Professional Documents
Culture Documents
Activity Based Costing Assignment
Activity Based Costing Assignment
Objectives of Activity Based Costing: The primary of objective of ABC systems are as follows: 1) To improve the accuracy of product costs by carefully changing the type and number of factors used to assign costs
1
Methodology
Direct labor and materials are relatively easy to trace directly to products, but it is more difficult to directly allocate indirect costs to products. Where products use common resources differently, some sort of weighting is needed in the cost allocation process. The measure of the use of a shared activity by each of the products is known as the cost driver. For example, the cost of the activity of bank tellers can be attributed to each product by measuring how long each product's transactions takes at the counter and then by measuring the number of each type of transaction.
ABC can be defined by the following equation: C/A = HD + M + E + S where C/A = Estimated cost per activity H = Number of labour hours required to perform the activity one time D = Wages per labour hour M = Material costs required to perform the activity one time E = Equipment costs to perform the activity one time S = Subcontracting costs to perform the activity one time
Limitations
y
Even in activity-based costing, some overhead costs are difficult to assign to products and customers, for example the chief executive's salary. These costs are termed 'business sustaining' and are not assigned to products and customers because there is no meaningful method. This lump of unallocated overhead costs must nevertheless be met by contributions from each of the products, but it is not as large as the overhead costs before ABC is employed. Although some may argue that costs untraceable to activities should be "arbitrarily allocated" to products, it is important to realize that the only purpose of ABC is to provide information to management. Therefore, there is no reason to assign any cost in an arbitrary manner.
ABC methodology is used when a project can be divided into defined activities. These activities are at the lowest function level of a project at which costs are
y y
y y
tracked and performance is evaluated. Depending on the project organization, the activity may coincide with an element of the work breakdown structure (WBS) or may combine one or more elements of the WBS. However, the activities must be defined so there is no overlap between them. After the activity is defined, the unit of work is established. All costs for the activity are estimated using the unit of work. The estimates for the units of work can be done by performing detailed estimates, using cost estimating relationships, obtaining outside quotes for equipment, etc. All costs including overhead, profit, and mark-ups should be included in the activity cost. It helps to identify inefficient product, department and activity It helps to allocate more resources on profitable product, department and activity It helps to control the cost at individual level and on departmental level It helps to find unnecessary costs
Identification of Activities
y
When defining an individual activity, the cost estimator must balance the need for accuracy with the amount of time available to prepare the estimate. An estimator may be able to develop an extremely accurate cost estimate by defining smaller and smaller activities; however, the amount of time required to prepare ABC estimates for each of these activities may not justify the increased accuracy. The total estimated project cost may be sufficiently accurate if 10 activities are used instead of 15. On the other hand, reliable cost information may not be accessible if the activity categories are too general. Since the activity is the basis for the estimate, it is very important that the activity be selected correctly.