Professional Documents
Culture Documents
Lot 1.14 - Running Procedures
Lot 1.14 - Running Procedures
A Introduction
The FS-Seal seals against the casing outside diameter, where wide tolerance and rough surface finish
create difficult sealing conditions. A bump on the ID of the seal provides adequate interference for the
allowable casing outside diameter tolerances. A curved recess on the back of the seal controls the
squeeze on the seal, by allowing it to deflect outward when sealing against a larger than normal casing
outside diameter. Two springs are molded into the outer edges of the sealing surface and provide the
seal anti-extrusion capacity. These features make the FS-seal work for 10,000 psi test pressure when
sealing against rough casing outside diameter, and work for 15000 psi test pressure when seal against
machined surface with good surface finish. Equipment rated for 10,000 psi and below will be equipped
with 1/2″ LP test fitting and equipment rated for 15,000 psi will be equipped with 9/16″ HP test
fittings. The same FS seals are used in 10,000 psi and 15,000 psi equipment. Figures 1 and 2 show
equipment rated for 10,000 psi and 15,000 psi respectively.
Figure 1
Low Pressure ‘FS’ Port Diagram (2000psi-10000psi Rated Working Pressure)
Figure 2
High Pressure ‘FS’ Port Diagram (15000psi Rated Working Pressure)
Bulletin 6-18
ENGINEERING BULLETIN Page 2 of 4
Revision 0
B Safety Considerations
Obey all applicable national, provincial/state, Refer to the Stream-Flo Corporate Health and
and local laws and regulations regarding Safety Policy Manual for complete safety-
hazardous work environments as required. related issues.
Always wear Personal Protective Equipment Obey all safety rules and follow safe work
(PPE) appropriate to the job/site. procedures.
Check tools, equipment, personal protective Before you begin work, familiarize yourself
and safety equipment for hazards before using. with the site and any hazards that may exist.
C General Preparation
1. Check stamping and/or name plates of the head, hanger, and adapter to verify their suitability.
2. Ensure all fittings, lockscrews, and ancillary equipment is in place and functioning.
3. Examine and ensure all ring grooves are clean and free of damage. If necessary, dress surface with
emery cloth to restore smoothness.
4. Check the FS-Seals are in place and in good shape. If necessary, Grease the FS-Seals and the FS-Seal
preparations, and then install the FS-seals to the FS-Seal grooves.
5. Verify and locate all ports on secondary. Mark if necessary. Ensure you can identify each port from
the flange OD.
F Installation
1. If necessary, install primary packoff to the head below.
2. Install a new ring gasket in the top flange of the head below
3. Fill the cavity of the head below with light oil.
4. Grease the outside diameter of the casing stub or extended neck of casing hanger, the inside of the
head secondary counter bore, and the FS-Seals.
5. Pick up the head and orient the side outlets properly if the head has side outlets.
6. Carefully lower the head over the casing stub or extended neck of casing hanger.
7. Install flange nuts and make up the flange connection. See the following Engineering Bulletins for
proper flange make-up instructions.
EB 13-10: API 6A Flange Overview and Assembly
EB 13-14: Recommended Flange Bolt Torque for API 6A Flanges
Figure 4A
Pressure Test Between FS Seals & Pressure Test Flange Connection
Bulletin 05-01
ENGINEERING BULLETIN Page 1 of 3
Revision 3
A General
The blowout preventer (BOP) test plug is used
to test the BOP stack and to run/retrieve the
bowl protectors. It is also called the
"Combination Test Plug and Running Tool".
Note: The test plug is only designed to test the
BOP stack with pressure above the test plug.
The test plug should never be used to
pressure test casing below the plug.
The standard Combination Test Plug has:
Profile, corresponding to the type of casing
head it will be used with.
Replaceable seal, to seal in the casing head.
Four lugs on the upper part of the test plug
body. Figure 1
Weeping holes with buried pipe plugs.
Drill pipe connections: box top and bottom
(different type of connection is available on
special orders).
Central bore.
1 1/2" plug to close central bore.
It is also possible to combine two sizes, usually 11"
and 13 5/8", into one tool, using a 13 5/8" sleeve
which can be attached to the 11" plug using four (4)
set screws.
The "CC" test plug should be used with the "CC 22"
and "CC 29" casing heads and the "CU" all-purpose
head.
The type "H" plug should be used for the type "H"
casing heads only.
Figure 2
Bulletin 05-01
ENGINEERING BULLETIN Page 2 of 3
Revision 3
C BOP TESTING
1. Check the Test Plug:
Verify type and size.
Remove any seal protector, then clean and
visually inspect seal.
Check if internal plug is installed.
Check weeping hole plugs: If the lower BOP
rams are to be tested thrrough drill pipe remove
plugs; otherwise they must be made up tight.
2. Ensure that all lockscrews on the head are backed off.
Note: Lockscrews should never be used to retain the
test plug.
3. Make up the test plug and a joint of drill pipe or make
it up into drill string:
Note : The four lugs must be above the seal (see
Figure 3)
4. Lubricate OD of tool and seals.
5. Lower the test plug thru fully opened BOP (and riser)
into the casing head and land it. The tool’s weight
along with the landing joint (drill pipe) weight should
be adequate for setting the tool. If additional force
is required, it indicates a problem and the tool
should be brought back to the floor (inspect the
tool and stack before proceeding). Figure 3
6. Test the BOP.
7. After test is completed, pull test plug out.
Disassemble it from the string, clean and inspect it.
Bulletin 9-147
ENGINEERING BULLETIN Page 1 of 6
Revision 0
B Safety Considerations
Obey all applicable national, provincial/state,
and local laws and regulations regarding
hazardous work environments as required.
Always wear Personal Protective Equipment
(PPE) appropriate to the job/site.
Check tools, equipment, personal protective
and safety equipment for hazards before using.
Refer to the Stream-Flo Corporate Health and
Safety Policy Manual for complete safety-
related issues.
Obey all safety rules and follow safe work
procedures.
Before you begin work, familiarize yourself Figure 1
with the site and any hazards that may exist. Tubing Hanger
Bulletin 9-147
ENGINEERING BULLETIN Page 2 of 6
Revision 0
Figure 3
CSBS Metal Seal Ring and Gap
Bulletin 9-147
ENGINEERING BULLETIN Page 4 of 6
Revision 0
Figure 4
Tubing Head Adapter Seals and Ports
Bulletin 9-147
ENGINEERING BULLETIN Page 5 of 6
Revision 0
Figure 5
Installed Assembly
Bulletin 18-09
ENGINEERING BULLETIN Page 1 of 4
Revision 4
A General
The standard type ‘A’ lockdown assembly come standard in all Stream-Flo Crown tubing heads and can be
installed in casing heads on request. The assembly consists of a lockscrew, one beveled washer, one flat
washer, packing, and a bushing (see Figure 1). The lockdown assemblies are intended to retain a hanger or
bore protector and to energize compression packing seals.
Figure 1
Type ‘A’ Lockdown Assembly
During operation of the lockdown assembly, it is important to note the flange stand-off dimension of both
the lockscrew (‘S’) and bushing (‘B’) to prevent damaging any equipment. Tables at the end of this
document list these dimensions for both the retracted and engaged positions for the common flange sizes.
The tables also contain the recommended torque values. As there are various combinations of equipment
that are used with these lockdown assemblies note the tolerances given within the tables. For any special
equipment not listed in these tables, contact the SFI Engineering Department.
When making up lockscrews to retain a hanger the lockscrews should be made up to the proper standoff and
torque listed in the tables.
When making up lockscrews to retain a bore protector the lockscrews will not engage as far, therefore
lockscrew engagement will measure 1/4” (0.25”) more than the engaged dimensions given in the tables (e.g.
“Se” + 0.25”) and a lockscrew torque range of 65 to 85 ft-lbf should be used.
Torque values given are for new and properly lubricated equipment and therefore any corrosion or damage
to the lockdown assembly or prep will greatly affect the torque and needs to be considered when operating
the lockdown assembly.
Bulletin 18-09
ENGINEERING BULLETIN Page 2 of 4
Revision 4
CAUTION: DO NOT retract the lockscrew or bushing further than the ‘Sr’ (Retracted
Lockscrew) and ‘Br’ (Retracted Bushing) dimensions listed in the tables
below.
CAUTION: DO NOT stand in front of, or allow others to be in the path of, the lockdown
assembly that is being operated.
CAUTION: Whenever possible, bleed all pressure from the annulus, Christmas tree,
or flange test port before operating the lockdown assemblies.
Bulletin 18-09
ENGINEERING BULLETIN Page 3 of 4
Revision 4
If the lockscrew contacts the equipment in the bore when the stand-off dimension is approximately
1/2” or greater than the value listed in the tables, the equipment is not properly installed in the bore or
there may be a problem with lockdown assembly.
5. Run the remaining lockscrews in pairs directly across from each other as shown in Figure 2. This will
help keep the hanger centered in the head. Repeat step 4, following Figure 2, until all lockscrews are
contacting the device in the head.
6. Tighten the lockscrews in the same order as they were first engaged. When the lockscrews are fully
engaged the flange standoff dimension should measure ‘Se’ (see Table 1) or less. Recommended
torque values are provided in the tables.
7. Check that all lockscrew standoff dimensions, ‘Se’ (see Table 1), are approximately the same.
A large difference between lockscrew standoff dimensions may indicate the equipment is not properly
landed in the head.
8. Tighten the bushings in pairs following the same procedure as was used for the lockscrews. The
bushing standoff dimension must be ‘Be’ (see Table 1). Recommended torque values are provided in
the tables.
Bulletin No: 14-40
Engineering Bulletin Page: 1 of 14
Revision No: 3
Table of Contents
6.0 Maintenance..................................................................................... 9
6.1 General 9
This valve is available from 2000 to 15000 psi (13.8 to 103.5 MPa) working pressures and
in nominal sizes of 1 13/16″ to 11″ (46 mm to 279 mm) in flanged, threaded, or composite
block valve.
Obey all applicable national, provincial/state, and local laws and regulations
regarding hazardous work environments as required.
Always wear Personal Protective Equipment (PPE) appropriate to the job/site.
Check tools, equipment, personal protective and safety equipment for hazards
before using them.
Maintenance should be done by qualified personnel and additional requirements
from the end-user may also need to be followed.
Obey all safety rules and follow safe work procedures.
Before you begin work, familiarize yourself with the site and any hazards that
may exist.
IMPORTANT! Water expands when it freezes. If water is trapped in a valve and freezes,
expansion of the freezing water can cause pressure to build up inside the valve. If the
valve does not have a pressure relief mechanism, the built-up pressure can exceed the
test pressure of the valve, potentially causing damage to the valve.
Bulletin No: 14-40
ENGINEERING BULLETIN Page: 4 of 15
Revision No: 3
Field Service Manual, Gate Valve Model SL-2 / SL-3
2.0 NAME PLATE MARKING
3.0 INSTALLATION
3.1 Preparation: Check markings on valve. Remove protectors from end connections and
clean grease from ring grooves. Inspect ends; care should be taken to inspect ring
grooves for scratches, nicks or dirt. Scratches or foreign particles may cause leaks.
Small scratches can be smoothed by emery cloth. More serious damage should be
repaired in a service shop. Ensure there are no foreign objects in the valve bore, and
check the valve operation.
3.2 Valves can be installed in any position, and being bi-directional, in either direction.
Ensure access is provided to the handwheel and all fittings.
3.3 The diagram below shows the recommended tightening sequence for
making up the flange bolting (8 bolt shown, with 12 bolt flange, continue
pattern).
Bulletin No: 14-40
ENGINEERING BULLETIN Page: 5 of 15
Revision No: 3
Field Service Manual, Gate Valve Model SL-2 / SL-3
4.0 OPERATION
4.1 Valve must be operated only in the fully open or fully closed position. Operating the
valve in partially open (throttling) position is not permitted, and can result in extensive
damage.
2 1/16 (52) 12 12 12 12 14
7-1/16 (179)
35.5 35.5 35.5
X 6-1/8 (155.6)
7-1/16 (179)
35.5 35.5 35.5
X 6-3/8 (161.9)
7-1/16 (179) 39.5 39.5 39.5
Gear Op 115 115
9 (229) 49.5 49.5 49.5
Gear Op 144 144 144
The Model SL-2 / SL-3 slab gate must float freely. The gate seal does not depend on
stem force, therefore it is imperative that in the open or closed position the stem is not
jamming the gate.
6.1.1 Bearings must be lubricated (see section 6.2) and some parts occasionally replaced.
6.1.2 Filling the body with grease (see section 6.3 or 6.4) improves the valve performance.
Lubrication should be done every 15 to 20 cycles or every six months, whichever occurs first.
The lubrication interval may vary depending on the service conditions and more frequent
lubrication may be required. It is recommended to lubricate the valve body when ‘shutting-in’
the wellhead. Jet-Lube Ezy-Turn Polar or comparable grease is recommended for all sizes
up to 5000 psi (34.5 MPa) and for 10,000 psi (69 MPa) and 15,000 psi (103.5 MPa) valves
under 4-1/16″. Jet-Lube EZY-Turn Arctic #3, EZY-Turn H2S, or comparable grease is
recommended for use in 10,000 psi (69 MPa) and 15,000 psi (103.5 MPa) valves 4-1/16″
and larger.
The following table shows the approximate quantities of grease to use in lbs (kg):
Quantity of Grease Required, lbs (kg)
1 13/16 (46) 1.5 (0.7) 1.5 (0.7) 1.5 (0.7) 1.5 (0.7)
2 9/16 (65) 2.5 (1.1) 2.5 (1.1) 2.5 (1.1) 3.5 (1.6)
Important: The preferred and safest way to fill the valve body with grease is when the
line pressure is zero.
Bulletin No: 14-40
ENGINEERING BULLETIN Page: 10 of 15
Revision No: 3
Field Service Manual, Gate Valve Model SL-2 / SL-3
6.2 GREASING STEM BEARINGS
The body lubricant (see section 6.1.2) is suitable for greasing the bearings. Inject grease
into the 1/8" bearing grease fitting (see fig. 1 & 2, item #7), until it appears at the weep
hole beneath the o-ring on the bearing housing (see fig. 1 & 2, item #8). The stem
bearings should be lubricated at the same interval as the body, or more frequently if
required.
6.3.2 Cycle the valve several times to release any pressure, which may be trapped in the body.
Leave the valve in the partially open position.
6.3.3 Remove the protective cap on the grease fitting (see fig. 1 & 2, item #20).
6.3.6 Pump the appropriate amount of grease into the valve cavity (see section 6.1.2). If the
valve is removed from service you will see the grease enter the bore, signaling it is full.
6.3.7 Remove the grease gun from the fitting and replace protective cap on the fitting. Cycle
the valve back to its original position.
6.4.1 The lubricating equipment must have a working pressure equal to, or greater than the valve
working pressure. The equipment should be tested to ensure it is in proper working order.
6.4.3 Extra caution should be taken when removing the protective cap on the grease fitting (see
fig. 1 & 2, item #20). Slowly loosen the cap on the grease fitting and watch for grease or
fluid. Then remove ~1/2 turn at a time, stopping to allow any pressure to escape. If the
pressure is constant and the fitting continues to bleed, retighten the cap. The line pressure
must be bled off and the fitting replaced.
Bulletin No: 14-40
ENGINEERING BULLETIN Page: 11 of 15
Revision No: 3
Field Service Manual, Gate Valve Model SL-2 / SL-3
6.4.4 Attach grease gun to the grease fitting. Refer to the table in 6.1.2 for the base amount of
grease to use, then increase that amount by 20% to account for line pressure. Turn the
handwheel back and forth approximately 1/4 turn while pumping grease. If the valve is
under pressure but not flowing, partially closing the valve may be required to ensure
grease enters the cavity.
Caution: The grease injection pressure in the grease gun should never exceed the
working pressure of the valve.
6.4.5 Remove the grease gun and replace the protective cap.
It is recommended to replace the stem packing with the line pressure at zero and the
valve removed from service. The following precautions should be used when replacing
the stem packing with a valve in service.
6.5.1 Valve must be ‘backseated’ if any pressure is present in the line. Close the valve
completely and do not backoff the handwheel.
6.5.2 Loosen the bearing housing and at the same time turn handwheel clockwise and take up
the slack created by loosening the bearing housing. Loosen the housing more and turn
handwheel clockwise. Repeat. If loosening of the housing will not create any slack to the
handwheel, it signals that the stem is ‘backseated’.
Caution: Bearing housing should not be loosened by more than 2 ½ turns before
‘backseating’ is achieved. If bearing housing does not move freely after 2 ½ turns, do not
remove the housing. The valve should be removed from service for the appropriate
repairs.
6.5.3 If the bearing housing rotates freely, remove protective cap from the grease fitting located
on the bonnet.
Note: Slowly loosen the cap on the grease fitting and watch for grease or fluid. Then
remove ~1/2 turn at a time, stopping to allow any pressure to escape. If the
pressure is constant and the fitting continues to bleed, retighten the cap. The line
pressure must be bled off and the fitting replaced.
Using a pressure relief tool, unseat the ball on the grease fitting and bleed off any
pressure trapped above backseat.
If pressure bleeds off to zero, valve is successfully ‘backseated’ and the bearing housing
may be disassembled. If there is a persistent leak, a moderate force is required to turn
handwheel clockwise tightly. Do not use a cheater bar or a wrench on the handwheel to
achieve backseat seal.
Bulletin No: 14-40
ENGINEERING BULLETIN Page: 12 of 15
Revision No: 3
Field Service Manual, Gate Valve Model SL-2 / SL-3
6.5.4 Remove the handwheel, bearing housing, and the outer bearing (each bearing consists of
two thrust washers and a roller cage assembly). Knock out the shear pin and remove the
stem adapter and other bearing. Inspect stem adapter and replace if bearing surfaces show
damage or pitting. Replace the o-rings on the bearing housing and stem adapter if required.
6.5.5 If only the shear pin and/or bearings need replacement go to step 6.5.9.
Note: When replacing stem packing on a valve in service, proceed with caution. If pressure
is found leaking from the backseat, immediately stop all further action and reduce line
pressure in the valve.
6.5.6 Unscrew the packing retainer (see Fig. 1 & 2, item #10).
BONNET
6.5.7 Retrieve the stem packing using a pick, STEM
prongs, or packing hooks to pull the
STEM
packing out, or by injecting body grease
PACKING
into the grease fitting to hydraulic the
packing out. Care should be taken not
to damage the sealing surface on the
stem or bonnet stuffing box. Apply
adequate grease to new packing set
and slide packing onto stem. Slowly
and evenly tap packing into the bonnet
taking care not to damage any of the
sealing surfaces.
6.5.8 Inspect and clean threads on the bonnet and packing retainer. Apply thread lubricant to
both threads and install the packing retainer. Thread packing retainer until it bottoms out
on the bonnet, then tighten firmly.
6.5.9 Pack bearings with grease. Install the bottom bearing, stem adapter, shear pin, and the top
bearing. Apply thread lubricant to the bearing housing and thread it onto the bonnet
ensuring the o-ring on the stem adapter is correctly in place. Do not fully tighten housing.
Replace handwheel.
6.5.10 Remove the pressure relief tool and replace the cap on the grease fitting. Very slowly unseat
the stem by turning it to open (counterclockwise) and tighten the bearing housing to
mechanically release the backseat seal.
6.5.12 Grease the bearings (see section 6.2) and the body (see section 6.3 or 6.4).
Bulletin No: 14-40
ENGINEERING BULLETIN Page: 13 of 15
Revision No: 3
Field Service Manual, Gate Valve Model SL-2 / SL-3
7.0 TROUBLESHOOTING AND REPAIRS
7.1 TROUBLESHOOTING
7.1.1 BODY
Problem Area Malfunctioning Procedure for
Component / Problem Repairing
Leakage at end Ring groove seal area Return for reconditioning
connection damaged
Inadequate torque on flange Apply torque as per API
studs and nuts 6A
Damaged threads of Return for reconditioning
threaded end connection
Threaded end connection Tighten as required
loose
Leakage downstream Scored or worn seats Replace seats
Scored or worn gate Replace gate
Improper operation Backoff handwheel ¼ to ½
turn (see section 4.2)
7.1.2 BONNET
Leakage at the Fitting failure Replace fitting
grease fitting (see Loose fitting Tighten fitting
fig. 1 & 2, item #20) Bonnet port thread damage Return for reconditioning
Leakage between Damaged bonnet gasket Return for reconditioning
body and bonnet Damaged bonnet seal area Return for reconditioning
(see fig. 1 & 2, item Damaged valve body Return for reconditioning
#21 and #15) Improper torque on bonnet Re-torque nuts as per
nuts (see fig. 1 & 2, item Stream-Flo specification
#14) (see section 7.2.5)
Leakage at bearing Stem packing failure Remove from service and
grease fitting (see fig. replace stem packing
1 & 2, item #7) or Replace stem packing after
beneath o-ring on backseating (see section
bearing housing (see 6.5)
fig. 1 & 2, item #8)
Unable to remove Threads stripped or Return for reconditioning
bearing housing (see damaged
fig. 1 & 2, item #4)
Bulletin No: 14-40
ENGINEERING BULLETIN Page: 14 of 15
Revision No: 3
Field Service Manual, Gate Valve Model SL-2 / SL-3
Problem Area Malfunctioning Procedure for
Component / Problem Repairing
Unable to backseat Bearing housing or bonnet Return for reconditioning
stem (see fig. 1 & 2, threads damaged
item #12) Damaged or corroded Return for reconditioning
backseat
Unable to remove Threads stripped or Return for reconditioning
packing retainer (see damaged
fig. 1 & 2, item #10)
7.1.3 OPERATION
Hard to operate Iced up due to hydrates or Heat valve using steam and
low temperature inject grease into body (see
section 6.3 or 6.4)
Accumulation of foreign Return for reconditioning
matter such as sand or
cement
Damaged stem bearings or Replace bearings (see
inadequate lubrication section 6.5)
Inject grease (see section
6.2)
Inadequate body lubrication Inject grease into valve
body (see section 6.3 or
6.4)
Damaged stem or lift nut Return for reconditioning
threads
Handwheel moves Shear pin broken Replace shear pin
freely but valve
operating
sporadically