Work Method

Statement

JOTUN NEW WATER BASE FACTORY


PROJECT

PT. TAIYO SINAR RAYA TEKNIK


Work Method Statement

Document History :

No. Revision Issuance Date Content Revision


1 0 Mei, 09 2024 New

Prepared By : Reviewed By : Aproved By :

Hermanto Fahruroji Rony Teguh Arifianto


QC Engineer Site Manager Project Manager
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

1. Purpose
Tujuan

1) Establish safe and high-quality work processes and procedures to achieve the goal of “zero
accidents and zero quality complaints”
Menetapkan proses dan prosedur kerja yang aman dan berkualitas tinggi untuk mencapai
target “nol kecelakaan dan nol keluhan kualitas”
2) Easy to understand working procedure and work items for worker
Pekerja mudah memehami langkah-langkah pekerjaan

2. Scope
Ruang Lingkup

The activity for this work is :


Kegiatan untuk pekerjaan ini adalah :

1) Preparing tools, materials and working area


Persiapan alat, material dan area kerja
2) Visual Check for all joint (welding, Flange, Valve, etc)
Visual cek untuk semua joint (welding, flange, valve, dll)
3) Dop pipe connection to equipment
Tutup koneksi pipa ke equipment
4) Put Air or water pressure to the pipe
Beri tekanan udara atau air ke pipa
5) House keeping
Bersih-Bersih

3. Hazard Potential & Countermeasure


Potensi Bahaya & Penanganan
Status Hazard Countemeasure
Yes / No Bahaya Penanganan
Yes Work at height  Use access scaffolding standard &
Bekerja diketinggian give tagging inspection
 Install life line on the area working at
height
 Perform by certified worker
 Use full body harness
 Gunakan akses scaffolding standart
dan pasang tagging inspeksi
 Pasang line line pada area kerja
ketinggian
 Dilakukan oleh pekerja yang
bersertifikasi
 Gunakan full body harness
Yes Falling Objects  Install safety net around working floor
Benda jatuh  Install canopy catch net for scaffold
 Install Barricade
 Void protection
 Pasang safety net sekeliling lantai
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

 Pasang jaring kanopi penangkap benda


jatuh untuk skafolding
 Pasang barricade
 Proteksi lubang
Yes Slip, trip & fall  Install Toe board and net
Tergelincir, tersandung & terjatuh  Use apropriate safety shoes
 install warning sign (Holes, different
level etc.)
 Install Life line
 Install Hard Barricade
 Install papan penghalang dan jaring
 Pakai sepatu safety yang bagus
 pasang tanda peringatan (Lubang,
beda level dll.)
 pasang life line
Yes Electrocuted  Turn off power
Kesetrum  Use electrical gloves
 Tool’s maintaining regularly
 Re check using voltage tester
 Install additional grounding for
equipment
 Clean the area from standing water
and flammable Material
 Matikan power
 Gunakan sarung tangan listrik
 Perawatan alat berulang
 Cek menggunakan tespen
 Pasang tambahan grounding untuk
equipment
 Bersihkan area dari genangan air
dan material mudah terbakar
No Handling and lifting  Check lifting devices
Angkat dan angkut  Coordinate during lifting
 Mark rated maximum load
 Lifting plan
 Use padding for protection material
before lifting & Barricade work area
 Ensure permission to enter heavy
equipment with Jotun security
 Cek alat angkat
 Koordinasi selama pengankatan
 Tandai maksimum beban
 Lifting plan
 Pasang padding untuk proteksi
material sebelum diangkat &
barikade area kerja
 Passtikan ijin masuk alat berat
dengan security Jotun
yes Traffic  Asses traffic activity and route
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

Lalulintas  Define speed limit


 Separate between pedestrian and
vehicle
 Flag man
 Chock
 Barricade
 Kenali aktivitas lalu lintas dan rute
 Tentukan batas kecepatan
 Pisahkan jalur pejalan kaki dengan
kendaraan
 Ganjal
 barikade
No B3 Waste  Place on special waste storage
Sampah B3  Handling by qualified person only
 Provide a proper B3 waste disposal
site
 Simpan pada tempat khusus
 Harus ditangani oleh orang yang
terkualifikasi
 Sediakan tempat pembuangan
sampah B3 yang proper
Yes Housekeeping  Provide 3 type of garbages
Bersih-bersih  Install washing bays
 Material layed on bearing and tag the
PIC name, phone number and photo
 Sediakan 3 tipe tong sampah
 Sediakan tempat cuci alas kaki dan
roda truck
 Taruh material pada bantalan
temmpel nama PIC, nomor hp dan
foto
No Excavation  Asses soil condition to define the
Penggalian protection for soil collapse
 Bluesheet for protection during rain
 Trap or sloping excavation
 Shoring for narrow area
 Install physical barrier
 Install safety sign
 Up down acces every 7 meters long
 Kenali kondisi tanah untuk
menentukan proteksi tanah runtuh
 Bluesheet untuk proteksi selama
hujan
 Pasang pembatas fisik
 Pasang safety sign
 Akses naik turun setiap 7 meter
No Hot Work  Provide APAR for fire protection
 Keep away flammable material
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

 Prepare fire blanket to avoid spark


flash over
 Sediakan APAR untuk proteksi
kebakaran
 Jauhkan material mudah terbakar
 Siapkan selimut api untuk
menghindari percikan api.

4. Personal Protective Equipment


Alat Pelindung Diri

Status Item of Work Personal Protective Equipment


Yes / No Item kerja Alat Pelindung Diri
General  Helmet
Yes Umum  Hard top and puncture proof safety
shoes
 Gloves
 Long sleeve
 Safety glasses
Work at height  Full body harness
Bekerja diketinggian  Double hook lanyard
Yes
 Absorber for height more than 6
meters
 Lifeline
 Toe board
 Canopy catch net
 Safety net
Welding, Grinding, Cutting and chemical  Long sleeves and anti flammable
handling clothes
No
Pengelasan, gerinda, pemotongan dan  Face shield
penanganan bahan kimia  Welder special gloves
Yes Dusty area  Dust mask
Area berdebu
Yes Noisy area (more than 85dB)  Ear plug
Area berisik (lebih dari 85dB)
Yes Electrical work  Electrical gloves
Kerja listrik  Voltage tester

5. Reference
Referensi

1) Document
a) Element 15 HSEQ
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

2) Attachment
a) Job Safety Analysis
b) WI-039 ( Instruksi kerja pekejaan testing/ Pnumatic)

6. Working Tool’s & Material’s


Alat kerja & Material

1) Tool’s

a) Compessor
Kompessor
b) Hydro pump
Pompa hydraulic
c) Pessure Gauge
Indicator tekanan
d) Valve
Keran
e) Hose
Selang

2) Material
a) Piping 304L (stainless steel )

7. Roles and Responsibilities


Peran dan tanggung jawab

1) QA & QC Manager

a) Prepare, revise and issued the Work Instructions


Mempersiapkan, merevisi dan menerbitkan Work Instructions
b) Monitoring the implementation of Work Instructions
Memantau pelaksanaan Work Instructions
c) Attending meeting called to discuss quality issues
Menghadiri meeting terkait masalah kualitas
d) Issued final acceptance report for each related work
Membuat laporan final untuk setiap pekerjaan terkait
2) Site QC Engineer

a) Prepare work method statement


Mersiapkan pernyataan metode kerja
b) Ensure the required preparation has been implemented before work
Pastikan persiapan yang diperlukan telah dilaksanakan sebelum pekerjaan dimulai
c) Check every step of work according to Work Instruction
Periksa setiap langkah pekerjaan sesuai dengan Instruksi Kerja
d) Ensure the material are proper material according consultant technical specification
Pastikan bahan yang digunakan sesuai dengan spesifikasi teknis konsultan
e) Reporting any conditions that may lead to a reduction in quality to the site manager for
further discussion with the consultant and owner
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

Melaporkan segala kondisi yang dapat mengakibatkan penurunan kualitas kepada


manajer proyek agar dapat dibahas lebih lanjut dengan konsultan dan pemilik proyek
f) Observe that the work result is free from misses, damages, defects, discontinuity, etc.
Perhatikan bahwa hasil pekerjaan bebas dari kesalahan, kerusakan, cacat,
ketidakberlanjutan, dll.
g) Observe the satisfactory of work result
Perhatikan kepuasan terhadap hasil pekerjaan
h) Photograph invisible area before closing or backfilling
Ambil foto area yang tidak terlihat sebelum penutupan atau pengisian kembali
i) Prepare inspection test plan
Siapkan rencana inspeksi dan pengujian
j) Photograph inspection test result and report
Foto dan laporkan hasil inspeksi dan pengujian

3) Site Manager

b) Implement a safe work system in accordance with established regulations


Melaksanakan sistem kerja yang aman sesuai peraturan yang telah ditetapkan
c) Coordinate with MI & Jotun regarding shop drawing
Berkoordinasi dengan MI & Jotun terkait shop drawing
d) Coordinate with engineering, supervisors and HSE Staff regarding work to be
excecuted
Berkoodinasi dengan engineering, supervisor dan HSE Staf terkait pekerjaan yang
akan dimulai

4) Engineer

a) Shop drawing preparation and ensure to be aproved before work begin


Menyiapkan shop drawning dan pastikan sudah approve sebelum pekerjaan dimulai
b) Coordinate to supervisor for work needs
Koordinasi dengan supervisor untuk kebutuhan pekerjaan
c) Make work method in term safety and quality
Pembuatan metode kerja baik dari segi safety dan quality

5) Supervisor

a) Make requests for work needs


Membuat request kebutuhan pekerjaan
b) Determine work schedules and targets
Menentukan schedule dan target pekerjaan
c) Analyse the potential hazards that will arise in the work
Menganalisa potensi bahaya yang akan timbul dalam pekerjaan
d) Explain work methods and shop drawings to workers
Menjelaskan metode kerja dan shop drawing kepada pekerja
e) Supervise the work process to be in accordance with the shop drawings
Mengawasi proses pekerjaan agar sesuai dengan shop drawing
f) Coordinate with other contractors or Consultants when there are difficulties in the
project
Berkoodinasi dengan pihak kontraktor lain atau Konsultan saat terdapat kesulitan di
lapangan
g) Evaluate the work during toll box meeting and KY everyday
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

Megevaluasi pekerjaan pada saat toll box meeting dan KY setiap hari
h) Sanctioning workers who perform work without following the rules
i) Memberikan Sanksi kepada pekerja yang melakukan pekerjaan diluar rencana

6) HSE

a) Verifying PTW according to work


Menverifikasi PTW sesuai pekerjaan
b) Implementing TBM and KY runs according to work items
Melaksanakan TBM dan KY berjalan sesuai item pekerjaa
c) Ensure work tools and PPE are appropriate
Memastikan alat kerja dan APD sesuai
d) Supervise safety-related work to achieve quality work
Mengawasi pekerjaan terkait safety untuk mencapai kualitas pekerjaan
e) Ensure that workers are registered in the PTW
Memastikan pekerja sesuai yang terdaftar dalam PTW
f) Ensure that appropriate working methods are in place
Memastikan bahwa metode kerja sesuai dapat berjalan
g) Sanctioning workers who break the rules
Memberikan sanksi kepada pekerja yang melanggar aturan

7) Operator Heavy equipment ( Forklip & crane )


a) Participate in TBM and KY and fill in the attendance list
Mengikuti TBM dan KY dan mengisi daftar hadir
b) Follow the safety and quality instructions and work rules contained in this work method
Mengikuti sesuai intruksi dan aturan kerja safety dan quality yang tertuang dalam
Metode kerja ini
c) Follow the direction of signalman & supervisor according to the work method that has
been approved by the Consultant / Owner
Mengikuti arahan signalman & supervisor sesuai metode kerja yang sudah disetujui
Konsultan/ Owner
d) Maintain working tools and care ( lifting fear )
Menjaga alat kerja dan merawat ( lifting gear )
e) Responsible for work
Bertanggung jawab atas pekerjaan
f) Perform house keeping in the work area
Melakukan house keeping di area kerjanya

8) Signalman
a) Participate in TBM and KY and fill in the attendance list
Mengikuti TBM dan KY dan mengisi daftar hadir
b) Follow the safety and quality instructions and work rules contained in this work method
Mengikuti sesuai intruksi dan aturan kerja safety dan quality yang tertuang dalam
Metode kerja ini
c) Provide direction to heavy equipment operators (forklip & crane) according to the work
method that has been approved by the Consultant / Owner.
Memberikan arahan ke operator heavy equipment ( forklip & crane ) sesuai metode
kerja yang sudah disetujui Konsultan/ Owner
d) Maintain working tools and care ( lifting fear )
Menjaga alat kerja dan merawat ( lifting gear )
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

e) Take responsibility for work and stop work if unsafe conditions and behaviors are
observed.
Bertanggung jawab atas pekerjaan dan stop pekerjaan jika melihat kondisi dan
perilaku yang tidak aman
f) Perform house keeping in the work area
Melakukan house keeping di area kerjanya

9) Riger
a) Participate in TBM & KY and fill in the attendance list
Mengikuti TBM dan KY dan mengisi daftar hadir
b) Follow the safety and quality instructions and work rules contained in this work method
Mengikuti sesuai intruksi dan aturan kerja safety dan quality yang tertuang dalam
Metode kerja ini
c) Can coordinate with the team involved in this work
Dapat bekoordinasi dengan tim yang terlibat dalam pekerjaan ini
d) Follow the safety and quality instructions and work rules contained in this work method
Mengikuti sesuai intruksi dan aturan kerja safety dan quality yang tertuang dalam
Metode kerja ini
e) Maintain working tools and care ( lifting fear )
Menjaga alat kerja dan merawat ( lifting gear )
f) Perform house keeping in the work area
Melakukan house keeping di area kerjanya

10) Worker

a) Participate in TBM and KY and fill in the attendance list


Mengikuti TBM dan KY dan mengisi daftar hadir
b) Follow the safety and quality instructions and work rules contained in this work
method
Mengikuti sesuai intruksi dan aturan kerja safety dan quality yang tertuang dalam
Metode kerja ini
c) Can coordinate with the team involved in this work
Dapat bekoordinasi dengan tim yang terlibat dalam pekerjaan ini
d) Maintain working tools and care
Menjaga alat kerja dan merawat
e) Responsible for work
Bertanggung jawab atas pekerjaan
f) Perform house keeping in the work area
Melakukan house keeping di area kerjanya

8. Step of Works
Langkah kerja :
1. Workers, Supervisors and safety conduct TBM and KY before start to work
Pekerja, Supervisor dan safety melakukan TBM dan KY sebelum pekerjaan di mulai
2. Workers transfer materials for hard barricade and work tools to the work area use mapping
layout
Pekerja mentransfer material untuk barricade dan alat kerja di area kerja menggunakan
mapping layout
3. Prepare a work planning the form of methods and work permits etc.
Menyiapkan rencana kerja sebagai bentuk metode dan izin kerja.
4. Prepare Working area with install barricade
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

Persiapan area kerja dengan pasang barikade.


5. Ensure that the work tool is suitable for use and has been inspected and already update the color code.
Memastikan alat kerja sesuai dan aman untuk digunakan serta sudah di inspeksi dan diberi tagging.
6. Check and inspected the pressure test tool , and make sure its safe for use and update the color
code.
Cek dan lakukan inspeksi alat dan alat flushing , dan pastikan aman untuk digunakan , dan update tagging
nya.
7. Before carrying out the work, coordinate with the relevant parties for the area.
Sebelum melakukan pekerjaan, lakukan koordinasi terlebih dahulu dengan pihak-pihak terkait.
8. Install hard barricades at work area .
Pemasangan hard barricade di area kerja.
9. PNEUMATIC TEST :
a) Prepare the compressor & N2 Bottle equipment (if needed) & make sure in good
condition & ready to use
Siapkan peralatan compressor & N2 Bottle ( jika diperlukan ) & pastikan dalam
keadaan baik & siap pakai
b) Perform a visual check for all joints (welding, flange, valve, etc.) on the pipe / tank
that will be tested & make sure it is ready to be tested
Lakukan visual chek untuk semua joint ( welding, flange, valve dll ) pada pipa / tanki
yang akan ditest & pastikan siap dilakukan test
c) Check all connections to the equipment & make sure they are closed
Chek semua connection ke equipment & pastikan dalam kondisi tertutup
d) Put up a sign / safety sign & police line indicating moderate a pneumatic test was
carried out
Pasang tanda / safety sign & police line yang menunjukkan sedang
dilakukan pneumatic test
e) Put up a sign prohibiting operating the valve, except by those who do the test
Pasang tanda larangan untuk mengoperasikan valve, kecuali oleh yang melakukan
test
f) Perform a pneumatic test, with a testing pressure of 1.5 x work pressure
Lakukan pneumatic test, dengan pressure pengetesan 1.5 x tekanan kerja
g) Look at the pressure on the pressure gauge & note any changes (if there is a drop in
pressure, it means there is a leak, do it Check all joints with soapy water & mark
leaking part)
Lihat tekanan pada pressure gauge & catat setiap ada perubahan ( bila terjadi
penurunan tekanan berarti ada kebocoran, lakukan pengecekan semua joint dengan
air sabun & marking / beri tanda bagian yang bocor )
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

10. HYDRO TEST


a. Prepare the necessary Hydrostatic test equipment & make sure it is in good condition
& ready to use.
Siapkan peralatan Hydrostatic test yang diperlukan & pastikan dalam
keadaan baik & siap pakai
b. Perform a visual check for all joints (welding, flange, valve, etc.) on the pipe / tank that
will be tested & make sure it is ready to be tested
Lakukan visual chek untuk semua joint ( welding, flange, valve dll ) pada pipa / tanki
yang akan di test & pastikan siap dilakukan test
c. Check all connections to the equipment & make sure they are closed
Chek semua connection ke equipment & pastikan dalam kondisi tertutup
d. Put up a sign / safety sign & police line indicating moderate hydrostatic test was carried
out
Pasang tanda / safety sign & police line yang menunjukkan sedang dilakukan
hydrostatic test
e. Put up a sign that prohibits operating the valve, except by those who carry out a test
Pasang tanda larangan untuk mengoperasikan valve, kecuali oleh yang melakuakan
test
f. Perform a Hydrostatic test, with a testing pressure of 1.5 x work pressure
Lakukan Hydrostatic test, dengan pressure pengetesan 1.5 x tekanan kerja
g. Look at the pressure on the pressure gauge & note any changes (if there is a drop in
pressure, it means there is a leak, do it Check all joints & mark the parts that are
leaking/occurring seepage or water droplets
Lihat tekanan pada pressure gauge & catat setiap ada perubahan ( bila terjadi
penurunan tekanan berarti ada kebocoran, lakukan pengecekan semua joint & beri
tanda bagian yang bocor / terjadi rembesan atau tetesan air.

11. Remove skit & House keeping


Pemindahan skit & Bersih-Bersih
Work Method Statement
PRESSURE TEST

Doc No : MEP_P-006-WMS Revisi : 0

Attachment a) :

JOB SAFETY ANALYSIS


JOB SAFETY ANALYSIS
JOTUN NEW WATER BASED FACTORY PROJECT Submission No. : MEP_P-006-JSA
Type of Works (JENIS PEKERJAAN) :
JOB SAFETY ANALYSIS TANGGAL : 9 May 2024

For high hazard classification of work or unprepared work method HYDROTEST JAM: 08.00 - 18.00
digunakan untuk pekerjaan yang termasuk High Hazard atau pekerjaan yang
PIC (Petugas yang melakukan pekerjaan) Supervisor: Site Manager : Approved by (Disetujui Oleh) : (Area Owner)
belum ada prosedur kerja
PERUSAHAAN/ CONTRACTOR
Fajar Ariffudin L
PLANT(lokasi) : Checked by (Diperiksa Oleh) : (HSE STAFF ) Acknowledge by (Diketahui oleh ): (SHE)
PT TAIYO SINAR
All area
Anung S
WORK DESCRIPTION (DESKRIPSI PEKERJAAN ):

PRESSURE TEST

HIGH HAZARD WORK berikut harus dilengkapi dengan Ijin Kerja (Permit To Work):
v WORK AT HEIGHT HIGH HAZARD ELECTRICAL WORK HAZARDOUS LINE BREAKING GROUND DISTURBANCE V GENERAL
HOT WORK CONFINED SPACE ENTRY CRITICAL LIFTING OPERATION DEMOLITION

SCOPE OF WORKS RISK POTENTIAL RECOMMENDED CORRECTIVE ACTION


(PEKERJAAN YANG DILAKUKAN) (POTENSI BAHAYA) (REKOMENDASI TINDAKAN PERBAIKAN)

write down the steps taken from start to finish the work potential to cause injury, harm or environmental write down the steps taken to prevent injury or environmental pollution
(tuliskan langkah-langkah yang dilakukan mulai dari awal sampai pollution(potensi menimbulkan cedera, bahaya atau (tuliskan langkah-langkah yang dilakukan untuk mencegah terjadinya cedera atau
menyelesaikan pekerjaan) pencemaran lingkungan) pencemaran lingkungan)

1.Prepare PTW and Tool box meeting a. TBM shall conduct prior operation.
pembuatan PTW dan tool box meeting 1. Failure Document. TBM agar dilakukan sebelum memulai operasional.
Kegagalan Dokumen b. Correct method shall be brief to the workers on TBM.
Correct method agar di briefingkan kepada pekerja di TBM.
a. Ensure the activity to be closely monitor by the supervisor.
Pastikan kegiatan di awasi oleh supervisor
2.Trip, falls, Miss communication, fatique, low consentration of
b. Communication device shall be use.
worker.
Gunakan alat komunikasi yang sesuai
Tergelincir, terjatuh, Miss komunikasi, kelelahan, konsentrasi
c. Worker to report to their Supervisor when unfit.
pekerja rendah
Jika kondisi kesehatan kurang Fit, agar segera melaporkan kepada supervisor.
d. ERT available and ready to perform when emergency event happened
ERT tersedia dan siap sedia melakukan evacuasi jika ada kejadian emergency.
2.Tool Preparation tool a.Ensure the material placement is not in the working acces area
Pesiapan alat kerja pastikan penempatan material tidak di akses jalan
Tools : barricade, scaffolding material,hose water 1.Stumble b.Make sure to walk on pedestrian access
alat kerja : baricade, material scaffolding, selang air tersandung pastikan berjalan di akses pejalan kaki
c.consentrate and focus during work
konsentrasi,fokus saat bekerja
a. Use proper tools
Gunakan alat yang proper
b. Electrical tools must be check before it used. Make sure already inspected by Electrical
Spv with update tagging.
Peralatan listrik harus diperiksa sebelum digunakan. Pastikan sudah diperiksa oleh
Electrical Spv dengan update tagging.
c. Correct method shall be practice
2. Struck againts, pinch point Metode penanganan yang tepat agar di briefingkan kepada pekerja.
Terbentur, terjepit
d. Correct method shall be brief to the workers on TBM.
Correct method agar di briefingkan kepada pekerja di TBM
e. Maintain communication and coordination at all time between involves
party/personnel.
Komunikasi harus selalu tetap dijaga antara semua personil yang terlibat.

f. Use PPE mandatory ( helmet, safety glases, hand gloves, safety shoes
Gunakan APD wajib ( helmet, kacamata safety, sarung tangan, sepatu safety )
3. Install scaffolding a. Manual lifting of loads exceeding 25 Kg must be avoided and it is required to use
Pemasangan scaffolding mechanical lifting aids
Pengangkatan secara manual pada Beban melebihi 25 Kg harus dihindari dan disyaratkan
untuk menggunakan alat bantu angkat angkut mekanis

b. Ensure floors and access are free of potential slip hazards.


Pastikan lantai dan akses bebas dari potensi bahaya tergelincir.
1. Manual Handling c. Personnel must understand how to perform manual handling safely.
Pengangkatan manual Personil harus mengerti bagaimana melakukan penanganan manual dengan aman.
d. All materials are lifted and handled manually not to be placed on main roads and other
areas that can cause direct obstacles to roads that are often used for traffic.
Semua material diangkat dan ditangani secara manual tidak untuk ditempatkan di jalan
utama dan daerah lainnya yang dapat menyebabkan hambatan langsung jalan yang
sering di pakai untuk lalu lalang.

e. use PPE hand gloves


gunakan APD sarung tangan
a. All accesses used to reach the workplace must be effectively secured.
Semua akses yang digunakan untuk mencapai tempat kerja harus dijamin aman secara
efektif.
'2. Improper road access
Akses jalan yang tidak benar b. No work is performed on the scaffold if there is no proper, designated secure means of
access leading to the work platform.
Tidak ada pekerjaan yang dilakukan pada perancah jika tidak ada cara akses yang tepat,
ditunjuk aman mengarah ke platform kerja.
a. Install the scaffolding must be done by a scaffolder that has a valid license and is
declared suitable for use by the scaffold inspetor with OK tagging installed
pasang scaffolding harus dilakukan oleh scaffolder yang mempunyai lisensi yang masih
berlaku dan dinyatakan layak digunakan oleh inspetor scaffold dengan dipasang tagging
OK
b. All open sides of the platform where someone might fall from a height of 2 meters
must be barricaded, with handrails, second handrails, and toe boards attached.
Semua sisi yg terbuka dari platform dimana seseorang berkemungnkinan jatuh dari
ketinggian 2 meter harus di barikade,dengan handrail,second handrail,dan di pasang toe
board.
3. Fall from Scaffolding
Terjatuh dari Scaffolding c. Safety rope must be available when working at height as an additional safety if there is
no harness safety rope.
Tali lintasan pengaman harus tersedia saat bekerja diketinggian sebagai salah satu
tambahan penganman jika tidak terdapatnya penambatan tali pengaman harness.

d. Install barricades & Sign "Beware. Watch your step".


nstall barricade & Sign "Hati-hati. Awas jatuh"
e. All scaffolding workers working at height must wear a full body harness with a double
lanyard and always attach the hookoff at a secure point.
Semua pekerja perancah yg bekerja di ketinggian harus memakai full body harness
dengan
double lanyard dan selalu dan harus memasang hookoff pada titik aman.

a. To be aware of pinch point, sharp edges, etc.


Perhatikan titik terjepit, sisi yang tajam, dll
b. Ensure proper access is provided .
4. Body Injury. Pastikan access sudah tersedia
Cidera tubuh
c. Assess surrounding area.
Periksa area sekitar.
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai
a. fasten work tools when working at height
ikat alat kerja pada saat bekerja di ketinggian
b. Transfer material using rope
transfer material menggunakan tali
c. Store work tools in a safe place, store them in bags or boxes
simpan alat kerja di tempat yang aman , simpan dalam tas atau box
5. crushed by d. barricade work area and install sign “ awas benda jatuh “
tertimpa material baricade area kerja dan pasang sign “ awas benda jatuh “
e. Make sure to install the toe board on each scaffolding
pastikan pasang toe board pada setiap scaffolding
f. use blue net on the scaffolding
pasang blue net pada scaffolding
g. use PPE safety Helmet
gunakan helm safety
a. install scaffolding by scaffolder certificated and inspction scaffold by supervisor scaffold
, give tagging .
Pasang scaffolding oleh scaffolder bersertifikat dan diispecksi oleh supervisor scaffold
dan pasang tagging
b. All open sides of the platform where someone might fall from a height of 2 meters
must be barricaded, with handrails, second handrails, and toe boards attached.
Semua sisi yg terbuka dari platform dimana seseorang berkemungnkinan jatuh dari
ketinggian 2 meter harus di barikade,dengan handrail,second handrail,dan di pasang toe
6. Fall from Scaffolding c. Safety rope must be available when working at height as an additional safety if there is
Terjatuh dari Scaffolding no harness safety rope.
Tali lintasan pengaman harus tersedia saat bekerja diketinggian sebagai salah satu
tambahan penganman jika tidak terdapatnya penambatan tali pengaman harness.
d. Install barricades & Sign "Beware. Watch your step".
Install barricade & Sign "Hati-hati. Awas jatuh"
e. All scaffolding workers working at height must wear a full body harness with a double
lanyard and always attach the hookoff at a secure point.
Semua pekerja perancah yg bekerja di ketinggian harus memakai full body harness
dengan double lanyard dan selalu dan harus memasang hookoff pada titik aman.
a. install scaffolding on the floor level place
pasang scaffolding pada lantai yang rata
b. install scaffolding by scaffolder , inspected by supervisor scaffolding & give tagging
inspection
pasang scaffolding oleh scaffolder, inspeksi supervisor scaffolding dan pasang taging
7. scaffolding collaps. inspeksi
Scaffolding collaps c. Assess surrounding area.
Periksa area sekitar.

d. when using scaffolding , do lock stoper wheel scaffolder


ketika menggunakan scaffoding , lakukan kunci roda scaffolding
e. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai
4. use the ladder a. Pay attention to the position of the ladder should be in a flat and strong place
penggunaan tangga Perhatikan position tangga harus di tempat yang rata dan kuat

b. The ladder should be worth using and give tagging OK .


Tangga harus layak digunakan dan berikan taging
1. Fall from lader
c. Check the surrounding area &; make sure when using the ladder there are workers
terjatuh dari tangga
holding the ladder .
Periksa area sekitar.pastikan & saat pemakaian tangga ada pekerja yang memegangi
tangga
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE ( termasuk sarung tangan ) yang sesuai

a. The ladder should be worth using and give tagging OK .


Tangga harus layak digunakan dan berikan taging
2. ladder broken when use
b. ensure chek condition ladder before use
tangga patah saat digunakan
pastikan cek kondisi tangga sebelum digunakan

c. tadder for use only 1 personnel


tangga hanya ntuk 1 personel
5. Preparation work area persiapan area a.Ensure the material placement is not in the working acces area
kerja pastikan penempatan material tidak di akses jalan
tools : Compresor, hydro pump,hose water, etc b.Make sure to walk on pedestrian access
materials : kompresor , mesin pompa selang air dll 1.Stumble
pastikan berjalan di akses pejalan kaki
tersandung
c.consentrate and focus during work
konsentrasi,fokus saat bekerja
a. Make sure use proper compresor, hydro pump & give taging inspection
Pastikan kompresor l, meisn pompa layak digunakan & pasang taging inspeksi
b. Electrical tools must be check before it used. Make sure already inspected by Electrical
Spv with update tagging.
Peralatan listrik harus diperiksa sebelum digunakan. Pastikan sudah diperiksa oleh
Electrical Spv dengan update tagging.
c. Correct method shall be practice
2. Struck againts, pinch point
Metode penanganan yang tepat agar di briefingkan kepada pekerja.
Terbentur, terjepit
d. Correct method shall be brief to the workers on TBM.
Correct method agar di briefingkan kepada pekerja di TBM
e. Maintain communication and coordination at all time between involves
party/personnel.
Komunikasi harus selalu tetap dijaga antara semua personil yang terlibat.

f. Use PPE mandatory ( helmet, safety glases, hand gloves, safety shoes
Gunakan APD wajib ( helmet, kacamata safety, sarung tangan, sepatu safety )
6. hydrotest using hydro pump a. To be aware of pinch point, sharp edges, etc.
hridrotest menggunakan mesin pompa Perhatikan titik terjepit, sisi yang tajam, dll
Tools : hydro pump , hose etc b. Ensure proper access is provided .
alat kerja : mesin pompa, selang, dll Pastikan access sudah tersedia
c. Assess surrounding area.
1. Hand Injury. Periksa area sekitar.
Cidera tangan
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai

c. Assess surrounding area.


Periksa area sekitar.
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai
a. make sure the hose proper
pastikan selang layak
b. Ensure proper access is provided .
2.Body Injury.
Pastikan access sudah tersedia
Cidera tubuh
c. Assess surrounding area. & hose does not block access
Periksa area sekitar. & selang jangan menghalangi akses
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai
a. All scaffolding workers working at height must wear a full body harness with a double
lanyard and always attach the hookoff at a secure point.
Semua pekerja perancah yg bekerja di ketinggian harus memakai full body harness
dengan double lanyard dan selalu dan harus memasang hookoff pada titik aman.
b. All open sides of the platform where someone might fall from a height of 2 meters
must be barricaded, with handrails, second handrails, and toe boards attached.
Semua sisi yg terbuka dari platform dimana seseorang berkemungnkinan jatuh dari
3. Fall from Scaffolding
ketinggian 2 meter harus di barikade,dengan handrail,second handrail,dan di pasang toe
Terjatuh dari Scaffolding
board.
c. Safety rope must be available when working at height as an additional safety if there is
no harness safety rope.
Tali lintasan pengaman harus tersedia saat bekerja diketinggian sebagai salah satu
tambahan penganman jika tidak terdapatnya penambatan tali pengaman harness.
d. Install barricades & Sign "Beware. Watch your step".
Install barricade & Sign "Hati-hati. Awas jatuh"
a. transfer material using rope
transfer material menggunakan tali
b. Tie the material as it goes up.
Ikat material saat dinaikkan ke atas.

c. Correct method shall be practice


4. Got hit by material
Metode yang tepat agar di briefingkan kepada pekerja.
Tertimpa material

d. Correct method shall be brief to the workers on TBM.


Correct method agar di briefingkan kepada pekerja di TBM
e. Proper PPE shall be wear and fit correctly.
PPE yang tepat agar digunakan dengan benar
a. Pay attention to the position of the ladder should be in a flat and strong place
Perhatikan position tangga harus di tempat yang rata dan kuat
b. The ladder should be worth using and give tagging OK .
Tangga harus layak digunakan dan berikan taging
5. Fall from lader c. Check the surrounding area &; make sure when using the ladder there are workers
terjatuh dari tangga holding the ladder .
Periksa area sekitar.pastikan & saat pemakaian tangga ada pekerja yang memegangi
tangga
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE ( termasuk sarung tangan ) yang sesuai
a.Breifing worker about principle 5R
Lakukan breifing pekerja tentang prinsip 5R

6. Environment Issue b. Throw the trash into the trash bag


Issue Lingkungan Buanglah sampah ke plastik sampah
c. Dispose of garbage according to its classification
Buang sampah sesuai klasifikasinya

d. keep a safe distance during doing housekeeping with equipment


jaga jarak aman selama melakukan kebersihan dengan peralatan
7. pneumatictest work using compresor a. make sure the hose proper
pekerjaan hpneumatik test menggunakan kompresor pastikan selang layak
material : tube N2 b. Ensure proper access is provided .
Pastikan access sudah tersedia
c. Assess surrounding area. & hose does not block access
1. Hand Injury. Periksa area sekitar. & selang jangan menghalangi akses
Cidera tangan
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai
c. Assess surrounding area.
Periksa area sekitar.
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai
a. To be aware of pinch point, sharp edges, etc.
Perhatikan titik terjepit, sisi yang tajam, dll
b. Ensure proper access is provided .
2.Body Injury.
Pastikan access sudah tersedia
Cidera tubuh
c. Assess surrounding area.
Periksa area sekitar.
d. Ensure appropriate PPE is used (including hand gloves) prior to work.
Pastikan pekerja memakai PPE yang sesuai
a. All scaffolding workers working at height must wear a full body harness with a double
lanyard and always attach the hookoff at a secure point.
Semua pekerja perancah yg bekerja di ketinggian harus memakai full body harness
dengan double lanyard dan selalu dan harus memasang hookoff pada titik aman.

b. All open sides of the platform where someone might fall from a height of 2 meters
must be barricaded, with handrails, second handrails, and toe boards attached.
3. Fall from Scaffolding Semua sisi yg terbuka dari platform dimana seseorang berkemungnkinan jatuh dari
Terjatuh dari Scaffolding ketinggian 2 meter harus di barikade,dengan handrail,second handrail,dan di pasang toe
board.
c. Safety rope must be available when working at height as an additional safety if there is
no harness safety rope.
Tali lintasan pengaman harus tersedia saat bekerja diketinggian sebagai salah satu
tambahan penganman jika tidak terdapatnya penambatan tali pengaman harness.
d. Install barricades & Sign "Beware. Watch your step".
Install barricade & Sign "Hati-hati. Awas jatuh"
a.Ensure the material ( hose ) placement is not in the working acces area
pastikan penempatan material t( selang )idak di akses jalan
4.Stumble b.Make sure to walk on pedestrian access
tersandung pastikan berjalan di akses pejalan kaki
c.consentrate and focus during work
konsentrasi,fokus saat bekerja
a. Keep on safe distance
jaga jarak aman
b. Take coordination before open valve compresor
koordinasi sebelum buka valve kompresor
5. Hit by hose compresor c. one comand when open valve
kena selang compresor satu komando ketika buka valve
d. Correct method shall be brief to the workers on TBM.
Correct method agar di briefingkan kepada pekerja di TBM
e. Proper PPE shall be wear and fit correctly.
PPE yang tepat agar digunakan dengan benar
a. check condition power electrical with tespen
cek kondisi power listrik dengan tespen

b. Check all of electrical tool's that will be use


Periksa semua peralatan kelistrikan yang akan digunakan
c. Make sure use proper compresor & give taging inspection
Pastikan kompresor layak digunakan & pasang taging inspeksi
d. Provided adequate lighting and ventilation
Penerangan dan ventilasi yang cukup agar disediakan
e. Inspected electrical tools shall be use.
6. Electrical Shocked. Periksa semua peralatan kelistrikan yang akan digunakan.
Kesetrum f . Install cable to hanging cable
pasang kabel pada gantungan kabel
g. baricade work area and install warning sign " awas kesetrum "
baricade area kerja dan pasang warning sign "awas kesetrum"

h. if do conection electrical is carried out by certified workers who are still valid (K3
electrical)
jika adakoneksi listrik dilakukan oleh pekerja bersertifikat yang masih berlaku ( K3 listrik
)
i. Proper PPE shall be wear and fit correctly.
Proper PPE agar digunakan dan dipasang dengan tepat
1. Make sure the condition of the tube is firmly bonded using a chain
pastikan kondisi tabung terikat kuat menggunakan rantai

2. use troly when transfer tube


7. drop tube gunakan troli saat transfer tabung
tabung jatuh
3. install place tube using pipe/steel
pasang tempat tabung menggunakan pipa / besi
4. cover tube must be install to tube
penutup tabung harus terpasang pada tabung
a.Breifing worker about principle 5R
Lakukan breifing pekerja tentang prinsip 5R
b. Throw the trash into the trash bag
8. Environment Issue
Buanglah sampah ke plastik sampah
Issue Lingkungan
c. Dispose of garbage according to its classification
Buang sampah sesuai klasifikasinya

d. keep a safe distance during doing housekeeping with equipment


jaga jarak aman selama melakukan kebersihan dengan peralatan
8. Cleaning work area
Pembersihan area kerja a.Breifing worker about principle 5R
Lakukan breifing pekerja tentang prinsip 5R

1. Environment Issue b. Throw the trash into the trash bag


Issue Lingkungan Buanglah sampah ke plastik sampah

c. Dispose of garbage according to its classification


Buang sampah sesuai klasifikasinya

d. keep a safe distance during doing housekeeping with equipment


jaga jarak aman selama melakukan kebersihan dengan peralatan

2. Struck by dust a. Proper PPE to be worn (safety glass, hand gloves, , Mask, etc).
Mata kelilipan debu Proper PPE agar dipakai (Safety glasess, hand glove, ear plugs, masker, dll)
a. organize it materials and tools into the tool box
3. Hand Injury rapikan material dan alat
Tangan terluka
b. Concentration
konsentrasi

c. Use PPE hand gloves


gunakan APD sarung tangan
Document No. : WI-038
INSTRUKSI KERJA Revision No. : 00

PEKERJAAN TESTING Revised on : 01 Aug. 2007


Taiyo Sinar
( HYDROSTATIC )
Gambar
A. URUTAN KERJA
Siapkan peralatan Hydrostatic test yang diperlukan & pastikan dalam
1 Siapkan peralatan Hydrostatic test yang diperlukan & pastikan dalam
keadaan baik & siap pakai
2 Lakukan visual chek untuk semua joint ( welding, flange, valve dll )
pada pipa / tanki yang akan di test & pastikan siap dilakukan test
3 Chek semua connection ke equipment & pastikan dalam kondisi tertutup
4 Pasang tanda / safety sign & police line yang menunjukkan sedang
dilakukan hydrostatic test
5 Pasang tanda larangan untuk mengoperasikan valve, kecuali oleh yang
melakuakan test
6 Lakukan Hydrostatic test, dengan pressure pengetesan 1.5 x
tekanan kerja
7 Lihat tekanan pada pressure gauge & catat setiap ada perubahan
( bila terjadi penurunan tekanan berarti ada kebocoran, lakukan
pengecekan semua joint & beri tanda bagian yang bocor / terjadi
rembesan atau tetesan air ).

B. HAL-HAL YANG PERLU DIPERHATIKAN

1 Selama test berlangsung, harus selalu dalam pengawasan


2 Tidak diperbolehkan meninggalkan pipa / tanki yang sedang
di test, dalam keadaan bertekanan
3 Selama melakukan test harus tetap menggunakan APD yang sesuai
4 Pengambilan dokumen harus menggunakan kamera ( tidak
diperkenankan menggunakan kamera HP )
5 Harus ada yang menjaga jangan sampai ada personil lain / pekerja
lain yang mendekati police line tersebut beri tulisan " Awas ada
pengetesan pipa / tanki bertekanan tinggi ".
6 Pada waktu pemeriksaan pada bagian flange, jangan segaris lurus
dengan joint flange tersebut.
Document No. : WI-039
INSTRUKSI KERJA Revision No. : 00

PEKERJAAN TESTING Revised on : 01 Aug. 2007


Taiyo Sinar
( PNEUMATIC )
Gambar
A. URUTAN KERJA

1 Siapkan peralatan compressor & N2 Bottle ( jika diperlukan ) & pastikan


dalam keadaan baik & siap pakai
2 Lakukan visual chek untuk semua joint ( welding, flange, valve dll )
pada pipa / tanki yang akan ditest & pastikan siap dilakukan test
3 Chek semua connection ke equipment & pastikan dalam kondisi tertutup
4 Pasang tanda / safety sign & police line yang menunjukkan sedang
dilakukan pneumatic test
5 Pasang tanda larangan untuk mengoperasikan valve, kecuali oleh yang
melakukan test
6 Lakukan pneumatic test, dengan pressure pengetesan 1.5 x
tekanan kerja
7 Lihat tekanan pada pressure gauge & catat setiap ada perubahan
( bila terjadi penurunan tekanan berarti ada kebocoran, lakukan
pengecekan semua joint dengan air sabun & marking / beri tanda
bagian yang bocor )

B. HAL-HAL YANG PERLU DIPERHATIKAN

HATI - HATI !!!!


ADA 1 Selama test berlangsung, harus selalu dalam pengawasan
PENGETESAN 2 Tidak diperbolehkan meninggalkan pipa / tanki yang sedang
PIPA di test, dalam keadaan bertekanan
3 Selama melakukan test harus tetap menggunakan APD yang sesuai
4 Jika pengetesan dengan menggunakan compressor & N2, maka
penambahan tekanan yang di supply dari bottle N2 harus pelan - pelan
& dilakukan oleh pekerja yang berpengalaman
5 Apabila ada kebocoran & perlu perbaikan dengan las, tekanan harus
di buang & usahakan sampai Nol
6 Pada waktu pengecekan kebocoran dengan cairan sabun pada
setiap sambungan flange / las harus menggunakan pelindung mata
7 Apabila pengetesan selesai, cara pembuangan udara bertekanan harus
pelan - pelan
& bila difungsikan sebagai flushing, harus bebas dari pekerja lain
di sekitarnya.
WORKING INSTRUCTION Disahkan oleh Diperiksa oleh Dibuat oleh

PENGUJIAN HYDROTEST DENGAN PRESSURE


CHART RECORDER

Plant Division
Jun Sano Suryanto Dedi Kartiwa

Doc No. :WI-PL-3002 Revisi No. : 0 Effective : 17 Desember 2011


TAIYO SINAR (Plant Div. Head) (General Manager) (QA/QC Manager)

Urutan Pekerjaan Pengujian Hydrotest

P1 P2

1.Lakukanlah Line check sesuai dengan Gambar ISO 2.Persipakan material dan alat-alat hydrotest dan 3.Buat Chart Digram Hydrotest pressure dan spesifikasi
Metric dan pastikan semua part telah terpasanag, lalu pastikan tidak ada sambungna las atau flange yang pengujian sesuai persyaratan line tersebut, lalu buatlah
buatlah Diagram Schematic Line yang akan di test belum tersambung dengan baik. ijin kerja dan persetujuan dari pihak client dan owner.

a Perhatian !

1. Jika terjadi penuruan tekanan akibat kebocoran


sambungan , maka buang terlebih dahulu air dalam pipa
lalu lakukan perbaikan, pastikan sudah disetujui oleh
client.

2. Ulangi pengujian tersebut hingga dipastikan tidak


terjadi penurunan akibat kebocorans ambungan.

3.Buatlah Laporan hasil pengujian dan mintalah


persetujuan dari client dan owner.

4.Pasang Manifold dan Presssure gauge, lalu sambungkan 5.Lakukan Pressure secara perlahan hingga mencapai holding pressure,
kep semua mesin pompa pastikan sambungan telah kencang lalu perhatikan recorder dan semua pressure indicator.Pastikan tidak ada
dan kuat. Isilah pipa dengan air , lalu tutup semua valve. penururan tekanan akibat kebocoran sabungan.
Reference : Date Revision Item Revised Rev .No.
17-Dec-11 Initial release 0