Professional Documents
Culture Documents
PMP 26.03.2024
PMP 26.03.2024
Planning Package – Details not there / We cannot Decompose (breaking into smaller components) – We
will be holding it and when we get details and then decompose. Such package is called the planning
package (not to be confused with real time. This is as per PMBOK)
Create WBS
1. Scope Management Plan
2. Refer to the Scope Statement
3. Consult Stakeholders
Techniques to be used
1. Documentation
2. Rolling Wave Planning – Create WBS & WBS Dictionary, Project Scope Statement
3. Progressive Elaboration – As we progress we are going to elaborate / expand the plan
Plan Schedule Management – How to manage the schedule, how to schedule activities, how to control
the schedule. What is the estimating technique we are going to use. How to measure performance, how
to strategize our process.
Define Activities
Inputs
1. Work Package – decompose – into activities – come out with the activity list
2. Scope Baseline
3. Schedule Management Plan
4. Environmental Factors
Techniques
1. Meetings
2. Expert Judgement
3. Decomposition
4. Rolling Wave Planning
Output
1. Activity List
2. Activity Attributes – Activity ID, WBS ID,
3. Milestone list
Sequencing the Activities
Techniques
1. Precedence Diagramming Method – Relationship between the Predecessor & Successor
1.1. FS – Finish to Start – Start the successor after completing the predecessor
1.2. SS – Start to Start – Starting the Successor in parallel to the start of predecessor
1.3. FF – Finish to Finish – After the predecessor finishes, the successor can be claimed as finish
1.4. SF – Start to Finish – Successor has to be finished, and then only we can go back to start the
predecessor
Dependency
1. Mandatory
2. Discretionary
3. Internal – Within Organization
4. External – Outsourcing
5. Internal Mandatory
6. External Mandatory
7. Internal Discretionary
8. External Discretionary
Sequence Activities
Inputs:
Schedule Management Plan
Activity List
Activity Attributes
Tools :
Dependency
Leads & Lags
Precedence Diagramming Method
Outcome:
Network Diagram
Estimate the Duration for Each Activity
Technique:
1. Analogous Estimating – Refer to the historical data & Consider the data as such (it would not be
accurate). In the very beginning, we may use analogous estimation
2. Parametric Estimation – Do a mathematic calculation based on variables (Extrapolation)
3. Bottom Up Estimation – Estimate at the lowest level and then sum-up (from duration of tasks to
activity to work packages to WBS) – it is more time consuming and better than Analogous
4. Three Point Estimation – 3 Reference Points
4.1. Triangular Distribution – Average of (P + M + O)
4.1.1. P – Pessimistic -
4.1.2. M – Most Likely -
4.1.3. O – Optimistic –
4.2. BETA / PERT – (P + 4M + O)/6 – this is more accurate
Inputs;
1. Schedule Management plan
2. Activity List
3. Activity Attributes
4. Risk Register
5. Resource Requirements
6. Environmental Factors
Techniques;
1. Analogous Estimating – historical data
2. Parametric Estimating – mathematical calculation based on variable
3. Bottom Up Estimating – estimate at the lowest level and sum up
4. Reserve Analysis – To manage the risk
5. Consult Experts
6. Conduct Meeting
7. Alternative Analysis – better reference
Output;
1. Duration Estimates
2. Basis of Estimates – Reference Document for estimates
The Estimates is only rough / approximate. We have to refine it and develop a Schedule
Note: in PMP 1 person or department has to execute the work from 8 hrs to 80 hrs
2. Schedule Compression
2.1. Fast Tracking – Doing Activities in parallel (Start to Start) in order to compress the schedule – when
there is no dependency – risk is higher
2.2. Crashing – Bring additional resources (only we have additional fund and additional resources)
Cost Management
Direct Cost – Cost incurred directly for the project
Indirect Cost – Cost incurred
Variable Cost
Fixed Cost
Processes
1. Plan Cost Management
Outcome is Cost Management Plan – How to define cost, budget & control cost
Estimate Cost – for the project
Techniques for Estimating Cost -
Came out with the budget
Identified Risk – Known Unknown – Identified the risk – come out with the action plan – allocate the cost
– its called as contingency reserve – PM has authority
Unidentified Risk – Unknown Unknown – Never know such risk but have to handle the risk – some
money can be allocated – this is called management reserve – PM does not have authority – PM can
request the management to allocate the funds and then use it
Risk Management
Assessment of Risks;
Probability – possibility of the risk happening (High, Low & Medium)
Impact – effect of the risk brought into the project
Note: Once the management approves the project management plan it is called “BASELINE”. Till then
changes can be made. Once the baseline is set, all changes have to go to through the Change request.
From now we move to the project execution.
Direct & Manage Project Work – Build the project as per the plan & the approved change request –
outcomes are the “Deliverables, Costing, Identifying Issues, Issue Log Update, Identify Change
Manage Project Knowledge – We are going to collect the knowledge (such as site beside and note down,
meeting)
Make the knowledge available to the team – going to use by share point / share drive (change request
may be initiated / once approved)
Interaction – Leadership / active listening skills / trustworthy person / being more mindful / taking care
of the people / trust will develop / networking / political awareness – aware of authoritative people /
change request can happen / based on the changes, respective plans can be updated
Manage Quality -
Check process & product design
Check the approved changes & Check the Operational Definition (Perform Quality Assurance)
Mcallends Theory of Needs
1. Needs for affiliation – people who like to be in an comfortable environment which is not or less
challenging
2. Needs for achievement – look for challenge
3. Needs for Power – people who need to be empowered
Mcgregors Theory
1. Theory X – people who micromanage. They do not trust the team
2. Theory Y – people who do not micromanage. They trust the team
Herzberg Theory
1. Motivating Factor – appreciations, recognitions, rewards, promotions for the team
2. Hygene Factor – do not motivate the individual but absence will demotivate the individual such as
Salary, Job Security
Expectancy Theory –
You are going to put in effort in expectation of a result
Result should fetch a value
Theory Z –
It’s a rare scenario
The employer are looking for a long term association and win-win situation whether they are not going
to override the other person.
Monitor Risks
1. Check for any more risks
2. Check for the priority for the already identifies risks
3. Check for the effectiveness of the risk response plan
Control Procurement
1. Inspect the physical product
2. Audit the processes are followed correctly
3. If there are changes, check for change requests
4. Make payment as per agreement