Equipment Dispatching Schedule

Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING SLOPE PROTECTION AND PCCP KABACAN FC 12:00 PM 4:00 PM NO UPDATE DUE TO LOW SIGNAL

2 TM-7 CAMANAY POURING PAVED SHOULDER ANTIPAS 12:00 PM 4:00 PM 1 BATCH

3 TM-8 ELONO POURING PAVED SHOULDER & PCCP ANTIPAS 12:00 PM 4:00 PM 1 BATCH

4 TM-9 SALMORIN POURING PAVED SHOULDER & PCCP ANTIPAS 12:00 PM 4:00 PM 2 BATCH

5 TM-12 PALMA POURING SLOPE PROTECTION AND PCCP PINGUIAMAN BR. 12:00 PM 4:00 PM

WAITING FOR PRIME TO DELIVER


6 TH-2 DARAUG MOBILIZED EQUIPMENT MARBOL BR. 12:00 PM 4:00 PM 1
THE MATERIALS

AT 3:40 PM, DONE LOADING


7 TH-3 NAVARRO TRANSPORT MATERIALS MARBOL BR. 12:00 PM 4:00 PM 1
MATERIALS

8 TH-4 BAJADOR UNLOADING BITUMEN JIP 12:00 PM 4:00 PM 1 AT 1:37 PM, START UNLOADING

9 TH-5 MAMBURAM PICK UP RCPC BANGKAL 12:00 PM 4:00 PM 1

10 TH-6 MARIPOSQUE PICK UP SMC (CANCELLED) LIBOO 12:00 PM 4:00 PM 1 AT 3:30 PM, DONE CHANGE TIRE

11 TH-7 AMILDA PICK UP CONTAINER VAN JIP 12:00 PM 4:00 PM 1 AT 3:40 PM, TRAVEL TO JIP

12 TH-8 YURAG PICK UP DIESEL GENSAN 12:00 PM 4:00 PM 1 WAITING FOR LOADING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 7:30 AM NO UPDATE DUE TO LOW SIGNAL

AT 9:30 AM, WALA PA KASTART


2 TM-7 CAMANAY POURING PCCP PANGAO-AN 6:00 AM BATCH
AT 9:30 AM, WALA PA KASTART
3 TM-8 ELONDO POURING PCCP PANGAO-AN 6:00 AM
BATCH
AT 9:30 AM, ONGOING DEWATERING
4 TM-9 SALMORIN POURING LEAN CONCRETE STA. FELOMINA 7:30 AM OF ABUTMENT

5 TM-12 PALMA CANCELLED POURING PINGUIAMAN BR. 7:30 AM DEFECTIVE INJECTION PUMP SA BH

6 TM-16 ABATAYO POURING PCCP SBC 7:30 AM 1 BATCH AT 8:37 AM, START BATCH

7 TM-19 PALMARES POURING PCCP SBC 7:30 AM 1 BATCH AT 8:12 AM, START BATCH

8 TM-20 MALLO POURING CONCRETE BARRIER CALUNASAN 7:30 AM 1 BATCH AT 9:27 AM, START BATCH

9 TM-19 PALMARES POURING LINE CANAL NEW RIZAL 7:30 AM 1 BATCH AT 9:47 AM, START BATCH

10 TH-2 DARAUG MOBILIZED BH-28 INAS FC - MATEO BR. 7:30 AM ON TRAVEL

11 TH-3 NAVARRO TRANSPORT BOOM & COUNTERWEIGHT (CR-01) MARBOL BR. - MATEO BR. 7:30 AM ON TRAVEL

12 TH-4 BAJADOR WAITING TO UNLOAD CONTAINER VAN JIP 7:30 AM STANDBY

13 TH-5 MAMBURAM DELIVER RCPC NEW RIZAL 7:30 AM ON TRAVEL

14 TH-6 MARIPOSQUE TRANSPORT DIESEL HAMMER MARBOL BR. - MATEO BR. 7:30 AM ON TRAVEL

15 TH-7 AMILDA WAITING TO UNLOAD BITUMEN JIP 7:30 AM AROUND 8:13 AM, ARRIVED AT JIP

12 TH-8 YURAG PICK UP DIESEL GENSAN 7:30 AM WAITING FOR LOADING


Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC
Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 22, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 7:30 AM 12:00 PM WAITING FOR UPDATE

2 TM-7 CAMANAY POURING PCCP PANGAO-AN 6:00 AM 12:00 PM WAITING FOR UPDATE

3 TM-8 ELONDO POURING PCCP PANGAO-AN 6:00 AM 12:00 PM WAITING FOR UPDATE

4 TM-9 SALMORIN POURING LEAN CONCRETE STA. FELOMINA 7:30 AM 12:00 PM WAITING FOR UPDATE

5 TM-12 PALMA CANCELLED POURING PINGUIAMAN BR. 7:30 AM 12:00 PM DEFECTIVE INJECTION PUMP SA BH

6 TM-16 ABATAYO POURING PCCP SBC 7:30 AM 12:00 PM 3 BATCH 25.2 CBM

7 TM-19 PALMARES POURING PCCP SBC 7:30 AM 12:00 PM 1 BATCH 8.4 CBM

8 TM-20 MALLO POURING CONCRETE BARRIER CALUNASAN 7:30 AM 12:00 PM 2 BATCH

9 TM-19 PALMARES POURING LINE CANAL NEW RIZAL 7:30 AM 12:00 PM 1 BATCH

10 TH-2 DARAUG MOBILIZED CR-01 MARBOL BR. - MATEO BR. 7:30 AM 12:00 PM WAITING FOR UPDATE

11 TH-3 NAVARRO TRANSPORT BOOM & COUNTERWEIGHT (CR-01) MARBOL BR. - MATEO BR. 7:30 AM 12:00 PM WAITING FOR UPDATE

PICK UP RCPC AT BANGKAL AFTER


12 TH-4 BAJADOR WAITING TO UNLOAD CONTAINER VAN JIP 7:30 AM 12:00 PM
UNLOAD CONTAINER VAN

PICK UP SMC AT DARONG AFTER


13 TH-5 MAMBURAM UNLOADING PHENOLIC BOARD LIBOO WAREHOUSE 7:30 AM 12:00 PM UNLOAD

14 TH-6 MARIPOSQUE TRANSPORT DIESEL HAMMER MARBOL BR. - MATEO BR. 7:30 AM 12:00 PM WAITING FOR UPDATE

15 TH-7 AMILDA WAITING TO UNLOAD BITUMEN JIP 7:30 AM 12:00 PM AROUND 8:13 AM, ARRIVED AT JIP

12 TH-8 YURAG PICK UP DIESEL GENSAN 7:30 AM 12:00 PM WAITING FOR LOADING
Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC
Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 22, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 12:00 PM 4:00 PM WAITING FOR UPDATE

2 TM-7 CAMANAY POURING PCCP PANGAO-AN 12:00 PM 4:00 PM WAITING FOR UPDATE

3 TM-8 ELONDO POURING PCCP PANGAO-AN 12:00 PM 4:00 PM WAITING FOR UPDATE

4 TM-9 SALMORIN POURING LEAN CONCRETE STA. FELOMINA 12:00 PM 4:00 PM WAITING FOR UPDATE

5 TM-12 PALMA CANCELLED POURING PINGUIAMAN BR. 12:00 PM 4:00 PM DEFECTIVE INJECTION PUMP SA BH

6 TM-16 ABATAYO POURING PCCP SBC 12:00 PM 4:00 PM 4 BATCH 7 BATCH IN TOTAL

7 TM-19 PALMARES POURING PCCP SBC 12:00 PM 4:00 PM 1 BATCH 1 BATCH IN TOTAL

8 TM-20 MALLO POURING PCCP CALUNASAN 12:00 PM 4:00 PM 1 BATCH 1 BATCH IN TOTAL

9 TM-20 MALLO POURING CONCRETE BARRIER CALUNASAN 12:00 PM 4:00 PM 2 BATCH 4 BATCH IN TOTAL

10 TM-19 PALMARES POURING LINE CANAL NEW RIZAL 12:00 PM 4:00 PM 1 BATCH 2 BATCH IN TOTAL

11 TH-2 DARAUG MOBILIZED CR-01 MARBOL BR. - MATEO BR. 12:00 PM 4:00 PM AT MATEO, ASSEMBLE CRANE

12 TH-3 NAVARRO TRANSPORT BOOM & COUNTERWEIGHT (CR-01) MARBOL BR. - MATEO BR. 12:00 PM 4:00 PM AT MATEO, ASSEMBLE CRANE

13 TH-4 BAJADOR PICK UP RCPC BANGKAL 12:00 PM 4:00 PM LOADING CEMENT FOR BANGKAL

14 TH-5 MAMBURAM PICK UP SMC DARONG 12:00 PM 4:00 PM ON TRAVEL

15 TH-6 MARIPOSQUE TRANSPORT DIESEL HAMMER MARBOL BR. - MATEO BR. 12:00 PM 4:00 PM AT MATEO, ASSEMBLE CRANE

16 TH-7 AMILDA WAITING TO UNLOAD BITUMEN JIP 12:00 PM 4:00 PM AROUND 8:13 AM, ARRIVED AT JIP
17 TH-8 YURAG PICK UP DIESEL GENSAN 12:00 PM 4:00 PM WAITING FOR LOADING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 23, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF APPROACH SLAB LINANGKOB BR. 7:30 AM ONGOING JO OF BALL BEARING

2 TM-7 CAMANAY POURING PCCP PANGAO-AN 5:00 AM WAITING FOR UPDATE

3 TM-8 ELONDO POURING PCCP PANGAO-AN 5:00 AM WAITING FOR UPDATE

4 TM-9 SALMORIN POURING OF GIRDER KABACAN BR. 7:30 AM AT 8:20 AM, LEAVE LIBOO COMP

AT 8:15 AM, DONE JO (INSTALL PTO


5 TM-11 ABATAYO POURING OF GIRDER KABACAN BR. 7:30 AM CROSSJOINT) , AT 8:20 AM, LEAVE
LIBOO COMP

6 TM-12 PALMA PINGUIAMAN BR. 7:30 AM WAITING FOR UPDATE

8 TM-19 PALMARES POURING PCCP NEW RIZAL 7:30 AM 1 BATCH 8:05 AM, START BATCH

9 TM-20 MALLO POURING PCCP NEW RIZAL 7:30 AM 1 BATCH 8:26 AM, START BATCH

10 TM-21 PLAZA POURING PCCP NEW RIZAL 7:30 AM 1 BATCH 8:39 AM, START BATCH

AT 8:30 AM, WAITING FOR BH AT


12 TH-2 DARAUG PULL OUT BH-29 DALIPE QUARRY - LIBOO 7:30 AM HIGHWAY

13 TH-3 NAVARRO PICK UP SMC DARONG 7:30 AM

14 TH-4 BAJADOR UNLOADING CEMENT BANGKAL 7:30 AM AFTER UNLOAD, PICK UP RCPC

15 TH-5 MAMBURAM ON GOING JO (ADJUST BRAKE-TRAILER) MOTORPOOL 7:30 AM

16 TH-6 MARIPOSQUE UNLOADING CEMENT LIBOO 7:30 AM

17 TH-7 AMILDA UNLOADING BITUMEN JIP 7:30 AM


18 TH-8 YURAG UNLOAD DIESEL JIP 7:30 AM

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 23, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF APPROACH SLAB LINANGKOB BR. 12:00 PM 4:00 PM WAITING FOR UPDATE

2 TM-7 CAMANAY POURING PCCP PANGAO-AN 12:00 PM 4:00 PM WAITING FOR UPDATE

3 TM-8 ELONDO POURING PCCP PANGAO-AN 12:00 PM 4:00 PM WAITING FOR UPDATE

4 TM-9 SALMORIN POURING OF GIRDER KABACAN BR. 12:00 PM 4:00 PM WAITING FOR UPDATE

5 TM-11 ABATAYO POURING OF GIRDER KABACAN BR. 12:00 PM 4:00 PM WAITING FOR UPDATE

6 TM-12 PALMA PINGUIAMAN BR. 12:00 PM 4:00 PM JO BH

8 TM-19 PALMARES POURING PCCP NEW RIZAL 12:00 PM 4:00 PM 3 BATCH

9 TM-20 MALLO POURING PCCP NEW RIZAL 12:00 PM 4:00 PM 2 BATCH TOTAL: 7 BATCH

10 TM-21 PLAZA POURING PCCP NEW RIZAL 12:00 PM 4:00 PM 2 BATCH

BANTAC - MANOBISA
12 TH-2 DARAUG TRANSPORT BH-07 12:00 PM 4:00 PM TRANSPORTED
QUARRY

13 TH-3 NAVARRO PICK UP RCPC BANGKAL 12:00 PM 4:00 PM EN ROUTE TO LIBOO

14 TH-4 BAJADOR PICK UP RCPC BANGKAL 12:00 PM 4:00 PM ON GOING LOADING

DELIVER 40TONS
15 TH-5 MAMBURAM TRANSPORT CEMENT PINGUIAMAN BR. 12:00 PM 4:00 PM SMC UNLOADINGG CEMENT

16 TH-6 MARIPOSQUE PICK UP BITUMEN PANABO 12:00 PM 4:00 PM EN ROUTE TO DAVAO

17 TH-7 AMILDA PICK UP HOLCIM PANACAN 12:00 PM 4:00 PM EN ROUTE TO DAVAO

18 TH-8 YURAG JO UNIT LIBOO 12:00 PM 4:00 PM WAITING TO UNLOAD DIESEL


Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC
Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 24, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 7:30 AM

2 TM-7 CAMANAY POURING PCCP ANTIPAS 7:30 AM

3 TM-8 ELONDO POURING PCCP ANTIPAS 7:30 AM

4 TM-9 SALMORIN POURING PCCP ANTIPAS 7:30 AM

5 TM-11 PALMARES POURING OF MANHOLE AND CATCH BASIN BUAYAN 7:30 AM

6 TM-12 PALMA PINGUIAMAN BR. 7:30 AM JO BH

TM-16 ABATAYO POURING PCCP NEW RIZAL 7:30 AM

9 TM-20 MALLO POURING PCCP NEW RIZAL 7:30 AM

10 TM-21 PLAZA POURING OF MANHOLE AND CATCH BASIN BUAYAN 7:30 AM

12 TH-2 DARAUG TRANSPORT BH-30 ANTIPAS 7:30 AM FROM SITE TO BATCHING PLANT

13 TH-3 NAVARRO PICK UP RCPC BANGKAL 7:30 AM

14 TH-4 BAJADOR PICK UP RCPC BANGKAL 7:30 AM

15 TH-5 MAMBURAM TRANSPORT CEMENT PINGUIAMAN BR. 7:30 AM WAITING TO UNLOAD

16 TH-6 MARIPOSQUE TRANSPORT BITUMEN JIP 7:30 AM WAIITNG FOR UNLOAD

17 TH-7 AMILDA PICK UP HOLCIM PANACAN 7:30 AM WAITING FOR LOADING

18 TH-8 YURAG JO UNIT LIBOO 7:30 AM


Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC
Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 27, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 1:00 PM WAITING FOR UPDATE

5 TM-11 PALMARES POURING RUBBLE CONRETE INAS FC 1:00 PM 3 BATCH

6 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 1:00 PM 1 BATCH

TM-16 ABATAYO POURING CONCRETE BARRIER CALUNASAN 1:00 PM 3 BATCH

9 TM-20 MALLO POURING PCCP NEW RIZAL 1:00 PM 3 BATCH

10 TM-21 PLAZA POURING PCCP NEW RIZAL 1:00 PM 2 BATCH

12 TH-2 TACDORO MOBILIZED EQUIPMENT MARBOL BR 1:00 PM TRANSPORT BH-16

13 TH-3 NAVARRO TRANSPORT CONCRETE PILES KABACAN BR 1:00 PM 6 CONCRETE PILES

14 TH-4 BAJADOR TRANSPORT WOBBLE CARMEN 1:00 PM AT JIP

15 TH-5 MAMBURAM PICK UP BITUMEN PANABO 1:00 PM ON TRAVEL (AT DAVAO)

16 TH-6 MARIPOSQUE PICK UP MATERIALS BANGKAL 1:00 PM ON GOING PICK UP

18 TH-8 YURAG PICK UP RCPC BANGKAL 1:00 PM ON GOING PICK UP

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 27, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 1:00 PM 4:00 PM WAITING FOR UPDATE

2 TM-11 PALMARES POURING RUBBLE CONRETE INAS FC 1:00 PM 4:00 PM 5 BATCH

3 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 1:00 PM 4:00 PM 1 BATCH WAITING FOR UPDATE

4 TM-16 ABATAYO POURING CONCRETE BARRIER CALUNASAN 1:00 PM 4:00 PM 5 BATCH 5 BATCH IN TOTAL

5 TM-20 MALLO POURING PAVED SHOULDER NEW RIZAL 1:00 PM 4:00 PM 3 BATCH
5 BATCH IN TOTAL
8 TM-21 PLAZA POURING PAVED SHOULDER NEW RIZAL 1:00 PM 4:00 PM 2 BATCH

6 TM-20 MALLO POURING LINE CANAL NEW RIZAL 1:00 PM 4:00 PM 1 BATCH
2 BATCH IN TOTAL
7 TM-21 PLAZA POURING LINE CANAL NEW RIZAL 1:00 PM 4:00 PM 1 BATCH

9 TH-2 TACDORO MOBILIZED EQUIPMENT KABACAN FC 1:00 PM 4:00 PM PULL OUT BH-10

10 TH-3 NAVARRO TRANSPORT CONCRETE PILES KABACAN BR 1:00 PM 4:00 PM 1 TRIP ONLY

11 TH-4 BAJADOR TRANSPORT WOBBLE CARMEN 1:00 PM 4:00 PM ON TRAVEL

12 TH-5 MAMBURAM PICK UP BITUMEN PANABO 1:00 PM 4:00 PM ON GOING PICK UP

13 TH-6 MARIPOSQUE PICK UP MATERIALS BANGKAL 1:00 PM 4:00 PM ON GOING PICK UP

14 TH-8 YURAG PICK UP RCPC BANGKAL 1:00 PM 4:00 PM ON GOING PICK UP

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 28, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 7:30 AM ONGOING JO OF HOPPER SUPPORT

2 TM-11 PALMARES POURING RUBBLE CONRETE INAS FC 7:30 AM CONTINUATION

3 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 7:30 AM

4 TM-16 ABATAYO POURING OF GROUTED RIPRAP MATALAM-MLANG 7:30 AM

TM-8 ELONDO POURING OF GIRDERS NIA BR. 7:30 AM

5 TM-20 MALLO POURING OF GROUTED RIPRAP MATALAM-MLANG 7:30 AM

TM-9 SALMORIN POURING OF GIRDERS NIA BR. 7:30 AM

9 TH-2 TACDORO MOBILIZED EQUIPMENT INAS FC - JIP 7:30 AM TRANSPORT BH-02

10 TH-3 NAVARRO TRANSPORT CONCRETE PILES KABACAN BR 7:30 AM LOADING CONCRETE PILES

11 TH-4 BAJADOR PICK UP CEMENT DARONG 7:30 AM WAITING FOR LOADING

12 TH-5 MAMBURAM PICK UP BITUMEN PANABO 7:30 AM ON GOING LOADING

13 TH-6 MARIPOSQUE PICK UP MATERIALS BANGKAL 7:30 AM ON GOING PICK UP

TH-7 AMILDA PICK UP CEMENT DARONG 7:30 AM ON TRAVEL

14 TH-8 YURAG TRANSPORT RCPC NEW RIZAL 7:30 AM UNLOAD RCPC

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule (FEBRUARY 28, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 7:30 AM 5:00 PM WAITING FOR UPDATE

2 TM-11 PALMARES POURING RUBBLE CONRETE INAS FC 7:30 AM 5:00 PM 3 BATCH CONTINUATION

3 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 7:30 AM 5:00 PM 1 BATCH

4 TM-16 ABATAYO POURING OF GROUTED RIPRAP MATALAM-MLANG 7:30 AM 5:00 PM 2 BATCH

5 TM-20 MALLO POURING OF GROUTED RIPRAP MATALAM-MLANG 7:30 AM 5:00 PM 3 BATCH

6 TM-8 ELONDO POURING OF GIRDERS NIA BR. 7:30 AM 5:00 PM 3 BATCH

7 TM-9 SALMORIN POURING OF GIRDERS NIA BR. 7:30 AM 5:00 PM 2 BATCH

8 TH-2 TACDORO MOBILIZED EQUIPMENT CARMEN 7:30 AM 5:00 PM

9 TH-3 NAVARRO TRANSPORT CONCRETE PILES KABACAN BR 7:30 AM 5:00 PM UNLOADING CONCRETE PILES

10 TH-4 BAJADOR PICK UP CEMENT DARONG 7:30 AM 5:00 PM DELIVER CEMENT TO BIAO

11 TH-5 MAMBURAM TRANSPORT BITUMEN PANABO - LIBOO 7:30 AM 5:00 PM AT 4:30 PM, NAABOT LIBOO

12 TH-6 MARIPOSQUE PICK UP MATERIALS BANGKAL 7:30 AM 5:00 PM ON GOING PICK UP

13 TH-7 AMILDA PICK UP CEMENT DARONG 7:30 AM 5:00 PM WAITING FOR LOADING

14 TH-8 YURAG UNLOAD RCPC LIBOO 7:30 AM 5:00 PM WAITING TO UNLOAD RCPC

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 1, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

WALA PA KALARGA KAY WALA PAY SEMENTO


1 TM-4 RAPISTA POURING OF GROUTED RIPRAP KABACAN FC 7:30 AM 10:00 AM
SA SITE

2 TM-11 AQUINO POURING LINE CANAL NEW RIZAL 7:30 AM 10:00 AM 1 BATCH CONTINUATION

3 TM-12 PALMA POURING OF FOUNDATION PINGUIAMAN BR. 7:30 AM 10:00 AM 2 BATCH

4 TM-16 MALLO POURING OF GROUTED RIPRAP MATALAM-MLANG 7:30 AM 10:00 AM 2 BATCH

5 TM-19 PALMARES POURING LINE CANAL NEW RIZAL 7:30 AM 10:00 AM 1 BATCH

6 TM-8 ELONDO POURING OF LINE CANAL PANGAO-AN 7:30 AM 10:00 AM

WALA PA KALARGA KAY NAGPAWELDING SA


7 TM-9 SALMORIN POURING OF LINE CANAL ANTIPAS 7:30 AM 10:00 AM
TAMBUBO

8 TH-2 TACDORO MOBILIZED EQUIPMENT MATEO BR. - ANTIPAS 7:30 AM 10:00 AM BH-28, BH-11

9 TH-4 BAJADOR TRANSPORT CEMENT DARONG - LIBOO 7:30 AM 10:00 AM WAITING TO UNLOAD

10 TH-5 MAMBURAM UNLOADING BITUMEN JIP 7:30 AM 10:00 AM ONGOING

11 TH-6 MARIPOSQUE TRANSPORT CONCRETE PILES KABACAN BR 7:30 AM 10:00 AM ON GOING

12 TH-7 AMILDA MOBILIZED EQUIPMENT MARBOL BR. - MATEO BR 7:30 AM 10:00 AM BH-16

13 TH-8 YURAG PICK UP DIESEL GENSAN 7:30 AM 10:00 AM WAITING FOR SO

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 2, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF SLOPE PROTECTION KABACAN FC 7:30 AM 11:30 AM WAITING FOR UPDATE

2 TM-11 AQUINO POURING LINE CANAL ANTIPAS 7:30 AM 11:30 AM 1 BATCH

3 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. 7:30 AM 11:30 AM STANDBY

4 TM-16 ABATAYO POURING PCCP NEW RIZAL 7:30 AM 11:30 AM 2 BATCH

5 TM-19 PALMARES POURING PCCP NEW RIZAL 7:30 AM 11:30 AM 2 BATCH

6 TM-21 PLAZA POURING PCCP NEW RIZAL 7:30 AM 11:30 AM 2 BATCH

TM-20 MALLO POURING CONCRETE BARRIER CALUNASAN 7:30 AM 11:30 AM 1 BATCH

7 TM-20 MALLO POURING SIDEWALK CALUNASAN 7:30 AM 11:30 AM 1 BATCH

8 TM-8 ELONDO POURING LINE CANAL ANTIPAS 7:30 AM 11:30 AM 1 BATCH

9 TM-9 SALMORIN POURING SLOPE PROTECTION LINANGKOB BR 7:30 AM 11:30 AM 2 BATCH 4.5 CBM PER BATCH

10 TH-2 TACDORO TRANSPORT BULK TRUCK JIP 7:30 AM 11:30 AM DONE

11 TH-2 TACDORO MOBILIZED EQUIPMENT JIP-SBC 7:30 AM 11:30 AM BH-02 ; DONE

12 TH-2 TACDORO MOBILIZED EQUIPMENT LIBOO-KABACAN FC 7:30 AM 11:30 AM BH-10; ONGOING

13 TH-4 AMILDA TRANSPORT CONCRETE PILES KABACAN BR 7:30 AM 11:30 AM WAITING FOR LOADING

14 TH-5 MAMBURAM TRANSPORT CONCRETE PILES KABACAN BR 7:30 AM 11:30 AM ONGOING LOADING

15 TH-6 MARIPOSQUE PICK UP BITUMEN PANABO 7:30 AM 11:30 AM ON TRAVEL

16 TH-8 YURAG PICK UP DIESEL GENSAN 7:30 AM 11:30 AM WAITING FOR LOADING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
]\'
Equipment Dispatching Schedule(March 2, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF SLOPE PROTECTION KABACAN FC 12:00 PM 5:00 PM 2 BATCH 4 BATCH IN TOTAL

2 TM-11 AQUINO POURING LINE CANAL ANTIPAS 12:00 PM 5:00 PM 1 BATCH

3 TM-11 AQUINO POURING BOX CULVERT ANTIPAS 12:00 PM 5:00 PM 1 BATCH IN TOTAL

4 TM-11 AQUINO POURING PAVED SHOULDER ANTIPAS 12:00 PM 5:00 PM 1 BATCH

5 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. 12:00 PM 5:00 PM STANDBY

6 TM-16 ABATAYO POURING PCCP NEW RIZAL 12:00 PM 5:00 PM 1 BATCH 3 BATCH IN TOTAL

7 TM-19 PALMARES POURING PCCP NEW RIZAL 12:00 PM 5:00 PM 1 BATCH 3 BATCH IN TOTAL

8 TM-21 PLAZA POURING PCCP NEW RIZAL 12:00 PM 5:00 PM 2 BATCH IN TOTAL

9 TM-20 MALLO POURING CONCRETE BARRIER CALUNASAN 12:00 PM 5:00 PM 2 BATCH 3 BATCH IN TOTAL; 6 CBM IN LAST BATCH

10 TM-20 MALLO POURING SIDEWALK CALUNASAN 12:00 PM 5:00 PM 1 BATCH IN TOTAL

11 TM-8 ELONDO POURING LINE CANAL ANTIPAS 12:00 PM 5:00 PM 1 BATCH 2 BATCH IN TOTAL

12 TM-8 ELONDO POURING PAVED SHOULDER ANTIPAS 12:00 PM 5:00 PM 1 BATCH

13 TM-8 ELONDO POURING LEAN CONCRETE ANTIPAS 12:00 PM 5:00 PM 1 BATCH

14 TM-9 SALMORIN POURING SLOPE PROTECTION LINANGKOB BR 12:00 PM 5:00 PM 2 BATCH 4 BATCH IN TOTAL (4.5CBM IN TOTAL)

15 TH-2 TACDORO MOBILIZED EQUIPMENT PANGAO-AN 12:00 PM 5:00 PM PULL OUT GD-05

16 TH-4 AMILDA TRANSPORT CONCRETE PILES KABACAN BR 12:00 PM 5:00 PM ONGOING

17 TH-5 MAMBURAM TRANSPORT CONCRETE PILES KABACAN BR 12:00 PM 5:00 PM ONGOING

18 TH-6 MARIPOSQUE PICK UP BITUMEN PANABO 12:00 PM 5:00 PM WAITING FOR LOADING

19 TH-8 YURAG PICK UP DIESEL GENSAN 12:00 PM 5:00 PM WAITING FOR LOADING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
]\'
Equipment Dispatching Schedule(March 3, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF SLOPE PROTECTION KABACAN FC 7:30 AM 11:30 AM NO UPDATE

2 TM-11 AQUINO POURING OF RUBBLE CONCRETE INAS FC 7:30 AM 11:30 AM 2 BATCH

3 TM-12 PALMA POURING PCCP PINGUIAMAN BR. 7:30 AM 11:30 AM 2 BATCH

4 TM-16 ABATAYO POURING STRUCTURAL CLASS B MATALAM OVERPASS 7:30 AM 11:30 AM 1 BATCH

5 TM-19 PALMARES POURING CURB AND GUTTER BUAYAN 7:30 AM 11:30 AM 2 BATCH

6 TM-9 SALMORIN POURING STRUCTURAL CLASS A STA FE. BR. 7:30 AM 11:30 AM NO UPDATE

7 TH-2 DARAUG MOBILIZED EQUIPMENT LINANGKOB BR 7:30 AM 11:30 AM PULL OUT BH-19

8 TH-3 NAVARRO PICK UP BITUMEN PANABO 7:30 AM 11:30 AM ON TRAVEL

9 TH-4 AMILDA PICK UP CEMENT DARONG 7:30 AM 11:30 AM WAITING FOR LOADING

10 TH-6 MARIPOSQUE UNLOAD BITUMEN JIP 7:30 AM 11:30 AM ONGOING

11 TH-8 YURAG UNLOAD DIESEL JIP 7:30 AM 11:30 AM TANK 3- 14K L THERMAL
HEATING - 1OK L

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
]\'
Equipment Dispatching Schedule(March 4, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF SLOPE PROTECTION KABACAN FC 7:30 AM 11:30 AM NO UPDATE

2 TM-11 AQUINO POURING OF RUBBLE CONCRETE INAS FC 7:30 AM 11:30 AM 2 BATCH

3 TM-12 PALMA POURING PCCP PINGUIAMAN BR. 7:30 AM 11:30 AM 2 BATCH

4 TM-16 ABATAYO POURING STRUCTURAL CLASS B MATALAM OVERPASS 7:30 AM 11:30 AM 1 BATCH

5 TM-19 PALMARES POURING CURB AND GUTTER BUAYAN 7:30 AM 11:30 AM 2 BATCH

6 TM-9 SALMORIN POURING STRUCTURAL CLASS A STA FE. BR. 7:30 AM 11:30 AM NO UPDATE

7 TH-2 DARAUG MOBILIZED EQUIPMENT LINANGKOB BR 7:30 AM 11:30 AM PULL OUT BH-19

8 TH-3 NAVARRO PICK UP BITUMEN PANABO 7:30 AM 11:30 AM ON TRAVEL

9 TH-4 AMILDA PICK UP CEMENT DARONG 7:30 AM 11:30 AM WAITING FOR LOADING

10 TH-6 MARIPOSQUE UNLOAD BITUMEN JIP 7:30 AM 11:30 AM ONGOING

11 TH-8 YURAG UNLOAD DIESEL JIP 7:30 AM 11:30 AM TANK 3- 14K L THERMAL
HEATING - 1OK L

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
]\'
Equipment Dispatching Schedule(March 4, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING OF SLOPE PROTECTION KABACAN FC 7:30 AM 11:30 AM JO; AROUND 10:00 AM NAKAGAWAS SA GATE

2 TM-8 ELONDO POURING PCCP PANGAO-AN 7:30 AM 11:30 AM 1 BATCH


AS OF 10:15 AM
3 TM-11 AQUINO POURING PCCP PANGAO-AN 7:30 AM 11:30 AM 1 BATCH

4 TM-9 SALMORIN POURING LINE CANAL ANTIPAS 7:30 AM 11:30 AM 1 BATCH

5 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. 7:30 AM 11:30 AM WAITING DELIVERY OF CEMENT

6 TM-16 ABATAYO POURING RUBBLE CONCRETE INAS FC 7:30 AM 11:30 AM 2 BATCH

7 TM-19 PALMARES POURING PAVED SHOULDER NEW RIZAL 7:30 AM 11:30 AM 2 BATCH

8 TM-20 MALLO POURING LINE CANAL NEW RIZAL 7:30 AM 11:30 AM 1 BATCH

9 TH-2 DARAUG MOBILIZED EQUIPMENT PANGAO-AN 7:30 AM 11:30 AM TRANSPORT BH-07 FROM MANOBISA QUARRY TO
PANGAO-AN

10 TH-3 NAVARRO UNLOAD BITUMEN JIP 7:30 AM 11:30 AM ONGOING

11 TH-4 BAJADOR TRANSPORT CEMENT PINGUIAMAN BR. 7:30 AM 11:30 AM ON TRAVEL

12 TH-6 MARIPOSQUE UNLOAD CONTAINER VAN LIBOO 7:30 AM 11:30 AM AFTER UNLOAD; JO

13 TH-6 MARIPOSQUE DELIVER CEMENT AND MATERIALS FROM LIBOO BANGKAL 7:30 AM 11:30 AM LOADING

14 TH-8 YURAG PICK UP BULK CEMENT DARONG 7:30 AM 11:30 AM LOADING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
]\'
Equipment Dispatching Schedule(March 6, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-8 ELONDO POURING OF FOOTING ABUTMENT A & LEAN STA. FE 11:30 AM 5:00 PM
CONCRETE
8 BATCH DONE IN TOTAL
2 TM-11 AQUINO POURING OF FOOTING ABUTMENT A & LEAN STA. FE 11:30 AM 5:00 PM
CONCRETE

3 TM-9 SALMORIN POURING PCCP ANTIPAS 11:30 AM 5:00 PM 4 BATCH 5 BATCH AS OF 4:30 PM

4 TM-9 SALMORIN POURING LINE CANAL ANTIPAS 11:30 AM 5:00 PM 2 BATCH IN TOTAL AS OF 4:30 PM

5 TM-12 PALMA POURING PCCP PINGUIAMAN BR. 11:30 AM 5:00 PM 1 BATCH 4 BATCH IN TOTAL; WASHING UNIT

6 TH-2 DARAUG PICK UP BULK CEMENT DARONG 11:30 AM 5:00 PM AROUND 4:15 PM, TRAVEL TO JIP TO PICK UP BULK
CARRIER

7 TH-3 NAVARRO PICK UP SMC DARONG 11:30 AM 5:00 PM WAITING FOR LOADING

8 TH-4 BAJADOR TRANSPORT CEMENT BANGKAL 11:30 AM 5:00 PM PICK UP MATERIALS

9 TH-5 MAMBURAM MOBILIZED EQUIPMENT PANGAO-AN 11:30 AM 5:00 PM TRANSPORT GD-05; DONE

10 TH-5 MAMBURAM PICK UP BULK CEMENT DARONG 11:30 AM 5:00 PM AROUND 4:30 PM, TRAVEL TO JIP TO PICK UP BULK
CARRIER

11 TH-6 MARIPOSQUE MOBILIZED EQUIPMENT LABO 11:30 AM 5:00 PM TRANSPORT BH-02; DONE

12 TH-7 AMILDA PICK UP MATERIALS DAVAO 11:30 AM 5:00 PM PICK UP COLOROOF

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
]\'
Equipment Dispatching Schedule(March 7, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-8 ELONDO POURING RUBBLE CONCRETE INAS FC 11:30 AM 4:30 PM 2 BATCH 3 BATCH IN TOTAL

2 TM-11 AQUINO POURING RUBBLE CONCRETE INAS FC 11:30 AM 4:30 PM 2 BATCH 4 BATCH IN TOTAL

3 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 11:30 AM 4:30 PM 1 BATCH 2 BATCH IN TOTAL AS OF 4:30 PM

4 TM-16 ABATAYO POURING PCCP NEW RIZAL 11:30 AM 4:30 PM 2 BATCH 4 BATCH IN TOTAL

5 TM-19 PALMARES POURING LINE CANAL NEW RIZAL 11:30 AM 4:30 PM 1 BATCH IN TOTAL

6 TM-19 PALMARES POURING PCCP NEW RIZAL 11:30 AM 4:30 PM 2 BATCH 3 B ATCH IN TOTAL

7 TM-20 MALLO POURING PCCP NEW RIZAL 11:30 AM 4:30 PM 2 BATCH 4 BATCH IN TOTAL

8 TH-2 DARAUG MOBILIZED EQUIPMENT NEW RIZAL 11:30 AM 4:30 PM TRANSPORT BH-14; DONE

9 TH-2 DARAUG MOBILIZED EQUIPMENT ANTIPAS 11:30 AM 4:30 PM PULL OUT BH-29 WITH BREAKER; DONE

TH-2 DARAUG PICK UP BULK CEMENT DARONG 11:30 AM 4:30 PM AROUND 4:30 PM PICK UP BULK TRUCK AT JIP

10 TH-3 NAVARRO PICK UP SMC DARONG 11:30 AM 4:30 PM AROUND 4:00 PM, NAABOT ANG RESCUE

11 TH-4 BAJADOR UNLOAD MATERIALS LIBOO 11:30 AM 4:30 PM DONE

TH-4 BAJADOR PICK UP SMC DARONG 11:30 AM 4:30 PM AROUND 2:00 PM, DEPARTURE

12 TH-5 MAMBURAM PICK UP SMC DARONG 11:30 AM 4:30 PM AROUND 1:00 PM ARRIVAL, WAITING FOR LOADING

13 TH-6 MARIPOSQUE PICK UP BITUMEN PANABO 11:30 AM 4:30 PM WAITING FOR LOADING

14 TH-7 AMILDA UNLOAD MATERIALS LIBOO 11:30 AM 4:30 PM ONGOING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
]\'
Equipment Dispatching Schedule(March 8, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-9 SALMORIN POURING RETAINING WALL STA. FE 7:30 AM 1:00 PM 1 BATCH ONGOIN G

2 TM-4 RAPISTA POURING PAVED SHOULDER ANTIPAS 7:30 AM 1:00 PM 1 BATCH

3 TM-4 RAPISTA POURING PCCP ANTIPAS 7:30 AM 1:00 PM 1 BATCH

4 TM-8 ELONDO POURING LINE CANAL ANTIPAS 7:30 AM 1:00 PM 1 BATCH

5 TM-11 AQUINO POURING PCCP ANTIPAS 7:30 AM 1:00 PM 2 BATCH

6 TM-11 AQUINO POURING LINE CANAL ANTIPAS 7:30 AM 1:00 PM 1 BATCH

7 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 7:30 AM 1:00 PM 1 BATCH

8 TM-16 ABATAYO POURING PAVED SHOULDER NEW RIZAL 7:30 AM 1:00 PM 1 BATCH

9 TM-16 ABATAYO POURING LINE CANAL NEW RIZAL 7:30 AM 1:00 PM 1 BATCH

10 TM-19 PALMARES POURING PAVED SHOULDER NEW RIZAL 7:30 AM 1:00 PM 3 BATCH

11 TM-20 MALLO POURING RUBBLE CONCRETE INAS FC 7:30 AM 1:00 PM 3 BATCH

12 TH-2 DARAUG MOBILIZED EQUIPMENT JIP 7:30 AM 1:00 PM TRANSPORT BH-29; DONE

ANTIPAS - MATALAM TRANSPORT BH-28; ON TRAVEL TO MATALAM


13 TH-2 DARAUG MOBILIZED EQUIPMENT OVERPASS - LABO 7:30 AM 1:00 PM
OVERPASS

14 TH-3 NAVARRO UNLOAD CEMENT BIAO 7:30 AM 1:00 PM DONE

15 TH-3 NAVARRO PICK UP SMC DARONG 7:30 AM 1:00 PM ON TRAVEL FROM BIAO

16 TH-4 BAJADOR UNLOAD CEMENT LIBOO 7:30 AM 1:00 PM DONE

18 TH-5 MAMBURAM UNLOAD CEMENT LIBOO 7:30 AM 1:00 PM DONE

19 TH-6 MARIPOSQUE UNLOAD BITUMEN JIP 7:30 AM 1:00 PM ONGOING

20 TH-7 AMILDA UNLOAD MATERIALS LIBOO 7:30 AM 1:00 PM ONGOING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 8, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

POURING RETAINING WALL STA. FE 1:00 PM AROUND 1:50 PM, NAHUMAN BUHOS

1 TM-9 SALMORIN TRAVEL TO ANTIPAS ANTIPAS 2:14 PM 3:27 PM

POURING RETAINING WALL ANTIPAS 4:16 PM 1 BATCH

POURING PAVED SHOULDER ANTIPAS 1:00 PM 5:00 PM 1 BATCH

2 TM-4 RAPISTA 1:03 PM 2:03 PM 1ST BATCH 1 BATCH


POURING PCCP ANTIPAS
2:12 PM 3:12 PM 2ND BATCH

1:00 PM 2:20 PM 1ST BATCH 1 BATCH


4 TM-8 ELONDO POURING LINE CANAL ANTIPAS
3:58 PM 2ND BATCH

POURING PCCP ANTIPAS 1:00 PM 1 BATCH 2 BATCH

5 TM-11 AQUINO POURING LINE CANAL ANTIPAS 1:00 PM 1 BATCH

POURING RETAINING WALL ANTIPAS 3:00 PM 1 BATCH

6 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 1:00 PM 5:00 PM 1 BATCH FOR THE WHOLE DAY 1 BATCH

POURING PAVED SHOULDER NEW RIZAL 1:00 PM 1 BATCH FOR THE WHOLE DAY 1 BATCH
7 TM-16 ABATAYO
POURING LINE CANAL NEW RIZAL 1:07 PM 4:13 PM 1ST BATCH 2 BATCH FOR THE WHOLEDAY 1 BATCH

8 TM-19 PALMARES POURING PAVED SHOULDER NEW RIZAL 12:48 PM 2:55 PM 1 BATCH 3 BATCH FOR THE WHOLEDAY 3 BATCH

1:49 PM 3:27 PM 1ST BATCH 3 BATCH


9 TM-20 MALLO POURING RUBBLE CONCRETE INAS FC 5 BATCH IN TOTAL
3:31 PM 2ND BATCH

10 JIP 1:00 PM 5:00 PM TRANSPORT BH-29; DONE


MOBILIZED EQUIPMENT
ANTIPAS - MATALAM
11 TH-2 DARAUG OVERPASS - LABO 1:00 PM 5:00 PM TRANSPORT BH-28;DONE

PICK UP BULK CEMENT DARONG 5:00 PM

12 TH-3 NAVARRO UNLOAD CEMENT BIAO 1:00 PM 5:00 PM DONE

13 TH-3 NAVARRO PICK UP SMC DARONG 1:00 PM 5:00 PM ON TRAVEL FROM BIAO

14 TH-4 BAJADOR UNLOAD CEMENT LIBOO 1:00 PM 5:00 PM DONE

15 TH-5 MAMBURAM UNLOAD CEMENT LIBOO 1:00 PM 5:00 PM DONE

16 TH-6 MARIPOSQUE UNLOAD BITUMEN JIP 1:00 PM 5:00 PM ONGOING

17 TH-7 AMILDA UNLOAD MATERIALS LIBOO 1:00 PM 5:00 PM ONGOING

Prepared by : XAVIER MACALDO/MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 9, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING SLOPE PROTECTION KABACAN FC 8:30 AM WAITING FOR UPDATE FROM P.I.

2 TM-8 ELONDO POURING OF LINE CANAL ANTIPAS 9:14 AM 11:17 AM 2ND BATCH 2 BATCH

3 POURING OF PAVE SHOULDER ANTIPAS 10:44 AM 1ST BATCH 2 BATCH

4 TM-9 SALMORIN POURING OF PCCP ANTIPAS 8:30 AM 9:30 AM 1ST BATCH

5 POURING OF PCCP ANTIPAS 9:30 AM 10:44 AM 3RD BATCH 3 BATCHES

6 POURING OF PCCP ANTIPAS 8:50 AM 10:06 AM 2ND BATCH

7 TM-11 AQUINO POURING OF LEAN CONCRETE ANTIPAS 10:06 AM 11:38 AM 1ST BATCH 1 BATCH

8 POURING OF PAVE SHOULDER ANTIPAS 11:38 AM 1:00 PM 2ND BATCH 2 BATCH

9 TM-12 PALMA POURING SLOPE PROTECTION PINGUIAMAN BR. 7:30 AM 1:00 PM WAITING UPDATE

10 TM-16 ABATAYO POURING OF SIDEWALK SBC 9:09 AM 1ST BATCH 1 BATCH

11 TM-19 PALMARES POURING CONCRETE BARRIER CALUNASAN 8:00 AM 11:03 AM 3RD BATCH 3 BATCHES

12 TM-20 MALLO POURING LINE CANAL CALUNASAN 8:38 AM 9:58 AM 2ND BATCH 2 BATCHES

13 TH-2 DARAUG MOBILIZED EQUIPMENT CALUNASAN 9:52 AM TRANSPORT BH 28 FROM LABO - ON TRAVEL

14 UNLOAD CEMENT LIBOO COMP. 7:30 AM 8:30 AM DONE


TH-3 NAVARRO
15 LOAD WAREHOUSE MATERIALS BANGKAL 8:30 AM 1:00 PM ON GOING

16 TH-4 BAJADOR MOBILIZED EQUIPMENT SARANGGANI 7:30 AM 1:00 PM ON TRAVEL

17 TH-5 MAMBURAM PICK UP RCPC BANGKAL 7:30 AM 1:00 PM LOADING

18 UNLOAD SMC CEMENT LIBOO COMP. 7:30 AM 9:00 AM ON TRAVEL


TH-6 MARIPOSQUE
19 PICK UP HOLCIM AT 3M1 SUPPLY KIDAPAWAN 9:00 AM 1:00 PM ON TRAVEL

20 TH-7 AMILDA MOBILIZED EQUIPMENT DAVAO 7:30 AM 1:00 PM ON TRAVEL

21 TH-8 AMILDA UNLOAD BITUMEN JIP 7:30 AM 1:00 PM ON GOIG UNLOAD

Prepared by : XAVIER MACALDO / MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 9, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING SLOPE PROTECTION KABACAN FC WAITING FOR UPDATE FROM P.I.

2 TM-8 ELONDO POURING OF LINE CANAL ANTIPAS 2:23 PM 4:00 PM 1 BATCH 3 BATCH AS OF 4:00 PM

3 POURING OF PAVE SHOULDER ANTIPAS 12:41 PM 1:35 PM 1 BATCH


3 BATCH AS OF 4 PM
4 TM-9 SALMORIN POURING OF PAVE SHOULDER ANTIPAS 1:40 PM 2:45 PM 2ND BATCH

5 POURING OF PCCP ANTIPAS 2 BATCH AS OF 4 PM

6 POURING OF PCCP ANTIPAS 1 BATCH AS OF 4PM

7 POURING OF LEAN CONCRETE ANTIPAS 1 BATCH AS OF 4PM


TM-11 AQUINO
8 POURING OF PAVE SHOULDER ANTIPAS 1:10 PM 2:13 PM 1ST BATCH
3 BATCH AS OF 4 PM
9 POURING OF PAVE SHOULDER ANTIPAS 2:49 PM 3:48 PM 2ND BATCH

10 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. STANDBY

11 TM-16 ABATAYO POURING OF SIDEWALK SBC 12:46 PM 3:28 PM 2ND BATCH 2 BATCH FOR THE WHOLE DAY

12 BUAYAN 12:25 PM 2:10 PM 1ST BATCH


TM-19 PALMARES POURING MANHOLE 2 BATCH FOR THE WHOLE DAY
13 BUAYAN 2:19 PM 4:07 PM 2ND BATCH

14 TM-19 PALMARES POURING CONCRETE BARRIER CALUNASAN 10:50 AM 12:00 PM 1 BATCH 3 BATCHES FOR THE WHOLEDAY

15 TM-20 MALLO POURING LINE CANAL CALUNASAN 2 BATCHES FOR THE WHOLEDAY

16 TH-2 DARAUG MOBILIZED EQUIPMENT CALUNASAN TRANSPORT BH 28 FROM LABO ; DONE

17 TH-2 DARAUG MOBILIZED EQUIPMENT LIBOO COMP. 1:00 PM 5:00 PM WAITING FOR DISPATCH

18 UNLOAD CEMENT LIBOO COMP. DONE


TH-3 NAVARRO
19 LOAD WAREHOUSE MATERIALS BANGKAL 1:00 PM 5:00 PM DONE

20 TH-3 NAVARRO PICK UP MATERIALS BANGKAL 1:00 PM 5:00 PM ON TRAVEL

21 TH-4 BAJADOR MOBILIZED EQUIPMENT SARANGGANI 1:00 PM 5:00 PM ON TRAVEL

22 TH-5 MAMBURAM PICK UP RCPC BANGKAL 1:00 PM 5:00 PM LOADING

23 UNLOAD SMC CEMENT LIBOO COMP. 1:00 PM 5:00 PM ON TRAVEL


TH-6 MARIPOSQUE
24 PICK UP HOLCIM AT 3M1 SUPPLY KIDAPAWAN 1:00 PM 2:00 PM DONE

25 TH-6 MARIPOSQUE PICK UP SMC DARONG 2:00 PM 5:00 PM ON TRAVEL

26 TH-7 AMILDA MOBILIZED EQUIPMENT DAVAO 1:00 PM 5:00 PM ON TRAVEL

27 TH-8 AMILDA UNLOAD BITUMEN JIP 1:00 PM 5:00 PM DONE

Prepared by : XAVIER MACALDO / MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 10, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING SLOPE PROTECTION KABACAN FC WAITING UPDATE

2 TM-8 ELONDO POURING OF PCCP PANGAO-AN 6:00 AM WAITING UPDATE

3 TM-9 SALMORIN POURING OF PCCP PANGAO-AN WAITING UPDATE

4 TM-10 POURING COPPING STA. FE WAITING UPDATE

5 TM-11 AQUINO POURING OF PCCP PANGAO-AN 7:30 AM WAITING UPDATE

6 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. WAITING UPDATE

7 TH-2 DARAUG MOBILIZED EQUIPMENT LIBOO COMP. WAITING DISPATCH

8 TH-3 NAVARRO PICK UP MATERIALS BANGKAL 1:00 PM 5:00 PM ON TRAVEL

9 TH-4 BAJADOR MOBILIZED EQUIPMENT SARANGGANI 7:30 AM ON TRAVEL

10 TH-5 MAMBURAM UNLOAD PHENOLIC LIBOO COMP. 7:30 AM 9:00 AM LOADING

10 TH-5 MAMBURAM DELIVER RCPC NEW RIZAL 9:00 AM LOADING

11 TH-6 MARIPOSQUE UNLOAD SMC CEMENT LIBOO COMP. 7:30 AM ON TRAVEL

12 TH-7 AMILDA PICK UP HOLCIM KIDAPAWAN 10:00 AM ON TRAVEL

13 TH-8 YURAG UNLOAD SMC CEMENT BANGKAL 9:00 AM ON GOING

Prepared by : XAVIER MACALDO / MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 11, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING SLOPE PROTECTION KABACAN FC 6:00 AM 12:00 PM WAITING UPDATE

2 9:05 AM 11:04 AM 1ST BATCH


TM-7 CAMANAY POURING PCCP NEW RIZAL
3 11:05 AM 12:55 PM 2ND BATCH

4 TM-8 ELONDO POURING OF GIRDER KABACAN BR. 7:30 AM 12:00 PM WAITING UPDATE

5 10:35 AM 12:10 PM 1ST BATCH


TM-9 SALMORIN POURING LINE CANAL ANTIPAS
6 12:53 PM 2ND BATCH

7 TM-11 AQUINO POURING OF GIRDER KABACAN BR. 7:30 AM 12:00 PM WAITING UPDATE

8 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. 7:30 AM 12:00 PM STANDBY

9 POURING PCCP 6:57 AM 8:38 AM 1 ST BATCH

10 TM-16 ABATAYO NEW RIZAL 9:27 AM 11:52 AM 1ST BATCH


POURING LINE CANAL
11 12:32 PM 2ND BATCH

12 7:30 AM 9:05 AM 1ST BATCH

13 TM-19 PALMARES POURING PCCP NEW RIZAL 10:10 AM 11:45 AM 2ND BATCH

14 12:10 PM 3RD BATCH

15 7:16 AM 8:39 AM 1ST BATCH

16 TM-20 MALLO POURING OF RUBBLE CONCRETE INAS FC 9:56 AM 11:26 AM 2ND BATCH

17 11:32 AM 1:11 PM 3RD BATCH

18 7:26 AM 10:37 AM 1ST BATCH


TM-21 PLAZA POURING OF RUBBLE CONCRETE INAS FC
19 10:39 AM 12:16 PM 2ND BATCH

20 TH-2 DARAUG TRANSPORT BULK CEMENT LIBOO COMP. 7:30 AM 8:48 AM DONE
ON GOING PICK UP; WAITING FOR LOADING
21 TH-3 NAVARRO PICK UP MATERIALS DAVAO 6:27 AM 12:00 PM
DRB
22 TH-4 BAJADOR UNLOAD CEMENT LIBOO COMP. 7:30 AM 9:00 AM DONE

23 TH-4 BAJADOR PICK UP RCPC BANGKAL 9:00 AM 12:00 PM ON TRAVEL; WAIITNG FOR UPDATE

DONE; ONGOING JO OF CLEARANCE


24 LIBOO COMP. 7:30 AM 11:00 AM
LIGHT(BLACKOUT)
TH-5 MAMBURAM UNLOAD CEMENT
25 BANGKAL 11:00 AM 12:00 PM ON TRAVEL
26 TH-6 MARIPOSQUE UNLOAD SMC CEMENT LIBOO COMP. 7:30 AM 12:00 PM ONGOING; ONLEAVE DRIVER

27 TH-7 AMILDA UNLOAD CEMENT LIBOO COMP. 7:30 AM 10:00 AM DONE

28 TH-7 AMILDA PICK UP RCPC BANGKAL 10:07 AM 12:00 PM ON TRAVEL; WAIITNG FOR UPDATE

29 TH-8 YURAG UNLOAD CEMENT LIBOO COMP. 7:30 AM 8:30 AM DONE

30 TH-8 YURAG PICK UP DIESEL GENSAN 8:30 AM 12:00 PM ON TRAVEL; WAIITNG FOR UPDATE

Prepared by : XAVIER MACALDO / MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 11, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING SLOPE PROTECTION KABACAN FC 6:30 AM 1:23 PM 1 BATCH 1 BATCH FOR THE WHOLE DAY

2 TM-7 CAMANAY POURING PCCP NEW RIZAL 1:07 PM 5:00 PM 3RD BATCH 3 BATCHES FOR THE WHOLE DAY

4 TM-8 ELONDO POURING OF GIRDER KABACAN BR. 1:00 PM 4:00 PM 2 BATCH 4 BATCH FOR THE WHOLEDAY

5 12:53 PM 3:11 PM 2ND BATCH 3 BATCHES FOR THE WHOLE DAY


TM-9 SALMORIN POURING LINE CANAL ANTIPAS
6 3:25 PM 5:00 PM 3RD BATCH 1 BATCH FOR THE WHOLE DAY

7 TM-11 AQUINO POURING OF GIRDER KABACAN BR. 1:00 PM 4:00 PM 3 BATCHES FOR THE WHOLE DAY

8 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. 12:00 PM 4:00 PM STANDBY

9 POURING PCCP 1:00 AM 3:18 PM 1 BATCH FOR THE WHOLE DAY


TM-16 ABATAYO NEW RIZAL
10 POURING LINE CANAL 3:18 PM 5:00 PM 3RD BATCH 3 BATCHES FOR THE WHOLE DAY

12 TM-19 PALMARES POURING PCCP NEW RIZAL 1:55 PM 5:00 PM 4TH BATCH 4 BATCHES FOR THE WHOLE DAY

15 1:23 PM 2:53 PM 4TH BATCH


TM-20 MALLO POURING OF RUBBLE CONCRETE INAS FC 5 B ATCHES FOR THE WHOLE DAY
16 2:53 PM 5:00 PM 5TH BATCH

18 12:46 PM 2:21 PM 3RD BATCH

19 TM-21 PLAZA POURING OF RUBBLE CONCRETE INAS FC 2:21 PM 4:24 PM 4TH BATCH 5 BATCHES FOR THE WHOLE DAY

4:24 PM 5:00 PM 5TH BATCH


ON GOING PICK UP; WAITING FOR LOADING
21 TH-3 NAVARRO PICK UP MATERIALS DAVAO 12:00 PM 12:00 PM
DRB
23 TH-4 BAJADOR PICK UP RCPC BANGKAL 12:00 PM 5:00 PM WAITING FOR LOADING

25 TH-5 MAMBURAM PICK UP RCPC BANGKAL 12:00 PM 5:00 PM WAITING FOR LOADING
26 TIBAO - BAGONTAPAY 2:50 PM 4:00 PM DONE TRANSPORT BH-28
TH-6 DARAUG MOBILIZED EQUIPMENT
26 JIP - LIBOO 4:00 PM 5:00 PM DONE TRANSPORT BH-29

28 TH-7 AMILDA PICK UP RCPC BANGKAL 10:07 AM 12:00 PM WAITING FOR LOADING

30 TH-8 YURAG PICK UP DIESEL GENSAN 12:00 PM 5:00 PM WAITING FOR LOADING

Prepared by : XAVIER MACALDO / MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(March 13, 2023)
Item Unit Driver/Operator Activities Project Location Time Started Time End Output Remarks

1 TM-4 RAPISTA POURING SLOPE PROTECTION KABACAN FC WAITING FOR UPDATE

2 8:45 AM 10:03 AM 1ST BATCH


TM-9 SALMORIN POURING RETAINING WALL ANTIPAS
10:35 AM 12:01 PM 2ND BATCH

3 7:35 AM 8:54 AM 1ST BATCH


POURING CON CRETE BARRIER CALUNASAN
4 TM-19 PALMARES 8:56 AM 10:18 AM 2ND BATCH

5 POURING LINE CANAL CALUNASAN 10:22 AM 11:29 AM 1ST BATCH

6 7:53 AM 9:10 AM 1ST BATCH

7 TM-20 MALLO POURING OF GROUTED RIPRAP TIBAO 9:14 AM 10:36 AM 2ND BATCH

8 10:42 AM 12:11 PM 3rd BATCH

9 8:09 AM 8:57 AM 1ST BATCH


POURING PAVED SHOULDER CALUNASAN
10 TM-16 ABATAYO 9:41 AM 11:26 AM 2ND BATCH

11 POURING PCCP TIBAO 11:43 AM 1ST BATCH ONGOING

12 9:10 AM 11:43 AM 1ST BATCH


TM-11 AQUINO POURING OF GIRDER NIA BR.
13 11:47 AM 1:00 PM 2ND BATCH

14 10:12 AM 11:25 AM 1ST BATCH


TM-7 CAMANAY POURING GIRDER NIA BR.
15 12:33 AM 2ND BATCH ONGOING

16 TM-8 ELONDO POURING OF COLUMN STA. FE 11:00 AM 1ST BATCH ONGOING

17 TM-12 PALMA NO POURING ACTIVITY PINGUIAMAN BR. STANDBY


18 TH-3 NAVARRO UNLOAD MATERIALS LIBOO 7:30 AM 11:30 AM DONE

19 UNLOAD RCPC NEW RIZAL 8:58 AM 10:30 AM DONE


TH-4 BAJADOR
20 PICK UP MATERIALS BANGKAL 10:35 AM 1:00 PM ON TRAVEL

21 TH-5 TACDORO UNLOAD RCPC BANGKAL 8:42 AM 1:09 PM DONE

22 LIBOO - JIP 9:02 AM 9:33 AM DONE TRANSPORT BH-29


TH-6 MARIPOSQUE MOBILIZED EQUIPMENT
KIDAPAWAN - SANGAT -
23 9:34 AM 12:06 PM DONE TRANSPORT WHEELTYPE BH; DONE
LIBOO
24 TH-7 AMILDA UNLOAD RCPC NEW RIZAL 10:11 PM 11:43 AM DONE

25 TH-8 YURAG UNLOAD DIESEL LIBOO - JIP 7:30 AM 12:00 PM DONE

Prepared by : XAVIER MACALDO / MAYLYN A. TABUGOC


Equipment In-Charge
Equipment Dispatching Schedule(June 13, 2023)
Driver/ Project Time
Item Unit Activities Time End Output Remarks
Operator Location Started
1 TM-11 PALMARES POURING LINE CANAL ANTIPAS 1:00 PM 5:00 PM 1 batch 2 batch done wholeday

1st batch
1:15 PM 2:13 PM
2 TM-5 AQUINO POURING RETAINING WALL STA FE 2nd batch 3 batch done wholeday(18m3); 3rd batch ongoing
2:18 PM 3:25 PM
3rd batch
3:30 PM
3 TM-16 ABATAYO POURING LINE CANAL PANGAO-AN 1:00 PM 5:00 PM 5 BATCHES DONE

4 TM-18 ELONDO POURING PCCP PANGAO-AN 1:00 PM 5:00 PM 6 BATCHES DONE 17 BATCHES DONE WHOLEDAY

5 TM-21 PALMA POURING LINE CANAL PANGAO-AN 1:00 PM 5:00 PM 6 BATCHES DONE

POURING COLUMN TIE 2 batch done wholeday


BEAM
6 TM-20 MALLO JIP 1:00 PM 5:00 PM
POURING FLOORING ongoing

POURING SLOPE 1 BATCH DONE WHOLEDAY; NAGPAJO KAY


7 TM-4 RAPISTA MARBOL FC 1:00 PM 5:00 PM
PROTECTION NAIGO SA BH ANG TAMBUBO
UNLOAD MATERIALS
LIBOO DONE
DARAUG/ (SHEETPILE)
8 TH-2 1:00 PM 5:00 PM
NERI
MOBILIZED EQUIPMENT ILOMAVIS TRANSPORT PL-04, PULL OUT DT-41
DEL CARMEN
9 TH-3 NAVARRO MOBILIZED EQUIPMENT 1:00 PM 5:00 PM PULL OUT BH-08
BR.

10 TH-4 BAJADOR PICK UP MEGGA CEMENT DAVAO 1:00 PM 5:00 PM ONGOING

TACDORO/
11 TH-5 GALLEGO PICK UP BITUMEN DAVAO 1:00 PM 5:00 PM ONGOING

MARIPOSQUE/
12 TH-6 LAZARITO PICK UP SHEETPILE DAVAO 1:00 PM 5:00 PM ONGOING

RETURN CONTAINER VAN,


13 TH-7 AMILDA DAVAO 1:00 PM 5:00 PM ONGOING
PICK UP MEGGA CEMENT

14 TH-8 YURAG UNLOAD DIESEL JIP 1:00 PM 5:00 PM done

Prepared TRISTAN AARON CAPOL


by : ENGR. MAYLYN A. TABUGOC Received By:
EMS HEAD
Equipment In-Charge
Equipment Dispatching Schedule(June 13, 2023)
Driver/ Project Time
Item Unit Activities Time End Output Remarks
Operator Location Started
1 TM-11 PALMARES POURING LINE CANAL ANTIPAS 7:30am 5:00 PM 1 batch 2 batch done wholeday

2 TM-5 AQUINO POURING RETAINING WALL STA FE 7:30am 5:00 PM 1st batch 3 batch done wholeday(18m3); 3rd batch ongoing

3 TM-16 ABATAYO POURING LINE CANAL PANGAO-AN 7:30am 5:00 PM 5 BATCHES DONE

4 TM-18 ELONDO POURING PCCP PANGAO-AN 7:30am 5:00 PM 6 BATCHES DONE 17 BATCHES DONE WHOLEDAY

5 TM-21 PALMA POURING LINE CANAL PANGAO-AN 7:30am 5:00 PM 6 BATCHES DONE

POURING COLUMN TIE


6 TM-20 MALLO JIP 7:30am 5:00 PM 2 batch done wholeday
BEAM
POURING SLOPE 1 BATCH DONE WHOLEDAY; NAGPAJO KAY
7 TM-4 RAPISTA MARBOL FC 7:30am 5:00 PM
PROTECTION NAIGO SA BH ANG TAMBUBO
UNLOAD MATERIALS
LIBOO DONE
(SHEETPILE)
8 TH-2 DARAUG/NERI 7:30am 5:00 PM
MOBILIZED EQUIPMENT ILOMAVIS TRANSPORT PL-04, PULL OUT DT-41

DEL CARMEN
9 TH-3 NAVARRO/DAPAN MOBILIZED EQUIPMENT 7:30am 5:00 PM PULL OUT BH-08
BR.

10 TH-4 BAJADOR PICK UP MEGGA CEMENT DAVAO 7:30am 5:00 PM ONGOING

TACDORO/
11 TH-5 GALLEGO PICK UP BITUMEN DAVAO 7:30am 5:00 PM ONGOING
MARIPOSQUE/
12 TH-6 LAZARITO PICK UP SHEETPILE DAVAO 7:30am 5:00 PM ONGOING

RETURN CONTAINER VAN,


13 TH-7 AMILDA DAVAO 7:30am 5:00 PM ONGOING
PICK UP MEGGA CEMENT

14 TH-8 YURAG UNLOAD DIESEL JIP 7:30am 5:00 PM done

Prepared TRISTAN AARON CAPOL


by : ENGR. MAYLYN A. TABUGOC Received By:
EMS HEAD
Equipment In-Charge