Professional Documents
Culture Documents
DPR 30 11 10
DPR 30 11 10
400 KV SWITCHYARD
Circuit Breaker with PIR Structure Erection Equipment Erection 2 Circuit Breaker without PIR Structure Erection Equipment Erection 3 CVTs Structure Erection Equipment Erection 4 EMVT Structure Erection Equipment Erection 5 Current Transformers 5a 5-Core Structure Erection Equipment Erection 5b 4-Core Structure Erection Equipment Erection 5c 2-Core Structure Erection Equipment Erection 6 Lighting Arrestor Structure Erection Equipment Erection 7 Pantograph Structure Erection Equipment Erection 8 Isolator Structure Erection Equipment Erection 9 Bus Post Insulators (H/L) Structure Erection Equipment Erection 10 Bus Post Insulators (L/L) Structure Erection Equipment Erection 11 Wave Trap Structure Erection
8 8 5 5 20 20 12 12
4 4 2 1 13 13 5 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
4 4 2 1 0 13 13 0 5 0
4 4 3 4 0 7 7 0 7 12
54 54 12 12 12 12 33 33 45 45 23 23 298 298 166 166 8 8 18 32 6 21 9 16 14 1 2400 3500 3000 4 2 12 7150 15.9 1 1 1 1 2 1 1 11 620 1
0 0 0 0 0 0 0 0 0 0 0 1 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 1 6 8 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Work in progress
Material is awaited
Material is awaited
Equipment unavailable 6 Nos of isolator alignment completed. Double E/S Isiolator erection work progress. HBPI structure assembly in progress & Fixing of clamps on the already erected BPI equipment in progress Erection work in progress
Nos Set Nos Nos Nos. Nos. Nos Nos. Nos Nos Nos Nos. Nos. Nos. No. of Span Lot Mtr Mtr Mtr. Nos. Set Nos Mtr KM Set Set Set Set Set Lot Set Nos Mtr Set
Earthing STR/EQI 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 1
Erection of Towers Tower T 1 Tower T 2 Tower T X Lighting Mast Beam B1 Beam B2 Twin moose conductor stringing Jumpering & connections Al Bus Bars 4" Al Bus Bars 4.5" Shield wire stringing Erection of AC Kiosk Erection of PLCC Erection of relay Panels Cable Tray Erection & Fabrication Cable Laying (Power & Control) Erection of battery 220V Erection of battery 48 V Erection of battery charger 220V Erection of battery charger 48V Erection of SAS & UPS Erection of 48 V & 220 V DCDB Erection of 415 V & Emergency ACDB Erection of 33 KV Panels Cable Tray Erection & Fabrication AC & Ventilation System 250MVA Trafo(GT) Trafo Erection Oil filtration with Vaccum 70/45/20 MVA Trafo(ST) Trafo Erection Oil filtration with Vaccum 45MVA Trafo(UT) Trafo Erection Oil filtration with Vaccum 10MVA Trafo Trafo Erection Oil filtration with Vaccum 16MVA Trafo(UAT) Trafo Erection Oil filtration with Vaccum 2.5MVA Trafo Trafo Erection Oil filtration with Vaccum 2 MVA Trafo Trafo Erection Oil filtration with Vaccum 150 KVA Trafo Trafo Erection Oil filtration with Vaccum 80 MVAR Bus Reactor
Earthing of the towers in progress Remaining fnds in progress 7 LMs charged Beam at the 400 KV side already completed
Al welding work in progress Bus erection work start from Monday Work in progress Material unavailable Material awaited AC KIOSK is not ready Including Switchyard,Transfoyard & swyd control Room Civil work is not completed Civil work is not completed Civil work is not completed Civil work is not completed Civil work is not completed Civil work is not completed Civil work is not completed Civil work is not completed Civil work is not completed Civil work is not completed
TRANSFORMER YARD
Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos KM
KM Nos Nos KM Nos Nos Nos Nos Nos Nos Nos Nos KM
7 7 2 2
2 0 2 0
0 0 0 0
0 0 0 0
2 0 0 2 0 0 4 0 0 0 0 0 4 0 0 0 0 0 0 0 0 0 0 0 11 11 22 0
5 7 0 2
4 0 0 0 4 0 0 0 0 0 0 0 0 11 11 22 0 0 0 0 0 130
0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 Nos Transformer erected with accesseries and for 1 more under progress
9 10
Earthing
Switchyard area
11 1 2 3 4 5 6
Untreated pit Treated pit No of Risers Details Survey Check Survey Foundation Structure Erection Tower Earthing Conductor Strining
47 29 21 0
0 0 0 145
49 30 21 0
20 38 46 22.5
8.) Foundation rectification work in progress 9.)Unit Transformer auxiliary erection in progress 10.) GT#3 reached site