AYUSH NIRMAN SEWA PVT.LTD.
BHAIRAHAWA -8, RUPANDEHI, NEPAL.
Summery of Cube Test Reports RA-02
Project:-Litmus Cables ,Hukai
SN Structure Location 7 Days(Mpa)- 28 Days(Mpa)- Remarks
Concrete Casting Date Avg. Avg.
1 Security Houses Footing-9 No's 3/5/24 28.09 30.33
2 Scrap Yard Footing-12 No's 10/5/24 32.10 32.32
3 Security Houses Column 1st Lift-9 No's 16/5/2024 28.74 38.55
4 Scrap Yard Column 1st Lift-6 No's 18/5/2024 26.48 29.87
5 Scrap Yard Column 1st Lift-6 No's 20/5/2024 17.69 26.64
6 CCR Footing(F1-2 no's & F2-2 no's) 31/5/2024 26.83
7 Scrap Yard Column 2nd Lift-12 No's 31/5/2025 26.00
8 CCR Footing(F3-2 no's ) 1/6/26 33.76
Prepared By:- Checked By:- Approved By:-
Prepared By:- Checked By:- Approved By:-
AYUSH NIRMAN SEWA PVT.LTD.
BHAIRAHAWA -8, RUPANDEHI, NEPAL.
Client Name: Litmus industris limited
Project Name:-Litmus 2.0 ,Hukui RA-07
SN Structure Location Grade 7 Days(Mpa)- 28 Days(Mpa)- Remarks
Concrete Casting Date Avg. Avg.
1 Security Houses Footing M25 3/5/24 28.09 30.33
2 Scrap Yard Footing M25 10/5/24 32.10 32.32
3 Security Houses Column M25 16/5/2024 28.74 38.55
4 Scrap Yard Column M25 18/5/2024 26.48 29.87
5 Scrap Yard Column M25 20/5/2024 17.69 26.64
6 CCR Footing M25 31/5/2024 26.83 32.31
7 Scrap Yard Column M25 31/5/2024 26.00 32.06
8 CCR Footing M25 1/6/24 33.76 41.55
9 CCR Footing M25 3/6/24 23.38 31.67
10 CCR Footing M25 4/6/24 25.97 34.70
11 CCR Footing M25 6/6/24 28.59 35.24
12 CCR Footing M25 8/6/24 21.45 28.73
13 CCR Footing M25 10/6/24 27.77 31.57
14 CCR PD M25 12/6/24 24.22 31.26
15 CCR PD M25 15/06/2024 28.07 30.83
16 CCR PD M25 15/06/2024 24.02 31.26
17 Quenching Tank Shear Wall 1st Lift M25 15/06/2024 26.68 33.82
18 CCR PD M25 18/06/2024 30.00 32.66
19 Security Houses PB M25 18/06/2024 31.78 33.20
20 Quenching Tank Raft M25 18/06/2024 30.24 34.94
21 CCR PD M25 19/06/2024 29.99 32.30
22 Quenching Tank Shear Wall M25 21/06/2024 24.37 37.15
23 CCR Footing M25 24/06/2024 29.21 37.51
24 Scrap Yard PB M25 24/06/2024 29.09 32.52
25 CCR PD M25 24/06/2024 25.38 34.03
26 CCR Footing M25 25/06/2024 28.29 36.94
27 Quenching Tank Shear Wall M25 25/06/2024 26.80 34.13
28 CCR Footing M25 29/06/2024 23.32 33.41
29 CCR Footing M25 29/06/2024 23.32 33.41
30 CCR Footing M25 29/06/2024 25.42 35.78
31 Security Houses Column M25 1/7/24 24.71 31.97
32 CCR PD M25 1/7/24 24.39 29.94
33 Quenching Tank Shear Wall M25 2/7/24 30.03 34.68
34 Security Houses Column M25 2/7/24 26.52 31.31
35 Scrap Yard Column M25 7/7/24 19.23 32.01
36 CCR PD M25 7/7/24 20.22 30.55
37 Security Houses Column M25 9/7/24 21.48 29.97
38 CCR PD M25 7/9/24 22.56 32.03
39 Scrap Yard Column M25 7/13/24 24.34 30.75
40 CCR PD M25 7/13/24 23.24 31.06
41 CCR PD M25 7/14/24 27.33 34.01
42 CCR PD M25 7/15/24 28.56 33.02
43 Quenching Tank Raft M25 7/16/24 32.92 40.73
44 Returning tank M10 19/07/2024 12.17 19.31
45 emulsion pool raft M25 22/07/2024 21.24 32.75
46 CCR Footing A5,6,7 M25 23/7/2024 31.64 33.24
47 Security Houses slab M25 24/7/2024 24.71 33.97
48 utility tank 150kl raft M25 26/7/2024 28.26 33.09
49 CCR pedestal G A 5,6,7 M25 26/7/2024 29.88 36.71
50 Substation Footing grid B4,3 M30 26/07/2024 26.36 36.18
51 Quenching Tank wall 1/2 nd lift M25 27/7/2024 29.74 33.04
52 CCR pedestal GA 2,3,4,b1,d,e1,2,3,4 M25 29/7/2024 21.78 31.98
53 Substation footing B5,a4 M30 29/7/2024 26.01 34.02
54 CCR pedestal A5,6,7 & A1 M25 31/7/2024 26.43 31.98
55 CCR pedestal grid E 5,6,7,8,9,10,11,13 M25 3/8/2024 29.3 31.62
56 Substation footing grid B4,A1 M30 3/8/2024 30.82 35.64
57 Substation footing M30 4/8/2024 32.28 37.02
58 CCR pedestal M25 4/8/2024 23.86 32.91
59 CCR grid A 8,9,,10,11,12 M25 6/8/2024 31.09 36.41
60 CCR grid A6,7,beam grid E M25 8/8/2024 29.22 36.93 28 days test at third party lab
Submitted By:- Checked By:- Approved By:-
35.72
61 ccr & substation sb-grid 1,2,3 footing & plinth beam ccr M30 9/8/2024 34.46
62 Substation B4 column,grid A 1,2,3 & footing GA5,GB5 M30 10/8/2024 29.35 36.99
63 CCR Grid B plinth beam from 4 to 6 column M30 11/8/2024 30.91 38.34
64 CCR plinth beam GA 1 to 4 G1 A to D M25 13/8/2024 24.23 35.70
65 Quenching pool shear wall M25 14/8/2024 28.12 40.38 microsilica used in concrete
66 Substation column GA 4,5 GB5 M30 14/8/2024 32.24 36.25
67 CCR Plinth beam GE 6 to 10 & G1 3 tot 4 M25 15/8/2024 23.63 36.14
68 CCR plinth beam G.e 10 to 13 M25 16/8/2024 24.27 32.84
69 CCR plinth beam GE M25 18/8/2024 23.78 31.71
70 Substation Plinth beam M30 28/8/2024 24.19 33.67
71 utility tank 150kl shear wall M25 28/8/2024 20.17 29.06 microsilica used in concrete
column grid E 1 to 3 & plinth beam G A 4 to
72 CCR 7 M25 29/8/2024 26.91 29.69 7 days test at third party lab
plinth beam 7 to 8 column of GA & column
73 CCR 2,3 M25 30/8/204 22.42 33.58
column GE 1,7,8,9,10, & footing of extenal
74 CCR column & scrap yard top 0.7m G2 M25 31/8/2024 22.53 30.25
substation column Gb 1,2,3,4,5 & ccr GE
75 Substation & CCR 11,12, G12D,GA 3column M30 2/9/2024 25.77 33.69
sb-grid A 1,2,3,4,5 & ccr GA 10,11,12 &
76 Substation & CCR Scrap yard 0.7m G1 All M30 04/09/204 23.477 34.73
77 CCR Grid A 6,7,8,9,13, Grid 13 B COLUMN M25 05/9/202 24.85 30.26
Plinth beam Grid 13 & Substation Column
78 ccr & substation 2nd lift grid B 1,2,3,4,5 M30 7/9/2024 24.13 32.61
79 Substation Column 2nd lift grid A 1,2,3,4,5 M30 8/9/2024 25.88 35.56
80 utility tank 150kl Shear wall 2nd lift & CCR toilet plinth beam M25 10.09.2024 22.84 30.02
81 emulsion pool Shear wall 3rd lift & CCR toilet column 2 nos M25 15.9.2024 24.59 32.185
82 HT Room Footing F1 M25 19.9.2024 19.67 29.33
83 HT Room Footing F2 M25 20.9.2024 24.53 31.15
84 HT Room Column C1,C2 M25 22.9.2024 18.40 26.13
85 Chimaney Footing M25 25.9.2024 21.378 26.12
86 utility tank 150kl Shear wall 3rd lift M25 26.9.2024 29.616 41.49
87 Substation Slab M25 05.10.2024 24.35 30.67
88 CCR Building toilet slab M25 05.10.2024 20.39 30.46
89 HT Room Column C3,C4 M25 06.10.2024 24.62 33.037
90 Chimaney platform M25 06.10.2024 25.01 32.72
91 RO Tank Raft M25 07.10.2024 18.50 29.5
92 utility tank 150kl Final lift M25 09.10.2024 22.77 29.59
93 FO Tank Raft M25 16.10.2024 20.84 28.81
94 Scrap Yard Flooring M25 16.10.2024 22.97 28.76
Lintel beam grid A 12-13 & Grid 13 A-B ,grid
95 CCR Building E 1-2,Grid 1 D-E M25 18.10.2024 26.98 30.41 7 days test at third party lab
96 RO Tank Shear Wall 1st Lift M25 21.10.2024 23.76 28.718
97 HT Room Lower tie beam M25 21.10.2024 24.95 31.48
98 Scrap Yard Ramp beam & CCR grid 1 A to B M25 23.10.2024 24.10 31.12
99 HT Room Column C1,C2,C3,C4 & CCR Lintel beam M25 24.10.2024 20.99 31.71
100 CCR Building Lintel beam grid E M25 26.10.2024 24.103 30.1
101 Scrap Yard Ramp flooring M25 26.10.2024 27.82 27.67
102 Machine foundation Raft M25 26.10.2024 24.011 33.33
103 Security Houses RCC flooring M25 27.10.2024 20.38 27.75
104 CCR Building Lintel beam grid E M25 27.10.2024 22.45 29.20
105 CCR Building Lintel beam grid E M25 27.10.2024 23.10 28.15
106 HT Room Tie beam M25 28.10.2024 21.38 27.53
107 DG Foundation Raft M25 29.10.2024 29.13 32.45
108 Machine foundation Raft M25 29.10.2024 26.04 32.86
109 Machine foundation Shear wall 18.11.2024 21.174
110 HT Room Trench Raft & Column C1 & C2 20.11.2024 19.60
111 Machine foundation Top Layer & furnace Raft 22.11.2024 24.79
Submitted By:- Checked By:- Approved By:-
Submitted By:- Checked By:- Approved By:-