC PH1 E102501 DISPLAY, LED PUBLIC ART LED DISPLAY 1 EA REPAIR 3.0000 1.0000 3.00 GENERALIST
1 TTC PH1 E102502 ILLUMINATION, SHAW ALLEY PUBLIC ART SHAW ALLEY 240 SF REPLACE BALLAST & LAMPS 0.4400 0.1000 10.56 GENERALIST
1 TTC PH1 E109902 BIRD CONTROL SYSTEM, ELECTRIFIED 1 EA REPAIR 2.0000 1.0000 2.00 GENERALIST
1 TTC PH1 E109903 SIGNAGE, WAYFINDING 1 EA REPAIR 5.0000 1.0000 5.00 GENERALIST
1 TTC PH1 G201202 CONCRETE VEHICULAR PAVING BUS PLAZA 933 SF MINOR REPAIR 0.0066 0.0667 0.41 ROAD WORKER
1 TTC PH1 G201202 CONCRETE VEHICULAR PAVING BUS DECK 138000 SF MINOR REPAIR 0.0066 0.0667 60.75 ROAD WORKER
1 TTC PH1 G203101 CONCRETE PEDESTRIAN PAVING GROUND LEVEL 93000 SF REPAIR 0.0123 0.0667 76.30 ROAD WORKER
1 BUS RAMP D501215 TRANSFORMER, SECONDARY BUS RAMP 1 EA REPAIR 1.5000 0.1000 0.15 ELECTRICIAN
Page A-8.10
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 BUS RAMP D502201 LIGHTING DIMMER PANEL BUS RAMP 1 EA REPAIR 0.4600 0.2000 0.09 ELECTRICIAN
1 BUS RAMP D502202 LIGHTING, EXTERIOR BUS RAMP 18 EA REPLACE BALLAST 0.4600 0.1000 0.83 GENERALIST
1 BUS RAMP G201202 CONCRETE VEHICULAR PAVING BUS RAMP 42495 SF MINOR REPAIR 0.0066 0.0667 18.71 ROAD WORKER
1 ROOF PARK B101901 FLOORING ‐ WOOD STRIP, FIR PORCH ROOF PARK 3700 SF REFINISH 0.0122 0.2000 9.03 CARPENTER
1 ROOF PARK B102001 ROOF (PER 100 SF) ROOF PARK BUS FOUNTAIN 120 SF REPAIR 0.1700 0.1000 2.04 ROOFER
1 ROOF PARK B102001 ROOF (PER 100 SF) ROOF PARK MEP ROOMS 50 SF REPAIR 0.1700 0.1000 0.85 ROOFER
1 ROOF PARK C301101 WALL FINISH ‐ PAINT COMMON/BOH 8377 SF REPAIR 0.0006 0.0500 0.25 PAINTER
1 ROOF PARK C301101 WALL FINISH ‐ PAINT COMMON/BOH 3345 SF REPAIR 0.0006 0.0500 0.10 PAINTER
1 ROOF PARK C301103 WALL FINISH ‐ TILE, CERAMIC / STONE COMMON/BOH 3321 SF REPAIR 0.0031 0.1000 1.03 CARPENTER
1 ROOF PARK C301104 WALL FINISH ‐ GLASS COMMON/BOH 1292 SF REPAIR 0.0088 0.0400 0.45 GLAZIER
1 ROOF PARK C302401 FLOORING ‐ TERRAZZO/POLISHED CONCRETE COMMON/BOH 464 SF REPAIR 0.0043 0.0667 0.13 CARPENTER
1 ROOF PARK C302402 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY COMMON/BOH 800 SF REPAIR 0.0041 0.0667 0.22 CARPENTER
1 ROOF PARK C302501 FLOORING ‐ CARPET, TILE OR ROLL COMMON/BOH 244 SF REPAIR 0.0008 0.2500 0.05 CARPENTER
1 ROOF PARK C303101 CEILING FINISH ‐ METAL OR SPECIALTY TILE COMMON/BOH 464 SF REPAIR 0.0066 0.1250 0.38 CARPENTER
1 ROOF PARK C303102 CEILING FINISH ‐ PAINTED OR STAINED COMMON/BOH 3140 SF REPAIR 0.0015 0.0400 0.19 CARPENTER
1 ROOF PARK C303102 CEILING FINISH ‐ PAINTED OR STAINED COMMON/BOH 800 SF REPAIR 0.0015 0.0400 0.05 CARPENTER
1 ROOF PARK D201101 TOILET PHASE 1 35 EA REPLACE FLUSH VALVE 0.3300 0.1000 1.16 PLUMBER
1 ROOF PARK D201201 URINAL PHASE 1 3 EA REPLACE FLUSH VALVE 0.9000 0.1429 0.39 PLUMBER
1 ROOF PARK D201301 LAVATORY PHASE 1 9 EA VALVE SET 0.6400 0.1000 0.58 PLUMBER
Page A-8.11
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 ROOF PARK D209905 PUMP, GENERAL‐USE BUS FOUNTAIN P201 2 EA REPAIR 3.5300 0.1000 0.71 PLUMBER
1 ROOF PARK D209905 PUMP, GENERAL‐USE BUS FOUNTAIN P301 2 EA REPAIR 3.5300 0.1000 0.71 PLUMBER
1 ROOF PARK G203101 CONCRETE PEDESTRIAN PAVING ROOF PARK 43000 SF REPAIR 0.0123 0.0667 35.28 ROAD WORKER
1 ROOF PARK G204601 FOUNTAIN ROOF PARK 1 EA REPAIR 6.0000 1.0000 6.00 PLUMBER
1 ROOF PARK G205702 IRRIGATION ZONE ROOF PARK 60 EA REPAIR 3.0000 1.0000 180.00 PLUMBER
1 BSF B102001 ROOF (PER 100 SF) BSF ADMIN BLDG 165 100 SF REPAIR 0.1700 0.1000 2.81 ROOFER
1 BSF B102001 ROOF (PER 100 SF) BSF GUARD SHACKS 0.5 100 SF REPAIR 0.1700 0.1000 0.01 ROOFER
1 BSF B102001 ROOF (PER 100 SF) BSF SUPPORT BLDG 9 100 SF REPAIR 0.1700 0.1000 0.15 ROOFER
1 BSF B201101 WALL, EXTERIOR, MASONRY BSF SITE WALL 8448 SF REPAIR 0.0034 0.0400 1.15 MASON
1 BSF B201101 WALL, EXTERIOR, MASONRY BSF SUPPORT BLDG 600 SF REPAIR 0.0034 0.0400 0.08 MASON
1 BSF B201103 WALL, EXTERIOR, SIDING BSF ADMIN BLDG 1710 SF REFINISH 0.0294 0.1000 5.03 PAINTER
1 BSF B201103 WALL, EXTERIOR, SIDING BSF GUARD SHACKS 90 SF REFINISH 0.0294 0.1000 0.26 PAINTER
1 BSF B202101 GLASS, WINDOW BSF ADMIN BLDG 10 EA REPAIR 0.3300 0.0500 0.17 GLAZIER
1 BSF B202101 GLASS, WINDOW BSF GUARD SHACKS 4 EA REPAIR 0.3300 0.0500 0.07 GLAZIER
1 BSF B203901 DOOR, SWINGING, EXTERIOR, MANUAL BSF ADMIN BLDG 3 EA REPAIR 0.7900 0.1000 0.24 GENERALIST
1 BSF B203901 DOOR, SWINGING, EXTERIOR, MANUAL BSF ADMIN BLDG 3 EA REPAIR 0.7900 0.1000 0.24 GENERALIST
1 BSF B203901 DOOR, SWINGING, EXTERIOR, MANUAL BSF GUARD SHACKS 2 EA REPAIR 0.7900 0.1000 0.16 GENERALIST
1 BSF B203901 DOOR, SWINGING, EXTERIOR, MANUAL BSF GUARD SHACKS 2 EA REPAIR 0.7900 0.1000 0.16 GENERALIST
1 BSF B203901 DOOR, SWINGING, EXTERIOR, MANUAL BSF SUPPORT BLDG 6 EA REPAIR 0.7900 0.1000 0.47 GENERALIST
1 BSF B203901 DOOR, SWINGING, EXTERIOR, MANUAL BSF SUPPORT BLDG 6 EA REPAIR 0.7900 0.1000 0.47 GENERALIST
1 BSF C101401 PARTITIONS, TOILET BSF ADMIN BLDG 5 EA REPAIR 0.8400 0.2500 1.05 CARPENTER
Page A-8.12
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 BSF C102107 DOOR, SWINGING, INTERIOR, MANUAL BSF ADMIN BLDG 6 EA REPAIR 0.8400 0.1000 0.50 GENERALIST
1 BSF C301101 WALL FINISH ‐ PAINT BSF ADMIN BLDG 2060 SF REPAIR 0.0006 0.0500 0.06 PAINTER
1 BSF C301101 WALL FINISH ‐ PAINT BSF SUPPORT BLDG 1980 SF REPAIR 0.0006 0.0500 0.06 PAINTER
1 BSF C302101 FLOORING ‐ ATHLETIC, RUBBER, TILE OR ROLL BSF ADMIN BLDG 1460 SF REPAIR 0.0005 0.1111 0.08 CARPENTER
1 BSF C302302 FLOORING ‐ FLUID APPLIED, PAINT OR CLEAR SEAL BSF GUARD SHACKS $37 SF REPAIR 0.0015 0.0667 0.00 PAINTER
1 BSF C302302 FLOORING ‐ FLUID APPLIED, PAINT OR CLEAR SEAL BSF SUPPORT BLDG 745 SF REPAIR 0.0015 0.0667 0.07 PAINTER
1 BSF C303102 CEILING FINISH ‐ PAINTED OR STAINED BSF ADMIN BLDG 2060 SF REPAIR 0.0015 0.0400 0.12 CARPENTER
1 BSF C303201 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE BSF ADMIN BLDG 438 SF REPAIR 0.0004 0.1111 0.02 CARPENTER
1 BSF D201101 TOILET BSF ADMIN BLDG 5 EA REPLACE FLUSH VALVE 0.3300 0.1000 0.17 PLUMBER
1 BSF D201201 URINAL BSF ADMIN BLDG 2 EA REPLACE FLUSH VALVE 0.9000 0.1429 0.26 PLUMBER
1 BSF D201301 LAVATORY BSF ADMIN BLDG 4 EA VALVE SET 0.6400 0.1000 0.26 PLUMBER
1 BSF D202102 PIPING, DOMESTIC COLD WATER BSF ADMIN BLDG 0.12 KLF RESOLDER JOINT 5.6800 0.1000 0.07 PLUMBER
1 BSF 0.12 KLF REPLACE 10' SECT. 2.0999 0.0500 0.01 PLUMBER
1 BSF D202202 WATER HEATER, ELECTRIC BSF ADMIN BLDG 3 EA DRAIN & FLUSH 2.6700 0.1429 1.14 PLUMBER
1 BSF D202209 PIPING, DOMESTIC HOT WATER BSF ADMIN BLDG 0.1 KLF RESOLDER JOINT 5.6800 0.1000 0.06 PLUMBER
1 BSF 0.1 KLF REPLACE 10' SECT. 2.0999 0.0500 0.01 PLUMBER
1 BSF D305107 AIR CONDITIONER, PACKAGE TERMINAL BSF GUARD SHACKS 2 EA REPAIR 1.7000 0.1000 0.34 HVAC TECHNICIAN
1 BSF D305202 PACKAGE HVAC UNIT, ELECTRIC HEAT BSF ADMIN BLDG 2 EA REPAIR 19.2000 0.1000 3.84 HVAC TECHNICIAN
1 BSF D502201 LIGHTING DIMMER PANEL 3 EA REPAIR 0.4600 0.2000 0.28 ELECTRICIAN
1 BSF D502202 LIGHTING, EXTERIOR BSF 10 EA REPLACE BALLAST 0.4600 0.1000 0.46 GENERALIST
1 BSF D502202 LIGHTING, EXTERIOR BSF 7 EA REPLACE BALLAST 0.4600 0.1000 0.32 GENERALIST
Page A-8.13
CM
Program UNIFORMAT TOTAL ANNUAL
PHASE COMPONENT DESCRIPTION IDENTIFIER BARCODE QUANTITY UNITS COMPLEXITY CM TITLE CM HOURS ANNUALIZED SHOP
Component II CM HOURS
FREQUENCY
1 BSF D502203 LIGHTING, INTERIOR, FLUORESCENT BSF ADMIN BLDG 20 EA REPLACE BALLAST & LAMPS 0.4400 0.1000 0.88 ELECTRICIAN
1 BSF D502203 LIGHTING, INTERIOR, FLUORESCENT BSF GUARD SHACKS 2 EA REPLACE BALLAST & LAMPS 0.4400 0.1000 0.09 ELECTRICIAN
1 BSF D502203 LIGHTING, INTERIOR, FLUORESCENT BSF SUPPORT BLDG 12 EA REPLACE BALLAST & LAMPS 0.4400 0.1000 0.53 ELECTRICIAN
1 BSF G201202 CONCRETE VEHICULAR PAVING BUS STORAGE FACILITY 27984 SF MINOR REPAIR 0.0066 0.0667 12.32 ROAD WORKER
1 BSF G203101 CONCRETE PEDESTRIAN PAVING BSF 7552 SF REPAIR 0.0123 0.0667 6.20 ROAD WORKER
Page A-8.14
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix B.1
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page B.1-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix B.2
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page B.2-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix B.3
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page B.3-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix B.4
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page B.4-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix B.5
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page B.5-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix C.1
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page C.1-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
Phase 1 TTC Phase 1 Roof Park* Phase 1 BSF Phase 1 Total
Floor Covering
Area Type Floor Covering Type Min/kSF NCSF 1 Min./Day NCSF 1 Min./Day NCSF 1 Min./Day NCSF 1 Min./Day
CIRCULATION APPLIED HARD 15.5 32,650 506 396 6 0 33,046 512
CIRCULATION CARPET CARPET 11.0 7,241 80 244 3 0 7,485 82
CIRCULATION SEALED CONCRETE HARD 15.5 24,473 379 0 0 24,473 379
CIRCULATION TERRAZZO/POLISHED CONCRETE HARD 15.5 72,864 1,129 464 7 0 73,328 1,137
CIRCULATION TERRAZZO ‐ PUBLIC ART HARD 15.5 21,166 328 0 0 21,166 328
CIRCULATION VINYL SHEET HARD 15.5 0 0 0 0 0
OFFICE APPLIED HARD 14.0 0 0 0 0 0
OFFICE CARPET CARPET 9.0 1,110 10 0 0 1,110 10
OFFICE PORCELAIN TILE 14.5 592 9 0 0 592 9
OFFICE SEALED CONCRETE HARD 14.0 19,098 267 0 0 19,098 267
OFFICE VINYL TILE HARD 14.0 5,772 81 0 0 5,772 81
RESTROOM/LOCKER ROOM PORCELAIN TILE 17.0 4,068 69 800 14 0 4,868 83
RESTROOM/LOCKER ROOM RUBBER COVERING 17.5 0 0 1,460 26 1,460 26
WORKROOM PORCELAIN TILE 14.5 142 2 0 0 142 2
Discrete Cleaning Tasks Item Count Count Min/Day Count Min/Day Count Min/Day Count Min/Day
Restrooms Fixtures 2.5 80 200.0 27 67.5 11 27.5 118 295.0
Showers EACH 5 2 10.0 0.0 0.0 2 10.0
Stairs EACH 6 35 210.0 3 18.0 0.0 38 228.0
Elevators EACH 5 11 55.0 0.0 0.0 11 55.0
Page C-1.3
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix C.2
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page C.2-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix C.3
TASK
CLEANING PROJECTS FREQ HOURS
Strip/refinish Composition
Floors 1 11.5
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page C.3-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix C.4
FLOOR
FLOOR COVERING PROJECT PROJECT
AREA TYPE COVERING TYPE NCSF MINUTES HRS
Circulation Applied Hard 396 48 0.8
Circulation Carpet Carpet 244 7 0.1
Sealed
Circulation Concrete Hard - 0 0.0
Terrazzo/
Polished
Circulation Concrete Hard 464 56 0.9
Terrazzo –
Circulation Public Art Hard - 0 0.0
Circulation Vinyl Sheet Hard - 0 0.0
Office Applied Hard - 0 0.0
Office Carpet Carpet - 0 0.0
Office Porcelain Tile - 0 0.0
Sealed
Office Concrete Hard - 0 0.0
Office Vinyl Tile Hard - 0 0.0
Restroom/Locker Room Porcelain Tile 800 48 0.8
Restroom/Locker Room Rubber Covering - 0 0.0
Workroom Porcelain Tile - 0 0.0
Net Cleanable Square Feet 1,904 2.6
TASK
CLEANING PROJECTS FREQ HOURS
Strip/refinish Composition
Floors 1 0.0
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page C.4-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix C.5
TASK
CLEANING PROJECTS FREQ HOURS
Strip/refinish Composition
Floors 1 0.0
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page C.5-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix D
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page D-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
Program Life Cycle
Phase Uniformat II Description COST BASIS Quantity Units Complexity Identifier Life Cycle
Component Adjustment
Phase 1 ‐ Transbay Transit Center
1 TTC PH1 B2010 AWNING, EXTERIOR, PERFORATED METAL PANEL RESTORATION 2015 158000 SF 1.12 W‐1 PERF MTL PNLS 40
1 TTC PH1 B2010 WALL, EXTERIOR, PANEL JOINT RESTORATION 2015 2600 SF 1.12 W‐16A 25
1 TTC PH1 B2010 WALL, EXTERIOR, PANEL JOINT RESTORATION 2015 92250 SF 1.12 W‐18 GLASS REINF CONC PNL 25
1 TTC PH1 B2010 WALL, EXTERIOR, PANEL JOINT RESTORATION 2015 8900 SF 1.12 W‐5 FORMERLY COLORED GLASS 25
1 TTC PH1 B2020 GLASS, CURTAIN WALL, STANDARD 2015 22350 SF 1.12 W‐2 60
1 TTC PH1 B2020 GLASS, CURTAIN WALL, STANDARD 2015 19200 SF 1.12 W‐3 60
1 TTC PH1 B2020 GLASS, CURTAIN WALL, STANDARD 2015 5000 SF 1.12 W‐4 60
1 TTC PH1 B2020 GLASS, CURTAIN WALL, STANDARD 2015 4000 SF 1.12 W‐7 EXCLUDING CHANNEL GLASS 60
1 TTC PH1 B2030 DOOR, EXTERIOR, SLIDING ENTRANCE SYSTEM, POWERED 2015 14 EA DC 15
1 TTC PH1 B2030 DOOR, EXTERIOR, SLIDING ENTRANCE SYSTEM, POWERED 2015 5 EA DORMA ESA300 15
1 TTC PH1 B2030 DOOR, EXTERIOR, OVERHEAD ROLLING METAL, LOCK 2015 1530 SF RETAIL/LOADING 30
1 TTC PH1 B2030 DOOR, EXTERIOR, OVERHEAD ROLLING METAL, LOCK 2015 3825 SF RETAIL/LOADING 30
1 TTC PH1 B2030 DOOR OPERATOR, POWER‐ASSIST 2015 2 EA AC 20
1 TTC PH1 B2030 DOOR OPERATOR, POWER‐ASSIST 2015 31 EA DC 20
1 TTC PH1 B2030 DOOR OPERATOR, OVERHEAD DOOR, COMMERCIAL, PADS 2015 6 EA RETAIL/LOADING 15
1 TTC PH1 B2030 DOOR OPERATOR, OVERHEAD DOOR, COMMERCIAL, PADS 2015 9 EA RETAIL/LOADING 15
1 TTC PH1 B3010 ROOF ‐ 1‐PLY, ADHERED (EPDM, PIB, CSPE, PVC) 2015 12000 SF ROOF PARK BUS FOUNTAIN 20
1 TTC PH1 B3010 ROOF ‐ 1‐PLY, ADHERED (EPDM, PIB, CSPE, PVC) 2015 5000 SF ROOF PARK MEP ROOMS 20
1 TTC PH1 B3020 ROOF SKYLIGHT ‐ GLASS WITH ALUMINUM FRAME 2015 7083 SF PARK LEVEL SKYLIGHTS 35
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 66 LEAF 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 29 LEAF AC 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 2 LEAF AC 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 10 LEAF DC 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 31 LEAF DC 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 1 LEAF RAMP MAIN 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 16 LEAF SEALED DOOR 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, FIRE‐RATED 2015 40 LEAF 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, FIRE‐RATED 2015 128 LEAF AC 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, FIRE‐RATED 2015 79 LEAF DC 40
1 TTC PH1 C1020 DOOR AND FRAME, INTERIOR, FIRE‐RATED 2015 4 LEAF DOOR CONTACT 40
1 TTC PH1 C1020 DOOR ‐ OVERHEAD, INTERIOR 2015 16 SF 30
1 TTC PH1 C1020 DOOR ‐ OVERHEAD, INTERIOR 2015 28 SF DC 30
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 66 EA 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 40 EA 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 29 EA AC 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 2 EA AC 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 128 EA AC 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 10 EA DC 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 31 EA DC 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 79 EA DC 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 4 EA DOOR CONTACT 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 1 EA RAMP MAIN 20
1 TTC PH1 C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 16 EA SEALED DOOR 20
1 TTC PH1 C3010 WALL FINISH ‐ PAINT, STANDARD 2015 324023 SF COMMON/BOH 12
1 TTC PH1 C3010 WALL FINISH ‐ PAINT, STANDARD 2015 10259 SF COMMON/BOH 12
1 TTC PH1 C3010 WALL FINISH ‐ TILE, CERAMIC / STONE, STANDARD 2015 4805 SF TRANSIT 30
1 TTC PH1 C3010 WALL FINISH ‐ TILE, CERAMIC / STONE, STANDARD 2015 8810 SF COMMON/BOH 30
1 TTC PH1 C3010 WALL FINISH ‐ TILE, CERAMIC / STONE, STANDARD 2015 6139 SF COMMON/BOH 30
1 TTC PH1 C3010 WALL FINISH ‐ GLASS 2015 25932 SF TRANSIT 40
1 TTC PH1 C3010 WALL FINISH ‐ GLASS 2015 1204 SF TRANSIT 40
1 TTC PH1 C3010 WALL FINISH ‐ GLASS 2015 6368 SF GENERAL 40
1 TTC PH1 C3010 WALL FINISH ‐ GLASS 2015 12153 SF GENERAL 40
1 TTC PH1 C3010 WALL FINISH ‐ GLASS 2015 12853 SF GENERAL 40
1 TTC PH1 C3010 WALL FINISH ‐ GLASS 2015 8729 SF GENERAL 40
1 TTC PH1 C3020 FLOORING ‐ CARPET, TILE OR ROLL, STANDARD 2015 8351 SF COMMON/BOH 12
1 TTC PH1 C3020 FLOORING ‐ VINYL COMPOSITION TILE, STANDARD 2015 5772 SF SECURITY 20
1 TTC PH1 C3020 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY STANDARD 2015 622 SF DRIVER SUPPORT 30
1 TTC PH1 C3020 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY STANDARD 2015 202 SF DRIVER SUPPORT 30
1 TTC PH1 C3020 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY STANDARD 2015 3446 SF COMMON/BOH 30
1 TTC PH1 C3020 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY STANDARD 2015 1144 SF COMMON/BOH 30
1 TTC PH1 C3020 FLOORING ‐ TERRAZZO/POLISHED CONCRETE RENEWAL 2015 67247 SF BUS DECK WAITING 50
1 TTC PH1 C3020 FLOORING ‐ TERRAZZO/POLISHED CONCRETE RENEWAL 2015 28606 SF COMMON/BOH 50
1 TTC PH1 C3020 FLOORING ‐ FLUID APPLIED, EPOXY / ACRYLIC / POLYURETHANE 2015 20655 SF COMMON/BOH 15
1 TTC PH1 C3020 FLOORING ‐ FLUID APPLIED, EPOXY / ACRYLIC / POLYURETHANE 2015 8969 SF COMMON/BOH 15
Page D.3
Program Life Cycle
Phase Uniformat II Description COST BASIS Quantity Units Complexity Identifier Life Cycle
Component Adjustment
1 TTC PH1 C3020 FLOORING ‐ FLUID APPLIED, EPOXY / ACRYLIC / POLYURETHANE 2015 88548 SF COMMON/BOH 15
1 TTC PH1 C3020 FLOORING ‐ FLUID APPLIED, PAINT OR CLEAR SEAL 2015 43571 SF COMMON/BOH 10
1 TTC PH1 C3030 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE, STANDARD 2015 202 SF DRIVER SUPPORT 30
1 TTC PH1 C3030 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE, STANDARD 2015 14612 SF COMMON/BOH 30
1 TTC PH1 C3030 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE, STANDARD 2015 193 SF COMMON/BOH 30
1 TTC PH1 C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 622 SF DRIVER SUPPORT 24
1 TTC PH1 C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 67247 SF BUS DECK WAITING 24
1 TTC PH1 C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 30365 SF COMMON/BOH 24
1 TTC PH1 C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 3628 SF COMMON/BOH 24
1 TTC PH1 C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 34776 SF COMMON/BOH 24
1 TTC PH1 C3030 CEILING FINISH ‐ METAL OR SPECIALTY TILE 2015 398 SF COMMON/BOH 40
1 TTC PH1 D1010 ELEVATOR MODERNIZATION ‐ TRACTION ‐ LOW RISE 2015 2 EA PE201,PE202 25
1 TTC PH1 D1010 ELEVATOR MODERNIZATION ‐ TRACTION ‐ LOW RISE 2015 2 EA PE502,PE503 25
1 TTC PH1 D1010 ELEVATOR MODERNIZATION ‐ TRACTION ‐ LOW RISE 2015 6 EA PE704&5,PE403&4,PE301&2 25
1 TTC PH1 D1010 ELEVATOR MODERNIZATION ‐ TRACTION ‐ LOW RISE 2015 1 EA SE202 25
1 TTC PH1 D1010 ELEVATOR MODERNIZATION ‐ TRACTION ‐ LOW RISE 2015 1 EA SE401 25
1 TTC PH1 D1010 ELEVATOR CAB RENOVATION ‐ PASSENGER 2015 2 EA PE201,PE202 12
1 TTC PH1 D1010 ELEVATOR CAB RENOVATION ‐ PASSENGER 2015 2 EA PE502,PE503 12
1 TTC PH1 D1010 ELEVATOR CAB RENOVATION ‐ PASSENGER 2015 6 EA PE704&5,PE403&4,PE301&2 12
1 TTC PH1 D1010 ESCALATOR 2015 7 EA E407T10,E510T12 25
1 TTC PH1 D1010 ESCALATOR 2015 2 EA 1.32 E610,E611 25
1 TTC PH1 D2010 PLUMBING FIXTURE ‐ LAVATORY, WALL HUNG 2015 38 EA PHASE 1 35
1 TTC PH1 D2010 PLUMBING FIXTURE ‐ SINK, SERVICE/LAUNDRY/UTILITY 2015 39 EA PHASE 1 35
1 TTC PH1 D2010 PLUMBING FIXTURE ‐ SHOWER VALVE AND HEAD 2015 2 EA PHASE 1 35
1 TTC PH1 D2010 PLUMBING FIXTURE ‐ URINAL 2015 7 EA PHASE 1 35
1 TTC PH1 D2010 PLUMBING FIXTURE ‐ WATER CLOSET, TANKLESS 2015 35 EA PHASE 1 35
1 TTC PH1 D2010 PLUMBING FIXTURE ‐ EMERGENCY EYEWASH 2015 1 EA PHASE 1 35
1 TTC PH1 D2010 PLUMBING FIXTURE ‐ EMERGENCY COMBINATION SHOWER/EYEWASH 2015 8 EA PHASE 1 35
1 TTC PH1 D2010 DRINKING FOUNTAIN, DUAL‐LEVEL 2015 12 EA PHASE 1 35
1 TTC PH1 D2020 BACKFLOW PREVENTER (1‐2 INCHES) 2015 1 EA BFP‐3‐A‐1 10
1 TTC PH1 D2020 BACKFLOW PREVENTER (1‐2 INCHES) 2015 1 EA BFP‐3‐D‐1 10
1 TTC PH1 D2020 BACKFLOW PREVENTER (1‐2 INCHES) 2015 1 EA BFP‐B1‐A‐2 10
1 TTC PH1 D2020 BACKFLOW PREVENTER (1‐2 INCHES) 2015 1 EA BFP‐B1‐A‐4 10
1 TTC PH1 D2020 BACKFLOW PREVENTER (1‐2 INCHES) 2015 1 EA BFP‐B1‐A‐5 10
1 TTC PH1 D2020 BACKFLOW PREVENTER (2‐3 INCHES) 2015 1 EA BFP‐B1‐A‐1 10
1 TTC PH1 D2020 BACKFLOW PREVENTER (6‐8 INCHES) 2015 1 EA FIRE SUPPRESSION 10
1 TTC PH1 D2020 BACKFLOW PREVENTER (8 INCHES) 2015 1 EA BFP‐B1‐A‐3 10
1 TTC PH1 D2020 DOMESTIC WATER BOOSTER SYSTEM 2015 60 HP DWP‐B2‐A‐1T3 20
1 TTC PH1 D2020 DOMESTIC WATER BOOSTER SYSTEM 2015 30 HP IRP‐B2‐A‐1,IRP‐B2‐A‐2 20
1 TTC PH1 D2020 SUPPLY PIPING SYSTEM ‐ RETAIL 2015 527490 SF 0.93 PHASE 1 35
1 TTC PH1 D2020 WATER HEATER ‐ RESIDENTIAL, GAS (<=35 GAL) 2015 38 GAL EWH‐2‐A‐1 20
1 TTC PH1 D2020 WATER HEATER ‐ RESIDENTIAL, GAS (<=35 GAL) 2015 19 GAL EWH‐3‐A‐1 20
1 TTC PH1 D2020 WATER HEATER ‐ RESIDENTIAL, GAS (<=35 GAL) 2015 19 GAL EWH‐3‐B‐1 20
1 TTC PH1 D2020 WATER HEATER ‐ RESIDENTIAL, GAS (<=35 GAL) 2015 19 GAL EWH‐4‐C‐1 20
1 TTC PH1 D2020 WATER HEATER ‐ RESIDENTIAL, GAS (<=35 GAL) 2015 19 GAL EWH‐5‐A‐1 20
1 TTC PH1 D2020 WATER HEATER ‐ RESIDENTIAL, GAS (>55 GAL) 2015 80 GAL EWH‐1‐A‐2 20
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 1 EA EWH‐1‐A‐1 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 1 EA EWH‐1‐B‐1 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 4 EA EWH‐1‐D‐1T4 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 1 EA EWH‐3‐A‐2 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 3 EA EWH‐3‐D‐1T3 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 1 EA EWH‐B1‐A‐1 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 1 EA EWH‐B1‐C‐1 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 1 EA EWH‐B1‐D‐1 10
1 TTC PH1 D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 1 EA EWH‐B2‐A‐1 10
1 TTC PH1 D2030 DRAIN PIPING SYSTEM ‐ RETAIL 2015 527490 SF 0.93 PHASE 1 40
1 TTC PH1 D2030 GRAY WATER LIFT STATION 2015 140 HP ALL GWP & OFP 20
1 TTC PH1 D2030 GRAY WATER LIFT STATION 2015 90 HP ALL GWP/OZ 20
1 TTC PH1 D2030 GRAY WATER LIFT STATION 2015 45 HP ALL SPG 20
1 TTC PH1 D2030 GRAY WATER LIFT STATION 2015 120 HP SP‐B2‐A‐1T6,SP‐B2‐B‐1T6,SP‐B2‐C‐1T6,SP‐B2‐D‐1T6 20
1 TTC PH1 D2030 SEWAGE LIFT STATION 2015 210 HP SE‐B2‐A‐1&2,SE‐B2‐B‐1T4,SE‐B2‐C‐1T4,SE‐B2‐D‐1T4 20
1 TTC PH1 D2030 GRAY WATER SUMP PUMP ‐SUBMERSIBLE PUMP (<0.5HP) 2015 6 EA SP‐B1‐A‐1&2,SP‐B1‐B‐1&2,SP‐B1‐C‐1&2 20
1 TTC PH1 D3030 COOLING TOWER (301‐550 TONS) 2015 445 TON CT‐B1‐A‐1 29
1 TTC PH1 D3030 COOLING TOWER (301‐550 TONS) 2015 445 TON CT‐B1‐A‐2 29
1 TTC PH1 D3030 CONDENSER ‐ WATER‐COOLED (<=50 TON) 2015 10 TON WHP‐B1‐A‐1 30
Page D.4
Program Life Cycle
Phase Uniformat II Description COST BASIS Quantity Units Complexity Identifier Life Cycle
Component Adjustment
1 TTC PH1 D3030 CONDENSER ‐ WATER‐COOLED (<=50 TON) 2015 30 TON WHP‐B1‐C‐1 30
1 TTC PH1 D3030 CONDENSER ‐ WATER‐COOLED (<=50 TON) 2015 30 TON WHP‐B1‐C‐2 30
1 TTC PH1 D3030 CONDENSER ‐ REFRIGERANT, AIR‐COOLED (<=10 TON) 2015 0.335 TON ACC‐B2‐A‐1&2,ACC‐B2‐D‐1&2 25
1 TTC PH1 D3040 AIR HANDLING UNIT ‐ INDOOR (12‐17 HP) 2015 15 HP AHU‐B1‐A‐1 25
1 TTC PH1 D3040 HEAT PUMP, WATER‐SOURCE 2015 1.56 TON (12) 1‐2 MBH UNITS 20
1 TTC PH1 D3040 HEAT PUMP, WATER‐SOURCE 2015 16.1 TON (14) 13‐15 MBH UNITS 20
1 TTC PH1 D3040 HEAT PUMP, WATER‐SOURCE 2015 2 TON (2) 10‐12 MBH UNITS 20
1 TTC PH1 D3040 HEAT PUMP, WATER‐SOURCE 2015 3 TON (2) 16‐18 MBH UNITS 20
1 TTC PH1 D3040 HEAT PUMP, WATER‐SOURCE 2015 13 TON (20) 7‐9 MBH UNITS 20
1 TTC PH1 D3040 HEAT PUMP, WATER‐SOURCE 2015 15.4 TON (44) 4‐6 MBH UNITS 20
1 TTC PH1 D3040 FAN ‐ AXIAL, RETURN, 1.5" SP (<=3 HP) 9,200 CFM 2015 1.5 HP EF‐B1‐D‐1 20
1 TTC PH1 D3040 FAN ‐ AXIAL, RETURN, 1.5" SP (<=3 HP) 9,200 CFM 2015 3 HP EF‐B2‐A‐1 20
1 TTC PH1 D3040 FAN ‐ AXIAL, SUPPLY, 2.5" SP (<=3 HP) 3800 CFM 2015 4 HP SF‐B2‐A‐1,STP‐2‐A‐1 20
1 TTC PH1 D3040 FAN ‐ AXIAL, SUPPLY, 2.5" SP (<=3 HP) 3800 CFM 2015 9 HP STP‐1‐A‐1,STP‐1‐A‐2,STP‐2‐D‐1 20
1 TTC PH1 D3040 FAN ‐ AXIAL, SUPPLY, 2.5" SP (<=3 HP) 3800 CFM 2015 1.5 HP STP‐2‐B‐1 20
1 TTC PH1 D3040 FAN ‐ AXIAL, SUPPLY, 2.5" SP (3‐5 HP) 6400 CFM 2015 10 HP STP‐B1‐C‐1,STP‐1‐B‐1 20
1 TTC PH1 D3040 FAN ‐ AXIAL, SUPPLY, 2.5" SP (7.5‐10 HP) 15,600 CFM 2015 20 HP SF‐B2‐B‐1,SF‐B2‐B‐2 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 4 HP (16) EF FANS 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 270 HP (27) CF FANS 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 3 HP EF‐1‐A‐1 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 0.66 HP EF‐1‐A‐4,EF‐B1‐A‐2 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 4 HP EF‐1‐B‐1,EF‐B1‐A‐3 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 1.02 HP EF‐1‐B‐2,EF‐1‐D‐1&2,EF‐2‐A‐3,EF‐2‐D‐1,EF‐3‐D‐3 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 2 HP EF‐2‐B‐2,EF‐B1‐A‐6 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 0.75 HP EF‐B1‐A‐4 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 1.5 HP EF‐B1‐A‐5 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 1 HP EF‐B1‐B‐1,EF‐B2‐A‐2 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 1 HP SF‐1‐A‐1,SF‐1‐A‐2,SF‐1‐B‐1,SF‐3‐A‐1 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 5 HP SF‐2‐D‐1 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 5 HP SF‐B1‐A‐1T2,SF‐B1‐B‐2,SF‐B1‐C‐1&2 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 2 HP SF‐B1‐A‐3 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 0.75 HP SF‐B1‐A‐4 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 0.33 HP SF‐B1‐B‐1 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 0.5 HP SF‐B1‐B‐3 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 0.13 HP SF‐B1‐D‐1 20
1 TTC PH1 D3040 FAN ‐ INLINE CENTRIFUGAL AIRFOIL, SUPPLY, 2.5" SP (<=30 HP) 2015 4.75 HP TRANSFER FANS (TF) 20
1 TTC PH1 D3040 FAN ‐ PROPELLER WITH LOUVER, 1/4" SP (>4 HP) 2015 10 HP SF‐B1‐C‐3,SF‐B1‐C‐4 20
1 TTC PH1 D3040 HVAC DISTRIBUTION NETWORKS ‐ RETAIL 2015 527490 SF 0.93 PHASE 1 40
1 TTC PH1 D3040 HEAT EXCHANGER ‐ PLATE FRAME (<=200 GPM) 2015 25 GPM HX‐B2‐C‐1 25
1 TTC PH1 D3040 HEAT EXCHANGER ‐ PLATE FRAME (<=200 GPM) 2015 25 GPM HX‐B2‐A‐1 25
1 TTC PH1 D3040 HEAT EXCHANGER ‐ PLATE FRAME (<=200 GPM) 2015 25 GPM HX‐B2‐D‐1 25
1 TTC PH1 D3040 HEAT EXCHANGER ‐ PLATE FRAME (>600 GPM) 2015 1200 GPM HX‐B1‐A‐2 25
1 TTC PH1 D3040 HEAT EXCHANGER ‐ PLATE FRAME (>600 GPM) 2015 1200 GPM HX‐B1‐A‐1 25
1 TTC PH1 D3040 PUMP ‐ ELECTRIC (<=10 HP) 2015 2 HP CWP‐B1‐C‐1,CWP‐B1‐D‐1 25
1 TTC PH1 D3040 PUMP ‐ ELECTRIC (<=10 HP) 2015 12 HP DIESEL PUMPS (DFP) 25
1 TTC PH1 D3040 PUMP ‐ ELECTRIC (<=10 HP) 2015 1 HP HWP‐B1‐A‐1 25
1 TTC PH1 D3040 PUMP ‐ ELECTRIC (<=10 HP) 2015 1 HP RFP‐B1‐C‐1 25
1 TTC PH1 D3040 PUMP ‐ ELECTRIC (<=10 HP) 2015 3 HP RFP‐B1‐C‐2 25
1 TTC PH1 D3040 PUMP ‐ ELECTRIC (10 ‐ 15 HP) 2015 45 HP CWP‐B1‐A‐1T3 25
1 TTC PH1 D3040 PUMP ‐ ELECTRIC (50 ‐ 75 HP) 2015 180 HP CWP‐B1‐A‐4T6 25
1 TTC PH1 D3050 COMPUTER ROOM AC UNIT ‐ REFRIGERANT, EXCL. HEAT REJECTION (<=3 TON) 2015 0.86 TON AC‐B1‐A‐1,AC‐B1‐A‐2 15
1 TTC PH1 D3050 COMPUTER ROOM AC UNIT ‐ REFRIGERANT, EXCL. HEAT REJECTION (<=3 TON) 2015 9.6 TON AC‐B1‐B‐1T3,AC‐B1‐D‐1T3 15
1 TTC PH1 D3060 HVAC CONTROLS SYSTEM ‐ RETAIL 2015 527490 SF 0.93 PHASE 1 18
1 TTC PH1 D4010 FIRE PUMP ‐ ELECTRIC, 1500 GPM, 6" ID (150‐250 HP) 2015 250 HP PHASE 1 25
1 TTC PH1 D4010 FIRE SPRINKLER SYSTEM 2015 527490 SF 0.93 PHASE 1 80
1 TTC PH1 D4040 FIRE ALARM PANEL, DIALER, BATTERY, & CHARGER 2015 1 EA 15
1 TTC PH1 D4040 FIRE ALARM SYSTEM ‐ DEVICES 2015 527490 SF 0.93 PHASE 1 18
1 TTC PH1 D4050 EXIT SIGN ‐ CENTRAL POWER 2015 323 EA PHASE 1 20
1 TTC PH1 D4090 FM200 OR INERGEN FIRE SUPPRESSION 2015 22680 CF MDF 25
1 TTC PH1 D5010 ELECTRICAL DISTRIBUTION NETWORK ‐ RETAIL 2015 527490 SF 0.93 PHASE 1 40
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (800‐1200 AMP) 2015 3600 AMP RMS‐B1‐A,RMS‐B1‐B,RMS‐B1‐C 20
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (1200‐1600 AMP) 2015 1600 AMP EDSH‐B1‐B 20
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (1200‐1600 AMP) 2015 1600 AMP EDSH‐B1‐C 20
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (1600‐2500 AMP) 2015 2000 AMP MS‐FP‐B1 20
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (>2500 AMP) 2015 3000 AMP EDSH‐B2‐A 20
Page D.5
Program Life Cycle
Phase Uniformat II Description COST BASIS Quantity Units Complexity Identifier Life Cycle
Component Adjustment
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (>2500 AMP) 2015 4000 AMP EDSH‐CTR GEN 20
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (>2500 AMP) 2015 4000 AMP EDSH‐WEST GEN 20
1 TTC PH1 D5010 MAIN SWITCHBOARD W/BREAKERS (>2500 AMP) 2015 15000 AMP MS‐B1‐A‐1,MS‐B1‐A‐2,MS‐B1‐B,MS‐B1‐C,MS‐B1‐D 20
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (<=5 HP) 2015 15 HP EF‐1‐A‐1,EF‐1‐A‐4,EF‐1‐B‐1 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (<=5 HP) 2015 15 HP EF‐B1‐A‐4,EF‐B1‐A‐5,EF‐B1‐A‐6 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (<=5 HP) 2015 10 HP RFP‐B1‐C‐1,RFP‐B1‐C‐2 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (<=5 HP) 2015 20 HP SF‐1‐A‐2,SF‐2‐D‐1,SF‐B1‐A‐1,SF‐B1‐A‐2 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (<=5 HP) 2015 20 HP SF‐B1‐B‐1,SF‐B1‐B‐2,SF‐B1‐C‐1,SF‐B1‐C‐2 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (<=5 HP) 2015 15 HP STP‐2‐A‐1,STP‐2‐B‐1,ATP‐2‐D‐1 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (<=5 HP) 2015 20 HP STP‐B1‐C‐1,STP‐1‐A‐1,STP‐1‐A‐2,STP‐1‐B‐1 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (7.5‐10 HP) 2015 40 HP CF‐3‐A‐1,CF‐3‐A‐2,CF‐3‐B‐1,CF‐3‐B‐10 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (7.5‐10 HP) 2015 50 HP CF‐3‐B‐11,CF‐3‐B‐2,CF‐3‐B‐3,CF‐3‐B‐4,CF‐3‐B‐5 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (7.5‐10 HP) 2015 40 HP CF‐3‐B‐6,CF‐3‐B‐7,CF‐3‐B‐8,CF‐3‐B‐9 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (7.5‐10 HP) 2015 50 HP CF‐3‐C‐1,CF‐3‐C‐2,CF‐3‐C‐3,CF‐3‐C‐4,CF‐3‐C‐5 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (7.5‐10 HP) 2015 50 HP CF‐3‐C‐6,CF‐3‐C‐7,CF‐3‐C‐8,CF‐3‐C‐9,CF‐3‐C‐10 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (7.5‐10 HP) 2015 40 HP CF‐3‐D‐1,CF‐3‐D‐2,CF‐3‐D‐3,CF‐3‐D‐4 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (10‐15 HP) 2015 45 HP CWP‐B1‐A‐1,CWP‐B1‐A‐2,CWP‐B1‐A‐3 12
1 TTC PH1 D5010 VARIABLE FREQUENCY DRIVE (40‐50 HP) 2015 150 HP CWP‐B1‐A‐4,CWP‐B1‐A‐5,CWP‐B1‐A‐6 16
1 TTC PH1 D5020 LIGHTING ‐ EXTERIOR, BOLLARD (SV, MH, ID, LED) COM 2015 605 EA PHASE 1 15
1 TTC PH1 D5020 LIGHTING SYSTEM, INTERIOR ‐ RETAIL 2015 527490 SF 0.93 PHASE 1 20
1 TTC PH1 D5030 CAMERA, CCTV 2015 70 EA PHASE 1 10
1 TTC PH1 D5030 AUDIO VISUAL ‐ DIGITAL SIGNAGE 2015 1 LOT PHASE 1 7
1 TTC PH1 D5030 AUDIO VISUAL ‐ SCHEDULING BOARD 2015 1 LOT PHASE 1 10
1 TTC PH1 D5030 DATA NETWORK HARDWARE 2015 1 LOT PHASE 1 7
1 TTC PH1 D5030 2‐WAY DISTRIBUTED ANTENNA SYSTEM 2015 1 LOT PHASE 1 7
1 TTC PH1 D5090 GENERATOR ‐ DIESEL (>500 KW) 2015 2000 KW CTR‐GEN GENERATOR 25
1 TTC PH1 D5090 GENERATOR ‐ DIESEL (>500 KW) 2015 2000 KW WEST GENERATOR 25
1 TTC PH1 D5090 SWITCH ‐ AUTO TRANSFER, 480 V (100‐400 AMP) 2015 150 AMP ATS‐B1‐A‐SOC 25
1 TTC PH1 D5090 SWITCH ‐ AUTO TRANSFER, 480 V (>400 AMP) 2015 1600 AMP ATS‐B1‐B‐LRS,ATS‐B1‐C‐LRS 25
1 TTC PH1 D5090 SWITCH ‐ AUTO TRANSFER, 480 V (>400 AMP) 2015 780 AMP ATS‐B2‐A‐EMG,ATS‐B1‐B‐EMG,ATS‐B1‐C‐EMG 25
1 TTC PH1 D5090 SWITCH ‐ AUTO TRANSFER, 480 V (>400 AMP) 2015 1800 AMP ATS‐B2‐A‐LRS,ATS‐B1‐B‐OPT,ATS‐B1‐D‐OPT 25
1 TTC PH1 D5090 SWITCH ‐ AUTO TRANSFER, 480 V (>400 AMP) 2015 800 AMP ATS‐B2‐FP1,ATS‐B2‐FP2 25
1 TTC PH1 D5090 UNINTERRUPTIBLE POWER SUPPLY ‐ 277/480 VOLTS 2015 3 EA UPS‐B1‐A‐SOC,UPS‐B1‐B,UPS‐B1‐D 15
1 TTC PH1 E1030 DOCK LEVELER 2015 8 EA 25
1 TTC PH1 G2012 CONCRETE VEHICULAR PAVING 2015 933 SF BUS PLAZA 40
1 TTC PH1 G2012 CONCRETE VEHICULAR PAVING 2015 138000 SF BUS DECK 40
1 TTC PH1 G2031 CONCRETE PEDESTRIAN PAVING 2015 93000 SF GROUND LEVEL 35
Phase 1 Transbay Transit Center Subtotal
Phase 1 Bus Ramp
1 BUS RAMP D5010 ELECTRICAL DISTRIBUTION NETWORK ‐ WAREHOUSE 2015 127488 SF 0.05 BUS RAMP 40
1 BUS RAMP D5020 LIGHTING ‐ EXTERIOR, STANCHION LUMINAIRE, 30‐FOOT 2015 18 EA BUS RAMP 15
1 BUS RAMP D5020 LIGHTING ‐ EXTERIOR, WALL FLOOD (SV, MH, ID, LED) 2015 12 EA BUS RAMP 15
1 BUS RAMP D5020 LIGHTING ‐ EXTERIOR, WALL LANTERN or FLOOD (INC, CFL, LED) 2015 15 EA BUS RAMP 15
1 BUS RAMP D5020 LIGHTING SYSTEM, INTERIOR ‐ WAREHOUSE 2015 127488 SF 0.05 BUS RAMP 20
1 BUS RAMP D5030 CAMERA, CCTV 2015 37 EA 10
1 BUS RAMP G2012 CONCRETE VEHICULAR PAVING 2015 42495 SF BUS RAMP 40
Phase 1 Bus Ramp Subtotal
Phase 1 Roof Park
1 ROOF PARK C3010 WALL FINISH ‐ PAINT, STANDARD 2015 8377 SF COMMON/BOH 12
1 ROOF PARK C3010 WALL FINISH ‐ PAINT, STANDARD 2015 3345 SF COMMON/BOH 12
1 ROOF PARK C3010 WALL FINISH ‐ TILE, CERAMIC / STONE, STANDARD 2015 3321 SF COMMON/BOH 30
1 ROOF PARK C3010 WALL FINISH ‐ GLASS 2015 1292 SF CALTRAIN 40
1 ROOF PARK B1010 FLOORING ‐ WOOD STRIP, FIR PORCH 2015 3700 SF ROOF PARK 30
1 ROOF PARK C3020 FLOORING ‐ CARPET, TILE OR ROLL, STANDARD 2015 244 SF COMMON/BOH 12
1 ROOF PARK C3020 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY STANDARD 2015 800 SF COMMON/BOH 30
1 ROOF PARK C3020 FLOORING ‐ TERRAZZO/POLISHED CONCRETE RENEWAL 2015 464 SF COMMON/BOH 50
1 ROOF PARK C3020 FLOORING ‐ FLUID APPLIED, EPOXY / ACRYLIC / POLYURETHANE 2015 3336 SF COMMON/BOH 15
1 ROOF PARK C3020 FLOORING ‐ FLUID APPLIED, EPOXY / ACRYLIC / POLYURETHANE 2015 758 SF COMMON/BOH 15
1 ROOF PARK C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 3140 SF COMMON/BOH 24
1 ROOF PARK C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 800 SF COMMON/BOH 24
1 ROOF PARK C3030 CEILING FINISH ‐ METAL OR SPECIALTY TILE 2015 464 SF COMMON/BOH 40
1 ROOF PARK D2010 PLUMBING FIXTURE ‐ LAVATORY, WALL HUNG 2015 9 EA PHASE 1 35
1 ROOF PARK D2010 PLUMBING FIXTURE ‐ URINAL 2015 3 EA PHASE 1 35
1 ROOF PARK D2010 PLUMBING FIXTURE ‐ WATER CLOSET, TANKLESS 2015 15 EA PHASE 1 35
1 ROOF PARK D2020 BACKFLOW PREVENTER (1‐2 INCHES) 2015 2 EA M101, M201 10
Page D.6
Program Life Cycle
Phase Uniformat II Description COST BASIS Quantity Units Complexity Identifier Life Cycle
Component Adjustment
1 ROOF PARK D3040 PUMP ‐ ELECTRIC (10 ‐ 15 HP) 2015 25 HP BUS FOUNTAIN P201 25
1 ROOF PARK D3040 PUMP ‐ ELECTRIC (10 ‐ 15 HP) 2015 40 HP BUS FOUNTAIN P301 25
1 ROOF PARK D5020 LIGHTING ‐ EXTERIOR, STANCHION LUMINAIRE, 30‐FOOT 2015 3 EA PHASE 1 15
1 ROOF PARK D5020 LIGHTING ‐ EXTERIOR, WALL LANTERN or FLOOD (INC, CFL, LED) 2015 282 EA PHASE 1 15
1 ROOF PARK G2031 CONCRETE PEDESTRIAN PAVING 2015 43000 SF ROOF PARK 35
Phase 1 Roof Park Subtotal
Phase 1 Bus Storage Facility
1 BSF B2010 WALL, EXTERIOR, MASONRY POINTING 2015 8448 SF BSF SITE WALL 30
1 BSF B2010 WALL, EXTERIOR, MASONRY POINTING 2015 600 SF BSF SUPPORT BLDG 30
1 BSF B2010 WALL, EXTERIOR, SIDING, METAL, HORIZONTAL OR VERTICAL 2015 1710 SF BSF ADMIN BLDG 30
1 BSF B2010 WALL, EXTERIOR, SIDING, METAL, HORIZONTAL OR VERTICAL 2015 90 SF BSF GUARD SHACKS 30
1 BSF B2020 GLASS, WINDOW, ALUMINUM OR WOOD, STANDARD 2015 210 SF BSF ADMIN BLDG 40
1 BSF B2020 GLASS, WINDOW, ALUMINUM OR WOOD, STANDARD 2015 50 SF BSF GUARD SHACKS 40
1 BSF B2030 DOOR AND FRAME, EXTERIOR, SWINGING, ALUMINUM AND GLASS 2015 2 LEAF BSF GUARD SHACKS 25
1 BSF B2030 DOOR AND FRAME, EXTERIOR, SWINGING, HOLLOW METAL 2015 3 LEAF BSF ADMIN BLDG 40
1 BSF B2030 DOOR AND FRAME, EXTERIOR, SWINGING, HOLLOW METAL 2015 6 LEAF BSF SUPPORT BLDG 40
1 BSF B2030 DOOR AND FRAME, EXTERIOR, SWINGING, SCREEN, LOCK 2015 10 LEAF BSF MAINT GATES 35
1 BSF B2030 DOOR AND FRAME, EXTERIOR, SWINGING, SCREEN, LOCK 2015 2 LEAF BSF SUPPORT BLDG 35
1 BSF B3010 ROOF ‐ PANEL, ALUMINUM OR GALVANIZED, STANDING SEAM 2015 1647 SF BSF ADMIN BLDG 40
1 BSF B3010 ROOF ‐ PANEL, ALUMINUM OR GALVANIZED, STANDING SEAM 2015 37 SF BSF GUARD SHACKS 40
1 BSF B3010 ROOF ‐ PANEL, ALUMINUM OR GALVANIZED, STANDING SEAM 2015 920 SF BSF SUPPORT BLDG 40
1 BSF C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 6 LEAF BSF ADMIN BLDG 40
1 BSF C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 6 EA BSF ADMIN BLDG 20
1 BSF C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 3 EA BSF ADMIN BLDG 20
1 BSF C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 2 EA BSF GUARD SHACKS 20
1 BSF C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 6 EA BSF SUPPORT BLDG 20
1 BSF C3010 WALL FINISH ‐ PAINT, STANDARD 2015 2060 SF BSF ADMIN BLDG 12
1 BSF C3010 WALL FINISH ‐ PAINT, STANDARD 2015 1980 SF BSF SUPPORT BLDG 12
1 BSF C3010 WALL FINISH ‐ PANEL, MEDICAL / LABORATORY APPLICATION 2015 1350 SF BSF ADMIN BLDG 20
1 BSF C3010 WALL FINISH ‐ PANEL, MEDICAL / LABORATORY APPLICATION 2015 140 SF BSF GUARD SHACKS 20
1 BSF C3020 FLOORING ‐ FLUID APPLIED, PAINT OR CLEAR SEAL 2015 37 SF BSF GUARD SHACKS 10
1 BSF C3020 FLOORING ‐ FLUID APPLIED, PAINT OR CLEAR SEAL 2015 745 SF BSF SUPPORT BLDG 10
1 BSF C3020 FLOORING ‐ ATHLETIC, RUBBER, TILE OR ROLL 2015 1314 SF BSF ADMIN BLDG 15
1 BSF C3030 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE, STANDARD 2015 438 SF BSF ADMIN BLDG 30
1 BSF C3030 CEILING FINISH ‐ PAINTED OR STAINED, STANDARD 2015 876 SF BSF ADMIN BLDG 24
1 BSF D2010 PLUMBING FIXTURE ‐ LAVATORY, COUNTER 2015 4 EA BSF ADMIN BLDG 35
1 BSF D2010 PLUMBING FIXTURE ‐ URINAL 2015 2 EA BSF ADMIN BLDG 35
1 BSF D2010 PLUMBING FIXTURE ‐ WATER CLOSET, TANKLESS 2015 5 EA BSF ADMIN BLDG 35
1 BSF D2020 SUPPLY PIPING SYSTEM ‐ SHOPS / TRADES, DRY LABORATORY 2015 1460 SF 1.18 BSF ADMIN BLDG 35
1 BSF D2020 WATER HEATER (ELECTRIC INSTANTANEOUS) 2015 3 EA BSF ADMIN BLDG 10
1 BSF D2030 DRAIN PIPING SYSTEM ‐ SHOPS / TRADES, DRY LABORATORY 2015 1460 SF 1.18 BSF ADMIN BLDG 40
1 BSF D3030 PTAC, DX/ HP COOL, ELEC HEAT (<=0.5 TON) 2015 0.5 TON BSF GUARD SHACKS 25
1 BSF D3050 PACKAGE HVAC UNIT, DX, GAS OR ELECTRIC HEAT, SINGLE‐ZONE (<= 5 TON) 2015 10 TON BSF ADMIN BLDG 25
1 BSF D4050 EXIT SIGN ‐ WITH BATTERY BACK‐UP 2015 2 EA BSF ADMIN BLDG 20
1 BSF D5010 ELECTRICAL DISTRIBUTION NETWORK ‐ OFFICE 2015 37 SF 1.18 BSF GUARD SHACKS 40
1 BSF D5010 ELECTRICAL DISTRIBUTION NETWORK ‐ SHOPS / TRADES, DRY LABORATORY 2015 1460 SF 1.18 BSF ADMIN BLDG 40
1 BSF D5010 ELECTRICAL DISTRIBUTION NETWORK ‐ WAREHOUSE 2015 827 SF 1.18 BSF SUPPORT BLDG 40
1 BSF D5010 MAIN SWITCHBOARD W/BREAKERS (<400 AMP) 2015 400 AMP BSF 20
1 BSF D5020 LIGHTING ‐ EXTERIOR, STANCHION LUMINAIRE, 12‐FOOT 2015 10 EA BSF 15
1 BSF D5020 LIGHTING ‐ EXTERIOR, STANCHION LUMINAIRE, 30‐FOOT 2015 7 EA BSF 15
1 BSF D5020 LIGHTING ‐ EXTERIOR, WALL LANTERN or FLOOD (INC, CFL, LED) 2015 7 EA BSF ADMIN BLDG 15
1 BSF D5020 LIGHTING SYSTEM, INTERIOR ‐ OFFICE 2015 37 SF 1.18 BSF GUARD SHACKS 20
1 BSF D5020 LIGHTING SYSTEM, INTERIOR ‐ SHOPS / TRADES, DRY LABORATORY 2015 1460 SF 1.18 BSF ADMIN BLDG 20
1 BSF D5020 LIGHTING SYSTEM, INTERIOR ‐ WAREHOUSE 2015 827 SF 1.18 BSF SUPPORT BLDG 20
1 BSF D5030 CAMERA, CCTV 2015 6 EA 10
1 BSF G2012 CONCRETE VEHICULAR PAVING 2015 27984 SF BUS STORAGE FACILITY 40
1 BSF G2031 CONCRETE PEDESTRIAN PAVING 2015 7552 LF BSF 35
1 BSF G2040 FENCING, PERIMETER SECURITY 2015 528 LF BSF 30
Phase 1 Bus Storage Facility Subtotal
Phase 1 Total
Page D.7
Program Life Cycle
Phase Uniformat II Description COST BASIS Quantity Units Complexity Identifier Life Cycle
Component Adjustment
1 URP B2010 WALL, EXTERIOR, TILE OR GLASS BLOCK CLEAN, GROUT, AND REPAIR 2015 310 SF 1.12 15
1 URP B2010 WALL, EXTERIOR, TILT‐UP OR PRECAST CONCRETE PANELS RESTORE 2015 1142 SF 1.12 30
1 URP B2020 GLASS, STOREFRONT 2015 1262 SF 1.12 TRANSOM, STOREFRONT 60
1 URP B2030 DOOR AND FRAME, EXTERIOR, SWINGING, ALUMINUM AND GLASS 2015 19 LEAF 25
1 URP B2030 DOOR, EXTERIOR, OVERHEAD ROLLING METAL, LOCK 2015 160 SF 30
1 URP B2030 DOOR OPERATOR, OVERHEAD DOOR, COMMERCIAL, PADS 2015 1 EA 15
1 URP B3010 ROOF ‐ PANEL, ALUMINUM OR GALVANIZED, STANDING SEAM 2015 985 SF 40
1 URP B3010 ROOF ‐ GREEN COVERING OVER MEMBRANE 2015 2858 SF S12 20
1 URP C1020 DOOR AND FRAME, INTERIOR, NON‐RATED 2015 12 LEAF 40
1 URP C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 12 EA 20
1 URP C1020 DOOR LOCK, COMMERCIAL‐GRADE 2015 19 EA 20
1 URP C3020 FLOORING ‐ TILE, CERAMIC / STONE / QUARRY STANDARD 2015 270 SF 30
1 URP C3020 FLOORING ‐ FLUID APPLIED, PAINT OR CLEAR SEAL 2015 1340 SF 10
1 URP C3030 CEILING FINISH ‐ SUSPENDED ACOUSTICAL TILE, STANDARD 2015 1610 SF 30
1 URP D2010 DRINKING FOUNTAIN, DUAL‐LEVEL 2015 1 EA 10
1 URP D2010 PLUMBING FIXTURE ‐ LAVATORY, WALL HUNG 2015 4 EA 35
1 URP D2010 PLUMBING FIXTURE ‐ SINK, SERVICE/LAUNDRY/UTILITY 2015 1 EA 35
1 URP D2010 PLUMBING FIXTURE ‐ URINAL 2015 2 EA 35
1 URP D2010 PLUMBING FIXTURE ‐ WATER CLOSET, TANKLESS 2015 4 EA 35
1 URP D2020 BACKFLOW PREVENTER (1‐2 INCHES) 2015 1 EA 10
1 URP D2020 SUPPLY PIPING SYSTEM ‐ RETAIL 2015 10376 SF 1.18 35
1 URP D2020 WATER HEATER ‐ COMMERCIAL, GAS (310‐613 MBH INPUT) 2015 500 MBH 25
1 URP D2030 DRAIN PIPING SYSTEM ‐ RETAIL 2015 10376 SF 1.18 40
1 URP D3040 AIR HANDLING UNIT ‐ OUTDOOR MAKEUP, GAS (208‐263 MBH INPUT) 2015 250 MBH 25
1 URP D3040 FAN ‐ CENTRIFUGAL ROOF EXHAUST, 1/4" SP (20"‐22" DIAMETER) 2015 4 EA 20
1 URP D3040 HVAC DISTRIBUTION NETWORKS ‐ RETAIL 2015 10376 SF 1.18 40
1 URP D3050 PACKAGE HVAC UNIT, DX, GAS OR ELECTRIC HEAT, SINGLE‐ZONE (9‐35 TON) 2015 37.5 TON ACU1‐3 25
1 URP D4010 FIRE SPRINKLER SYSTEM 2015 10376 SF 1.18 80
1 URP D4040 FIRE ALARM SYSTEM ‐ DEVICES 2015 10376 SF 1.18 18
1 URP D4050 EXIT SIGN ‐ CENTRAL POWER 2015 12 EA 20
1 URP D5010 ELECTRICAL DISTRIBUTION NETWORK ‐ RETAIL 2015 10376 SF 1.18 40
1 URP D5020 LIGHTING ‐ EXTERIOR, STANCHION LUMINAIRE, 12‐FOOT 2015 29 EA 15
1 URP D5020 LIGHTING ‐ EXTERIOR, WALL FLOOD (SV, MH, ID, LED) 2015 9 EA 15
1 URP D5020 LIGHTING SYSTEM, INTERIOR ‐ RETAIL 2015 10376 SF 1.18 20
1 URP G2012 ASPHALT VEHICULAR PAVING ‐ SEALCOAT AND STRIPE 2015 1214 SY P1 7
1 URP G2012 ASPHALT VEHICULAR PAVING ‐ SEALCOAT AND STRIPE 2015 12229 SY P2 7
Phase 1 Under Ramp Park Subtotal
Page D.8
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix E
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page E-1 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority
TRANSBAY TRANSIT CENTER PROGRAM
Operations and Maintenance Report Appendix E
In Association with Hatch Mott MacDonald and EPC Consultants, Inc. Page E-2 Rev. 0 MAR 16
Consultants to Transbay Joint Powers Authority