Professional Documents
Culture Documents
Draft Project On International Commercial Arbitration
Draft Project On International Commercial Arbitration
INDIA
By
AUSHIM KHULLAR
40/ADR/ILI/2017-18
This paper dissertation aims to summarize the position under Indian law
on international commercial arbitration (“ICA”), seated within and
outside India and discusses the recent judicial decisions in this field.
The changes introduced by the Amendment Act are a step in the right
direction towards ensuring an arbitration friendly nation, and have been
captured in this paper.
2. Indian Arbitration Regime
I. History of Arbitration in India
Until the Arbitration and Conciliation Act, 1996 (“Act”), the law governing
arbitration in India consisted mainly of three statutes:
The 1940 Act was the general law governing arbitration in India and
resembled the English Arbitration Act of 1934.
The Act was also aimed to provide a speedy and efficacious dispute
resolution mechanism in the existing judicial system which was marred
with inordinate delays and backlog of cases.
Part II of the Act deals only with foreign awards1 and enforcement under the
Convention on the Recognition and Enforcement of Foreign Arbitral Awards,
1958 (“New York Convention”) and Convention on the Execution of Foreign
Arbitral Awards, 1927 (“Geneva Convention”). Part III of the Act is a
statutory embodiment of conciliation provisions.
In Part I, Section 8 regulates the commencement of arbitration in India,
Sections 3, 4, 5, 6, 10 to 26, and 28 to 33 regulate the conduct of
arbitration, Section 34 regulates the challenge to the award and Sections 35
and 36 regulate the recognition and enforcement of the award. Sections 1, 2,
7, 9,27, 37 and 38 to 43 are ancillary provisions that either support the
arbitral process or are structurally necessary.
The courts have found that Chapters III to VI, specifically, Section 10 to 33
of Part 1 of the Act, contain curial or procedural law which parties would
have autonomy to opt out from. The other Chapters of Part I of the Act form
part of the proper law, thus making those provisions non-derogable by
parties subjected to Part I, even by contract.
Part II, on the other hand regulates arbitration only in respect to the
commencement and recognition / enforcement of a foreign award and no
provisions under the same can be derogated by a contract between two
parties.
The Amendment Act provides with strict timelines for completion of the
arbitral proceedings along with the scope for resolving disputes by a fast
track mechanism.
The Amendment Act has introduced insertion of new provisions in
addition to amendments to the existing provisions governing the process
of appointment of an arbitrator. It also clarified the grounds to challenge
an arbitrator for the lack of independence and impartiality. As a welcome
move, the Amendment Act provides for assistance from Indian courts, even
in foreign-seated arbitrations in the form of interim relief before the
commencement of the arbitration. Further, the introduction ‘cost follow
the event’ regime in the Act has been inserted to bring the Act in line with
inter- national standards. The process of enforcement and execution under
the Act has also been streamlined so that challenge petitions do not
operate as an automatic stay on the execution process.
A. Pre-arbitral proceedings
i. Expeditious disposal
ii. Costs
C. Post-arbitral proceedings
Upon filing a challenge, under Section 34 of the Act, there will not
be any automatic stay on the execution of award – and more
specifically, an order has to be passed by the court expressly staying
the execution proceedings.
3. International Commercial Arbitration –
Meaning
Section 2(1)(f) of the Act defines an ICA as a legal relationship which must be
considered commercial,5 where either of the parties is a foreign national or
res- ident or is a foreign body corporate or is a company, association or body
of individuals whose central management or control is in foreign hands.
Thus, under Indian law, an arbitration with a seat in India, but involving a
foreign party will also be regarded as an ICA, and hence subject to Part I of
the Act. Where an ICA is held outside India, Part I of the Act would have no
applicability on the parties (save the stand alone provisions introduced by
the Amendment Act unless excluded by the parties, as discussed later) but
the par- ties would be subject to Part II of the Act.
The Amendment Act has deleted the words ‘a company’ from the purview
of the definition thereby restricting the definition of ICA only to the body
of individuals or association. There- fore, by inference, it has been made
clear that if a company has its place of incorporation as India then
central management and control would be irrelevant as far as its
determination of being an “international commercial arbitration” is
concerned.
The scope of this section was determined by the Supreme Court in the
case of TDM Infrastructure Pvt. Ltd. v. UE Development India Pvt. Ltd.
wherein, despite TDM Infrastructure Pvt. Ltd. having a foreign control, it
was concluded that, “a company incorporated in India can only have
Indian nationality for the purpose of the Act.”
In Booz Allen and Hamilton Inc. v. SBI Home Finance Ltd. the Supreme Court
discussed the concept of arbitrability in detail and held that the term
‘arbitrability’ had different meanings in different contexts: (a) disputes
capable of being adjudicated through arbitration, (b) disputes covered by
the arbitration agreement, and (c) disputes that parties have referred to
arbitration. It stated that in principle, any dispute than can be decided by a
civil court can also be resolved through arbitration. However, certain
disputes may, by necessary implication, stand excluded from resolution by
a private forum. Such non-arbitrable disputes include:
(i) disputes relating to rights and liabilities which give rise to or arise
out of criminal offences;
(ii) matrimonial disputes relating to divorce, judicial separation,
restitution of conjugal rights, or child custody;
(iii) guardianship matters;
(iv) insolvency and winding up matters;
(v) testamentary matters (grant of probate, letters of administration
and succession certificate); and
(vi) eviction or tenancy matters governed by special statutes where the
tenant enjoys statutory protection against eviction and only the
specified courts are conferred jurisdiction to grant eviction or decide
the disputes.
However, in Vimal Shah & Ors. v Jayesh Shah & Ors, the Supreme Court
has held that disputes arising out of Trust Deeds and the Indian Trusts
Act, 1882 cannot be referred to arbitration.
I. Notice of arbitration
Arbitration is said to have commenced when the notice of arbitration
requires the other party to take steps in connection with the
arbitration or do something on his part in the matter of arbitration.
Under Section 21 of the Act, a notice of arbitration has to be served to
the other party, requesting that the dispute be referred to arbitration.
The day on which the respondent receives the notice, arbitral
proceedings commences under the Act. In a Notice of Arbitration, a party
communicates: a) an intention to refer the dispute to arbitration; and
b) the requirement that other party should do something on his part in
that regard. This will generally suffice to define the commencement of
arbitration under the Act.
More importantly, taking heed from the judgment of the Supreme Court in
Chloro Controls, which effectively applied only to foreign-seated arbitrations,
the definition of the word ‘party’ to an arbitration agreement has been
expanded under the Amendment Act to also include persons claiming
through or under such party.
A party may, before, or during arbitral proceedings or at any time after the
making of the Arbitral Award but before it is enforced, apply to a court for
seeking interim measures and protections including interim injunctions
under Section 9 of the Act.
b. Post the grant of interim protection under Section 9 of the Act, the
arbitral proceedings must commence within a period of 90 (ninety)
days from the date of the interim protection order or within such time
as the court may determine.
There has always been a concern in India with respect to the time taken
for appointment of arbitrators due to the existing jurisprudence and
procedure. The time-frame for such appointment was usually 12-18
months. This amendment seeks to address this delay by introducing a
timeline and clarifying the procedure of appointment to be an exercise of
administrative power by the courts.
However, in such cases, application for setting aside the arbitral award can
be made to the court under Section 34 of the Act. If the court agrees to the
challenge, the arbitral award can be set aside. Thus, even if the arbitrator
does not accept the challenge to his appointment, the other party cannot
stall further arbitration proceedings by rushing to the court.
The arbitration can continue and challenge can be made in court only after the
arbitral award is made.
VIII. Applicability of Amendment Act
The Amendment Act provides a form for disclosure in the new Fifth
Schedule. Such disclosure is in accordance with internationally
accepted practices to be made applicable for arbitration proceedings
commenced on or after October 23, 2015.
There is however, a decision of Punjab and Haryana High Court which has
held that there is no bar on a former employee to sit as an arbitrator in a
dispute. This is an indicative list in addition to disqualifying situations that
have been affirmed by case law such as the holding of the Supreme Court
that the arbitrator cannot be qualified to arbitrate if he is the part of the
contract.
The Amendment Act has clarified the lacuna that existed since the
inception of the Act. The provision earlier only dealt with the expiration of
the man- date of an arbitrator and did not deal with the procedure for re-
appointment. For arbitrations commencing after October 23, 2015, a
fresh application for appointment need not be filed in case of
termination and substitution may be made, however the practical
application is yet to be tested.
This will surely help a party to ensure a time bound arbitration process
while entering into a contract and in compelling the arbitrator to deliver
his award within the stipulated time- lines. At the same time it equally
becomes important to stipulate realistic timeliness for conclusion of an
arbitration process so as to avoid forced expiry of the arbitrator’s
mandate despite best efforts to deliver an award in a timely fashion.
The Arbitral Tribunal should treat the parties equally and each party should
be given full opportunity to present its case. The Arbitral Tribunal is not
bound by the CPC or the Indian Evidence Act, 1872. The parties to
arbitration are free to agree on the procedure to be followed by the Arbitral
Tribunal. If the parties do not agree to the procedure, the procedure will be
as determined by the Arbitral Tribunal.
The Claimant should submit the statement of claims, points of issue and
the relief or remedy sought. The Respondent should state his defense in
respect of these particulars. All relevant documents must be submitted.
Such claim or defense can be amended or supplemented at any time.
By the Amendment Act, the time limit for conduct of the arbitral
proceedings have been streamlined and arbitrators are mandated to
complete the entire arbitration proceedings within a span of 12 (twelve)
months from the date the Arbitral Tribunal enters upon the reference.
However, a 6 (six) months extension may be granted to the arbitrator by
mutual consent of the parties. Beyond 6 (six) months, any further
extension may be granted to the arbitrator at the discretion of the court
or else the proceedings shall stand terminated. An application for
extension of time towards completion of arbitral proceedings has to be
disposed of expeditiously. There is also a provision made for awarding
additional fees, as consented upon by the parties, to them for passing
the award within the time span of 6 months.
For the stated purpose the time limit for making an award under this
section has been capped at 6 months from the date the Arbitral Tribunal
enters upon the reference.
Under Section 30 of the Act, even in the absence of any provision in the
arbitration agreement, the Arbitral Tribunal can, with the express consent of
the parties, mediate or conciliate with the parties, to resolve the disputes
referred for arbitration.
The Limitation Act, 1963 is applicable to arbitrations under Part I. For this
purpose, date on which the aggrieved party requests other party to refer
the matter to arbitration shall be considered. If on that date, the claim is
barred under Limitation Act, the arbitration cannot continue. If arbitration
award is set aside by court, time spent in arbitration will be excluded for the
purposes of Limitation Act. This enables a party to initiate a fresh action in
court or fresh arbitration without being barred by limitation.
It must state the reasons for the award unless the parties have agreed that
no reason for the award is to be given. The Award should be dated and the
place where it is made should be mentioned (i.e. the seat of arbitration). A
copy of the award should be given to each party. Arbitral Tribunals can also
make interim awards.
The interest rate payable on damages and costs awarded, unless the
arbitral award otherwise directs, shall be 18 percent per annum, calculated
from the date of the award to the date of payment.
The regime for costs has been established which has applicability to both
arbitration proceedings as well as the litigations arising out of
arbitration.
The explanation defining the term ‘costs’ for the purpose of this sub-
section has been added. The circumstances which have to be taken into
account while determining the costs have been laid down in the sub-
section (3) of the freshly added section (Section 31A). In a nutshell this
provision is added to determine the costs incurred during the
proceedings including the ones mentioned under Section 31(8) of the
Act.
Section 34 provides for the manner and grounds for challenge of the
arbitral award. The time period for the challenge is before the expiry of 3
months from the date of receipt of the arbitral award (and a further
period of 30 days on sufficient cause being shown for condonation of
delay). If that period expires, the award holder can apply for execution of
the arbitral award as a decree of the court. But as long as this period has
not elapsed, enforcement is not possible.
Under Section 34 of the Act, a party can challenge the arbitral award
on the following grounds-
iii. the award contains decisions on matters beyond the scope of the
arbitration agreement;
The Amendment Act clarifies that an award will not be set aside by the
court merely on erroneous application of law or by re-appreciation of
evidence. A court will not review the merits of the dispute in deciding
whether the award is in contravention with the fundamental policy of
Indian law. The Amendment Act has also introduced a new section
providing that the award may be set aside if the court finds that it is vitiated
by patent illegality which appears on the face of the award in case of
domestic arbitrations. For ICA seated in India, ‘patent illegality’ has been keep
outside the purview of the arbitral challenge.
3 months + 30
days of the date of
receipt of District court or HC (as
award/date of applicable), where
correction subject matter of
dispute lies or where
respondent resides or
carries on business in
case of domestic award
Application to set
aside the award
Appeals
A challenge under this section can be filed only after providing prior
notice to the opposite party.
Under the Act, there was an automatic stay once an application to set
aside the award under Section 34 of the Act was filed before the Indian
courts.
a. Party was under some incapacity; Ground (a) – (f) in the pre-amendment era has
been retained with the addition of the following:
b. Arbitration agreement not valid under the
governing law of the agreement; a. In the explanation to Section 34 of the Act,
public policy of
c. Applicant not given proper notice India has been clarified to mean only if:
and not able to present its case; (a) the making of the award was induced or
affected by fraud or corruption or was in
d. Award deals with a dispute not contemplated violation of Section 75 or 81; or (b) it is in
by terms of the submission to arbitration, or contravention with the fundamental policy of
beyond the scope of the submission to Indian law; or (c) it is in contravention with the
arbitration; most basic notions of the morality or justice;
e. Composition of Arbitral Tribunal or the b. A new section has been inserted providing
arbitral procedure not in accordance with that the award may be set aside if the court
the agreement or not in accordance with Part finds it vitiated by patent illegality which
I of the Act; appears on the face of the award. For
international commercial arbitrations
f. Subject-matter of the dispute not seated in India,
capable of settlement by arbitration ‘patent illegality’ has been keep outside
under the law; the purview of the arbitral challenge;
g. Award in conflict with the public policy of India c. An award will not be set aside by the court
(if induced or affected by fraud or corruption merely on erroneous application of law or by re-
or was in vio- lation of confidentiality appreciation of evidence;
requirements of a conciliation or where a
confidential settlement proposal d. A court will not review the merits of the dispute
in a conciliation is introduced in an arbitration). in deciding whether the award is in
contravention with the fundamental policy of
Indian law.
An appeal lies from the following orders and from no others to the court
authorized by law to hear appeals from original decrees of the court
passing the order
ii. setting aside or refusing to set aside an Arbitral Award under Section 34
However, a three judge Bench of the Supreme Court has recently held in
Centrotrade Minerals & Metal v. Hindustan Copper that parties may
provide for an appeal to lie from the award to an appellate arbitral tribunal.
Such a clause was held not to be contrary to the laws of the country and
thus enforceable. It appears that the scope of appeal in such cases is far
wider than an appeal to a court.
Appeal shall also lie to a court from an order of the Arbitral Tribunal-
i. accepting the plea referred to in sub-section (2) or sub- section (3) of Section
16; or
ii. granting or refusing to grant an interim meas- ure under Section 17.
Moreover, no second appeal shall lie from an order passed in appeal under
this Section but nothing in Section 37 shall affect or take away any right
to appeal to the Supreme Court.
XVII. Enforcement and execution of the award
In India, the enforcement and execution of arbitral awards both domestic
and foreign are governed by the Act read with the CPC. While the former
lays down the substantive law governing enforceability and execution of an
award, the latter deals with the procedures required to be followed when
seeking execution of an award.
When the period for filing objections has expired or objections have been
rejected, the award can be enforced under the CPC in the same manner as
if it were a decree passed by a court of law.
Also, the mere fact that an application for setting aside an arbitral award has
been filed in the court does not itself render the award unenforceable unless
the court grants a stay in accordance with the provisions of sub-section 3, in
a separate application. It is the discretion of the court to impose such
conditions as it deems fit while deciding the stay application.
B. Attachment of Property
Post the decision of the Supreme Court in BALCO , Indian arbitration law
has been made seat-centric. The Amendment Act clarifies that Part I of the
Act will not be applicable in foreign seated arbitrations, save and except the
standalone provisions discussed below in the table.
About 48 countries have been notified by the Indian government so far. They
are:- Australia; Austria; Belgium; Botswana; Bulgaria; Central African
Republic; Chile; China (including Hong Kong and Macau) Cuba;
Czechoslovak Socialist Republic; Denmark; Ecuador; Federal Republic of
Germany; Finland; France; German; Democratic Republic; Ghana; Greece;
Hungary; Italy; Japan; Kuwait; Malagasy Republic; Malaysia; Mauritius,
Mexico; Morocco; Nigeria; Norway; Philippines; Poland; Republic of Korea;
Romania; Russia; San Marino; Singapore; Spain; Sweden; Switzerland;
Syrian Arab Republic; Thailand; The Arab Republic of Egypt; The
Netherlands; Trinidad and Tobago; Tunisia; United Kingdom; United
Republic of Tanzania and United States of America.
Thus, to reach the conclusion that a particular award is a foreign award, the
following conditions must be satisfied -
Further, Section 45 can only be applied when the matter is the subject of
a New York Convention arbitration agreement, whereas Section 8 applies
in general to all arbitration clauses falling under Part I of the Act.
In Chloro Controls (I) P. Ltd. v. Severn Trent Water Purification Inc. &
Ors., the Supreme Court has held that the expression ‘person claiming
through or under’ as provided under Section 45 of the Act would mean
and include within its ambit multiple and multi-party agreements. Hence
even non-signatory parties to some of the agreements can pray and be
referred to arbitration.
This ruling has widespread implications for foreign investors and parties
as now, in certain exceptional cases involving composite transactions and
inter- linked agreements, even non-parties such as a parent company,
subsidiary, group companies or directors can be referred to and made
parties to an ICA.
A. Commercial transaction
The award must be given in a convention country to resolve commercial
disputes arising out of a legal relationship. In the case of RM
Investment & Trading v. Boeing, the Supreme Court observed that the
term “commercial” should be liberally construed as having regard to
manifold activities which are an integral part of international trade.
B. Written agreement
The Geneva Convention and the New York Convention provide that a
foreign arbitral agreement must be worded formally or be in accordance
with a particular format.
iii. the award contains decisions on matters beyond the scope of the
arbitration agreement;
iv. the composition of the arbitral authority or the arbitral procedure was not
in accordance with the arbitration agreement;
vii. the enforcement of the award would be contrary to Indian public policy.
The term “public policy” as mentioned under Section 48 (2) (b) is one of the
conditions to be satisfied before enforcing a foreign award. The Supreme
Court in Renusagar Power Co. Ltd. v. General Electric Co., (“Renusagar”)
held that the enforcement of foreign award would be refused on the ground
that it is contrary to public policy if such enforcement would be contrary to:
Thus by the above decisions, the courts in India have laid down certain
threshold which defines “public policy” for enforcing foreign awards in
India. The courts, after the land mark judgment, have further narrowed
down the meaning of the words “public policy” in order to give effect to the
Act.
However, in Shri Lal Mahal Ltd. v. Progetto Grano Spa(“Lal Mahal”), it was held
that enforcement of foreign award would be refused under Section 48(2) (b) only
if such enforcement would be contrary to (i) fundamental policy of Indian law;
or (ii) the interests of India; or (iii) justice or morality. The wider meaning given
to the expression “public policy of India” occurring in Section 34(2)(b)(ii) in Saw
Pipes is not applicable where objection is raised to the enforcement of the
foreign award under Section 48(2)(b). The Supreme Court further discussed
Phulchand Exports Limited v. O.O.O. Patriot (“Phulchand”), wherein it was
accepted that the meaning given to the expression “public policy of India” in
Section 34 in Saw Pipes, must be applied to the same expression occurring in
Section 48(2)(b) of the 1996 Act. The Supreme Court concluded that “public
policy of India used in Section 48(2) (b) has to be given a wider meaning and
the award could be set aside, if it is patently illegal” does not lay down correct
law, and has hence overruled the earlier decisions on this point.
The Amendment Act seems to have taken into account the findings
of the court in pro-arbitration judgments such as Shri Lal Mahal Ltd.
Vs Progetto Grand Spa by now specifically providing an explanation
in Section 48, for the avoidance of all doubts, that an award is in
conflict with the public policy of India, only if (i) the making of the
award was induced or affected by fraud or corruption or was in
violation of section 75 or section 81; or (ii) it is in contravention with
the fundamental policy of Indian law; or (iii) it is in conflict with the
most basic notions of morality or justice.
The Supreme Court in Shin-Etsu Chemical Co. Ltd. v. Aksh Optifibre Ltd., held
that-
In the recent past, there has been a lot of enthusiasm on evolving laws of
arbitration in India and the emerging issues therein, such as (a)
prospective applicability of the Amendment Act; (b) whether two Indian
parties can chose a foreign seat of arbitration; (c) whether it is possible to
arbitrate a dispute arising over allegations of oppression and
mismanagement.
There are conflicting decisions of various High Courts. The Madras High
Court in New Tripur Area Development Corporation Limited v. M/s.
Hindustan Construction Co. Ltd. & Ors., had ruled that the language used
in the Section 26 of the Amendment Act only refers to arbitral
proceedings and not court proceedings due to deletion of the language “in
relation to.” Section 26 of the Amendment Act is not applicable to the
stage post arbitral proceedings. This view has been supported by the
division bench of Calcutta High Court in Tufan Chatterjee v. Rangan Dhar
AIR 2016 Cal 213;
The Madhya Pradesh High Court primarily relied on the ruling in the case
of Atlas Exports Industries v. Kotak & Compan wherein the Supreme
Court ruled that two Indian parties could contract to have a foreign-seated
arbitration; although, the judgment was in context of the 1940 Arbitration
Act. Under appeal, although expected, the Supreme Court did not opine on
this issue.
The Bombay High Court opined that a petition under Sections 397 and
398 of the Companies Act, 1953 may comprise of conduct of
clandestine non-contractual actions that result in the mismanagement
of the company’s affairs or in the oppression of the minority
shareholders, or both.
8. Conclusion
In spite of India being one of the original signatories of the New York
Convention, arbitration in India has not always kept up with international
best practices. However, the last five years have seen a significant positive
change in approach. Courts and legislators have acted with a view to bringing
Indian arbitration law in line with international practice.
With the pro-arbitration approach of the courts and the Amendment Act in
place, there is cause to look forward to best practices being adopted in Indian
arbitration law in the near future. Exciting times are ahead for Indian
arbitration jurisprudence and our courts are ready to take on several matters
dealing with the interpretation of the Amendment Act.
Annexure
A. Background
The Madras High Court (“Madras HC”) in its recent judgment of New
Tirupur Area Development Corporation Ltd. (“NTADCL”) v. M/s
Hindustan has Construction Co. ltd. (“HCC”)dealt with the
interpretation and applicability of Section 26 of the Amendment Act. The
Madras HC held that Section 26 of the Amendment Act is not applicable
to post arbitral proceedings and therefore separate application needs to
be filed under Section 36 (2) of the Act as required under the amended
provisions to stay enforcement proceedings pending challenge of an
arbitral award.
Section 36 (2) and (3) as introduced by the Arbitration Ordinance, 2015
with effect from October 23, 2015 stipulates a condition for filing a
separate application along with the Section 34 petition for setting aside
the arbitral award to stay the enforcement proceedings.
NTADCL had filed its challenge to an arbitral award and contended that
since Section 26 of the Amendment Act clarifies that it is not applicable to
arbitration proceedings commenced under the Act, there is no
requirement to file a separate stay application. By virtue of filing the
challenge petition under Section 34 of the Act, the arbitral award
automatically becomes unenforceable till such time the challenge petition
under section 34 of the Act is disposed of.
Further relying on the Supreme Court ruling of Thyssen Stahl Union GMBH v.
Steel Authority of India Ltd., NTADCL argued that the requirement of filing of
separate stay application under the amended Section 36 (2) would apply
only in relation to arbitral proceedings commenced on or after the date of
commencement of the Amendment Act. The Supreme Court in Thyssen held
that the expression “in relation to arbitral proceedings” would also cover
court proceedings within its ambit due to the usage of the words “in relation
to”. The judgment was rendered in the con- text of repeal and savings clause.
Section 85(2) of the Act is applicable in two limbs which clarifies that pro-
visions of the old act would apply to arbitral proceedings which commenced
prior to the Act coming into force unless otherwise agreed by the parties and
Act would apply in relation to arbitral proceedings which commenced on or
after the Act came into force.
The usage of the words “in relation to” cannot be interpreted in a narrow
manner and would include all proceedings including court proceedings.
The court held that the legislative intent of making the provisions of the
Amendment Act applicable to court proceedings was clear in view of the
following:
This judgment deals only with the scenario of post arbitral proceedings
however the ruling may have a much wider impact in case of other types
of court proceedings (interim reliefs, seeking evidence, appeals) initiated
post October 23, 2015 in cases where arbitration proceedings may have
commenced prior to coming into force of the Amendment Act. There will
be two set of laws applicable in such cases with no clarity on the
practical implementation of the different regimes to arbitral and court
proceedings.
II. Two Indian Parties Opting for Foreign- Seated
Arbitration: No Bar?
A. Background
The Madhya Pradesh High Court (“Court”) in its recent decision in Sasan
Power Ltd v. North America Coal Corporation India Pvt Ltd has held that two
Indian parties may conduct arbitration in a foreign seat under English law.
The Court relied upon an earlier decision of a Division Bench of the Supreme
Court of India (“Supreme Court”) in Atlas Exports Industries v. Kotak & Company
(“Atlas Exports”) wherein the Supreme Court, under the Arbitration Act, 1940
(“1940 Act”), had held that it was not against the public policy of India when two
Indian parties contract to have a foreign-seated arbitration.
Whilst this judgment provides certain answers in the longstanding and yet
inconclusive debate on the issue of whether two Indian parties can seat their
arbitration abroad, it also throws up larger questions.
B. Factual Matrix
Sasan Power entered into an association agreement with North
American Coal Corporation-US (“NACC-US”) in 2007 (“Agreement”). The
Agreement, inter alia, provided for resolution of disputes by way of
arbitration to be administered by ICC in London, England, under laws
of the United King- dom. In 2011, NACC-US assigned its rights, liabilities
and obligations under the Agreement to the Respondent - North
America Coal Corporation India Pvt Ltd. (“NACC-India”) by way of an
Assignment Agreement. Interestingly, whilst an assignment to NACC-
India was conducted, it appears that the obligations and liabilities of
NACC-US under the Agreement continued.
A second request for arbitration was filed by NACC-US before the ICC.
Sasan Power filed a second suit challenging the request for arbitration
filed by NACC-US.
NACC-India filed applications for rejection of plaint under Order VII Rule
11 of the Code of Civil Procedure, 1908 (“Code”) read with Section 45 of
the Arbitration & Conciliation Act, 1996 (“Act”) and vacation of the anti-
arbitration injunction granted by District Court (“Applications”), before
the District Court. The District Court allowed the Applications moved by
NACC-India and dismissed the suit filed by Sasan Power. Consequently,
Sasan Power filed this appeal under Section 96 of the Code.
C. Issues
The Court, amongst other things, considered:
D. Gist of Arguments
Sasan Power contended that TDM Infrastructure did not permit two Indian
parties to derogate from Indian law by agreeing to conduct arbitration with
a foreign seat and a foreign substantive law. Further, reliance on Atlas
Exports was erroneous since it was a judgment under the 1940 Act and
only the Act would be applicable to the present case.
The mandate of Section 45 of the Act would not be attracted since an
arbitration clause contemplating a foreign seated arbitration between two
Indian parties was invalid; hence Applications based on such a void, null
and inoperative arbitration clause would not be maintainable.
NACC-India argued that that no appeal laid against an order passed under
Section 45 of the Act. Further, it was argued that TDM Infrastructure was
limited in scope to appointment of an arbitrator during proceedings
under Section 11(6) of the Act, where the seat of arbitration was India. The
provisions of Section 28(1) of the Act were not applicable in the present
situation since the seat of arbitration was England. Atlas Exports,
wherein it was stated that by virtue of the Exception 1 to Section 28 of the
Contract Act, two Indian parties could have a foreign seated arbitration;
would apply. Given that Atlas Exports was passed by a two- judge bench, it
would be considered precedent even assuming TDM Infrastructure were
to apply not only in cases related to Section 11(6) of the Act.
3. The Court stated that the principle laid down in Atlas Exports (that
was by a larger bench than TDM Infrastructure) would, in light of the
decision in Fuerst Day Lawson Ltd v. Jindal Exports, wherein it was
observed by the Supreme Court that there was not much difference
between provisions of the Act and 1940 Act; be binding precedent in
relation to the issue at hand.
4. The Court noted that in TDM Infrastructure the Supreme Court had
clarified by way of an Official Corrigendum that:
“It is, however, made clear that any findings/ observations made
hereinbefore were only for the purpose of determining the jurisdiction of this
Court
as envisaged under Section 11 of the 1996 Act and not for any other
purpose.”
5. The Court observed that the scheme of the Act indicated that the
classification of an arbitration as an international commercial
arbitration depended only on the nationality of the parties, which is
only relevant for the appointment arbitrators as contemplated under
Section 11 of the Act.
6. The Court opined that the nationality of the parties would not
influence the applicability of Part II of the Act, the applicability of
which would flow depending on the seat of arbitration.
7. The Court, relying upon Enercon (India) Private Limited v. Enercon GMBH
and Chatterjee Petroleum v. Haldia Petro Chemicals, was of the opinion
that where the parties had agreed to resolve their disputes through
arbitration, the courts were to give effect to the intention of the
parties and interfere only when the agreement was null or void or
inoperative.
This judgment interprets the scheme of the Act, whereby it clarifies that
applicability of Part II of the Act is not based on the nationality of the
parties but on the basis of where the arbitration is “seated”. If
arbitration is seated outside India, irrespective of the nationality of the
parties involved, it will be considered to be a “foreign award”.
The issue before the court was whether two Indian parties could seat an
arbitration in a foreign country with foreign law as the substantive law
governing the dispute. The concern with allowing the same has been the
permissibility for Indian parties to be governed by laws other than the laws
of India. The consequence of such an act, allowing Indian parties to expressly
con- tract out of Indian law, being arguably against Indian public policy; is a
matter of concern since it would impact the enforceability of the award.
However, the Court also noted that position was qualified with a
statement that “if the seat of arbitration would have been at
Singapore, certainly English law will have to be applied”.
Should this judgment be upheld, another potential issue that may arise is
that since the arbitrability of a dispute is determined by the law of the
seat, it would not be unimaginable for Indian parties to refer disputes,
which would otherwise not be arbitrable in India, to binding arbitration
merely by choosing foreign seat.
In the meanwhile, this judgment would come as some relief for Indian
companies (especially subsidiaries of foreign companies) that may have
unwittingly entered into arbitration agreements providing for a foreign seat
and a foreign substantive law, with other Indian parties; perhaps unaware of
the complexities surrounding this issue.
At the very least, enforcement of such award still remains untested and
may prove to be a challenge. In light of the contentious point of law and
the various issues, it is expected that this matter may find its way before
the Supreme Court in due course. The judgment of the Supreme Court is
eagerly awaited in this respect.
III. Allegations of Fraud not a Bar to Foreign
Seated Arbitration
The only exception is in cases where the court finds the arbitration
agreement to be null and void or inoperative or incapable of being
performed.
A. Introduction
B. Background
The dispute pertained to obtaining media rights for the Indian sub-
continent from the Board of Cricket Control of India. In this regards WSG
and MSM entered into a Deed for Provision of Facilitation Services
(Facilitation Deed”), where under MSM was to pay WSG ₹ 4,250,000,000 as
facilitation fees.
The Facilitation Deed was governed by English Law and parties had agreed
to settle their disputes through arbitration before the International
Chamber of Commerce (“ICC”), with a seat of arbitration in Singapore
(“Arbitration Agreement”).
C. MSM’s Case
It was MSM’s case that since the Facilitation Deed, which contained the
Arbitration Agreement, in null and void on account of the
misrepresentation and fraud of WSG, the Arbitration Agreement itself
was void and could not be invoked.
D. WSG’s Case
It was WSG’s case unless the Arbitration Agreement, itself, apart from the
Facilitation Deed, is assailed as vitiated by fraud or misrepresentation; the
Arbitral Tribunal will have jurisdiction to decide all issues including
validity and scope of the arbitration agreement.
E. Impugned Judgment
The Bombay HC had, in the impugned Judg- ment, held that disputes
where allegation of fraud and serious malpractice on the part of a party are
in issue, it is only the court which can decide these issues through
furtherance of judicial evidence by the party and these issues cannot be
properly gone into by the arbitrator, thereby granting the anti-arbitration
injunction sought for. This decision of the Bombay HC was the only
judgment where an Indian Court had held allegations of fraud as a bar to
foreign seated arbitrations, though such findings were prevalent in the
sphere of domestic arbitrations.
F. Judgment of the Supreme Court
The Supreme Court, by re-enforcing its pro-arbitration approach, set aside
the Impugned Judgment and held that only bar to refer parties to foreign
seated arbitrations are those which are specified in Section 45 of the
Indian Arbitration and Conciliation Act, 1996 (“Act”) i.e. in cases where the
arbitration agreement is either (i) null and void or (ii) inoperative or (iii)
incapable of being performed.
While explaining the term null and void, the Supreme Court clarified
that the arbitration agreement being a separate agreement does not
stand vitiated if the main contract is terminated, frustrated or is
voidable at the option of one party.
The Supreme Court held that a court will have to see in each case whether
the arbitration agreement is also void along with the main agreement or
whether the arbitration agreement stands apart from the main
agreement and is not null and void, thus accepting the submissions of
WSG.
G. Analysis
This is a welcome decision for foreign parties having arbitration
agreements with Indian counter-parts. Before this judgment was delivered,
Indian parties were increasing challenging arbitrability of disputes where
allegations of fraud were made against them, relying of the Supreme
Court’s own decision in the case of N. Radhakrishnan v. Masestro Engineers
& Ors (“N Radhakrishnan”). By this decision the Supreme Court has
limited the applicability of its decision in N Radhakrishnan to domestic
arbitrations hence clarifying that, allegations of fraud against a party or
consequential rescission of the main agreement is not a bar on
arbitrability of disputes between the parties under Indian Law, when the
seat of arbitration is outside India.
IV. Enforcement of Foreign Awards Becomes
Easier: ‘Patent Illegality’ Removed from
the Scope of Public Policy
A. Facts
The dispute arose out of a contract between an Indian seller (“Appellant”)
and a foreign buyer (“Respondent”) whereby the Appellant had agreed to
supply certain type of wheat to the Respondent. The Respondent had
alleged that the wheat supplied was not of the quality as agreed to by the
parties and as a result it had suffered significant damages.
The matter was referred to the Arbitral Tribunal of the Grain and Feed Trade
Association, London (“GAFTA”), which passed an award in favour of the
Respondent. Thereafter, the Appellant carried such award in appeal before
the Board of Appeal of GAFTA, which also passed the award in favour of the
Respondent. The awards were then challenged by the Appellant before
the courts in U.K., where again the awards were upheld.
The Respondent on the other hand argued that the matters as raised by
the Appellant were questions regarding appreciation of evidence and were
questions of fact which could not be gone into at the stage of challenge to
enforcement of a foreign award under section 48 of the Act.
B. Issue
Thus, issue arose regarding the scope and interpretation of the
expression ‘public policy’ which is provided as a ground to refuse
enforcement of a foreign award under section 48(2)(b) of the Act and
whether the enforcement of the awards could be refused on the grounds
as alleged by the Appellant.
The issue further was whether the expression ‘public policy’ shall have the
same meaning and purport under section 34(2)(b)(ii) and section 48(2)(b) of the
Act?
C. Judgment
As the question revolved around the interpretation of the scope of the
expression ‘public policy’ the Supreme Court considered the following three
landmark rulings in this regard:
The court further observed that ONGC dealt with a situation where the
arbitral award was sought to be set aside under section 34 as opposed to
an application to refuse enforcement of an award under section 48. It
was stated that the expression ‘public policy of India’ under 34 was
required to be interpreted in the context of the jurisdiction of the
court where the validity of the award is challenged before it becomes
final and executable in contrast to enforcement of award after it
becomes final. Thus, it was seen that under Section 34 the expression
public policy would also entail within its folds any ‘patent illegality’ for
setting aside the award.
3. justice or morality.
The wider meaning given to the expression “public policy of India” occurring
in Section 34(2)(b) (ii) in Saw Pipes (ONGC) is not applicable where objection is
raised to the enforcement of the foreign award under Section 48(2)(b).”
Thus, relying on the above law, the Supreme Court observed that the
same ground had also been raised by the Appellant before the courts in
U.K. to have the award set aside.
However, the High Court of Justice at London did not consider the
ground to be sufficient enough for the award to be set aside. Thus, the
court viewed that the same argument could hardly be good enough to
refuse enforcement. The court further provided that section 48 does not
offer an opportunity to have a second look at the foreign award at the
enforcement stage. The court affirmed that sec- tion 48 does not permit
review of the award on merits and also that procedural defects in course
of foreign arbitration do not necessarily imply that foreign award would
be unenforceable. Accordingly, the appeal was dismissed by the court
and that award was held to be enforceable.
D. Analysis
The judgment in ONGC led to expansion of the meaning of the
expression ‘public policy’ as pro- vided under section 34 of the Act, which
opened the
floodgates to petitions challenging the arbi- tral award on the ground of
‘patent illegality’. The decision was criticized as it allowed the parties to
have a second bite at the matter, to the extent that the ground of patent
illegality was viewed broad/y.
The above decision coupled with the pre- BALCO scenario i.e. applying the
law as enunciated under the Bhatia International case, permitted
awards passed in arbitrations seated outside India to be challenged under
section 34 in certain cases. This led to a very broad ground being available
to parties to set aside awards passed in international commercial
arbitrations. Though, the BALCO decision has now clarified that awards
passed in foreign seated arbitrations cannot be challenged under section
34, the difficulty arose on account of the judgment of Phulchand.
A. Introduction
The Delhi High Court (“Court”) in the case of Virgoz Oils and Fats Pte. Ltd.
(“Vigoz”) v National Agricultural Marketing Federation of India (“NAFED”) has
refused the enforcement of a foreign arbitral award after allowing an
objection to its enforcement under Section 48 of the Arbitration and
Conciliation Act, 1996 (“The Act”). The Court has referred to and relied upon
the requirements set out under the Convention on the Recognition and
Enforcement of Awards, 1958 (“The Convention”) and the Act, to examine
the requirements of a valid arbitration agreement. Applying these
guidelines, the Court has held that the arbitration agreement between the
parties in the present matter, was a part of a written agreement which was
not signed by NAFED. Thereby, rendering the arbitration agreement
inoperable and invalid against NAFED.
B. Facts
Virgoz and NAFED, through a broker, had entered into negotiations for
the sale of edible oil by Virgoz to NAFED. Through the negotiations, a series
of sales contracts were formed, which were transmitted to NAFED by the
broker. NAFED, upon receipt of the same, requested a deferred date of
shipment of the goods to the broker, who in turn, communicated the
same to Virgoz. The contracts were amended accordingly by Virgoz with
the changes in the date of shipment being the only material alteration.
The contracts were signed by the broker and Virgoz, but not by NAFED or
its representatives (“Impugned Contracts”). Virgoz, proceeded, with its
obligations under the Impugned Contracts assuming the same to have
become effectively concluded between the parties and shipped the goods
to NAFED. Upon NAFED’s failure to provide a Letter of Credit, as per the
terms of the Impugned Contracts, Vigoz declared NAFED to be in default.
Thereafter, Virgoz proceeded to initiate arbitration proceedings before an
arbitral tribunal constituted under the Palm Oil Refiners Association of
Malaysia, Rules of Arbitration and Appeal (“PORAM Rules”), in accordance
with the arbitration clause contained in the contracts.
The Tribunal passed an award on April 5, 2012, which accepted two key
submissions advanced by Virgoz being (a) a letter dated July 29, 2008,
from NAFED requesting a deferred date of shipment while making
reference to the contracts, was evidence of the existence of a contractual
arrangement between the parties and (b) the signing of an Agreement by
a broker on behalf of the buyer, was ‘common practice’ in the industry. The
award was passed in favor of Virgoz.
C. Issue
Whether there existed a valid arbitration agreement between the
parties.
D. Contentions
Virgoz advanced two primary contentions to establish that the award
being a foreign award must be enforced under Part II of the Act, they
were
(a) the parties were dealing with each other through a broker and therefore
there was no requirement for NAFED to sign the Impugned Contract and
(b) the Letter dated July 29, 2008, indicated that NAFED had accepted the
terms of the Impugned Contract and requested a deferred date of shipment.
E. Judgment
The Court analyzed the definition of a ‘foreign award’ under section 44 of the
Act, which stipulates that the award must be rendered in pursuance of an
arbitration agreement in writing between the parties, to which the
Convention shall apply. In order to examine whether there was a valid
arbitration agreement in terms of the Convention, the Court analyzed
Paragraph 2 of Article II of the Convention, which states that an ‘agreement
in writing’ would inter alia mean an arbitration clause contained in a
contract signed by the parties or contained in an exchange of letters or
telegrams.
The Court held that, Virgoz had relied upon an arbitration agreement
contained in the Impugned Contracts and not in any correspondence
exchanged between the parties. Therefore, as per the aforementioned
requirements under the Convention, the Impugned Contracts should have
been signed by all parties to the contract in order to deem it as a valid
arbitration agreement. This requirement was not met as NAFED had not
signed the contracts, thus, resulting in the arbitration agreement
becoming invalid and inoperative with respect to NAFED. The Court also
examined the communications between the par- ties, holding that the
Letter dated July 29, 2008, did not evidence the intention of NAFED to bind
itself to the terms of the Impugned Contract or the arbitration clause
contained therein.
2. The broker signed the Impugned Contract in his own capacity and not
for and on behalf of NAFED
F. Analysis
The judgment of the Court, might be construed as a departure from the
pro-arbitration stance adopted by the judiciary of late. If an appeal was to
be preferred it would be interesting to observe whether the Appellate Court
would consider (a) the usual trade practice between parties trading in palm
oil in India to have unsigned contracts; (b) the correspondence exchanged
between the parties by which the Impugned Contract was deliberated upon
and amended and (c) the verdict of an expert body mandated to preside
over disputes in that particular industry.
However, it must be noted that the legal analysis con- ducted by the Court
which formed the basis of the judgment is sound. The requirement of an
agreement in writing, when evidenced in an arbitration agree- ment, results
in the consequent requirement that the agreement must be of the nature
of a valid contract. The lack of a party’s signature upon the contract, would
be strong evidence as to the lack of the party’s consent to the agreement and
consequently to an arbitration clause contained therein.
A valuable take away from this pronouncement is to ensure that all parties to a
contract containing the arbitration agreement should sign the same even if
they are being represented by another for all practical purposes. Further, if
parties intend to enter into commercial transactions basis communications
exchanged, then they must ensure to incorporate a dispute resolution
mechanism in the same.
A. Introduction
The Supreme Court of India (“Supreme Court”), in A. Ayyasamy (Appellant) v.
A. Paramasivam & Ors. (Respondents) has held that disputes involving
allegations of fraud arising out of contracts bearing an arbitration clause shall
be referred to arbitration.
Distinguishing, yet not casting away, the oft- cited ruling of the
Supreme Court in the case of N. Radhakrishnan v. Maestro Engineers in
matters involving arbitrability of fraud, a division bench of the
Supreme Court has held that N. Radhakrishnan did not subscribe to
the blanket proposition of non- arbitrability of fraud and that
allegations which could be adjudicated upon in courts could also be
adjudicated upon in arbitral proceedings, subject to certain carve-outs.
B. Facts
The parties entered into a partnership deed on 1 April 1994 for running a
hotel. While the Appellant was entrusted with administration, the
Respondents alleged that the Appellant had failed to make regular
deposits of money into the common operating bank account and had
fraudulently siphoned off an amount of INR 10,00,050.
In a separate raid conducted by the CBI on premises of the Appellant’s
relative, an amount of INR 45,00,000 was seized and alleged to have
been given by the Appellant for business of the hotel.
The Respondents filed a civil suit seeking right of administration of the
hotel. The Appellant sought reference of the dispute to arbitration under
Section 8 of the Arbitration & Conciliation Act, 1996 (“A&C Act”). The
High Court rejected the Appellant’s application on the ground that the
dispute involved allegations of fraud. Aggrieved by the decision, the
Appellant preferred an appeal before the Supreme Court.
The Court held that Section 16 of the A&C Act also operated in the same
vein while equipping the arbitrator to rule upon its own jurisdiction and
minimizing court intervention. Further, the doctrine of separability (where
the arbitration agreement survived nullity, even if embodied in a contract
assailed on the grounds of fraud), helped to retain powers of the arbitral
tribunal and adjudicate upon nullity of the contract. Thus, tribunals are
vested with jurisdiction to consider issues of fraud.
Despite the aforesaid observation, the Supreme Court did not expressly
reject the reasoning in N. Radhakrishnan and held that serious allegations
of fraud were non-arbitrable, while mere allegations of fraud would be
arbitrable. It distinguished, by way of example, between simple and serious
allegations of fraud.
E. Analysis
The judgment is seminal in the arena of fraud related disputes arising
out of contracts bearing arbitration clauses in India seated domestic
arbitrations. In case of foreign seated arbitrations, the Supreme Court
in World Sport Group (Mauritius) Ltd. v. MSM Satellite (Singapore) Pte.
Ltd. had held that allegations of fraud did not prevent the court from
making reference to arbitration under Section 45 of the A&C Act.
However, in the case of India seated domestic arbitrations, there was a
cloud on efficacy of arbitral proceedings to resolve issues of fraud,
particularly in light of the ruling in N. Radhakrishnan.
The Court has also subtly stated that allegations of fraud can be
adjudicated upon in courts when the person against whom such
allegations are levelled desires to be tried in court. This will be an
additional factor to be considered by courts in deciding applications for
reference to arbitration. It will also be crucial for courts to scrutinize if
fraud is directed at the arbitration agreement, thereby impeaching the
agreement (and the resultant arbitration, the same being creature of the
arbitration agreement), as contra-distinguished from the main contract.
A. Brief facts
B. Respondent’s Objections
The Respondent’s primary objection was on the ground that Part I of
the Act is inapplicable to proceedings held outside India and that by
choosing Singapore as the Seat, the parties have impliedly excluded the
applicability of Section 9 of the Act and that therefore the present
Petition is not maintainable. The Respondent’s also contended that the
Amendment Act is inapplicable to the present arbitral proceedings by
virtue of Section 26 of the Amendment Act, as the arbitral proceedings
had commenced prior to the date of commencement of the Amendment
Act.
C. Petitioner’s Contentions
The Petitioner contended that the very purpose for the amended Section
2 (2) was to confer jurisdiction on Indian Courts in respect of Sections 9
and 27 of the Act, even if the seat is foreign and that the expression
“subject to an agreement to the contrary” as found in the amended
Section 2 (2) would mean and require something more than mere
choice of law and seat of arbitration. It was also contended that the
expression “to arbitral proceedings” as used in the first limb of Section
26 does not apply to court proceedings and that therefore the
Amendment Act ought to apply to the present case.
The Court however, also observes that the two limbs of Section 26
of the Amendment Act are not exhaus- tive as the first limb refers
only to proceedings commenced in accordance with Section 21
(found
in Part 1) of the Act, and that therefore Section 26 is silent regarding
applicability of the Amendment Act to proceedings which are not
expressly indicated therein. Due to the lack of any express
indication as to the applicability of the Amendment Act to
arbitrations instituted outside India, the Court adopts a purposive
interpretation, sets out the legislative intent behind the
Amendment Act, and holds that even in cases where there is no
express provision regarding retrospective applicability of the new
law, the Courts should look to further intention of the legislature.
Considering that the very purpose of the amended Section 2 (2) of
the Act was to enable a party to approach Indian Courts for
interim relief even in foreign seated arbitrations, the Court
clarifies that the position regarding non-applicability of Part I of
the Act in foreign seated arbitrations, as held in Bharat Aluminium
Company Vs. Kaiser Aluminium Technical Services Inc., stands
amended as far as Section 2 (2) of the Act is concerned and that
parties now have recourse to Section 9 of the Act even in foreign
seated arbitrations. The Court therefore allows the present
Petition and makes it clear that choice of a foreign law or a foreign
seat or foreign institutional rules does not amount to implied
exclusion of Section 9 of the Act.
A. Introduction
The Delhi High Court (“Delhi HC”) in one of its recent judgment in
Assignia-Vil (“Petitioner”) JV v Rail Vikas Nigam Ltd.(“Respondent”),
taking cognizance of the amendment to Section 12(5) of the
Arbitration & Conciliation Act, 1996 (“Act”) held that under the
Amendment Act, the court is duty bound to secure appointment of
an independent and impartial Arbitral Tribunal.
B. Brief Facts
The parties entered into a works contract (“Contract”) under which
the Petitioner undertook to carry out certain construction works
(“Work”) for the Respondent, to be completed by February 15,
2015. Certain disputes arose between the parties. The Petitioner
had raised three claims (“First Dispute”) against the Respondents
during the execution of the Contract and sought payments. Due to
failure of Respondent, to resolve issues amicably, an arbitral
tribunal (“the First Tribunal”) was constituted in relation to these
three claims. The First Tribunal consisted of serving and retired
employees of the Respondent and was constituted before the
commencement of the Amendment Act.
During the pendency of the First Dispute, an extension of time for
completion of work was granted to the Petitioner, however before
this period had lapsed the Respondent served a notice of termination
to the Petitioner due to faulty execution of the Work. The Petitioner
opposed the termination and sought losses suffered due to untimely
termination. As the attempt to resolve disputes amicable failed, the
Petitioner by its letter dated October 26, 2015 invoked arbitration
(“Second Dispute”) and called upon the Petitioner to suggest five names
for constituting an independent arbitral tribunal. The Respondent’s
failure to respond to the said invocation of arbitration, lead to the
present application under Section 11 (6) of the Act.
C. Issue
The issue before the Delhi HC was whether the dispute relating to the
termination of the Contract had to be referred to the First Tribunal for
resolution, or to a newly constituted independent arbitral tribunal, in
view of the Amendment Act.
D. Arguments
E. Judgment
The Delhi HC, after hearing all the submissions, held that in the normal
course, with due consent of parties, the issue of termination of Contract
could contract should also be referred to the First Tribunal in the pending
arbitration proceedings itself. This would be in the interest of time, cost-
efficiency and to avoid conflicting decisions.
The Respondents had relied upon certain case laws to argue that ‘all
disputes’ arising out of an agreement could be referred to the same Arbitral
Tribunal, and that therefore the issue of the untimely termination of the.
The Delhi HC refered to the Supreme Court’s decision in Dolphin Drilling
Limited v Oil and Natural Gas Corporation Limited which had dealt with the
issue of disputes arising between the parties prior to the invocation of
arbitration and those arising during the pendency of the arbitration dealing
with the past disputes.
The Delhi HC thereafter noted that the First Dispute was invoked before the
commencement of the Amendment Act and the Second Dispute was
invoked post commencement. On the question of applicability of the
Amendment Act, the Delhi HC highlighted that the arbitration clause in the
Contract encompassed statutory modifications to the Arbitration and
Conciliation Act, 1996, and therefore, since the amendments came into
force prior to the invocation of arbitration of the Second Dispute, the
provisions of the Amendment Act would apply.
In light of the amendments brought about by the Amendment Act, the Delhi
HC held that it was the prerogative of the Petitioner to seek constitution of
an independent and impartial Arbitral Tribunal for adjudicating the issue of
termination of the Contract, due to change in law under Section 11 (8) of
the Act and the fact that the First Tribunal comprised of employees of the
Respondent. Having the same tribunal resolve the Second Dispute would
negate the very purpose of the amendments to Section 12 of the
Amendment Act.
F. Analysis
The recent judgment may be amongst the first of many heralding a new era
for the arbitration regime in India, bringing it in line with international best
practices having stringent conflict of interest regimes. It has been common
practice for public sector undertakings in India to have a panel of in-house
arbitrators that are technically proficient in that particular sector, leading to
an unfair advantage over the opposite party.
This judgment marks the end of such in-house arbi- trators and stresses
the importance of compliance with guidelines provided under Section 12(5)
read with Seventh Schedule of the Amendment Act for appointment of
arbitrators to maintain independence and impartiality. Interestingly, the
Delhi HC, by directing the parties to appear before the Delhi International
Arbitration Centre, may have taken a conscious decision to go in for
institutional arbitration, instead of ad-hoc. This may also be in line with the
push for institutional arbitration as was envisaged under the law
commission report but did not find place in the Amendment Act.