BSR Standard Data 2013 02 04 03 13
BSR Standard Data 2013 02 04 03 13
SUPERINTENDING ENGINEER
PUBLIC WORKS DEPARTMENT
NATIONAL HIGHWAY, CIRCLE JAIPUR
INDEX
CHAPTER-11 HORTICULTURE
CHAPTER-12 FOUNDATIONS
CHAPTER-13 SUB-STRUCTURE
CHAPTER-14 SUPER-STRUCTURE
CHAPTER-11 HORTICULTURE
11.08
CHAPTER-12 FOUNDATIONS
9.87
CHAPTER-13 SUB-STRUCTURE
8.85
CHAPTER-14 SUPER-STRUCTURE
8.79
LEAD CHART
NOTE: Part of Km beyond 1Km will be treated as under :
1.499=1.00 Km; 1.500 Km = 2.00 Km.
Rates
1.10.1 Up to 50 Kg. Each - - - 5.0 0.0 6.0 0.0 8.0 0.0 9.0 0.0 11.0
1.10.2 51 to 70 Kg. Each - - - 7.0 0.0 8.0 0.0 10.0 0.0 12.0 0.0 11.0
1.10.3 71 to 100 Kg. Each - - - 8.0 1.0 11.0 0.0 12.0 0.0 14.0 0.0 11.0
1.11 RCC Hume Pipe with Collar - - - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 11.0
1.11.1 Dia 300 mm Meter - - 20.0 24.0 1.0 27.0 0.0 28.0 0.0 30.0 0.0 11.0
1.11.2 Dia 600 mm Meter - - 54.0 57.0 1.0 62.0 1.0 69.0 1.0 78.0 1.0 11.0
1.11.3 Dia 900 mm Meter - - 134.0 143.0 3.0 153.0 2.0 164.0 2.0 182.0 1.0 11.0
1.11.4 Dia 1200 mm Meter - - 167.0 185.0 3.0 198.0 3.0 212.0 2.0 230.0 1.0 11.0
Average Increage % 11.0
1
CHAPTER :
PART - "B" ROAD MATERIALS & THEIR CARRIAGE
R-1
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
PART - A CARRIAGE OF MATERIALS
Carriage of Bitumen mixed material from Hot Mix
1.12
Plant in Tipper to Paver Finisher
For the first km. (rate is included in the respective
1.12.1
item).
1.12.2 Add for each subsequent Km. Lead
[Link] 2nd Km. Up to 10 Km. Cum/KM. 3.80 3.40 12.0
[Link] 11th Km. Up to 20 Km Cum/KM. 3.20 2.90 10.0
[Link] Beyond 20 Km Cum/KM. 2.90 2.60 12.0
Loading in or unloading cement of the railway
wagons at siding and carrying the same from or
into god owns adjacent to the viding including
1.13 stacking the same properly in rows up to any height M.T. 33.30 30.00 11.0
as per direction of Engineer in-charge sweeping
the wagons and screening the swept cement and
filling in bags complete
2
CHAPTER :
PART - "B" ROAD MATERIALS & THEIR CARRIAGE
R-1
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
1.19 Collection of crusher dust Cum 222.00 200.00 11.0
Average Increage % 11.1
3
CHAPTER :
SITE CLEARANCE & DISMANTLING
R-2
Item No. Item Description
%
Rate (Rs.) increase
Unit Rate (Rs.)
2012 over
BSR-2012
2.1.1 (i) Girth from 300 mm to 600 mm Each 194.00 172.00 13.0
2.1.2 (ii) Girth from 600 mm to 900 mm Each 330.00 293.00 13.0
2.1.3 (iii) Girth from 900 mm to 1800 mm Each 667.00 593.00 12.0
2.1.4 (iv) Girth above 1800 mm Each 1287.00 1143.00 13.0
Clearing grass and removal of rubbish maximum
2.2 150mm up to a distance of 100 Meter outside the Hectare 14339.00 12705.00 13.0
periphery of the area by manual means.
Note : where only grass is met with , the area clear
shall be measured & paid for under this item
(MoRTH clause 201 )
Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs,
saplings and trees girth up to 300 mm, removal of
stumps of trees cut earlier and disposal of
2.3 unserviceable materials and stacking of
serviceable material up to a lead of 1000m
including removal and disposal of top organic soil
not exceeding in 150 mm thickness as per MoRTH
specification clause 201
2.4.1 Concrete
[Link] By Manual Means.
Lime concrete, cement concrete grade M-10 and
[Link].1 Cum 280.00 249.00 12.0
below
[Link].2 Cement concrete grade M-15 & M-20. Cum 337.00 300.00 12.0
Pre-stressed/ reinforced cement concrete grade M-
[Link].3 Cum 941.00 832.00 13.0
20 & above
3
CHAPTER :
SITE CLEARANCE & DISMANTLING
R-2
Item No. Item Description
%
Rate (Rs.) increase
Unit Rate (Rs.)
2012 over
BSR-2012
4
CHAPTER :
SITE CLEARANCE & DISMANTLING
R-2
Item No. Item Description
%
Rate (Rs.) increase
Unit Rate (Rs.)
2012 over
BSR-2012
5
CHAPTER :
SITE CLEARANCE & DISMANTLING
R-2
Item No. Item Description
%
Rate (Rs.) increase
Unit Rate (Rs.)
2012 over
BSR-2012
6
12
CHAPTER :
EARTH WORK, EROSION CONTROL AND DRAINAGE FOR ROADS
R-3
Item Description
% increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over BSR-
2012
2012
12
13
CHAPTER :
EARTH WORK, EROSION CONTROL AND DRAINAGE FOR ROADS
R-3
Item Description
% increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over BSR-
2012
2012
13
14
CHAPTER :
EARTH WORK, EROSION CONTROL AND DRAINAGE FOR ROADS
R-3
Item Description
% increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over BSR-
2012
2012
14
15
CHAPTER :
EARTH WORK, EROSION CONTROL AND DRAINAGE FOR ROADS
R-3
Item Description
% increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over BSR-
2012
2012
15
16
CHAPTER :
EARTH WORK, EROSION CONTROL AND DRAINAGE FOR ROADS
R-3
Item Description
% increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over BSR-
2012
2012
16
17
CHAPTER :
EARTH WORK, EROSION CONTROL AND DRAINAGE FOR ROADS
R-3
Item Description
% increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over BSR-
2012
2012
17
CHAPTER :
SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS
R-4
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Providing laying, spreading and compacting inverted
choke of specified graded aggregate in sub base
course in uniform layer on a prepared base with
4.1 motor grader and compacting with power roller etc.(by Cum 401.00 349.00 15
mechanical means).[MoRTH Specification : Clause
404.3.2.]
18
CHAPTER :
SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS
R-4
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Construction of granular sub-base by providing
coarse graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix
4.4 in place method with rotavator at OMC, and
compacting with vibratory roller to achieve the desired
density, complete as per clause 401.
4.6.1 Lime Treated Soil for Sub- Base Cum 438.00 394.00 11
Cement Treated Soil Sub Base with 4% qty of cement
4.6.2 Cum 666.00 627.00
by wt. of soil
Construction of sub-base using lime- Fly ash
admixture with granular soil, free from organic matter/
deleterious material or clayey silts and low plasticity
4.7 clays having PI between 5 and 20 and liquid limit less Cum 450.00 409.00 10
than 25 and commercial dry lime (slacked)
19
CHAPTER :
SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS
R-4
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Providing, laying, spreading and compacting stone
aggregate of specific sizes as per table 400-7 to
Water Bound Macadam specification including
spreading in uniform thickness, hand packing rolling
with vibratory roller in stages to proper grade and
camber, applying and brooming requisite type of
screening and binding materials to fill up the
4.8 interstices of coarse aggregates watering (with water
browser) and rolling, making necessary earthen bund
to protect edges, lighting, guarding, barricading and
maintenance of diversion etc. [MoRTH specification :
Clause 404] ( By manual means).
20
CHAPTER :
SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS
R-4
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
4.12
Construction of footpath/ separator by providing a 150
mm compacted granular sub- base as per Clause 401 Sqm 412.00 375.00 10
and 25 mm thick cement concrete grade M-15, over
laid with precast concrete tiles 300x300x25 mm in
cement mortar 1:3 including provision of all drainage
4.13
Providing crushed stone aggregate, depositing on a
prepared surface by hauling vehicles, spreading and
mixing with a motor grader, watering and compacting
with a vibratory roller 8-10 tonne to form a layer of
sub-base/ base as per MoRTH specifications Clause
410.
4.13.1 By Mix in place method
[Link] (i) For 53 mm maximum size Cum 935.00 813.00 15
[Link] (ii) For 45 mm maximum size Cum 923.00 803.00 15
4.13.2 By Mixing Plant
[Link] (i) For 53 mm maximum size Cum 1165.00 1013.00 15
[Link] (ii) For 45 mm maximum size Cum 726.00 631.00 15
Average Increage 1
%1.66667
21
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
5.4.1 50 mm thick. - Bitumen grade 60/70 VG 30 @ 5 Kg. Per Sqm Sqm 367.00 322.00 14
5.4.2 75 mm thick. - Bitumen grade 60/70 VG 30. @ 6.8 Kg. Per Sqm Sqm 487.00 429.00 14
22
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
23
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Grading II (10 mm nominal size) - Bitumen @5 % of mix &
5.7.2
thickness 25 - 30 mm with lead of mix material 20 km
[Link] 60/70 grade VG 30 Cum 8826.00 7758.00 14
[Link] CRMB-60 grade Cum 8784.00 7952.00 10
[Link] PMB - 40 grade Cum 10403.00 8533.00 22
5.7.3 Extra rate for carriage of mixed material additional lead from :-
Cum
[Link] Beyond 20 Km 2.60 2.40 8
per Km
24
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
5.11.1 a) Type "A" (22 Kg. binder per 10 Sqm) bitumen 60/70 grade VG 30 Sqm 167.00 146.00 14
25
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
b) Type "A" (22 Kg. Binder per 10 Sqm) crumb rubber modified
5.11.2 Sqm 167.00 151.00 11
bitumen- CRMB 60
5.11.3 a) Type "B" (19 Kg. Binder per 10 Sqm) bitumen 60/70 grade VG 30 Sqm 150.00 131.00 15
b) Type "B" (19 Kg. Binder per 10 Sqm) crumb rubber modified
5.11.4 Sqm 149.00 134.00 11
bitumen- CRMB 60
Providing and laying seal coat for sealing the voids in a bituminous
surface laid to the specified levels, grade and cross fall, including
cleaning and rolling with a smooth wheeled roller 8 - 10 tonne
5.12 capacity finished to required level and grades, complete as per Sqm 68.00 60.00 13
MoRTH specification clause 513 Type A - comprising of 11.2 mm to
2.36 mm size aggregate @ 0.09 Cum per 10 Sqm and bitumen
binder @ 9.8 Kg / 10 Sqm complete.
Providing and applying premix seal coat type "B" comprising of thin
application of fine aggregate (0.06 cum per 10 Sqm) premix with
6.8 Kgs. Per 10 Sqm bitumen binder (Grade 60/70) (including cost
5.12.1 of anti-stripping compound wherever required) In mini hot mix plant Sqm 51.00 45.00 13
6-10 TPH and laying with mechanical paver and rolling with power
roller 8-10 tonne including all lead of mix material ( MoRTH
Specifications Clause 513)
Providing and laying premix seal coat using hot mix plant and paver
finisher with aggregates of 6.7mm size defined as 100% passing
through 11.20mm sieve and retained on 2.36mm sieve with 0.09
5.12.3
cum per 10 Sqm and 4.5%bitumen including preparation and
transportation of mix, spreading, laying and rolling etc. complete in
all respect including cost of binder.
with lead of mix material 1km
[Link] 60/70 grade VG 30 Sqm 71.00 62.00 15
[Link] CRMB-60 grade Sqm 76.00 72.00 6
26
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
27
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Crack width below 6mm using modified binder (PMB - 40) @ 9Kg.
5.19.1 Sqm 76.00 62.00 23
Per 10 Sqm crushed stone aggregate 0.11 Cum per 10 Sqm.
28
CHAPTER :
BASES AND SURFACE COURSES (BITUMINOUS)
R-5
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Deduct the amount of cleaning in item no 4 & 5 if same is not
provided as per item no 1 & 2
Providing and laying of Chelmac PR mix for repair of roads in
adverse climate conditions on the prepared surface, cleaning with
hydruling laying in proper camber and grade with regular size
5.24 kg 27.00 24 13
compaction with hand rammer/road roller and transportation, with
all lead and -lift complete in all respect as per directions of
Engineer in charge
5.25 Labour charges only for laying of Chelmac PR mix. kg 3.30 3 10
Average Increage % 12.94
29
CHAPT
ER : R- CEMENT CONCRETE PAVEMENTS
6
%
increase
Item Rate (Rs.)
Item Description Unit Rate (Rs.) over
No. 2012
BSR-
2012
30
%
increase
Item Rate (Rs.)
Item Description Unit Rate (Rs.) over
No. 2012
BSR-
2012
31
CHAPTE
GEOSYNTHETICS AND REINFORCED EARTH
R : R-7
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
32
Assembling, joining and laying of reinforcing
7.5 elements. Etc. complete as per MoRTH
specification clause 3102 in:
Type A - With reinforcing element of steel /
7.5.1
Aluminum strips / polymeric strips. Using
[Link] [Link] carbon steel strips RM 269.00 240.00 12
[Link] [Link] strips RM 407.00 370.00 10
[Link] [Link] strips RM 346.00 309.00 12
[Link] [Link] steel strips RM 369.00 335.00 10
[Link] reinforced polymer/fiber reinforced
[Link] RM 240.00 218.00 10
polymer/polymeric strips
Type B - With reinforcing elements of synthetic
7.5.2 Sqm 527.00 474.00 11
geogrids using
[Link] Facing elements of RCC Sqm 1087.00 990.00 10
Average Increage % 10.73
33
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
34
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
35
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
36
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
37
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
38
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
39
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
40
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
41
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
42
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
43
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
8.40.1 Single row for one utility service [Link] 816.00 735.00
8.40.2 Double row for two utility services [Link] 1496.00 1348.00
8.40.3 Three row for three utility services [Link] 2291.00 2064.00
Installation of a steel portable barricade with
horizontal rail 300 mm wide, 2.5 m in length fitted
on a "A" frame made with 45 x 45 x 5 mm angle
iron section, 1.5 m in height, horizontal rail
8.41 painted (2 coats) with yellow and white strips , Each 2670.00 2405.00
150 mm in width at an angle of 450 , 'A' frame
painted with 2 coats of yellow paint, complete as
per IRC: SP:55-2001.
44
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
45
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
46
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
47
CHAPT
ER : R-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
48
% increase
over BSR-
2012
10
10
10
13
4
11
11
11
14
5
11
11
11
11
11
11
11
11
11
11
49
% increase
over BSR-
2012
10
10
11
11
9
9
11
11
11
11
11
11
11
11
11
11
50
% increase
over BSR-
2012
11
11
11
11
11
11
51
% increase
over BSR-
2012
11
11
11
11
11
11
11
52
% increase
over BSR-
2012
11
11
11
53
% increase
over BSR-
2012
11
11
11
11
11
54
% increase
over BSR-
2012
11
11
11
11
11
11
11
11
11
11
11
11
55
% increase
over BSR-
2012
11
11
11
11
56
% increase
over BSR-
2012
11
11
11
11
57
% increase
over BSR-
2012
11
11
11
58
% increase
over BSR-
2012
11
11
11
11
11
11
11
59
% increase
over BSR-
2012
11
60
% increase
over BSR-
2012
11
11
11
61
% increase
over BSR-
2012
11
11
10
11
25
10
13
11
11
15
9
15
11
10
62
% increase
over BSR-
2012
11
11
12
11
11
12
11
12
11
10
11
10
17
10.93
63
CHAPTER
PIPE CULVERTS & CULVERTS
: R-09
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Providing and laying mechanically mixed and
vibrated Cement Concrete in foundation up to a
9.1 depth of 1.5 meters below ground level and 1.50
meters above Ground/Bed level.[MoRTH
Specification : Clause 1000/1700]
Cement concrete [Link] mix crushed stone
9.1.1 Cum 2780 2503 11
aggregates 40mm nominal size.
Cement concrete [Link] mix hand broken stone
9.1.2 Cum 2800 2149 30
aggregates 20mm nominal size.
Cement concrete [Link] mix crushed stone
9.1.3 Cum 3351 2996 12
aggregates 40mm nominal size.
Cement concrete [Link] mix with stone aggregate
9.1.4 Cum 3373 3003 12
20mm crusher broken.
Providing and laying Plain cement concrete M15 mix
with stone aggregate 20mm nominal size
9.2 mechanically mixed and vibrated, in foundation up to Cum 3879 3509 11
a depth of 1.50 below Ground level and or 1.50
meters above ground/bed level.
Providing and laying Plain cement concrete M15 mix
with stone aggregate20mm nominal size
mechanically mixed and vibrated, in superstructure
9.3 Cum 4073 3684 11
up to 4 meter above 1.5 meter level from
Bed/Ground level.[MoRTH Specification: Clause
1000/1700]
64
CHAPTER
PIPE CULVERTS & CULVERTS
: R-09
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Providing and laying First class brick masonry
(min.10.5 MPa) in cement mortar 1:3 up to a depth
9.7 of 1.50 meters below ground and above 1.50m from Cum 3785 3595.00 5
Bed/ground level. [MoRTH Specification : Clause
1000/1300]
Extra for brick works in superstructure up to a height
4 meters or part thereof above 1.5 meter level from
9.8 Cum 73.00 66.00 11
Bed/Ground level [MoRTH specification: Clause
1000/1300].
Providing and laying Brick-on-edge flooring with 1st
class bricks (min.10.5 Mpa) including cement slurry
9.9 Sqm 242.00 218 11
in cement sand mortar 1:4 at all levels.[MoRTH
Specification : Clause 1000/1300]
Providing and laying Coursed / Random Rubble
stone masonry in cement sand mortar 1:3, in
9.10 foundation up to a depth of 1.50 meters and also
1.50 meters above Ground /Bed level [MoRTH
Specification : Clause 1000/1400]
9.10.1 Square Rubble Coursed Rubble Masonry (first sort) Cum 3899 New item
9.10.2 Random Rubble Masonry Cum 3296 3061.00 8
Extra for coursed/Random rubble stone masonry in
superstructure up to a height of 4 meters or part
9.11 Cum 107.00 96.00 11
thereof above 1.50 meters from Ground /Bed level
[MoRTH Specification : Clause 1000/1400]
Providing Cement pointing 1:3 deep grooved (cut or
9.12 weather) on brick / stone and tile work at all levels. Sqm 50.00 47.30 6
[MoRTH Specification : Clause 1000/1300]
Providing Cement pointing 1:3, flush on Brick-on-
9.13 edge floor at all levels.[MoRTH Specification: Clause Sqm 50.00 47.30 6
1000/1300]
Plaster on new surface with cement mortar (1:3)
9.14 including racking of joint etc. complete fine finished Sqm 102.00 96 6
20mm thick.
Providing and laying reinforced cement concrete
pipes N.P.4 for culverts including jointing ends and
9.15
fixing collar with cement mortar 1:2 [MoRTH
Specification : Clause : 1000/2900]
9.15.1 300 mm Dia meter 2572 2300 12
9.15.2 600 mm Dia meter 3853 3450 12
9.15.3 900 mm Dia Meter 5691 5164 10
9.15.4 1000 mm Dia Meter 6479 5782 12
9.15.5 1200 mm Dia Meter 7221 6557.00 10
Providing and laying Rubble stone kharanja in
9.16 cement sand mortar 1:3 in flooring at all levels Cum 1685.00 1518.00 11
[MoRTH Specification : Clause : 1400]
65
CHAPTER
PIPE CULVERTS & CULVERTS
: R-09
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
66
CHAPTER
PIPE CULVERTS & CULVERTS
: R-09
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Pointing of stone masonry in cement mortar (1:3)
9.24 Sqm 55.00 55.00 0
raised & cut pointing.
Plaster on new surface with cement mortar (1:3)
9.25 including racking of joint etc. complete fine finished Sqm 102.00 102.00 0
20mm thick.
Plaster on new surface with cement mortar (1:4)
9.26 including racking of joint etc. complete fine finished Sqm 87.00 77.00 13
20mm thick.
Random rubble stone masonry for foundation &
9.27 plinth in cement sand mortar above 30 cm thick
walls
9.27.1 In cement sand mortar 1:4 Cum 2966.00 2703.00 10
9.27.2 In cement sand mortar 1:6 Cum 2669.00 2545.00 5
[Link] Span 701 to 1200 mm Standard size 1500x600mm Sqm 1685.00 1518.00 11
[Link] Span 1201 to 1500 mm Standard size 2100x500mm Sqm 2564.00 2310.00 11
9.30.2 For Class - 'AA' loading
[Link] Span 300 to 450 mm Standard size 600x800mm Sqm 1392.00 1254.00 11
[Link] Span 451 to 700 mm Standard size 1000x800mm Sqm 1612.00 1452.00 11
[Link] Span 701 to 1200 mm Standard size 1500x600mm Sqm 2051.00 1848.00 11
[Link] Span 1201 to 1500 mm Standard size 2100x500mm Sqm 2930.00 2640.00 11
67
CHAPTER
PIPE CULVERTS & CULVERTS
: R-09
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
68
CHAPTER
PIPE CULVERTS & CULVERTS
: R-09
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
9.33.1 40mm thick Sqm 404.00 364.00 11
9.33.2 Up to 60mm thick Sqm 500.00 450.00 11
9.33.3 Up to 80mm thick Sqm 613.00 552.00 11
9.33.4 Up to 115mm thick Sqm 758.00 683.00 11
Average Increage % 9.48
69
CHAPTER
MAINTENANCE OF ROADS
: R-8
Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
70
CHAPTER
MAINTENANCE OF ROADS
: R-8
Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
71
CHAPTER
MAINTENANCE OF ROADS
: R-8
Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
72
CHAPTER
MAINTENANCE OF ROADS
: R-8
Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
73
CHAPTER
MAINTENANCE OF ROADS
: R-8
Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Cutting of black topped surface up to 30mm depth for
fixing of Kerb/Dand stones/Medians including
10.18 cleaning of surface laying bed mortar & removal of Sqm 14 13 8
dismantled material with all lead & traffic diversion
arrangements complete
Digging out entire WBM/WMM surface including
10.19 sorting out serviceable material its stacking & Cum 68 61.00 11
removal of rubbish up to 50 Mtr. lead.
Cutting WBM road and soling up to 1.5 Mtr. depth for
10.20 laying pipe line etc. & making good to original Sqm 363 326.00 11
condition complete.
74
CHAPTER
MAINTENANCE OF ROADS
: R-8
Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
10.26.1 Up to 3 cm height Sqm 19.00 17.00 12
10.26.2 Above 3 to 5 cm height Sqm 22.00 20.00 10
10.26.3 Above 5 to 8 cm height Sqm 29.00 26.00 12
10.26.4 Above 8 cm height Sqm 32.00 29.00 10
Dressing of berms including digging of earth up to 10
10.27 Sqm 1.10 1.00 10
cm depth
Dismantling tile work in floors and roofs laid in
cement mortar including stacking of serviceable
10.28 Sqm 8.40 7.50 12
material and disposal of unserviceable material within
50 Mtr. lead.
Providing and fixing steel gate grating and grills made
of angles, tees, square bars or other flats black pipe
10.29 with hold fast and fittings complete as per design and Kg 73.00 66 11
drawing including cutting welding and fabrication with
priming coat of red oxide.
Providing stone slab covering over drains including
filling of joints in cement sand mortar 1:3 with 35mm
10.30 thick cement concrete flooring [Link] mix complete Sqm 406.00 365 11
with good finish with stone slab 60 to 75mm thick
average.
Repair of iron sign board at road side including
10.31 cutting welding and refixing as per directions but Nos. 390.00 359 9
excluding painting and lettering.
75
CHAPTER
MAINTENANCE OF ROADS
: R-8
Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
76
CHAPTER :
HORTICULTURE
R-11
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Supply at site of work well-decayed farmyard
manure, from any available source, approved by
11.1 Cum 220.00 198.00 11
the Engineer in charge including carriage,
screening and stacking.
Supplying at site of work/store Deolied Neem
11.2 Quintal 645.00 581.00 11
Cake duly packed in used gunny bags.
11.3 Supplying sludge duly stacked at site/store Cum 88.00 79.00 11
77
CHAPTER :
HORTICULTURE
R-11
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
78
CHAPTER :
HORTICULTURE
R-11
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
Planting permanent hedges including digging of
trenches 60cm wide and 45cm deep refilling the
excavated earth mixed with farm yard manure
11.19 100 Meters 10769.00 9702.00 11
supplied at the rate of 4.65 cum per 100 meters
and supplying and planting hedge plants at 30 cm
apart.
Maintaining the hedges for the first two years
11.20
including watering etc. complete.
11.20.1 For first year Meters 56.00 50.00 12
11.20.2 For second year Meters 47.00 42.00 12
11.21.1 Hole 1.2 mm dia and 1.2m deep One hole 32.00 29.00 10
11.21.2 Hole 0.6 m dia and 0.6 m deep Each 14.00 13.00 8
11.22 Planting & maintenance of plants and shrubs.
Plants and shrubs in central verge where verge is
11.22.1 3.0 meters and above (200 plants 800 shrubs in
two rows in one Km).
[Link] Planting plants and shrubs in central verge. Meter 16.00 14.00 14
Maintenance of plants and shrubs in Central
[Link] Meter 99.00 89.00 11
verge for one year.
Plants and shrubs in central verge where verge is
11.22.2 less than 3.0 meters with one row of 400 shrubs
and 100 tree plants in one Km.
[Link] Planting plants and shrubs Meter 8.00 7.00 14
[Link] Maintenance of plants and shrubs for one year Meter 52.00 47.00 11
Renovating lawns including weeding, chilling the
grass, forking the ground, top dressing with
forked soil, watering and maintaining the lawns for
30 days or more till the grass forms a thick lawn,
11.23 100 Sqm 642.00 578.00 11
free from weeds and fit for moving, Disposal of
rubbish as directed, including supplying good
earth, if needed; but excluding the cost of well
decayed farm-yard manure.
79
CHAPTER :
HORTICULTURE
R-11
Item No. Item Description %
increase
Rate (Rs.)
Unit Rate (Rs.) over
2012
BSR-
2012
80
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Earth work in excavation for foundation of
structure complete with all lift, dewatering
shoring and shuttering etc. .including refilling
of trenches in [Link] layers, ramming,
12.1 watering and disposal of surplus soil within a
lead of 1000 meters, as per drawing and
technical specification.[MoRTH Specification :
Clause : 304]
81
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Filter medium behind abutment, wing wall and
return wall, complete as per drawing and
12.4 technical specification. [MoRTH Specification : Cum 592.00 533.00 11
Clause: Clause:2504].
Brick masonry work in cement mortar 1:3, with
mechanical mixer, in foundation (at any level)
complete, including all scaffolding etc.,
12.5 excluding pointing and plastering, as per Cum 3785.00 3595.00 5
drawing and technical specification. [MoRTH
Specification : Section 1000,1300]
82
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Structural Concrete (Design mix) in well
foundations [MoRTH Specification: 1200(N),
1500(N),1700(N)]
12.9.1 Well Curb , including formwork etc.
[Link] R.C.C M-20 grade Cum 4526.00 4151.00 9
[Link] R.C.C.M-25 grade Cum 5133.00 4725.00 9
[Link] R.C.C.M-35 grade Cum 5294.00 4877.00 9
12.9.2 Well steining, including formwork etc.
[Link] P.C.C.M-15 Grade Cum 4103.00 3712.00 11
[Link] P.C.C.M-20 Grade Cum 4580.00 4167.00 10
[Link] R.C.C.M-20 Grade Cum 4613.00 4198.00 10
[Link] P.C.C.M-25 Grade Cum 4532.00 4174.00 9
[Link] R.C.C.M-25 Grade Cum 4705.00 4331.00 9
[Link] P.C.C.M-30 Grade Cum 4572.00 4213.00 9
[Link] R.C.C M-30 Grade Cum 4592.00 4231.00 9
[Link] R.C.C M-35 Grade Cum 4853.00 4471.00 9
[Link] R.C.C M-40 Grade Cum 4914.00 4530.00 8
Bottom plug, including forming sump,
12.9.3
protective bounds, chiseling etc.
[Link] P.C.C.M-20 grade Cum 4199.00 3857.00 9
[Link] P.C.C.M-25 grade Cum 4422.00 4070.00 9
[Link] P.C.C.M-30 grade Cum 4467.00 4113.00 9
[Link] P.C.C.M-35 grade Cum 4565.00 4206.00 9
Intermediate plug, include extra protective
12.9.4
works and dewatering etc.
[Link] P.C.C.M-20 grade Cum 4023.00 3695.00 9
[Link] P.C.C.M-25 grade Cum 4236.00 3899.00 9
[Link] P.C.C.M-30 grade Cum 4279.00 3940.00 9
Top plug in Plain Cement Concrete,
12.9.5 including extra protective works and
dewatering etc.
[Link] P.C.C.M-15 grade Cum 3730.00 3375.00 11
[Link] P.C.C.M-20 grade Cum 4164.00 3789.00 10
[Link] P.C.C.M-25 grade Cum 4120.00 3795.00 9
[Link] P.C.C.M-30 grade Cum 4156.00 3830.00 9
12.9.6 Well cap
[Link] R.C.C.M-20 grade Cum 3878.00 3556.00 9
[Link] R.C.C.M-25 grade Cum 4307.00 3968.00 9
[Link] R.C.C.M-30 grade Cum 4319.00 3980.00 9
[Link] R.C.C.M-35 grade Cum 4406.00 4064.00 8
[Link] R.C.C.M-40 grade Cum 4636.00 4275.00 8
Sinking of well, true and vertical, through all
types of soil and rock (other than pneumatic
12.10 method of sinking), complete as per drawing
and technical specification.[MoRTH
Specification : 1200(N)]
12.10.1 Well of 6m external diameter
83
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
[Link] In Sandy soil)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 3672.00 3321.00 11
[Link].2 Beyond 3m up to [Link], Meter 5286.00 4784.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Clayey soil.(Well of 6m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 5293.00 4792.00 10
[Link].2 Beyond 3m up to [Link], Meter 11385.00 10302.00 11
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Soft rock. .(Well of 6m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 14489.00 13006.00 11
84
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Beyond 10m up to 20m depth : Add 7.5% for
every additional meter depth of sinking over
[Link].3 the rate of sinking for the previous meter. Meter 7.50% 7.50%
85
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 5587.00 5058.00 10
[Link].2 Beyond 3m up to [Link], Meter 7595.00 6879.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Clayey soil.(Well of 7m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 7595.00 6879.00 10
[Link].2 Beyond 3m up to [Link], Meter 10968.00 9937.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Soft rock. .(Well of 7m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 12697.00 11441.00 11
86
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Beyond 10m up to 20m depth : Add 7.5% for
every additional meter depth of sinking over
[Link].3 the rate of sinking for the previous meter. Meter 7.50% 7.50%
87
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 6899.00 6247.00 10
[Link].2 Beyond 3m up to [Link], Meter 8527.00 7721.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Clayey soil.(Well of 8m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 9288.00 8413.00 10
[Link].2 Beyond 3m up to [Link], Meter 11840.00 10711.00 11
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Soft rock. .(Well of 8m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 14152.00 12748.00 11
88
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Beyond 10m up to 20m depth : Add 7.5% for
every additional meter depth of sinking over
[Link].3 the rate of sinking for the previous meter. Meter 7.50% 7.50%
89
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 6971.00 6310.00 10
[Link].2 Beyond 3m up to [Link], Meter 9366.00 8481.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Clayey soil.(Well of 9m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 9786.00 8863.00 10
[Link].2 Beyond 3m up to [Link], Meter 12779.00 11560.00 11
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Soft rock. .(Well of 9m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 17928.00 16159.00 11
90
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Beyond 10m up to 20m depth : Add 7.5% for
every additional meter depth of sinking over
[Link].3 the rate of sinking for the previous meter. Meter 7.50% 7.50%
91
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 8434.00 7638.00 10
[Link].2 Beyond 3m up to [Link], Meter 9872.00 8937.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Clayey soil.(Well of 10m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 10690.00 9674.00 11
[Link].2 Beyond 3m up to [Link], Meter 12493.00 11293.00 11
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Soft rock. .(Well of 10m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 18307.00 16500.00 11
92
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Beyond 10m up to 20m depth : Add 7.5% for
every additional meter depth of sinking over
[Link].3 the rate of sinking for the previous meter. Meter 7.50% 7.50%
93
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 19548.00 17714.00 10
[Link].2 Beyond 3m up to [Link], Meter 20583.00 18634.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Clayey soil.(Well of 11m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 17788.00 16099.00 10
[Link].2 Beyond 3m up to [Link], Meter 25645.00 23177.00 11
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Soft rock. .(Well of 11m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 41110.00 37056.00 11
94
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Beyond 10m up to 20m depth : Add 7.5% for
every additional meter depth of sinking over
[Link].3 the rate of sinking for the previous meter. Meter 7.50% 7.50%
95
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 40174.00 36391.00 10
[Link].2 Beyond 3m up to [Link], Meter 44898.00 40644.00 10
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
In Clayey soil.(Well of 12m. External
[Link]
diameter)
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 43738.00 39597.00 10
[Link].2 Beyond 3m up to [Link], Meter 65300.00 59073.00 11
Beyond 10m up to 20m depth : Add 5% for
[Link].3 every additional meter depth of sinking over Meter 5% 5%
the rate of sinking for the previous meter.
Beyond 20m up to 30m depth: Add 7.5% for
[Link].4 every additional meter depth of sinking over Meter 7.50% 7.50%
the rate of sinking for the previous meter
Beyond 30m up to 40m depth: Add 10% for
[Link].5 every additional meter depth of sinking over Meter 10% 10%
the rate of sinking for the previous meter
Kent ledge(supports, loading arrangement,
[Link].6 Meter 20% 20%
labour etc.)
[Link].7 Add for dewatering if required
[Link].7.1 Depth up to 3m Meter 5% 5%
[Link].7.2 Depth 3 to10m Meter 5% 5%
[Link].7.3 Depth above 10m Meter 5% 5%
[Link] In Soft rock.
Depth from 0-3 meters from cutting edge level.
[Link].1 Meter 97265.00 87725.00 11
96
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Beyond 10m up to 20m depth : Add 7.5% for
every additional meter depth of sinking over
[Link].3 the rate of sinking for the previous meter. Meter 7.50% 7.50%
97
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
Sand filling with compaction in wells complete
as per level on drawing and technical
12.11 specification. [MoRTH Specification : Clause Cum 884.00 802.00 10
1207(N)]
Providing and laying Steel reinforcement at
any level in foundation complete as per
12.12 drawing and technical Specification.[MoRTH
Specification : Section: 1600(N)]
12.12.1 HYSD bar reinforcement Tonnes 67784.00 60561.00 12
12.12.2 Mild Steel reinforcement Tonnes 65496.00 60019.00 9
Pneumatic sinking of wells complete as per
Lump
12.13 drawing and technical specification.[MoRTH 41287.00 39905.00
Sum
Specification : Section 1200(N)]
Providing structural steel liner for curbs and
seining for wells including fabricating and
12.14 setting out as per detailed drawing .[MoRTH Tonnes 78678.00 70634.00 11
Specification : Section 1200(N)&1900(N)]
Board/cast-in-situ R.C.C piles complete as per
drawing and technical specification. [MoRTH
12.15 Specification : Section 1100,1600&1700(N)]
Using Batching Plant, Transit Mixture, and
Concrete Pump.
12.15.1 750 mm Dia piles (excluding reinforcement)
[Link] Concrete M25 in R.C.C (Design mix) Meter 4386.00 4033.00 9
[Link] Concrete M30 in R.C.C (Design mix) Meter 4476.00 4115.00 9
[Link] Concrete M35 in R.C.C (Design mix) Meter 4567.00 4199.00 9
12.15.2 1000mm Dia pile (excluding reinforcement)
[Link] Concrete M25 in R.C.C (Design mix) Meter 7248.00 6662.00 9
[Link] Concrete M30 in R.C.C (Design mix) Meter 7396.00 6798.00 9
[Link] Concrete M35 in R.C.C (Design mix) Meter 7547.00 6937.00 9
12.15.3 1200mm Dia piles (excluding reinforcement)
[Link] Concrete M25 in R.C.C (Design mix) Meter 9293.00 8541.00 9
[Link] Concrete M30 in R.C.C (Design mix) Meter 9483.00 8715.00 9
[Link] Concrete M35 in R.C.C (Design mix) Meter 9677.00 8893.00 9
Reinforced cement concrete in pile cap
complete at all levels with steel formwork etc.
12.16 as per drawing and technical specification.
Using Batching Plant, Transit Mixture, and
Concrete Pump.
Design mix concrete. [MoRTH Specification :
12.16.1
1100(N),1500(N), 1700(N)]
[Link] M20 grade Cum 3913.00 3586.00 9
[Link] M25 grade Cum 4321.00 3977.00 9
[Link] M30 grade Cum 4373.00 4028.00 9
[Link] M35 grade Cum 4481.00 4130.00 8
[Link] M40 grade Cum 5184.00 4320.00 20
98
CHAPTER R12 FOUNDATIONS
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
If the bottom level of pile cap is below the
water table, add20% extra for under water
12.16.3 concreting/ dewatering/ shoring, [MoRTH 20% 20%
Specification: 1100(N),1500(N), 1700(N)]
If the pile cap rests on ground add for leveling
12.16.4 course. [MoRTH Specification : Cum 3689.00 3332.00 11
100(N),1500(N),1700(N)]
Driven cast-in-place true and vertical R.C.C
piles complete as per drawing and technical
12.17 specification.[MoRTH Specification : Section :
1100,1600,1700 (N)]
Concrete M35 in R.C.C (Design mix)
12.17.1 750 mm Dia piles Meter 3182.00 2910.00 9
12.17.1 1000mm Dia piles Meter 5155.00 4719.00 9
12.17.1 1200 mm Dia piles Meter 7516.00 6879.00 9
Driven precast true and vertical R.C.C piles
complete as per drawing and technical
12.18 specification.[MoRTH Specification : Section :
1100,1600,1700 (N)]
12.18.1 550mm Dia piles (excluding reinforcement)
[Link] Concrete M25 in R.C.C (Design mix) Meter 1864.00 1775.00 5
[Link] Concrete M30 in R.C.C (Design mix) Meter 1928.00 1836.00 5
[Link] Concrete M35 in R.C.C (Design mix) Meter 2001.00 1906.00 5
12.18.2 500mm Dia piles (excluding reinforcement)
[Link] Concrete M25 in R.C.C (Design mix) Meter 1557.00 1483.00 5
[Link] Concrete M30 in R.C.C (Design mix) Meter 1630.00 1552.00 5
[Link] Concrete M35 in R.C.C (Design mix) Meter 1702.00 1621.00 5
12.18.3 450mm Dia piles (excluding reinforcement)
[Link] Concrete M25 in R.C.C (Design mix) Meter 1237.00 1178.00 5
[Link] Concrete M30 in R.C.C (Design mix) Meter 1296.00 1234.00 5
[Link] Concrete M35 in R.C.C (Design mix) Meter 1368.00 1303.00 5
12.18.4 750mm Dia piles (excluding reinforcement)
Concrete M35 in R.C.C (Design mix) Meter 2251.00 2144.00 5
12.18.5 1200mm Dia piles (excluding reinforcement)
Concrete M35 in R.C.C (Design mix) Meter 3809.00 3628.00 5
Steel Reinforcement for Board/Cast-in situ
piles as per design (Rate may taken from the
12.19 relevant item of reinforcement in foundation
work)
12.19.1 H Y S D steel Tonne 67784.00 60561.00 12
12.19.1 Mild Steel. Tonne 65496.00 60019.00 9
12.20 Load testing of piles.
Initial and routine test for vertical load testing. Tonne
12.20.1 634.00 528.00 20
load
12.20.2 For lateral load testing of pile Each pile 22810.00 19008.00 20
Average Increage % 9.866667
99
CHAPTER :
SUB STRUCTURE
R-13
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2010
100
CHAPTER :
SUB STRUCTURE
R-13
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2010
[Link] R.C.C.M20 grade , including formwork.
[Link].1 Up to 5 meter height Cum 4149.00 3805.00 9.0
[Link].2 For 5m to 10m height Cum 4190.00 3843.00 9.0
[Link].3 Above 10m height Cum 4232.00 3881.00 9.0
[Link] R.C.C.M25 grade, including formwork.
[Link].1 Up to 5 meter height Cum 4705.00 4331.00 9.0
[Link].2 For 5m to 10m height Cum 4752.00 4374.00 9.0
[Link].3 Above 10m height Cum 4800.00 4418.00 9.0
[Link] R.C.C.M30 grade, including formwork
[Link].1 Up to 5 meter height Cum 4592.00 4231.00 9.0
[Link].2 For 5m to 10m height Cum 4638.00 4273.00 9.0
[Link].3 Above 10m height Cum 4684.00 4316.00 9.0
[Link] R.C.C.M35 grade
[Link].1 Up to 5 meter height Cum 4853.00 4471.00 9.0
[Link].2 For 5m to 10m height Cum 4902.00 4516.00 9.0
[Link].3 Above 10m height Cum 4951.00 4561.00 9.0
[Link] R.C.C.M40 grade
[Link].1 Up to 5 meter height Cum 5096.00 4695.00 9.0
[Link].2 For 5m to 10m height Cum 5147.00 4742.00 9.0
[Link].3 Above 10m height Cum 5198.00 4789.00 9.0
Pointing of any design with cement mortar
13.4 (1:3)on Brick / Stone work in substructure at Sqm 50.00 47.30 6.0
any height [MoRTH Specification: Clause
1309]
Plaster on new surface with cement mortar
13.5 (1:3) including racking of joint etc. complete Sqm 102.00 96.00 6.0
fine finished 20mm thick.
101
CHAPTER :
SUB STRUCTURE
R-13
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2010
102
CHAPTER :
SUB STRUCTURE
R-13
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2010
13.15.4 Providing & fixing 20 mm thick compressible Meter 156.00 141.00 11.0
fibre board in expansion joint complete as per
drawing & Technical Specification.
Providing & Fixing in position 20mm thick
13.15.5 moulded joint filler in expansion joint Meter 106.00 94.00 13.0
complete.
Providing and filling joint sealing compound - Meter per
13.15.6 20.00 18.00 11.0
Coarse sand with bitumen (6% by weight) Cms depth
103
CHAPTER :
SUB STRUCTURE
R-13
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2010
13.16.4 Modular Strip / Box Seal Joint
104
CHAPTER :
SUPERSTRUCTURE
R-14
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2012
Structural Cement concrete for reinforced
concrete/PSC in superstructure complete
including steel formwork, scaffolding etc. as per
14.1 drawing and technical specification. Using
Batching Plant, Transit Mixture, and Concrete
Pump.
105
CHAPTER :
SUPERSTRUCTURE
R-14
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2012
[Link].1 Height up to 5m Cum 5907.00 5448.00 8
[Link].2 Height from 5m to 10m Cum 6335.00 5843.00 8
[Link].3 Height above 10m Cum 6763.00 6238.00 8
14.1.5 M 40 grade
[Link] Solid slab/Voided slab superstructure
[Link].1 Height up to 5m Cum 5279.00 4867.00 8
[Link].2 Height from 5m to 10m Cum 5503.00 5073.00 8
[Link].3 Height above 10m Cum 5727.00 5280.00 8
T-beam, slab , precast girders and slab for
[Link] Superstructure including transportation and
launching up to 40m span.
[Link].1 Height up to 5m Cum 5503.00 5073.00 8
[Link].2 Height from 5m to 10m Cum 5727.00 5280.00 8
[Link].3 Height above 10m Cum 5950.00 5486.00 8
Box girder and balanced cantilever
[Link]
superstructure
[Link].1 Height up to 5m Cum 6174.00 5692.00 8
[Link].2 Height from 5m to 10m Cum 6621.00 6104.00 8
[Link].3 Height above 10m Cum 7069.00 6517.00 8
14.1.6 M 45 grade
[Link] Solid slab/Voided slab superstructure
[Link].1 Height up to 5m Cum 5478.00 5060.00 8
[Link].2 Height from 5m to 10m Cum 5714.00 5278.00 8
[Link].3 Height above 10m Cum 5950.00 5496.00 8
T-beam, slab , precast girders and slab for
[Link] Superstructure including transportation and
launching up to 40m span.
[Link].1 Height up to 5m Cum 5714.00 5278.00 8
[Link].2 Height from 5m to 10m Cum 5950.00 5496.00 8
[Link].3 Height above 10m Cum 6186.00 5714.00 8
Box girder and balanced cantilever
[Link]
superstructure
[Link].1 Height up to 5m Cum 6422.00 5932.00 8
[Link].2 Height from 5m to 10m Cum 6894.00 6369.00 8
[Link].3 Height above 10m Cum 7367.00 6805.00 8
14.1.7 M 50 grade ( PSC )
Box girder and balanced cantilever
[Link]
superstructure
[Link].1 Height up to 5m Cum 6614.00 6118.00 8
[Link].2 Height from 5m to 10m Cum 7104.00 6571.00 8
[Link].3 Height above 10m Cum 7594.00 7024.00 8
14.1.8 M 55 grade (PSC )
Box girder and balanced cantilever
[Link]
superstructure
[Link].1 Height up to 5m Cum 6989.00 6477.00 8
[Link].2 Height from 5m to 10m Cum 7507.00 6956.00 8
106
CHAPTER :
SUPERSTRUCTURE
R-14
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2012
[Link].3 Height above 10m Cum 8025.00 7436.00 8
Providing and laying HYSD bar reinforcement at
any level in superstructure complete as per
14.2 drawing and technical specification .[MoRTH Tonne 68888.00 61529.00 12
Specification 1600(N)]
Providing and laying High tensile steel
wires/strands at any level including all
accessories for stressing, stressing operations
14.3 and grouting complete as per drawing and Tonne 123655.00 111592.00 11
technical specification.[MoRTH Specification
1800(N)]
107
CHAPTER :
SUPERSTRUCTURE
R-14
Item Description %
increase
Rate (Rs.)
Item No. Unit Rate (Rs.) over
2012
BSR-
2012
14.9.3 M 40 grade Cum 7857.00 7141.00 10
P&F on culverts/ bridges deck rain water spouts
14.10 made of cast iron as per MoRTH specification Each 1451.00 1319.00 10
complete
14.11 PSL item epoxy
Providing anticorrosive treatment to heeds
reinforcement with fusion bonded epoxy coating
the rate includes cost of anticorrosive coating
including cost of powder, sand blasting, cleaning,
induction, heating ,depreciation of machinery etc.
wastage in cut length of bars, provision of
a wooden battens between rows of coated bars, Tonne 13733 12372 11
cover to work bush pains/bar bending machines
etc.-for bars of 20mm to 32 mm diameter-
confirming to IS 13620-1993
108
CHAPTER :
RIVER TRAINING AND PROTECTION WORK
R-15
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
109
CHAPTER :
RIVER TRAINING AND PROTECTION WORK
R-15
%
increase
Rate (Rs.)
Item No. Item Description Unit Rate (Rs.) over
2012
BSR-
2012
For filling wire crates made of 5mm dia G I wire by
stone in specified position at site including 5 mm
15.6.5 dia G I wire for binding complete in all respect . Cum 363.00 324.00 12
110
CHAPTER :
REPAIR & REHABILITATION
R-16
Item No. Item Description
Rate (Rs.)
Unit Rate (Rs.)
2012
111
CHAPTER :
REPAIR & REHABILITATION
R-16
Item No. Item Description
Rate (Rs.)
Unit Rate (Rs.)
2012
112
CHAPTER :
REPAIR & REHABILITATION
R-16
Item No. Item Description
Rate (Rs.)
Unit Rate (Rs.)
2012
113
CHAPTER :
REPAIR & REHABILITATION
R-16
Item No. Item Description
Rate (Rs.)
Unit Rate (Rs.)
2012
114
CHAPTER :
REPAIR & REHABILITATION
R-16
Item No. Item Description
Rate (Rs.)
Unit Rate (Rs.)
2012
Average Increage %
115
%
increase
over
BSR-
2012
11
11
11
11
11
11
11
11
11
11
116
%
increase
over
BSR-
2012
10
12
10
117
%
increase
over
BSR-
2012
10
12
11
11
118
%
increase
over
BSR-
2012
11
13
11
11
11
11
11
10
11
119
%
increase
over
BSR-
2012
10.85714
120
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
1 Providing and Inserting
indigenously manufactured
Prefabricated Vertical Drain
with Polypropylene core and
wrapped with Non-woven
geotextile in the very soft clay
for quick consolidation.
121
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
(b) Type II (TFI - Tech Geo
PR20) , minimum width 5.0
Meter. As per the approved [Link]. 148.0 31.0 133.0 28.0 11 11
Comparative Statement
(c) Type-III (TFI- TechGeo
PR25), minimum width 5.0
Meter. As per the approved [Link]. 164.0 31.0 148.0 28.0 11 11
Comparative Statement.
(d) Type-IV (TFI - TechGeo
PR30), minimum width 5.0
Meter. As per the approved [Link]. 191.0 31.0 172.0 28.0 11 11
Comparative Statement.
(e) Type-V (TFI - TechGeo
PR40), minimum width 5.0
Meter. As per the approved [Link]. 242.0 31.0 218.0 28.0 11 11
Comparative Statement
(f) Type-VI (TFI - TechGeo
PR50), minimum width 5.0
Meter. As per the approved [Link]. 294.0 31.0 265.0 28.0 11 11
Comparative Statement
(g) Type-VII - (TFI - TechGeo
PR60), minimum width 5.0
Meter. As per the approved [Link]. 346.0 31.0 312.0 28.0 11 11
Comparative Statement
122
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
Providing and Laying Needle
punched and mechanically
bonded Non-woven Paving
Fabric indigenously
manufactured from high
quality Polypropylene stable
fibers (continuous filament will
not be accepted) over a tack
coat of paving grade bitumen
80-100 preparation, laid at the
rate of 1 kg per Sqm over
thoroughly cleaned and
repaired surface to provide a
water resistant membrane and
crack retarding layer. Paving
fabric to be laid before cooling
of tack coat, brooming and
rolling of surface with
pneumatic roller to maximize
paving fabric contact with
pavement surface as per
drawing and product approval
certificate from M/s CRRI,
New Delhi.
123
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
(a) Type 50 (TFI - Tec glass
50 ken X 50 ken) minimum
width of 2.5 Meter/ 5.0 Meter. [Link]. 191.0 31.0 172.0 28.0 11 11
As per the approved
Comparative Statement
(b) Type 100 (TFI - Tec glass
100kN X 100 ken), minimum
width of 2.5 Meter/ 5.0 Meter. [Link]. 294.0 31.0 265.0 28.0 11 11
As per the approved
Comparative Statement
(c) Type 200 (TFI - Tec glass
100 kN X 200 kN, minimum
width of 2.5 Meter/ 5.0 Meter. [Link]. 369.0 31.0 332.0 28.0 11 11
As per the approved
Comparative Statement
4 Providing and Laying CE
marked woven multifilament
Polyester Geotextile
indigenously manufactured
from high quality polyester
filament yarns for soil
reinforcement and stabilization
on the prepared subgrade with
necessary overlaps and as per
drawing
124
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
(a) Type-A (TFI 1x1x1), size
1mx1mx1m with
100mmx100mm aperture size. [Link]. 1859.0 61.0 1675.0 55.0 11 11
As per the approved
Comparative Statement.
(b) Type-B (TFI - 1x1x2), size
1mx1mx2m with
100mmx100mm aperture size. [Link]. 3279.0 61.0 2954.0 55.0 11 11
As per the approved
Comparative Statement
(c) Type-C (TFI - 1x1x3) , size
1mx1mx3m with
100mmx100mm aperture size. [Link]. 4848.0 61.0 4368.0 55.0 11 11
As per the approved
Comparative Statement
Providing and Fixing Gabions
of only TFI made of
mechanically woven
hexagonal shaped wire mesh
of type, 10X12cm with edges
selvedge made of heavily
(Zinc + PVC) coated GI wires
as per BS:443, mesh wire
2.70mm Ǿ edge wire 3.4mm
Ǿ of only TFI/ TechBox type
filled with 20 kg to 50 kg
weight trap stones including
conveying with all the leads &
lifts and placing at required
places in required line, level,
slope, section as directed etc
to complete Reinforced Earth
Walls & Slopes as per
Drawing
125
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
6 Providing and Laying CE
Marked Knitted and PVC
coated Polyester Biaxial
Geogrid for Basal
Reinforcement indigenously
manufactured from selected
high tenacity polyester yarn
with high molecular weight (>
25000 g/mol), and low
carboxyl end group
(<30mmol/kg) for soil
reinforcement application for
stabilization, requirement of
geogrid strength in both
direction with granular fill
(extruded PP geogrids &
Polyester strips & Geostrips &
Steel Strips not allowed).
Coating of Geogrid/
Reinforcing geosynthetic
material with LDPE, Latex,
Bitumen and any other coating
is not accepted.
126
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
(d) Type IV = TFI - TechGrid
TGB 90(90 kN/mx90 KN/m
Ultimate tensile strength),
minimum width of 5.0 Meter, [Link]. 294.0 31.0 265.0 28.0 11 11
as per the approved
Comparative Statement.
127
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
8 Providing and Laying CE
Marked Knitted and PVC
coated Polyester Uniaxial
Geogrid, indigenously
manufactured from selected
high tenacity polyester yarn
with high molecular weight (>
25000 g/mole), and low
carboxyl end group
(<30mmol/kg) for reinforced
soil wall and reinforced slope
application with granular fill as
per design prepared by
technology provider of
reinforced earth wall and
slope.(Reinforcing
geosynthetic product of
extruded PP geogrids &
Polyester strips & Geostrips &
Steel Strips not allowed and
not accepted). The reinforced
earth wall and slope should
have 100% coverage of
Knitted and PVC coated
Polyester Uniaxial Geogrid.
(Coating of Geogrid and
Geosynthetic reinforcing
material with LDPE, Latex,
Bitumen and any other coating
will not be allowed).
128
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
(c) Type-III (TFI - TechGrid
TGU80) (80 KN/m Ultimate
tensile strength), minimum
with of 5.0 Meter, as per the [Link]. 205.0 31.0 185.0 28.0 11 11
approved Comparative
Statement.
129
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
Providing and Laying only CE
Marked Knitted and PVC
coated Polyester Uniaxial
Geogrid-Techgrid indigenously
manufactured from selected
high tenacity polyester yarn
with high molecular weight (>
25000 g/mole), and low
carboxyl end group
(<30mmol/kg) for Reinforced
soil wall (Reinforcing
Geosynthetic product material
of extruded PP geogrids &
Polyester strips & Geostrips &
Steel strips not allowed) with
granular fill of PHi-32 degree
(design is to be carried out in
accordance with BS-8006 /
FHWA) with concrete block
(M35) as facia, casting &
erection of blocks with
Techgrid, providing & laying of
leveling pad of M15, providing
and laying coping beam
(M35), providing and laying
300mm thick filter media etc.
completed as per the
necessary drawing and
instruction of Engineer In
Charge. Excluding providing,
laying and compacting
selected backfill and retained
fill behind the wall, excavation
and ground improvement, if
any. The reinforced earth wall
and slope should have 100%
coverage of 5m width Knitted
(Coating of Geogrid/
Reinforcing geosynthetic
material with LDPE, Latex,
Bitumen and any other coating
will not be allowed and will not
be accepted).
(a) PVC coated polyester
geogrid-Techgrid 1 Meter [Link] 6236.0 1735.0 5618.0 1563.0 11 11
to 4 meter
(b) PVC coated polyester
geogrid-Techgrid 4 Meter [Link] 6805.0 1735.0 6131.0 1563.0 11 11
to 6 meter
130
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
(c) PVC coated polyester
geogrid-Techgrid 6 Meter [Link] 7362.0 1735.0 6632.0 1563.0 11 11
to 8 meter
(d) PVC coated polyester
geogrid-Techgrid 8 Meter [Link] 8252.0 1735.0 7434.0 1563.0 11 11
to 10 meter
(e) PVC coated polyester
geogrid-Techgrid 10 Meter [Link] 9315.0 1735.0 8392.0 1563.0 11 11
to 12 meter
(f) PVC coated polyester
geogrid-Techgrid 14 Meter [Link] 9963.0 1735.0 8976.0 1563.0 11 11
to 16 meter
9 Providing and Laying a Woven
Polypropylene multifilament
Geotextile of indigenously
manufactured from
multifilament polypropylene
yarn on the prepared
subgrade (CBR less than 3%)
as a separator cum drainage
cum reinforcement with
necessary overlaps as per
drawings
131
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
10 Providing and Laying CE
Marked Woven Polypropylene
Geotextile indigenously
manufactured from black UV
stabilized polypropylene flat
tape/ fibrillated tape yarns on
the prepared subgrade (CBR
less than 3%) as a separator
cum Reinforcement with
necessary overlaps having
minimum 5 years Performance
certificate from any State
PWD and as per drawings
132
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
11 Providing and Laying Needle
punched and mechanically
bonded Non-woven Paving
Fabric indigenously
manufactured from high
quality Polypropylene stable
fibers (continuous filament will
not be accepted) over a tack
coat of paving grade bitumen
80-100 preparation, laid at the
rate of 1 kg per Sqm over
thoroughly cleaned and
repaired surface to provide a
water resistant membrane and
crack retarding layer. Paving
fabric to be laid before cooling
of tack coat, brooming and
rolling of surface with
pneumatic roller to maximize
paving fabric contact with
pavement surface as per
drawing and product approval
certificate from M/s CRRI,
New Delhi.
133
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
12 Providing and Fixing Gabions
of only TFI made of
mechanically woven
hexagonal shaped wire mesh
of type, 10X12cm with edges
selvedge made of heavily
(Zinc + PVC) coated GI wires
as per BS:443, mesh wire
2.70mm Ǿ edge wire 3.4mm
Ǿ of only TFI/ TechBox type
filled with 20 kg to 50 kg
weight trap stones including
conveying with all the leads &
lifts and placing at required
places in required line, level,
slope, section as directed etc.
to complete Reinforced Earth
Walls & Slopes as per
Drawing
134
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
13 Providing and Laying only CE
Marked Knitted and PVC
coated Polyester Uniaxial
Geogrid-Techgrid indigenously
manufactured from selected
high tenacity polyester yarn
with high molecular weight (>
25000 g/mole), and low
carboxyl end group
(<30mmol/kg) for Reinforced
soil wall (Reinforcing
Geosynthetic product material
of extruded PP geogrids &
Polyester strips & Geostrips &
Steel strips not allowed) with
granular fill of PHi-32 degree
(design is to be carried out in
accordance with BS-8006 /
FHWA) with concrete block
(M35) as facia, casting &
erection of blocks with
Techgrid, providing & laying of
levelling pad of M15, providing
and laying coping beam
(M35), providing and laying
300mm thick filter media etc.
completed as per the
necessary drawing and
instruction of Engineer In
Charge. Excluding providing,
laying and compacting
selected backfill and retained
fill behind the wall, excavation
and ground improvement, if
any. The reinforced earth wall
and slope should have 100%
coverage of 5m width Knitted
(a) PVC coated polyester
geogrid-Techgrid 1 Meter [Link] 6236.0 1735.0 5618.0 1563.0 11 11
to 4 meter
(b) PVC coated polyester
geogrid-Techgrid 4 Meter [Link] 6805.0 1735.0 6131.0 1563.0 11 11
to 6 meter
(c) PVC coated polyester
geogrid-Techgrid 6 Meter [Link] 7362.0 1735.0 6632.0 1563.0 11 11
to 8 meter
(d) PVC coated polyester
geogrid-Techgrid 8 Meter [Link] 8252.0 1735.0 7434.0 1563.0 11 11
to 10 meter
135
CHAP
TER;- GEOTEXTILE MISC ITEMS
R17
[Link]. %
%
Increase
Increase
Item Labour Item Rate Labour in
Description Unit in item
Rate Rate 2012 Rate 2012 Labour
Rate
Rate
2012
2012
(e) PVC coated polyester
geogrid-Techgrid 10 Meter [Link] 9315.0 1735.0 8392.0 1563.0 11 11
to 12 meter
(f) PVC coated polyester
geogrid-Techgrid 14 Meter [Link] 9963.0 1735.0 8976.0 1563.0 11 11
to 16 meter
11.02 11.00
11.01
136
(A) Usage Rates of Plant and Machinery
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 271 240 13%
P&M-002 Batching and Mixing Plant (a) 30 cum Concrete Mixing cum/hour 20 hour 2109 1850 14%
capacity
P&M-003 Batching and Mixing Plant (b) 15 - 20 cum Concrete Mixing cum/hour 13 hour 1725 1500 15%
capacity
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 744 689 8%
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 224 200 12%
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 2442 2200 11%
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 570 500 14%
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 115 100 15%
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 130 119 9%
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 204 179 14%
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1055 950 11%
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2373 2100 13%
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 1595 1450 10%
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 706 625 13%
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 770 700 10%
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 741 650 14%
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 572 525 9%
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1026 900 14%
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 12000 9500 26%
137
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 11000 9000 22%
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 9000 8000 13%
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 7500 6500 15%
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 1568 1425 10%
P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable cum/hour 60 /60 /60 hour 914 831 10%
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 6704 6150 9%
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 13552 12100 12%
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 271 238 14%
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 184 160 15%
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 1680 1500 12%
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 735 650 13%
P&M-034 Paver Finisher Hydrostatic with sensor Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 1695 1500 13%
control 100 TPH
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 715 650 10%
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment Rm/hour 2 to 3 hour 4158 3850 8%
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1265 1100 15%
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 2998 2750 9%
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 627 550 14%
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 109 95 15%
P&M-043 Road marking machine Road marking Sqm/hour 100 hour 84 75 12%
138
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 224 202 11%
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 935 850 10%
P&M-046 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 km 243 219 11%
P&M-047 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 [Link] 2 2 0%
P&M-048 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 hour 250 219 14%
P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 813 713 14%
P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 [Link] 2 2 0%
P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 690 600 15%
P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 [Link] 2 2 0%
P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 228 200 14%
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 222 200 11%
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 220 200 10%
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 222 200 11%
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 [Link] 2.25 2 13%
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1188 1100 8%
P&M-060 Water Tanker Water Transport capacity in KL 6 hour 130 115 13%
P&M-062 Wet Mix Plant 75 TPH Wet Mix cum/hour 25 hour 944 850 11%
139
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 300 270 11%
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 1512 1350 12%
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 7560 6750 12%
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 1857 1688 10%
P&M-069 Cold milling machine @ 20 cum per hour hour 189 169 12%
P&M-075 Crane with grab 0.75 cum capacity hour 1045 950 10%
P&M-076 Compressor with guniting equipment along with accessories hour 313 282 11%
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 5040 4500 12%
P&M-082 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. hour 6244 5625 11%
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 186 169 10%
P&M-084 Jack for Lifting 40 tonne lifting capacity. day 3713 3375 10%
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 3746 3375 11%
140
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 631 563 12%
P&M-088 Texturing machine (for rigid pavement) hour 250 225 11%
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 687 619 11%
P&M-093 Wet Mix Plant 100 TPH hour 1210 1100 10%
(B) Labour
L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 350 300 17%
141
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
L-12-1 Surveyor / Draftman / computer draftman/ operator day 350 300 17%
142
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
(C) Materials
Rate
Sl. No. Description Unit Rate
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 337 281 20%
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 337 281 20%
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 526 438 20%
M-004 Coarse sand at Mixing Plant (Crusher dust) cum 240 200 20%
M-009 Granular Material or hard murrum for GSB works at Site Cum 240 200 20%
M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 240 200 20%
M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 210 175 20%
M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 300 250 20%
143
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
Rate at
Plant
Description Unit (HMP/Bat Rate at Site Rate at Site #VALUE!
ching)
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 358 358 325 10%
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 358 358 325 10%
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 358 358 325 10%
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 358 358 325 10%
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 330 330 300 10%
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 330 330 300 10%
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm 330 330 300 10%
M-020 Close graded Granular sub-base Material 2.36 mm cum 308 308 280 10%
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 308 308 280 10%
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 308 308 280 10%
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm 330 330 300 10%
M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 358 358 325 10%
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 358 358 325 10%
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 369 369 335 10%
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 369 369 335 10%
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 369 369 335 10%
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 369 369 335 10%
144
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-052 Aggregates 13.2/12.5 mm nominal size cum 670 670 535 25%
145
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-059 Aluminium alloy plate 2mm Thick sqm 4620 4200 10%
M-061 Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling sqm 5500 5000 10%
holes, nuts, bolts [Link] signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 330 300 10%
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 48400 44000 10%
M-066 Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by 14520 10%
the process of vulcanisation,) nos 13200
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 73920 66000 12%
M-068 Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless 123200 12%
steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all comp nos 110000
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 30250 27500 10%
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 30800 27500 12%
M-073 Bitumen Cationic Emulsion SS-2 for Fog seal, crack seal, slurry seal, premix seal coat tonne 47652.00 41900 14%
146
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-077 Bitumen Emulsion Rapid RS-1 for tack coat tonne 40000.00 41900 -5%
M-077-1 Bitumen Emulsion Rapid RS-2 for Surface dressing, Grouting and Penetration macadam tonne 46000.00
M-077-2 Bitumen Emulsion (medium) MS for Patch work, 20mm PMC tonne 41600.00
M-077-3 Bitumen Emulsion (slow) SS-1 for Prime coat- WMM/WBM surface tonne 40400.00
M-082 Cold twisted bars (HYSD Bars) tonne 51000 45600 12%
M-083 Coller for joints 300 mm dia CC nos 275 250 10%
M-089 Credit for excavated rock found suitable for use cum 200 180 11%
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 533 480 11%
M-092 Earth Cost or compensation for earth taken from private land cum 45 45 0%
147
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-093 Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 10656 11%
915.1 of IRC: 83 (part II), metre 9600
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 660 600 10%
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 880 800 10%
M-098 Epoxy resin-hardner mix for prime coat kg 555 500 11%
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 244 220 11%
M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 55 50 10%
148
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 40 36 11%
M-127 Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly metre 8936 8050 11%
comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel
M-128 Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly metre 10304 9200 12%
containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and
M-134 Perforated geosynthetic pipe 150 mm dia metre 258 230 12%
M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 253 230 10%
149
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-137 Pipes 200 mm dia, 2.5 m long for drainage AC metre 138 125 10%
M-137-1 Plastic sheet with back side adhesive , 1.25 mm thick for printing letter sqm 202 180 12%
M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 67 60 12%
M-139 Plastic tubes 50 cm dia, 1.2 m high nos 358 320 12%
M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 271 242 12%
M-142 Pre-coated stone chips of 13.2 mm nominal size cum 1149 1035 11%
M-143 Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for 185 168 10%
the full length of a joint to ensure water tightness. metre
M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 380 345 10%
M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 5152 4600 12%
M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 5693 5175 10%
M-150-1 RCC Pipe NP 4 heavy duty non presure pipe 900 mm dia metre 4500 920 389%
M-150-2 RCC Pipe NP 4 heavy duty non presure pipe 600 mm dia metre 3000
M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 2050
M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 304 276 10%
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 199 178 12%
150
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 177 161 10%
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 275 250 10%
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 258 230 12%
M-159 Sand bags (Cost of sand and Empty cement bag) nos 8 7 14%
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 19 17 12%
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 320 288 11%
M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 7340 6613 11%
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 10304 9200 12%
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 258 230 12%
M-173 Steel helmet and cushion block on top of pile head during driving. kg 58 52 12%
M-175 Steel pipe 50 mm external dia as per IS:1239 metre 258 230 12%
151
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 389 350 11%
M-186 Traffic cones with 150 mm reflective sleeve (Plastic) nos 555 500 11%
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 1277 1150 11%
M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 168 150 12%
M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 13 12 8%
152
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
Overheads for Bridge Works 10 % for input of Overheads or Contractors profit please type in collum C as like
below
Overheads for Bridge Works 10 % Type symble of apostrope(') then input value then one space then symble
(Rehabilitation) of percentage (%) for example '08 %
Lead from Mixing Plant to working site 20 km 1 Km for Chapter 1 to 5 and 20 for other Chapter.
153
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate
per cm
Item 8.3 Printing new letter and figures of any shade (ii) English Roman height per 0.40
letter
Item 8.3 .1 Printing new letter and figures with backgound of any shade over plastic sheet (ii) Hindi / English / Roman sqm 180.00
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 50.00
Item 8.9 Painting angle iron post two coats sqm 50.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 4,615.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 3,788.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 2,647.00
Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 3,899.00
Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 2,868.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 3,879.00
Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,083.00
Item 12.8 (B) PCC PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,441.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,466.00
Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 3,922.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,117.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,751.00
154
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 4,274.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,405.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,779.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,535.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,785.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,435.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,798.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,450.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,884.00
Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 3,754.00
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 4,543.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,646.00
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,790.00
Mixer
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,325.00
Batching Plant
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,967.00
Mixer
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,501.00
Batching Plant
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 4,001.00
Mixer
155
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,536.00
Batching Plant
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 4,079.00
Mixer
Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 4,565.00
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,613.00
Batching Plant
Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 4,406.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 229.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 30.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum
4,475.00
Item 14.1(B) RCC Grade M30 for super-structure including OH & CP by Batching Plant cum
4,952.00
Item 14.1(E) RCC Grade M40 for super-structure including OH & CP by Batching Plant cum
5,446.32
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum
4,143.00
Item 14.1(C) RCC Grade M40 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum
3,452.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 56,932.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 67,899.00
Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 63.00
Item 5.21 Case-II Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 75.00
156
% Increase
Output of Rate 2012 Over BSR
Sl. No. Description of Machine Activity Output Unit Rate 2012 Rates
Machine
Item 5.21 Case-IV Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked sqm 101.00
area above 50 %
Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 503.00
Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 27.00
Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 87.00
Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 72.00
157
This softawre is based on Standard Data book for analysis of Rates for Road and Bridge
Works
This Software runs on Microsoft Excel
INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable
SUMMARY - In this sheet summary of all the rates analysized is presented
ANALYSIS- The analysis has been presented in 16 nos. of spread sheets
Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS
Worksheet- 2 : CHAPTER-2 SITE CLEARANCE
Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE
Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND
SHOULDERS
Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS
Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH
Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD
APPURTENANCES
Worksheet- 9 : CHAPTER-9 PIPE CULVERTS AND CULVERTS
Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS
Worksheet- 11 : CHAPTER-11 HORTICULTURE
Worksheet- 12 : CHAPTER-12 FOUNDATIONS
Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE
Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE
Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS
Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION
GOVERNMENT OF RAJASTHAN
PUBLIC WORKS DEPARTMENT
RATE - ANALYSIS
OF
BASIC SCHEDULE OF RATES MARCH 2013
SUPERINTENDING ENGINEER
PUBLIC WORKS DEPARTMENT
NATIONAL HIGHWAY, CIRCLE JAIPUR
(A) Usage Rates of Plant and Machinery
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 271 240
P&M-002 Batching and Mixing Plant (a) 30 cum Concrete Mixing cum/hour 20 hour 2109 1850
capacity
P&M-003 Batching and Mixing Plant (b) 15 - 20 cum Concrete Mixing cum/hour 13 hour 1725 1500
capacity
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 744 689
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 224 200
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 2442 2200
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 570 500
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 115 100
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 130 119
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 204 179
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2373 2100
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 1595 1450
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 706 625
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 770 700
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 741 650
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 572 525
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1026 900
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 12000 9500
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 11000 9000
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 9000 8000
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 7500 6500
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 1568 1425
P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable cum/hour 60 /60 /60 hour 914 831
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 6704 6150
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 13552 12100
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 271 238
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 184 160
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 1680 1500
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 735 650
P&M-034 Paver Finisher Hydrostatic with sensor Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 1695 1500
control 100 TPH
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 715 650
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment Rm/hour 2 to 3 hour 4158 3850
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1265 1100
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 2998 2750
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 627 550
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 109 95
P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 224 202
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 935 850
P&M-046 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 km 243 219
P&M-047 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 [Link] 2 2
P&M-048 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 hour 250 219
P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 813 713
P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 [Link] 2 2
P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 690 600
P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 [Link] 2 2
1
P&M-053 Tractor Pulling capacity in HP 50 hour 193 175
P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 228 200
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 222 200
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 220 200
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 222 200
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 [Link] 2.25 2
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1188 1100
P&M-062 Wet Mix Plant 75 TPH Wet Mix cum/hour 25 hour 944 850
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 300 270
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 1512 1350
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 7560 6750
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 1857 1688
P&M-069 Cold milling machine @ 20 cum per hour hour 189 169
P&M-075 Crane with grab 0.75 cum capacity hour 1045 950
P&M-076 Compressor with guniting equipment along with accessories hour 313 282
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 5040 4500
P&M-082 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. hour 6244 5625
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 186 169
P&M-084 Jack for Lifting 40 tonne lifting capacity. day 3713 3375
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 3746 3375
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 631 563
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 687 619
2
% Increase
Over BSR
2012 Rates
13%
14%
15%
8%
12%
11%
14%
15%
9%
14%
11%
11%
14%
13%
10%
13%
10%
14%
9%
14%
26%
22%
13%
15%
10%
10%
9%
12%
14%
9%
15%
12%
13%
13%
10%
8%
15%
9%
14%
15%
15%
13%
12%
11%
10%
11%
0%
14%
14%
0%
15%
0%
3
10%
14%
11%
10%
11%
13%
8%
13%
8%
11%
#VALUE!
11%
12%
12%
11%
12%
10%
12%
11%
12%
12%
12%
10%
10%
11%
12%
10%
11%
10%
10%
11%
10%
10%
11%
11%
12%
11%
11%
10%
12%
11%
10%
11%
4
(B) Labour
(C) Materials
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 337
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 337
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 526
M-009 Granular Material or hard murrum for GSB works at Site Cum 240
M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 240
M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 210
M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 300
Rate at
Plant
Description Unit (HMP/Bat Rate at Site
ching)
5
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 358 358
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 358 358
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 358 358
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 358 358
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 330 330
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 330 330
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm 330 330
M-020 Close graded Granular sub-base Material 2.36 mm cum 308 308
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 308 308
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 308 308
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm 330 330
M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 358 358
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 358 358
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 369 369
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 369 369
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 369 369
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 369 369
M-061 Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling sqm 5500
holes, nuts, bolts [Link] signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 330
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 48400
M-066 Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by 14520
the process of vulcanisation,) nos
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 73920
6
M-068 Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless 123200
steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components nos
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 30250
M-071 Bentonite kg 18
M-073 Bitumen Cationic Emulsion SS-2 for Fog seal, crack seal, slurry seal, premix seal coat tonne 47652.00
M-077 Bitumen Emulsion Rapid RS-1 for tack coat tonne 40000.00
M-077-1 Bitumen Emulsion Rapid RS-2 for Surface dressing, Grouting and Penetration macadam tonne 46000.00
M-077-2 Bitumen Emulsion (medium) MS for Patch work, 20mm PMC tonne 41600.00
M-077-3 Bitumen Emulsion (slow) SS-1 for Prime coat- WMM/WBM surface tonne 40400.00
M-089 Credit for excavated rock found suitable for use cum 200
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 533
M-092 Earth Cost or compensation for earth taken from private land cum 45
M-093 Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 10656
915.1 of IRC: 83 (part II), metre
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 660
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 880
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 244
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 40
7
M-123 M.S. Clamps nos 33
Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly
M-127 comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel sections metre 8936
protected against corrosion and installed by the manufacturer or his authorised representative
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly
M-128 containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and control metre 10304
system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative
M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 253
M-137 Pipes 200 mm dia, 2.5 m long for drainage AC metre 138
M-137-1 Plastic sheet with back side adhesive , 1.25 mm thick for printing letter sqm 202
M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 271
M-143 Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for 185
the full length of a joint to ensure water tightness. metre
M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 380
M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 5152
M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 5693
M-150-1 RCC Pipe NP 4 heavy duty non presure pipe 900 mm dia metre 4500
M-150-2 RCC Pipe NP 4 heavy duty non presure pipe 600 mm dia metre 3000
M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 2050
M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 304
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 199
M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 177
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 275
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 258
M-159 Sand bags (Cost of sand and Empty cement bag) nos 8
M-162 Seeds kg 77
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 19
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 320
M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 7340
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 10304
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 258
M-173 Steel helmet and cushion block on top of pile head during driving. kg 58
8
M-177 Steel wire rope 40 mm kg 77
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 389
M-186 Traffic cones with 150 mm reflective sleeve (Plastic) nos 555
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 1277
M-189 Water KL 64
M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 13
9
Overheads for Road Works 10 %
Overheads for Bridge Works 10 % for input of Overheads or Contractors profit please type in collum C as like
below
Overheads for Bridge Works 10 % Type symble of apostrope(') then input value then one space then symble
(Rehabilitation) of percentage (%) for example '08 %
Lead from Mixing Plant to working site 20 km 1 Km for Chapter 1 to 5 and 20 for other Chapter.
10
Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate
per cm
Item 8.3 Printing new letter and figures of any shade (ii) English Roman height per 0.40
letter
Item 8.3 .1 Printing new letter and figures with backgound of any shade over plastic sheet (ii) Hindi / English / Roman sqm 180.00
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 50.00
Item 8.9 Painting angle iron post two coats sqm 50.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 4,615.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 3,788.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 2,647.00
Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 3,899.00
Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 2,868.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 3,879.00
Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,083.00
Item 12.8 (B) PCC PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,441.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,466.00
Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 3,922.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,117.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,751.00
Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 4,274.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,405.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,779.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,535.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,785.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,435.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,798.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,450.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,884.00
Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 3,754.00
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 4,543.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,646.00
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,790.00
Mixer
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,325.00
Batching Plant
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,967.00
Mixer
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,501.00
Batching Plant
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 4,001.00
Mixer
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,536.00
Batching Plant
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 4,079.00
Mixer
Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 4,565.00
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,613.00
Batching Plant
Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 4,406.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 229.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 30.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum
4,475.00
Item 14.1(B) RCC Grade M30 for super-structure including OH & CP by Batching Plant cum
4,952.00
Item 14.1(E) RCC Grade M40 for super-structure including OH & CP by Batching Plant cum
5,446.32
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum
4,143.00
11
Item 14.1(C) RCC Grade M40 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum
3,452.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 56,932.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 67,899.00
Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 63.00
Item 5.21 Case-II Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 75.00
Item 5.21 Case-IV Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked sqm 101.00
area above 50 %
Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 503.00
Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 27.00
Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 87.00
Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 72.00
12
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
1.1 Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity 13 Min
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 250.00 82.50 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 770.00 254.10 P&M-017
cum/hour
b) Overheads @ 10 % on (a) 33.66
c) Contractors profit @ 10 % on (a+b) 37.03
Cost for 5.5 cum = a+b+c 407.29
Rate per cum = (a+b+c)/ 5.5 74.05
Note Unloading will be by tipping. say 74.00
1.4 Cost of Haulage Excluding Loading and Unloading
13
Cost for 100 t .km = a+b+c 251.08
Rate per [Link] = (a+b+c)/100 2.51
say 2.50
1.4(III) Case III Katcha Track and Track in river bed / nallah bed and
choe bed.
Speed with load : 10 km / hour
Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 250.00 250.00 P&M-048
Time taken for empty return trip hour 0.670 250.00 167.50 P&M-048
b) Overheads @ 10 % on (a) 41.75
c) Contractors profit @ 10 % on (a+b) 45.93
Cost for 100 t .km = a+b+c 505.18
Rate per [Link] = (a+b+c)/100 5.05
say 5.10
1.5 Hand Broken Stone Aggregates 63 mm nominal size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 300.00 18.00 L-12
Mazdoor day 1.500 225.00 337.50 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 337.00 370.70 M-002
c) Overheads @ 10 % on (a+b) 72.62
d) Contractors profit @ 10 % on (a+b+c) 79.88
Rate per cum = a+b+c+d 878.70
say 879.00
1.6 Crushing of stone aggregates 13.2 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 300.00 228.00 L-12
Mazdoor Skilled day 2.000 225.00 450.00 L-14
Mazdoor including breaking of any oversize boulder. day 17.000 225.00 3825.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 337.00 269600.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 13552.00 81312.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 770.00 15400.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 250.00 5000.00 P&M-048
d) Overheads @ 10 % on (a+b+c) 37581.50
e) Contractors profit @ 10 % on (a+b+c+d) 41339.65
14
Cost for 600 cum = a+b+c+d+e 454736.15
Rate per cum = (a+b+c+d+e)*0.95/600 720.00
say 720.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a by-
product.
Unit : cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 300.00 228.00 L-12
Mazdoor Skilled day 2.000 225.00 450.00 L-14
Mazdoor including breaking of any size boulder. day 17.000 225.00 3825.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 337.00 269600.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 13552.00 81312.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 770.00 15400.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 250.00 5000.00 P&M-048
d) Overheads @ 10 % on (a+b+c) 37581.50
e) Contractors profit @ 10 % on (a+b+c+d) 41339.65
Cost for 670 cum = a+b+c+d+e 454736.15
Rate per cum = (a+b+c+d+e)*0.90/670 610.84
say 611.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust
which comes out as a by-product.
Unit : cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 300.00 228.00 L-12
15
Mazdoor Skilled day 2.000 225.00 450.00 L-14
Mazdoor day 17.000 225.00 3825.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 337.00 269600.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 13552.00 81312.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 770.00 15400.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 250.00 5000.00 P&M-048
d) Overheads @ 10 % on (a+b+c) 37581.50
e) Contractors profit @ 10 % on (a+b+c+d) 41339.65
Cost for 750 cum = (a+b+c+d+e)x0.85 386525.73
Rate per cum = (a+b+c+d+e)x0.85/750 515.37
say 515.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust
which comes out as a by-product.
Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 300.00 132.00 L-12
Mazdoor day 9.000 225.00 2025.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 184.00 1324.80 P&M-031
Air compressor 250 cfm hour 7.200 271.00 1951.20 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 1568.00 9408.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 250.00 1500.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Bitumen pressure distributor hour 6.000 744.00 4464.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 224.00 1344.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 49100.00 530280.00 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 680.00 91800.00 M-053
cum per sqm
d) Overheads @ 10 % on (a+b+c) 64934.90
e) Contractors profit @ 10 % on (a+b+c+d) 71428.39
Cost for 9000 sqm= a+b+c+d+e 785712.29
16
Rate per sqm = (a+b+c+d+e)/9000 87.30
say 87.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 300.00 132.00 L-12
Mazdoor day 9.000 225.00 2025.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 184.00 1324.80 P&M-031
Air compressor 250 cfm hour 7.200 271.00 1951.20 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 1568.00 9408.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 250.00 1500.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1188.00 7128.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 49100.00 441900.00 M-074
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 670.00 60300.00 M-052
cum per sqm
d) Overheads @ 10 % on (a+b+c) 53525.30
e) Contractors profit @ 10 % on (a+b+c+d) 58877.83
Cost for 9000 sqm= a+b+c+d+e 647656.13
Rate per sqm = (a+b+c+d+e)/9000 71.96
say 72.00
Note [Link] the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Mechanical broom hour 6.000 184.00 1104.00 P&M-031
17
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Mobile slurry seal equipment hour 6.000 735.00 4410.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 250.00 1500.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1265.00 7590.00 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
c) Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11 tonne 19.360 40000.00 774400.00 M-077
Fine aggregate 4.75 mm and below 87 % of total cum 102.080 683.00 69720.64 M-005
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5,= 153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02 tonne 3.520 3885.00 13675.20 M-188
Cost of water KL 12.000 64.00 768.00 M-189
d) Overheads @ 10 % on (a+b+c) 88109.58
e) Contractors profit @ 10 % on (a+b+c+d) 96920.54
Cost for 16000 sqm= a+b+c+d+e 1066125.97
Rate per sqm = (a+b+c+d+e)/16000 66.63
say 67.00
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 5.000 225.00 1125.00 L-13
b) Machinery
Mechanical broom hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Mobile slurry seal equipment hour 6.000 735.00 4410.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 250.00 1500.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
c) Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13 tonne 17.160 40000.00 686400.00 M-077
Fine aggregate 3 mm and below 85 % of total mix, 60x cum 74.800 683.00 51088.40 M-005
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02 tonne 2.640 3885.00 10256.40 M-188
Cost of water KL 12.000 64.00 768.00 M-189
d) Overheads @ 10 % on (a+b+c) 76321.78
e) Contractors profit @ 10 % on (a+b+c+d) 83953.96
Cost for 30000 sqm= a+b+c+d+e 923493.54
Rate per sqm = (a+b+c+d+e)/20000 46.17
say 46.00
Case III 1.5 mm thickness
18
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 5.000 225.00 1125.00 L-13
b) Machinery
Mechanical broom hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Mobile slurry seal equipment hour 6.000 735.00 4410.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 250.00 1500.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
c) Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16 tonne 12.670 40000.00 506800.00 M-077
Fine aggregate 2.36 mm and below,82 % of total cum 43.300 308.00 13336.40 M-022
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x 0.02 tonne 1.580 3885.00 6138.30 M-188
Cost of water KL 12.000 64.00 768.00 M-189
d) Overheads @ 10 % on (a+b+c) 54174.77
e) Contractors profit @ 10 % on (a+b+c+d) 59592.25
Cost for 24000 sqm= a+b+c+d+e 655514.72
Rate per sqm = (a+b+c+d+e)/24000 27.31
say 27.00
Note [Link] coat, if required to be provided, before laying slurry
seal may be measured and paid separately
19
Rate per sqm = (a+b+c+d+e)/10500 37.23
say 37.00
[Link] case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor for precoating of grit day 4.000 225.00 900.00 L-13
c) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 358.00 9397.50 M-024
Bitumenemulsion for precoating grit @ 2 % of tonne 0.790 40000.00 31600.00 M-077
grit,39.38 x 0.02
41945.50
3.99
say 4.00
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Hydraulic Chip spreader hour 6.000 1568.00 9408.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 224.00 1344.00 P&M-044
c) Material
Modified binder tonne 9.450 48800.00 461160.00 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 670.00 70350.00 M-050
d) Overheads @ 10 % on (a+b+c) 55087.80
e) Contractors profit @ 10 % on (a+b+c+d) 60596.58
Cost for 10500 sqm= a+b+c+d+e 666562.38
Rate per sqm = (a+b+c+d+e)/10500 63.48
say 63.00
20
Case - II Stress Absorbing Membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 271.00 1626.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Hydraulic Chip spreader hour 6.000 1568.00 9408.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 224.00 1344.00 P&M-044
c) Material
Modified binder tonne 11.550 48800.00 563640.00 M-078
Crushed stone chipping 11.2 mm size cum 105.000 670.00 70350.00 M-051
d) Overheads @ 10 % on (a+b+c) 65335.80
e) Contractors profit @ 10 % on (a+b+c+d) 71869.38
Cost for 10500 sqm= a+b+c+d+e 790563.18
Rate per sqm = (a+b+c+d+e)/10500 75.29
say 75.00
Case III Stress Absorbing Membrane (SAM) crack width above 9
mm and cracked area above 50 %
Providing and laying a single coatn of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 kg per 10 sqm
and spreading 11.2 mm crushed stone aggregates @ 0.12
cum per 10 sqm, sweeping the surface for uniform spread
of aggregates and surface finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 271.00 1626.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
21
Hydraulic Chip spreader hour 6.000 1568.00 9408.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 224.00 1344.00 P&M-044
c) Material
Modified binder tonne 15.750 48800.00 768600.00 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 670.00 84420.00 M-051
d) Overheads @ 10 % on (a+b+c) 87288.80
e) Contractors profit @ 10 % on (a+b+c+d) 96017.68
Cost for 10500 sqm= a+b+c+d+e 1056194.48
Rate per sqm = (a+b+c+d+e)/10500 100.59
say 101.00
Case IV Case - IV : Bitumen Impregnated Geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 704.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 300.00 168.00 L-12
Mazdoor day 12.000 225.00 2700.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Air compressor 250 cfem capacity hour 2.800 271.00 758.80 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 744.00 1488.00 P&M-004
Pneumatic roller hour 2.000 1265.00 2530.00 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 48100.00 177008.00 M-075
kg per sqm
Geotextile including 10 % for overlaps sqm 3850.000 330.00 1270500.00 M-108
d) Overheads @ 10 % on (a+b+c) 145616.80
e) Contractors profit @ 10 % on (a+b+c+d) 160178.48
Cost for 10500 sqm= a+b+c+d+e 1761963.28
Rate per sqm = (a+b+c+d+e)/3500 503.42
say 503.00
NOTE As bitumen overlay construction shallfollow closely the fabric
placement on the same day, an output of 3500 sqm only
has been considered for the analysis which will cover a
length of 500 m, of 7 m widecarriagway. This can be
conveniently overlaid by a bitumenious course in a day
22
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 300 21.00
Painter Ist class day 1.25 350 437.50
Mazdoor day 0.50 225 112.50
b) Material
Paint Litre 0.50 171 85.50
c) Overheads @ 10 % on (a+b) 65.65
d) Contractors profit @ 10 % on (a+b+c) 72.22
Cost for 1600 cm = a+b+c+d 794.37
Rate per cm height per letter = (a+b+c +d)/1600 0.50
say 0.50
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.12 300 36.00
Painter day 2.00 350 700.00
Mazdoor day 1.00 225 225.00
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.00 190 1140.00
23
Cost for 10 sqm = a+b+c+d 530.75
Rate per sqm = (a+b+c+d)/10 53.08
say 53.00
12.6 Sub- Cement mortar1:3 (1cement :3 sand)
analysis
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.51 5600.00 2856.00
Sand cum 1.05 683.00 717.15
b) Labour
Mate day 0.04 300.00 12.00
Mazdoor day 0.90 225.00 202.50
Total Material and Labour = (a+b) 3788.00
Unit = cum
Taking output = 5 cum
(A) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 773.00 4251.50 M-169
Through and bond stone each 35.00 38.00 1330.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 3788.00 5682.00 Item 12.6
analysis) (A)
b) Labour
Mate day 0.66 300.00 198.00 L-12
24
Mason day 7.50 350.00 2625.00 L-11
Mazdoor day 9.00 225.00 2025.00 L-13
c) Overhead charges @ 10 % on (a+b) 1611.15
d) Contractor's profit @ 10 % on (a+b+c) 1772.27
Cost for 5 cum = a+b+c+d 19494.92
Rate per cum (a+b+c+d)/5 3898.98
say 3899.00
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 383.00 2106.50
Through and bond stone Nos 35.00 38.00 1330.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A) cum 1.55 3788.00 5871.40
b) Labour
Mate day 0.62 300.00 186.00
Mason day 6.00 350.00 2100.00
Mazdoor day 9.00 225.00 2025.00
c) Overheads @ 10 % on (a+b) 1361.89
d) Contractors profit @ 10 % on (a+b+c) 1498.08
Cost for 5 cum = a+b+c+d 16478.87
Rate per cum (a+b+c+d)/5 3295.77
say 3296.00
@ The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
12.7 (Add) 1400 Stone masonry work in cement mortar 1:6 in foundation
complete as drawing and Technical Specification
Unit = cum
Taking output = 5 cum
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 383.00 2106.50
Through and bond stone Nos 35.00 38.00 1330.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D) cum 1.55 2647.00 4102.85
b) Labour
Mate day 0.62 300.00 186.00
Mason day 6.00 350.00 2100.00
Mazdoor day 9.00 225.00 2025.00
c) Overheads @ 10 % on (a+b) 1185.04
d) Contractors profit @ 10 % on (a+b+c) 1303.54
Cost for 5 cum = a+b+c+d 14338.92
Rate per cum (a+b+c+d)/5 2867.78
say 2868.00
@ The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
25
12.8 1500, 1700 Plain/Reinforced cement concrete in open foundation
& 2100 complete as per drawing and technical specifications
26
b) Labour
Mate day 0.86 300.00 258.00
Mason day 1.50 350.00 525.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
Generator 33 KVA hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,466.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 5600.00 233296.00
Coarse Sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Lead beyond 1 km, L-lead in km T-km 300L 2.00 12000.00 L= 20
Concrete Pump hour 6 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,117.00
d) Formwork @ 4% on cost of concrete [Link] of material, 14958.52
labour and machinery
e) Overheads @ 10 % on (a+b+c+d) 38892.15
f) Contractors profit @ 10 % on (a+b+c+d+e) 42781.37
Cost for 120 cum = a+b+c+d+e+f 470595.04
Rate per cum = ( a+b+c+d+e+f )/120 3921.63
say 3922.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 5.99 5600.00 33544.00
Coarse sand cum 6.75 683.00 4610.25
40 mm Aggregate cum 5.40 660.00 3564.00
20 mm Aggregate cum 5.40 680.00 3672.00
10 mm Aggregate cum 2.70 670.00 1809.00
b) Labour
Mate day 0.86 300.00 258.00
Mason day 1.50 350.00 525.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
Generator 33 KVA hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,751.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
27
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 5600.00 268520.00
Coarse sand cum 54.00 240.00 12960.00
40 mm Aggregate cum 43.20 660.00 28512.00
20 mm Aggregate cum 43.20 680.00 29376.00
10 mm Aggregate cum 21.60 670.00 14472.00
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 2.00 12000.00 L= 20
1 Km, L - lead in Kilometer
Concrete Pump hour 6 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,405.00
d) Formwork @ 3.75% of cost of concrete [Link] of 15320.21
material, labour and machinery
e) Overheads @ 10 % on (a+b+c+d) 42385.92
f) Contractors profit @ 10 % on (a+b+c+d+e) 46624.51
cost of 120 cum = a+b+c+d+e+f 512869.65
Rate per cum (a+b+c+d+e+f)/120 4273.91
say 4274.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 5600.00 33880.00
Coarse sand cum 6.75 683.00 4610.25
20 mm Aggregate cum 8.10 680.00 5508.00
10 mm Aggregate cum 5.40 670.00 3618.00
b) Labour
Mate day 0.86 300.00 258.00
Mason day 1.50 350.00 525.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
Generator 33 KVA hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,779.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.38 5600.00 270928.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
Admixer Kg 193.52 65.00 12578.80
b) Labour
28
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity 1 cum hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 2.00 12000.00 L= 20
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,535.00
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 5600.00 34048.00
Coarse sand cum 6.75 683.00 4610.25
40 mm Aggregate cum 5.40 660.00 3564.00
20 mm Aggregate cum 5.40 680.00 3672.00
10 mm Aggregate cum 2.70 670.00 1809.00
b) Labour
Mate day 0.86 300.00 258.00
Mason day 1.50 350.00 525.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
Generator 33 KVA hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,785.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.60 5600.00 272160.00
Coarse sand cum 54.00 240.00 12960.00
40 mm Aggregate cum 43.20 660.00 28512.00
20 mm Aggregate cum 43.20 680.00 29376.00
10 mm Aggregate cum 21.60 670.00 14472.00
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 2.00 12000.00 L= 20
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,435.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
29
Taking output = 15 cum
a) Material
Cement MT 6.10 5600.00 34160.00
Coarse sand cum 6.75 683.00 4610.25
20 mm Aggregate cum 8.10 680.00 5508.00
10 mm Aggregate cum 5.40 670.00 3618.00
b) Labour
Mate day 0.86 300.00 258.00
Mason day 1.50 350.00 525.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
Generator 33 KVA hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,798.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 5600.00 273280.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 2.00 12000.00 L= 20
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,450.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.33 5600.00 35448.00
Coarse sand cum 6.75 683.00 4610.25
20 mm Aggregate cum 8.10 680.00 5508.00
10 mm Aggregate cum 5.40 670.00 3618.00
b) Labour
Mate day 0.86 300.00 258.00
Mason day 1.50 350.00 525.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
Generator 33 KVA hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,884.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
30
Taking Output = 120 cum
a) Material
Cement MT 50.64 5600.00 283584.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
Admixer Kg 202.56 65.00 13166.40
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 2.00 12000.00 L= 20
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,646.00
d) Formwork @ 3% on cost of concrete [Link] of material, 13122.52
labour and machinery
e) Overheads @ 10 % on (a+b+c+d) 45053.99
f) Contractors profit @ 10 % on (a+b+c+d+e) 49559.39
cost of 120 cum = a+b+c+d+e+f 545153.31
Rate per cum (a+b+c+d+e+f)/120 4542.94
say 4543.00
Rate per cum (a+b+c+d)/120 Excluding OH & CP 3754.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.
C Bottom Plug
Concrete to be placed using tremie pipe
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 5600.00 31080.00
Coarse sand cum 6.75 683.00 4610.25
40 mm Aggregate cum 5.40 660.00 3564.00
20 mm Aggregate cum 5.40 680.00 3672.00
10 mm Aggregate cum 2.70 670.00 1809.00
Admixer Kg 18.60 65.00 1209.00
b) Labour
Mate day 0.90 300.00 270.00
Mason day 1.50 350.00 525.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
31
Generator 33 KVA hour 6.00 500.00 3000.00
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 304.00 1824.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3790.00
Note 10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 5600.00 248640.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
Admixer Kg 148.80 65.00 9672.00
b) Labour
Mate day 0.88 300.00 264.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 2.00 12000.00 L= 20
lead in Kilometer
Concrete Pump hour 6.00 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3325.00
32
a) Material
Cement MT 47.88 5600.00 268128.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
Admixer Kg 172.80 65.00 11232.00
b) Labour
Mate day 0.88 300.00 264.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 2.00 12000.00 L= 20
lead in Kilometer
Concrete Pump hour 6.00 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3501.00
33
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader 1 cum capacity hour 6.00 770.00 4620.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 2.00 12000.00 L= 20
lead in Kilometer
Concrete Pump hour 6.00 570.00 3420.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3536.00
(iv) PCC Grade M35
34
Add 5% of cost of material and labour towards cost of 19206.60
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 5600.00 283584.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader(capacity 1 cum) hour 6.00 770.00 4620.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 12000.00 L= 20
Concrete Pump hour 6.00 570.00 3420.00
Formwork @ 3% of (a+b+c) 12727.53
d) Overheads @ 10 % on (a+b+c) 43697.85
e) Contractors profit @ 10 % on (a+b+c+d) 48067.64
cost of 120 cum = a+b+c+d+e 528744.02
Rate per cum (a+b+c+d+e)/120 4406.20
Say 4406.00
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.
35
a) Labour
Mate day 0.320 300.00 96.00 L-12
Mazdoor day 8.000 225.00 1800.00 L-13
b) Overheads @ 10 % on (a) 189.60
c) Contractors profit @ 10 % on (a+b) 208.56
Cost for 10 cum = a+b+c 2294.16
Rate per cum = (a+b+c)/10 229.42
say 229.00
Note Cost of dewatering may be added where required upto 10 %
of labour cost Assessment for dewatering shall be made as
per site conditions..
B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 300 96.00
Mazdoor day 8.00 225 1800.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 914 5484.00
c) Overheads @ 10 % on (a+b) 738.00
d) Contractors profit @ 10 % on (a+b+c) 811.80
Cost for 300 cum = a+b+c+d 8929.80
Rate per cum = (a+b+c+d)/300 29.77
say 30.00
Note Cost of dewatering upto 5% of (a+b) may be added, where
required. Assessment for dewatering shall be made as per
site conditions..
36
Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 40.92 5600.00 229152.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader hour 6.00 770.00 4620.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 813.00 12195.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 12000.00 L= 20
Concrete Pump hour 6.00 570.00 3420.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 369819.00
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.95 5600.00 268520.00
Coarse sand cum 54.20 240.00 13008.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
b) Labour
Mate day 0.84 300.00 252.00
Mason day 3.00 350.00 1050.00
Mazdoor day 18.00 225.00 4050.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader hour 6.00 770.00 4620.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 813.00 12195.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 12000.00 L= 20
Concrete Pump hour 6.00 570.00 3420.00
37
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 409235.00
For formwork and staging add the following:
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 409235.00
120 cum
d) Formwork and staging 20 % of (a+b+c) 20.00 81847.00
e) Overheads @ 10 % on (a+b+c+d) 49108.20
f) Contractors profit @ 10 % on (a+b+c+d+e) 54019.02
Cost for 15 cum= a+b+c+d+e+f 594209.22
Rate per cum (a+b+c+d+e+f)/120 4951.74
say 4952.00
C RCC Grade M 30
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.79 5600.00 273224.00
Coarse sand cum 54.60 240.00 13104.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
b) Labour
Mate day 0.88 300.00 264.00
Mason day 3.00 350.00 1050.00
Mazdoor day 19.00 225.00 4275.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader hour 6.00 770.00 4620.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 813.00 12195.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 12000.00 L= 20
Concrete Pump hour 6.00 570.00 3420.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 414272.00
For formwork and staging add the following:
38
E PSC Grade M-40
Case 1 Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.45 5600.00 36120.00
Coarse sand cum 6.75 683.00 4610.25
20 mm Aggregate cum 8.10 680.00 5508.00
10 mm Aggregate cum 5.40 670.00 3618.00
Admixture @ 0.4% of cement kg 25.80 65.00 1677.00
b) Labour
Mate day 0.96 300.00 288.00
Mason day 2.00 350.00 700.00
Mazdoor day 22.00 225.00 4950.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00
Generator 33 KVA hour 6.00 500.00 3000.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum 61252.00
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 51.60 5600.00 288960.00
Coarse sand cum 54.00 240.00 12960.00
20 mm Aggregate cum 64.80 680.00 44064.00
10 mm Aggregate cum 43.20 670.00 28944.00
Admixture @ 0.4% of cement kg 206.40 65.00 13416.00
Admixer Kg 216.00 65.00 14040.00
b) Labour
Mate day 0.94 300.00 282.00
Mason day 3.50 350.00 1225.00
Mazdoor day 20.00 225.00 4500.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00
Generator 100 KVA hour 6.00 743.00 4458.00
Loader hour 6.00 770.00 4620.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 813.00 12195.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 12000.00 L= 20
Concrete Pump hour 6.00 570.00 3420.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 457738.00
For formwork and staging add the following:
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 457738.00
120 cum
d) Formwork and staging 18 % of (a+b+c) 18.00 82392.84
e) Overheads @ 10 % on (a+b+c+d) 54013.08
f) Contractors profit @ 10 % on (a+b+c+d+e) 59414.39
Cost for 15 cum= a+b+c+d+e+f 653558.32
Rate per cum (a+b+c+d+e+f)/120 5446.32
say 5446.00
39
Note [Link] ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
40
RATE OF BITUMENOUS MATERIALS
Basic Hr.
Educatio Carriage Grand Total
Type of price of Excise Educatio VAT @ Entry Tax Total 5 + 6 Rate
[Link]. nal cess Total 3 + 4 Km per 10
bitumen refinery Duty 14% nal cess 4% @ 4% +7 adopted
@ 3% Tonne + 11
Rs. @ 1%
1 2 3 4 5 6 7 8 9 10 11 12 13
1 80/100
Penetration 36780.00 5149.00 1103.00 368.00 43400.00 1736.00 1736.00 46872.00 1200.00 48072.00 48100.00
grade VG10
2 60/70
Penetration 37580.00 5261.00 1127.00 376.00 44344.00 1773.76 1773.76 47891.52 1200.00 49091.52 49100.00
grade VG 30
3 CRMB 60
Modified 37370.00 5232.00 1121.00 374.00 44097.00 1763.88 1763.88 47624.76 1200.00 48824.76 48800.00
grade
4 PMB 40
Modified 54858.00 0.00 0.00 0.00 54858.00 2194.32 2194.32 59246.64 1200.00 60446.64 60400.00
grade
5 Bitumen
Emulsion
Rapid RS-1 30450.00 4263.00 914.00 305.00 35932.00 1437.28 1437.28 38806.56 1200.00 40006.56 40000.00
for tack coat
6 Cationic
Emulsion SS-
2 for Fog
seal, crack 36746.00 0.00 0.00 0.00 36746.00 1469.84 1469.84 39685.68 1200.00 40885.68 40900.00
seal, slurry
seal, premix
seal coat
7 Cutback
Bitumen 41338.00 5787.00 1240.00 413.00 48778.00 1951.12 1951.12 52680.24 1200.00 53880.24 53900.00
MC800
8 Bitumen
Emulsion
Rapid RS-2
for Surface
dressing, 41476.00 0.00 0.00 0.00 41476.00 1659.04 1659.04 44794.08 1200.00 45994.08 46000.00
Grouting and
Penetration
macadam
9 Bitumen
Emulsion
(medium) MS
for Patch 37453.00 0.00 0.00 0.00 37453.00 1498.12 1498.12 40449.24 1200.00 41649.24 41600.00
work, 20mm
PMC
10 Bitumen
Emulsion
(slow) SS-1
for Prime 36276.00 0.00 0.00 0.00 36276.00 1451.04 1451.04 39178.08 1200.00 40378.08 40400.00
coat-
WMM/WBM
surface
41
CHAPTER-1
CARRIAGE OF MATERIALS
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
1.1 Loading and Unloading of Stone Boulder/Stone cum
aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 13 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 250.00 82.50 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 770.00 254.10 P&M-017
cum/hour
b) Overhead charges @ 10 % on (a) 33.66
c) Contractor's profit @ 10 % on (a+b) 37.03
Cost for 5.5 cum = a+b+c 407.29
Rate per cum = (a+b+c)/ 5.5 74.05
Note Unloading will be by tipping. say 74.00
1.2 Loading and Unloading of Boulders by Manual Means
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 300.00 33.00 L-12
Mazdoor for loading and unloading day 0.750 225.00 168.75 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 250.00 187.50 P&M-048
c) Overhead charges @ 10 % on (a+b) 38.93
d) Contractor's profit @ 10 % on (a+b+c) 42.82
Cost for5.5 cum = a+b+c+d 470.99
Rate per cum = (a+b+c+d)/5.5 85.64
Note Unloading will be by tipping. say 86.00
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor for loading and unloading day 2.000 225.00 450.00 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 222.00 444.00 P&M-057
c) Overhead charges @ 10 % on (a+b) 91.80
d) Contractor's profit @ 10 % on (a+b+c) 100.98
Cost for10 tonnes = a+b+c+d 1110.78
Rate per tonnes = (a+b+c+d)/10 111.08
say 111.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = [Link]
Taking output 10 tonnes load and lead 10 km = 100 [Link]
42
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
cost for 100 t km = a+b+c 208.73
Rate per [Link] = (a+b+c)/100 2.09
say 2.10
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.500 250.00 125.00 P&M-048
Time taken for empty return trip hour 0.330 250.00 82.50 P&M-048
b) Overhead charges @ 10 % on (a) 20.75
c) Contractor's profit @ 10 % on (a+b) 22.83
Cost for 100 t .km = a+b+c 251.08
Rate per [Link] = (a+b+c)/100 2.51
say 2.50
1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and
Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 250.00 250.00 P&M-048
Time taken for empty return trip hour 0.670 250.00 167.50 P&M-048
b) Overhead charges @ 10 % on (a) 41.75
c) Contractor's profit @ 10 % on (a+b) 45.93
Cost for 100 t .km = a+b+c 505.18
Rate per [Link] = (a+b+c)/100 5.05
say 5.10
1.5 Hand Broken Stone Aggregates 63 mm Nominal Size
Unit = cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 300.00 228.00 L-12
Mazdoor Skilled day 2.000 225.00 450.00 L-14
Mazdoor including breaking of any oversize boulder. day 17.000 225.00 3825.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 337.00 269600.00 M-001
43
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 13552.00 81312.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 770.00 15400.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 250.00 5000.00 P&M-048
d) Overhead charges @ 10 % on (a+b+c) 37581.50
e) Contractor's profit @ 10 % on (a+b+c+d) 41339.65
Cost for 600 cum = a+b+c+d+e 454736.15
Rate per cum = (a+b+c+d+e)*0.95/600 720.00
say 720.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the
production of 600 cum of stone chips of 13.2 mm size and
balance 5 per cent to the production of stone dust which
comes out as a by-product.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 300.00 228.00 L-12
Mazdoor Skilled day 2.000 225.00 450.00 L-14
Mazdoor including breaking of any size boulder. day 17.000 225.00 3825.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 337.00 269600.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 13552.00 81312.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 770.00 15400.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 250.00 5000.00 P&M-048
d) Overhead charges @ 10 % on (a+b+c) 37581.50
e) Contractor's profit @ 10 % on (a+b+c+d) 41339.65
Cost for 670 cum = a+b+c+d+e 454736.15
Rate per cum = (a+b+c+d+e)*0.90/670 610.84
say 611.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the
production of 670 cum of stone aggregates of 20mm size
and balance 10 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
Unit = cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 300.00 228.00 L-12
Mazdoor Skilled day 2.000 225.00 450.00 L-14
44
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor day 17.000 225.00 3825.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 337.00 269600.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 13552.00 81312.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 770.00 15400.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 250.00 5000.00 P&M-048
d) Overhead charges @ 10 % on (a+b+c) 37581.50
e) Contractor's profit @ 10 % on (a+b+c+d) 41339.65
Cost for 750 cum = (a+b+c+d+e)x0.85 386525.73
Rate per cum = (a+b+c+d+e)x0.85/750 515.37
say 515.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the
production of 750 cum of stone aggregates of 40mm size
and balance 15 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
45
CHAPTER-2
SITE CLEARANCE
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
2.1 201 Cutting of Trees, including cutting of
Trunks, Branches and Removal
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoors for cutting trees day 0.600 225.00 135.00 L-13
including cutting, refilling,
compaction of backfilling and
stacking of serviceable materials
within 1000 metres lead by manual
means.
b) Machinery
Tractor-trolley hour 0.100 193.00 19.30 P&M-053
c) Overhead charges @ 10 % on 16.03
(a+b)
d) Contractor's profit @ 10 % on 17.63
(a+b+c)
Rate for each tree = a+b+c+d 193.96
say 194.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoors for cutting trees day 0.900 225.00 202.50 L-13
including cutting, refilling,
compaction of backfilling, and
stacking of serviceable materials
within 1000 metres lead by manual
means
b) Machinery
Tractor-trolley hour 0.300 193.00 57.90 P&M-053
c) Overhead charges @ 10 % on 27.24
(a+b)
d) Contractor's profit @ 10 % on 29.96
(a+b+c)
Rate for each tree = a+b+c+d 329.60
say 330.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoors for cutting trees day 2.000 225.00 450.00 L-13
including cutting, refilling,
compaction of backfilling and
stacking of serviceable materials
within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 193.00 77.20 P&M-053
c) Overhead charges @ 10 % on 55.12
(a+b)
d) Contractor's profit @ 10 % on 60.63
(a+b+c)
Rate for each tree = a+b+c+d 666.95
say 667.00
2.1 (iv) Girth above 1800 mm
a) Labour
46
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.160 300.00 48.00 L-12
Mazdoors for cutting trees day 4.000 225.00 900.00 L-13
including cutting, refilling,
compaction of backfilling and
stacking of serviceable materials
within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 193.00 115.80 P&M-053
c) Overhead charges @ 10 % on 106.38
(a+b)
d) Contractor's profit @ 10 % on 117.02
(a+b+c)
Rate for each tree = a+b+c+d 1287.20
say 1287.00
2.2 201 Clearing Grass and Removal of
Rubbish
Clearing grass and removal of rubbish
up to a distance of 50 metres outside
the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 300.00 600.00 L-12
Mazdoor day 50.000 225.00 11250.00 L-13
b) Overhead charges @ 10 % on 1185.00
(a)
c) Contractor's profit @ 10 % on 1303.50
(a+b)
Rate per Hectare = a+b+c 14338.50
say 14339.00
2.3 201 Clearing and Grubbing Road Land .
Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 300.00 1800.00 L-12
Mazdoor day 150.000 225.00 33750.00 L-13
b) Machinery
Tractor-trolley hour 1.000 193.00 193.00 P&M-053
c) Overhead charges @ 10 % on 3574.30
(a+b)
d) Contractor's profit @ 10 % on 3931.73
(a+b+c)
Rate per Hectare = a+b+c+d 43249.03
say 43249.00
2.3 (i) B In area of thorny jungle
a) Labour
Mate day 8.000 300.00 2400.00 L-12
Mazdoor day 200.000 225.00 45000.00 L-13
b) Machinery
Tractor-trolley hour 2.000 193.00 386.00 P&M-053
47
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Overhead charges @ 10 % on 4778.60
(a+b)
d) Contractor's profit @ 10 % on 5256.46
(a+b+c)
Rate per Hectare = a+b+c+d 57821.06
say 57821.00
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor day 4.000 225.00 900.00 L-13
b) Machinery
Dozer 80 HP with attachment for hour 10.000 2373.00 23730.00 P&M-014
removal of trees & stumps
Tractor-trolley hour 1.000 193.00 193.00 P&M-053
c) Overhead charges @ 10 % on 2487.10
(a+b)
d) Contractor's profit @ 10 % on 2735.81
(a+b+c)
Rate per Hectare = a+b+c+d 30093.91
say 30094.00
2.3 (ii) B In area of thorny jungle
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Dozer 80 HP with attachment for hour 12.000 2373.00 28476.00 P&M-014
removal of trees & stumps
Tractor-trolley hour 1.500 193.00 289.50 P&M-053
c) Overhead charges @ 10 % on 3018.75
(a+b)
d) Contractor's profit @ 10 % on 3320.63
(a+b+c)
Rate per Hectare = a+b+c+d 36526.88
say 36527.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like
culverts, bridges, retaining walls and
other structure comprising of masonry,
cement concrete, wood work, steel
work, including T&P and scaffolding
wherever necessary, sorting the
dismantled material, disposal of
unserviceable material and stacking the
serviceable material with all lifts and
lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete
grade M-10 and below
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor for dismantling and day 1.000 225.00 225.00 L-13
loading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 28.91
(a+b)
d) Contractor's profit @ 10 % on 31.80
(a+b+c)
48
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost for 1.25 cum = a+b+c+d 349.82
Rate per cum = (a+b+c+d)/ 1.25 279.86
say 280.00
2.4 (i) B Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.050 300.00 15.00 L-12
Mazdoor for dismantling and day 1.250 225.00 281.25 L-13
loading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 34.84
(a+b)
d) Contractor's profit @ 10 % on 38.32
(a+b+c)
Cost for 1.25 cum = a+b+c+d 421.52
Rate per cum = (a+b+c+d)/ 1.25 337.21
say 337.00
2.4 (i) C Prestressed / Reinforced cement
concrete grade M-20 & above
a) Labour
Mate day 0.150 300.00 45.00 L-12
Blacksmith day 0.250 350.00 87.50 L-02
Mazdoor for dismantling, loading day 3.500 225.00 787.50 L-13
and unloading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 97.21
(a+b)
d) Contractor's profit @ 10 % on 106.93
(a+b+c)
Cost for 1.25 cum = a+b+c+d 1176.25
Rate per cum = (a+b+c+d)/ 1.25 941.00
say 941.00
2.4 II By Mechanical Means for items No.
202( b)& ( c)
A Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor for loading and unloading day 0.250 225.00 56.25 L-13
49
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor for loading and unloading day 0.250 225.00 56.25 L-13
b) Machinery
Air Compressor 250 cfm with 2 hour 1.000 271.00 271.00 P&M-001
leads of pneumatic breaker @
1.00 cum per hour
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 63.04
(a+b)
d) Contractor's profit @ 10 % on 69.34
(a+b+c)
Cost for 1.25 cum = a+b+c+d 762.74
Rate per cum = (a+b+c+d)/ 1.25 610.19
say 610.00
2.4 (ii) Dismantling Brick / Tile work
A In lime mortar
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor for dismantling, loading day 0.500 225.00 112.50 L-13
and unloading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 17.06
(a+b)
d) Contractor's profit @ 10 % on 18.77
(a+b+c)
Cost for 1.25 cum = a+b+c+d 206.44
Rate per cum = (a+b+c+d)/ 1.25 165.15
say 165.00
2.4 (ii) B In cement mortar
a) Labour
Mate day 0.030 300.00 9.00 L-12
Mazdoor for dismantling, loading day 0.750 225.00 168.75 L-13
and unloading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 22.99
(a+b)
d) Contractor's profit @ 10 % on 25.28
(a+b+c)
Cost for 1.25 cum = a+b+c+d 278.13
Rate per cum = (a+b+c+d)/ 1.25 222.50
say 223.00
2.4 (ii) C In mud mortar
a) Labour
Mate day 0.016 300.00 4.80 L-12
Mazdoor for dismantling and day 0.400 225.00 90.00 L-13
loading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 14.69
(a+b)
d) Contractor's profit @ 10 % on 16.16
(a+b+c)
Cost for 1.25 cum = a+b+c+d 177.76
Rate per cum = (a+b+c+d)/ 1.25 142.21
say 142.00
2.4 (ii) D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 300.00 4.20 L-12
50
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor for Dismantling, loading day 0.350 225.00 78.75 L-13
and unloading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 13.51
(a+b)
d) Contractor's profit @ 10 % on 14.86
(a+b+c)
Cost for 1.25 cum = a+b+c+d 163.42
Rate per cum = (a+b+c+d)/ 1.25 130.74
say 131.00
2.4 (iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 300.00 7.20 L-12
Mazdoor for dismantling, loading day 0.600 225.00 135.00 L-13
and unloading.
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 19.43
(a+b)
d) Contractor's profit @ 10 % on 21.37
(a+b+c)
Cost for 1.25 cum = a+b+c+d 235.12
Rate per cum = (a+b+c+d)/ 1.25 188.09
say 188.00
2.4 (iii) B Rubble stone masonry in cement
mortar.
a) Labour
Mate day 0.030 300.00 9.00 L-12
Mazdoor for dismantling, loading day 0.750 225.00 168.75 L-13
and unloading.
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 22.99
(a+b)
d) Contractor's profit @ 10 % on 25.28
(a+b+c)
Cost for 1.25 cum = a+b+c+d 278.13
Rate per cum = (a+b+c+d)/ 1.25 222.50
say 223.00
2.4 (iii) C Rubble Stone Masonry in mud
mortar.
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor for dismantling, loading day 0.500 225.00 112.50 L-13
and unloading.
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 17.06
(a+b)
d) Contractor's profit @ 10 % on 18.77
(a+b+c)
Cost for 1.25 cum = a+b+c+d 206.44
Rate per cum = (a+b+c+d)/ 1.25 165.15
say 165.00
2.4 (iii) D Dry rubble masonry
a) Labour
Mate day 0.018 300.00 5.40 L-12
Mazdoor for dismantling, loading day 0.450 225.00 101.25 L-13
and unloading.
51
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 15.88
(a+b)
d) Contractor's profit @ 10 % on 17.46
(a+b+c)
Cost for 1.25 cum = a+b+c+d 192.10
Rate per cum = (a+b+c+d)/ 1.25 153.68
say 154.00
2.4 (iii) E Dismantling stone pitching/ dry stone
spalls.
a) Labour
Mate day 0.016 300.00 4.80 L-12
Mazdoor for dismantling, loading day 0.400 225.00 90.00 L-13
and unloading.
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 14.69
(a+b)
d) Contractor's profit @ 10 % on 16.16
(a+b+c)
Cost for 1.25 cum = a+b+c+d 177.76
Rate per cum = (a+b+c+d)/ 1.25 142.21
say 142.00
2.4 (iii) F Dismantling boulders laid in wire
crates including opening of crates
and stacking dismantled materials.
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor for dismantling, loading day 0.500 225.00 112.50 L-13
and unloading
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 17.06
(a+b)
d) Contractor's profit @ 10 % on 18.77
(a+b+c)
Cost for 1.25 cum = a+b+c+d 206.44
Rate per cum = (a+b+c+d)/ 1.25 165.15
say 165.00
2.4 (iv) Wood Work wrought framed and
fixed in frames of trusses upto a
height of 5 m above plinth level
a) Labour
Mate day 0.060 300.00 18.00 L-12
Carpenter day 0.500 350.00 175.00 L-04
Mazdoor for dismantling, loading day 1.000 225.00 225.00 L-13
and unloading.
b) Machinery
Tractor-trolley hour 0.270 193.00 52.11 P&M-053
c) Overhead charges @ 10 % on 47.01
(a+b)
d) Contractor's profit @ 10 % on 51.71
(a+b+c)
Cost for 1.25 cum = a+b+c+d 568.83
Rate per cum = (a+b+c+d)/ 1.25 455.07
say 455.00
2.4 (v) Steel Work in all types of sections
upto a height of 5 m above plinth
level excluding cutting of rivet.
Unit = tonne
52
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 300.00 42.00 L-12
Blacksmith day 1.000 350.00 350.00 L-02
Mazdoor for dismantling, loading day 2.500 225.00 562.50 L-13
and unloading
Add 2.5 per cent of cost of labour for 23.86
gas cutting, ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 193.00 32.81 P&M-053
c) Overhead charges @ 10 % on 101.12
(a+b)
d) Contractor's profit @ 10 % on 111.23
(a+b+c)
Rate per tonne = a+b+c+d 1223.52
say 1224.00
2.4 (v) B Excluding dismembering.
a) Labour
Mate day 0.220 300.00 66.00 L-12
Mazdoor for dismantling, loading day 2.000 225.00 450.00 L-13
and unloading
Blacksmith day 0.500 350.00 175.00 L-02
Add 2.5 per cent of cost of labour for 17.28
gas cutting, ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 193.00 32.81 P&M-053
c) Overhead charges @ 10 % on 74.11
(a+b)
d) Contractor's profit @ 10 % on 81.52
(a+b+c)
Rate per tonne = a+b+c+d 896.71
say 897.00
2.4 (v) C Extra over item No( v ) A and( v ) B
for cutting rivets.
Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 300.00 3.00 L-12
Blacksmith day 0.130 350.00 45.50 L-02
Mazdoor day 0.130 225.00 29.25 L-13
b) Overhead charges @ 10 % on 7.78
(a)
c) Contractor's profit @ 10 % on 8.55
(a+b)
Cost for 10 rivets = a+b+c 94.08
Rate for each rivet = ( a+b+c)/10 9.41
say 9.00
2.4 (vi) Scraping of Bricks Dismantled from
Brick Work including Stacking.
Unit = numbers
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 300.00 42.00 L-12
Mazdoor day 3.500 225.00 787.50 L-13
b) Overhead charges @ 10 % on 82.95
(a)
c) Contractor's profit @ 10 % on 91.25
(a+b)
53
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per1000 Nos = a+b+c 1003.70
say 1004.00
2.4 (iv) B In mud mortar
a) Labour
Mate day 0.050 300.00 15.00 L-12
Mazdoor day 1.250 225.00 281.25 L-13
b) Overhead charges @ 10 % on 29.63
(a)
c) Contractor's profit @ 10 % on 32.59
(a+b)
Rate per1000 Nos = a+b+c 358.46
say 358.00
2.4 (vii) Scraping of Stone from Dismantled
Stone Masonry
Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.060 300.00 18.00 L-12
Mazdoor day 1.400 225.00 315.00 L-13
b) Overhead charges @ 10 % on 33.30
(a)
c) Contractor's profit @ 10 % on 36.63
(a+b)
Rate per cum = a+b+c 402.93
say 403.00
2.4 (vii) B In Mud mortar
a) Labour
Mate day 0.010 300.00 3.00 L-12
Mazdoor day 0.300 225.00 67.50 L-13
b) Overhead charges @ 10 % on 7.05
(a)
c) Contractor's profit @ 10 % on 7.76
(a+b)
Rate per cum = a+b+c 85.30
say 85.00
2.4 (viii) Scarping Plaster in Lime or Cement
Mortar from Brick/ Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor for scarping and loading day 4.000 225.00 900.00 L-13
b) Machinery
Tractor-trolley hour 0.320 193.00 61.76 P&M-053
c) Overhead charges @ 10 % on 100.98
(a+b)
d) Contractor's profit @ 10 % on 111.07
(a+b+c)
Cost for 100 sqm = a+b+c+d 1221.81
Rate per sqm = (a+b+c+d)/100 12.22
say 12.00
2.4 (ix) Removing all type of Hume Pipes and
Stacking within a lead of 1000 metres
including Earthwork and Dismantling
of Masonry Works.
Unit = metre
Taking output = 1 metre
54
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
A Up to 600 mm dia
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor day 0.520 225.00 117.00 L-13
b) Overhead charges @ 10 % on 12.30
(a)
c) Contractor's profit @ 10 % on 13.53
(a+b)
Rate per metre = a+b+c 148.83
say 149.00
2.4 (ix) B Above 600 mm to 900 mm dia
a) Labour
Mate day 0.030 300.00 9.00 L-12
Mazdoor day 0.700 225.00 157.50 L-13
b) Overhead charges @ 10 % on 16.65
(a)
c) Contractor's profit @ 10 % on 18.32
(a+b)
Rate per metre = a+b+c 201.47
say 201.00
2.4 (ix) C Above 900 mm
a) Labour
Mate day 0.050 300.00 15.00 L-12
Mazdoor day 1.200 225.00 270.00 L-13
b) Overhead charges @ 10 % on 28.50
(a)
c) Contractor's profit @ 10 % on 31.35
(a+b)
Rate per metre = a+b+c 344.85
say 345.00
Note 1. The excavation of earth, dismantling
of stone masonry work in head walls
and protection works is not included
which is to be measured and paid
separately.
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 300.00 18.00 L-12
Mazdoor for dismantling, loading day 1.500 225.00 337.50 L-13
and unloading
b) Machinery
Tractor-trolley hour 0.380 193.00 73.34 P&M-053
c) Overhead charges @ 10 % on 42.88
(a+b)
d) Contractor's profit @ 10 % on 47.17
(a+b+c)
Rate per cum = a+b+c+d 518.90
say 519.00
2.5 I B Granular courses
55
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor for dismantling, loading day 1.000 225.00 225.00 L-13
and unloading.
b) Machinery
Tractor-trolley hour 0.330 193.00 63.69 P&M-053
c) Overhead charges @ 10 % on 30.07
(a+b)
d) Contractor's profit @ 10 % on 33.08
(a+b+c)
Rate per cum = a+b+c+d 363.83
say 364.00
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 300.00 3.00 L-12
Mazdoor day 0.300 225.00 67.50 L-13
b) Machinery
Tractor-trolley hour 0.380 193.00 73.34 P&M-053
Farm tractor with ripper @ 60 cum hour 0.017 222.00 3.77 P&M-055
per hour
c) Overhead charges @ 10 % on 14.76
(a+b)
d) Contractor's profit @ 10 % on 16.24
(a+b+c)
Rate per cum = a+b+c+d 178.61
say 179.00
B Granular course
a) Labour
Mate day 0.010 300.00 3.00 L-12
Mazdoor day 0.250 225.00 56.25 L-13
b) Machinery
Tractor-trolley hour 0.330 193.00 63.69 P&M-053
Farm tractor with ripper @ 60 cum hour 0.015 222.00 3.33 P&M-055
per hour
c) Overhead charges @ 10 % on 12.63
(a+b)
d) Contractor's profit @ 10 % on 13.89
(a+b+c)
Rate per cum = a+b+c+d 152.79
say 153.00
2.6 202 Dismantling of Cement Concrete
Pavement
Dismantling of cement concrete
pavement by mechanical means using
pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and
stock piling at designated locations and
disposal of dismantled materials up to a
lead of 1000 metres, stacking
serviceable and unserviceable materials
separately
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 300.00 9.00 L-12
Semi skilled mazdoor for operating day 0.500 225.00 112.50 L-14
pneumatic tools
Mazdoors as helpers including day 0.500 225.00 112.50 L-13
loading and unloading
b) Machinery
56
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor 250 cfm with two hour 1.000 271.00 271.00 P&M-001
leads for pneumatic cutters/
hammers @ 1 cum per hour
Tractor-trolley hour 0.400 193.00 77.20 P&M-053
Joint Cutting Machine with 2-3 hour 1.000 186.00 186.00 P&M-083
blades
c) Overhead charges @ 10 % on 76.82
(a+b)
d) Contractor's profit @ 10 % on 84.50
(a+b+c)
Rate per cum = a+b+c+d 929.52
say 930.00
Note The above analysis is for removal of
complete pavement. In case full depth
repair work is required to be done after
dismantling, provision of a concrete
cutting and sawing machine may be
added for 0.25 hours.
57
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Dismantling kerb stone channel by
manual means and disposal of
dismantled material with all lifts and up
to a lead of 1000 metre
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392
cum
a) Labour
Mate day 0.130 300.00 39.00 L-12
Mazdoor day 0.750 225.00 168.75 L-13
b) Machinery
Tractor-trolley hour 0.150 193.00 28.95 P&M-053
c) Overhead charges @ 10 % on 23.67
(a+b)
d) Contractor's profit @ 10 % on 26.04
(a+b+c)
Rate for one 5th KM stone = a+b+c+d 286.41
say 286.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269
cum
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor day 0.500 225.00 112.50 L-13
b) Machinery
Tractor-trolley hour 0.100 193.00 19.30 P&M-053
c) Overhead charges @ 10 % on 13.78
(a+b)
d) Contractor's profit @ 10 % on 15.16
(a+b+c)
Rate for one ordinary KM stone = 166.74
a+b+c+d
say 167.00
C Hectometre Stone
Quantity of cement concrete = 0.048
cum
a) Labour
Mate day 0.004 300.00 1.20 L-12
58
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor day 0.100 225.00 22.50 L-13
b) Machinery
Tractor-trolley hour 0.020 193.00 3.86 P&M-053
c) Overhead charges @ 10 % on 2.76
(a+b)
d) Contractor's profit @ 10 % on 3.03
(a+b+c)
Rate for one Hectometre stone = 33.35
a+b+c+d
say 33.00
2.11 202 Dismantling of Fencing
Dismantling of barbed wire fencing/ wire
mesh fencing including posts,
foundation concrete, back filling of pit by
manual means including disposal of
dismantled material with all lifts and up
to a lead of 1000 metres, stacking
serviceable material and unserviceable
material separately.
59
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note The rate analysis does not include any
excavation in earth or dismantling of
masonry works which are to be
measured and paid separately.
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor day 10.000 225.00 2250.00 L-13
Electrician/Lineman day 2.000 350.00 700.00 L-02
b) Machinery
Tractor-trolley hour 1.500 193.00 289.50 P&M-053
c) Overhead charges @ 10 % on 338.35
(a+b)
d) Contractor's profit @ 10 % on 372.19
(a+b+c)
Cost for 30 poles = a+b+c+d 4094.04
Rate per pole = (a+b+c+d)/30 136.47
say 136.00
60
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
3.1 301 Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 300.00 540.00 L-12
Mazdoor day 45.000 225.00 10125.00 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 222.00 2220.00 P&M-057
c) Overhead charges @ 10 % on (a+b) 1288.50
d) Contractor's profit @ 10 % on (a+b+c) 1417.35
Cost of 120 cum = a+b+c+d 15590.85
Rate per cum = (a+b+c+d)/120 129.92
say 130.00
Note In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 300.00 840.00 L-12
Mazdoor day 70.000 225.00 15750.00 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 222.00 2220.00 P&M-057
c) Overhead charges @ 10 % on (a+b) 1881.00
d) Contractor's profit @ 10 % on (a+b+c) 2069.10
Cost for 120 cum = a+b+c+d 22760.10
Rate per cum = (a+b+c+d)/120 189.67
say 190.00
Note In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
3.3 301 Excavation in Soil with Dozer with lead upto 100 metres
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 2373.00 14238.00 P&M-014
c) Overhead charges @ 10 % on (a+b) 1471.20
d) Contractor's profit @ 10 % on (a+b+c) 1618.32
Cost for 180 cum = a+b+c+d 17801.52
Rate per cum = (a+b+c+d)/180 98.90
say 99.00
3.4 301 Excavation in Ordinary Rock with Dozer with lead upto
100 metres
61
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate day 0.120 300.00 36.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
b) Machinery
Dozer, 80 HP @ 20 cum per hour hour 6.000 2373.00 14238.00 P&M-014
c) Overhead charges @ 10 % on (a+b) 1494.90
d) Contractor's profit @ 10 % on (a+b+c) 1644.39
Cost for 108 cum = a+b+c+d 18088.29
Rate per cum = (a+b+c+d)/108 167.48
say 167.00
3.5 301 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking 0utput = 180 cum
a) Labour
Mate day 0.220 300.00 66.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
Driller day 2.000 250.00 500.00 L-06
Blaster day 0.250 250.00 62.50 L-03
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 2373.00 14238.00 P&M-014
Air compressor, 250 cfm with 2 jack hammer hour 6.000 271.00 1626.00 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper10 tonne capacity hour 11.250 250.00 2812.50 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 111.00 6993.00 M-104
Electric Detonators @ 1 detonator for 2 gelatin sticks of each 252.000 6.60 1663.20 M-094 /100
125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 (200.00) (18000.00) M-089
per cent quantity blasted
d) Overhead charges @ 10 % on (a+b+c) 1525.62
e) Contractor's profit @ 10 % on (a+b+c+d) 1678.18
Cost for 180 cum = a+b+c+d+e 18460.00
Rate per cum = (a+b+c+d+e)/180 102.56
say 103.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
3.6 301 Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
62
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 hour 6.000 914.00 5484.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 250.00 4000.00 P&M-048
c) Overhead charges @ 10 % on (a+b) 995.80
d) Contractor's profit @ 10 % on (a+b+c) 1095.38
Cost for 360 cum = a+b+c+d 12049.18
Rate per cum = (a+b+c+d)/360 33.47
say 33.00
3.7 301 Excavation in Ordinary Rock using Hydraulic Excavator
CK-90 and Tippers with Disposal upto 1000 metres.
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36 hour 6.000 914.00 5484.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 250.00 2750.00 P&M-048
c) Overhead charges @ 10 % on (a+b) 870.80
d) Contractor's profit @ 10 % on (a+b+c) 957.88
Cost for 240 cum = a+b+c+d 10536.68
Rate per cum = (a+b+c+d)/240 43.90
say 44.00
3.8 301 Excavation in Hard Rock (blasting prohibited)
Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A Mechanised
Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.400 300.00 120.00 L-12
Mazdoor for trimming slopes including mannul loading day 10.000 225.00 2250.00 L-13
in truck
b) Machinery
Hydraulic excavator with rock breaker attachment @ 6 hour 6.000 914.00 5484.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 250.00 1625.00 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 18.000 (200.00) (3600.00) M-089
per cent of excavated quantity
c) Overhead charges @ 10 % on (a+b) 587.90
d) Contractor's profit @ 10 % on (a+b+c) 646.69
Cost for 36 cum = a+b+c+d 7113.59
Rate per cum = (a+b+c+d)/36 197.60
say 198.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
63
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
[Link] small quantity, manual loading will be economical in
this case and has been provided accordingly.
3.8 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 300.00 492.00 L-12
Mazdoor including loading in truck day 16.000 225.00 3600.00 L-13
Chiseller day 24.000 250.00 6000.00 L-05
Blacksmith day 1.000 350.00 350.00 L-02
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 250.00 725.00 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 8.000 (200.00) (1600.00) M-089
per cent of excavated
c) Overhead charges @ 10 % on (a+b) 956.70
d) Contractor's profit @ 10 % on (a+b+c) 1052.37
Cost for 16 cum = a+b+c+d 11576.07
Rate per cum = (a+b+c+d)/16 723.50
say 724.00
Note 1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.
3.9 301 Excavation in Hard Rock (controlled blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.220 300.00 66.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
Driller day 2.000 250.00 500.00 L-06
Blaster day 0.500 250.00 125.00 L-03
b) Machinery
Dozer 80 HP @ 30 cum per hour hour 6.000 2373.00 14238.00 P&M-014
Air compressor, 250 cfm with 2 jack hammers hour 6.000 271.00 1626.00 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 5.5 cum capacity, 4 trips per hour. hour 8.200 250.00 2050.00 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 111.00 6993.00 M-104
Electric Detonators @ 1 detonator for1/2 gelatin stick each 1008.000 6.60 6652.80 M-094 /100
of 125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 (200.00) (18000.00) M-089
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling 1877.29
arrangements to guard against any rock fly off during
blasting
d) Overhead charges @ 10 % on (a+b+c) 2142.31
e) Contractor's profit @ 10 % on (a+b+c+d) 2356.54
Cost for 180 cum = a+b+c+d+e 25921.94
Rate per cum = (a+b+c+d+e)/180 144.01
say 144.00
Note 1. Credit is considered for 50 per cent of quantity of
blastered rock, if found suitable for construction..
64
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
3.10 301 Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 hour 6.000 914.00 5484.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 250.00 3410.00 P&M-048
c) Overhead charges @ 10 % on (a+b) 936.80
d) Contractor's profit @ 10 % on (a+b+c) 1030.48
Cost for 300 cum = a+b+c+d 11335.28
Rate per cum = (a+b+c+d)/300 37.78
say 38.00
3.11 301 Removal of Unserviceable Soil with Disposal upto 1000
metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour 6.000 914.00 5484.00 P&M-026
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 250.00 4090.00 P&M-048
c) Overhead charges @ 10 % on (a+b) 1004.80
d) Contractor's profit @ 10 % on (a+b+c) 1105.28
Cost for 360 cum = a+b+c+d 12158.08
Rate per cum = (a+b+c+d)/360 33.77
say 34.00
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.12 303 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)
a) Labour
Mate day 0.600 300.00 180.00 L-12
Mazdoor day 15.000 225.00 3375.00 L-13
b) Machinery
65
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor 250 cfm with 2 leads @ 20 cum per hour 6.000 271.00 1626.00 P&M-001
hour
Dozer, 80 HP hour 6.000 2373.00 14238.00 P&M-014
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
c) Materials
Gelatin 80 per cent kg 42.000 111.00 4662.00 M-104
Electric Detonators @ 1 detonator for 1/2 gelatin stick each 672.000 6.60 4435.20 M-094 /100
of 125 gms each
d) Overhead charges @ 10 % on (a+b+c) 3313.62
e) Contractor's profit @ 10 % on (a+b+c+d) 3644.98
Cost for 400 sqm = a+b+c+d+e 40094.80
Rate per sqm = (a+b+c+d+e)/400 100.24
say 100.00
Note In case blasted rock is used to the contractor against
payment for constructed work, the cost of carriage shall be
reduced to that extent.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
66
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.400 300.00 120.00 L-12
Mazdoor day 10.000 225.00 2250.00 L-13
b) Overhead charges @ 10 % on (a) 237.00
c) Contractor's profit @ 10 % on (a+b) 260.70
Cost for 10 cum = a+b+c 2867.70
Rate per cum = (a+b+c)/10 286.77
say 287.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) B Mechanical Means
Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 914.00 5484.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 690.60
d) Contractor's profit @ 10 % on (a+b+c) 759.66
Cost for 216 cum = a+b+c+d 8356.26
Rate per cum = (a+b+c+d)/216 38.69
say 39.00
Note [Link] of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
[Link] case of rock, foundation beyond3 m is not dug and
hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 300.00 159.00 L-12
ii) Driller day 0.840 250.00 210.00 L-06
iii) Blaster day 0.400 250.00 100.00 L-03
iv) Mazdoor day 12.000 225.00 2700.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 271.00 180.67 P&M-001
per hour
c) Material
Blasting Material kg 3.500 111.00 388.50 M-104
Detonator electric each 14.000 6.60 92.40 M-094 /100
67
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor day 5.000 225.00 1125.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 271.00 2710.00 P&M-001
breaker @ 1 cum per hour
c) Overhead charges @ 10 % on (a+b) 389.50
d) Contractor's profit @ 10 % on (a+b+c) 428.45
Cost for 10 cum = a+b+c+d 4712.95
Rate per cum = (a+b+c+d)/10 471.29
say 471.00
Note 1. Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
[Link] case of rock, foundation beyond 3 m is not dug and
hence not included.
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 300.00 120.00 L-12
Mazdoor day 10.000 225.00 2250.00 L-13
b) Machinery
Tractor-trolley hour 2.670 193.00 515.31 P&M-053
c) Material
Selected earth for refilling cum 5.000 171.00 855.00 M-163
d) Overhead charges @ 10 % on (a+b+c) 374.03
e) Contractor's profit @ 10 % on (a+b+c+d) 411.43
Cost for 10 cum = a+b+c+d+e 4525.78
Rate per cum = ( a+b+c+d+e)/ 10 452.58
say 453.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.13 (v) B Mechanical Means
a) Labour
i) Mate day 0.080 300.00 24.00 L-12
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 225.00 450.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 914.00 155.38 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 250.00 112.50 P&M-048
c) Material
Selected earth for refilling cum 5.000 171.00 855.00 M-163
d) Overhead charges @ 10 % on (a+b+c) 159.69
e) Contractor's profit @ 10 % on (a+b+c+d) 175.66
Cost for 10 cum = a+b+c+d+e 1932.22
Rate per cum = (a+b+c+d+e)/10 193.22
say 193.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
68
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
3.14 305 Construction of Embankment with Material obtained
from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor day 1.000 225.00 225.00 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 914.00 1526.38 P&M-026
per hour
Tipper 10 tonne capacity [Link] 160 x L 2.25 3600.00 Lead =10
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 360.00
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2373.00 1186.50 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 1680.00 1680.00 P&M-032
Water tanker6 KL capacity hour 4.000 130.00 520.00 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1188.00 1188.00 P&M-059
c) Material
Cost of water KL 24.000 64.00 1536.00 M-189
Compensation for earth taken from private land cum 100.000 45.00 4500.00 M-092
d) Overhead charges @ 10 % on (a+b+c) 1633.39
e) Contractor's profit @ 10 % on (a+b+c+d) 1796.73
Cost for 100 cum = a+b+c+d+e 19763.99
Rate per cum = (a+b+c+d+e)/100 197.64
say 198.00
Note Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor day 0.500 225.00 112.50 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2373.00 1186.50 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 1680.00 1680.00 P&M-032
Water tanker6 KL capacity hour 4.000 130.00 520.00 P&M-060
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 1188.00 1188.00 P&M-059
c) Material
Cost of water KL 24.000 64.00 1536.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 622.90
e) Contractor's profit @ 10 % on (a+b+c+d) 685.19
Rate for 100 cum = a+b+c+d+e 7537.09
Rate per cum = (a+b+c+d+e)/100 75.37
say 75.00
69
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor day 1.000 225.00 225.00 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 914.00 1526.38 P&M-026
per hour
Tipper 10 tonne capacity [Link] 175xL 2.25 3937.50 Lead =10
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 393.75
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2373.00 1186.50 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 1680.00 3360.00 P&M-032
Water tanker with 6 km lead hour 4.000 130.00 520.00 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1188.00 1485.00 P&M-059
c) Material
Cost of water KL 24.000 64.00 1536.00 M-189
Compensation for earth taken from private land cum 100.000 45.00 4500.00 M-092
d) Overhead charges @ 10 % on (a+b+c) 1868.21
e) Contractor's profit @ 10 % on (a+b+c+d) 2055.03
Cost for 100 cum = a+b+c+d+e 22605.38
Rate per cum = (a+b+c+d+e)/100 226.05
say 226.00
3.17 305.3.4 Compacting Original Ground
Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 300.00 36.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
b) Machinery
Tractor with ripper attachment hour 9.000 222.00 1998.00 P&M-055
Motor grader for grading hour 6.000 1680.00 10080.00 P&M-032
Water tanker 6 KL capacity hour 4.000 130.00 520.00 P&M-060
Vibratory roller 8-10 tonne @ 80 cum/hour hour 7.500 1188.00 8910.00 P&M-059
c) Material
Cost of water KL 24.000 64.00 1536.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 2375.50
e) Contractor's profit @ 10 % on (a+b+c+d) 2613.05
Cost for 600 cum = a+b+c+d+e 28743.55
Rate per cum = (a+b+c+d+e)/600 47.91
say 48.00
70
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
3.18 Case-II :Compacting original ground supporting embankment
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Tractor with ripper attachment hour 6.000 222.00 1332.00 P&M-055
Vibratory road roller 8-10 tonne capacity hour 7.500 1188.00 8910.00 P&M-059
Water tanker6 KL capacity hour 4.000 130.00 520.00 P&M-060
c) Material
Cost of water KL 24.000 64.00 1536.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 1277.20
e) Contractor's profit @ 10 % on (a+b+c+d) 1404.92
Cost for 600 cum = (a+b+c+d+e) 15454.12
Rate per sqm = (a+b+c+d+e)/600 25.76
say 26.00
3.19 305 Stripping and Storing Top Soil
Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 5.000 225.00 1125.00 L-13
b) Machinery
Dozer 80 HP @ 100 cum per hour hour 0.100 2373.00 237.30 P&M-014
c) Overhead charges @ 10 % on (a+b) 142.23
d) Contractor's profit @ 10 % on (a+b+c) 156.45
Cost for 10 cum = (a+b+c+d) 1720.98
Rate per cum = (a+b+c+d)/10 172.10
say 172.00
3.20 Stripping, Storing and Re-laying Top Soil from Borrow
Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Dozer, 80 HP hour 6.000 2373.00 14238.00 P&M-014
c) Overhead charges @ 10 % on (a+b) 1471.20
d) Contractor's profit @ 10 % on (a+b+c) 1618.32
Cost for 300 cum = (a+b+c+d) 17801.52
Rate per cum = (a+b+c+d)/300 59.34
71
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
say 59.00
3.24 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 300.00 36.00 L-12
Mazdoor for preparation of ground and fetching of sods day 3.000 225.00 675.00 L-13
b) Machinery
Water tanker including watering for 3 months hour 2.000 130.00 260.00 P&M-060
Tractor-trolley hour 1.000 193.00 193.00 P&M-053
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 320.00 57.60 M-167
work
Cost of water KL 12.000 64.00 768.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 198.96
e) Contractor's profit @ 10 % on (a+b+c+d) 218.86
Cost for 100 sqm = a+b+c+d+e 2407.42
Rate per 100 sqm = (a+b+c+d+e)/100 24.07
say 24.00
3.25 308 Seeding and Mulching
Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 300.00 120.00 L-12
Mazdoor day 10.000 225.00 2250.00 L-13
b) Machinery
Water tanker 6 KL capacity including watering for 3 hour 14.000 130.00 1820.00 P&M-060
months
Tractor-trolley hour 2.400 193.00 463.20 P&M-053
c) Material
Seeds kg 3.600 77.00 277.20 M-162
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 320.00 137.60 M-167
Bitumen Emulsion litre 55.200 40.00 2208.00 M-077
Jute netting, open weave, 2.5 cm square opening sqm 264.000 40.00 10560.00 M-121
Cost of water for 3 months KL 84.000 64.00 5376.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 2321.20
e) Contractor's profit @ 10 % on (a+b+c+d) 2553.32
Cost for 240 sqm = a+b+c+d+e 28086.52
Rate per sqm = (a+b+c+d+e)/240 117.03
say 117.00
3.26 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A Mechanical means
72
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Labour
Mate day 0.010 300.00 3.00 L-12
Mazdoor for dressing of bed and side of drain day 0.250 225.00 56.25 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30 hour 0.330 914.00 301.62 P&M-026
metres per hour
c) Overhead charges @ 10 % on (a+b) 36.09
d) Contractor's profit @ 10 % on (a+b+c) 39.70
Cost for 10 metres = a+b+c+d 436.65
Rate per metre = (a+b+c+d)/10 43.67
say 44.00
B Manual Means
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Overhead charges @ 10 % on (a) 47.40
c) Contractor's profit @ 10 % on (a+b) 52.14
Cost for 10 metres = a+b+c 573.54
Rate per metre = (a+b+c)/10 57.35
say 57.00
Note Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
Unit = metre
Taking output = 10 metres
A Mechanical Means
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor for dressing of bed and side of drain day 0.500 225.00 112.50 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 15 hour 0.670 914.00 612.38 P&M-026
metres per hour
c) Overhead charges @ 10 % on (a+b) 73.09
d) Contractor's profit @ 10 % on (a+b+c) 80.40
Cost for 10 metres = a+b+c+d 884.36
Rate per metre = (a+b+c+d)/10 88.44
say 88.00
B Manual Means
a) Labour
Mate day 0.120 300.00 36.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
b) Overhead charges @ 10 % on (a) 71.10
c) Contractor's profit @ 10 % on (a+b) 78.21
Cost for 10 metres = a+b+c 860.31
Rate per metre = (a+b+c)/10 86.03
say 86.00
309 Surface Drains in Hard Rock
Rate per metre may be worked out based on quantity of
hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
3.28 309 Sub-Surface Drains with Perforated Pipe
73
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Construction of subsurface drain with perforated pipe of 100
mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor for excavation and back filling day 2.000 225.00 450.00 L-13
c) Material
Perforated pipe of cement concrete, internal dia 100 metre 10.000 253.00 2530.00 M-135
mm
Crushed stone as per table 300-3 cum 2.400 300.00 720.00 M-012
d) Overhead charges @ 10 % on (a+b+c) 371.20
e) Contractor's profit @ 10 % on (a+b+c+d) 408.32
Cost for 10 metres = a+b+c+d+e 4491.52
Rate per metre = (a+b+c+d+e)/10 449.15
say 449.00
Note Type of pipe may be modified depending upon provision in
design.
3.29 309 Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor for excavation and back filling with day 1.500 225.00 337.50 L-13
aggregates
b) Material
Crushed stone as per table 300-3 cum 1.350 300.00 405.00 M-012
c) Overhead charges @ 10 % on (a+b) 74.85
d) Contractor's profit @ 10 % on (a+b+c) 82.34
Cost for 10 metres = a+b+c+d 905.69
Rate per metre = (a+b+c+d)/10 90.57
say 91.00
3.30 309 Underground Drain at Edge of Pavement
Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil cum 1.500 30.00 45.00 Item No.
3.13
b) RCC work M-20 cum 0.495 3922.00 1941.39 Item 12.8
(C) RCC
Rate per metre = (a+b) 1986.39
Rates for these items may be taken from chapters on earth say 1986.00
work and substructures respectively.
3.31 310 Preparation and Surface Treatment of Formation.
Preparation and surface treatment of formation by removing
mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
74
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Labour
Mate day 0.280 300.00 84.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
Mazdoor skilled day 1.000 250.00 250.00 L-15
b) Machinery
Smooth 3 wheeled steel roller 8-10 tonnes hour 3.000 224.00 672.00 P&M-044
Water tanker 6 KL, one trip per hour hour 3.000 130.00 390.00 P&M-060
c) Material
Cost of water KL 18.000 64.00 1152.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 389.80
e) Contractor's profit @ 10 % on (a+b+c+d) 428.78
Cost for 3500 sqm = a+b+c+d+e 4716.58
Rate per sqm = (a+b+c+d+e)/3500 1.35
say 1.30
3.32 313 Construction of Rock fill Embankment
Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor day 1.500 225.00 337.50 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2373.00 1186.50 P&M-014
Vibratory road roller 8-10 tonnes @ 100 cum per hour hour 1.000 1188.00 1188.00 P&M-059
Water tanker 6 KL, one trip per hour hour 2.000 130.00 260.00 P&M-060
c) Material
Cost of water KL 12.000 64.00 768.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 375.20
e) Contractor's profit @ 10 % on (a+b+c+d) 412.72
Cost for 100 cum = a+b+c+d+e 4539.92
Rate per cum = (a+b+c+d+e)/100 45.40
say 45.00
Note It is assumed that rock is available locally at site from
roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
75
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost for 260 cum = a+b+c+d 28168.80
Rate per cum = (a+b+c+d)/260 108.34
say 108.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 300.00 96.00 L-12
Mazdoor day 8.000 225.00 1800.00 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 2373.00 14238.00 P&M-014
Front end loader hour 7.000 770.00 5390.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 250.00 1750.00 P&M-048
c) Overhead charges @ 10 % on (a+b) 2327.40
d) Contractor's profit @ 10 % on (a+b+c) 2560.14
Cost for 170 cum = a+b+c+d 28161.54
Rate per cum = (a+b+c+d)/170 165.66
say 166.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 300.00 147.00 L-12
Mazdoor day 10.000 225.00 2250.00 L-13
Driller day 2.000 250.00 500.00 L-06
Blaster day 0.250 250.00 62.50 L-03
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 2373.00 14238.00 P&M-014
Air compressor 250 cfm with two jack hammer @ 20 hour 5.000 271.00 1355.00 P&M-001
cum per hour
Front end loader hour 7.000 770.00 5390.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 250.00 1750.00 P&M-048
c) Materials
Gelatine 80 per cent kg 35.000 111.00 3885.00 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 140.000 6.60 924.00 M-094 /100
of 125 gms each
d) Overhead charges @ 10 % on (a+b+c) 3050.15
e) Contractor's profit @ 10 % on (a+b+c+d) 3355.17
Cost for 170 cum = a+b+c+d+e 36906.82
Rate per cum = (a+b+c+d+e)/170 217.10
say 217.00
76
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor day 4.000 225.00 900.00 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 914.00 5484.00 P&M-026
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes [Link] 432 x L 2.25 9720.00 Lead =10
km & P&M-
058
Add 10 per cent of cost of carriagefor loading and 972.00
unloading
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 2373.00 4271.40 P&M-014
Motor Grader for grading @ 100 cum/hour hour 3.600 1680.00 6048.00 P&M-032
Water tanker6 KL capacity hour 12.000 130.00 1560.00 P&M-060
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 1188.00 4276.80 P&M-059
c) Overhead charges @ 10 % on (a+b) 3328.02
d) Contractor's profit @ 10 % on (a+b+c) 3660.82
77
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost for 360 cum = a+b+c+d 40269.04
Rate per cum = (a+b+c+d)/360 111.86
say 112.00
Note [Link] flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.
[Link] earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.
78
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:-
400-1)
A Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 300.00 120.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 8.000 225.00 1800.00 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 1210.00 7260.00 P&M-093
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Water tanker 6 KL capacity 5 km lead with one trip per hour 4.500 130.00 585.00 P&M-060
hour
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne [Link] 450 x L 2.25 20250.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover loading and 2025.00
unloading
Motor Grader 110 HP hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8-10 t hour 6.000 1188.00 7128.00 P&M-059
c) Material
Close graded Granular sub-base Material as per table 400-1
79
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note Any one of the grading for material may be adopted as per
design
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor unskilled day 10.000 225.00 2250.00 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1188.00 7128.00 P&M-059
Tractor - Rotavator hour 12.000 228.00 2736.00 P&M-054
Water tanker 6 KL capacity hour 3.000 130.00 390.00 P&M-060
c) Material
Close graded Granular sub-base Material as per table 400-1
80
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note Any one of the grading for material may be adopted as per
design
4.2 401 Granular Sub-Base with Coarse Graded Material (Table:-
400- 2)
Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 300.00 120.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 8.000 225.00 1800.00 L-13
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1188.00 7128.00 P&M-059
Water tanker 6 KL capacity hour 3.000 130.00 390.00 P&M-060
c) Material
For coarse graded Granular sub-base Materials per table 400-
2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 134.400 369.00 49593.60 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 369.00 63763.20 M-026
2.36 mm below @ 20 per cent (Coarse Sand) cum 76.800 308.00 23654.40 M-022
Cost of water KL 18.000 64.00 1152.00 M-189
OR
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 369.00 106272.00 M-026
2.36 mm below @ 25 per cent cum 96.000 308.00 29568.00 M-022
Cost of water KL 18.000 64.00 1152.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 66 per cent cum 255.000 358.00 91290.00 M-025
2.36 mm below @ 34 per cent cum 129.000 308.00 39732.00 M-022
Cost of water KL 18.000 64.00 1152.00 M-189
4.2 (i) Rate per cum for grading-I Material
d) Overhead charges @ 10 % on (a+b+c) 15818.12
e) Contractor's profit @ 10 % on (a+b+c+d) 17399.93
Cost for 300 cum = a+b+c+d+e 191399.25
Rate per cum = (a+b+c+d+e)/300 638.00
say 638.00
4.2 (ii) Rate per cum for grading-II Material
d) Overhead charges @ 10 % on (a+b+c) 15701.00
e) Contractor's profit @ 10 % on (a+b+c+d) 17271.10
Cost for 300 cum = a+b+c+d+e 189982.10
Rate per cum = (a+b+c+d+e)/300 633.27
say 633.00
4.2 (iii) Rate per cum for grading-III Material
d) Overhead charges @ 10 % on (a+b+c) 15219.20
e) Contractor's profit @ 10 % on (a+b+c+d) 16741.12
Cost for 300 cum = a+b+c+d+e 184152.32
Rate per cum = (a+b+c+d+e)/300 613.84
say 614.00
Note Any one of the grading for material may be adopted as per
design
4.3 402 Lime Stabilisation for Improving Sub-grade
81
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density
to form a layer of improved sub grade
Unit = cum
Taking output = 300 cum (525 tonne)
A By Mechanical Means
a) Labour
Mate day 0.360 300.00 108.00 L-12
Skilled mazdoor for alignment and geometrics day 1.000 250.00 250.00 L-15
Mazdoor for spraying lime day 8.000 225.00 1800.00 L-13
b) Machinery
Tractor with ripper and rotavator attachments @ 60 cum hour 12.000 222.00 2664.00 P&M-055
per hour for ripping and 25 cum per hour for mixing
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 - 10 tonne capacity hour 6.00x0.65* 1188.00 4633.20 P&M-059
Water tanker 6 KL capacity hour 12.000 130.00 1560.00 P&M-060
c) Material
Lime at site tonne 15.750 3885.00 61188.75 M-188
Cost of water KL 72.000 64.00 4608.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 8689.20
e) Contractor's profit @ 10 % on (a+b+c+d) 9558.11
Cost for 300 cum= a+b+c+d+e 105139.26
Rate per cum =( a+b+c+d+e)/300 350.46
say 350.00
Note * Though vibratory roller is required only for 3 hours as per
norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.
Unit = cum
82
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = 300 cum (525 tonnes)
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 10.000 225.00 2250.00 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 914.00 5484.00 P&M-026
Tipper for carriage of soil [Link] 525 x L 2.25 11812.50 Lead =10
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 1181.25
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1188.00 7128.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 228.00 2736.00 P&M-054
Water tanker 6 KL capacity hour 12.000 130.00 1560.00 P&M-060
c) Material
Lime at site tonne 15.750 3885.00 61188.75 M-188
Cost of water KL 72.000 64.00 4608.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 10867.25
e) Contractor's profit @ 10 % on (a+b+c+d) 11953.98
Cost for 300 cum = a+b+c+d+e 131493.73
Rate per cum= (a+b+c+d+e)/300 438.31
say 438.00
4.5 403 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 10.000 225.00 2250.00 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 914.00 5484.00 P&M-026
Tipper for carriage of soil [Link] 525 x L 2.25 11812.50 Lead =10
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 1181.25
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1188.00 7128.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 228.00 2736.00 P&M-054
Water tanker 6 KL capacity hour 12.000 130.00 1560.00 P&M-060
c) Material
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 5600.00 117600.00 M-081
Cost of water KL 72.000 64.00 4608.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 16508.38
e) Contractor's profit @ 10 % on (a+b+c+d) 18159.21
Cost for 300 cum = a+b+c+d+e 199751.34
Rate per cum= (a+b+c+d+e)/300 665.84
say 666.00
4.6 403 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
83
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 10.000 225.00 2250.00 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1188.00 7128.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 228.00 2736.00 P&M-054
Water tanker 6 KL capacity hour 10.000 130.00 1300.00 P&M-060
c) Material
Cement at site @ 4 per cent by weight of crushed tonne 24.000 5600.00 134400.00 M-081
aggregate (600 tonne)
Grading of material for Base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 358.00 75609.60 M-014
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 358.00 27494.40 M-025
4.75 mm to 75 micron @ 25 per cent cum 96.000 330.00 31680.00 M-019
Cost of water KL 60.000 64.00 3840.00 M-189
or
Grading of material for Sub Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 369.00 46051.20 M-028
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 358.00 6873.60 M-025
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 330.00 79200.00 M-023
Cost of water KL 60.000 64.00 3840.00 M-189
4.6 (i) For Sub-Base course
d) Overhead charges @ 10 % on (a+b+c) 29716.20
e) Contractor's profit @ 10 % on (a+b+c+d) 32687.82
Cost for 300 cum = a+b+c+d+e 359566.02
Rate per cum = (a+b+c+d+e)/300 1198.55
say 1199.00
4.6 (ii) For Base course
d) Overhead charges @ 10 % on (a+b+c) 29450.28
e) Contractor's profit @ 10 % on (a+b+c+d) 32395.31
Cost for 300 cum = a+b+c+d+e 356348.39
Rate per cum = (a+b+c+d+e)/300 1187.83
say 1188.00
Note Quantities of aggregates provided under 'c' above are
uncompacted quantities.
4.7 404.3.1 Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
84
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Tractor-trolley hour 0.200 193.00 38.60 P&M-053
c) Overhead charges @ 10 % on (a+b) 51.26
d) Contractor's profit @ 10 % on (a+b+c) 56.39
Cost for 210 sqm= a+b+c+d 620.25
Rate per sqm =(a+b+c+d) 520.25
say 520.00
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor day 4.000 225.00 900.00 L-13
b) Machinery
Tractor-trolley hour 0.400 193.00 77.20 P&M-053
c) Overhead charges @ 10 % on (a+b) 102.52
d) Contractor's profit @ 10 % on (a+b+c) 112.77
Cost for 210 sqm= a+b+c+d 1240.49
Rate per sqm =(a+b+c+d)/210 1240.49
say 1240.00
4.8 404.3.2 Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 300.00 276.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 21.000 225.00 4725.00 L-13
b) Machinery
Motor Grader 110 HP hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 1188.00 7128.00 P&M-059
Water tanker 6 KL capacity hour 18.000 130.00 2340.00 P&M-060
c) Material
Screening type 'B' or coarse sand cum 720.000 240.00 172800.00 M-004
Cost of water KL 108.000 64.00 6912.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 20476.10
e) Contractor's profit @ 10 % on (a+b+c+d) 22523.71
Cost for 600 cum = a+b+c+d+e 247760.81
Rate per cum = ( a+b+c+d+e)/600 412.93
say 413.00
4.9 404 Water Bound Macadam
Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required
density.
A By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 300.00 3024.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 250.000 225.00 56250.00 L-13
b) Machinery
85
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Vibratory roller 8 - 10 tonne @ 60cum per hour hour 6.000 1188.00 7128.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 12.000
Water tanker 6 KL capacity hour 24.000 130.00 3120.00 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9A (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 560.00 243936.00 M-039
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 670.00 65124.00 M-052
OR
Crushable type such as Moorum or Gravel for grading-I cum 108.000 196.00 21168.00 M-007
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 196.00 5644.80 M-007
material
Cost of water KL 144.000 64.00 9216.00 M-189
4.9A (i) (a) Using Scrining Crushable type such as Moorum or Gravel
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 670.00 38592.00 M-052
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 196.00 20695.64 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 670.00 57888.00 M-051
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 196.00 5644.80 M-007
material
Cost of water KL 144.000 64.00 9216.00 M-189
4.9A (a) Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 10 % on (a+b+c) 37436.16
e) Contractor's profit @ 10 % on (a+b+c+d) 41179.78
Cost for 360 cum = a+b+c+d+e 452977.58
Rate per cum = (a+b+c+d+e)/360 1258.27
86
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
say 1258.00
OR
4.9A (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 10 % on (a+b+c) 39790.28
e) Contractor's profit @ 10 % on (a+b+c+d) 43769.31
Cost for 360 cum = a+b+c+d+e 481462.39
Rate per cum = (a+b+c+d+e)/360 1337.40
say 1337.00
4.9A (c) Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 10 % on (a+b+c) 41719.88
e) Contractor's profit @ 10 % on (a+b+c+d) 45891.87
Cost for 360 cum = a+b+c+d+e 504810.55
Rate per cum = (a+b+c+d+e)/360 1402.25
say 1402.00
4.9A (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 630.00 274428.00 M-036
for compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 670.00 57888.00 M-051
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 196.00 20695.64 M-007
&III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 196.00 5644.80 M-007
material
Cost of water KL 144.000 64.00 9216.00 M-189
4.9A (a) Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 10 % on (a+b+c) 37436.16
e) Contractor's profit @ 10 % on (a+b+c+d) 41179.78
Cost for 360 cum = a+b+c+d+e 452977.58
Rate per cum = (a+b+c+d+e)/360 1258.27
say 1258.00
OR
4.9A (b) Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 10 % on (a+b+c) 41719.88
e) Contractor's profit @ 10 % on (a+b+c+d) 45891.87
Cost for 360 cum = a+b+c+d+e 504810.55
Rate per cum = (a+b+c+d+e)/360 1402.25
say 1402.00
( Anyone of the aggregate grading, screening and binding
material may be used as per design)
4.9 B By Mechanical Means:
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.680 300.00 204.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 15.000 225.00 3375.00 L-13
b) Machinery
Motor grader 110 HP @ 50cum/hr. for spreading hour 7.200 1680.00 12096.00 P&M-032
Vibratory roller 8-10 tonnes @ 60cum/hr. hour 6.000 1188.00 7128.00 P&M-059
87
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Water tanker 6 KL capacity hour 24.000 130.00 3120.00 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9B (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 560.00 243936.00 M-039
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 670.00 65124.00 M-052
OR
Crushable type such as Moorum or Gravel for grading-I cum 108.000 196.00 21168.00 M-007
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 196.00 5644.80 M-007
material
Cost of water KL 144.000 64.00 9216.00 M-189
4.9B (i) (a) Using Scrining Crushable type such as Moorum or Gravel
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 670.00 38592.00 M-052
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 196.00 20695.64 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 670.00 57888.00 M-051
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 196.00 5644.80 M-007
material
Cost of water KL 144.000 64.00 9216.00 M-189
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 10 % on (a+b+c) 33076.26
e) Contractor's profit @ 10 % on (a+b+c+d) 36383.89
Cost for 360 cum = a+b+c+d+e 400222.79
Rate per cum = (a+b+c+d+e)/360 1111.73
say 1112.00
88
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
OR
4.9B (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 10 % on (a+b+c) 35430.38
e) Contractor's profit @ 10 % on (a+b+c+d) 38973.42
Cost for 360 cum = a+b+c+d+e 428707.60
Rate per cum = (a+b+c+d+e)/360 1190.85
say 1191.00
4.9B (c) Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 10 % on (a+b+c) 37359.98
e) Contractor's profit @ 10 % on (a+b+c+d) 41095.98
Cost for 360 cum = a+b+c+d+e 452055.76
Rate per cum = (a+b+c+d+e)/360 1255.71
say 1256.00
4.9B (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 630.00 274428.00 M-036
for compacted thickness of 75 mm
Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 670.00 57888.00 M-051
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 196.00 20695.64 M-007
&III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 196.00 5644.80 M-007
material
Cost of water KL 144.000 64.00 9216.00 M-189
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 10 % on (a+b+c) 33076.26
e) Contractor's profit @ 10 % on (a+b+c+d) 36383.89
Cost for 360 cum = a+b+c+d+e 400222.79
Rate per cum = (a+b+c+d+e)/360 1111.73
say 1112.00
OR
4.9B (b) Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 10 % on (a+b+c) 37359.98
e) Contractor's profit @ 10 % on (a+b+c+d) 41095.98
Cost for 360 cum = a+b+c+d+e 452055.76
Rate per cum = (a+b+c+d+e)/360 1255.71
say 1256.00
Note As three wheeled smooth rollers are also very commonly
used, the same has been provided as an alternative.
4.10 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except the use of
screening or binding Material.
Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 300.00 1248.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
89
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor for crushing broken cement concrete day 102.000 225.00 22950.00 L-13
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr. hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 1188.00 7128.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 720 x L 2.25 32400.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 3240.00
loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 trip per hour 12.000 130.00 1560.00 P&M-060
hour
c) Material
Material available from dismantled concrete slab after crushing
/ breaking and only carriage is required to be provided
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 300.00 168.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 12.000 225.00 2700.00 L-13
b) Machinery
Mechanical broom hydraulic @ 1250 sqm per hour hour 6.000 184.00 1104.00 P&M-031
Hydraulic self propelled chips spreader hour 6.000 1568.00 9408.00 P&M-025
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity hour 6.000 250.00 1500.00 P&M-048
Vibratory roller 8 -10 tonnes @ 30 cum per hour hour 6.00x0.65* 1188.00 4633.20 P&M-059
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 744.00 3184.32 P&M-004
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 670.00 65325.00 M-051
Bitumen (60-70 grade) tonne 0.250 49100.00 12275.00 M-074
d) Overhead charges @ 10 % on (a+b+c) 10541.75
e) Contractor's profit @ 10 % on (a+b+c+d) 11595.93
Cost for 7500 sqm = a+b+c+d+e 127555.20
90
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per sqm = (a+b+c+d+e)/7500 17.01
say 17.00
Note Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 10.000 225.00 2250.00 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 999.00 6593.40 P&M-094
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum capacity hour 6.000 770.00 4620.00 P&M-017
Paver finisher hour 6.000 715.00 4290.00 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 1188.00 4633.20 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 130.00 390.00 P&M-060
Tipper [Link] 495 x L 2.25 22275.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 2227.50
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 690.00 61479.00 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 690.00 81972.00 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 420.00 37422.00 M-022
Cost of water KL 18.000 64.00 1152.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 23439.41
e) Contractor's profit @ 10 % on (a+b+c+d) 25783.35
Cost for 225 cum = a+b+c+d+e 283616.86
Rate per cum = (a+b+c+d+e)/225 1260.52
say 1261.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
4.13 407 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a) Labour
91
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 130.00 130.00 P&M-060
Plate compactor @ 3.5 cum per hour hour 6.000 94.00 564.00 P&M-086
c) Material
Cost of water KL 6.000 64.00 384.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 250.00
e) Contractor's profit @ 10 % on (a+b+c+d) 275.00
Cost for 21 cum = a+b+c+d+e 3025.00
Rate per cum = (a+b+c+d+e)/21 129.05
say 129.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.
4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor day 4.000 225.00 900.00 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 130.00 130.00 P&M-060
Plate Compactor @ 3.5 cum per hour hour 6.000 94.00 564.00 P&M-086
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 914.00 457.00 P&M-026
per hour
Tipper 10 tonne capacity [Link] 52.5 x L 2.25 1181.25 Lead =10
km & P&M-
058
Add 10 per cent of cost of transportation to cover cost 118.13
of loading and unloading
c) Material
Cost of water KL 6.000 64.00 384.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 378.24
e) Contractor's profit @ 10 % on (a+b+c+d) 416.06
Cost for 21 cum = a+b+c+d+e 4576.67
Rate per cum = (a+b+c+d+e)/ 21 217.94
say 218.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
92
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.
4.16 409 Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 300.00 408.00 L-12
Mason day 4.000 350.00 1400.00 L-11
Mazdoor day 30.000 225.00 6750.00 L-13
b) Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 1188.00 891.00 P&M-059
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 130.00 260.00 P&M-060
Concrete mixer 0.4/0.28 cum per hour hour 6.000 130.00 780.00 P&M-009
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 369.00 7671.51 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 369.00 9863.37 M-026
2.36 mm below @ 20 per cent cum 11.880 308.00 3659.04 M-022
ii) For cement concrete grade M157.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 670.00 4522.50 M-052
Sand @ 0.45 cum/cum of concrete cum 3.380 683.00 2308.54 M-005
Cement tonne 1.880 5600.00 10528.00 M-081
iii) For cement plaster 1:3
Sand cum 3.840 683.00 2622.72 M-005
Cement tonne 1.830 5600.00 10248.00 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 11.00 36300.00 M-184
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 138.00 3105.00 M-137
vi) Cost of water KL 12.000 64.00 768.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 10208.57
e) Contractor's profit @ 10 % on (a+b+c+d) 11229.42
Cost for 300 sqm = a+b+c+d+e 123523.67
Rate per sqm = (a+b+c+d+e)/300 411.75
say 412.00
4.17 410 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base
Unit = cum
Taking output = 360 cum
A By Mix in Place Method
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor skilled day 2.000 250.00 500.00 L-15
Mazdoor day 10.000 225.00 2250.00 L-13
b) Machinery
Tractor attached with rotavator @ 25 cum per hour hour 12.000 228.00 2736.00 P&M-054
Motor grader 110 HP hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 -10 tonnes @ 60 cum per hour hour 6.000 1188.00 7128.00 P&M-059
93
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Water tanker 6 KL capacity hour 6.000 130.00 780.00 P&M-060
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 157.460 630.00 99199.80 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 151.060 690.00 104231.40 M-032
Below 5.6 mm @ 35 per cent cum 166.680 420.00 70005.60 M-030
Cost of water KL 36.000 64.00 2304.00 M-189
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 24.120 690.00 16642.80 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 237.600 690.00 163944.00 M-032
Below 5.6 mm@ 45 per cent cum 213.480 420.00 89661.60 M-030
Cost of water KL 36.000 64.00 2304.00 M-189
4.17A (i) For 53 mm maximum size
d) Overhead charges @ 10 % on (a+b+c) 29935.88
e) Contractor's profit @ 10 % on (a+b+c+d) 32929.47
Cost for 360.0cum = a+b+c+d+e 362224.15
Rate per cum = (a+b+c+d+e)/360 1006.18
or say 1006.00
4.17A (ii) For 45 mm maximum size
d) Overhead charges @ 10 % on (a+b+c) 29617.04
e) Contractor's profit @ 10 % on (a+b+c+d) 32578.74
Cost for 360.0cum = a+b+c+d+e 358366.18
Rate per cum = (a+b+c+d+e)/360 995.46
say 995.00
Note Any one of the aggregate grading may be adopted
4.17 B By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a) Labour
Mate day 0.280 300.00 84.00 L-12
Mazdoor skilled day 1.000 250.00 250.00 L-15
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Wet mix plant @ 75 tonne per hour hour 6.000 1210.00 7260.00 P&M-093
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Motor grader 110 HP hour 6.000 1680.00 10080.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1188.00 7128.00 P&M-059
Water tanker 6 KL capacity hour 3.000 130.00 390.00 P&M-060
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 2025.00
loading and unloading
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 98.400 630.00 61992.00 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 94.410 690.00 65142.90 M-032
Below 5.6 mm @ 35 per cent cum 104.180 420.00 43755.60 M-030
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 15.060 690.00 10391.40 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 148.500 690.00 102465.00 M-032
Below 5.6 mm@ 45 per cent cum 133.430 420.00 56040.60 M-030
94
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost of water KL 18.000 64.00 1152.00 M-189
4.17 B (i) For 53 mm maximum size
d) Overhead charges @ 10 % on (a+b+c) 22877.35
e) Contractor's profit @ 10 % on (a+b+c+d) 25165.09
Cost for 225cum = a+b+c+d+e 276815.94
Rate per cum = (a+b+c+d+e)/225 1230.29
say 1230.00
4.17 B (ii) For 45 mm maximum size
d) Overhead charges @ 10 % on (a+b+c) 22793.20
e) Contractor's profit @ 10 % on (a+b+c+d) 25072.52
Cost for 360.0cum = a+b+c+d+e 275797.72
Rate per cum = (a+b+c+d+e)/360 766.10
say 766.00
4.18 Suggest Lime, Flyash Stabilised Soil Sub-Base
ive
Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as per clause 4.3 of
IRC: 88-1984, lime + Flyash content ranging between 10 to 30
per cent, the minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25 per cent respectively, all as specified in
IRC: 88-1984.
Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50 t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
Mazdoor (Skilled) day 1.000 250.00 250.00 L-15
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ hour 6.000 914.00 5484.00 P&M-026
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes [Link] 576 x L 2.25 13005.00 Lead =10
km & P&M-
058
Tipper 10T capacity for carriage of 115 tonnes Flyash [Link] 115 x L 2.25 2587.50 Lead =10
km & P&M-
058
Tipper 10T capacity for carriage of 29 tonnes of lime hour 3.000 250.00 750.00 P&M-048
from store to work site
Add 10 per cent of cost of carriage to cover cost of 75.00
loading and unloading
Tractor with disc harrows for pulverisation hour 6.000 193.00 1158.00 P&M-053
Motor Grader 110 HP @ 50 cum per hour for mixing in- hour 9.600 1680.00 16128.00 P&M-032
place and grading
Vibratory roller 8 - 10 tonne hour 6.000 1188.00 7128.00 P&M-059
Water tanker 6 KL capacity hour 12.000 130.00 1560.00 P&M-060
c) Material
95
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Slaked Lime tonne 29.000 3885.00 112665.00 M-188
Compensation for earth taken from private source cum 360.000 45.00 16200.00 M-092
d) Overhead charges @ 10 % on (a+b+c) 17841.25
e) Contractor's profit @ 10 % on (a+b+c+d) 19625.38
Cost for 480 cum = a+b+c+d+e 215879.13
Rate per cum= (a+b+c+d+e)/480 449.75
say 450.00
Note [Link] for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
96
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
5.1 502 Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.60 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Air compressor 250 cfm hour 2.800 271.00 758.80 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 744.00 1488.00 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 130.00 130.00 P&M-060
c) Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 40400.00 84840.00 M-077
Cost of water KL 6.000 64.00 384.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 8859.00
e) Contractor's profit @ 10 % on (a+b+c+d) 9744.90
Cost for 3500 sqm = a+b+c+d+e 107193.90
Rate per sqm = (a+b+c+d+e)/3500 30.63
say 31.00
Note Bitumen primer has been provided @ 0.60 kg per sqm as
per clause 502.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Air compressor 250 cfm hour 2.800 271.00 758.80 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 744.00 1488.00 P&M-004
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.700 40000.00 28000.00 M-077
d) Overhead charges @ 10 % on (a+b+c) 3123.60
e) Contractor's profit @ 10 % on (a+b+c+d) 3435.96
Cost for 3500 sqm = a+b+c+d+e 37795.56
Rate per sqm = (a+b+c+d+e)/3500 11.81
say 12.00
Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
97
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 225.00 3600.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 12000.00 72000.00 P&M-021
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 184.00 404.80 P&M-031
Air compressor 250 cfm hour 2.200 271.00 596.20 P&M-001
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1695.00 10170.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 928.00 5568.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 224.00 873.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1188.00 4633.20 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 935.00 3646.50 P&M-045
roller.
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.850 49100.00 729135.00 M-074
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 670.00 29151.70 M-049
25 - 10 mm 45 per cent cum 130.550 690.00 90079.50 M-046
10 - 5 mm 25 per cent cum 72.530 690.00 50045.70 M-040
5 mm and below15 per cent cum 43.510 420.00 18274.20 M-030
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 690.00 80067.60 M-046
10 - 5 mm 40 per cent cum 116.040 690.00 80067.60 M-040
5 mm and below 20 per cent cum 58.020 420.00 24368.40 M-030
* Any one of the alternative may be adopted as per
approved design
(i) for Grading I ( 40 mm nominal size )
d) Overhead charges @ 10 % on (a+b+c) 104657.54
e) Contractor's profit @ 10 % on (a+b+c+d) 115123.29
Cost for 205 cum = a+b+c+d+e 1266356.23
Rate per cum = (a+b+c+d+e)/205 (For Grading I) 6177.35
say 6177.00
(ii) for GradingII(19 mm nominal size)
d) Overhead charges @ 10 % on (a+b+c) 104352.79
e) Contractor's profit @ 10 % on (a+b+c+d) 114788.07
Cost for 205 cum = a+b+c+d+e 1262668.76
Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 6159.36
say 6159.00
98
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65.
A 50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour
Mate day 0.320 300.00 96.00 L-12
Mazdoor including for brooming of key aggregates day 6.000 225.00 1350.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 1568.00 9408.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm = 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour hour 2.570 744.00 1912.08 P&M-004
Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 250.00 2500.00 P&M-048
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1188.00 7128.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
c) Material
Bitumen@ 5 kg per sqm tonne 22.500 49100.00 1104750.00 M-074
Crushed stone coarse aggregate passing 45 mm and cum 270.000 690.00 186300.00 M-033
retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8 cum 67.500 690.00 46575.00 M-031
mm sieve @ 0.015 cum per sqm
d) Overhead charges @ 10 % on (a+b+c) 136513.91
e) Contractor's profit @ 10 % on (a+b+c+d) 150165.30
Cost for 4500 sqm = a+b+c+d+e 1651818.29
Rate per sqm = (a+b+c+d+e)/4500 367.07
say 367.00
Note 2 tippers will be needed to match the capacity of chip
spreader and front end loader.
5.4 B 75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour
Mate day 0.400 300.00 120.00 L-12
Mazdoor including for brooming of key aggregates day 8.000 225.00 1800.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
99
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Hydraulic self propelled chip spreader both for hour 6.000 1568.00 9408.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm
Bitumen pressure distributor for@ 1750 sqm per hour hour 2.570 744.00 1912.08 P&M-004
Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 250.00 2500.00 P&M-048
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1188.00 7128.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
c) Material
Bitumen@ 6.8 kg per sqm tonne 30.600 49100.00 1502460.00 M-074
Crushed stone coarse aggregate (loose passing 63 cum 405.000 620.00 251100.00 M-037
mm and retained on 2.8 mm sieve @ 0.09 cum per
sqm
Key aggregates passing 26.5 mm and retained on 2.8 cum 81.000 369.00 29889.00 M-026
mm sieve @ 0.018 cum per sqm
d) Overhead charges @ 10 % on (a+b+c) 181143.71
e) Contractor's profit @ 10 % on (a+b+c+d) 199258.08
Cost for 4500 sqm = a+b+c+d+e 2191838.87
Rate per sqm = (a+b+c+d+e)/4500 487.08
say 487.00
Note 2 tippers and 2 rollers will be needed to match the capacity
of chip spreader and front end loader.
5.5 506 Built-up-Spray Grout
Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may
be used with application of bituminous binder after each
layer, and with key aggregates placed on top of the second
layer to serve as a Base conforming to the line, grades and
cross-section specified, the compacted layer thickness being
75 mm
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate day 0.400 300.00 120.00 L-12
Mazdoor including for brooming of key aggregates day 8.000 225.00 1800.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 1568.00 9408.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm
Bitumen pressure distributor for 3000 x 2 sqm @ 1750 hour 3.430 744.00 2551.92 P&M-004
sqm per hour
Tipper 5.5 cum capacity hour 10.000 250.00 2500.00 P&M-048
Vibratory roller 8 tonnes hour 6.000 1188.00 7128.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
c) Material
Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for tonne 9.000 49100.00 441900.00 M-074
each layer
Crushed stone coarse aggregate passing 53 mm and cum 300.000 690.00 207000.00 M-035
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer
Key aggregates passing 22.4 mm and retained on 2.8 cum 39.000 690.00 26910.00 M-031
mm sieve @ 0.13 cum per 10 sqm
d) Overhead charges @ 10 % on (a+b+c) 70443.79
e) Contractor's profit @ 10 % on (a+b+c+d) 77488.17
Cost for 3000 sqm = a+b+c+d+e 852369.88
Rate per sqm = (a+b+c+d+e)/3000 284.12
say 284.00
Note 2 tippers will be needed to match the capacity of hydraulic
chip spreader and front end loader.
100
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
5.6 507 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam
with 100-120 TPH batch type HMP producing an average
output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 4.0 to
4.5 per cent by weight of total mix and filler, transporting the
hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per
MoRTH specification clause No. 507 complete in all
respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 225.00 3600.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 11000.00 66000.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1695.00 10170.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 928.00 5568.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 224.00 873.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1188.00 4633.20 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 935.00 3646.50 P&M-045
roller.
c) Materials
Bitumen @ 4.5 per cent of weight of mix tonne 19.130 49100.00 939283.00 M-074
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 670.00 42337.30 M-049
25 - 10 mm 13 per cent cum 37.340 690.00 25764.60 M-046
10 -4.75 mm 19 per cent cum 54.580 690.00 37660.20 M-040
4.75 mm and below 44 per cent cum 126.390 420.00 53083.80 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188
or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 690.00 59450.40 M-046
10 - 5 mm 28 per cent cum 80.430 690.00 55496.70 M-040
5 mm and below 40 per cent cum 114.900 420.00 48258.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188
* Any one of the alternative may be adopted as per
approved design
(i) For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10 % on (a+b+c) 125450.59
e) Contractor's profit @ 10 % on (a+b+c+d) 137995.65
Cost for 205 cum = a+b+c+d+e 1517952.14
101
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7784.37
say 7784.00
(ii) For GradingII(19 mm nominal size)
d) Overhead charges @ 10 % on (a+b+c) 125886.51
e) Contractor's profit @ 10 % on (a+b+c+d) 138475.16
Cost for 205 cum = a+b+c+d+e 1523226.77
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7811.42
say 7811.00
Note *1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 225.00 3600.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 11000.00 66000.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1695.00 10170.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 928.00 5568.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of 2025.00
loading and unloading
102
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 224.00 873.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1188.00 4633.20 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 935.00 3646.50 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
Bitumen VG 30 @4.5 per cent of weight of mix tonne 20.250 49100.00 994275.00 M-074
Bitumen CRMB-60 @4.5 per cent of weight of mix tonne 20.250 48800.00 988200.00 M-078
Bitumen PMB 40 @4.5 per cent of weight of mix tonne 20.250 60400.00 1223100.00 M-078-1
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 690.00 39537.00 M-044
10 - 5 mm 38 per cent cum 108.870 690.00 75120.30 M-040
5 mm and below 40 per cent cum 114.600 420.00 48132.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188
or
Grading II: 10 mm (Nominal Size)
Bitumen VG 30 @5 per cent of weight of mix tonne 22.500 49100.00 1104750.00 M-074
Bitumen CRMG-60 @5 per cent of weight of mix tonne 22.500 48800.00 1098000.00 M-078
Bitumen PMB 40 @5 per cent of weight of mix tonne 22.500 60400.00 1359000.00 M-078-1
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 690.00 112090.50 M-040
4.75 and below@ 41 per cent cum 116.850 420.00 49077.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188
*Any one of the alternative may be adopted as per
approved design
(i) for Grading I ( 13 mm nominal size ) using VG30 Binder
103
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 9569.96
say 9570.00
5.7 (iv) for GradingII(10 mm nominal size) using VG-30 binder
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 225.00 3600.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 11000.00 66000.00 P&M-022
104
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1695.00 10170.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 928.00 5568.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 224.00 873.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1188.00 4633.20 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 935.00 3646.50 P&M-045
roller.
c) Material
Bitumen VG 30 @5 per cent of weight of mix tonne 22.500 49100.00 1104750.00 M-074
Bitumen CRMG-60 @5 per cent of weight of mix tonne 22.500 48800.00 1098000.00 M-078
Bitumen PMB 40 @5 per cent of weight of mix tonne 22.500 60400.00 1359000.00 M-078-1
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 690.00 68827.50 M-045
10 - 5 mm 23 per cent cum 65.550 690.00 45229.50 M-040
5 mm and below 40 per cent cum 114.000 420.00 47880.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 690.00 58995.00 M-044
10 - 5 mm 25 per cent cum 71.250 690.00 49162.50 M-040
5 mm and below43 per cent cum 122.550 420.00 51471.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188
*Any one of the alternative may be adopted as per
approved design
(i) for Grading-I ( 19 mm nominal size ) using binder VG-30
105
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
5.8 (iv) for Grading-II(13mm nominal size) using binder VG-30
Unit = sqm
Taking output = 9000 sqm
Case -1 :-19 mm nominal chipping size
a) Labour
Mate day 0.440 300.00 132.00 L-12
Mazdoor day 9.000 225.00 2025.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 184.00 1324.80 P&M-031
Air compressor 250 cfm hour 7.200 271.00 1951.20 P&M-001
106
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 1568.00 9408.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 250.00 1500.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Bitumen pressure distributor hour 6.000 744.00 4464.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 224.00 1344.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 49100.00 530280.00 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 680.00 91800.00 M-053
cum per sqm
d) Overhead charges @ 10 % on (a+b+c) 64934.90
e) Contractor's profit @ 10 % on (a+b+c+d) 71428.39
Cost for 9000 sqm = a+b+c+d+e 785712.29
Rate per sqm = (a+b+c+d+e)/9000 87.30
say 87.00
5.9 Case - II 13 mm nominal size chipping
a) Labour
Mate day 0.440 300.00 132.00 L-12
Mazdoor day 9.000 225.00 2025.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 184.00 1324.80 P&M-031
Air compressor 250 cfm hour 7.200 271.00 1951.20 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 1568.00 9408.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 250.00 1500.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1188.00 7128.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 49100.00 441900.00 M-074
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 670.00 60300.00 M-052
cum per sqm
d) Overhead charges @ 10 % on (a+b+c) 53525.30
e) Contractor's profit @ 10 % on (a+b+c+d) 58877.83
Cost for 9000 sqm = a+b+c+d+e 647656.13
Rate per sqm = (a+b+c+d+e)/9000 71.96
say 72.00
Case - III 10 mm nominal size chipping
a) Labour
Mate day 0.440 300.00 132.00 L-12
Mazdoor day 9.000 225.00 2025.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 184.00 1324.80 P&M-031
Air compressor 250 cfm hour 7.200 271.00 1951.20 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 1568.00 9408.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 250.00 1500.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1188.00 7128.00 P&M-059
c) Material
Bitumen @ 0.90kg per sqm tonne 8.100 49100.00 397710.00 M-074
107
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Crushed stone chipping,13 mm nominal size @ 0.01 cum 72.000 670.00 48240.00 M-052
cum per sqm
d) Overhead charges @ 10 % on (a+b+c) 47900.30
e) Contractor's profit @ 10 % on (a+b+c+d) 52690.33
Cost for 9000 sqm = a+b+c+d+e 579593.63
Rate per sqm = (a+b+c+d+e)/9000 64.40
say 64.00
Note [Link] the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
[Link] for the second coat, where required, will be the same 0.00
as per the Ist coat mentioned above
5.10 511 Open - Graded Premix Surfacing
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or
cut-back or emulsion to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a
smooth wheeled roller 8-10 tonne capacity, finished to
required level and grades.
Unit = sqm
Taking output = 10250 sqm (205 cum)
(i) Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less than
75 tonnes/hour .
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 225.00 3600.00 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
i) Batch type HMP 75 tonne per hour hour 6.000 12000.00 72000.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 928.00 5568.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
iv) Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 1695.00 10170.00 P&M-034
iv) Smooth wheeled/tandom roller 8-10 tonnes weight hour 6.000 935.00 5610.00 P&M-045
c) Material
Bitumen@ 14.60 kg per 10 sqm (VG-30) tonne 14.970 49100.00 735027.00 M-074
Bitumen@ 14.60 kg per 10 sqm (CRMB-60) tonne 14.970 48800.00 730536.00 M-078
Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum 276.750 690.00 190957.50 M-043
cum per 10 sqm
Using VG-30 binder
d) Overhead charges @ 10 % on (a+b+c) 105132.95
e) Contractor's profit @ 10 % on (a+b+c+d) 115646.25
Cost for 10250 sqm = a+b+c+d+e 1272108.69
Rate per sqm = (a+b+c+d+e)/10250 124.11
say 124.00
Using CRMB-60 binder
d) Overhead charges @ 10 % on (a+b+c) 104683.85
e) Contractor's profit @ 10 % on (a+b+c+d) 115152.24
Cost for 10250 sqm = a+b+c+d+e 1266674.59
Rate per sqm = (a+b+c+d+e)/10250 124.58
say 125.00
108
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note If a premix sand seal coat of 'B' type is proposed, the same
is required to be provided over the open graded premix
carpet immediately on the same day. As the same HMP and
other machines will be used for laying of premix sand seal
coat, out of 6 effective working hours, 4.00 hours may be
utilised for laying of premix carpet and balance 2.00 hours
for the seal coat. The rate for the premix sand seal coat
under clause 513 (case II) has been worked out accordingly
by utilising the HMP for 2.00 hours for the purpose of seal
coat. In case type 'A' seal coat is proposed, HMP can be
worked for six hours for the premix carpet as type 'A' seal
coat does not require the use of HMP.
Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27 cum 24.300 690.00 16767.00 M-043
cum per 10 sqm
d) Overhead charges @ 10 % on (a+b+c) 10438.50
e) Contractor's profit @ 10 % on (a+b+c+d) 11482.35
Cost for 900 sqm = a+b+c+d+e 126305.85
Rate per sqm = (a+b+c+d+e)/900 140.34
say 140.00
5.11 512 Close Graded Premix Surfacing/Mixed Seal Surfacing
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 225.00 3600.00 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
i) HMP of appropicate capacity. hour 6.000 12000.00 72000.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 928.00 5568.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
iv) Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 1695.00 10170.00 P&M-034
109
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
iv) Smooth wheeled8-10 tonnes weight hour 6.000 224.00 1344.00 P&M-044
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm (type VG-30) tonne 22.500 49100.00 1104750.00 M-074
* Bitumen@ 22 kg per 10 sqm (type CRMB-60) tonne 22.500 48800.00 1098000.00 M-078
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum 276.750 690.00 190957.50 M-041
cum per 10 sqm
or
Type - B
* Bitumen @ 19 kg per 10 sqm (type VG-30) tonne 19.480 49100.00 956468.00 M-074
* Bitumen @ 19 kg per 10 sqm (type CRMB 60) tonne 19.480 48800.00 950624.00 M-078
Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 276.750 690.00 190957.50 M-042
0.27 cum per 10 sqm
Type - A Using VG-30 grade bitumen
d) Overhead charges @ 10 % on (a+b+c) 141678.65
e) Contractor's profit @ 10 % on (a+b+c+d) 155846.51
Cost for 10250 sqm = a+b+c+d+e 1714311.67
Rate per sqm = (a+b+c+d+e)/10250 167.25
say 167.00
Type - A Using CRMB-60 grade bitumen
d) Overhead charges @ 10 % on (a+b+c) 141003.65
e) Contractor's profit @ 10 % on (a+b+c+d) 155104.01
Cost for 10250 sqm = a+b+c+d+e 1706144.17
Rate per sqm = (a+b+c+d+e)/10250 167.45
say 167.00
Type - B Using VG-30 grade bitumen
d) Overhead charges @ 10 % on (a+b+c) 126850.45
e) Contractor's profit @ 10 % on (a+b+c+d) 139535.50
Cost for 10250 sqm = a+b+c+d+e 1534890.44
Rate per sqm = (a+b+c+d+e)/10250 149.75
say 150.00
Type - B Using CRMB-60 grade bitumen
d) Overhead charges @ 10 % on (a+b+c) 126266.05
e) Contractor's profit @ 10 % on (a+b+c+d) 138892.66
Cost for 10250 sqm = a+b+c+d+e 1527819.21
Rate per sqm = (a+b+c+d+e)/10250 149.06
say 149.00
* Any one of the alternative may be adopted
5.12 513 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
(i) Case - I : Type A
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 1568.00 9408.00 P&M-025
Tipper 5.5 cum capacity hour 6.000 250.00 1500.00 P&M-048
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Smooth wheeled roller 8 -10 tonne weight hour 6.000 224.00 1344.00 P&M-044
c) Material
110
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Bitumen@ 9.80 kg per 10 sqm tonne 10.050 49100.00 493455.00 M-074
Crushed stone chipping of 6.7 mm size defined as 100 cum 92.250 670.00 61807.50 M-050
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ 10 % on (a+b+c) 57802.05
e) Contractor's profit @ 10 % on (a+b+c+d) 63582.26
Cost for 10250 sqm = a+b+c+d+e 699404.81
Rate per sqm = (a+b+c+d+e)/10250 68.23
say 68.00
Note Since seal coat is provided immediately over the bituminous
layers, mechanical broom for clearing has not been catered.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor day 4.000 225.00 900.00 L-13
b) Machinery
HMP of 75 tonnes/hour. hour 2.000 11000.00 22000.00 P&M-022
Electric Generator Set 250 KVA hour 2.000 928.00 1856.00 P&M-081
Front end loader 1 cum bucket capacity hour 2.000 770.00 1540.00 P&M-017
Tipper 10 tonne capacity [Link] 104 x 'L' 2.25 4680.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 468.00
and unloading
Paver finisher hydrostatic with sensor attachment hour 2.000 1695.00 3390.00 P&M-034
Smooth wheeled 8-10 tonnes capacity hour 2.000 224.00 448.00 P&M-044
c) Material
Bitumen@ 6.80 kg per 10 sqm tonne 5.340 49100.00 262194.00 M-074
Crushed stone chipping of 6.7 mm size defined as cum 47.160 670.00 31597.20 M-050
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.06 cum per 10 sqm
d) Overhead charges @ 10 % on (a+b+c) 32912.12
e) Contractor's profit @ 10 % on (a+b+c+d) 36203.33
Cost for 7858 sqm = a+b+c+d+e 398236.65
Rate per sqm = (a+b+c+d+e)/7858 50.68
say 51.00
5.12 Premixed Seal Coat
Providing and laying premix seal coat using hot mix plant
and paver finisher with aggregates of 6.7mm size defined as
100% passing through 11.20mm sieve and retained on
2.36mm sieve with 0.09 cum per 10 Sqm and 4.5%bitumen
including preparation and transportation of mix, spreading,
laying and rolling etc. complete in all respect including cost
of binder.
Unit = sqm
Taking output = 10250 sqm (92.25 cum or 212.17 T)
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
HMP of 75 tonnes/hour. hour 4.000 11000.00 44000.00 P&M-022
Electric Generator Set 250 KVA hour 4.000 928.00 3712.00 P&M-081
Front end loader 1 cum bucket capacity hour 4.000 770.00 3080.00 P&M-017
111
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Tipper 10 tonne capacity [Link] 104 x 'L' 2.25 4680.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 468.00
and unloading
Paver finisher hydrostatic with sensor attachment hour 8.000 1695.00 13560.00 P&M-034
Smooth wheeled 8-10 tonnes capacity hour 8.000 224.00 1792.00 P&M-044
c) Material
Bitumen grade VG30 @ 4.50% tonne 9.548 49100.00 468789.61 M-074
Crushed stone chipping of 6.7 mm size defined as 100 cum 92.250 670.00 61807.50 M-050
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ 10 % on (a+b+c) 60331.11
e) Contractor's profit @ 10 % on (a+b+c+d) 66364.22
Cost for 10250 sqm = a+b+c+d+e 730006.45
Rate per sqm = (a+b+c+d+e)/10250 71.22
say 71.00
c) Material
Bitumen grade CRMB60 @ 4.50% tonne 9.548 48800.00 465925.32 M-078
Crushed stone chipping of 6.7 mm size defined as 100 cum 92.250 670.00 61807.50 M-050
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ 10 % on (a+b+c) 60044.68
e) Contractor's profit @ 10 % on (a+b+c+d) 66049.15
Cost for 10250 sqm = a+b+c+d+e 726540.65
Rate per sqm = (a+b+c+d+e)/10250 75.88
say 76.00
Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour
112
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.440 300.00 132.00 L-12
Mazdoor day 10.000 225.00 2250.00 L-13
Mazdoor skilled day 1.000 250.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 184.00 11.04 P&M-031
Air compressor 250 cfm hour 0.060 271.00 16.26 P&M-001
Mastic cooker 1 tonne capacity hour 6.000 48.00 288.00 P&M-030
Bitumen boiler 1500 litres capacity hour 6.000 224.00 1344.00 P&M-005
Tractor for towing and positioning of mastic cooker and hour 1.000 193.00 193.00 P&M-053
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with
coarse aggregates (based on mix design done by CRRI for a
specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight tonne 0.204 49100.00 10016.40 M-074
of mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on cum 0.390 308.00 120.12 M-021
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less tonne 0.360 3885.00 1398.60 M-188
than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cum 0.550 690.00 379.50 M-043
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for cum 0.018 1149.00 20.68 M-142
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight kg 0.500 49.00 24.50 M-074
= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
(i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
113
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mechanical broom hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Mobile slurry seal equipment hour 6.000 735.00 4410.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 250.00 1500.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1265.00 7590.00 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
c) Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 tonne 19.360 46000.00 890560.00 M-077-1
Fine aggregate 4.75 mm and below 87 per cent of cum 102.080 420.00 42873.60 M-030
total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5, = 153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 tonne 3.520 3885.00 13675.20 M-188
Cost of water KL 12.000 64.00 768.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 97040.88
e) Contractor's profit @ 10 % on (a+b+c+d) 106744.97
Cost for 16000 sqm = a+b+c+d+e 1174194.65
Rate per sqm = (a+b+c+d+e)/16000 69.39
say 69.00
5.14 (ii) 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 5.000 225.00 1125.00 L-13
b) Machinery
Mechanical broom hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Mobile slurry seal equipment hour 6.000 735.00 4410.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 250.00 1500.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
c) Material
Residual Binder @ 13 per cent of mix = 60 x 2.2 x tonne 17.160 46000.00 789360.00 M-077-1
0.13
Fine aggregate 3 mm and below 85 per cent of total cum 74.800 308.00 23038.40 M-022
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 per cent of total mix = 60x 2.2 x 0.02 tonne 2.640 3885.00 10256.40 M-188
Cost of water KL 12.000 64.00 768.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 83812.78
e) Contractor's profit @ 10 % on (a+b+c+d) 92194.06
Cost for 30000 sqm = a+b+c+d+e 1014134.64
Rate per sqm = (a+b+c+d+e)/20000 50.71
say 48.00
5.14 (iii) 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 5.000 225.00 1125.00 L-13
b) Machinery
Mechanical broom hour 6.000 184.00 1104.00 P&M-031
114
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Mobile slurry seal equipment hour 6.000 735.00 4410.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 250.00 1500.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
c) Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 tonne 12.670 46000.00 582820.00 M-077-1
Fine aggregate 2.36 mm and below,82 per cent of cum 43.300 308.00 13336.40 M-022
total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density
1.5
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02 tonne 1.580 3885.00 6138.30 M-188
Cost of water KL 12.000 64.00 768.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 61776.77
e) Contractor's profit @ 10 % on (a+b+c+d) 67954.45
Cost for 24000 sqm = a+b+c+d+e 747498.92
Rate per sqm = (a+b+c+d+e)/24000 31.15
say 29.00
Note [Link] coat, if required to be provided, before laying slurry
seal may be measured and paid separately
5.15 517 Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the
required grade, level and thickness, all as specified in clause
517.
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day 0.480 300.00 144.00 L-12
Mazdoor day 10.000 225.00 2250.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000 189.00 1134.00 P&M-069
Mechanical broom @ 1250 sqm per hour hour 1.280 184.00 235.52 P&M-031
Air compressor 250 cfm hour 1.280 271.00 346.88 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 0.910 744.00 677.04 P&M-004
Hot mix plant 100-120 TPH producing an average of hour 3.000 12000.00 36000.00 P&M-021
75 tonnes per hour
Electric generator set 250 KVA hour 3.000 928.00 2784.00 P&M-081
Front end loader 1.00 cum bucket capacity hour 3.000 770.00 2310.00 P&M-017
Tipper 5.5 cum capacity hour 18.000 250.00 4500.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 224.00 436.80 P&M-044
Vibratory roller 8 tonnes hour 3.00x0.65* 1188.00 2316.60 P&M-059
Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 935.00 1823.25 P&M-045
c) Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 tonne 1.987 49100.00 97571.52 M-074
per cent = 82.8 x 0.60 x0.04 = 1.99
115
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Bitumen required for fresh mix of 193.2 tonnes = 193.2 tonne 7.728 49100.00 379444.80 M-074
x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent
116
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
5.17 519 Bituminous Cold Mix ( Including Gravel Emulsion)
Providing, laying and rolling of bituminous cold mix on
prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including
mixing in a plant of suitable type and capacity, transporting,
laying, compacting and finishing to specified grades and
levels.
Unit = cum
Taking output = 205 cum (450 tonne)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 per cent By weight
of total mix
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor day 16.000 225.00 3600.00 L-13
Mazdoor skilled day 5.000 250.00 1250.00 L-15
b) Machinery
Drum mix plant for cold mixes of appropriate capacity hour 6.000 5040.00 30240.00 P&M-077
but not less than 75 tonnes/hour.
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Paver finisher hour 6.000 1695.00 10170.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1265.00 4933.50 P&M-037
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 935.00 3646.50 P&M-045
c) Material
Bitumen emulsion MC800 @ 8 per cent tonne 36.000 41600.00 1497600.00 M-077-2
Filler (lime)@ 2 per cent tonne 9.000 3885.00 34965.00 M-188
Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5 cum 75.000 690.00 51750.00 M-045
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000 690.00 60030.00 M-040
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 420.00 45360.00 M-030
d) Overhead charges @ 10 % on (a+b+c) 177513.80
e) Contractor's profit @ 10 % on (a+b+c+d) 195265.18
Cost for 205 cum = a+b+c+d+e 2147916.98
Rate per cum = (a+b+c+d+e)/205 10477.64
say 10478.00
(Applicable to cases I to IV)
Note [Link] of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
117
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor day 16.000 225.00 3600.00 L-13
Mazdoor skilled day 5.000 250.00 1250.00 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 5040.00 30240.00 P&M-077
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Paver finisher hour 6.000 1695.00 10170.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1265.00 4933.50 P&M-037
Smooth wheeled steel tandom roller 6-8 tonnes hour 6.00x0.65* 935.00 3646.50 P&M-045
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 41600.00 1497600.00 M-077-2
Filler (lime)@ 2 per cent tonne 9.000 3885.00 34965.00 M-188
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 670.00 50250.00 M-048
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 690.00 62100.00 M-047
Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5 cum 105.000 420.00 44100.00 M-030
d) Overhead charges @ 10 % on (a+b+c) 177444.80
e) Contractor's profit @ 10 % on (a+b+c+d) 195189.28
Cost for 205 cum = a+b+c+d+e 2147082.08
Rate per cum = (a+b+c+d+e)/205 10473.57
say 10474.00
Note [Link] of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
118
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 5040.00 30240.00 P&M-077
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Paver finisher hour 6.000 1695.00 10170.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1265.00 4933.50 P&M-037
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 935.00 3646.50 P&M-045
c) Material
Cutback bitumen @ 4 per cent tonne 18.000 53900.00 970200.00 M-076
Filler (lime)@ 2 per cent tonne 9.000 3885.00 34965.00 M-188
Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5 cum 78.000 690.00 53820.00 M-045
Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5 cum 93.000 690.00 64170.00 M-040
Aggregates size 6 to 0.075 mm - 450 x 0.37 x 1/1.5 cum 111.000 420.00 46620.00 M-030
d) Overhead charges @ 10 % on (a+b+c) 125520.80
e) Contractor's profit @ 10 % on (a+b+c+d) 138072.88
Cost for 205 cum = a+b+c+d+e 1518801.68
Rate per cum = (a+b+c+d+e)/205 7408.79
say 7409.00
Note [Link] of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
119
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cutback bitumen on @ 4 per cent tonne 18.000 53900.00 970200.00 M-076
Filler (lime)@ 2 per cent tonne 9.000 3885.00 34965.00 M-188
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 670.00 50250.00 M-048
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 690.00 62100.00 M-047
Aggregates size 6 to 0.075 mm - 450 x0.39 x 1/1.5 cum 117.000 420.00 49140.00 M-030
d) Overhead charges @ 10 % on (a+b+c) 125208.80
e) Contractor's profit @ 10 % on (a+b+c+d) 137729.68
Cost for 205 cum = a+b+c+d+e 1515026.48
Rate per cum = (a+b+c+d+e)/205 7390.37
say 7390.00
Note [Link] of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate day 0.840 300.00 252.00 L-12
Mazdoor day 16.000 225.00 3600.00 L-13
Mazdoor skilled day 5.000 250.00 1250.00 L-15
b) Machinery
Hot Mix Plant of appropriate capacity but not less than hour 6.000 9000.00 54000.00 P&M-023
75 tonnes/hour
Electric generator set 250 KVA hour 6.000 928.00 5568.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Paver finisher hour 6.000 1695.00 10170.00 P&M-034
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65 224.00 873.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65 1188.00 4633.20 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandom hour 6.00x0.65 935.00 3646.50 P&M-045
rollers.
c) Material
Composition of mix (450 tonne) is assumed to be as
under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen 4 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 94 per cent
Bitumen@ 4 per cent tonne 18.000 49100.00 883800.00 M-074
Filler (lime)@ 2 per cent tonne 9.000 3885.00 34965.00 M-188
Sand of size 4.75 to 0.075 mm - 450 x 0.94 x 1/1.5 cum 282.000 240.00 67680.00 M-004
d) Overhead charges @ 10 % on (a+b+c) 109733.33
e) Contractor's profit @ 10 % on (a+b+c+d) 120706.66
Cost for 205 cum = a+b+c+d+e 1327773.29
120
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cum = (a+b+c+d+e)/205 6476.94
say 6477.00
Note 1. Tack coat will be measured and paid separately
2. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of this roller, their
usage rates has been multiplied by a factor of 0.65
Unit = tonne
The use of modified binder is expected to result in an
extended service life of bituminous pavements subject to
heavy traffic loads in extreme climatic conditions, thus
justifying the entire cost of adding modifiers/fibres. Other
advantages include lower temperature susceptibility, higher
resistance to aging, higher fatigue life, higher resistance to
cracking and better adhesion between aggregates and
binder.
121
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
(i) Stress absorbing membrane (SAM) crack width less
than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader, sweeping
the surface for uniform spread of aggregates and surface
finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Hydraulic Chip spreader hour 6.000 1568.00 9408.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 224.00 1344.00 P&M-044
c) Material
Modified binder tonne 9.450 60400.00 570780.00 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 670.00 70350.00 M-050
d) Overhead charges @ 10 % on (a+b+c) 66049.80
e) Contractor's profit @ 10 % on (a+b+c+d) 72654.78
Cost for 10500 sqm = a+b+c+d+e 799202.58
Rate per sqm = (a+b+c+d+e)/10500 76.11
say 76.00
5.19 (ii) Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm capacity hour 6.000 271.00 1626.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Hydraulic Chip spreader hour 6.000 1568.00 9408.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 224.00 1344.00 P&M-044
c) Material
Modified binder tonne 11.550 60400.00 697620.00 M-078
Crushed stone chipping 11.2 mm size cum 105.000 670.00 70350.00 M-051
d) Overhead charges @ 10 % on (a+b+c) 78733.80
e) Contractor's profit @ 10 % on (a+b+c+d) 86607.18
Cost for 10500 sqm = a+b+c+d+e 952678.98
Rate per sqm = (a+b+c+d+e)/10500 90.73
say 91.00
5.19 (iii) Stress absorbing membrane (SAM) crack width above 9
mm and cracked area above 50 per cent
122
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 184.00 1104.00 P&M-031
Air compressor 250 cfm capacity hour 6.000 271.00 1626.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 744.00 4464.00 P&M-004
Hydraulic Chip spreader hour 6.000 1568.00 9408.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 224.00 1344.00 P&M-044
c) Material
Modified binder tonne 15.750 60400.00 951300.00 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 670.00 84420.00 M-051
d) Overhead charges @ 10 % on (a+b+c) 105558.80
e) Contractor's profit @ 10 % on (a+b+c+d) 116114.68
Cost for 10500 sqm = a+b+c+d+e 1277261.48
Rate per sqm = (a+b+c+d+e)/10500 121.64
say 122.00
Note In case 2nd coat is also required to be provided, material
provided for the 2nd coat shall be as per table 500-47.
5.20 (iv) Case - IV : Bitumen impregnated geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 703.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 300.00 168.00 L-12
Mazdoor day 12.000 225.00 2700.00 L-13
Mazdoor skilled day 2.000 250.00 500.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Air compressor 250 cfm capacity hour 2.800 271.00 758.80 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 744.00 1488.00 P&M-004
Pneumatic roller hour 2.000 1265.00 2530.00 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 48100.00 177008.00 M-075
kg per sqm
Geotextile including 10 per cent for overlaps sqm 3850.000 330.00 1270500.00 M-108
d) Overhead charges @ 10 % on (a+b+c) 145616.80
e) Contractor's profit @ 10 % on (a+b+c+d) 160178.48
Cost for 10500 sqm = a+b+c+d+e 1761963.28
Rate per sqm = (a+b+c+d+e)/3500 503.42
say 503.00
123
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
NOTE As bitumen overlay construction shall follow closely the
fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will cover a
length of 500 m, of 7 m wide carriagway. This can be
conveniently overlaid by a bitumenious course in a day
Unit = cum
Taking output = 205 cum (450 tonnes)
(i) 75 mm thickness
a) Labour
Mate day 1.000 300.00 300.00 L-12
Mazdoor day 12.000 225.00 2700.00 L-13
Mazdoor skilled day 5.000 250.00 1250.00 L-15
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity hour 6.000 1512.00 9072.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum capacity hour 6.000 770.00 4620.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1695.00 10170.00 P&M-034
cum per hour
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Pneumatic tyred roller12-15 tonnes. hour 6.00x0.65* 1265.00 4933.50 P&M-037
Smooth wheeled steel roller6-8 tonnes. hour 6.00x0.65* 224.00 873.60 P&M-044
Water tanker6 KL capacity hour 1.000 130.00 130.00 P&M-060
c) Material
Bitumen emulsion @ 45 litres per tonne tonne 20.250 47652.00 964953.00 M-073
Crushed stone aggregates 40 mm nominal size cum 297.000 660.00 196020.00 M-055
Cost of water KL 6.000 64.00 384.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 122212.71
e) Contractor's profit @ 10 % on (a+b+c+d) 134433.98
Cost for 10500 sqm = a+b+c+d+e 1478773.79
Rate per sqm = (a+b+c+d+e)/205 7213.53
say 7214.00
Note (Case I to III)
1. These mixes are considered suitable for minor repair work
and temporary road surface improvement.
2. In case concrete mixtures are required to be used for
mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
*[Link] the rollers have to be available at site to match with
the output of batch mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted to cater for the
idling period of road rollers.
124
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Batch type cold mixing plant100-120 TPH capacity hour 6.000 1512.00 9072.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum capacity hour 6.000 770.00 4620.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1695.00 10170.00 P&M-034
cum per hour
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Pneumatic tyred roller 12-15 tonnes. hour 6.00x0.65* 1265.00 4933.50 P&M-037
Smooth wheeled steel roller 6-8 tonnes. hour 6.00x0.65* 224.00 873.60 P&M-044
Water tanker6 KL capacity hour 1.000 130.00 130.00 P&M-060
c) Material
Bitumen emulsion @ 70 litres per tonne tonne 31.500 47652.00 1501038.00 M-073
Crushed stone aggregates 14 mm nominal size cum 287.000 670.00 192290.00 M-052
Cost of water KL 6.000 64.00 384.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 175448.21
e) Contractor's profit @ 10 % on (a+b+c+d) 192993.03
Cost for 10500 sqm = a+b+c+d+e 2122923.34
Rate per sqm = (a+b+c+d+e)/205 10355.72
say 10356.00
5.22 (iii) 25 mm thickness
a) Labour
Mate day 1.000 300.00 300.00 L-12
Mazdoor day 12.000 225.00 2700.00 L-13
Mazdoor skilled day 5.000 250.00 1250.00 L-15
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity hour 6.000 1512.00 9072.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 741.00 4446.00 P&M-018
Front end loader 1 cum capacity hour 6.000 770.00 4620.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1695.00 10170.00 P&M-034
cum per hour
Tipper 10 tonne capacity [Link] 450 x L 2.25 20250.00 Lead =20 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 2025.00
and unloading
Pneumatic tyred roller hour 6.00x0.65* 1265.00 4933.50 P&M-037
Smooth wheeled steel roller hour 6.00x0.65* 224.00 873.60 P&M-044
Water tanker6 KL capacity hour 1.000 130.00 130.00 P&M-060
c) Material
Bitumen emulsion @ 85 litres per tonne tonne 38.250 47652.00 1822689.00 M-073
Crushed stone aggregates 6 mm nominal size cum 270.000 670.00 180900.00 M-050
Cost of water KL 6.000 64.00 384.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 206474.31
e) Contractor's profit @ 10 % on (a+b+c+d) 227121.74
Cost for 10500 sqm = a+b+c+d+e 2498339.15
Rate per sqm = (a+b+c+d+e)/205 12187.02
say 12187.00
125
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
5.1 502 Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.60 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Air compressor 250 cfm hour 2.800 271.00 758.80 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 744.00 1488.00 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 130.00 130.00 P&M-060
c) Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 40400.00 84840.00 M-077
Cost of water KL 6.000 64.00 384.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 8859.00
e) Contractor's profit @ 10 % on (a+b+c+d) 9744.90
Cost for 3500 sqm = a+b+c+d+e 107193.90
Rate per sqm = (a+b+c+d+e)/3500 30.63
say 31.00
Note Bitumen primer has been provided @ 0.60 kg per sqm as
per clause 502.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Air compressor 250 cfm hour 2.800 271.00 758.80 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 744.00 1488.00 P&M-004
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.700 40000.00 28000.00 M-077
d) Overhead charges @ 10 % on (a+b+c) 3123.60
e) Contractor's profit @ 10 % on (a+b+c+d) 3435.96
Cost for 3500 sqm = a+b+c+d+e 37795.56
Rate per sqm = (a+b+c+d+e)/3500 11.81
say 12.00
Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
126
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 224.00 873.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1188.00 4633.20 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 935.00 3646.50 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
Bitumen VG 30 @4.5 per cent of weight of mix tonne 20.250 49100.00 994275.00 M-074
Bitumen CRMB-60 @4.5 per cent of weight of mix tonne 20.250 48800.00 988200.00 M-078
Bitumen PMB 40 @4.5 per cent of weight of mix tonne 20.250 60400.00 1223100.00 M-078-1
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 690.00 39537.00 M-044
10 - 5 mm 38 per cent cum 108.870 690.00 75120.30 M-040
5 mm and below 40 per cent cum 114.600 420.00 48132.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188
or
Grading II: 10 mm (Nominal Size)
Bitumen VG 30 @5 per cent of weight of mix tonne 22.500 49100.00 1104750.00 M-074
Bitumen CRMG-60 @5 per cent of weight of mix tonne 22.500 48800.00 1098000.00 M-078
Bitumen PMB 40 @5 per cent of weight of mix tonne 22.500 60400.00 1359000.00 M-078-1
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 690.00 112090.50 M-040
4.75 and below@ 41 per cent cum 116.850 420.00 49077.00 M-030 98732
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3885.00 33488.70 M-188 994275.00
*Any one of the alternative may be adopted as per
approved design 153575.7
(i) for Grading I ( 13 mm nominal size ) using VG30 Binder
1246582.7
d) Overhead charges @ 10 % on (a+b+c) 131344.13 124658.27
e) Contractor's profit @ 10 % on (a+b+c+d) 144478.54 137124.1
Cost for 205 cum = a+b+c+d+e 1589263.97 1508365.1
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8150.07 7735.2055
say 8150.00
(ii) for Grading I ( 13 mm nominal size ) using CRMB 60
Binder
d) Overhead charges @ 10 % on (a+b+c) 130736.63
e) Contractor's profit @ 10 % on (a+b+c+d) 143810.29
Cost for 205 cum = a+b+c+d+e 1581913.22
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8112.38
say 8112.00
(iii) for Grading I ( 13 mm nominal size ) using PMB 40
Binder
d) Overhead charges @ 10 % on (a+b+c) 154226.63
e) Contractor's profit @ 10 % on (a+b+c+d) 169649.29
127
CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 8-
10 tonnes vibratory roller, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 300.00 336.00 L-12
Mazdoor skilled day 6.000 250.00 1500.00 L-15
Mazdoor day 22.000 225.00 4950.00 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 1857.00 11142.00 P&M-068
Electric generator 100 KVA hour 6.000 743.00 4458.00 P&M-080
Paver with electronic sensor hour 6.000 1695.00 10170.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1188.00 9504.00 P&M-059
Water tanker6 KL capacity hour 8.000 130.00 1040.00 P&M-060
Tipper [Link] 990 x L 2.25 44550.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 4455.00
and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5 cum 405.000 675.00 273375.00 M-052 and
mm nominal sizes graded as per table 600-1 @ 0.90 M-054
cum/cum of concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 203.000 240.00 48720.00 M-004
concrete
Cement @ 150 kg/cum of concrete tonne 67.500 5600.00 378000.00 M-081
Cost of water KL 48.000 64.00 3072.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 79989.20
e) Contractor's profit @ 10 % on (a+b+c+d) 87988.12
Cost for 205 cum = a+b+c+d+e 967869.32
Rate per cum = (a+b+c+d+e)/450 2150.82
say 2151.00
Note Quantity provided for aggregate is for estimating purpose.
Exact quantity shall be as per mix design.
6.2 602 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a batching and mixing plant
as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 300.00 600.00 L-12
Mazdoor skilled day 15.000 250.00 3750.00 L-15
Mazdoor day 35.000 225.00 7875.00 L-13
b) Machinery
128
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Road Sweeper @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Front end loader 1 cum bucket capacity hour 18.000 770.00 13860.00 P&M-017
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 7560.00 45360.00 P&M-067
(effective output)
Electric generator 250 KVA hour 6.000 928.00 5568.00 P&M-081
Slip form paver with electronic sensor hour 6.000 2442.00 14652.00 P&M-006
Water tanker6 KL capacity hour 36.000 130.00 4680.00 P&M-060
Transit truck agitator 5 cum capacity. [Link] 2415xL 2.25 108675.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 10867.50
and unloading
Concrete joint cutting machine . hour 12.000 186.00 2232.00 P&M-083
Texturing machine . hour 12.000 250.00 3000.00 P&M-088
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.000 675.00 637875.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 cum 473.000 240.00 113520.00 M-004
@ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.000 5600.00 2318400.00 M-081
32 mm mild steel dowel bars of grade S 240 tonne 9.450 50000.00 472500.00 M-126
16 mm deformed steel tie bars of grade S 415 tonne 1.170 51000.00 59670.00 M-082
Separation Membrane of impermeable plastic sheeting sqm 3675.000 19.00 69825.00 M-164
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.330 271.00 4425.43 M-141
joint.
Joint sealant kg 875.000 739.00 646625.00 M-120
Sealant primer kg 116.670 560.00 65335.20 M-097
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 67.00 3126.89 M-138
Curing compound liter 1850.000 93.00 172050.00 M-090
Super plastisizer admixture IS marked as per 9103- kg 2070.000 65.00 134550.00 M-180
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.000 64.00 13824.00 M-189
Add 1 per cent of material for cost of miscellaneous 47117.27
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 300.00 360.00 L-12
Mazdoor skilled day 7.000 250.00 1750.00 L-15
Mazdoor day 23.000 225.00 5175.00 L-13
129
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 1857.00 11142.00 P&M-068
Electric generator 100 KVA hour 6.000 743.00 4458.00 P&M-080
Paver with electronic sensor @ 75 cum/hr. hour 6.000 1695.00 10170.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1188.00 9504.00 P&M-059
Water tanker with 5 km lead 6 KL capacity hour 8.000 130.00 1040.00 P&M-060
Tipper [Link] 990xL 2.25 44550.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 4455.00
and unloading
c) Material
Crushed stone coarse aggregates of 25mm and cum 405.000 675.00 273375.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause 602.2.3 cum 203.000 240.00 48720.00 M-004
@ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete tonne 90.000 5600.00 504000.00 M-081
Cost of water KL 48.000 64.00 3072.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 92639.10
e) Contractor's profit @ 10 % on (a+b+c+d) 101903.01
Cost for 450cum = a+b+c+d+e 1120933.11
Rate per cum = (a+b+c+d+e)/450 2490.96
say 2491.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will
be as per mix design.
New Transition Section between Rigid and Flexible Pavement
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 300.00 336.00 L-12
Mazdoor skilled day 6.000 250.00 1500.00 L-15
Mazdoor day 22.000 225.00 4950.00 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 770.00 4620.00 P&M-017
130
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 1857.00 11142.00 P&M-068
Electric generator 100 KVA hour 6.000 743.00 4458.00 P&M-080
Paver finisher with electronic sensor hour 6.000 1695.00 10170.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1188.00 9504.00 P&M-059
Water tanker6 KL capacity hour 8.000 130.00 1040.00 P&M-060
Tipper 10 T Capacity [Link] 990 x L 2.25 44550.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 4455.00
and unloading
c) Material
Crushed stone coarse aggregate of 40 mm nominal cum 405.000 660.00 267300.00 M-055
size @ 0.90 cum/cum of concrete conforming to table 2
of IRC: 74-1979.
Coarse Sand as per IS: 383 - 1970 cum 110.960 240.00 26630.40 M-004
Cement @ 150 kg/cum of concrete tonne 67.500 5600.00 378000.00 M-081
Fly ash conforming to IS: 3812 ( Part II ) cum 91.540 210.00 19223.40 M-011
( Total fine aggregates = 450 x 0.45 = 202.50 cum To be
divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of IRC:
74-1979).
d) Overhead charges @ 10 % on (a+b+c) 78787.88
e) Contractor's profit @ 10 % on (a+b+c+d) 86666.67
Cost for 450cum = a+b+c+d+e 953333.35
Rate per cum = (a+b+c+d+e)/450 2118.52
say 2119.00
Note [Link] upon approved designs, crushed stone
aggregates of nominal size 20mm can also be used as per
gradation given in table 2 of IRC: 74-1979.
[Link] ratio of specific gravities of fly ash and sand has been
assumed to be 0.827.
[Link] quantities of materials given in the analyses are for
estimating purposes. Actual quantities shall be as per job
mix formula.
[Link] procedure as laid down in clause, of IRC: 74-
1979 shall be followed.
6.6 6.5 Cement - Flyash Concrete Pavement.
Construction reinforced-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base with
43 grade cement, coarse and fine aggregate conforming to
IS 383, maximum size of coarse aggregate not exceeding 25
mm, replacing cement by fly ash to the extent of 15 per cent
and sand by 10 per cent, mixed in a batching and mixing
plant as per approved mix design, transported to site, laid
with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 300.00 600.00 L-12
Mazdoor skilled day 15.000 250.00 3750.00 L-15
Mazdoor day 35.000 225.00 7875.00 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 184.00 515.20 P&M-031
Front end loader 1 cum bucket capacity hour 18.000 770.00 13860.00 P&M-017
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 7560.00 45360.00 P&M-067
(effective output)
Electric generator 250 KVA hour 6.000 928.00 5568.00 P&M-081
Slip form paver with electronic sensor hour 6.000 2442.00 14652.00 P&M-006
131
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Water tanker6 KL capacity hour 36.000 130.00 4680.00 P&M-060
Transit truck agitator 5 cum capacity. [Link] 2415xL 2.00 96600.00 P&M-050
Lead= 20
km
Add 10 per cent of cost of carriage to cover cost of loading 9660.00
and unloading
Concrete joint cutting machine . hour 12.000 186.00 2232.00 P&M-083
Texturing machine . hour 12.000 250.00 3000.00 P&M-088
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.000 675.00 637875.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 cum 425.000 240.00 102000.00 M-004
132
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
7.1 702 Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties
as given in clause 702.2.3 formed in to a stable network and
a planar geocomposite structure, joints wrapped with
geotextile to prevent ingress of soil, all as per clause 702
and approved drawings including excavation and backfilling
Unit = sqm
Taking output = 2800 sqm
a) Labour
133
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.800 300.00 240.00 L-12
Mazdoor day 20.000 225.00 4500.00 L-13
b) Machinery
Road sweeper 1250 sqm per hour hour 2.240 184.00 412.16 P&M-031
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1265.00 1771.00 P&M-037
Bitumen pressure distributor 1750 sqm per hour hour 1.680 744.00 1249.92 P&M-004
c) Material
Paving Fabric sqm 2940.000 192.00 564480.00 M-133
Paving Bitumen 80-100 tonne 2.800 48100.00 134680.00 M-075
c) Overhead charges @ 10 % on (a+b) 70733.31
d) Contractor's profit @ 10 % on (a+b+c) 77806.64
Cost for 2800 sqm = a+b+c+d+e 855873.03
Rate per sqm =(a+b+c+d+e)/2800 305.67
say 306.00
7.4 704 Laying Boulder Apron in Crates of Synthetic Geogrids
Unit = cum
Taking output = 3.00 cum
a) Labour
Mate day 0.060 300.00 18.00 L-12
Mazdoor skilled day 0.500 250.00 125.00 L-15
Mazdoor day 1.500 225.00 337.50 L-13
b) Material
Geo grids sqm 21.000 560.00 11760.00 M-105
Connectors/ Staples each 50.000 55.00 2750.00 M-085
Polymer braids metre 20.000 225.00 4500.00 M-140
Stones with minimum size of 200 mm cum 3.450 526.00 1814.70 M-003
Stones spall for filling voids cum 0.450 300.00 135.00 M-008
c) Overhead charges @ 10 % on (a+b) 2144.02
d) Contractor's profit @ 10 % on (a+b+c) 2358.42
Cost for 3 cum = a+b+c+d 25942.64
Rate per cum = (a+b+c+d)/ 3 1995.59
say 1996.00
7.5 3100 Reinforced Earth Structures
Reinforced earth Structures have four main components as
under:
a) Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing
elements (facia material).
b) Facia material and its placement.
c) Assembling, joining with facing elements and laying of
the reinforcing elements.
d) Earth fill with granular material which is to be retained
by the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
7.5 3102 (i) Assembling, joining and laying of reinforcing elements.
134
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 300.00 108.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
Mazdoor skilled day 3.000 250.00 750.00 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as per
clause 3102.
[Link] carbon steel strips metre 450*1.1 199.00 98505.00 M-154
or
[Link] Strips metre 450*1.1 304.00 150480.00 M-153
or
[Link] Strips metre 450*1.1 258.00 127710.00 M-157
or
[Link] steel strips metre 450*1.1 275.00 136125.00 M-156
or
[Link] reinforced polymer/fibre reinforced metre 450*1.1 177.00 87615.00 M-155
polymer/polymeric strips
@ Any one of the above alternative may be adopted as per
approved design.
Add 10 per cent of the cost of reinforcing strip towards
accessories like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia pannels, overlaps,
heat bonding or extension.
135
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = 300 sqm
a) Labour
Mate day 0.360 300.00 108.00 L-12
Mazdoor day 6.000 225.00 1350.00 L-13
Mazdoor skilled day 3.000 250.00 750.00 L-15
b) Material
Synthetic Geogrids as per clause 3102.8 and approved sqm 300.000 389.00 116700.00 M-181
design and specifications.
Add 10 per cent of the cost of reinforcing elements 11670.00
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps and other
protective elements for synthetic geogrids.
136
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
[Link] type of reinforcing elements to be adopted shall be as
per approved design and specifications.
[Link] market rate for supply of reinforcing elements and
their accessories are to be ascertained from reputed firms in
the field of earth reinforcement.
[Link] earth fill material shall be clean, free draining,
granular with high friction and low cohesion, non-corrosive,
coarse grained with not 10 per cent of particles passing 75
micron sieve, free of any deleterious matter, chlorides, salts,
acids, alkalies, mineral oil, fungus and microbes and shall be
of specified PH value.
137
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
138
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Concrete batching and mixing plant @ 15 cum/hr. hour 2.700 1725.00 4657.50 P&M-003
Water tanker6 KL capacity hour 6.000 130.00 780.00 P&M-060
Tipper of 5.5 cum capacity hour 6.000 250.00 1500.00 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 680.00 24881.20 M-053
cent cum 36.590
139
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per metre = (a+b+c+d+e)/300 368.78
say 369.00
8.3 801 Printing New Letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
Unit = Each
Taking output = one traffic sign
229.00 49.46 Item No.
i) Excavation for foundation cum 0.216 3.13
3879.00 465.48 Item 12.8
ii) Cement concrete M15 grade cum 0.120 (A)
iii) Painting angle iron post two coats sqm 0.430 50.00 21.50 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 300.00 3.00 L-12
Mazdoor day 0.250 225.00 56.25 L-13
b) Material
51.52 978.88 M-179
Mild steel angle iron 75 x 75 x 6 mm kg 19.000 /1000
140
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 5500.00 1925.00 M-061
or
( ii ) 60 cm equilateral triangle sqm 0.156 5500.00 858.00 M-061
or
( iii ) 60 cm circular sqm 0.283 5500.00 1556.50 M-061
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 5500.00 2640.00 M-061
or
(v) 60 cm x 45 cm rectangular sqm 0.270 5500.00 1485.00 M-061
or
(vi ) 60 cm x 60 cm square sqm 0.360 5500.00 1980.00 M-061
or
( vii ) 90 cm high octagon sqm 0.672 5500.00 3696.00 M-061
c) Machinery
Tractor-trolley hour 0.010 193.00 1.93 P&M-053
(i) 90 cm equilateral triangle
d) Overhead charges @ 10 % on (a+b+c) 296.51
e) Contractor's profit @ 10 % on (a+b+c+d) 326.16
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4124.17
say 4124.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 10 % on (a+b+c) 189.81
e) Contractor's profit @ 10 % on (a+b+c+d) 208.79
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2833.10
say 2833.00
( iii ) 60 cm circular
d) Overhead charges @ 10 % on (a+b+c) 259.66
e) Contractor's profit @ 10 % on (a+b+c+d) 285.62
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3678.28
say 3678.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 10 % on (a+b+c) 368.01
e) Contractor's profit @ 10 % on (a+b+c+d) 404.81
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4989.32
say 4989.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 10 % on (a+b+c) 252.51
e) Contractor's profit @ 10 % on (a+b+c+d) 277.76
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3591.77
say 3592.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 10 % on (a+b+c) 302.01
e) Contractor's profit @ 10 % on (a+b+c+d) 332.21
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4190.72
say 4191.00
( vii ) 90 cm high octagon
d) Overhead charges @ 10 % on (a+b+c) 473.61
e) Contractor's profit @ 10 % on (a+b+c+d) 520.97
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6267.08
say 6267.00
141
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
[Link] one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
[Link] for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.5 801 Direction and Place Identification Signs upto 0.9 sqm
Size Board.
Unit = sqm
Taking output = 0.9 sqm
229.00 49.46 Item No.
i) Excavation for foundation cum 0.216 3.13
3879.00 465.48 Item 12.8
ii) Cement concrete M15 grade cum 0.120 (A)
iii) Painting angle iron post two coats sqm 0.430 50.00 21.50 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 300.00 3.00 L-12
Mazdoor day 0.200 225.00 45.00 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 51.52 978.88 M-179
metres long kg 19.000 /1000
Aluminium sheeting fixed with encapsulated lens type 5500.00 4950.00 M-061
reflective sheeting of size 0.9 sqm sqm 0.900
8.6 801 Direction and Place Identification Signs with size more
than 0.9 sqm size Board.
Unit = sqm
Taking output = 1.50 sqm
142
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
229.00 98.47 Item No.
i) Excavation for foundation cum 0.430 3.13
3879.00 930.96 Item 12.8
ii) Cement concrete M15 grade cum 0.240 (A)
iii) Painting angle iron post 2 coats sqm 0.860 50.00 43.00 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 300.00 3.00 L-12
Mazdoor day 0.300 225.00 67.50 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 51.52 1957.76 M-179
metres long, 2 nos kg 38.000 /1000
Aluminium sheeting fixed with encapsulated lens type 5500.00 8250.00 M-061
reflective sheeting sqm 1.500
Add 1 per cent on cost of material for nuts, bolts and drilling 493.92
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses 7482.89
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 304.00 912.00 P&M-013
Truck hour 0.500 222.00 111.00 P&M-057
d) Overhead charges @ 10 % on (a+b+c) 6006.38
e) Contractor's profit @ 10 % on (a+b+c+d) 6607.02
Rate per tonne = (a+b+c+d+e) 72677.21
say 72677.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
143
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.020 300.00 6.00 L-12
Blacksmith day 0.100 350.00 35.00 L-02
Mazdoor day 0.150 225.00 33.75 L-13
b) Material
Aluminium alloy plate,2 mm thick, fixed with high 4620.00 4620.00 M-059
intensity grade sheeting vide clause 801.3 sqm 1.000
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like 0.75
ladders, pulleys, ropes etc
c) Overhead charges @ 10 % on (a+b) 469.55
d) Contractor's profit @ 10 % on (a+b+c) 516.50
Rate per sqm = (a+b+c+d) 5681.55
say 5682.00
1. The cost of excavation and foundation concrete for fixing
Note of vertical support system to be worked out separately as
per the approved drawing/design and to be included in the
estimate.
144
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
d) Contractor's profit @ 10 % on (a+b+c) 50.65
Cost for 10 sqm = a+b+c+d 557.16
Rate per sqm= (a+b+c+d)/10 55.72
say 56.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 300.00 9.00 L-12
Painter day 0.500 350.00 175.00 L-18
Mazdoor day 0.200 225.00 45.00 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 171.00 256.50 M-131
Add @ 1 per cent on cost of material for scaffolding 2.57
Add @ 5 per cent cost of labour and materials to 24.28
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 10 % on (a+b) 51.23
d) Contractor's profit @ 10 % on (a+b+c) 56.36
Cost for 10 sqm = a+b+c+d 619.93
Rate per sqm = (a+b+c+d)/10 61.99
say 62.00
145
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost for 10 sqm = a+b+c+d 881.42
Rate per sqm = (a+b+c+d)/10 88.14
say 88.00
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 300.00 9.00 L-12
Mazdoor day 0.750 225.00 168.75 L-13
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 84.00 840.00 P&M-043
Tractor-trolley hour 0.500 193.00 96.50 P&M-053
c) Material
Hot applied thermoplastic compound Litre 1500.000 198.00 297000.00 M-118
Reflectorising glass beads kg 150.000 65.00 9750.00 M-152
d) Overhead charges @ 10 % on (a+b+c) 30786.43
146
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
e) Contractor's profit @ 10 % on (a+b+c+d) 33865.07
Cost for 600 sqm = a+b+c+d+e 372515.74
Rate per sqm = a+b+c+d+e)/600 620.86
say 621.00
1. A sealing primer may be applied in advance on cement
Note concrete pavement to ensure proper bonding. Any laitance
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
[Link] of painter is already included in hire charges of road
marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
3879.00 9115.65 Item 12.8
a) M-15 grade of concrete cum 2.350 (A)
67.90 1499.21 Item
b) Steel reinforcement @ 5 kg per sqm kg 22.080 13.6 /1000
229.00 384.72 Item No.
c) Excavation in soil for foundation cum 1.680 3.13
d) Painting two coats on concrete surface sqm 9.850 50.00 492.50 Item 8.8
e) Lettering on km post (average 30 letters of 10 per cm per 0.40 720.00 Item 8.3
cm height each) letter 1800.000
147
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i) 22134.35
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor for fixing day 1.000 225.00 225.00 L-13
b) Material
Cost of approved type of delineators from ISI certified 533.00 15990.00 M-091
firm as per the standard drawing given in IRC - 79 each 30.000
148
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
Unit = Each
Taking output = 57 Nos.
3879.00 4848.75 Item 12.8
a) M-15 grade of the boundary stone cum 1.250 (A)
67.90 5418.34 Item
b) Steel reinforcement kg 79.800 13.6 /1000
229.00 2454.88 Item No.
c) Excavation in soil cum 10.720 3.13
0.40 912.00 Item 8.3
d) Lettering, each 10 cm high per letter 2280.000
per cm high
149
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per metre = (a+b+c+d+e)/30 269.29
say 269.00
Cost of excavation for foundation and foundation concrete to
Note be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
8.18 807 G.I Barbed Wire Fencing 1.8 Metre High
150
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75 kg 293.000
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c) Machinery
Tractor-trolley hour 0.100 193.00 19.30 P&M-053
d) Painting
Painting two coats including priming sqm 8.000 50.00 400.00 Item 8.9
e) Overhead charges @ 10 % on (a+b+c) 1535.69
f) Contractor's profit @ 10 % on (a+b+c+e) 1689.26
Cost for 30 metre = a+b+c+d+e+f 18981.90
Rate per metre = (a+b+c+d+e+f)/30 632.73
say 633.00
8.21 808 Tubular Steel Railing on Precast RCC Posts, 1.2 m High
Above Ground Level
151
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 3879.00 2513.59 Item 12.8
0.6 x 0.3 cum 0.648 (A)
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 4475.00 1432.00 Item
metres each cum 0.320 14.1(A)
iv) Painting of pipe sqm 4.710 50.00 235.50 Item 8.9
a) Labour
Mate day 0.014 300.00 4.20 L-12
Mazdoor day 0.350 225.00 78.75 L-13
Plumber day 0.010 350.00 3.50 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 258.00 7740.00 M-175
c) Machinery
Tractor-trolley hour 0.250 193.00 48.25 P&M-053
d) Overhead charges @ 10 % on (a+b+c) 787.47
e) Contractor's profit @ 10 % on (a+b+c+d) 866.22
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 14006.26
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1400.63
say 1401.00
8.22 809 Reinforced Cement Concrete Crash Barrier
152
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 300.00 18.00 L-12
Blacksmith day 0.500 350.00 175.00 L-02
Mazdoor day 1.000 225.00 225.00 L-13
b) Machinery
Tractor-trolley hour 0.100 193.00 19.30 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section 51.52 2123.14 M-179
railing,4.5 m in length kg 41.210 /1000
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 51.52 4562.61 M-179
16.4 kg per metre kg 88.560 /1000
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 51.52 836.68 M-179
16.4 kg per metre kg 16.240 /1000
Nuts and bolts kg 20.000 65.00 1300.00 M-130
Add 25 per cent of the cost of material for fabrication, nuts, 2205.61
bolts and washers etc.)
d) Overhead charges @ 10 % on (a+b+c) 1146.53
e) Contractor's profit @ 10 % on (a+b+c+d) 1261.19
Cost for 4.5 metre = a+b+c+d+e 13873.07
Rate per metre = (a+b+c+d+e)/4.5 3082.90
say 3083.00
8.23 B Type - B, "THRIE" : Metal Beam Crash Barrier
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 51.52 5069.57 M-179
kg per metre kg 98.400 /1000
51.52 1383.83 M-179
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860 /1000
Nuts and bolts kg 30.000 65.00 1950.00 M-130
Add 15 per cent of the cost of material for fabrication, nuts, 1916.97
bolts and washers etc.)
d) Overhead charges @ 10 % on (a+b+c) 1513.41
e) Contractor's profit @ 10 % on (a+b+c+d) 1664.75
Cost for 4.5 metre = a+b+c+d+e 18312.22
Rate per metre= (a+b+c+d+e)/4.5 4069.38
say 4069.00
153
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
8.24 811 Road Traffic Signals electrically operated
Add 5 per cent of cost of material for drilling, gripping, fixing, 1343.50
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface sqm 16.500 50.00 825.00 Item 8.9
d) Machinery
Tractor-trolley hour 0.250 193.00 48.25 P&M-053
e) Overhead charges @ 10 % on (a+b+d) 2909.78
f) Contractor's profit @ 10 % on (a+b+d+e) 3200.76
Cost for 15 m = a+b+c+d+e+f 36033.39
Rate per m = (a+b+c+d+e+f)/15 2402.23
say 2402.00
The items of excavations and cement concrete works will be
Note measured and included separately as per the approved
designs and drawings.
154
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
155
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 300.00 9.00 L-12
Mazdoor day 0.500 225.00 112.50 L-13
Electrician day 0.250 350.00 87.50 L-02
b) Material
i) Steel circular hollow pole of standard specification for 10304.00 10304.00 M-171
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp each 1.000 1008.00 1008.00 M-168
Add 5 per cent of cost of material for holder, electric cable, 565.60
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel 50.00 287.50 Item 8.9
circular hollow pipe with overhang on both sides sqm 5.750
ii) Sodium vapour lamp 70 watt each 1.000 1008.00 1008.00 M-168
Add 1 per cent of cost of material for holder, electric cable, 83.48
insulation, ladder, scaffolding etc
156
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Painting
Providing two coats of alluminium paint over steel 50.00 138.00 Item 8.9
circular hollow pipe sqm 2.760
Collar for joints 300 mm dia each 9.000 275.00 2475.00 M-083
4615.00 92.30 Item 12.6
Cement mortar 1:2 for joints cum 0.020 (B)
d) Machinery
Tractor-trolley hour 0.500 193.00 96.50 P&M-053
e) Overhead charges @ 10 % on (b+c+d) 4569.43
f) Contractor's profit @ 10 % on (b+c+d+e) 5026.37
Cost for 20 metre = a+b+c+d+e+f 62058.58
Rate per metre = (a+b+c+d+e+f)/20 3102.93
say 3103.00
8.29 (ii) Double row for two utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 2868.00 9665.16 Item 12.7
mortar 1:6 for head wall both sides. cum 3.370 (Addl) B)
b) Labour
Mate day 0.050 300.00 15.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
Mazdoor skilled day 0.250 250.00 62.50 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 40.000 2050.00 82000.00 M-151
Granular soil with PI less than 6 for bedding and sides 240.00 3456.00 M-009
of pipe (0.6 x 0.6 x 40 m) cum 14.400
157
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Collar for joints 300 mm dia each 18.000 275.00 4950.00 M-083
4615.00 184.60 Item 12.6
Cement mortar 1:2 for joints cum 0.040 (B)
d) Machinery
Tractor-trolley hour 1.000 193.00 193.00 P&M-053
e) Overhead charges @ 10 % on (b+c+d) 9131.11
f) Contractor's profit @ 10 % on (b+c+d+e) 10044.22
Cost for 20 metre = a+b+c+d+e+f 120151.59
Rate per metre = (a+b+c+d+e+f)/20 6007.58
say 6008.00
8.29 (iii) Triple rRow for three utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 2868.00 12561.84 Item 12.7
mortar 1:6 for head wall both sides. cum 4.380 (Addl) B)
b) Labour
Mate day 0.160 300.00 48.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
Mazdoor skilled day 1.000 250.00 250.00 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 60.000 2050.00 123000.00 M-151
Granular soil with PI less than 6 for bedding and sides 240.00 5184.00 M-009
of pipe (0.6 x 0.6 x 60 m) cum 21.600
Collar for joints 300 mm dia each 27.000 275.00 7425.00 M-083
4615.00 276.90 Item 12.6
Cement mortar 1:2 for joints cum 0.060 (B)
d) Machinery
Tractor-trolley hour 1.500 193.00 289.50 P&M-053
e) Overhead charges @ 10 % on (b+c+d) 13714.84
f) Contractor's profit @ 10 % on (b+c+d+e) 15086.32
Cost for 20 metre = a+b+c+d+e+f 178511.40
Rate per metre = (a+b+c+d+e+f)/20 8925.57
say 8926.00
158
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 300.00 24.00 L-12
159
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor day 1.500 225.00 337.50 L-13
Blacksmith day 0.250 350.00 87.50 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 129.00 10320.00 M-161
20 mm steel wire rope kg 150.000 77.00 11550.00 M-176
Add 1 per cent of cost of wire rope for clamps etc. 115.50
c) Machinery
Tractor-trolley hour 3.000 193.00 579.00 P&M-053
d) Overhead charges @ 10 % on (a+b+c) 2301.35
e) Contractor's profit @ 10 % on (a+b+c+d) 2531.49
Cost for 20 sqm = a+b+c+d+e 27846.34
Rate per sqm = (a+b+c+d+e)/20 1392.32
say 1392.00
8.34 B Using Plastic/Steel Barrel, Filled with Sand
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 300.00 39.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
Blacksmith day 0.250 350.00 87.50 L-02
b) Material
Plastic barrels each 50.000
or
Steel barrels each 50.000 258.00 12900.00 M-172
Sand cum 8.000 240.00 1920.00 M-004
20 mm steel wire rope kg 15.000 77.00 1155.00 M-176
Add 1 per cent of cost of wire rope for clamps etc. 11.55
c) Machinery
Tractor-trolley hour 2.000 193.00 386.00 P&M-053
d) Overhead charges @ 10 % on (a+b+c) 1717.41
e) Contractor's profit @ 10 % on (a+b+c+d) 1889.15
Cost for 20 sqm = a+b+c+d+e 20780.60
Rate per sqm = (a+b+c+d+e)/20 1039.03
say 1039.00
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-
determined time, thus absorbing the energy)
Unit = sqm
Taking output = 10sqm
a) Labour
Mate day 0.100 300.00 30.00 L-12
Mazdoor day 2.500 225.00 562.50 L-13
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 358.00 14320.00 M-139
Cost of water KL 12.000 64.00 768.00 M-189
20 mm steel wire rope kg 100.000 77.00 7700.00 M-176
Add 1 per cent of cost of wire rope for clamps etc. 77.00
160
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Machinery
Tractor-trolley hour 2.000 193.00 386.00 P&M-053
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 2410.35
e) Contractor's profit @ 10 % on (a+b+c+d) 2651.39
Cost for 10 sqm = a+b+c+d+e 29165.24
Rate per sqm = (a+b+c+d+e)/10 2916.52
say 2917.00
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor day 1.000 225.00 225.00 L-13
b) Material
Aluminium studs 100 x 100 mm fitted with lense 330.00 16500.00 M-062
reflectors each 50.000
Add 10 per cent of cost of material for fixing and installation 1650.00
161
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings
Unit = each
Taking output = one number
Earthwork Quantities of these items to be cum
calculated as per approved design and
Cement Concrete cost added as per rates of these items cum
brick masonry or given in chapter 3 and 13 cum
stone masonry cum
Painting sqm 2.500
a) Labour
Mate day 0.090
Mazdoor day 1.000
Blacksmith day 1.000
Welder day 0.250
b) Material
Steel pipe 100 mm dia metre 3.500
Steel pipe 25 mm dia metre 10.000
CGI sheets kg 8.000
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500
d) Overheads @ per cent on (a+b+c)
e) Contractors Profit@ per cent on (a+b+c+d)
Rate per policeman umbrella = a+b+c+d+e
162
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = each
163
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55-2001 and
IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor day 0.250 225.00 56.25 L-13
Painter day 0.500 350.00 175.00 L-18
Welder day 0.250 350.00 87.50 L-02
b) Material
51.52 1288.00 M-179
Angle iron 45 x 45 x 5 mm kg 25.000 /1000
51.52 772.80 M-179
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 /1000
Paint litre 0.500 171.00 85.50 M-131
164
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Add 2 per cent of cost of steel for welding consumables, 41.22
nuts & bolts and drilling holes
c) Overhead charges @ 10 % on (a+b) 251.23
d) Contractor's profit @ 10 % on (a+b+c) 276.35
Rate per barricade = a+b+c+d 3039.84
say 3040.00
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 300.00 15.00 L-12
Mazdoor day 0.300 225.00 67.50 L-13
Painter day 0.600 350.00 210.00 L-18
Welder day 0.300 350.00 105.00 L-02
b) Material
51.52 772.80 M-179
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 /1000
MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m 51.52 2576.00 M-179
length kg 50.000 /1000
Paint litre 1.000 171.00 171.00 M-131
Add 1 per cent of cost of steel for welding consumables, 66.98
nuts & bolts and drilling holes
c) Overhead charges @ 10 % on (a+b) 398.43
d) Contractor's profit @ 10 % on (a+b+c) 438.27
Rate per barricade = a+b+c+d 4820.97
say 4821.00
8.44 B With wooden components
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 300.00 15.00 L-12
Mazdoor day 0.300 225.00 67.50 L-13
Painter day 0.600 350.00 210.00 L-18
Carpenter day 0.600 350.00 210.00 L-04
b) Material
Timber cum 0.180 8800.00 1584.00 M-185
Add 1 per cent of cost of timber for nuts & bolts, nails, etc. 15.84
c) Overhead charges @ 10 % on (a+b) 210.23
d) Contractor's profit @ 10 % on (a+b+c) 231.26
Rate per barricade = a+b+c+d 2543.83
say 2544.00
8.44 C With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
165
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = one barricade
a) Labour
Mate day 0.240 300.00 72.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
Painter day 1.000 350.00 350.00 L-18
Mason day 2.000 350.00 700.00 L-11
b) Material
Brick each 1800.000 3.10 5580.00 M-079
5.60 123.20 M-081
Cement kg 22.000 /1000
Sand cum 0.090 683.00 61.47 M-005
Paint litre 1.250 171.00 213.75 M-131
c) Overhead charges @ 10 % on (a+b) 777.54
d) Contractor's profit @ 10 % on (a+b+c) 855.30
Rate per barricade = a+b+c+d 9408.26
say 9408.00
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 300.00 6.00 L-12
Mazdoor day 0.250 225.00 56.25 L-13
Painter day 0.250 350.00 87.50 L-18
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen 258.00 258.00 M-172
drum each 1.000
166
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = Sqm
Taking output = 10 Sqm
(i) a) M 30 grade concrete 50 mm thick
4952.00 2476.00 Item
M 30 grade concrete cum 0.500 14.1(B)
b) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
Mason day 2.000 350.00 700.00 L-11
c) Material
Sand cum 0.500 683.00 341.50 M-005
167
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
say 695.00
(iv) a) M 50 grade concrete 100 mm thick
6292.00 6292.00 Item
M 50 grade concrete cum 1.000 14.1(B)
b) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
Mason day 2.000 350.00 700.00 L-11
c) Material
Sand cum 0.500 690.00 345.00 M-005
b) Labour
Mate day 0.040 300.00 12.00 L-12
Printing in shade and colour required Sqm 10.000 180.00 1800.00 Item 8.3 .1
Mazdoor day 1.000 225.00 225.00 L-13
c) Overhead charges @ 10 % on (a+b) 415.80
d) Contractor's profit @ 10 % on (a+b+c) 457.38
Cost for 10 sqm = a+b+c+d 5031.18
Rate per sqm = (a+b+c+d)/10 503.12
say 503.00
168
CHAPTER-9
PIPE CULVERTS
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
9.1 408 PCC [Link] in Foundation
Plain cement concrete [Link] mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 300.00 192.00 L-12
Mason day 1.000 350.00 350.00 L-11
Mazdoor day 15.000 225.00 3375.00 L-13
b) Material
40mm Aggregate at site cum 12.600 660.00 8316.00 M-055
Sand at site cum 6.300 683.00 4302.90 M-005
Cement at site tonne 2.250 5600.00 12600.00 M-081
Cost of water KL 18.000 64.00 1152.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 130.00 780.00 P&M-009
Generator set 33 KVA hour 6.000 500.00 3000.00 P&M-079
Water tanker6 KL capacity hour 3.000 130.00 390.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 3445.79
e) Contractor's profit @ 10 % on (a+b+c+d) 3790.37
Cost for 15 cum = a+b+c+d+e 41694.06
Rate per cum = (a+b+c+d+e)/15 2779.60
say 2780.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.1 408 PCC [Link] in Foundation
Plain cement concrete [Link] mix with crushed stone
aggregate 20 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 300.00 192.00 L-12
Mason day 1.000 350.00 350.00 L-11
Mazdoor day 15.000 225.00 3375.00 L-13
b) Material
20mm Aggregate at site cum 12.600 680.00 8568.00 M-055
Sand at site cum 6.300 683.00 4302.90 M-005
Cement at site tonne 2.250 5600.00 12600.00 M-081
Cost of water KL 18.000 64.00 1152.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 130.00 780.00 P&M-009
Generator set 33 KVA hour 6.000 500.00 3000.00 P&M-079
Water tanker6 KL capacity hour 3.000 130.00 390.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 3470.99
e) Contractor's profit @ 10 % on (a+b+c+d) 3818.09
Cost for 15 cum = a+b+c+d+e 41998.98
Rate per cum = (a+b+c+d+e)/15 2799.93
say 2800.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.1 408 PCC [Link] in Foundation
169
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Plain cement concrete [Link] mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 300.00 192.00 L-12
Mason day 1.000 350.00 350.00 L-11
Mazdoor day 15.000 225.00 3375.00 L-13
b) Material
40mm Aggregate at site cum 13.800 660.00 9108.00 M-055
Sand at site cum 6.900 683.00 4712.70 M-005
Cement at site tonne 3.300 5600.00 18480.00 M-081
Cost of water KL 18.000 64.00 1152.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 130.00 780.00 P&M-009
Generator set 33 KVA hour 6.000 500.00 3000.00 P&M-079
Water tanker6 KL capacity hour 3.000 130.00 390.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 4153.97
e) Contractor's profit @ 10 % on (a+b+c+d) 4569.37
Cost for 15 cum = a+b+c+d+e 50263.04
Rate per cum = (a+b+c+d+e)/15 3350.87
say 3351.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.1 408 PCC [Link] in Foundation
Plain cement concrete [Link] mix with crushed stone
aggregate 20 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 300.00 192.00 L-12
Mason day 1.000 350.00 350.00 L-11
Mazdoor day 15.000 225.00 3375.00 L-13
b) Material
20mm Aggregate at site cum 13.800 680.00 9384.00 M-055
Sand at site cum 6.900 683.00 4712.70 M-005
Cement at site tonne 3.300 5600.00 18480.00 M-081
Cost of water KL 18.000 64.00 1152.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 130.00 780.00 P&M-009
Generator set 33 KVA hour 6.000 500.00 3000.00 P&M-079
Water tanker6 KL capacity hour 3.000 130.00 390.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 4181.57
e) Contractor's profit @ 10 % on (a+b+c+d) 4599.73
Cost for 15 cum = a+b+c+d+e 50597.00
Rate per cum = (a+b+c+d+e)/15 3373.13
say 3373.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.15 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
170
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 300 mm dia
a) Labour
Mate day 0.090 300.00 27.00 L-12
Mason day 0.250 350.00 87.50 L-11
Mazdoor day 2.000 225.00 450.00 L-13
b) Material
Sand at site cum 0.017 683.00 11.61 M-005
Cement at site tonne 0.013 5600.00 70.00 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 2050.00 25625.00 M-151
collar at site
Granular material passing 5.6 mm sieve for bedding cum 1.250 240.00 300.00 M-009
c) Overhead charges @ 10 % on (a+b) 2657.11
d) Contractor's profit @ 10 % on (a+b+c) 2922.82
Cost for 12.5 metres = a+b+c+d 32151.04
Rate per metre = (a+b+c+d)/12.5 2572.08
say 2572.00
B 600 mm dia
a) Labour
Mate day 0.140 300.00 42.00 L-12
Mason day 0.500 350.00 175.00 L-11
Mazdoor day 3.000 225.00 675.00 L-13
b) Material
Sand at site cum 0.070 683.00 47.81 M-005
Cement at site tonne 0.050 5600.00 280.00 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 3000.00 37500.00 M-150-2
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 240.00 1080.00 M-009
c) Overhead charges @ 10 % on (a+b) 3979.98
d) Contractor's profit @ 10 % on (a+b+c) 4377.98
Cost for 12.5 metres = a+b+c+d 48157.77
Rate per metre = (a+b+c+d)/12.5 3852.62
say 3853.00
C 900 mm dia
a) Labour
Mate day 0.180 300.00 54.00 L-12
Mason day 0.500 350.00 175.00 L-11
Mazdoor day 4.000 225.00 900.00 L-13
b) Material
Sand at site cum 0.070 683.00 47.81 M-005
Cement at site tonne 0.050 5600.00 280.00 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 4500.00 56250.00 M-150-1
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 240.00 1080.00 M-009
c) Overhead charges @ 10 % on (a+b) 5878.68
d) Contractor's profit @ 10 % on (a+b+c) 6466.55
Cost for 12.5 metres = a+b+c+d 71132.04
Rate per metre = (a+b+c+d)/12.5 5690.56
say 5691.00
D 1000 mm dia
a) Labour
Mate day 0.180 300.00 54.00 L-12
Mason day 0.500 350.00 175.00 L-11
Mazdoor day 4.000 225.00 900.00 L-13
b) Material
Sand at site cum 0.070 683.00 47.81 M-005
Cement at site tonne 0.050 5600.00 280.00 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 5152.00 64400.00 M-149
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 240.00 1080.00 M-009
c) Overhead charges @ 10 % on (a+b) 6693.68
d) Contractor's profit @ 10 % on (a+b+c) 7363.05
Cost for 12.5 metres = a+b+c+d 80993.54
Rate per metre = (a+b+c+d)/12.5 6479.48
say 6479.00
171
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.360 300.00 108.00 L-12
Mason day 1.000 350.00 350.00 L-11
Mazdoor day 8.000 225.00 1800.00 L-13
b) Material
Sand at site cum 0.140 683.00 95.62 M-005
Cement at site tonne 0.100 5600.00 560.00 M-081
RCC pipe NP-4/prestressed concrete pipe including metre 25.000 5152.00 128800.00 M-149
collar at site
Granular material passing 5.6 mm sieve for bedding cum 12.500 240.00 3000.00 M-009
c) Overhead charges @ 10 % on (a+b) 13471.36
d) Contractor's profit @ 10 % on (a+b+c) 14818.50
Cost for 12.5 metres = a+b+c+d 163003.48
Rate per metre = (a+b+c+d)/12.5 13040.28
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 13040.00
is to be calculated as per design and priced separately and
added .
172
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
173
CHAPTER- 10
MAINTENANCE OF ROADS
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
10.1 3002 Restoration of Rain Cuts
Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original alignment, levels and slopes
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour hour 0.130 914.00 118.82 P&M-026
Tipper ( L is average lead in km for borrow earth) [Link] 12 x L 2.25 270.00 Lead =10
km & P&M-
058
Add 10 per cent of cost of carriage towards loading and 27.00
unloading charges.
Plate compactor hour 0.500 94.00 47.00 P&M-086
c) Overhead charges @ 10 % on (a+b) 93.68
d) Contractor's profit @ 10 % on (a+b+c) 103.05
Cost for 10 cum = a+b+c+d 1133.55
Rate per cum = (a+b+c+d)/10 113.36
say 113.00
Note Only 75 per cent of fresh material has been provided as 25
per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of there in cuts
Tipper ( L is average lead in km for borrow earth) [Link] 24xL 2.25 540.00 Lead =10
km & P&M-
058
Add 10 per cent of cost of transportation to cover cost of 54.00
loading and unloading
Plate compactor @ 25 sqm per hour hour 12.000 94.00 1128.00 P&M-086
c) Overhead charges @ 10 % on (a+b) 301.70
d) Contractor's profit @ 10 % on (a+b+c) 331.87
Cost for 100 sqm = a+b+c+d 3650.57
Rate per sqm = (a+b+c+d)100 36.51
say 37.00
10.3 3003 Maintenance of Earth Shoulder (stripping excess soil)
174
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 94.00 376.00 P&M-086
c) Overhead charges @ 10 % on (a+b) 96.85
d) Contractor's profit @ 10 % on (a+b+c) 106.54
Cost for 100 sqm = a+b+c+d 1171.89
Rate per sqm on = (a+b+c+d)100 11.72
say 11.70
Note The earth stripped from earthen shoulders to be dumped on
the side slopes locally for disposal.
10.3.1 3004 Repair of pot holes by Wet Mix Macadam material
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
compacting base of excavation as per clause 503, back
filling the pot holes with wet mix macadam material by
mannual means as per clause 406, compacting with roller
8-10T, trimming and finishing the surface to form a smooth
continuous surface, all as per clause 3004.
Unit = cum
Taking output = 15 cum (18 tonnes)
a) Labour
Mate day 0.280 300.00 84.00 L-12
Mazdoor skilled day 1.000 250.00 250.00 L-15
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 0.400 999.00 399.60 P&M-094
Electric generator 125 KVA hour 0.400 741.00 296.40 P&M-018
Front end loader 1 cum capacity hour 0.400 770.00 308.00 P&M-017
Paver finisher hour 0.000 715.00 0.00 P&M-035
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 6x0.65 224.00 873.60 P&M-044
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 300.00 1128.00 L-12
Mazdoor Day 90.000 225.00 20250.00 L-13
Mazdoor skilled Day 4.000 250.00 1000.00 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 12000.00 72000.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 250.00 11250.00 P&M-048
175
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Smooth wheeled roller 8-10 tonnes hour 12.000 224.00 2688.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 670.00 123615.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 670.00 61807.50 M-051
Bitumen 80/100 tonne 14.970 48100.00 720057.00 M-075
Bitumen emulsion for tack coat including vertical sides tonne 2.460 40000.00 98400.00 M-077
of pot hole.
d) Overhead charges @ 10 % on (a+b+c) 111382.15
e) Contractor's profit @ 10 % on (a+b+c+d) 122520.36
Cost for 10250 sqm = a+b+c+d+e 1347724.02
Rate per sqm = (a+b+c+d+e)/10250 131.49
say 131.00
10.4.1 3004.2 Filling Pot- holes and Patch Repairs with mix seal
surfacing type "B", 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 300.00 1128.00 L-12
Mazdoor Day 90.000 225.00 20250.00 L-13
Mazdoor skilled Day 4.000 250.00 1000.00 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 12000.00 72000.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 250.00 11250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 224.00 2688.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 670.00 123615.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 670.00 61807.50 M-051
Bitumen 80/100 tonne 19.475 48100.00 936747.50 M-075
Bitumen emulsion for tack coat including vertical sides tonne 2.563 40000.00 102500.00 M-077
of pot hole.
d) Overhead charges @ 10 % on (a+b+c) 133461.20
e) Contractor's profit @ 10 % on (a+b+c+d) 146807.32
Cost for 10250 sqm = a+b+c+d+e 1614880.52
Rate per sqm = (a+b+c+d+e)/375 157.55
say 158.00
10.4.2 3004.2 Filling Pot- holes and Patch Repairs with open - graded
Premix surfacing, 20mm followed by seal coat type "B".
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 300.00 1128.00 L-12
Mazdoor Day 95.000 225.00 21375.00 L-13
Mazdoor skilled Day 5.000 250.00 1250.00 L-15
b) Machinery
176
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 12000.00 72000.00 P&M-021
Tipper 10 tonnes capacity hour 53.000 250.00 13250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 224.00 2688.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 670.00 123615.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 670.00 61807.50 M-051
Coarse Sand/Crusher dust for seal coat cum 61.500 240.00 14760.00 M-004
Bitumen 80/100 tonne 21.935 48100.00 1055073.50 M-075
Bitumen emulsion for tack coat including vertical sides tonne 2.563 40000.00 102500.00 M-077
of pot hole.
d) Overhead charges @ 10 % on (a+b+c) 147107.30
e) Contractor's profit @ 10 % on (a+b+c+d) 161818.03
Cost for 10250 sqm = a+b+c+d+e 1779998.33
Rate per sqm = (a+b+c+d+e)/10250 173.66
say 174.00
10.4.3 3004.2 Filling Pot- holes and Patch Repairs with open - graded
Premix surfacing, 20mm followed by seal coat type "B"
using emulsion as binder
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with emulsion rapid
setting as binder as per clause 511, compacting, trimming
and finishing the surface to form a smooth continuous
surface, all as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 300.00 1128.00 L-12
Mazdoor Day 90.000 225.00 20250.00 L-13
Mazdoor skilled Day 4.000 250.00 1000.00 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 12000.00 72000.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 250.00 11250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 224.00 2688.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 670.00 123615.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 670.00 61807.50 M-051
Coarse Sand/Crusher dust for seal coat cum 61.500 369.00 22693.50 M-027
Bitumen 80/100 tonne 0.000 48100.00 0.00 M-075
Bitumen emulsion for tack coat including vertical sides tonne 24.498 41600.00 1019096.00 M-077
of pot hole.
d) Overhead charges @ 10 % on (a+b+c) 133715.40
e) Contractor's profit @ 10 % on (a+b+c+d) 147086.94
Cost for 10250 sqm = a+b+c+d+e 1617956.34
Rate per sqm = (a+b+c+d+e)/10250 157.85
say 158.00
10.5 3004.2 Filling Pot-holes and Patch Repairs with Bituminous
concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 223 sqm (8.92 cum)(20 Tonnes)
177
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Labour
Mate Day 0.480 300.00 144.00 L-12
Mazdoor Day 12.000 225.00 2700.00 L-13
Mazdoor skilled Day 2.000 250.00 500.00 L-15
b) Machinery
Air compressor 250 cfm hour 10.000 271.00 2710.00 P&M-001
HMP 100-110 TPH Capacity hour 1.000 11000.00 11000.00 P&M-022
Tipper 10 tonnes capacity hour 12.000 250.00 3000.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 10.000 224.00 2240.00 P&M-044
c) Material
I) Bitumen tonne 1.000 48100.00 48100.00 M-075
ii) Bitumen emulsion for tack coat . tonne 0.113 40000.00 4500.00 M-077
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent cum 4.466 675.00 3014.55 M-051,M-
052,M-053
and M-054
Unit = Sqm
Taking out put = 223 sqm (5.55 cum)(12.55 Tonnes)
178
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Labour
Mate Day 0.480 300.00 144.00 L-12
Mazdoor Day 12.000 225.00 2700.00 L-13
Mazdoor skilled Day 2.000 250.00 500.00 L-15
b) Machinery
Air compressor 250 cfm hour 10.000 271.00 2710.00 P&M-001
HMP 100-110 TPH Capacity hour 1.000 11000.00 11000.00 P&M-022
Tipper 10 tonnes capacity hour 12.000 250.00 3000.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 10.000 224.00 2240.00 P&M-044
c) Material
I) Bitumen tonne 0.628 48100.00 30182.75 M-075
ii) Bitumen emulsion for tack coat . tonne 0.067 40000.00 2676.00 M-077
iii) Aggregates
13.2-10 mm 30 per cent cum 2.508 670.00 1680.36 M-051 and
M-052
10-5 mm 25 per cent cum 2.090 358.00 748.22 M-025
5 mm and Below43 per cent cum 3.595 435.00 1563.74 M-021,M-
022 and
M-024
Filler 2 per cent tonne 0.251 3885.00 975.14 M-188
Add 5 per cent for wastage 248.37
d) Overhead charges @ 10 % on (a+b+c) 6036.86
e) Contractor's profit @ 10 % on (a+b+c+d) 6640.54
Cost for 223 sqm = a+b+c+d+e 73045.98
Rate per Sqm = (a+b+c+d+e)/223 327.56
say 328.00
Note For detailed working of quantities of aggregates, refer item
5.8 of chapter 5
10.6 3004.3.3 Crack Filling
Filling of crack using slow - curing bitumen emulsion and
applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor day 1.000 225.00 225.00 L-13
b) Material
Slow-curing bitumen emulsion Kg 33.000 40.00 1320.00 M-077
Stone crusher dust cum 0.020 308.00 6.16 M-021
c) Overhead charges @ 10 % on (a+b) 156.32
d) Contractor's profit @ 10 % on (a+b+c) 171.95
Cost for 500sqm = a+b+c+d 1891.42
Rate per meter = (a+b+c+d+e)/500 3.78
say 3.80
10.7 3004.4 Dusting
Applying crusher dust to areas of road where bleeding
of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Material
Stone crusher dust finer than 3mm with not more cum 6.250 308.00 1925.00 M-021
than 10 per cent passing 0.075 sieve.
c) Overhead charges @ 10 % on (a+b) 239.90
d) Contractor's profit @ 10 % on (a+b+c) 263.89
Cost for 3500sqm = a+b+c+d 2902.79
179
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per meter = (a+b+c+d)/3500 0.83
say 0.80
10.8 (A) Fog Seal sqm 41.00 Item 5.17
3004.3.2
(B) Crack Prevention courses.
3004.3.4
(i) Stress Absorbing Membrane (SAM) crack width less than 6 sqm 63.00 Item 5.21
mm Case-I
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm sqm 75.00 Item 5.21
to 9 mm Case-II
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm sqm 101.00 Item 5.21
and cracked area above 50 per cent Case-IV
(iv) Bitumen Impregnated Geotextile sqm 503.00 Item 5.21
Case-IV
10.8 (C) 3004.5 Slurry Seal
180
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 271.00 13.55 P&M-001
d) Overhead charges @ 10 % on (a+b+c) 90.76
e) Contractor's profit @ 10 % on (a+b+c+d) 99.83
Cost for 10 metres = a+b+c+d+e 1098.14
Rate per metre = (a+b+c+d+e)/10 109.81
say 110.00
10.11 3000 Hill Side Drain Clearance
Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2
cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 1.000 225.00 225.00 L-13
b) Overhead charges @ 10 % on (a+b) 24.90
c) Contractor's profit @ 10 % on (a+b) 27.39
Cost for 10 metres = a+b+c 301.29
Rate per metre = (a+b+c)/10 30.13
say 30.00
10.12 3000 Land Slide Clearance in soil
Clearance of land slides in soil and ordinary rock by a bull-
dozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor day 1.000 225.00 225.00 L-13
b) Machinery
Dozer 180 HP @ 60 cum per hour hour 1.670 2373.00 3962.91 P&M-014
c) Overhead charges @ 10 % on (a+b) 419.99
d) Contractor's profit @ 10 % on (a+b+c) 461.99
Cost for 100 cum = a+b+c+d 5081.89
Rate per cum = (a+b+c+d)/100 50.82
say 51.00
Note Land Slide clearance involves pushing of loose earth slided
on the road surface from hill face on the valley side. Since
no cutting of original ground is involved, the output of dozer
has been taken as 60 cum per hour for soil, ordinary rock
and blasted hard rock. However, if there are objection to
disposing of earth on valley side, additional resources for its
disposal shall be considered as per site conditions.
181
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Dozer D 80 A-12,180 HP @ 60 cum per hour hour 1.670 2373.00 3962.91 P&M-014
Air compressor 250 cfm with two jack hammer hour 2.500 271.00 677.50 P&M-001
c) Materials
Gelatine 80 per cent @ 35 kg per 100 cum kg 17.500 111.00 1942.50 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 70.000 6.60 462.00 M-094 /100
of 125 gms each
c) Overhead charges @ 10 % on (a+b) 761.44
d) Contractor's profit @ 10 % on (a+b+c) 837.59
Cost for 100 cum = a+b+c+d+e 9213.44
Rate per cum = (a+b+c+d+e)/100 92.13
say 92.00
Note Credit for the rock if found acceptable as construction
material shall be afforded
10.14 3000 Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer 165 Hp
and disposing it on the valley side
Unit = cum
Taking output = 5000 cum
a) Labour
Mate day 0.080 300.00 24.00 L-12
Mazdoor day 2.000 225.00 450.00 L-13
b) Machinery
Dozer D 80 A-12,180 HP @ 850 cum per hour hour 5.880 2373.00 13953.24 P&M-014
c) Overhead charges @ 10 % on (a+b) 1442.72
d) Contractor's profit @ 10 % on (a+b+c) 1587.00
Cost for 5000 cum = a+b+c+d 17456.96
Rate per cum = (a+b+c+d)/5000 3.49
say 3.00
Note i) Labour provided will not be cutting the snow. They will be
guiding the dozer operator on the alignment of the road as
entire surface gets covered with snow and the edges of the
road are not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any eventuality of
avalanches, slide etc
182
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor day 4.000 225.00 900.00 L-13
b) Machinery
Transportation either board at shop or welding Km 20.000 50.00 1000.00 P&M-087
machine at site
Welding machine with rods Hrs 6.000 167.00 1002.00 P&M-095
c) Overhead charges @ 10 % on (a+b) 231.00
d) Contractor's profit @ 10 % on (a+b+c) 354.30
Cost for 10 Nos. (a+b+c+d) 3897.30
Rate per cum = (a+b+c+d)/10 389.73
say 390.00
10.17 3000 Repair of road side cuts by earthen bags
Repair of road side cuts by earthen bags using empty gunny
bag or cement bag including filling by dry sandy soil or local
dry soil, transporting and fixing properly at site as per
directions by Engineer.
Unit = Nos.
Taking output = 100 Nos.
a) Labour
Mate day 0.200 300.00 60.00 L-12
Mazdoor day 5.000 225.00 1125.00 L-13
b) Machinery
Transportation either board at shop or welding Km 10.000 50.00 500.00 P&M-087
machine at site
c) Overhead charges @ 10 % on (a+b) 168.50
d) Contractor's profit @ 10 % on (a+b+c) 185.35
Cost for 100 Nos. (a+b+c+d) 2038.85
Rate per bag = (a+b+c+d)/100 20.39
say 20.00
10.18 Survey and Preparation of drawings for road work
Supplying of survey sheets Plan, L section, Cross sections
and calculation sheets in two hard copies with soft copy
(CD), including carrying out survey at 10m interval with 1
mm staff in 30m width i.e.15 m on either side of centre of
road, submission of drawings Plan, L section and cross
section including Cross sections of CD work up to culverts
plane table survey of populated area and calculation sheets
of Earth work, GSB, WMM, BM layer , SDBC layer and
earthwork for side drain as required by engineer in charge.
Work includes making of Bench marks 0.45x0.45x0.75 m
keeping 0.30m outside, plaster thereon duly painted and
marked at suitable interval or every 2Km and all T&P and
labour and material in all respect. Complete as per MoRTH
specifications.
183
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Survey level Total station theodilite/ Autolevel/ staff, day 10.000 800.00 8000.00
measuring tape. Ranging rods etc. all other
instruments hire charges
Enamel paint Litre 2.000 171.00 342.00 M-007
Unit = Nos.
Taking output = 3 nos.
a) Labour
Mate day 0.760 300.00 228.00 L-12
Mazdoor day 15.000 225.00 3375.00 L-13
Surveyor day 3.000 350.00 1050.00 L-12-1
Computer draftman day 2.000 350.00 700.00 L-12-1
Printing charges of sheets L section. Plan and cross Each 3.000 2000.00 6000.00
sections, calculation sheets etc. in 2 copies
b) Machinery
Transportation of man and machinary at site day 3.000 1000.00 3000.00
Survey level Total station theodilite/ Autolevel/ staff, day 3.000 800.00 2400.00
measuring tape. Ranging rods etc. all other
instruments hire charges
c) Material
Making of bench marks using brick masonry in cement Nos. 6.000 633.01 3798.05
mortar 1:3 size 0.45x0.45x0.75m kepping 0.30m
outside ground (0.456x0.45x0.75=0.152 cum and 0.56
sqm plaster on all 5 faces)
Survey level Total station theodilite/ Autolevel/ staff, day 3.000 800.00 2400.00
measuring tape. Ranging rods etc. all other
instruments hire charges
Enamel paint Litre 2.000 171.00 342.00 M-007
184
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Repair of road by built up spray grout by Providing, laying
and rolling of built-up-spray grout layer over prepared base
consisting of a two layer composite construction of
compacted crushed coarse aggregates using motor grader
for aggregates. key stone chips spreader may be used with
application of bituminous binder after each layer, and with
key aggregates placed on top of the second layer to serve
as a Base conforming to the line, grades and cross-section
specified, the compacted layer thickness being 75 mm
Unit = sqm
Taking output = 300 sqm (22.5 cum)
a) Labour
Mate day 0.560 300.00 168.00 L-12
Mazdoor including for brooming of key aggregates day 10.000 225.00 2250.00 L-13
Mazdoor skilled day 4.000 250.00 1000.00 L-15
b) Machinery
Tipper 5.5 cum capacity hour 10.000 250.00 2500.00 P&M-048
roller 8 tonnes hour 10.000 1188.00 11880.00 P&M-059
Air compressor hour 6.000 271.00 1626.00 P&M-001
c) Material
Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for tonne 0.900 49100.00 44190.00 M-074
each layer
Crushed stone coarse aggregate passing 53 mm and cum 30.000 690.00 20700.00 M-035
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer
Key aggregates passing 22.4 mm and retained on 2.8 cum 3.900 690.00 2691.00 M-031
mm sieve @ 0.13 cum per 10 sqm
d) Overhead charges @ 10 % on (a+b+c) 8700.50
e) Contractor's profit @ 10 % on (a+b+c+d) 9570.55
Cost for 300 sqm = a+b+c+d+e 105276.05
Rate per sqm = (a+b+c+d+e)/300 350.92
say 351.00
185
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 94.00 376.00 P&M-086
c) Overhead charges @ 10 % on (a+b) 96.85
d) Contractor's profit @ 10 % on (a+b+c) 106.54
Cost for 100 sqm = a+b+c+d 1171.89
Rate per sqm on = (a+b+c+d)100 11.72
say 11.70
Note The earth stripped from earthen shoulders to be dumped on
the side slopes locally for disposal.
10.3.1 3004 Repair of pot holes by Wet Mix Macadam material
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
compacting base of excavation as per clause 503, back
filling the pot holes with wet mix macadam material by
mannual means as per clause 406, compacting with roller
8-10T, trimming and finishing the surface to form a smooth
continuous surface, all as per clause 3004.
Unit = cum
Taking output = 15 cum (18 tonnes)
a) Labour
Mate day 0.280 300.00 84.00 L-12
Mazdoor skilled day 1.000 250.00 250.00 L-15
Mazdoor day 6.000 225.00 1350.00 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 0.400 999.00 399.60 P&M-094
Electric generator 125 KVA hour 0.400 741.00 296.40 P&M-018
Front end loader 1 cum capacity hour 0.400 770.00 308.00 P&M-017
Paver finisher hour 0.000 715.00 0.00 P&M-035
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 6x0.65 224.00 873.60 P&M-044
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 300.00 1128.00 L-12
Mazdoor Day 90.000 225.00 20250.00 L-13
Mazdoor skilled Day 4.000 250.00 1000.00 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 12000.00 72000.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 250.00 11250.00 P&M-048
186
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Smooth wheeled roller 8-10 tonnes hour 12.000 224.00 2688.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 670.00 123615.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 670.00 61807.50 M-051
Bitumen 80/100 tonne 14.970 48100.00 720057.00 M-075
Bitumen emulsion for tack coat including vertical sides tonne 2.460 40000.00 98400.00 M-077
of pot hole.
d) Overhead charges @ 10 % on (a+b+c) 111382.15
e) Contractor's profit @ 10 % on (a+b+c+d) 122520.36
Cost for 10250 sqm = a+b+c+d+e 1347724.02
Rate per sqm = (a+b+c+d+e)/10250 131.49
say 131.00
10.4.1 3004.2 Filling Pot- holes and Patch Repairs with mix seal
surfacing type "B", 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 300.00 1128.00 L-12
Mazdoor Day 90.000 225.00 20250.00 L-13
Mazdoor skilled Day 4.000 250.00 1000.00 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 271.00 1626.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 12000.00 72000.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 250.00 11250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 224.00 2688.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 670.00 123615.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 670.00 61807.50 M-051
Bitumen 80/100 tonne 19.475 48100.00 936747.50 M-075
Bitumen emulsion for tack coat including vertical sides tonne 2.563 40000.00 102500.00 M-077
of pot hole.
d) Overhead charges @ 10 % on (a+b+c) 133461.20
e) Contractor's profit @ 10 % on (a+b+c+d) 146807.32
Cost for 10250 sqm = a+b+c+d+e 1614880.52
Rate per sqm = (a+b+c+d+e)/375 157.55
say 158.00
10.4.2 3004.2 Filling Pot- holes and Patch Repairs with open - graded
Premix surfacing, 20mm followed by seal coat type "B".
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 300.00 1128.00 L-12
Mazdoor Day 95.000 225.00 21375.00 L-13
Mazdoor skilled Day 5.000 250.00 1250.00 L-15
b) Machinery
187
CHAPTER-11
HORTICULTURE
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
11.1 307 Spreading of Sludge Farm Yard Manure or/and good
Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 300.00 12.00 L-12
Mazdoor day 1.000 225.00 225.00 L-13
b) Overhead charges @ 10 % on (a) 23.70
c) Contractor's profit @ 10 % on (a+b) 26.07
Cost for 15 cum= a+b+c 286.77
Rate per cum = (a+b+c)/15 19.12
say 19.00
11.2 307 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 300.00 51.00 L-12
Mazdoor for grassing day 0.750 225.00 168.75 L-13
Mazdoor for maintenance for 30 days day 1.000 225.00 225.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 130.00 65.00 P&M-060
c) Material
Doob grass kg 100.000 66.00 6600.00 M-112
d) Overhead charges @ 10 % on (a+b+c) 710.98
e) Contractor's profit @ 10 % on (a+b+c+d) 782.07
Cost for 100 sqm = a+b+c+d+e 8602.80
Rate per sqm= (a+b+c+d+e)/100 86.03
say 86.00
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.220 300.00 66.00 L-12
Mazdoor for grassing. day 1.250 225.00 281.25 L-13
for maintenance for 30 days day 1.000 225.00 225.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 130.00 97.50 P&M-060
c) Material
Doob grass kg 200.000 66.00 13200.00 M-112
d) Overhead charges @ 10 % on (a+b+c) 1386.98
e) Contractor's profit @ 10 % on (a+b+c+d) 1525.67
Cost for 100 sqm = a+b+c+d+e 16782.40
Rate per sqm = (a+b+c+d+e)/100 167.82
say 168.00
Note In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants
require more care.
11.3 307 Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.150 300.00 45.00 L-12
Mazdoor for preparation of ground day 0.500 225.00 112.50 L-13
188
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Mali for fetching doobs grass roots and grassing at 15 day 1.000 300.00 300.00 L-09
cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 130.00 65.00 P&M-060
Tractor with tiller hour 0.010 193.00 1.93 P&M-053
c) Material
Supply of farm yard manure at site of work cum 0.180 320.00 57.60 M-167
Fine grass kg 100.000 112.00 11200.00 M-113
d) Overhead charges @ 10 % on (a+b+c) 1178.20
e) Contractor's profit @ 10 % on (a+b+c+d) 1296.02
Cost for 100 sqm = a+b+c+d+e 14256.26
Rate per sqm = (a+b+c+d+e)/100 142.56
say 143.00
11.4 307 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 300.00 3000.00 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 130.00 1950.00 P&M-060
c) Material
Cost of water KL 90.000 64.00 5760.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 1071.00
e) Contractor's profit @ 10 % on (a+b+c+d) 1178.10
Cost for 100 sqm = a+b+c+d+e 12959.10
Rate per sqm = (a+b+c+d+e)/100 129.59
say 130.00
11.5 307 Turfing Lawns with Fine Grassing including Ploughing,
Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 300.00 75.00 L-12
Mazdoor for preparation of ground day 1.000 225.00 225.00 L-13
Mali for fetching doobs grass roots hedges and day 1.500 300.00 450.00 L-09
grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 130.00 65.00 P&M-060
Tractor with tiller hour 0.010 193.00 1.93 P&M-053
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 320.00 192.00 M-167
per 100 sqm
Fine grass kg 100.000 112.00 11200.00 M-113
d) Overhead charges @ 10 % on (a+b+c) 1220.89
e) Contractor's profit @ 10 % on (a+b+c+d) 1342.98
Cost for 100 sqm = a+b+c+d+e 14772.81
Rate per sqm = (a+b+c+d+e)/100 147.73
say 148.00
11.6 307 Maintenance of Lawns with Fine Grassing for the First
Year
Maintenance of lawns with fine grassing for the first year
including watering etc
Unit = sqm
189
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Taking output = 100 sqm
a) Labour
Mali day 10.000 300.00 3000.00 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 130.00 2600.00 P&M-060
c) Material
Cost of water KL 60.000 64.00 3840.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 944.00
e) Contractor's profit @ 10 % on (a+b+c+d) 1038.40
Cost for 100 sqm = a+b+c+d+e 11422.40
Rate per sqm = (a+b+c+d+e)/100 114.22
say 114.00
11.7 307 Planting and Maintaining of Permanent Hedges
(a) Planting permanent hedges including digging of
trenches
Planting permanent hedges including digging of trenches, 60
cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 130.00 65.00 P&M-060
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 33.00 22440.00 M-116
Supply of farm yard manure at site of work cum 4.670 320.00 1494.40 M-167
Pesticide kg 0.250 258.00 64.50 M-136
Cost of water KL 3.000 64.00 192.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 2782.59
e) Contractor's profit @ 10 % on (a+b+c+d) 3060.85
Cost for 100 metres = a+b+c+d+e 33669.34
Rate per metre = a+b+c+d+e)/100 336.69
say 337.00
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 3.000 300.00 900.00 L-12
Mazdoor day 30.000 225.00 6750.00 L-13
b) Machinery
Water tanker6 KL capacity hour 5.000 130.00 650.00 P&M-060
c) Material
Manure sludge/Farm yard manure cum 2.000 320.00 640.00 M-167
Pesticide kg 0.500 258.00 129.00 M-136
Cost of water KL 30.000 64.00 1920.00 M-189
Cost of hedge plants @ 10 per cent casualty each 68.000 33.00 2244.00 M-116
d) Overhead charges @ 10 % on (a+b+c) 1323.30
e) Contractor's profit @ 10 % on (a+b+c+d) 1455.63
Cost for 100 metres = a+b+c+d+e 16011.93
190
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Rate per metre = a+b+c+d+e)/100 160.12
say 160.00
11.8 307 Planting and Maintaining of Flowering Plants and
Shrubs
(a) Planting flowering plants and shrubs in central verge
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 300.00 510.00 L-12
Mazdoor for planting day 2.000 225.00 450.00 L-13
Mazdoor for maintenance for one year day 15.000 225.00 3375.00 L-13
b) Machinery
191
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Water tanker6 KL capacity hour 2.000 130.00 260.00 P&M-060
c) Material
Sapling 2 m high 25 mm dia each 10.000 65.00 650.00 M-160
Farm yard manure cum 0.940 320.00 300.80 M-167
Pesticide kg 0.500 258.00 129.00 M-136
Cost of water KL 12.000 64.00 768.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 644.28
e) Contractor's profit @ 10 % on (a+b+c+d) 708.71
Cost for 10 trees = a+b+c+d+e 7795.79
Rate per trees = (a+b+c+d+e)/10 779.58
say 780.00
11.10 308 Renovation Lawns including, Weeding, Forking the
Ground, Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground,
top dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 300.00 36.00 L-12
Mazdoor day 3.000 225.00 675.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 130.00 65.00 P&M-060
c) Material
Cost of water KL 3.000 64.00 192.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 96.80
e) Contractor's profit @ 10 % on (a+b+c+d) 106.48
Cost for 100 sqm = a+b+c+d+e 1171.28
Rate per sqm = (a+b+c+d+e) 11.71
say 12.00
11.11 308.2 Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly cum 1.000 320.00 320.00 M-167
screened, loading, carriage, unloading and
stacking at site
b) Overhead charges @ 10 % on (a) 32.00
c) Contractor's profit @ 10 % on (a+b) 35.20
Rate per cum = (a+b+c) 387.20
387.00
11.12 308.20 Supply at Site of Work/ Store-Deoiled Neem Cake
Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in quintal 1.000
store/site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per quintal = a+b+c
11.13 308.2 Supplying Sludge
192
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, loading, cum 1.000
unloading and stacking at site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per cum = a+b+c
11.14 New Half Brick Circular Tree Guard, in 2nd Class Brick,
internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 300.00 15.00 L-12
Mason day 0.250 350.00 87.50 L-11
Mazdoor day 0.250 225.00 56.25 L-13
b) Material
Brick 2nd class including carriage each 230.000 3.10 713.00 M-079
Cement mortar 1:6 cum 0.025 2647.00 66.18 Item 12.6
(D)
c) Overhead charges @ 10 % on (a+b) 93.79
d) Contractor's profit @ 10 % on (a+b+c) 103.17
Rate per tree Guard = a+b+c+d 1134.89
say 1135.00
11.15 New Edging with 2nd Class Bricks, Laid Dry Lengthwise
Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres
Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 300.00 0.60 L-12
Mason day 0.050 350.00 17.50 L-11
Mazdoor day 0.050 225.00 11.25 L-13
b) Material
Brick 2nd class including carriage each 50.000 3.10 155.00 M-079
c) Overhead charges @ 10 % on (a+b) 18.44
d) Contractor's profit @ 10 % on (a+b+c) 20.28
Cost for 10 metre = a+b+c+d 223.06
Rate per metre = (a+b+c+d)/10 22.31
say 22.00
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 300.00 6.00 L-12
193
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Blacksmith day 0.150 350.00 52.50 L-02
Mazdoor day 0.070 225.00 15.75 L-13
b) Material
Empty bitumen drum each 1.000 258.00 258.00 M-172
MS sheet 50 x 0.5 mm kg 0.650 51.52 33.49 M-179
/1000
Rivets 6 mm dia and 10 mm in length each 22.000 1.00 22.00 M-158
d) Overhead charges @ 10 % on (a+b+c) 38.77
e) Contractor's profit @ 10 % on (a+b+c+d) 42.65
Rate for each tree guard = a+b+c+d 469.16
say 469.00
11.17 New Making Tree Guard 53 cm dia and 2 Metre High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects
Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 300.00 12.00 L-12
Blacksmith day 0.200 350.00 70.00 L-02
Mazdoor 0.200 225.00 45.00 L-13
b) Material
Empty bitumen drum each 1.500 258.00 387.00 M-172
MS sheet50 x 0.5 mm kg 0.650 51.52 33.49 M-179
/1000
Rivets 6 mm dia and 10 mm in length each 50.000 1.00 50.00 M-158
MSplate30 x 3 mm kg 1.300 51.52 66.98 M-179
/1000
c) Overhead charges @ 10 % on (a+b) 66.45
d) Contractor's profit @ 10 % on (a+b+c) 73.09
Rate for each tree guard = a+b+c+d 804.00
say 804.00
11.18 New Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 300.00 135.00 L-12
Blacksmith/ welder for cutting to design and shape and day 2.000 350.00 700.00 L-02
jointing
Mazdoor for fixing and helper for Blacksmith/welder day 2.500 225.00 562.50 L-13
b) Material
Angle, tees, channels etc quintal 1.050 5152.00 5409.60 M-179 /10
Deduct the cost of scrap quintal 0.050 (1717.33) (85.87) M-179/10/3
Add 5 per cent of cost of material for welding rods and other 266.19
welding accessories
c) Overhead charges @ 10 % on (a+b) 698.74
d) Contractor's profit @ 10 % on (a+b+c) 768.62
Rate per quintal = a+b+c+d 8454.78
say 8455.00
194
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
11.19 New Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 300.00 15.00 L-12
Blacksmith day 0.250 350.00 87.50 L-02
Mazdoor day 0.250 225.00 56.25 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 51.52 989.18 M-179
/1000
MS iron 25 x 3 mm kg 9.600 51.52 494.59 M-179
/1000
Add 5 per cent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 193.00 7.72 P&M-053
d) Painting
Painting two coats including priming sqm 1.770 50.00 88.50 Item 8.9
e) Overhead charges @ 10 % on (a+b+c) 165.02
f) Contractor's profit @ 10 % on (a+b+c+e) 181.53
Rate per tree guard =a+b+c+d+e+f 2085.30
say 2085.00
Note 1 The items of excavation and concreting to be measured
and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
11.20 New Tree Guard with MS Angle Iron and Steel Wire
Providing and fixing tree guard 0.60 metre square, 2.00
metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one
a) Labour
Mate day 0.050 300.00 15.00 L-12
Blacksmith day 0.250 350.00 87.50 L-02
Welder day 0.250 350.00 87.50 L-02
Mazdoor day 0.250 225.00 56.25 L-13
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 51.52 695.52 M-179
/1000
MS iron 25 x 3 mm kg 18.000 51.52 927.36 M-179
/1000
Steel wire 3 mm dia kg 6.000 168.00 1008.00 M-192
Add 5 per cent of cost of material for riveting, bolting 131.54
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 193.00 7.72 P&M-053
d) Painting
Painting two coats including priming sqm 1.500 50.00 75.00 Item 8.9
e) Overhead charges @ 10 % on (a+b+c) 301.64
f) Contractor's profit @ 10 % on (a+b+c+e) 331.80
Rate per tree guard = a+b+c+d+e+f 3724.84
say 3725.00
195
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
11.21 New Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate day 2.500 300.00 750.00 L-12
Mazdoor day 25.000 225.00 5625.00 L-13
ii) For Maintenance for one year
Mate day 5.000 300.00 1500.00 L-12
Mazdoor day 50.000 225.00 11250.00 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 1595.00 15950.00 P&M-015
Water tanker6 KL capacity (for planting) hour 3.000 130.00 390.00 P&M-060
Water tanker6 KL capacity (for maintenance) hour 25.000 130.00 3250.00 P&M-060
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 52.00 15080.00 M-160 x
0.8
Add 10 per cent of sapling each 29.000 52.00 1508.00 M-160 x
0.8
Decayed farm yard/sludge manure (planting) cum 60.900 320.00 19488.00 M-167
Decayed farm yard/sludge manure (maintenance) cum 4.000 320.00 1280.00 M-167
Pesticides for planting kg 0.500 258.00 129.00 M-136
Pesticides for maintenance kg 1.500 258.00 387.00 M-136
Cost of water KL 18.000 64.00 1152.00 M-189
d) Overhead charges @ 10 % on (a+b+c) 7773.90
e) Contractor's profit @ 10 % on (a+b+c+d) 8551.29
Rate per hectare = a+b+c+d+e 94064.19
say 94064.00
Note Cost of fencing to be provided as per size of plot and
approved design, measured and paid separately
196
CHAPTER-12
FOUNDATIONS
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 300.00 42.00 L-12
Mazdoor day 3.50 225.00 787.50 L-13
b) Overhead charges @ 10 % on (a) 82.95
c) Contractor's profit @ 10 % on (a+b) 91.25
Cost for 10 cum = a+b+c 1003.70
Rate per cum = (a+b+c)/10 100.37
say 100.00
Note 1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
[Link] excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
197
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cum = (a+b+c+d)/240 37.21
say 37.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
12.1 (I) B (ii) Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 300.00 96.00 L-12
Mazdoor day 8.00 225.00 1800.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 914.00 5484.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 738.00
d) Contractor's profit @ 10 % on (a+b+c) 811.80
Cost for 210 cum = a+b+c+d 8929.80
Rate per cum = (a+b+c+d)/210 42.52
say 43.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B (iii) Depth above 6m
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 300.00 120.00 L-12
Mazdoor day 10.00 225.00 2250.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 914.00 5484.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 785.40
d) Contractor's profit @ 10 % on (a+b+c) 863.94
Cost for 180 cum = a+b+c+d 9503.34
Rate per cum = (a+b+c+d)/180 52.80
say 53.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
[Link] provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 300.00 60.00 L-12
Mazdoor day 5.00 225.00 1125.00 L-13
b) Overhead charges @ 10 % on (a) 118.50
c) Contractor's profit @ 10 % on (a+b) 130.35
Cost for 10 cum = a+b+c 1433.85
Rate per cum = (a+b+c)/10 143.39
say 143.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) B Mechanical Means
Unit = cum
Taking output = 180 cum
198
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Labour
Mate day 0.24 300.00 72.00 L-12
Mazdoor day 6.00 225.00 1350.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 914.00 5484.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 690.60
d) Contractor's profit @ 10 % on (a+b+c) 759.66
Cost for 180 cum = a+b+c+d 8356.26
Rate per cum = (a+b+c+d)/180 46.42
say 46.00
Note [Link] of dewatering upto 10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
[Link] case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 300.00 105.00 L-12
Driller day 0.50 250.00 125.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 8.00 225.00 1800.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 271.00 271.00 P&M-001
drilling.
c) Material
Blasting Material kg 3.50 111.00 388.50 M-104
Detonator electric each 14.00 6.60 92.40 M-094/100
d) Overhead charges @ 10 % on (a+b+c) 284.44
e) Contractor's profit @ 10 % on (a+b+c+d) 312.88
Cost for 10 cum = a+b+c+d+e 3441.72
Rate per cum = (a+b+c+d+e)/10 344.17
say 344.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering shall be
made as per site conditions.
12.1 IV Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.20 300.00 60.00 L-12
Mazdoor day 5.00 225.00 1125.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 271.00 1626.00 P&M-001
breaker
c) Overhead charges @ 10 % on (a+b) 281.10
d) Contractor's profit @ 10 % on (a+b+c) 309.21
Cost for 10 cum = a+b+c+d 3401.31
Rate per cum = (a+b+c+d)/10 340.13
say 340.00
Note 1. Cost of dewatering upto10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
[Link] case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 V Marshy Soil
199
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.40 300.00 120.00 L-12
Mazdoor day 10.00 225.00 2250.00 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 193.00 515.31 P&M-053
c) Overhead charges @ 10 % on (a+b) 288.53
d) Contractor's profit @ 10 % on (a+b+c) 317.38
Cost for 10 cum = a+b+c+d 3491.23
Rate per cum = ( a+b+c+d)/ 10 349.12
say 349.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil
12.1 (V) B Mechanical Means
a) Labour
Mate day 0.08 300.00 24.00 L-12
Mazdoor for dressing sides, bottom and backfilling day 2.00 225.00 450.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 914.00 155.38 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 250.00 112.50 P&M-048
c) Overhead charges @ 10 % on (a+b) 74.19
d) Contractor's profit @ 10 % on (a+b+c) 81.61
Cost for 10 cum = a+b+c+d 897.67
Rate per cum = (a+b+c+d)/10 89.77
say 90.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 300.00 36.00 L-12
Mazdoor for dressing sides, bottom and backfilling day 3.00 225.00 675.00 L-13
b) Machinery
Tractor-trolley for transportation hour 2.00 193.00 386.00 P&M-053
c) Overhead charges @ 10 % on (a+b) 109.70
d) Contractor's profit @ 10 % on (a+b+c) 120.67
Cost for 6 cum = a+b+c+d 1327.37
Rate per cum = (a+b+c+d)/6 221.23
say 221.00
12.2 304 Filling Annular Space Around Footing in Rock
Unit = cum
Taking out put = 1 cum
200
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Lean cement concrete [Link] nominal mix. Rate may be
taken as per item 12.4.
12.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 300.00 3.00 L-12
Mazdoor day 0.30 225.00 67.50 L-13
b) Material
Sand (assuming 20 per cent voids) cum 1.20 550.00 660.00 M-006
c) Overhead charges @ 10 % on (a+b) 73.05
d) Contractor's profit @ 10 % on (a+b+c) 80.36
Rate per cum = a+b+c+d 883.91
say 884.00
12.4 2100 PCC [Link] in Foundation
Plain cement concrete [Link] nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 300.00 192.00 L-12
Mason day 1.00 350.00 350.00 L-11
Mazdoor day 15.00 225.00 3375.00 L-13
b) Material
40 mm Aggregate cum 13.50 660.00 8910.00 M-055
coarse Sand cum 6.75 683.00 4610.25 M-005
cement tonne 3.45 5600.00 19320.00 M-081
Cost of water KL 18.00 64.00 1152.00 M-189
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Water tanker 6 KL capacity hour 2.00 130.00 260.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 4194.93
e) Contractor's profit @ 10 % on (a+b+c+d) 4614.42
Cost for 15 cum = a+b+c+d+e 50758.59
Rate per cum = (a+b+c+d+e)/15 3383.91
say 3384.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
12.5 1300 Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 3.10 7750.00 M-079
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.20 3788.00 4545.60 Item 12.6
analysis) (A)
b) Labour
Mate day 0.48 300.00 144.00 L-12
Mason day 4.00 350.00 1400.00 L-11
Mazdoor day 8.00 225.00 1800.00 L-13
c) Overhead charges @ 10 % on (a+b) 1563.96
d) Contractor's profit @ 10 % on (a+b+c) 1720.36
Cost for 5 cum = a+b+c+d 18923.92
201
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cum (a+b+c+d)/5 3784.78
say 3785.00
12.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)
analysis
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 5600.00 2856.00 M-081
Sand cum 1.05 683.00 717.15 M-005
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mazdoor day 0.90 225.00 202.50 L-13
Total Material and Labour = (a+b) say 3788.00
Sub- (B) Cement Mortar1:2 (1cement :2 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 5600.00 3763.20 M-081
Sand cum 0.93 683.00 635.19 M-005
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mazdoor day 0.90 225.00 202.50 L-13
Total Material and Labour = (a+b) say 4613.00
Sub- (C) Cement Mortar1:4 (1cement :4 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 5600.00 2257.92 M-081
Sand cum 1.12 683.00 764.96 M-005
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mazdoor day 0.90 225.00 202.50 L-13
Total Material and Labour = (a+b) say 3237.00
Sub- (D) Cement Mortar1:6 (1cement :6 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 5600.00 1612.80 M-081
Sand cum 1.34 683.00 913.27 M-005
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mazdoor day 0.90 225.00 202.50 L-13
Total Material and Labour = (a+b) say 2741.00
12.7 1400 Stone Masonry Work in Cement Mortar 1:3 in
Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)
202
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Material
Stone cum 5.50 773.00 4251.50 M-169
Through and bond stone each 35.00 38.00 1330.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 3788.00 5682.00 Item 12.6
analysis) (A)
b) Labour
Mate day 0.66 300.00 198.00 L-12
Mason day 7.50 350.00 2625.00 L-11
Mazdoor day 9.00 225.00 2025.00 L-13
c) Overhead charges @ 10 % on (a+b) 1611.15
d) Contractor's profit @ 10 % on (a+b+c) 1772.27
Cost for 5 cum = a+b+c+d 19494.92
Rate per cum (a+b+c+d)/5 3898.98
say 3899.00
1405.3 (B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 383.00 2106.50 M-148
Through and bond stone each 35.00 38.00 1330.00 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.55 3788.00 5871.40 Item 12.6
analysis) (A)
b) Labour
Mate day 0.62 300.00 186.00 L-12
Mason day 6.00 350.00 2100.00 L-11
Mazdoor day 9.00 225.00 2025.00 L-13
c) Overhead charges @ 10 % on (a+b) 1361.89
d) Contractor's profit @ 10 % on (a+b+c) 1498.08
Cost for 5 cum = a+b+c+d 16478.87
Rate per cum (a+b+c+d)/5 3295.77
say 3296.00
Note The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
12.8 1500, Plain/Reinforced Cement Concrete in Open Foundation
1700 & complete as per Drawing and Technical Specifications.
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5600.00 23128.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
40 mm Aggregate cum 8.10 660.00 5346.00 M-055
20 mm Aggregate cum 4.05 680.00 2754.00 M-053
10 mm Aggregate cum 1.35 670.00 904.50 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 63 KVA hour 6.00 572.00 3432.00 P&M-019
Per Cum Basic Cost of Labour, Material & Machinery 3083.00
(a+b+c)
203
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
d) Formwork @ 4 per cent on cost of concrete i.e. cost 1849.51
of material, labour and machinery
204
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cum = ( a+b+c+d+e+f )/15 4360.38
say 4360.00
12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 5600.00 233296.00 M-081
Coarse Sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 km, L-lead in km [Link] 300L 2.00 12000.00 P&M-050
Lead= 20
km
Concrete Pump hour 6 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3117.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 14958.52
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 38892.15
f) Contractor's profit @ 10 % on (a+b+c+d+e) 42781.37
Cost for 120 cum = a+b+c+d+e+f 470595.04
Rate per cum = ( a+b+c+d+e+f )/120 3921.63
say 3922.00
12.8 D PCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 5600.00 33544.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
40 mm Aggregate cum 5.40 660.00 3564.00 M-055
20 mm Aggregate cum 5.40 680.00 3672.00 M-053
10 mm Aggregate cum 2.70 670.00 1809.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3751.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 2109.83
e) Overhead charges @ 10 % on (a+b+c+d) 5837.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 6420.93
Cost for 15 cum = a+b+c+d+e+f 70630.22
Rate per cum = ( a+b+c+d+e+f )/15 4708.68
say 4709.00
205
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 5600.00 268520.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
40 mm Aggregate cum 43.20 660.00 28512.00 M-055
20 mm Aggregate cum 43.20 680.00 29376.00 M-053
10 mm Aggregate cum 21.60 670.00 14472.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3405.00
(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. 15320.21
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 42385.92
f) Contractor's profit @ 10 % on (a+b+c+d+e) 46624.51
cost of 120 cum = a+b+c+d+e+f 512869.65
Rate per cum = (a+b+c+d+e+f)/120 4273.91
say 4274.00
12.8 E RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5600.00 33880.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3779.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 2125.47
e) Overhead charges @ 10 % on (a+b+c+d) 5880.47
f) Contractor's profit @ 10 % on (a+b+c+d+e) 6468.52
cost of 15 cum = a+b+c+d+e+f 71153.71
Rate per cum (a+b+c+d+e+f )/15 4743.58
say 4744.00
12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump
206
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 5600.00 270928.00 M-081
Coarse sand cum 54.00 683.00 36882.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3630.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 16331.89
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 45184.89
f) Contractor's profit @ 10 % on (a+b+c+d+e) 49703.38
cost of 120 cum = a+b+c+d+e+f 546737.15
Rate per cum (a+b+c+d+e+f )/120 4556.14
say 4556.00
12.8 F PCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 5600.00 34048.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
40 mm Aggregate cum 5.40 660.00 3564.00 M-055
20 mm Aggregate cum 5.40 680.00 3672.00 M-053
10 mm Aggregate cum 2.70 670.00 1809.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3785.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 1986.82
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 5875.31
f) Contractor's profit @ 10 % on (a+b+c+d+e) 6462.84
cost of 15 cum = a+b+c+d+e+f 71091.21
Rate per cum (a+b+c+d+e+f )/15 4739.41
say 4739.00
12.8 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit : cum
207
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking Output = 120 cum
a) Material
Cement tonne 48.60 5600.00 272160.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
40 mm Aggregate cum 43.20 660.00 28512.00 M-055
20 mm Aggregate cum 43.20 680.00 29376.00 M-053
10 mm Aggregate cum 21.60 670.00 14472.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3435.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 14426.27
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 42660.53
f) Contractor's profit @ 10 % on (a+b+c+d+e) 46926.58
cost of 120 cum = a+b+c+d+e+f 516192.37
Rate per cum (a+b+c+d+e+f )/120 4301.60
say 4302.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5600.00 34160.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3798.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 1993.57
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 5895.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 6484.81
cost of 15 cum = a+b+c+d+e+f 71332.92
Rate per cum = (a+b+c+d+e+f)/15 4755.53
say 4756.00
12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
208
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Material
Cement tonne 48.80 5600.00 273280.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3450.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 14488.15
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 42843.51
f) Contractor's profit @ 10 % on (a+b+c+d+e) 47127.87
cost of 120 cum = a+b+c+d+e+f 518406.53
Rate per cum (a+b+c+d+e+f )/120 4320.05
say 4320.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5600.00 35448.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3884.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 1747.42
e) Overhead charges @ 10 % on (a+b+c+d) 5999.47
f) Contractor's profit @ 10 % on (a+b+c+d+e) 6599.41
cost of 15 cum = a+b+c+d+e+f 72593.55
Rate per cum = (a+b+c+d+e+f)/15 4839.57
say 4840.00
12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 5600.00 283584.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
209
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3536.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 12727.53
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 43697.85
f) Contractor's profit @ 10 % on (a+b+c+d+e) 48067.64
cost of 120 cum = a+b+c+d+e+f 528744.02
Rate per cum = (a+b+c+d+e+f)/120 4406.20
say 4406.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
12.9 1200 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m dia.
Well.
A Assuming depth of water 1.0 m and height of island to
be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 45.0 11304.00 M-092
Sand bags each 750.00 8.00 6000.00 M-159
b) Labour
Mate day 0.40 300.00 120.00 L-12
Mazdoor for filling sand bags, stitching and placing day 15.00 225.00 3375.00 L-13
c) Machinery
Crane with grab 1 cum capacity hour 20.00 659.00 13180.00 P&M-012
Consumables @ 2.5 per cent of (c) above 329.50
d) Overhead charges @ 10 % on (a+b+c) 3430.85
e) Contractor's profit @ 10 % on (a+b+c+d) 3773.94
Rate per No. (a+b+c+d+e) 41513.28
say 41513.00
Note It is assumed that earth will be available within the working
space of crane with grab bucket.
12.9 B Assuming depth of water 4.0 m and height of island 4.5
m.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 45.00 40694.40 M-092
Sand bags each 6000.00 8.00 48000.00 M-159
Wooden ballies 8" Dia and 9 m long each 95.00 13.00 1235.00 M-194
Wooden ballies 2" Dia for bracing metre 190.00 2.00 380.00 M-193
210
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Labour
Mate day 5.60 300.00 1680.00 L-12
Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 225.00 4050.00 L-13
Mazdoor for bracing with 2" dia ballies day 12.00 225.00 2700.00 L-13
Mazdoor for filling sand bags, stitching and placing day 110.00 225.00 24750.00 L-13
c) Machinery
Crane with grab 1 cum capacity hour 50.00 659.00 32950.00 P&M-012
Consumables and other arrangements for piling ballies @ 3910.99
2.5 per cent of (a+b+c).
d) Overhead charges @ 10 % on (a+b+c) 16035.04
e) Contractor's profit @ 10 % on (a+b+c+d) 17638.54
Rate per No. (a+b+c+d+e) 194023.97
say 194024.00
Note For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 51520.00 54096.00 M-179
cent wastage
Nuts & bolts Kg 20.00 65.00 1300.00 M-130
b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Mate day 1.32 300.00 396.00 L-12
Fitter day 5.50 350.00 1925.00 L-08
Blacksmith day 5.50 350.00 1925.00 L-02
Welder day 5.50 350.00 1925.00 L-02
Mazdoor day 16.50 225.00 3712.50 L-13
Electrodes, cutting gas and other consumables @ 10 per 5539.60
cent of cost of (a) above
c) Overhead charges @ 10 % on (a+b) 7081.91
211
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
d) Contractor's profit @ 10 % on (a+b+c) 7790.10
Rate per MT (a+b+c+d) 85691.11
say 85691.00
12.11 1200, Plain/Reinforced Cement Concrete, in Well Foundation
1500 & complete as per Drawing and Technical Specification.
1700
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.
212
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate perm (a+b+c+d+e+f) 5639.57
say 5640.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery 3646.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 729.20
e) Overhead charges @ 10 % on (a+b+c+d) 437.52
f) Contractor's profit @ 10 % on (a+b+c+d+e) 481.27
Rate perm (a+b+c+d+e+f) 5293.99
say 5294.00
Note. If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.
213
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
214
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
say 4572.00
'12.11 B (vii) RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 5600.00 288960.00 M-081
Coarse Sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
Admixture kg 206.00 65.00 13390.00 M-180
b) Labour
Mate day 0.84 300.00 252.00 L-12
Meson day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant hour 6.00 2109.00 12654.00 P&M-002
215
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. [Link] 300xL 2.00 12000.00 Lead= 20 ,
P&M-050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 29535.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost 44301.70
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 48731.87
f) Contractor's profit @ 10 % on (a+b+c+d+e) 53605.06
cost of 120 cum = a+b+c+d+e+f 589655.63
Rate per cum = (a+b+c+d+e+f)/120 4913.80
say 4914.00
12.11 C C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 5600.00 31080.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
40 mm Aggregate cum 5.40 660.00 3564.00 M-055
20 mm Aggregate cum 5.40 680.00 3672.00 M-053
10 mm Aggregate cum 2.70 670.00 1809.00 M-051
Admixture Kg 18.60 65.00 1209.00 M-180
b) Labour
Mate day 0.90 300.00 270.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 304.00 1824.00 P&M-013
216
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Admixture Kg 148.80 65.00 9672.00 M-180
b) Labour
Mate day 0.88 300.00 264.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3325.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 17482.20
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
217
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = 120 cum
a) Material
Cement tonne 47.88 5600.00 268128.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
Admixture Kg 172.80 65.00 11232.00 M-180
b) Labour
Mate day 0.88 300.00 264.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3501.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 18534.60
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
218
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
cost of 15 cum = a+b+c+d+e 75898.90
Rate per cum = (a+b+c+d+e)/15 5059.93
say 5060.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 5600.00 272384.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
Admixture Kg 172.80 65.00 11232.00 M-180
b) Labour
Mate day 0.88 300.00 264.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - [Link] 300L 2.00 12000.00 P&M-050
lead in Kilometer Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3536.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 18747.40
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
219
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Add 5 per cent of cost of material and labour towards cost 2778.91
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
220
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cum = (a+b+c+d+e) 4023.25
say 4023.00
'12.11 D (ii) Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3967.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 396.70
e) Contractor's profit @ 10 % on (a+b+c+d) 436.37
Rate per cum = (a+b+c+d+e) 4800.07
say 4800.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Machinery 3501.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 350.10
e) Contractor's profit @ 10 % on (a+b+c+d) 385.11
Rate per cum = (a+b+c+d+e) 4236.21
say 4236.00
'12.11 D (iii) Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 4001.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 400.10
e) Contractor's profit @ 10 % on (a+b+c+d) 440.11
Rate per cum = (a+b+c+d+e) 4841.21
say 4841.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery 3536.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 353.60
e) Contractor's profit @ 10 % on (a+b+c+d) 388.96
Rate per cum = (a+b+c+d+e) 4278.56
say 4279.00
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3083.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 308.30
e) Contractor's profit @ 10 % on (a+b+c+d) 339.13
Rate per cum = (a+b+c+d+e) 3730.43
say 3730.00
'12.11 E (ii) Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3441.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 344.10
e) Contractor's profit @ 10 % on (a+b+c+d) 378.51
Rate per cum = (a+b+c+d+e) 4163.61
say 4164.00
'12.11 E (iii) Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Case I Using Concrete Mixer
221
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3751.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 375.10
e) Contractor's profit @ 10 % on (a+b+c+d) 412.61
Rate per cum = (a+b+c+d+e) 4538.71
say 4539.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery 3405.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 340.50
e) Contractor's profit @ 10 % on (a+b+c+d) 374.55
Rate per cum = (a+b+c+d+e) 4120.05
say 4120.00
'12.11 E (iv) Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3785.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 378.50
e) Contractor's profit @ 10 % on (a+b+c+d) 416.35
Rate per cum = (a+b+c+d+e) 4579.85
say 4580.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iv) pump
Per Cum Basic Cost of Labour, Material & Machinery 3435.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 343.50
e) Contractor's profit @ 10 % on (a+b+c+d) 377.85
Rate per cum = (a+b+c+d+e) 4156.35
say 4156.00
12.11 F Well cap
(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 5600.00 28672.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Form Work @ 4 per cent of a+b+c 2058.85
d) Overhead charges @ 10 % on (a+b+c) 5353.01
e) Contractor's profit @ 10 % on (a+b+c+d) 5888.31
cost of 15 cum = a+b+c+d+e 64771.42
Rate per cum = (a+b+c+d+e)/15 4318.09
say 4318.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i)
Unit = cum
Taking output = 120 cum
222
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Material
Cement tonne 40.92 5600.00 229152.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader (capacity 1 cum) hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 P&M-050
Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Formwork @ 4 per cent of (a+b+c) 14792.76
d) Overhead charges @ 10 % on (a+b+c) 38461.18
e) Contractor's profit @ 10 % on (a+b+c+d) 42307.29
cost of 120 cum = a+b+c+d+e 465380.23
Rate per cum = (a+b+c+d+e)/120 3878.17
say 3878.00
12.11 F (ii) RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5600.00 33880.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Form Work @ 3.75 per cent of a+b+c 2125.47
d) Overhead charges @ 10 % on (a+b+c) 5880.47
e) Contractor's profit @ 10 % on (a+b+c+d) 6468.52
cost of 15 cum = a+b+c+d+e 71153.71
Rate per cum = (a+b+c+d+e)/15 4743.58
say 4744.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 5600.00 271040.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
223
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader (capacity 1 cum) hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 P&M-050
Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Formwork @ 3.75 per cent of ( a+b+c) 15439.01
d) Overhead charges @ 10 % on (a+b+c) 42714.60
e) Contractor's profit @ 10 % on (a+b+c+d) 46986.06
cost of 120 cum = a+b+c+d+e 516846.68
Rate per cum = (a+b+c+d+e)/120 4307.06
say 4307.00
12.11 F (iii) RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5600.00 34160.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Formwork @ 3.5 per cent of (a+b+c) 1993.57
d) Overhead charges @ 10 % on (a+b+c) 5895.28
e) Contractor's profit @ 10 % on (a+b+c+d) 6484.81
cost of 15 cum = a+b+c+d+e 71332.92
Rate per cum = (a+b+c+d+e)/15 4755.53
say 4756.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 5600.00 273224.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
224
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Loader (capacity 1 cum) hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 P&M-050
Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Formwork @ 3.5 per cent of (a+b+c) 14486.19
d) Overhead charges @ 10 % on (a+b+c) 42837.72
e) Contractor's profit @ 10 % on (a+b+c+d) 47121.49
cost of 120 cum = a+b+c+d+e 518336.39
Rate per cum = (a+b+c+d+e)/120 4319.47
say 4319.00
12.11 F (iv) RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5600.00 35448.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Formwork @ 3 per cent of (a+b+c) 1747.42
d) Overhead charges @ 10 % on (a+b+c) 5999.47
e) Contractor's profit @ 10 % on (a+b+c+d) 6599.41
cost of 15 cum = a+b+c+d+e 72593.55
Rate per cum = (a+b+c+d+e)/15 4839.57
say 4840.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iv)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 5600.00 283584.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader (capacity 1 cum) hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 P&M-050
Lead= 20
km
225
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Formwork @ 3 per cent of (a+b+c) 12727.53
d) Overhead charges @ 10 % on (a+b+c) 43697.85
e) Contractor's profit @ 10 % on (a+b+c+d) 48067.64
cost of 120 cum = a+b+c+d+e 528744.02
Rate per cum = (a+b+c+d+e)/120 4406.20
say 4406.00
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 5600.00 292320.00 M-081
Coarse Sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
Admixture kg 206.00 65.00 13390.00 M-180
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader 1 cum capacity hour 6.00 770.00 4620.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 813.00 12195.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. [Link] 300.L 2.00 12000.00 P&M-050
Lead= 20
km
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Formwork @ 3 per cent on cost of concrete i.e. cost of 13391.31
material, labour and machinery
d) Overhead charges @ 10 % on (a+b+c) 45976.83
e) Contractor's profit @ 10 % on (a+b+c+d) 50574.51
cost of 120 cum = a+b+c+d+e 556319.66
Rate per cum = (a+b+c+d+e)/120 4636.00
say 4636.00
12.12 Section Sinking of 6 m external diameter well (other than
1200 pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
226
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Hire & running charges of crane with grab bucket of hour 2.00 1045.00 2090.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 209.00
c) Overhead charges @ 10 % on (a+b) 303.50
d) Contractor's profit @ 10 % on (a+b+c) 333.85
Rate per metre = (a+b+c+d) 3672.35
say 3672.00
12.12 A (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 300.00 45.00 L-12
Sinker day 1.25 250.00 312.50 L-15
Sinking helper ( semi-skilled ) day 2.50 225.00 562.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1045.00 3135.00 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 313.50
c) Overhead charges @ 10 % on (a+b) 436.85
d) Contractor's profit @ 10 % on (a+b+c) 480.54
Rate per metre = (a+b+c+d) 5285.89
say 5286.00
12.12 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 5550.00
12th m 5% 5828.00
13th m 5% 6119.00
14th m 5% 6425.00
15th m 5% 6746.00
16th m 5% 7083.00
17th m 5% 7437.00
18th m 5% 7809.00
19th m 5% 8199.00
20th m 5% 8609.00
Total Cost from 10m upto 20m 69805.00
Avg Rate per metre 6981.00
12.12 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 9255.00 11106.00
22nd m 7.5% 9949.00 11939.00
23rd m 7.5% 10695.00 12834.00
24th m 7.5% 11497.00 13796.00
25th m 7.5% 12359.00 14831.00
26th m 7.5% 13286.00 15943.00
27th m 7.5% 14282.00 17138.00
28th m 7.5% 15353.00 18424.00
29th m 7.5% 16504.00 19805.00
30th m 7.5% 17742.00 21290.00
Total Cost from 20m upto 30m 130922.00 157106.00
Avg Rate per metre 13092.00 15711.00
12.12 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
227
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
31st m 10% 19516.00 23419.00
32nd 10% 21468.00 25762.00
33rd m 10% 23615.00 28338.00
34th m 10% 25977.00 31172.00
35th m 10% 28575.00 34290.00
36th m 10% 31433.00 37720.00
37th m 10% 34576.00 41491.00
38th m 10% 38034.00 45641.00
39th m 10% 41837.00 50204.00
40th m 10% 46021.00 55225.00
Total Cost from 30m upto 40m 311052.00 373262.00
Avg Rate per metre 31105.00 37326.00
12.12 B Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 300.00 45.00 L-12
Sinker ( skilled ) day 1.50 250.00 375.00 L-15
Sinking helper ( semi-skilled ) day 2.25 225.00 506.25 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1045.00 3135.00 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 313.50
c) Overhead charges @ 10 % on (a+b) 437.48
d) Contractor's profit @ 10 % on (a+b+c) 481.22
Rate per metre = (a+b+c+d) 5293.45
say 5293.00
12.12 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 300.00 90.00 L-12
Sinker day 3.00 250.00 750.00 L-15
Sinking helper ( semi-skilled ) day 4.50 225.00 1012.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 300.00 600.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 687.00
c) Overhead charges @ 10 % on (a+b) 940.95
d) Contractor's profit @ 10 % on (a+b+c) 1035.05
Rate per metre = (a+b+c+d) 11385.50
say 11385.00
12.12 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
228
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
17th m 5% 16021.00 16822.00
18th m 5% 16822.00 17663.00
19th m 5% 17663.00 18546.00
20th m 5% 18546.00 19473.00
Total Cost from 10m upto 20m 150366.00 157885.00
Avg Rate per metre 15037.00 15789.00
12.12 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering of the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
21st m 7.5% 19937.00 24921.00 26167.00
22nd m 7.5% 21432.00 26790.00 28130.00
23rd m 7.5% 23039.00 28799.00 30239.00
24th m 7.5% 24767.00 30959.00 32507.00
25th m 7.5% 26625.00 33281.00 34945.00
26th m 7.5% 28622.00 35778.00 37567.00
27th m 7.5% 30769.00 38461.00 40384.00
28th m 7.5% 33077.00 41346.00 43413.00
29th m 7.5% 35558.00 44448.00 46670.00
30th m 7.5% 38225.00 47781.00 50170.00
Total Cost from 20m upto 30m 282051.00 352564.00 370192.00
Avg Rate per metre 28205.00 35256.00 37019.00
12.12 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 42048.00 50458.00 52981.00
32nd 10% 46253.00 55504.00 58279.00
33rd m 10% 50878.00 61054.00 64107.00
34th m 10% 55966.00 67159.00 70517.00
35th m 10% 61563.00 73876.00 77570.00
36th m 10% 67719.00 81263.00 85326.00
37th m 10% 74491.00 89389.00 93858.00
38th m 10% 81940.00 98328.00 103244.00
39th m 10% 90134.00 108161.00 113569.00
40th m 10% 99147.00 118976.00 124925.00
Total Cost from 30m upto 40m 670139.00 804168.00 844376.00
Avg Rate per metre 67014.00 80417.00 84438.00
12.12 C Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 300.00 276.00 L-12
Sinker ( skilled ) day 3.00 250.00 750.00 L-15
Sinking helper ( semi-skilled ) day 20.00 225.00 4500.00 L-14
Diver day 0.50 250.00 125.00 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1045.00 4180.00 P&M-075
0.75 cum capacity and accessories.
229
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor with pneumatic breakers hour 3.50 300.00 1050.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 523.00
Add for dewatering @ of 5 per cent of (a+b), if 570.20
required
c) Overhead charges @ 10 % on (a+b) 1197.42
d) Contractor's profit @ 10 % on (a+b+c) 1317.16
Rate per metre = (a+b+c+d) 14488.78
say 14489.00
12.12 D Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 111.00 444.00 M-104
Electric Detonators each 18.00 6.60 118.80 M-094/100
b) Labour
Mate day 1.56 300.00 468.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 12.00 225.00 2700.00 L-13
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 300.00 600.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 580.03
Consumables in sinking @ 10 per cent of cost of (b). 687.00
d) Overhead charges @ 10 % on (a+b+c) 1343.03
e) Contractor's profit @ 10 % on (a+b+c+d) 1477.34
Rate per metre = (a+b+c+d+e) 16250.69
say 16251.00
12.13 Section Sinking of 7 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
230
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Labour
Mate day 0.18 300.00 54.00 L-12
Sinker day 1.50 250.00 375.00 L-15
Sinking helper ( semi-skilled ) day 3.00 225.00 675.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1045.00 4702.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 470.25
c) Overhead charges @ 10 % on (a+b) 627.68
d) Contractor's profit @ 10 % on (a+b+c) 690.44
Rate per metre = (a+b+c+d) 7594.87
say 7595.00
12.13 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 7975.00
12th m 5% 8374.00
13th m 5% 8793.00
14th m 5% 9233.00
0.165 15th m 5% 9695.00
16th m 5% 10180.00
17th m 5% 10689.00
18th m 5% 11223.00
19th m 5% 11784.00
20th m 5% 12373.00
Total Cost from 10m upto 20m 100319.00
Avg Rate per metre 10032.00
12.13 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour). for Kentledge
21st m 7.5% 13301.00 15961.00
22nd m 7.5% 14299.00 17159.00
23rd m 7.5% 15371.00 18445.00
24th m 7.5% 16524.00 19829.00
25th m 7.5% 17763.00 21316.00
26th m 7.5% 19095.00 22914.00
27th m 7.5% 20527.00 24632.00
28th m 7.5% 22067.00 26480.00
29th m 7.5% 23722.00 28466.00
30th m 7.5% 25501.00 30601.00
Total Cost from 20m upto 30m 188170.00 225803.00
Avg Rate per metre 18817.00 22580.00
12.13 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 28051.00 33661.00
32nd 10% 30856.00 37027.00
33rd m 10% 33942.00 40730.00
34th m 10% 37336.00 44803.00
35th m 10% 41070.00 49284.00
36th m 10% 45177.00 54212.00
37th m 10% 49695.00 59634.00
38th m 10% 54665.00 65598.00
39th m 10% 60132.00 72158.00
231
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
40th m 10% 66145.00 79374.00
Total Cost from 30m upto 40m 447069.00 536481.00
Avg Rate per metre 44707.00 53648.00
12.13 B Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 300.00 54.00 L-12
Sinker ( skilled ) day 1.50 250.00 375.00 L-15
Sinking helper ( semi-skilled ) day 3.00 225.00 675.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1045.00 4702.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 470.25
d) Overhead charges @ 10 % on (a+b) 627.68
e) Contractor's profit @ 10 % on (a+b+c) 690.44
Rate per metre = (a+b+c+d) 7594.87
say 7595.00
12.13 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 300.00 78.00 L-12
Sinker day 2.00 250.00 500.00 L-15
Sinking helper ( semi-skilled ) day 4.00 225.00 900.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 300.00 627.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 689.70
c) Overhead charges @ 10 % on (a+b) 906.47
d) Contractor's profit @ 10 % on (a+b+c) 997.12
Rate per metre = (a+b+c+d) 10968.29
say 10968.00
12.13 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
232
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
31st m 7.5% 19208.00 24010.00 25211.00
32nd 7.5% 20649.00 25811.00 27102.00
33rd m 7.5% 22198.00 27748.00 29135.00
34th m 7.5% 23863.00 29829.00 31320.00
35th m 7.5% 25653.00 32066.00 33669.00
36th m 7.5% 27577.00 34471.00 36195.00
37th m 7.5% 29645.00 37056.00 38909.00
38th m 7.5% 31868.00 39835.00 41827.00
39th m 7.5% 34258.00 42823.00 44964.00
40th m 7.5% 36827.00 46034.00 48336.00
Total Cost from 30m upto 40m 271746.00 339683.00 356668.00
Avg Rate per metre 27175.00 33968.00 35667.00
12.13 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 40510.00 48612.00 51043.00
32nd 10% 44561.00 53473.00 56147.00
33rd m 10% 49017.00 58820.00 61761.00
34th m 10% 53919.00 64703.00 67938.00
35th m 10% 59311.00 71173.00 74732.00
36th m 10% 65242.00 78290.00 82205.00
37th m 10% 71766.00 86119.00 90425.00
38th m 10% 78943.00 94732.00 99469.00
39th m 10% 86837.00 104204.00 109414.00
40th m 10% 95521.00 114625.00 120356.00
Total Cost from 30m upto 40m 645627.00 774751.00 813490.00
Avg Rate per metre 64563.00 77475.00 81349.00
12.13 C Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 300.00 174.00 L-12
Sinker ( skilled ) day 4.00 250.00 1000.00 L-15
Sinking helper ( semi-skilled ) day 10.00 225.00 2250.00 L-14
Diver day 0.75 250.00 187.50 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1045.00 4702.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 300.00 1125.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 582.75
Add for dewatering @ of 5 per cent of (a+b), if 471.95
required
c) Overhead charges @ 10 % on (a+b) 1049.37
d) Contractor's profit @ 10 % on (a+b+c) 1154.31
Rate per metre = (a+b+c+d) 12697.38
say 12697.00
12.13 D Hard Rock ( 7m dia well )
233
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 111.00 777.00 M-104
Electric Detonators each 30.00 6.60 198.00 M-094/100
b) Labour
Mate day 1.60 300.00 480.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 18.00 225.00 4050.00 L-13
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Diver day 0.50 250.00 125.00 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 300.00 600.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 654.38
Consumables in sinking @ 10 per cent of cost of (b). 752.44
d) Overhead charges @ 10 % on (a+b+c) 1546.93
e) Contractor's profit @ 10 % on (a+b+c+d) 1701.62
Rate per metre = (a+b+c+d+e) 18717.87
say 18718.00
12.14 Section Sinking of 8 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
234
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Consumables in sinking @10 per cent of (b) 522.50
c) Overhead charges @ 10 % on (a+b) 704.75
d) Contractor's profit @ 10 % on (a+b+c) 775.23
Rate per metre = (a+b+c+d) 8527.48
say 8527.00
12.14 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 8954.00
12th m 5% 9402.00
13th m 5% 9872.00
14th m 5% 10366.00
15th m 5% 10884.00
16th m 5% 11428.00
17th m 5% 11999.00
18th m 5% 12599.00
19th m 5% 13229.00
20th m 5% 13890.00
Total Cost from 10m upto 20m 112623.00
Avg Rate per metre 11262.00
12.14 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 14932.00 17918.00
22nd m 7.5% 16052.00 19262.00
23rd m 7.5% 17256.00 20707.00
24th m 7.5% 18550.00 22260.00
25th m 7.5% 19941.00 23929.00
26th m 7.5% 21437.00 25724.00
27th m 7.5% 23045.00 27654.00
28th m 7.5% 24773.00 29728.00
29th m 7.5% 26631.00 31957.00
30th m 7.5% 28628.00 34354.00
Total Cost from 20m upto 30m 211245.00 253493.00
Avg Rate per metre 21125.00 25349.00
12.14 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 31491.00 37789.00
32nd 10% 34640.00 41568.00
33rd m 10% 38104.00 45725.00
34th m 10% 41914.00 50297.00
35th m 10% 46105.00 55326.00
36th m 10% 50716.00 60859.00
37th m 10% 55788.00 66946.00
38th m 10% 61367.00 73640.00
39th m 10% 67504.00 81005.00
40th m 10% 74254.00 89105.00
Total Cost from 30m upto 40m 74254.00 89105.00
Avg Rate per metre 7425.00 8911.00
12.14 B Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
235
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 300.00 66.00 L-12
Sinker ( skilled ) day 2.00 250.00 500.00 L-15
Sinking helper ( semi-skilled ) hour 3.50 225.00 787.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of 5.50 1045.00 5747.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 574.75
c) Overhead charges @ 10 % on (a+b) 767.58
d) Contractor's profit @ 10 % on (a+b+c) 844.33
Rate per metre = (a+b+c+d) 9287.66
say 9288.00
12.14 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 300.00 96.00 L-12
Sinker day 2.50 250.00 625.00 L-15
Sinking helper ( semi-skilled ) day 4.50 225.00 1012.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 300.00 1050.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 732.00
c) Overhead charges @ 10 % on (a+b) 978.55
d) Contractor's profit @ 10 % on (a+b+c) 1076.41
Rate per metre = (a+b+c+d) 11840.46
say 11840.00
12.14 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
31st m 7.5% 20734.00 25918.00 27214.00
32nd 7.5% 22289.00 27861.00 29254.00
33rd m 7.5% 23961.00 29951.00 31449.00
236
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
34th m 7.5% 25758.00 32198.00 33808.00
35th m 7.5% 27690.00 34613.00 36344.00
36th m 7.5% 29767.00 37209.00 39069.00
37th m 7.5% 32000.00 40000.00 42000.00
38th m 7.5% 34400.00 43000.00 45150.00
39th m 7.5% 36980.00 46225.00 48536.00
40th m 7.5% 39754.00 49693.00 52178.00
Total Cost from 30m upto 40m 293333.00 366668.00 385002.00
Avg Rate per metre 29333.00 36667.00 38500.00
12.14 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 43729.00 52475.00 55099.00
32nd 10% 48102.00 57722.00 60608.00
33rd m 10% 52912.00 63494.00 66669.00
34th m 10% 58203.00 69844.00 73336.00
35th m 10% 64023.00 76828.00 80669.00
36th m 10% 70425.00 84510.00 88736.00
37th m 10% 77468.00 92962.00 97610.00
38th m 10% 85215.00 102258.00 107371.00
39th m 10% 93737.00 112484.00 118108.00
40th m 10% 103111.00 123733.00 129920.00
Total Cost from 30m upto 40m 696925.00 836310.00 878126.00
Avg Rate per metre 69693.00 83631.00 87813.00
12.14 C Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 300.00 204.00 L-12
Sinker ( skilled ) day 4.00 250.00 1000.00 L-15
Sinking helper ( semi-skilled ) day 12.00 225.00 2700.00 L-14
Diver day 1.00 250.00 250.00 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1045.00 5225.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 300.00 1125.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 635.00
Add for dewatering @ of 5 per cent of (a+b), if 556.95
required
c) Overhead charges @ 10 % on (a+b) 1169.60
d) Contractor's profit @ 10 % on (a+b+c) 1286.55
Rate per metre = (a+b+c+d) 14152.10
say 14152.00
12.14 D Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 111.00 888.00 M-104
Electric Detonators each 32.00 6.60 211.20 M-094/100
237
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Labour
Mate day 1.09 300.00 327.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 20.00 225.00 4500.00 L-13
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 300.00 600.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 662.98
Consumables in sinking @ 10 per cent of cost of (b). 638.95
d) Overhead charges @ 10 % on (a+b+c) 1566.06
e) Contractor's profit @ 10 % on (a+b+c+d) 1722.67
Rate per metre = (a+b+c+d+e) 18949.36
say 18949.00
12.15 Section Sinking of 9 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
238
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12th m 5% 10327.00
13th m 5% 10843.00
14th m 5% 11385.00
15th m 5% 11954.00
16th m 5% 12552.00
17th m 5% 13180.00
18th m 5% 13839.00
19th m 5% 14531.00
20th m 5% 15258.00
Total Cost from 10m upto 20m 123704.00
Avg Rate per metre 12370.00
12.15 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 16402.35 19683.00
22nd m 7.5% 17633.00 21160.00
23rd m 7.5% 18955.00 22746.00
24th m 7.5% 20377.00 24452.00
25th m 7.5% 21905.00 26286.00
26th m 7.5% 23548.00 28258.00
27th m 7.5% 25314.00 30377.00
28th m 7.5% 27213.00 32656.00
29th m 7.5% 29254.00 35105.00
30th m 7.5% 31448.00 37738.00
Total Cost from 20m upto 30m 232049.35 278461.00
Avg Rate per metre 23205.00 27846.00
12.15 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 34592.80 41511.00
32nd 10% 38052.00 45662.00
33rd m 10% 41857.00 50228.00
34th m 10% 46043.00 55252.00
35th m 10% 50647.00 60776.00
36th m 10% 55712.00 66854.00
37th m 10% 61283.00 73540.00
38th m 10% 67411.00 80893.00
39th m 10% 74152.00 88982.00
40th m 10% 81567.00 97880.00
Total Cost from 30m upto 40m 551316.80 661578.00
Avg Rate per metre 55132.00 66158.00
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 300.00 72.00 L-12
Sinker ( skilled ) day 2.25 250.00 562.50 L-15
Sinking helper ( semi-skilled ) day 3.75 225.00 843.75 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1045.00 6008.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 600.88
239
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Overhead charges @ 10 % on (a+b) 808.79
d) Contractor's profit @ 10 % on (a+b+c) 889.67
Rate per metre = (a+b+c+d) 9786.33
say 9786.00
12.15 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 300.00 102.00 L-12
Sinker day 2.50 250.00 625.00 L-15
Sinking helper ( semi-skilled ) day 5.00 225.00 1125.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1045.00 6792.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.75 300.00 1125.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 791.75
c) Overhead charges @ 10 % on (a+b) 1056.13
d) Contractor's profit @ 10 % on (a+b+c) 1161.74
Rate per metre = (a+b+c+d) 12779.11
say 12779.00
12.15 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
31st m 7.5% 22377.00 27971.00 29370.00
32nd 7.5% 24055.00 30069.00 31572.00
33rd m 7.5% 25859.00 32324.00 33940.00
34th m 7.5% 27798.00 34748.00 36485.00
35th m 7.5% 29883.00 37354.00 39222.00
36th m 7.5% 32124.00 40155.00 42163.00
37th m 7.5% 34533.00 43166.00 45324.00
38th m 7.5% 37123.00 46404.00 48724.00
39th m 7.5% 39907.00 49884.00 52378.00
40th m 7.5% 42900.00 53625.00 56306.00
Total Cost from 30m upto 40m 316559.00 395700.00 415484.00
Avg Rate per metre 31656.00 39570.00 41548.00
240
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.15 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 47190.00 56628.00 59459.00
32nd 10% 51909.00 62291.00 65406.00
33rd m 10% 57100.00 68520.00 71946.00
34th m 10% 62810.00 75372.00 79141.00
35th m 10% 69091.00 82909.00 87054.00
36th m 10% 76000.00 91200.00 95760.00
37th m 10% 83600.00 100320.00 105336.00
38th m 10% 91960.00 110352.00 115870.00
39th m 10% 101156.00 121387.00 127456.00
40th m 10% 111272.00 133526.00 140202.00
Total Cost from 30m upto 40m 752088.00 902505.00 947630.00
Avg Rate per metre 75209.00 90251.00 94763.00
12.15 C Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 300.00 228.00 L-12
Sinker ( skilled ) day 4.00 250.00 1000.00 L-15
Sinking helper ( semi-skilled ) day 14.00 225.00 3150.00 L-14
Diver day 1.20 250.00 300.00 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1045.00 6792.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 300.00 1200.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 799.25
Add for dewatering @ of 5 per cent of (a+b), if 1346.98
required
c) Overhead charges @ 10 % on (a+b) 1481.67
d) Contractor's profit @ 10 % on (a+b+c) 1629.84
Rate per metre = (a+b+c+d) 17928.24
say 17928.00
12.15 D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 111.00 1110.00 M-104
Electric Detonators each 40.00 6.60 264.00 M-094/100
b) Labour
Mate day 1.17 300.00 351.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 22.00 225.00 4950.00 L-13
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Diver day 1.00 250.00 250.00 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1045.00 7315.00 P&M-075
0.75 cum capacity and accessories.
241
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Hire & running charges of compressor with pneumatic hour 2.50 300.00 750.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 758.93
Consumables in sinking @ 10 per cent of cost of (b). 711.35
d) Overhead charges @ 10 % on (a+b+c) 1802.28
e) Contractor's profit @ 10 % on (a+b+c+d) 1982.51
Rate per metre = (a+b+c+d+e) 21807.56
say 21808.00
12.16 1200 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
242
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
20th m 5% 16080.00
Total Cost from 10m upto 20m 130374.00
Avg Rate per metre 13037.00
12.16 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 17286.00 20743.00
22nd m 7.5% 18582.00 22298.00
23rd m 7.5% 19976.00 23971.00
24th m 7.5% 21474.00 25769.00
25th m 7.5% 23085.00 27702.00
26th m 7.5% 24816.00 29779.00
27th m 7.5% 26677.00 32012.00
28th m 7.5% 28678.00 34414.00
29th m 7.5% 30829.00 36995.00
30th m 7.5% 33141.00 39769.00
Total Cost from 20m upto 30m 244544.00 293452.00
Avg Rate per metre 24454.00 29345.00
12.16 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 36455.00 43746.00
32nd 10% 40101.00 48121.00
33rd m 10% 44111.00 52933.00
34th m 10% 48522.00 58226.00
35th m 10% 53374.00 64049.00
36th m 10% 58711.00 70453.00
37th m 10% 64582.00 77498.00
38th m 10% 71040.00 85248.00
39th m 10% 78144.00 93773.00
40th m 10% 85958.00 103150.00
Total Cost from 30m upto 40m 580998.00 697197.00
Avg Rate per metre 58100.00 69720.00
12.16 B Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 300.00 75.00 L-12
Sinker ( skilled ) day 2.50 250.00 625.00 L-15
Sinking helper ( semi-skilled ) day 5.50 225.00 1237.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 627.00
c) Overhead charges @ 10 % on (a+b) 883.45
d) Contractor's profit @ 10 % on (a+b+c) 971.80
Rate per metre = (a+b+c+d) 10689.75
say 10690.00
12.16 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 300.00 120.00 L-12
243
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Sinker day 3.00 250.00 750.00 L-15
Sinking helper ( semi-skilled ) day 5.50 225.00 1237.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 300.00 1200.00 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 747.00
c) Overhead charges @ 10 % on (a+b) 1032.45
d) Contractor's profit @ 10 % on (a+b+c) 1135.70
Rate per metre = (a+b+c+d) 12492.65
say 12493.00
12.16 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
31st m 7.5% 21875.00 27344.00 28711.00
32nd 7.5% 23516.00 29395.00 30865.00
33rd m 7.5% 25280.00 31600.00 33180.00
34th m 7.5% 27176.00 33970.00 35669.00
35th m 7.5% 29214.00 36518.00 38344.00
36th m 7.5% 31405.00 39256.00 41219.00
37th m 7.5% 33760.00 42200.00 44310.00
38th m 7.5% 36292.00 45365.00 47633.00
39th m 7.5% 39014.00 48768.00 51206.00
40th m 7.5% 41940.00 52425.00 55046.00
Total Cost from 30m upto 40m 309472.00 386841.00 406183.00
Avg Rate per metre 30947.00 38684.00 40618.00
12.16 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 46134.00 55361.00 58129.00
32nd 10% 50747.00 60896.00 63941.00
244
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
33rd m 10% 55822.00 66986.00 70335.30
34th m 10% 61404.00 73685.00 77369.25
35th m 10% 67544.00 81053.00 85105.65
36th m 10% 74298.00 89158.00 93615.90
37th m 10% 81728.00 98074.00 102977.70
38th m 10% 89901.00 107881.00 113275.05
39th m 10% 98891.00 118669.00 124602.45
40th m 10% 108780.00 130536.00 137062.80
Total Cost from 30m upto 40m 735249.00 882299.00 926414.10
Avg Rate per metre 73525.00 88230.00 92641.00
12.16 C Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 300.00 258.00 L-12
Sinker ( skilled ) day 4.00 250.00 1000.00 L-15
Sinking helper ( semi-skilled ) day 16.00 225.00 3600.00 L-14
Diver day 1.40 250.00 350.00 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1045.00 7315.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 300.00 1275.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 859.00
Add for dewatering @ 5 per cent of cost, if required 472.45
c) Overhead charges @ 10 % on (a+b) 1512.95
d) Contractor's profit @ 10 % on (a+b+c) 1664.24
Rate per metre = (a+b+c+d) 18306.63
say 18307.00
12.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 111.00 1221.00 M-104
Electric Detonators each. 44.00 6.60 290.40 M-094/100
b) Labour
Mate day 1.27 300.00 381.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 24.00 225.00 5400.00 L-13
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 1045.00 8882.50 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 300.00 900.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 489.13
Consumables in sinking @ 10 per cent of cost of 1761.51
(b+c).
d) Overhead charges @ 10 % on (a+b+c) 2088.80
e) Contractor's profit @ 10 % on (a+b+c+d) 2297.68
Rate per metre = (a+b+c+d+e) 25274.53
say 25275.00
245
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.17 1200 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
246
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 36044.00 43253.00
22nd m 7.5% 38747.00 46496.00
23rd m 7.5% 41653.00 49984.00
24th m 7.5% 44777.00 53732.00
25th m 7.5% 48135.00 57762.00
26th m 7.5% 51745.00 62094.00
27th m 7.5% 55626.00 66751.00
28th m 7.5% 59798.00 71758.00
29th m 7.5% 64283.00 77140.00
30th m 7.5% 69104.00 82925.00
Total Cost from 20m upto 30m 509912.00 611895.00
Avg Rate per metre 50991.00 61190.00
12.17 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 76014.00 91217.00
32nd 10% 83615.00 100338.00
33rd m 10% 91977.00 110372.00
34th m 10% 101175.00 121410.00
35th m 10% 111293.00 133552.00
36th m 10% 122422.00 146906.00
37th m 10% 134664.00 161597.00
38th m 10% 148130.00 177756.00
39th m 10% 162943.00 195532.00
40th m 10% 179237.00 215084.00
Total Cost from 30m upto 40m 1211470.00 1453764.00
Avg Rate per metre 121147.00 145376.00
12.17 B Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 300.00 78.00 L-12
Sinker ( skilled ) day 2.50 250.00 625.00 L-15
Sinking helper (semi-skilled) day 4.00 225.00 900.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1045.00 5225.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 522.50
c) Overhead charges @ 10 % on (a+b) 735.05
d) Contractor's profit @ 10 % on (a+b+c) 808.56
Cost for 0.5m = a+b+c+d 8894.11
Rate per metre = (a+b+c+d)/0.50 17788.21
say 17788.00
12.17 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 300.00 129.00 L-12
Sinker day 3.50 250.00 875.00 L-15
Sinking helper (semi-skilled) day 5.75 225.00 1293.75 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1045.00 6270.00 P&M-075
0.75 cum capacity and accessories.
247
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor with pneumatic chisel attachment for hour 4.25 300.00 1275.00 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 754.50
c) Overhead charges @ 10 % on (a+b) 1059.73
d) Contractor's profit @ 10 % on (a+b+c) 1165.70
Cost for 0.5m = a+b+c+d 12822.67
Rate per metre = (a+b+c+d)/0.50 25645.35
say 25645.00
12.17 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
31st m 7.5% 44907.00 56134.00 58941.00
32nd 7.5% 48275.00 60344.00 63361.00
33rd m 7.5% 51896.00 64870.00 68114.00
34th m 7.5% 55788.00 69735.00 73222.00
35th m 7.5% 59972.00 74965.00 78713.00
36th m 7.5% 64470.00 80588.00 84617.00
37th m 7.5% 69305.00 86631.00 90963.00
38th m 7.5% 74503.00 93129.00 97785.00
39th m 7.5% 80091.00 100114.00 105120.00
40th m 7.5% 86098.00 107623.00 113004.00
Total Cost from 30m upto 40m 635305.00 794133.00 833840.00
Avg Rate per metre 63531.00 79413.00 83384.00
12.17 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 94708.00 113650.00 119333.00
32nd 10% 104179.00 125015.00 131266.00
33rd m 10% 114597.00 137516.00 144392.00
34th m 10% 126057.00 151268.00 158831.00
35th m 10% 138663.00 166396.00 174716.00
36th m 10% 152529.00 183035.00 192187.00
248
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
37th m 10% 167782.00 201338.00 211405.00
38th m 10% 184560.00 221472.00 232546.00
39th m 10% 203016.00 243619.00 255800.00
40th m 10% 223318.00 267982.00 281381.00
Total Cost from 30m upto 40m 1509409 1811291 1901857
Avg Rate per metre 150941.00 181129.00 190186.00
12.17 C Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 300.00 285.00 L-12
Sinker ( skilled ) day 4.25 250.00 1062.50 L-15
Sinking helper (semi-skilled) day 18.00 225.00 4050.00 L-14
Diver day 1.50 250.00 375.00 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 1045.00 8360.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 300.00 1350.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 971.00
Add for dewatering @ 5 per cent of cost, if required 534.05
c) Overhead charges @ 10 % on (a+b) 1698.76
d) Contractor's profit @ 10 % on (a+b+c) 1868.63
Cost for 0.5m = a+b+c+d 20554.94
Rate per metre = (a+b+c+d)/0.50 41109.87
say 41110.00
12.17 D Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 111.00 1332.00 M-104
Electric Detonators each. 48.00 6.60 316.80 M-094/100
b) Labour
Mate day 1.35 300.00 405.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 26.00 225.00 5850.00 L-13
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1045.00 10450.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 300.00 1050.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 575.00
Consumables in sinking @ 10 per cent of cost of 1931.75
(b+c).
d) Overhead charges @ 10 % on (a+b+c) 2347.31
e) Contractor's profit @ 10 % on (a+b+c+d) 2582.04
Cost for 0.5m = a+b+c+d 28402.39
Rate per metre = (a+b+c+d)/0.50 56804.78
say 56805.00
249
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.18 1200 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
250
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 78619.00 94343.00
22nd m 7.5% 84515.00 101418.00
23rd m 7.5% 90854.00 109025.00
24th m 7.5% 97668.00 117202.00
25th m 7.5% 104993.00 125992.00
26th m 7.5% 112867.00 135440.00
27th m 7.5% 121332.00 145598.00
28th m 7.5% 130432.00 156518.00
29th m 7.5% 140214.00 168257.00
30th m 7.5% 150730.00 180876.00
Total Cost from 20m upto 30m 1112224.00 1334669.00
Avg Rate per metre 111222.00 133467.00
12.18 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 165803.00 198964.00
32nd 10% 182383.00 218860.00
33rd m 10% 200621.00 240745.00
34th m 10% 220683.00 264820.00
35th m 10% 242751.00 291301.00
36th m 10% 267026.00 320431.00
37th m 10% 293729.00 352475.00
38th m 10% 323102.00 387722.00
39th m 10% 355412.00 426494.00
40th m 10% 390953.00 469144.00
Total Cost from 30m upto 40m 2642463 3170956
Avg Rate per metre 264246.00 317096.00
12.18 B Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 300.00 90.00 L-12
Sinker ( skilled ) day 3.00 250.00 750.00 L-15
Sinking helper (semi-skilled) day 4.50 225.00 1012.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1045.00 6531.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 653.13
c) Overhead charges @ 10 % on (a+b) 903.69
d) Contractor's profit @ 10 % on (a+b+c) 994.06
Cost for 0.25m = a+b+c+d 10934.62
Rate per metre = (a+b+c+d)/0.25 43738.48
say 43738.00
12.18 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 300.00 144.00 L-12
Sinker day 3.75 250.00 937.50 L-15
Sinking helper (semi-skilled) day 6.00 225.00 1350.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1045.00 8704.85 P&M-075
0.75 cum capacity and accessories.
251
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor with pneumatic chisel attachment for hour 4.50 300.00 1350.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1005.49
c) Overhead charges @ 10 % on (a+b) 1349.18
d) Contractor's profit @ 10 % on (a+b+c) 1484.10
Cost for 0.25m = a+b+c+d 16325.12
Rate per metre = (a+b+c+d)/0.25 65300.48
say 65300.00
12.18 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
31st m 7.5% 114347.00 142934.00 150081.00
32nd 7.5% 122923.00 153654.00 161337.00
33rd m 7.5% 132142.00 165178.00 173437.00
34th m 7.5% 142053.00 177566.00 186444.00
35th m 7.5% 152707.00 190884.00 200428.00
36th m 7.5% 164160.00 205200.00 215460.00
37th m 7.5% 176472.00 220590.00 231620.00
38th m 7.5% 189707.00 237134.00 248991.00
39th m 7.5% 203935.00 254919.00 267665.00
40th m 7.5% 219230.00 274038.00 287740.00
Total Cost from 30m upto 40m 1617676 2022097 2123203
Avg Rate per metre 161768.00 202210.00 212320.00
12.18 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 241153.00 289384.00 303853.00
32nd 10% 265268.00 318322.00 334238.00
33rd m 10% 291795.00 350154.00 367662.00
34th m 10% 320975.00 385170.00 404429.00
35th m 10% 353073.00 423688.00 444872.00
36th m 10% 388380.00 466056.00 489359.00
252
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
37th m 10% 427218.00 512662.00 538295.00
38th m 10% 469940.00 563928.00 592124.00
39th m 10% 516934.00 620321.00 651337.00
40th m 10% 568627.00 682352.00 716470.00
Total Cost from 30m upto 40m 3843363 4612037 4842639
Avg Rate per metre 384336.00 461204.00 484264.00
12.18 C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 300.00 318.00 L-12
Sinker ( skilled ) day 4.50 250.00 1125.00 L-15
Sinking helper (semi-skilled) day 20.00 225.00 4500.00 L-14
Diver day 1.75 250.00 437.50 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1045.00 10450.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 300.00 1425.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1187.50
Add for dewatering @ 5 per cent, if required 653.13
c) Overhead charges @ 10 % on (a+b) 2009.61
d) Contractor's profit @ 10 % on (a+b+c) 2210.57
Cost for 0.25m = a+b+c+d 24316.31
Rate per metre = (a+b+c+d)/0.25 97265.25
say 97265.00
12.18 D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 111.00 1554.00 M-104
Electric detonator each. 56.00 6.60 369.60 M-094/100
b) Labour
Mate day 1.44 300.00 432.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 28.00 225.00 6300.00 L-13
Mazdoor (Skilled) day 4.50 250.00 1125.00 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 1045.00 13062.50 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 300.00 1200.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 713.13
Consumables in sinking @ 10 per cent of (c). 1497.56
d) Overhead charges @ 10 % on (a+b+c) 2681.63
e) Contractor's profit @ 10 % on (a+b+c+d) 2949.79
Cost for 0.25m = a+b+c+d+e 32447.71
Rate per metre = (a+b+c+d+e)/0.25 129790.83
say 129791.00
253
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.19 1200 Sinking of Twin D Type well (other than pneumatic
method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
254
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 17214.00 20657.00
22nd m 7.5% 18505.00 22206.00
23rd m 7.5% 19893.00 23872.00
24th m 7.5% 21385.00 25662.00
25th m 7.5% 22989.00 27587.00
26th m 7.5% 24713.00 29656.00
27th m 7.5% 26566.00 31879.00
28th m 7.5% 28558.00 34270.00
29th m 7.5% 30700.00 36840.00
30th m 7.5% 33003.00 39604.00
Total Cost from 20m upto 30m 243526.00 292233.00
Avg Rate per metre 24353.00 29223.00
12.19 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 36303.00 43564.00
32nd 10% 39933.00 47920.00
33rd m 10% 43926.00 52711.00
34th m 10% 48319.00 57983.00
35th m 10% 53151.00 63781.00
36th m 10% 58466.00 70159.00
37th m 10% 64313.00 77176.00
38th m 10% 70744.00 84893.00
39th m 10% 77818.00 93382.00
40th m 10% 85600.00 102720.00
Total Cost from 30m upto 40m 578573.00 694289.00
Avg Rate per metre 57857.00 69429.00
12.19 B Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 300.00 78.00 L-12
Sinker ( skilled ) day 2.50 250.00 625.00 L-15
Sinking helper (semi-skilled) day 4.00 225.00 900.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1045.00 6531.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 653.13
c) Overhead charges @ 10 % on (a+b) 878.74
d) Contractor's profit @ 10 % on (a+b+c) 966.61
Rate per metre = (a+b+c+d) 10632.72
say 10633.00
12.19 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 300.00 135.00 L-12
Sinker day 3.25 250.00 812.50 L-15
Sinking helper (semi-skilled) day 6.00 225.00 1350.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 1045.00 6970.15 P&M-075
0.75 cum capacity and accessories.
255
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Air compressor with pneumatic chisel attachment for hour 4.50 300.00 1350.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 832.02
c) Overhead charges @ 10 % on (a+b) 1144.97
d) Contractor's profit @ 10 % on (a+b+c) 1259.46
Rate per metre = (a+b+c+d) 13854.09
say 13854.00
12.19 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5% for
loading arrangement and Labour ). for Kentledge dewatering, if
required
31st m 7.5% 24260.00 30325.00 31841.00
32nd 7.5% 26080.00 32600.00 34230.00
33rd m 7.5% 28036.00 35045.00 36797.00
34th m 7.5% 30139.00 37674.00 39558.00
35th m 7.5% 32399.00 40499.00 42524.00
36th m 7.5% 34829.00 43536.00 45713.00
37th m 7.5% 37441.00 46801.00 49141.00
38th m 7.5% 40249.00 50311.00 52827.00
39th m 7.5% 43268.00 54085.00 56789.00
40th m 7.5% 46513.00 58141.00 61048.00
Total Cost from 30m upto 40m 343214.00 429017.00 450468.00
Avg Rate per metre 34321.00 42902.00 45047.00
12.19 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5% for
loading arrangement and Labour). for Kentledge dewatering, if
required
31st m 10% 51164.00 61397.00 64467.00
32nd 10% 56280.00 67536.00 70913.00
33rd m 10% 61908.00 74290.00 78005.00
34th m 10% 68099.00 81719.00 85805.00
35th m 10% 74909.00 89891.00 94386.00
36th m 10% 82400.00 98880.00 103824.00
37th m 10% 90640.00 108768.00 114206.00
256
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
38th m 10% 99704.00 119645.00 125627.00
39th m 10% 109674.00 131609.00 138189.00
40th m 10% 120641.00 144769.00 152007.00
Total Cost from 30m upto 40m 815419.00 978504.00 1027429.00
Avg Rate per metre 81542.00 97850.00 102743.00
12.19 C Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 300.00 258.00 L-12
Sinker ( skilled ) day 4.50 250.00 1125.00 L-15
Sinking helper (semi-skilled) day 15.00 225.00 3375.00 L-14
Diver day 1.50 250.00 375.00 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1045.00 8704.85 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 300.00 1800.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 1050.49
Add for dewatering @ 5 per cent, if required 577.77
c) Overhead charges @ 10 % on (a+b) 1726.61
d) Contractor's profit @ 10 % on (a+b+c) 1899.27
Rate per metre = (a+b+c+d) 20891.98
say 20892.00
12.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 111.00 1110.00 M-104
Electric detonators each. 40.00 6.60 264.00 M-094/100
b) Labour
Mate day 1.34 300.00 402.00 L-12
Driller day 2.00 250.00 500.00 L-06
Blaster day 0.25 250.00 62.50 L-03
Mazdoor day 25.00 225.00 5625.00 L-13
Mazdoor (Skilled) day 4.25 250.00 1062.50 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1045.00 10450.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 300.00 900.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 950.10
Consumables in sinking @ 10 per cent of (b). 1230.01
d) Overhead charges @ 10 % on (a+b+c) 2255.61
e) Contractor's profit @ 10 % on (a+b+c+d) 2481.17
Rate per metre = (a+b+c+d+e) 27292.89
say 27293.00
257
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.20 1200 Pneumatic sinking of wells with equipment of approved
design, drawing and specifications worked by
competent and trained personnel and comprising of
compression and decompression chambers, reducers,
two air locks separately for men and plant & materials,
arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than 6
mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required,
staircases and 1 m wide landing plateforms with railing,
arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for rest
and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of
MoRTH Specifications.
Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.00 4543.00 36344.00 Item 12.8
equipment (Dimensions as per ground conditions). (H)
Rate may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 51000.00 24480.00 M-082
Blasting material
Gelatine 80 per cent Kg 1.50 111.00 166.50 M-104
Electric detonators each 6.00 6.60 39.60 M-094/100
b) Labour
Medical Officer day 0.50 800.00 400.00 L-16
Para medical personnel day 1.00 350.00 350.00 L-19
Mate day 1.86 300.00 558.00 L-12
Driller day 1.00 250.00 250.00 L-06
Blaster day 0.50 250.00 125.00 L-03
Mazdoor (for cutting, blasting, cleaning, removal of day 30.00 225.00 6750.00 L-13
Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter day 10.00 250.00 2500.00 L-15
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)
258
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note [Link] cost of induction, deinduction and erection of
equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 51520.00 54096.00 M-179
b) Labour
Mate day 1.24 300.00 372.00 L-12
Fitter day 6.00 350.00 2100.00 L-08
Blacksmith day 5.00 350.00 1750.00 L-01
Welder day 5.00 350.00 1750.00 L-02
Mazdoor day 10.00 225.00 2250.00 L-13
Electrodes, cutting gas and other consumables @ 5 2704.80
per cent on cost a (a) above.
c) Overhead charges @ 10 % on (a+b) 6502.28
d) Contractor's profit @ 10 % on (a+b+c) 7152.51
Rate for per MT (a+b+c+d) 78677.59
say 78678.00
12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
259
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
PCC Grade M35 cum 6.62 4565.00 30220.30 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4158.00 24948.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 304.00 152.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.30 770.00 231.00 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.30 250.00 75.00 P&M-048
bore hole
Bentonite kg 300.00 18.00 5400.00 M-071
c) Labour
Mate/Supervisor day 0.14 300.00 42.00 L-12
Mazdoor day 3.50 225.00 787.50 L-13
d) Overhead charges @ 10 % on (b+c) 3163.55
e) Contractor's profit @ 10 % on (b+c+d) 3479.91
Cost for 15 m = a+b+c+d+d+e 68499.26
Rate per metre (a+b+c+d+e)/15 4566.62
say 4567.00
12.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding
1100,16 Reinforcement complete as per Drawing and Technical
00 & Specifications and removal of excavated earth with all
1700 lifts and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 4565.00 35835.25 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4158.00 24948.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 304.00 152.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.40 770.00 308.00 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.40 250.00 100.00 P&M-048
bore hole
Bentonite kg 350.00 18.00 6300.00 M-071
c) Labour
Mate/Supervisor day 0.16 300.00 48.00 L-12
Mazdoor day 4.00 225.00 900.00 L-13
d) Overhead charges @ 10 % on (b+c) 3275.60
e) Contractor's profit @ 10 % on (b+c+d) 3603.16
Cost for 10 m = a+b+c+d+d+e 75470.01
Rate per metre (a+b+c+d+e)/10 7547.00
say 7547.00
12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
260
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 4565.00 46426.05 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4158.00 24948.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 304.00 152.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.50 770.00 385.00 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 250.00 125.00 P&M-048
bore hole
Bentonite kg 385.00 18.00 6930.00 M-071
c) Labour
Mate/Supervisor day 0.18 300.00 54.00 L-12
Mazdoor day 4.50 225.00 1012.50 L-13
d) Overhead charges @ 10 % on (b+c) 3360.65
e) Contractor's profit @ 10 % on (b+c+d) 3696.72
Cost for 9 m = a+b+c+d+d+e 87089.92
Rate per metre (a+b+c+d+e)/9 9676.66
say 9677.00
12.26 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35 cum 17.66 4565.00 80617.90 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 53.00 8480.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 55.00 3850.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 58.00 2900.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 3746.00 22476.00 P&M-085
acting pile driving hammer complete with power unit
and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 313.00 156.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 300.00 36.00 L-12
Mazdoor day 3.00 225.00 675.00 L-13
e) Overhead charges @ 10 % on (b+c+d) 3857.35
f) Contractor's profit @ 10 % on (b+c+d+e) 4243.09
Cost for 40 m = a+b+c+d+e 127291.84
Rate per metre (a+b+c+d+e)/40 3182.30
say 3182.00
261
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Note [Link] quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
[Link] case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.27 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 4565.00 107505.75 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 53.00 8480.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 55.00 3850.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 58.00 2900.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 3746.00 22476.00 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 313.00 156.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering hour 0.50 304.00 152.00 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 300.00 48.00 L-12
Mazdoor day 4.00 225.00 900.00 L-13
e) Overhead charges @ 10 % on (b+c+d) 3896.25
f) Contractor's profit @ 10 % on (b+c+d+e) 4285.88
Cost for 30 m = a+b+c+d+e 154650.38
Rate per metre (a+b+c+d+e)/30 5155.01
say 5155.00
Note [Link] quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
[Link] case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.28 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
PCC Grade M35 cum 22.61 4565.00 103214.65 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 53.00 8480.00 M-080
262
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 55.00 3850.00 M-124
iii) Steel helmet on top of casing head during driving Kg 50.00 58.00 2900.00 M-173
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 3746.00 22476.00 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 313.00 156.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 300.00 54.00 L-12
Mazdoor day 4.50 225.00 1012.50 L-13
e) Overhead charges @ 10 % on (b+c+d) 3892.90
f) Contractor's profit @ 10 % on (b+c+d+e) 4282.19
Cost for 20 m = a+b+c+d+e 150318.74
Rate per metre (a+b+c+d+e)/20 7515.94
say 7516.00
Note [Link] quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
[Link] case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.29 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 4406.00 51902.68 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes Kg 240.00 53.00 12720.00 M-080
b) M.S. shoes Kg 105.00 54.00 5670.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 58.00 1740.00 M-173
during driving.
c) Machinery
Crane20 t capacity hour 6.00 599.00 3594.00 P&M-073
Vibrating Pile driving hammer complete with power unit hour 6.00 687.00 4122.00 P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.12 300.00 36.00 L-12
Mazdoor day 3.00 225.00 675.00 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 804.60
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on (b+c+d) 2936.16
f) Contractor's profit @ 10 % on (b+c+d+e) 3229.78
Cost for 60 m = a+b+c+d+e+f 87430.21
Rate per metre (a+b+c+d+e+f)/60 1457.17
say 1457.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
263
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
12.30 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 4406.00 97284.48 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes Kg 160.00 53.00 8480.00 M-080
b) M.S. shoes Kg 70.00 54.00 3780.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 40.00 58.00 2320.00 M-173
during driving.
c) Machinery
Crane 40 T capacity hour 6.00 649.00 3894.00 P&M-074
Vibrating Pile driving hammer complete with power unit hour 6.00 687.00 4122.00 P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.16 300.00 48.00 L-12
Mazdoor day 4.00 225.00 900.00 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 1208.28
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on (b+c+d) 2475.23
f) Contractor's profit @ 10 % on (b+c+d+e) 2722.75
Cost for 50 m = a+b+c+d+e+f 127234.74
Rate per metre (a+b+c+d+e+f)/50 2544.69
say 2545.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.31 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 31.40 4406.00 138348.40 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.00 53.00 8480.00 M-080
b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 54.00 3780.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 50.00 58.00 2900.00 M-173
during driving.
c) Machinery
Crane 50 t capacity. hour 6.00 1055.00 6330.00 P&M-011
Vibrating Pile driving hammer complete with power unit hour 6.00 687.00 4122.00 P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.20 300.00 60.00 L-12
Mazdoor day 5.00 225.00 1125.00 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 1651.45
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on (b+c+d) 2844.85
f) Contractor's profit @ 10 % on (b+c+d+e) 3129.33
264
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost for 40 m = a+b+c+d+e+f 172771.03
Rate per metre (a+b+c+d+e+f)/40 4319.28
say 4319.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.32 1100&17 Driven precast vertical M35 grade R.C.C. Piles excluding
00 Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 5.40 4406.00 23792.40 Item 12.11
plug vide item no. 12.11( F ) (IV) (F) iv
b ) Material Pile shoes
a) C I shoes kg 240.00 53.00 12720.00 M-080
b) M. S shoes kg 105.00 54.00 5670.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 58.00 1740.00 M-173
during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 379.00 2274.00 P&M-071
Vibrating Pile driving hammer complete with power unit hour 6.00 687.00 4122.00 P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.12 300.00 36.00 L-12
Mazdoor day 3.00 225.00 675.00 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 510.29
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on (b+c+d) 2774.73
f) Contractor's profit @ 10 % on (b+c+d+e) 3052.20
Cost for 60 m = a+b+c+d+e+f 57366.63
Rate per metre (a+b+c+d+e+f)/60 956.11
say 956.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.33 1100 Driven precast vertical M35 grade R.C.C. Piles excluding
&1700 Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 12.50 4406.00 55075.00 Item 12.11
plug vide item no. 12.11( F ) (IV) (F) iv
b ) Material Pile shoes
a) C I shoes kg 160.00 53.00 8480.00 M-080
b) M. S shoes kg 70.00 54.00 3780.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 58.00 1740.00 M-173
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 599.00 3594.00 P&M-073
Vibrating Pile driving hammer complete with power unit hour 6.00 687.00 4122.00 P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.16 300.00 48.00 L-12
Mazdoor day 4.00 225.00 900.00 L-13
265
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Add 1 per cent of (a+b+c) for carriage of piles from 777.39
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on (b+c+d) 2344.14
f) Contractor's profit @ 10 % on (b+c+d+e) 2578.55
Cost for 50 m = a+b+c+d+e+f 83439.08
Rate per metre (a+b+c+d+e+f)/50 1668.78
say 1669.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.34 1100 Driven precast vertical M35 grade R.C.C. Piles excluding
&1700 Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 22.50 4406.00 99135.00 Item 12.11
plug vide item no. 13.11( F ) (IV) (F) iv
b ) Material
Pile shoes
a) C I shoes kg 160.00 53.00 8480.00 M-080
b) M. S shoes kg 70.00 54.00 3780.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 58.00 1740.00 M-173
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 599.00 3594.00 P&M-073
Vibrating Pile driving hammer complete with power unit hour 6.00 687.00 4122.00 P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.18 300.00 54.00 L-12
Mazdoor day 4.50 225.00 1012.50 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 1219.18
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on (b+c+d) 2400.17
f) Contractor's profit @ 10 % on (b+c+d+e) 2640.18
Cost for 40 m = a+b+c+d+e+f 128177.03
Rate per metre (a+b+c+d+e+f)/40 3204.43
say 3204.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.35 1100, Driven Vertical Steel Piles complete as per Drawing and
1900 & Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 tonnes 6.04 51520.00 311180.80 M-179
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 379.00 2274.00 P&M-071
Vibrating Pile driving hammer complete with power unit hour 6.00 687.00 4122.00 P&M-092
and other accessories.
c) Labour
Mate/Supervisor day 0.12 300.00 36.00 L-12
Mazdoor day 3.00 225.00 675.00 L-13
266
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Add 0.5 per cent of (a+b+c) for providing steel 1591.44
helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and
other imponderables during installation.
267
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 500.00 3000.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 2065.33
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 5369.86
e) Contractor's profit @ 10 % on (a+b+c+d) 5906.84
Cost for 15 cum = a+b+c+d+e 64975.28
Rate per metre (a+b+c+d+e)/15 4331.69
say 4332.00
12.38A (ii) Using Batching Plant, Transit Mixer and Concrete Pump
a) Material
Cement tonne 5.12 5600.00 28672.00 M-081
Coarse sand cum 6.75 240.00 1620.00 M-004
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.16 300.00 48.00 L-12
Mason day 0.38 300.00 114.00 L-10
Mazdoor for concreting day 2.50 225.00 562.50 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2109.00 1581.75 P&M-002
Generator 100 KVA hour 0.75 743.00 557.25 P&M-080
Loader (capacity 1 cum) hour 0.75 770.00 577.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 813.00 1626.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 37.5L 2.00 1500.00 Lead =20
km & P&M-
050
Concrete Pump hour 0.75 570.00 427.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 1865.50
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 4850.30
e) Contractor's profit @ 10 % on (a+b+c+d) 5335.33
Cost for 15 cum = a+b+c+d+e 58688.63
Rate per metre (a+b+c+d+e)/15 3912.58
say 3913.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 B RCC Grade M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 5600.00 33544.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.90 300.00 270.00 L-12
Mason day 1.50 300.00 450.00 L-10
Mazdoor for concreting day 20.00 225.00 4500.00 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
268
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 500.00 3000.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 2260.21
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 5876.55
e) Contractor's profit @ 10 % on (a+b+c+d) 6464.20
Cost for 15 cum = a+b+c+d+e 71106.21
Rate per metre (a+b+c+d+e)/15 4740.41
say 4740.00
12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump
a) Material
Cement tonne 5.99 5600.00 33544.00 M-081
Coarse sand cum 6.75 240.00 1620.00 M-004
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.16 300.00 48.00 L-12
Mason day 0.38 300.00 114.00 L-10
Mazdoor for concreting day 2.50 225.00 562.50 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2109.00 1581.75 P&M-002
Generator 125 KVA hour 0.75 741.00 555.75 P&M-018
Loader (capacity 1 cum) hour 0.75 770.00 577.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 813.00 1626.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 37.5L 2.00 1500.00 Lead =20
km & P&M-
050
Concrete Pump hour 0.75 570.00 427.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 2060.32
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 5356.83
e) Contractor's profit @ 10 % on (a+b+c+d) 5892.52
Cost for 15 cum = a+b+c+d+e 64817.67
Rate per metre (a+b+c+d+e)/15 4321.18
say 4321.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 C RCC Grade M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 5600.00 34160.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.90 300.00 270.00 L-12
Mason day 1.50 300.00 450.00 L-10
Mazdoor for concreting day 20.00 225.00 4500.00 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
269
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Generator (capacity 33 KVA) hour 6.00 500.00 3000.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 2284.85
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 5940.61
e) Contractor's profit @ 10 % on (a+b+c+d) 6534.67
Cost for 15 cum = a+b+c+d+e 71881.38
Rate per metre (a+b+c+d+e)/15 4792.09
say 4792.00
'12.38C (ii) Using Batching Plant, Transit Mixer and Concrete Pump
a) Material
Cement tonne 6.10 5600.00 34160.00 M-081
Coarse sand cum 6.75 240.00 1620.00 M-004
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.16 300.00 48.00 L-12
Mason day 0.38 300.00 114.00 L-10
Mazdoor for concreting day 2.50 225.00 562.50 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2109.00 1581.75 P&M-002
Generator 100 KVA hour 0.75 743.00 557.25 P&M-080
Loader (capacity 1 cum) hour 0.75 770.00 577.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 813.00 1626.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 37.5L 2.00 1500.00 Lead =20
km & P&M-
050
Concrete Pump hour 0.75 570.00 427.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 2085.02
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 5421.05
e) Contractor's profit @ 10 % on (a+b+c+d) 5963.16
Cost for 15 cum = a+b+c+d+e 65594.73
Rate per metre (a+b+c+d+e)/15 4372.98
say 4373.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 D RCC Grade M35
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.33 5600.00 35448.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.90 300.00 270.00 L-12
Mason day 1.50 300.00 450.00 L-10
Mazdoor day 20.00 225.00 4500.00 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 500.00 3000.00 P&M-079
270
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Formwork @ 4 per cent on cost of concrete i.e. cost 2336.37
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 6074.56
e) Contractor's profit @ 10 % on (a+b+c+d) 6682.02
Cost for 15 cum = a+b+c+d+e 73502.20
Rate per metre (a+b+c+d+e)/15 4900.15
say 4900.00
'12.38D (ii) Using Batching Plant, Transit Mixer and Concrete Pump
a) Material
Cement tonne 6.33 5600.00 35448.00 M-081
Coarse sand cum 6.75 240.00 1620.00 M-004
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.16 300.00 48.00 L-12
Mason day 0.38 300.00 114.00 L-10
Mazdoor for concreting day 2.50 225.00 562.50 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 225.00 225.00 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2109.00 1581.75 P&M-002
Generator 125 KVA hour 0.75 741.00 555.75 P&M-018
Loader (capacity 1 cum) hour 0.75 770.00 577.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 813.00 1626.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 37.5L 2.00 1500.00 Lead =20
km & P&M-
050
Concrete Pump hour 0.75 570.00 427.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 2136.48
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 5554.85
e) Contractor's profit @ 10 % on (a+b+c+d) 6110.33
Cost for 15 cum = a+b+c+d+e 67213.66
Rate per metre (a+b+c+d+e)/15 4480.91
say 4481.00
12.39 1100&17 Levelling Course for Pile cap
00
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5600.00 23128.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
40 mm aggregate cum 8.10 660.00 5346.00 M-055
20 mm Aggregate cum 4.05 680.00 2754.00 M-053
10 mm Aggregate cum 1.35 670.00 904.50 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 300.00 450.00 L-10
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
d) Overhead charges @ 10 % on (a+b+c) 4573.08
e) Contractor's profit @ 10 % on (a+b+c+d) 5030.38
Cost for 15 cum = a+b+c+d+e 55334.21
271
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per metre (a+b+c+d+e)/15 3688.95
say 3689.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 51000.00 53550.00 M-082
272
CHAPTER-13
SUB-STRUCTURE
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
13.1 1300 & Brick masonry work in 1:3 in sub-structure complete
2200 excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 3.10 1550.00 M-079
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.24 3788.00 909.12 Item 12.6
analysis) (A)
b) Labour
Mate day 0.06 300.00 18.00 L-12
Mason day 0.80 350.00 280.00 L-11
Mazdoor day 0.80 225.00 180.00 L-13
Add for scaffolding @ 5 per cent of cost of material 146.86
and labour
c) Overhead charges @ 10 % on (a+b) 308.40
d) Contractor's profit @ 10 % on (a+b+c) 339.24
Rate per cum (a+b+c+d) 3731.61
say 3732.00
13.2 1300 & Pointing with cement mortar (1:3 ) on brick work in
2200 substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 3788.00 113.64 Item 12.6
(A)
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mason day 0.50 350.00 175.00 L-11
Mazdoor day 0.50 225.00 112.50 L-13
c) Overhead charges @ 10 % on (a+b) 41.31
d) Contractor's profit @ 10 % on (a+b+c) 45.45
Rate per 10 sqm (a+b+c+d) 499.90
say 500.00
Note Scaffolding is already included in item 13.1
13.3 1300 & Plastering with cement mortar (1:3 ) on brick work in
2200 sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 3788.00 545.47 Item 12.6
(A)
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mason day 0.50 350.00 175.00 L-11
Mazdoor day 0.50 225.00 112.50 L-13
c) Overhead charges @ 10 % on (a+b) 84.50
d) Contractor's profit @ 10 % on (a+b+c) 92.95
Rate per 10 sqm (a+b+c+d) 1022.42
say 1022.00
Note [Link] is already included in item no. 13.1
[Link] number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
13.4 1400 & Stone masonry work in cement mortar 1:3 for
2200 substructure complete as per drawing and Technical
Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 383.00 2106.50 M-148
Through and bond stone No 35.00 38.00 1330.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
273
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cement mortar 1:3 (Rate as in Item 12.6) cum 1.55 3788.00 5871.40 Item 12.6
(A)
b) Labour
Mate day 0.62 300.00 186.00 L-12
Mason day 6.00 350.00 2100.00 L-11
Mazdoor day 9.00 225.00 2025.00 L-13
Add for scaffolding @ 5 per cent of cost of a) 680.95
Material and b) Labour
c) Overhead charges @ 10 % on (a+b) 1429.98
d) Contractor's profit @ 10 % on (a+b+c) 1572.98
Rate per cum (a+b+c+d)/5 3460.56
say 3461.00
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 383.00 421.30 M-148
Through and bond stone each 7.00 38.00 266.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 3788.00 1136.40 Item 12.6
(A)
b) Labour
Mate day 0.12 300.00 36.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 1.50 225.00 337.50 L-13
Add for scaffolding @ 5 per cent of cost of material 136.11
and labour
c) Overhead charges @ 10 % on (a+b) 285.83
d) Contractor's profit @ 10 % on (a+b+c) 314.41
Rate per cum (a+b+c+d) 3458.56
say 3459.00
13.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 773.00 858.03 M-169
Through and bond stone each 7.00 38.00 266.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3788.00 1250.04 Item 12.6
(A)
b) Labour for masonry work
Mate day 0.20 300.00 60.00 L-12
Mason day 2.50 350.00 875.00 L-11
Mazdoor day 2.50 225.00 562.50 L-13
Add for scaffolding @ 5 per cent of cost of a) 193.58
Material and b) Labour
c) Overhead charges @ 10 % on (a+b) 406.51
d) Contractor's profit @ 10 % on (a+b+c) 447.17
Rate per cum (a+b+c+d) 4918.83
say 4919.00
Note The labour already considered in the cement mortar have
been taken into account while providing these categories in
the stone masonry works.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
274
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
(p) Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 3083.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 308.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 339.13
f) Contractor's profit @ 10 % on (a+b+c+d+e) 373.04
Rate perm (a+b+c+d+e+f) 4103.47
say 4103.00
13.5 B PCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 3117.00 Item 12.8 (B) PCC
(a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 311.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 342.87
f) Contractor's profit @ 10 % on (a+b+c+d+e) 377.16
Rate perm (a+b+c+d+e+f) 4148.73
say 4149.00
13.5 C PCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.
275
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3751.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 450.12
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 75.02
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 427.61
f) Contractor's profit @ 10 % on (a+b+c+d+e) 470.38
Rate perm (a+b+c+d+e+f) 5174.13
say 5174.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3405.00
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 408.60
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 68.10
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 388.17
f) Contractor's profit @ 10 % on (a+b+c+d+e) 426.99
Rate perm (a+b+c+d+e+f) 4696.86
say 4697.00
13.5 C (r) Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
material, labour and machinery.
276
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3785.00
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 378.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 416.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 457.99
Rate perm (a+b+c+d+e+f) 5037.84
say 5038.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3435.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 343.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 377.85
f) Contractor's profit @ 10 % on (a+b+c+d+e) 415.64
Rate perm (a+b+c+d+e+f) 4571.99
say 4572.00
13.5 D (q) Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
277
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Add 15 per cent of cost of material, labour and 15.00 567.75
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 151.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 450.41
f) Contractor's profit @ 10 % on (a+b+c+d+e) 495.46
Rate perm (a+b+c+d+e+f) 5450.02
say 5450.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3435.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 515.25
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 137.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 408.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 449.64
Rate perm (a+b+c+d+e+f) 4946.06
say 4946.00
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3466.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 346.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 381.26
f) Contractor's profit @ 10 % on (a+b+c+d+e) 419.39
Rate perm (a+b+c+d+e+f) 4613.25
say 4613.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3117.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 311.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 342.87
f) Contractor's profit @ 10 % on (a+b+c+d+e) 377.16
Rate perm (a+b+c+d+e+f) 4148.73
say 4149.00
13.5 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .
278
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
f) Contractor's profit @ 10 % on (a+b+c+d+e) 434.64
Rate perm (a+b+c+d+e+f) 4781.00
say 4781.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3117.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 374.04
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 62.34
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 355.34
f) Contractor's profit @ 10 % on (a+b+c+d+e) 390.87
Rate perm (a+b+c+d+e+f) 4299.59
say 4300.00
13.5 E (r) Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.
279
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
say 5030.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3535.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 353.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 388.85
f) Contractor's profit @ 10 % on (a+b+c+d+e) 427.74
Rate perm (a+b+c+d+e+f) 4705.09
say 4705.00
13.5 F (q) Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3779.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 445.92
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 68.02
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 429.29
f) Contractor's profit @ 10 % on (a+b+c+d+e) 472.22
Rate perm (a+b+c+d+e+f) 5194.46
say 5194.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3535.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 417.13
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 63.63
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 401.58
f) Contractor's profit @ 10 % on (a+b+c+d+e) 441.73
Rate perm (a+b+c+d+e+f) 4859.07
say 4859.00
13.5 F (r) Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3779.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 566.85
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 151.16
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 449.70
f) Contractor's profit @ 10 % on (a+b+c+d+e) 494.67
Rate perm (a+b+c+d+e+f) 5441.38
say 5441.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3535.00
(a+b+c) of Item 12.8 (E) Case II
280
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
d) formwork
Add 15 per cent of cost of material, labour and 15.00 530.25
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 141.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 420.66
f) Contractor's profit @ 10 % on (a+b+c+d+e) 462.73
Rate perm (a+b+c+d+e+f) 5090.05
say 5090.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3798.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 379.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 417.78
f) Contractor's profit @ 10 % on (a+b+c+d+e) 459.56
Rate perm (a+b+c+d+e+f) 5055.14
say 5055.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3450.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 345.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 379.50
f) Contractor's profit @ 10 % on (a+b+c+d+e) 417.45
Rate perm (a+b+c+d+e+f) 4591.95
say 4592.00
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3798.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 436.77
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 60.77
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 429.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 472.51
Rate perm (a+b+c+d+e+f) 5197.60
say 5198.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3450.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 396.75
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 55.20
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 390.20
281
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
f) Contractor's profit @ 10 % on (a+b+c+d+e) 429.21
Rate perm (a+b+c+d+e+f) 4721.36
say 4721.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3798.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 531.72
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 132.93
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 446.27
f) Contractor's profit @ 10 % on (a+b+c+d+e) 490.89
Rate perm (a+b+c+d+e+f) 5399.81
say 5400.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3450.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and 14.00 483.00
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 120.75
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 405.38
f) Contractor's profit @ 10 % on (a+b+c+d+e) 445.91
Rate perm (a+b+c+d+e+f) 4905.04
say 4905.00
13.5 H RCC Grade M35
(p) Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3884.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 388.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 427.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 469.96
Rate perm (a+b+c+d+e+f) 5169.60
say 5170.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3646.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 364.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 401.06
f) Contractor's profit @ 10 % on (a+b+c+d+e) 441.17
Rate perm (a+b+c+d+e+f) 4852.83
say 4853.00
13.5 H (q) Height 5m to 10m
282
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3884.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 11 per cent of cost of material, labour and 11.00 427.24
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 54.38
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 436.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 480.22
Rate perm (a+b+c+d+e+f) 5282.40
say 5282.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3646.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 401.06
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 51.04
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 409.81
f) Contractor's profit @ 10 % on (a+b+c+d+e) 450.79
Rate perm (a+b+c+d+e+f) 4958.71
say 4959.00
13.5 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3884.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 504.92
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 116.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 450.54
f) Contractor's profit @ 10 % on (a+b+c+d+e) 495.60
Rate perm (a+b+c+d+e+f) 5451.58
say 5452.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3646.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 473.98
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 109.38
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 422.94
f) Contractor's profit @ 10 % on (a+b+c+d+e) 465.23
Rate perm (a+b+c+d+e+f) 5117.53
say 5118.00
Note The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:
283
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
a) Ramps/Stairs: Extra expenditure on structures which
are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use by the working parties.
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per metre 31.50 22.00 693.00 M-056
cent )
Average length of weep hole is taken as one metre for the
purpose of estimating.
MS clamp each. 30.00 33.00 990.00 M-123
collar for AC pipe (average) taking 10% of above pipe each. 10.00 2.20 22.00 M-056/10
rate
284
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3788.00 189.40 Item 12.6
(A)
b) Labour
Mate day 0.03 300.00 9.00 L-12
Mason day 0.50 350.00 175.00 L-11
Mazdoor day 0.25 225.00 56.25 L-13
c) Overhead charges @ 10 % on (a+b) 213.47
d) Contractor's profit @ 10 % on (a+b+c) 234.81
Cost for 30 m = a+b+c+d 2582.93
Rate per m (a+b+c+d)/30 86.10
say 86.00
Note 1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 300.00 84.00 L-12
Mazdoor day 7.00 225.00 1575.00 L-13
b) Material
Granular material cum 12.00 240.00 2880.00 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 94.00 235.00 P&M-086
Water Tanker hour 0.05 130.00 6.50 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 478.05
e) Contractor's profit @ 10 % on (a+b+c+d) 525.86
Cost for 10 cum of granular backfill = a+b+c+d+e 5784.41
Rate per cum = (a+b+c+d+e)/10 578.44
say 578.00
13.9 B Sandy material
a) Labour
Mate day 0.28 300.00 84.00 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 225.00 1575.00 L-13
b) Material
Sand cum 12.00 550.00 6600.00 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 94.00 235.00 P&M-086
Water Tanker hour 0.06 130.00 7.80 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 850.18
e) Contractor's profit @ 10 % on (a+b+c+d) 935.20
Cost for 10 cum of sandy backfill = a+b+c+d+e 10287.18
Rate per cum = (a+b+c+d+e)/10 1028.72
say 1029.00
285
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
13.10 710.1.4. Providing and laying of Filter media with granular
of materials/stone crushed aggregates satisfying the
IRC:78 requirements laid down in clause 2504.2.2. of MoRTH
and specifications to a thickness of not less than 600 mm
2200 with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 300.00 96.00 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 225.00 1575.00 L-13
Mazdoor (Skilled) day 1.00 250.00 250.00 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 300.00 3600.00 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 130.00 7.80 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 552.88
e) Contractor's profit @ 10 % on (a+b+c+d) 608.17
cost for 10 cum of Fiter Media = a+b+c+d+e 6689.85
Rate per cum = (a+b+c+d+e)/10 668.98
say 669.00
13.11 2000, Supplying, fitting and fixing in position true to line and
1000 & level cast steel rocker bearing conforming to IRC: 83(Pt.-
2200 1) section IX and clause 2003 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
286
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Forged steel roller bearing of 250 tonne design load each. 1.00 73920.00 73920.00 M-067
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 739.20
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 10 % on (a+b) 7502.72
d) Contractor's profit @ 10 % on (a+b+c) 8252.99
cost for 250 tonnes capacity bearing = a+b+c+d 90782.91
Rate per tonne capacity = (a+b+c+d)/250 363.13
say 363.00
13.13 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per
drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of
MoRTH Specifications.
287
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 0.95
say 0.90
13.15 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
288
CHAPTER-14
SUPER-STRUCTURE
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and
1700 Technical Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 5600.00 28672.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) 51472.00
for 15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 51472.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 10294.40
e) Overhead charges @ 10 % on (a+b+c+d) 6176.64
f) Contractor's profit @ 10 % on (a+b+c+d+e) 6794.30
Cost for 15 cum = a+b+c+d+e+f 74737.34
Rate per cum = (a+b+c+d+e+f)/15 4982.49
say 4982.00
14.1A (q) Height 5m to 10m
Case I (i)
289
Basic Cost of Labour, Material & Machinery (a+b+c) for 51472.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 12868.00
e) Overhead charges @ 10 % on (a+b+c+d) 6434.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7077.40
Cost for 15 cum = a+b+c+d+e+f 77851.40
Rate per cum = (a+b+c+d+e+f)/15 5190.09
say 5190.00
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 51472.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 15441.60
e) Overhead charges @ 10 % on (a+b+c+d) 6691.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7360.50
Cost for 15 cum = a+b+c+d+e+f 80965.46
Rate per cum = (a+b+c+d+e+f)/15 5397.70
say 5398.00
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 51472.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 18015.20
e) Overhead charges @ 10 % on (a+b+c+d) 6948.72
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7643.59
Cost for 15 cum = a+b+c+d+e+f 84079.51
Rate per cum = (a+b+c+d+e+f)/15 5605.30
say 5605.00
14.1A Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 5600.00 229152.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 369819.00
for 120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 369819.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 73963.80
e) Overhead charges @ 10 % on (a+b+c+d) 44378.28
290
f) Contractor's profit @ 10 % on (a+b+c+d+e) 48816.11
Cost for 120 cum = a+b+c+d+e+f 536977.19
Rate per cum = (a+b+c+d+e+f)/120 4474.81
say 4475.00
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 369819.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 92454.75
e) Overhead charges @ 10 % on (a+b+c+d) 46227.38
f) Contractor's profit @ 10 % on (a+b+c+d+e) 50850.11
Cost for 120 cum = a+b+c+d+e+f 559351.24
Rate per cum = (a+b+c+d+e+f)/120 4661.26
say 4661.00
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 369819.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 110945.70
e) Overhead charges @ 10 % on (a+b+c+d) 48076.47
f) Contractor's profit @ 10 % on (a+b+c+d+e) 52884.12
Cost for 120 cum = a+b+c+d+e+f 581725.29
Rate per cum = (a+b+c+d+e+f)/120 4847.71
say 4848.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 369819.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 92454.75
e) Overhead charges @ 10 % on (a+b+c+d) 46227.38
f) Contractor's profit @ 10 % on (a+b+c+d+e) 50850.11
Cost for 120 cum = a+b+c+d+e+f 559351.24
Rate per cum = (a+b+c+d+e+f)/120 4661.26
say 4661.00
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 369819.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 110945.70
e) Overhead charges @ 10 % on (a+b+c+d) 48076.47
f) Contractor's profit @ 10 % on (a+b+c+d+e) 52884.12
Cost for 120 cum = a+b+c+d+e+f 581725.29
Rate per cum = (a+b+c+d+e+f)/120 4847.71
say 4848.00
14.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 369819.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 129436.65
e) Overhead charges @ 10 % on (a+b+c+d) 49925.57
f) Contractor's profit @ 10 % on (a+b+c+d+e) 54918.12
Cost for 120 cum = a+b+c+d+e+f 604099.34
Rate per cum = (a+b+c+d+e+f)/120 5034.16
say 5034.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
291
a) Material
Cement tonne 5.99 5600.00 33544.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.86 300.00 258.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) 56344.00
for 15 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 56344.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 11268.80
e) Overhead charges @ 10 % on (a+b+c+d) 6761.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7437.41
Cost for 15 cum = a+b+c+d+e+f 81811.49
Rate per cum = (a+b+c+d+e+f)/15 5454.10
say 5454.00
14.1B (q) Height 5m to 10m
Case I (i)
292
Basic Cost of Labour, Material & Machinery (a+b+c) for 56344.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 16903.20
e) Overhead charges @ 10 % on (a+b+c+d) 7324.72
f) Contractor's profit @ 10 % on (a+b+c+d+e) 8057.19
Cost for 15 cum = a+b+c+d+e+f 88629.11
Rate per cum = (a+b+c+d+e+f)/15 5908.61
say 5909.00
14.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 56344.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 19720.40
e) Overhead charges @ 10 % on (a+b+c+d) 7606.44
f) Contractor's profit @ 10 % on (a+b+c+d+e) 8367.08
Cost for 15 cum = a+b+c+d+e+f 92037.92
Rate per cum = (a+b+c+d+e+f)/15 6135.86
say 6136.00
14.1B Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 5600.00 268520.00 M-081
Coarse sand cum 54.20 240.00 13008.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.84 300.00 252.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 18.00 225.00 4050.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 409235.00
for 120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 409235.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 81847.00
e) Overhead charges @ 10 % on (a+b+c+d) 49108.20
f) Contractor's profit @ 10 % on (a+b+c+d+e) 54019.02
Cost for 120 cum = a+b+c+d+e+f 594209.22
Rate per cum = (a+b+c+d+e+f)/120 4951.74
say 4952.00
14.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 409235.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 102308.75
e) Overhead charges @ 10 % on (a+b+c+d) 51154.38
293
f) Contractor's profit @ 10 % on (a+b+c+d+e) 56269.81
Cost for 120 cum = a+b+c+d+e+f 618967.94
Rate per cum = (a+b+c+d+e+f)/120 5158.07
say 5158.00
14.1B (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 409235.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 122770.50
e) Overhead charges @ 10 % on (a+b+c+d) 53200.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 58520.61
Cost for 120 cum = a+b+c+d+e+f 643726.66
Rate per cum = (a+b+c+d+e+f)/120 5364.39
say 5364.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 409235.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 102308.75
e) Overhead charges @ 10 % on (a+b+c+d) 51154.38
f) Contractor's profit @ 10 % on (a+b+c+d+e) 56269.81
Cost for 120 cum = a+b+c+d+e+f 618967.94
Rate per cum = (a+b+c+d+e+f)/120 5158.07
say 5158.00
14.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 409235.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 122770.50
e) Overhead charges @ 10 % on (a+b+c+d) 53200.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 58520.61
Cost for 120 cum = a+b+c+d+e+f 643726.66
Rate per cum = (a+b+c+d+e+f)/120 5364.39
say 5364.00
14.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 409235.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 143232.25
e) Overhead charges @ 10 % on (a+b+c+d) 55246.73
f) Contractor's profit @ 10 % on (a+b+c+d+e) 60771.40
Cost for 120 cum = a+b+c+d+e+f 668485.37
Rate per cum = (a+b+c+d+e+f)/120 5570.71
say 5571.00
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5600.00 34160.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.90 300.00 270.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 21.00 225.00 4725.00 L-13
c) Machinery
294
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) 57197.00
for 15 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 57197.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 11439.40
e) Overhead charges @ 10 % on (a+b+c+d) 6863.64
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7550.00
Cost for 15 cum = a+b+c+d+e+f 83050.04
Rate per cum = (a+b+c+d+e+f)/15 5536.67
say 5537.00
14.1C (q) Height 5m to 10m
Case I (i)
295
Basic Cost of Labour, Material & Machinery (a+b+c) for 57197.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 20018.95
e) Overhead charges @ 10 % on (a+b+c+d) 7721.60
f) Contractor's profit @ 10 % on (a+b+c+d+e) 8493.75
Cost for 15 cum = a+b+c+d+e+f 93431.30
Rate per cum = (a+b+c+d+e+f)/15 6228.75
say 6229.00
14.1C Case II Using Batching Plant, Transit Mixer and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 5600.00 273224.00 M-081
Coarse sand cum 54.60 240.00 13104.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.88 300.00 264.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 19.00 225.00 4275.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 414272.00
for 120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 414272.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 82854.40
e) Overhead charges @ 10 % on (a+b+c+d) 49712.64
f) Contractor's profit @ 10 % on (a+b+c+d+e) 54683.90
Cost for 120 cum = a+b+c+d+e+f 601522.94
Rate per cum = (a+b+c+d+e+f)/120 5012.69
say 5013.00
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 414272.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 103568.00
e) Overhead charges @ 10 % on (a+b+c+d) 51784.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 56962.40
Cost for 120 cum = a+b+c+d+e+f 626586.40
Rate per cum = (a+b+c+d+e+f)/120 5221.55
say 5222.00
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 414272.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 124281.60
e) Overhead charges @ 10 % on (a+b+c+d) 53855.36
296
f) Contractor's profit @ 10 % on (a+b+c+d+e) 59240.90
Cost for 120 cum = a+b+c+d+e+f 651649.86
Rate per cum = (a+b+c+d+e+f)/120 5430.42
say 5430.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 414272.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 103568.00
e) Overhead charges @ 10 % on (a+b+c+d) 51784.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 56962.40
Cost for 120 cum = a+b+c+d+e+f 626586.40
Rate per cum = (a+b+c+d+e+f)/120 5221.55
say 5222.00
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 414272.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 124281.60
e) Overhead charges @ 10 % on (a+b+c+d) 53855.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 59240.90
Cost for 120 cum = a+b+c+d+e+f 651649.86
Rate per cum = (a+b+c+d+e+f)/120 5430.42
say 5430.00
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 414272.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 144995.20
e) Overhead charges @ 10 % on (a+b+c+d) 55926.72
f) Contractor's profit @ 10 % on (a+b+c+d+e) 61519.39
Cost for 120 cum = a+b+c+d+e+f 676713.31
Rate per cum = (a+b+c+d+e+f)/120 5639.28
say 5639.00
14.1 D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5600.00 35448.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
b) Labour
Mate day 0.90 300.00 270.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 21.00 225.00 4725.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) 58485.00
for 15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 58485.00
15 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 10527.30
297
e) Overhead charges @ 10 % on (a+b+c+d) 6901.23
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7591.35
Cost for 15 cum = a+b+c+d+e+f 83504.88
Rate per cum = (a+b+c+d+e+f)/15 5566.99
say 5567.00
14.1D (q) Height 5m to 10m
Case I (i)
298
Basic Cost of Labour, Material & Machinery (a+b+c) for 58485.00
15 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 22224.30
e) Overhead charges @ 10 % on (a+b+c+d) 8070.93
f) Contractor's profit @ 10 % on (a+b+c+d+e) 8878.02
Cost for 15 cum = a+b+c+d+e+f 97658.25
Rate per cum = (a+b+c+d+e+f)/15 6510.55
say 6511.00
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 58485.00
15 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 28072.80
e) Overhead charges @ 10 % on (a+b+c+d) 8655.78
f) Contractor's profit @ 10 % on (a+b+c+d+e) 9521.36
Cost for 15 cum = a+b+c+d+e+f 104734.94
Rate per cum = (a+b+c+d+e+f)/15 6982.33
say 6982.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 58485.00
15 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 33921.30
e) Overhead charges @ 10 % on (a+b+c+d) 9240.63
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10164.69
Cost for 15 cum = a+b+c+d+e+f 111811.62
Rate per cum = (a+b+c+d+e+f)/15 7454.11
say 7454.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 5600.00 283584.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
b) Labour
Mate day 0.88 300.00 264.00 L-12
Mason day 3.00 350.00 1050.00 L-11
Mazdoor day 19.00 225.00 4275.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 424488.00
for 120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 76407.84
e) Overhead charges @ 10 % on (a+b+c+d) 50089.58
299
f) Contractor's profit @ 10 % on (a+b+c+d+e) 55098.54
Cost for 120 cum = a+b+c+d+e+f 606083.97
Rate per cum = (a+b+c+d+e+f)/120 5050.70
say 5051.00
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 97632.24
e) Overhead charges @ 10 % on (a+b+c+d) 52212.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 57433.23
Cost for 120 cum = a+b+c+d+e+f 631765.49
Rate per cum = (a+b+c+d+e+f)/120 5264.71
say 5265.00
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 118856.64
e) Overhead charges @ 10 % on (a+b+c+d) 54334.46
f) Contractor's profit @ 10 % on (a+b+c+d+e) 59767.91
Cost for 120 cum = a+b+c+d+e+f 657447.01
Rate per cum = (a+b+c+d+e+f)/120 5478.73
say 5479.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 97632.24
e) Overhead charges @ 10 % on (a+b+c+d) 52212.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 57433.23
Cost for 120 cum = a+b+c+d+e+f 631765.49
Rate per cum = (a+b+c+d+e+f)/120 5264.71
say 5265.00
14.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 118856.64
e) Overhead charges @ 10 % on (a+b+c+d) 54334.46
f) Contractor's profit @ 10 % on (a+b+c+d+e) 59767.91
Cost for 120 cum = a+b+c+d+e+f 657447.01
Rate per cum = (a+b+c+d+e+f)/120 5478.73
say 5479.00
14.1D (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 140081.04
e) Overhead charges @ 10 % on (a+b+c+d) 56456.90
f) Contractor's profit @ 10 % on (a+b+c+d+e) 62102.59
Cost for 120 cum = a+b+c+d+e+f 683128.54
Rate per cum = (a+b+c+d+e+f)/120 5692.74
say 5693.00
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent
Case II of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
300
d) Formwork and staging 38 per cent of (a+b+c) 38.00 161305.44
e) Overhead charges @ 10 % on (a+b+c+d) 58579.34
f) Contractor's profit @ 10 % on (a+b+c+d+e) 64437.28
Cost for 120 cum = a+b+c+d+e+f 708810.06
Rate per cum = (a+b+c+d+e+f)/120 5906.75
say 5907.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 203754.24
e) Overhead charges @ 10 % on (a+b+c+d) 62824.22
f) Contractor's profit @ 10 % on (a+b+c+d+e) 69106.65
Cost for 120 cum = a+b+c+d+e+f 760173.11
Rate per cum = (a+b+c+d+e+f)/120 6334.78
say 6335.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 424488.00
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 246203.04
e) Overhead charges @ 10 % on (a+b+c+d) 67069.10
f) Contractor's profit @ 10 % on (a+b+c+d+e) 73776.01
Cost for 120 cum = a+b+c+d+e+f 811536.16
Rate per cum = (a+b+c+d+e+f)/120 6762.80
say 6763.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 5600.00 36120.00 M-081
Coarse sand cum 6.75 683.00 4610.25 M-005
20 mm Aggregate cum 8.10 680.00 5508.00 M-053
10 mm Aggregate cum 5.40 670.00 3618.00 M-051
Admixture @ 0.4 per cent of cement kg 25.80 65.00 1677.00 M-180
b) Labour
Mate day 0.96 300.00 288.00 L-12
Mason day 2.00 350.00 700.00 L-11
Mazdoor day 22.00 225.00 4950.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 130.00 780.00 P&M-009
Generator 33 KVA hour 6.00 500.00 3000.00 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) 61252.00
for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 61252.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 12250.40
e) Overhead charges @ 10 % on (a+b+c+d) 7350.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 8085.26
Cost for 15 cum = a+b+c+d+e+f 88937.90
Rate per cum = (a+b+c+d+e+f)/15 5929.19
say 5929.00
14.1E (q) Height 5m to 10m
Case I (i)
301
Basic Cost of Labour, Material & Machinery (a+b+c) for 61252.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 15313.00
e) Overhead charges @ 10 % on (a+b+c+d) 7656.50
f) Contractor's profit @ 10 % on (a+b+c+d+e) 8422.15
Cost for 15 cum = a+b+c+d+e+f 92643.65
Rate per cum = (a+b+c+d+e+f)/15 6176.24
say 6176.00
14.1E (r) Height above 10m
Case I (i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 5600.00 288960.00 M-081
Coarse sand cum 54.00 240.00 12960.00 M-004
20 mm Aggregate cum 64.80 680.00 44064.00 M-053
10 mm Aggregate cum 43.20 670.00 28944.00 M-051
Admixture @ 0.4 per cent of cement kg 206.40 65.00 13416.00 M-180
b) Labour
302
Mate day 0.94 300.00 282.00 L-12
Mason day 3.50 350.00 1225.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 443698.00
120 cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 443698.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 79865.64
e) Overhead charges @ 10 % on (a+b+c+d) 52356.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 57592.00
Cost for 15 cum = a+b+c+d+e+f 633512.00
Rate per cum = (a+b+c+d+e+f)/120 5279.27
say 5279.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 443698.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 102050.54
e) Overhead charges @ 10 % on (a+b+c+d) 54574.85
f) Contractor's profit @ 10 % on (a+b+c+d+e) 60032.34
Cost for 120 cum = a+b+c+d+e+f 660355.73
Rate per cum = (a+b+c+d+e+f)/120 5502.96
say 5503.00
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 443698.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 124235.44
e) Overhead charges @ 10 % on (a+b+c+d) 56793.34
f) Contractor's profit @ 10 % on (a+b+c+d+e) 62472.68
Cost for 120 cum = a+b+c+d+e+f 687199.46
Rate per cum = (a+b+c+d+e+f)/120 5726.66
say 5727.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 443698.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 102050.54
e) Overhead charges @ 10 % on (a+b+c+d) 54574.85
f) Contractor's profit @ 10 % on (a+b+c+d+e) 60032.34
Cost for 120 cum = a+b+c+d+e+f 660355.73
Rate per cum = (a+b+c+d+e+f)/120 5502.96
say 5503.00
14.1E (q) Height 5m to 10m
Case II
(ii)
303
Basic Cost of Labour, Material & Machinery (a+b+c) for 443698.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 124235.44
e) Overhead charges @ 10 % on (a+b+c+d) 56793.34
f) Contractor's profit @ 10 % on (a+b+c+d+e) 62472.68
Cost for 120 cum = a+b+c+d+e+f 687199.46
Rate per cum = (a+b+c+d+e+f)/120 5726.66
say 5727.00
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 443698.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 146420.34
e) Overhead charges @ 10 % on (a+b+c+d) 59011.83
f) Contractor's profit @ 10 % on (a+b+c+d+e) 64913.02
Cost for 120 cum = a+b+c+d+e+f 714043.19
Rate per cum = (a+b+c+d+e+f)/120 5950.36
say 5950.00
14.1E (iii) For cast-in-situ box girder, segment construction and
Case II balanced cantilever, 38-58 per cent of cost of concrete.
304
b) Labour
Mate day 0.94 300.00 282.00 L-12
Mason day 3.50 350.00 1225.00 L-11
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 468310.00
for 120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-26 per
cent of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 468310.00
120 cum
d) Formwork and staging 16 per cent of (a+b+c) 16.00 74929.60
e) Overhead charges @ 10 % on (a+b+c+d) 54323.96
f) Contractor's profit @ 10 % on (a+b+c+d+e) 59756.36
Cost for 120 cum = a+b+c+d+e+f 657319.92
Rate per cum = (a+b+c+d+e+f)/120 5477.67
say 5478.00
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 468310.00
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 98345.10
e) Overhead charges @ 10 % on (a+b+c+d) 56665.51
f) Contractor's profit @ 10 % on (a+b+c+d+e) 62332.06
Cost for 120 cum = a+b+c+d+e+f 685652.67
Rate per cum = (a+b+c+d+e+f)/120 5713.77
say 5714.00
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 468310.00
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 121760.60
e) Overhead charges @ 10 % on (a+b+c+d) 59007.06
f) Contractor's profit @ 10 % on (a+b+c+d+e) 64907.77
Cost for 120 cum = a+b+c+d+e+f 713985.43
Rate per cum = (a+b+c+d+e+f)/120 5949.88
say 5950.00
14.1F (ii) For T-beam & slab including launching of precast
girders by launching truss upto 40 m span, 21-31 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 468310.00
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 98345.10
e) Overhead charges @ 10 % on (a+b+c+d) 56665.51
f) Contractor's profit @ 10 % on (a+b+c+d+e) 62332.06
Cost for 120 cum = a+b+c+d+e+f 685652.67
Rate per cum = (a+b+c+d+e+f)/120 5713.77
say 5714.00
14.1F (q) Height 5m to 10m
(ii)
305
Basic Cost of Labour, Material & Machinery (a+b+c) for 468310.00
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 121760.60
e) Overhead charges @ 10 % on (a+b+c+d) 59007.06
f) Contractor's profit @ 10 % on (a+b+c+d+e) 64907.77
Cost for 120 cum = a+b+c+d+e+f 713985.43
Rate per cum = (a+b+c+d+e+f)/120 5949.88
say 5950.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 468310.00
120 cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 145176.10
e) Overhead charges @ 10 % on (a+b+c+d) 61348.61
f) Contractor's profit @ 10 % on (a+b+c+d+e) 67483.47
Cost for 120 cum = a+b+c+d+e+f 742318.18
Rate per cum = (a+b+c+d+e+f)/120 6185.98
say 6186.00
14.1F (iii) For cast-in-situ box girder, segmental construction and
balanced cantilever, 36-56 per cent of cost of concrete.
306
Mazdoor day 20.00 225.00 4500.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2109.00 12654.00 P&M-002
Generator 100 KVA hour 6.00 743.00 4458.00 P&M-080
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 485890.00
for 120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete
307
Loader hour 6.00 770.00 4620.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 813.00 12195.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer [Link] 300L 2.00 12000.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 570.00 3420.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 513432.00
for 120 cum
For formwork and staging add the following:
14.1H (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete
308
b) Labour for cutting, bending, tying and placing in
position
Mate day 0.44 300.00 132.00 L-12
Blacksmith day 3.00 350.00 1050.00 L-02
Mazdoor day 8.00 225.00 1800.00 L-13
Basic Cost of Labour & Material (a+b) 56932.00
c) Overhead charges @ 10 % on (a+b) 5693.20
d) Contractor's profit @ 10 % on (a+b+c) 6262.52
Rate per MT = a+b+c+d 68887.72
say 68888.00
14.3 1800 High tensile steel wires/strands including all
accessories for stressing, stressing operations and
grouting complete as per drawing and Technical
Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight =
0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for tonne 0.39 59400.00 22869.00 M-119
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra metre 42.00 323.00 13566.00 M-165
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, each 2.00 1277.00 2554.00 M-187
permanent wedges etc
Cement for grouting including 3 per cent wastage @ tonne 0.125 5600.00 700.00 M-081
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)
309
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.15 225.00 33.75 L-13
c) Overhead charges @ 10 % on (a+b) 695.37
d) Contractor's profit @ 10 % on (a+b+c) 764.90
Rate per cum (a+b+c+d) 8413.92
say 8414.00
14.5 515 & Mastic Asphalt
2702
Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum
per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100 deg.
C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 300.00 147.00 L-12
Mazdoor day 11.00 225.00 2475.00 L-13
Mazdoor (Skilled) day 1.25 250.00 312.50 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 184.00 11.04 P&M-031
Air compressor 250 cfm hour 0.06 271.00 16.26 P&M-001
Mastic cooker 1 tonne capacity hour 6.00 48.00 288.00 P&M-030
Bitumen boiler 1500 litres capacity hour 6.00 224.00 1344.00 P&M-005
Tractor for towing and positioning of mastic cooker and hour 1.00 193.00 193.00 P&M-053
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with
coarse aggregates (based on mix design done by CRRI for a
specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent tonne 0.204 49100.00 10016.40 M-074
by weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of cum 0.39 308.00 120.12 M-021
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 =
0.39
iii) Lime stone dust filler with calcium carbonate tonne 0.36 3885.00 1398.60 M-188
content not less than 80 per cent by weight @ 17.92
per cent by weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 cum 0.55 670.00 368.50 M-051
per cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size for cum 0.036 1149.00 41.36 M-142
skid resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by kg 1.05 49.10 51.56 M-
weight = 0.036 x 1.456 x 2/100 = 0.001048MT = 074/1000
1.05kg
d) Overhead charges @ 10 % on (a+b+c) 1678.33
e) Contractor's profit @ 10 % on (a+b+c+d) 1846.17
Cost for 72.46 sqm = a+b+c+d+e 20307.84
Rate per sqm = (a+b+c+d+e)/72.46 280.26
say 280.00
Note [Link] rates for 6 mm or any other thickness may be worked
out on pro-rata basis.
310
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
[Link] quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
[Link] rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
[Link] quantity of bitumen works out 17 per cent of the
mastic asphalt blocks without aggregates and falls within the
standards laid down by MoRTH Specifications.
14.6 2703, Construction of precast RCC railing of M30 Grade,
1500, aggregate size not exceeding 12 mm, true to line and
1600 & grade, tolerance of vertical RCC post not to exceed 1 in
1700 500, centre to centre spacing between vertical post not
to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.09 3452.00 14125.58 Item
concrete in Item 14.1(C) by using batching plant, 14.1(C)
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Add 5 per cent of above cost for form work for casting 706.28
in casting yard.
HYSD bar reinforcement Rate as per item No tonne 0.87 56932.00 49246.18 Item 14.2 A
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of 3203.90
precast panels in position
b) Overhead charges @ 10 % on (a) 6728.19
c) Contractor's profit @ 10 % on (a+b) 7401.01
Rate for 48 m (a+b+c) 81411.15
Rate per metre (a+b+c)/48 1696.07
say 1696.00
Note [Link] of material have been adopted from standard
plans of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of
24 m span.
14.7 2703, Construction of RCC railing of M30 Grade in-situ with 20
1500, mm nominal size aggregate, true to line and grade,
1600 & tolerance of vertical RCC post not to exceed 1 in 500,
1700 centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 3452.00 14125.58 Item
concrete in Item 14.1(C) by using batching plant, 14.1(C)
excluding formwork i.e. per cum basic cost (a+b+c)
311
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 51520.00 151777.92 M-179
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 51520.00 52138.24 M-179
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 51520.00 9273.60 M-179
4) MS bolts, nuts and washers tonne 0.15 65000.00 9750.00 M-
130*1000
Add @ 5 per cent of cost of material for painting one 11146.99
shop coat with red oxide primer and three coats of
synthetic enamel paint and consumables to safeguard
against weathering and corrosion.
Add for cost of concrete for fixing vertical posts in the 2229.40
performed recess @ 1 per cent of cost of material.
Add for electricity charges, welding and drilling 2229.40
equipment, electrodes and other consumables @ 1 per
cent of cost of material.
b) Labour
Mate day 2.80 300.00 840.00 L-12
Mazdoor (Skilled) day 30.00 250.00 7500.00 L-15
Mazdoor day 40.00 225.00 9000.00 L-13
c) Overhead charges @ 10 % on (a+b) 25588.55
d) Contractor's profit @ 10 % on (a+b+c) 28147.41
Cost for 100 m steel railing = a+b+c+d 309621.51
Rate per metre (a+b+c+d)/100 3096.22
say 3096.00
14.9 2705 Drainage Spouts complete as per drawing and Technical
specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per cent Kg 4.00 50.82 203.28 M-
wastage 087/1000
GI pipe 100mm dia metre 6.00 22.00 132.00 M-056
GI bolt 10 mm Dia each 6.00 13.00 78.00 M-110
Galvanised MS flat clamp each 2.00 330.00 660.00 M-101
b) Labour
For fabrication
Mate day 0.02 300.00 6.00 L-12
Skilled (Blacksmith, welder etc.) day 0.02 350.00 7.00 L-02
Mazdoor day 0.02 225.00 4.50 L-13
312
For fixing in position
Mate day 0.01 300.00 3.00 L-12
Mason day 0.01 350.00 3.50 L-11
Mazdoor day 0.20 225.00 45.00 L-13
Add @ 5 per cent of cost of material and labour for 57.11
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
c) Overhead charges @ 10 % on (a+b) 119.94
d) Contractor's profit @ 10 % on (a+b+c) 131.93
Rate per metre (a+b+c+d) 1451.27
say 1451.00
Note 1. In case of viaducts in urban areas, the drainage spouts
should be connected with suitably located pipelines to
discharge the surface run-off to drains provided at ground
level.
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 3730.00 3730.00 Item 12.8
formworks (A)
Rate per cum say 3730.00
14.11 1500,16 Reinforced cement concrete approach slab including
00,1700 reinforcement and formwork complete as per drawing
& 2704 and Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.00 3450.00 3450.00 Item 12.8
concrete in item 12.8(G)by using batching plant, (G)
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
HYSD bar reinforcement Rate as per item No tonne 0.05 56932.00 2846.60 Item 14.2 A
14.2(Excluding OH & CP)
b) Overhead charges @ 10 % on (a) 636.56
c) Contractor's profit @ 10 % on(a+b) 700.22
Rate per cum (a+b+c) 7702.38
say 7702.00
Note The grade of reinforced cement concrete may be adopted as
M30 for severe conditions and M25 for moderate conditions.
313
Providing, precasting, transportation and placing in
position precast pretensioned concrete girders as per
drawing and technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Cement tonne 0.47 5600.00 2632.00 M-081
Coarse sand cum 0.45 240.00 108.00 M-004
20 mm Aggregate cum 0.54 680.00 367.20 M-053
10 mm Aggregate cum 0.36 670.00 241.20 M-051
Admixture @ 0.4 per cent of cement Kg 1.88 65.00 122.20 M-180
HYSD steel . tonne 0.10 51000.00 5100.00 M-082
HT strand with 5 per cent as wastage and extra length tonne 0.06 59400.00 3564.00 M-119
for anchoring
LDO for steam curing Litre 37.00 37.00 1369.00 M-122
Add consumables such as binding wire, foam, packing 135.04
tape, shuttering oil, HDPE pipe for unbonding of
strand, bolt & nuts etc @ 1 per cent of material cost
b) Labour
(i) Cutting, bending, making reinforcement cage, placing
in position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete
including laps and wastage
Mate day 0.06 300.00 18.00 L-12
Mazdoor (Skilled) day 0.35 250.00 87.50 L-15
Mazdoor day 1.40 225.00 315.00 L-13
(ii) Cable cutting and threading in position including
binding by insulation tape with HDPE pipes etc.,
prestessing and cutting of extra length of HT strand
after de-stressing.
314
Transit Mixer 4 cum capacity hour 0.10 813.00 81.30 P&M-049
Concrete Pump stationary hour 0.05 570.00 28.50 P&M-007
Crane 35 tonne capacity hour 0.10 659.00 65.90 P&M-012
Trailor 30 tonne capacity hour 0.10 375.00 37.50 P&M-089
Loader hour 0.05 770.00 38.50 P&M-017
ii) For transportation and placement at site
Crane 35 tonne capacity hour 0.15 659.00 98.85 P&M-012
Trailer 30 tonne capacity for transporting to site. [Link] 2.5xL 372.00 18600.00 Lead =20
km & P&M-
090
(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 0.15 375.00 56.25 P&M-089
Cost of formwork, steam curing arrangement, 785.62
pretensioning arrangement etc @ 5 per cent of cost
material, labour and machinery
d) Overhead charges @ 10 % on (a+b+c) 3525.32
e) Contractor's profit @ 10 % on (a+b+c+d) 3877.85
Rate per cum = (a+b+c+d+e) 42656.32
say 42656.00
14.14 1700 & Providing and fixing Helical pipes in voided concrete
1800 slabs
Unit = 1 RM
Taking output = 1 RM
a) Material
Helical pipes 600mm diameter metre 1.00 990.00 990.00 M-117
Tie rods 20mm diameter each 1.00 303.00 303.00 M-183
Consumables for sealing joints etc.@ 5 per cent of cost of 64.65
material
b) Labour
Mate day 0.01 300.00 3.00 L-12
Fitter day 0.05 350.00 17.50 L-08
Mazdoor day 0.20 225.00 45.00 L-13
c) Overhead charges @ 10 % on (a+b) 142.32
d) Contractor's profit @ 10 % on (a+b+c) 156.55
Rate per Rm (a+b+c+d) 1722.01
say 1722.00
14.15 800 Crash Barriers
The rate analysis for rigid crash barrier in reinforced cement
concrete, semi-rigid crash barrier with metal beam and
flexible crash barrier with wire ropes have been made and
included in chapter-8 on Traffic and Transportation.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 300.00 3.00 L-12
Painter day 0.25 350.00 87.50 L-18
Mazdoor (Skilled) day 0.25 250.00 62.50 L-15
b) Material
Water based paint of approved quality for cement Litres 5.00 39.00 195.00 M-190
concrete surface
c) Overhead charges @ 10 % on (a+b) 34.80
d) Contractor's profit @ 10 % on (a+b+c) 38.28
Cost for 10 sqm (a+b+c+d) 421.08
Rate per sqm (a+b+c+d)/10 42.11
say 42.00
315
14.17 2604 Burried Joint
Providing and laying a burried expansion joint,
expansion gap being 20 mm, covered with 12 mm thick,
200 mm wide galvanised weldable structural steel plate
as per IS: 2062, placed symmetrical to centre line of the
joint, resting freely over the top surface of the deck
concrete, welding of 8 mm dia. 100 mm long galvanised
nails spaced 300 mm c/c along the centre line of the
plate, all as specified in clause 2604.
316
20 mm thick compressible fibre board 12 m long x 25 sqm 3.00 500.00 1500.00 M-084
cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 10 % on (a+b) 154.99
d) Contractor's profit @ 10 % on (a+b+c) 170.49
Cost for 12 m = (a+b+c+d) 1875.38
Rate per m = (a+b+c+d)/12 156.28
say 156.00
14.18 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed ends
of simply supported spans not exceeding 10 m to cater
for a horizontal movement upto 20 mm, covered with
sealant complete as per drawing and technical
specifications.
317
Providing and laying of asphaltic plug joint to provide
for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75 mm
to 100 mm, width varying from 500 mm to 750 mm (in
traffic direction), covered with a closure plate of 200mm
x 6mm of weldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder, carefully selected single size aggregate
of 12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings and
specifications.
318
Cost for 12 m = (a+b+c+d) 162906.66
Rate per m = (a+b+c+d)/12 13575.55
say 13576.00
14.21 2600 Compression Seal Joint
Providing and laying of compression seal joint
consisting of steel armoured nosing at two edges of the
joint gap suitably anchored to the deck concrete and a
preformed chloroprene elastomer or closed cell foam
joint sealer compressed and fixed into the joint gap with
special adhesive binder to cater for a horizontal
movement upto 40 mm and vertical movement of 3 mm.
Add 5 per cent of cost of above for structural steel for 1237.54
anchorage, welding and other incidentals.
Preformed continuous chloroprene elastomer or closed metre 12.00 185.00 2220.00 M-143
cell foam sealing element with high tear strength,
vulcanised in a single operation for the full length of a
joint to ensure water tightness.
319
d) Contractor's profit @ 10 % on (a+b+c) 12420.23
Cost for 12 m = (a+b+c+d) 136622.58
Rate per m = (a+b+c+d)/12 11385.22
say 11385.00
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
320
Supply of a modular box/box seal joint assembly metre 12.00 10304.00 123648.00 M-128
containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system, all
steel sections protected against corrosion and installed
by the manufacturer or his authorised representative.
321
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x sqm 22.00 244.00 5368.00 M-102
100 mm.
Stone cum 5.63 526.00 2961.38 M-003
Stone Spalls cum 1.13 300.00 339.00 M-008
b) Labour
Mate day 0.18 300.00 54.00 L-12
Mazdoor (Skilled) day 1.50 250.00 375.00 L-15
Mazdoor day *3.00 225.00 675.0 L-13
c) Overhead charges @ 10 % on (a+b) 977.2
d) Contractor's profit @ 10 % on (a+b+c) 1074.96
Cost for 5.63 cum = a+b+c+d 11824.58
Rate per cum = (a+b+c+d)/5.63 2100.28
say 2100.00
* Including excavation for trimming for preparation of bed.
Note Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 3879.00 3879.00 Item 12.8
including OH & CP (A)
Add 2 per cent of cost to account for excavation for 77.58
preparation of bed, nominal surface reinforcement and
filling of granular material in recesses between blocks.
322
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
15.4 2504 Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing
and Technical specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 526.00 526.00 M-003
Stone spalls of minimum 25 mm size cum 0.20 300.00 60.00 M-008
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mason day 0.35 350.00 122.50 L-11
Mazdoor day 0.75 225.00 168.75 L-13
c) Overhead charges @ 10 % on (a+b) 88.93
d) Contractor's profit @ 10 % on (a+b+c) 97.82
Rate per cum = (a+b+c+d) 1075.99
say 1076.00
15.4 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in
cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 3879.00 3879.00 Item 12.8
(A)
Add 2 per cent of cost to account for nominal surface 77.58
reinforcement and filling of granular material in
recesses between blocks.
Rate per cum 3956.58
say 3957.00
15.5 2504 Providing and laying Filter material underneath pitching
in slopes complete as per drawing and Technical
specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 300.00 360.00 M-012
b) Labour
Mate day 0.05 300.00 15.00 L-12
Mazdoor (Skilled) day 0.25 250.00 62.50 L-15
Mazdoor * day 1.00 225.00 225.00 L-13
c) Overhead charges @ 10 % on (a+b) 66.25
d) Contractor's profit @ 10 % on (a+b+c) 72.88
Rate per cum = (a+b+c+d) 801.63
say 802.00
Includes Mazdoor required for trimming of slope to proper
profile and preparation of bed.
15.6 700 & Geotextile Filter
2504
Laying of a geotextile filter between pitching and
embankment slopes on which pitching is laid to prevent
escape of the embankment material through the voids of the
stone pitching/cement concrete blocks as well as to allow
free movement of water without creating any uplift head on
the pitching.
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.02 300.00 6.00 L-12
Mazdoor day 0.30 225.00 67.50 L-13
Mazdoor (Skilled) day 0.10 250.00 25.00 L-15
b) Material
Permeable synthetic geotextile including 5 per cent for sqm 11.00 389.00 4279.00 M-181
overlap and wastage
323
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
c) Overhead charges @ 10 % on (a+b) 437.75
d) Contractor's profit @ 10 % on (a+b+c) 481.53
Cost for 10 sqm = a+b+c+d 5296.78
Rate per sqm = (a+b+c+d)/10 529.68
say 530.00
15.7 2504.4 Toe protection
A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal mix if
cement concert block have been used for pitching . Rates for
toe wall can be adopted from respective clauses depending
upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been
analysed and given in respective chapters.
324
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
b) Labour
Mate day 0.10 300.00 30.00 L-12
Mason day 0.50 350.00 175.00 L-11
mazdoor day 1.50 225.00 337.50 L-13
Add 1 per cent of (b) for trimming and preparation of 5.43
base.
c) Overhead charges @ 10 % on (a+b) 113.39
d) Contractor's profit @ 10 % on (a+b+c) 124.73
Rate per cum = (a+b+c+d) 1372.05
say 1372.00
15.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1.00 3899.00 3899.00 Item 12.7
(A )
Rate same as per item No. 12.7 (A) including OH & CP
Rate per cum say 3899.00
or
15.10 B Cement concrete Grade M15
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 3879.00 3879.00 Item 12.8
including OH & CP (A)
Rate per cum say 3879.00
Note Other items like excavation for foundation, filling behind wall,
filter media, weep holes etc. shall be added separately as
per approved design.
15.11 2507.2 Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less
than 40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 526.00 526.00 M-003
Stone Spalls cum 0.20 300.00 60.00 M-008
b) Labour
Mate day 0.05 300.00 15.00 L-12
Mason day 0.25 350.00 87.50 L-11
Mazdoor day 1.00 225.00 225.00 L-13
Add 1 per cent of cost of (a+b) for trimming and 9.14
preparation of bed.
c) Overhead charges @ 10 % on (a+b) 92.26
d) Contractor's profit @ 10 % on (a+b+c) 101.49
Rate per cum = (a+b+c+d) 1116.39
say 1116.00
15.12 2503.3 Gabian Structure for Retaining Earth
Providing and construction of a gabian structure for retaining
earth with segments of wire crates of size 7 m x 3 m x 0.6 m
each divided into 1.5 m compartments by cross netting,
made from 4 mm galvanised steel wire @ 32 kg per 10 sqm
having minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826,
woven into mesh with double twist, mesh size not exceeding
100 x 100 mm, filled with boulders with least dimension of
200 mm, all loose ends to be tied with 4 mm galvanised
steel wire
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 300.00 84.00 L-12
Mazdoor day 5.00 225.00 1125.00 L-13
Mazdoor (Skilled) day 2.00 250.00 500.00 L-15
b) Material
325
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Galvanised steel wire crates of mesh size 100 mm x sqm 61.00 244.00 14884.00 M-102
100 mm woven with 4mm dia. GI wire in rolls of
required size.
Stone boulders with least dimension of 200 mm cum 12.60 526.00 6627.60 M-003
Stone spalls of minimum size 25 mm cum 2.52 300.00 756.00 M-008
c) Overhead charges @ 10 % on (a+b) 2397.66
d) Contractor's profit @ 10 % on (a+b+c) 2637.43
Cost for 12.60 cum (a+b+c+d) 29011.69
Rate per cum (a+b+c+d)/12.60 2302.51
say 2303.00
Note Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.14 300.00 42.00 L-12
Mazdoor day 2.50 225.00 562.50 L-13
Mazdoor (Skilled) day 1.00 250.00 250.00 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x sqm 65.00 244.00 15860.00 M-102
100 mm woven with 4mm dia. GI wire in rolls of
required size to cover 6.00 cum.
Stone boulders with least dimension of 200 mm cum 6.00 526.00 3156.00 M-003
Stone spalls of minimum size 25 mm cum 1.20 300.00 360.00 M-008
c) Overhead charges @ 10 % on (a+b) 2023.05
d) Contractor's profit @ 10 % on (a+b+c) 2225.36
Cost for 6.00 cum (a+b+c+d) 24478.91
Rate per cum (a+b+c+d)/6.00 4079.82
say 4080.00
Note Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
326
CHAPTER-16
REPAIR AND REHABILITATION
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
16.1 2809 Removal of existing cement concrete wearing coat
including its disposal complete as per Technical
Specification without causing any detrimental effect to
any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000 m
Unit = Sq m
Taking output = 2.5 sqm
a) Labour
Mate day 0.03 300.00 9.00 L-12
Mazdoor day 0.75 225.00 168.75 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic breaker. hour 0.75 271.00 203.25 P&M-001
Tractor-trolley. hour 0.40 193.00 77.20 P&M-053
c) Overhead charges @ 10 % on (a+b) 45.82
d) Contractor's profit @ 10 % on (a+b+c) 50.40
Cost for 2.5 sqm = (a+d+c+d) 554.42
Rate per sqm = (a+b+c+d)/2.5 221.77
say 222.00
16.3 2807 Guniting concrete surface with cement mortar applied
with compressor after cleaning surface and spraying
with epoxy complete as per Technical Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 5.60 89.60 M-
081/1000
Graded sand cum 0.04 683.00 27.32 M-005
Wire mesh 50mm x 50mm size of 3mm wire kg 2.00 168.00 336.00 M-192
Epoxy kg 0.67 880.00 589.60 M-095
Accelerator compound for guniting @ 4 per cent of kg 0.64 65.00 41.60 M-180
weight of cement
Add 2 per cent of cost of material for miscellaneous 21.68
consumables like nozzles, wire brush, cotton waste
etc.
b) Labour
Mate day 0.01 300.00 3.00 L-12
Mason day 0.04 350.00 14.00 L-11
Mazdoor day 0.14 225.00 31.50 L-13
c) Machinery
Compressor with guniting equipment along with hour 0.10 313.00 31.30 P&M-076
accessories
d) Overhead charges @ 10 % on (a+b+c) 118.56
e) Contractor's profit @ 10 % on (a+b+c+d) 130.42
Rate per sqm = (a+b+c+d+e) 1434.58
say 1435.00
327
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
16.4 2800 Providing and inserting nipples with approved fixing
compound after drilling holes for grouting as per
Technical Specifications including subsequent
cutting/removal and sealing of the hole as necessary of
nipples after completion of grouting with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 25.00 25.00 M-129
Cement, fixing compound and consumables @ 15 per 3.75
cent of cost of nipple
b) Labour
Mate day 0.01 300.00 3.00 L-12
Mazdoor (Skilled) labour for drilling day 0.08 250.00 20.00 L-15
Mazdoor (Skilled) labour for fixing nipple and sealing day 0.08 250.00 20.00 L-15
inlets
Mazdoor for cutting and removing of nipples day 0.04 225.00 9.00 L-13
Add 10 per cent of labour cost for drilling holes etc 5.20
c) Overhead charges @ 10 % on (a+b) 8.60
d) Contractor's profit @ 10 % on (a+b+c) 9.45
Rate per No. = (a+b+c+d) 104.00
say 104.00
16.5 2806 Sealing of cracks/porous concrete by injection process
through nipples/Grouting complete as per Technical
Specification.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.10 5.60 6.16 M-
081/1000
Admixtures (anti shrinkage compound) @ 20 per 1.23
cent of cost of cement
b) Labour
Mate day 0.08 300.00 24.00 L-12
Mazdoor (Skilled) day 0.10 250.00 25.00 L-15
Mazdoor day 0.10 225.00 22.50 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 336.00 33.60 M-111
d) Overhead charges @ 10 % on (a+b+c) 11.25
e) Contractor's profit @ 10 % on (a+b+c+d) 12.37
Rate per kg = (a+b+c+d+e) 136.12
say 136.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 0.55 5.60 3.08 M-
081/1000
Sand including 10 per cent wastage kg 0.55 0.46 0.25 M-
005/1500
Admixtures (anti shrinkage compound) @ 20 per 0.62
cent of cost of cement
b) Labour
Mate day 0.08 300.00 24.00 L-12
Mazdoor (Skilled) day 0.10 250.00 25.00 L-15
Mazdoor day 0.10 225.00 22.50 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 336.00 33.60 M-111
d) Overhead charges @ 10 % on (a+b+c) 10.90
328
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
e) Contractor's profit @ 10 % on (a+b+c+d) 12.00
Rate per kg = (a+b+c+d+e) 131.95
say 132.00
16.6 2800 Patching of damaged concrete surface with polymer
concrete and curing compounds, initiator and promoter,
available in present formulations, to be applied as per
instructions of manufacturer and as approved by the
Engineer.
Unit = sqm
Taking output = 10 sqm for an average thickness of
25mm.
a) Labour
Mate day 0.06 300.00 18.00 L-12
Mazdoor (Skilled) day 0.75 250.00 187.50 L-15
Mazdoor day 0.75 225.00 168.75 L-13
b) Material
Pre-packed polymer concrete based on epoxy system kg 315.00 380.00 119700.00 M-145
complete with curing compound, intiator and promoter
including 5 per cent wastage.
c) Machinery
Grout pump with agitator and accessories hour 2.00 336.00 672.00 M-111
d) Overhead charges @ 10 % on (a+b+c) 12074.63
e) Contractor's profit @ 10 % on (a+b+c+d) 13282.09
Cost for 10 sqm = a+b+c+d+e 146102.96
Rate per sqm = (a+b+c+d+e)/10 14610.30
say 14610.00
Note This item is a proprietory item available in market as pre-
packed polymer concrete and is required to be applied as
per instructions of the manufacturer.
16.7 2803 Sealing of crack / porous concrete with Epoxy Grout by
injection through nipples complete as per clause 2803.1.
Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage kg 1.10 880.00 968.00 M-095
b) Labour
Mate day 0.08 300.00 24.00 L-12
Mazdoor (Skilled) day 0.10 250.00 25.00 L-15
Mazdoor day 0.10 225.00 22.50 L-13
c) Machinery
Epoxy Injection gun hour 0.10 248.00 24.80 P&M-078
d) Overhead charges @ 10 % on (a+b+c) 106.43
e) Contractor's profit @ 10 % on (a+b+c+d) 117.07
Rate per kg = (a+b+c+d+e) 1287.80
say 1288.00
16.8 2804 Applying epoxy mortar over leached, honey combed and
spalled concrete surface and exposed steel
reinforcement complete as per Technical Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat kg 2.50 555.00 1387.50 M-098
Epoxy mortar kg 2.20 336.00 739.20 M-096
Epoxy resin -hardener mix for seal coat. kg 2.00 555.00 1110.00 M-098
Add 3 per cent cost of material for other consumables 97.10
like acetone etc and to cover wastage.
b) Labour
329
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.04 300.00 12.00 L-12
Mazdoor (Skilled) day 0.50 250.00 125.00 L-15
Mazdoor day 0.50 225.00 112.50 L-13
c) Overhead charges @ 10 % on (a+b) 358.33
d) Contractor's profit @ 10 % on (a+b+c) 394.16
Cost for 10 sqm = a+b+c+d 4335.79
Rate per sqm = (a+b+c+d)/10 433.58
say 434.00
16.9 2807 Removal of defective concrete, cleaning the surface
thoroughly, applying the shotcrete mixture mechanically
with compressed air under pressure, comprising of
cement, sand, coarse aggregates, water and quick
setting compound in the proportion as per clause
2807.1., sand and coarse aggregates conforming to IS:
383 and table 1 of IS: 9012 respectively, water cement
ratio ranging from 0.35 to 0.50, density of gunite not less
than 2000 kg/cum, strength not less than 25 Mpa and
workmanship conforming to clause 2807.6.
unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate day 0.04 300.00 12.00 L-12
Mazdoor day 0.50 225.00 112.50 L-13
Mazdoor (Skilled) day 0.50 250.00 125.00 L-15
b) Machinery
Air compressor 250 cfm hour 1.00 271.00 271.00 P&M-001
Shotcreteing equipment hour 1.00 313.00 313.00 P&M-076
water tanker 6 KL capacity hour 0.02 130.00 2.60 P&M-060
c) Material
Cement kg 120.00 5.60 672.00 M-
081/1000
Sand cum 0.15 683.00 102.45 M-005
Coarse aggregate of size 4.75mm cum 0.15 358.00 53.70 M-024
Quick setting compound kg 2.50 25.00 62.50 M-147
Water KL 0.10 64.00 6.40 M-189
d) Overhead charges @ 10 % on (a+b+c) 173.32
e) Contractor's profit @ 10 % on (a+b+c+d) 190.65
Cost for 10 sqm = a+b+c+d+e 2097.11
Rate per sqm = (a+b+c+d+e)/10 209.71
say 210.00
16.10 2800 Applying pre-packed cement based polymer mortar of
strength 45 Mpa at 28 days for replacement of spalled
concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.40 336.00 470.40 M-057
pre-packed cement based polymer mortar of strength kg 12.00 380.00 4560.00 M-145
45 Mpa at 28 days
Add 3 per cent of (a ) above for wastage. 150.91
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mazdoor (Skilled) day 0.50 250.00 125.00 L-15
Mazdoor day 0.50 225.00 112.50 L-13
c) Overhead charges @ 10 % on (a+b) 543.08
d) Contractor's profit @ 10 % on (a+b+c) 597.39
Cost for 10 sqm = a+b+c+d 6571.28
330
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Rate per sqm = (a+b+c+d)/10 657.13
say 657.00
16.11 2805 Eproxy bonding of new concrete to old concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes kg 8.00 555.00 4440.00 M-098
and satisfying testing as per clause 2803.9
Add 3 per cent of (a ) above for wastage. 133.20
b) Labour
Mate day 0.04 300.00 12.00 L-12
Mazdoor (Skilled) day 0.50 250.00 125.00 L-15
Mazdoor day 0.50 225.00 112.50 L-13
c) Overhead charges @ 10 % on (a+b) 482.27
d) Contractor's profit @ 10 % on (a+b+c) 530.50
Cost for 10 sqm = a+b+c+d 5835.47
Rate per sqm = (a+b+c+d)/10 583.55
say 584.00
16.12 2810 Providing external prestressing with high tensile steel
wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42
kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra tonne 1.05 59400.00 62370.00 M-119
length for jacking
HDPE pipes 75mm dia including 5 per cent wastage metre 112.00 92.00 10304.00 M-114
Cement for grouting kg 400.00 5.60 2240.00 M-
081/1000
Tube anchorage set complete with bearing plate, each 8.00 1277.00 10216.00 M-187
permanent wedges etc
Epoxy kg 6.00 880.00 5280.00 M-095
MS plates for deviator (where deviator blocks are not tonne 2.10 51520.00 108192.00 M-179
provided)
Add 20 per cent cost of material for other materials 39720.40
like lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.24 300.00 72.00 L-12
Mazdoor Semi-skilled) day 3.00 225.00 675.00 L-14
Mazdoor day 3.00 225.00 675.00 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 0.44 300.00 132.00 L-12
Blacksmith day 3.00 350.00 1050.00 L-02
Mazdoor day 8.00 225.00 1800.00 L-13
iii) For prestressing
Mate/Supervisor day 0.13 300.00 39.00 L-12
Fitter day 0.70 350.00 245.00 L-08
Mazdoor day 2.65 225.00 596.25 L-13
iv) For grouting
Mate/Supervisor day 0.13 300.00 39.00 L-12
Mason day 0.70 350.00 245.00 L-11
331
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mazdoor day 2.65 225.00 596.25 L-13
c) Machinery
Stressing jack with pump hour 4.00 109.00 436.00 P&M-040
Grouting pump with agitator hour 1.35 336.00 453.60 M-111
d) Overhead charges @ 10 % on (a+b+c) 24537.65
e) Contractor's profit @ 10 % on (a+b+c+d) 26991.42
Rate per MT = (a+b+c+d+e) 296905.57
say 296906.00
16.13 2810 Providing external prestressing with high tensile steel
wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73
kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra tonne 3.10 59400.00 184140.00 M-119
length for jacking
HDPE pipes 90mm dia including 5 per cent wastage metre 224.00 134.00 30016.00 M-115
Cement for grouting tonne 1.01 5600.00 5656.00 M-081
Tube anchorage set complete with bearing plate, each 8.00 1277.00 10216.00 M-187
permanent wedges etc
Epoxy kg 10.00 880.00 8800.00 M-095
MS plates for deviator (where deviator blocks are not tonne 7.00 51520.00 360640.00 M-179
provided)
Add 20 per cent cost of material for other materials 119893.60
like lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.08 300.00 24.00 L-12
Mazdoor Semi-skilled) day 8.00 225.00 1800.00 L-14
Mazdoor day 8.00 225.00 1800.00 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 1.28 300.00 384.00 L-12
Blacksmith day 7.00 350.00 2450.00 L-02
Mazdoor day 25.00 225.00 5625.00 L-13
iii) For prestressing
Mate/Supervisor day 0.20 300.00 60.00 L-12
Fitter day 1.00 350.00 350.00 L-08
Mazdoor day 4.00 225.00 900.00 L-13
iv) For grouting
Mate/Supervisor day 0.26 300.00 78.00 L-12
Mason day 1.50 350.00 525.00 L-11
Mazdoor day 5.00 225.00 1125.00 L-13
c) Machinery
Stressing jack with pump hour 7.00 109.00 763.00 P&M-040
Grouting pump with agitator hour 3.00 336.00 1008.00 M-111
d) Overhead charges @ 10 % on (a+b+c) 73625.36
e) Contractor's profit @ 10 % on (a+b+c+d) 80987.90
Cost for 3.10 MT = a+b+c+d+e 890866.86
Rate per MT = (a+b+c+d+e)/3.10 287376.41
say 287376.00
332
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
16.14 2810 Providing external prestressing with high tensile steel
wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Unit = No
333
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = 3 Nos. of 250 T capacity
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length
of 30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 3713.00 11139.00 P&M-084
Mate day 0.64 300.00 192.00 L-12
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Mazdoor day 12.00 225.00 2700.00 L-13
v) Wooden packing cum 0.15 2530.00 379.50 M-195
b) Replacement of bearing
Cast steel rocker bearing assembly of 250 tonne each 3.00 48400.00 145200.00 M-065
design load capacity duly painted complete with all its
components as per drawing and specifications
c) Overhead charges @ 10 % on (a+b) 16061.05
d) Contractor's profit @ 10 % on (a+b+c) 17667.16
Cost of repair of 3 bearings of 250 T = a+b+c+d 194338.71
Rate of repair per Tonne capacity = (a+b+c+d)/(3*250) 259.12
say 259.00
Note The work entails replacement of all the bearings on one side
of the span.
16.15.2 2808 Replacement of forged steel roller bearing complete as
per Technical Specification including Lifting of
superstructure span by jacking up from below i.e. by
placing the jacks on pier/abutment caps for all span
length, Supplying, fitting and fixing in position true to
line and level forged steel roller bearing conforming to
IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as per
drawing and Technical Specifications
Unit = No
Taking output = 3 [Link] 250 T capacity
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length
of 30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 3713.00 11139.00 P&M-084
Mate day 0.64 300.00 192.00 L-12
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Mazdoor day 12.00 225.00 2700.00 L-13
v) Wooden packing cum 0.15 2530.00 379.50 M-195
b) Replacement of bearing
Cost of bearing. each 3.00 73920.00 221760.00 M-065
c) Overhead charges @ 10 % on (a+b) 23717.05
d) Contractor's profit @ 10 % on (a+b+c) 26088.76
forged steel roller bearing assembly of 250 tonne 286976.31
design load capacity duly painted complete with all its
components as per drawing and specifications
Rate of repair per Tonne capacity = (a+b+c+d)/(3*250) 382.64
say 383.00
Note The work entails replacement of all the bearings on one side
of the span.
334
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
16.15.3 2808 Replacement of sliding plate bearing with PTFE
complete as per Technical Specification including
Lifting of superstructure span by jacking up from below
i.e. by placing the jacks on pier/abutment caps for all
span length, Supplying, fitting and fixing in position true
to line and level sliding plate bearing with PTFE surface
sliding on stainless steel complete including all
accessories as per drawing and Technical
Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE)
and clause 2004 of MoRTH Specifications.
Unit = No
Taking output = 3 Nos. of 80 T capacity
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length
of 30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 3713.00 11139.00 P&M-084
Mate day 0.64 300.00 192.00 L-12
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Mazdoor day 12.00 225.00 2700.00 L-13
v) Wooden packing cum 0.15 2530.00 379.50 M-195
b) Replacement of bearing
Cost of bearing. each 3.00 30250.00 90750.00 M-065
c) Overhead charges @ 10 % on (a+b) 10616.05
d) Contractor's profit @ 10 % on (a+b+c) 11677.66
Cost of repair of 3 bearings = a+b+c+d 128454.21
Rate of repair per Tonne capacity = (a+b+c+d)/(3*80) 535.23
say 535.00
Note The work entails replacement of all the bearings on one side
of the span.
16.15.4 2808 Replacement of elastomeric bearing complete as per
Technical Specification including Lifting of
superstructure span by jacking up from below i.e. by
placing the jacks on pier/abutment caps for all span
length, Supplying, fitting and fixing in position true to
line and level elastomeric bearing conforming to IRC: 83
(Part-II) section IX and clause 2005 of MoRTH
specifications complete including all accessories as per
drawing and Technical Specifications.
Unit = No
Taking output = one cubic centimeter
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length
of 30m.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 [Link]
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 [Link].
Hence volume of elastometer = 14655 [Link].
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 3713.00 11139.00 P&M-084
Mate day 0.64 300.00 192.00 L-12
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Mazdoor day 12.00 225.00 2700.00 L-13
v) Wooden packing cum 0.15 2530.00 379.50 M-195
b) Replacement of bearing
335
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Cost of bearing. each 3.00 14520.00 43560.00 M-065
c) Overhead charges @ 10 % on (a+b) 5897.05
d) Contractor's profit @ 10 % on (a+b+c) 6486.76
Cost of repair of 3 bearings = a+b+c+d 71354.31
Rate of repair per cc = (a+b+c+d)/(3*19200) 1.24
say 1.20
Note The work entails replacement of all the bearings on one side
of the span.
16.15.5 2808 Replacement of sliding plate bearing with mild steel
matrix complete as per Technical Specification
including Lifting of superstructure span by jacking up
from below i.e. by placing the jacks on pier/abutment
caps for all span length, Supplying, fitting and fixing in
position true to line and level sliding plate bearing with
stainless steel plate sliding on stainless steel plate with
mild steel matrix complete including all accessories as
per drawing and Technical Specifications.
Unit = No
Taking output = 3 Nos. of 80 T capacity
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length
of 30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 3713.00 11139.00 P&M-084
Mate day 0.64 300.00 192.00 L-12
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Mazdoor day 12.00 225.00 2700.00 L-13
v) Wooden packing cum 0.15 2530.00 379.50 M-195
b) Replacement of bearing
Cost of bearing. each 3.00 30250.00 90750.00 M-065
c) Overhead charges @ 10 % on (a+b) 10616.05
d) Contractor's profit @ 10 % on (a+b+c) 11677.66
Cost of repair of 3 bearings = a+b+c+d 128454.21
Rate of repair per Tonne capacity = (a+b+c+d)/(3*80) 535.23
say 535.00
Note The work entails replacement of all the bearings on one side
of the span.
16.15.6 2808 Replacement of POT-PTFE complete as per Technical
Specification including Lifting of superstructure span by
jacking up from below i.e. by placing the jacks on
pier/abutment caps for all span length, Supplying, fitting
and fixing in position true to line and level POT-PTFE
bearing consisting of a metal piston supported by a disc
or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete
assembly to be of cast steel/fabricated structural steel,
metal and elastomer elements to be as per IRC: 83 part-I
& II respectively and other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of MoRTH
Specifications complete as per drawing and approved
Technical Specifications.
Unit = No
Taking output = 3 Nos. of 250 T capacity
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length
of 30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 3713.00 11139.00 P&M-084
336
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.64 300.00 192.00 L-12
Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
Mazdoor day 12.00 225.00 2700.00 L-13
v) Wooden packing cum 0.15 2530.00 379.50 M-195
b) Replacement of bearing
Cost of bearing. each 3.00 123200.00 369600.00 M-065
c) Overhead charges @ 10 % on (a+b) 38501.05
d) Contractor's profit @ 10 % on (a+b+c) 42351.16
Cost of repair of 3 bearings = a+b+c+d 465862.70
Rate of repair per Tonne capacity = (a+b+c+d)/(3*250) 621.15
say 621.00
Note The work entails replacement of all the bearings on one side
of the span.
16.16 2808 Rectification of Bearings as per Technical Specifications
Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by jacking up from
below i.e. by placing the jacks on pier/abutment caps for
span length of 30m.
i) Hire charges for jack of 40 tonne lifting capacity. each 3.00 3713.00 11139.00 P&M-084
ii) Mate day 0.64 300.00 192.00 L-12
iii) Mazdoor (Skilled) day 4.00 250.00 1000.00 L-15
iv) Mazdoor day 12.00 225.00 2700.00 L-13
v) Wooden packing cum 0.15 2530.00 379.50 M-195
b) Cost of parts to be replaced for 3 bearings. each 3.00 24200.00 72600.00 M-064
c) Overhead charges @ 10 % on (a+b) 8801.05
d) Contractor's profit @ 10 % on (a+b+c) 9681.16
Cost of repair of 3 bearings = a+b+c+d 106492.71
Rate of repair per bearing = (a+b+c+d)/3 35497.57
say 35498.00
Note The rectification of 3 bearings included in this analysis are
on the same side of the span.
16.17 Replacement of Expansion Joints complete as per
drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg 9.60 880.00 8448.00 M-095
kg/sqm
M-30 grade cement concrete excluding OH & CP (Rate cum 3.60 4143.00 14914.80 Item
as per items 14.1 C (i) 14.1(C)
b) Labour
Removal of old expansion joint including breaking of
concrete, cutting of lugs and shifting of broken material etc.
Mate day 0.26 300.00 78.00 L-12
Mazdoor day 6.00 225.00 1350.00 L-13
Mazdoor (Skilled) day 0.50 250.00 125.00 L-15
c) Overhead charges @ 10 % on (a+b) 2491.58
d) Contractor's profit @ 10 % on (a+b+c) 2740.74
Cost for replacement of 12 RM = a+b+c+d 30148.12
Rate per RM = (a+b+c+d)/12 2512.34
say 2512.00
Note The rate for the installation of new expansion joints may be
taken from the chapter on superstructure. Broken concrete
will have to be replaced which has been included in this
analysis.
337
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.20 300.00 60.00 L-12
Mazdoor day 5.00 225.00 1125.00 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 193.00 193.00 P&M-053
c) Overhead charges @ 10 % on (a+b) 137.80
d) Contractor's profit @ 10 % on (a+b+c) 151.58
Cost for 10 m = a+b+c+d 1667.38
Rate per metre = (a+b+c+d)/10 166.74
say 167.00
Note The rate for the provision of new railing may be adopted
from the chapter on superstructure.
16.19 Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.40 300.00 120.00 L-12
Mazdoor day 10.00 225.00 2250.00 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 193.00 193.00 P&M-053
c) Overhead charges @ 10 % on (a+b) 256.30
d) Contractor's profit @ 10 % on (a+b+c) 281.93
Cost for 10 m = a+b+c+d 3101.23
Rate per metre = (a+b+c+d)/10 310.12
say 310.00
Note The rate for the construction of new crash barrier may be
adopted from chapter 8 on Traffic and Transportation.
16.20 Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.16 300.00 48.00 L-12
Mazdoor day 4.00 225.00 900.00 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 193.00 193.00 P&M-053
c) Overhead charges @ 10 % on (a+b) 114.10
d) Contractor's profit @ 10 % on (a+b+c) 125.51
Cost for 10 m = a+b+c+d 1380.61
Rate per metre = (a+b+c+d)/10 138.06
say 138.00
16.21 Repair of Crash Barrier
Repair of concrete crash barrier with cement concert of M-30
grade by cutting and trimming the damaged portion to a
regular shape, cleaning the area to be repaired thoroughly,
applying cement concert after erection of proper form work.
338
Ref. to Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs Input ref.
Spec.
Mate day 0.04 300.00 12.00 L-12
Mazdoor day 1.00 225.00 225.00 L-13
* For dismantling and trimming the surface to a regular shape
and removal of damaged material.
b) Material
M-30 grade cement concrete excluding OH & CP (Rate cum 0.30 4143.00 1242.90 Item
as per items 14.1 C (i) 14.1(C)
This may be priced based on the rate given the chapter of
superstructure.
c) Overhead charges @ 10 % on (a) 23.70
d) Contractor's profit @ 10 % on (a+c) 26.07
Cost for 10 m = a+b+c+d 1529.67
Rate per m = (a+b+c+d)/10 152.97
say 153.00
16.22 Repair of RCC Railing
Carrying out repair of RCC M30 railing to bring it to the
original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent .
a) Material
M-30 grade cement concrete excluding OH & CP (Rate cum 0.10 4143.00 414.30 Item
as per items 14.1 C (i) 14.1(C)
HYSD bar reinforcement Rate as per item No tonne 0.01 56932.00 740.12 Item 14.2 A
14.2(Excluding OH & CP)
b) Labour*
Mate day 0.016 300.00 4.80 L-12
mazdoor day 0.20 225.00 45.00 L-13
* For dismantling and trimming the surface to a regular shape
and removal of damaged material.
c) Overhead charges @ 10 % on (b) 4.98
d) Contractor's profit @ 10 % on (b+c) 5.48
Cost for 10 m = a+b+c+d 1214.67
Rate per m = (a+b+c+d)/10 121.47
say 121.00
16.23 Repair of Steel Railing
Repair of steel railing to bring it to the original shape
It is assumed that the damage to the steel railing is to the
extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a) Material
Mild steel ISMC series kg 29.00 51.52 1494.08 M-
179/1000
Flat iron kg 10.00 51.52 515.20 M-
179/1000
MS Bolt and nuts kg 1.00 65.00 65.00 M-130
Add 5 per cent of cost of material for painting. 103.71
b) Labour
Mate day 0.016 300.00 4.80 L-12
Mazdoor (Skilled) day 0.20 250.00 50.00 L-15
Mazdoor day 0.20 225.00 45.00 L-13
c) Overhead charges @ 10 % on (a+b) 227.78
d) Contractor's profit @ 10 % on (a+b+c) 250.56
Cost of repair for10m = a+b+c+d 2756.13
Cost of meter = (a+b+c+d)/10 275.61
say 276.00
339
(A) Usage Rates of Plant and Machinery Jaipur Jodhpur Kota
Output of
Sl. No. Description of Machine Activity Output Unit Rate Unit Rate Unit Rate
Machine
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 150 hour 225 hour 201
P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 1500 hour 2000 hour 2010
P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1200 hour 1600 hour 1608
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 580 hour 600 hour 737
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 150 hour 200 hour 201
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 1600 hour 2000 hour 2010
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 500 hour 300 hour 201
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 100 hour 100 hour 134
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 100 hour 100 hour 134
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 150 hour 150 hour 201
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 800 hour 800 hour 1072
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 500 hour 500 hour 670
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 225 hour 225 hour 301.5
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2000 hour 2000 hour 1530
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 1400 hour 1400 hour 1730
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 580 hour 600 hour 737
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 650 hour 500 hour 938
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 650 hour 600 hour 804
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 525 hour 500 hour 670
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 650 hour 1000 hour 871
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 6900 hour 10800 hour 20000
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 6700 hour 8300 hour 18000
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 6500 hour 6700 hour 16000
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 6300 hour 4600 hour 14000
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 1200 hour 1200 hour 1608
P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable cum/hour 60 /60 /60 hour 700 hour 700 hour 938
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 5600 hour 5600 hour 7504
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 11000 hour 11000 hour 14740
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 200 hour 200 hour 268
P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 40 hour 40 hour 53.6
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 150 hour 150 hour 201
Page 1 of 563
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 1200 hour 1200 hour 1608
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 550 hour 550 hour 737
P&M-034 Paver Finisher Hydrostatic with sensor control 100 Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 1500 hour 1400 hour 1876
TPH
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 580 hour 550 hour 737
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment Rm/hour 2 to 3 hour 3500 hour 3500 hour 4700
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1000 hour 1000 hour 1340
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 2500 hour 2500 hour 3350
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 500 hour 500 hour 670
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 80 hour 80 hour 107.2
P&M-043 Road marking machine Road marking Sqm/hour 100 hour 65 hour 60 hour 80.4
P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 170 hour 200 hour 214.4
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 700 hour 700 hour 938
P&M-046 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix Capacity in cum 5.5 km 185 km 175 km 28.1
etc.
P&M-047 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix Capacity in cum 5.5 [Link] 1.85 [Link] 1.74 [Link] 2.81
etc.
P&M-048 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix Capacity in cum 5.5 hour 185 hour 175 hour 234.5
etc.
P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 600 hour 600 hour 804
P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 [Link] 1.85 [Link] 1.74 [Link] 2.33
P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 550 hour 550 hour 737
P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 [Link] 1.85 [Link] 5.5 [Link] 3.00
P&M-053 Tractor Pulling capacity in HP 50 hour 150 hour 125 hour 201
P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 150 hour 125 hour 201
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 175 hour 125 hour 234.5
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 185 km 175 km 28.1
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 185 hour 175 hour 234.5
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 [Link] 1.85 [Link] 1.74 [Link] 2.81
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1000 hour 1000 hour 1340
P&M-060 Water Tanker Water Transport capacity in KL 6 hour 105 hour 100 hour 134
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 800 hour 750 hour 1005
Sl. No. Description of Machine Unit Rate Unit Rate Unit Rate
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 250 hour 150 hour 201
Page 2 of 563
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 1200 hour 1200 hour 1608
P&M-065 Belt conveyor system hour 120 hour 120 hour 160.8
P&M-066 Boat to carry atleast 20 persons hour 1500 hour 1500 hour 2010
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 6000 hour 6000 hour 8040
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 1500 hour 1500 hour 2010
P&M-069 Cold milling machine @ 20 cum per hour hour 150 hour 150 hour 201
P&M-070 Crane 5 tonne capacity hour 250 hour 250 hour 335
P&M-071 Crane 10 tonne capacity hour 300 hour 300 hour 402
P&M-072 Crane 15 tonne capacity hour 400 hour 400 hour 536
P&M-073 Crane 20 tonne capacity hour 475 hour 450 hour 603
P&M-075 Crane with grab 0.75 cum capacity hour 900 hour 550 hour 737
P&M-076 Compressor with guniting equipment along with accessories hour 250 hour 200 hour 400
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 4000 hour 4000 hour 5360
P&M-078 Epoxy Injection gun hour 200 hour 200 hour 268
P&M-080 Generator 100 KVA hour 600 hour 600 hour 804
P&M-081 Generator 250 KVA hour 750 hour 700 hour 1005
P&M-082 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. hour 5000 hour 5000 hour 6700
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 150 hour 150 hour 201
P&M-084 Jack for Lifting 40 tonne lifting capacity. day 3000 day 20000 day 26800
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 3000 hrs 3000 hrs 4020
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 500 hour 500 hour 670
P&M-088 Texturing machine (for rigid pavement) hour 200 hour 200 hour 268
P&M-089 Truck Trailor 30 tonne capacity hour 300 hour 300 hour 402
P&M-090 Truck Trailor 30 tonne capacity [Link] 300 [Link] 300 [Link] 402
P&M-091 Tunnel Boring machine hour 350 hour 350 hour 469
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 550 hour 550 hour 737
P&M-093 Wet Mix Plant 100 TPH hour 1000 hour 2000 hour 5360
(B) Labour
Page 3 of 563
Sl. No. Description of Labour Unit Rate Unit Rate Unit Rate
L-01 Blacksmith (IInd class) day 130 day 150 day 150
L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 150 day 200 day 200
L-03 Blaster (Stone cutter) day 150 day 150 day 150
L-05 Chiseller (Head Mazdoor) day 150 day 200 day 200
L-10 Mason (IInd class) day 175 day 200 day 200
L-11 Mason (Ist class) day 250 day 250 day 250
L-14 Mazdoor/Dresser (Semi Skilled) day 120 day 150 day 125
L-19 Para medical personnel day 250 day 200 day 200
(C) Materials
Page 4 of 563
Sl. No. Description Unit Rate Unit Rate Unit Rate
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 200 cum 180 cum 200
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 210 cum 250 cum 200
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 265 cum 300 cum 250
M-004 Coarse sand at Mixing Plant (Crusher dust) cum 160 cum 200 cum 150
M-005 Coarse sand at Site cum 455 cum 250 cum 420
M-006 Fine sand at Site cum 400 cum 250 cum 350
M-008 Gravel/Quarry spall at Site Cum 160 Cum 120 Cum 150
M-009 Granular Material or hard murrum for GSB works at Site Cum 160 Cum 130 Cum 200
M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 160 Cum 130 Cum 200
M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 150 Cum 10 Cum 150
M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 160 Cum 130 MT 300
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 275 275 130 130 200 200
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 275 275 120 120 200 200
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 275 275 110 110 200 200
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 275 275 110 110 175 175
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 275 275 110 110 175 175
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 275 275 110 110 175 175
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm 275 275 110 110 175 175
M-020 Close graded Granular sub-base Material 2.36 mm cum 275 275 105 105 150 150
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 275 275 125 150 150 150
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 275 275 250 130 150 150
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm 275 275 105 130 150 150
M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 275 275 105 130 150 150
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 275 275 110 130 150 150
Page 5 of 563
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 275 275 120 120 175 175
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 275 275 120 120 175 175
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 275 275 120 120 175 175
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 275 275 125 125 175 175
M-030 Aggregates below 5.6 mm cum 300 300 150 180 460 460
M-031 Aggregates 22.4 mm to 2.36 mm cum 490 490 425 425 650 650
M-032 Aggregates 22.4 mm to 5.6 mm cum 490 490 280 425 650 650
M-033 Aggregates 45 mm to 2.8 mm cum 490 490 280 400 560 560
M-034 Aggregates 45 mm to 22.4 mm cum 490 490 425 425 560 560
M-035 Aggregates 53 mm to 2.8 mm cum 490 490 280 300 560 560
M-036 Aggregates 53 mm to 22.4 mm cum 490 490 325 400 560 560
M-037 Aggregates 63 mm to 2.8 mm cum 490 490 280 280 560 560
M-038 Aggregates 63 mm to 45 mm (Crusher Broken) cum 490 490 300 350 560 560
M-039 Aggregates 90 mm to 45 mm (Hand Broken) cum 490 490 175 300 250 250
M-041 Aggregates 11.2 mm to 0.09 mm cum 490 490 300 300 650 650
M-042 Aggregates 13.2 mm to 0.09 mm cum 490 490 300 300 650 650
M-043 Aggregates 13.2 mm to 5.6 mm cum 490 490 300 300 650 650
M-044 Aggregates 13.2 mm to 10 mm cum 490 490 300 300 650 650
M-048 Aggregates 37.5 mm to 19 mm cum 500 500 280 280 560 560
M-049 Aggregates 37.5 mm to 25 mm cum 500 500 280 280 560 560
M-050 Aggregates 6 mm nominal size cum 500 500 180 350 400 400
M-051 Aggregates 10 mm nominal size cum 500 500 325 425 650 650
M-052 Aggregates 13.2/12.5 mm nominal size cum 410 410 325 425 650 650
M-053 Aggregates 20 mm nominal size cum 510 510 290 450 650 650
M-054 Aggregates 25 mm nominal size cum 510 510 300 450 650 650
M-055 Aggregates 40 mm nominal size cum 490 490 300 400 560 560
M-057 Acrylic polymer bonding coat litre 225 litre 225 litre 320
M-059 Aluminium alloy plate 2mm Thick sqm 750 sqm 4200 sqm 400
Page 6 of 563
M-060 Aluminium alloy/galvanised steel tonne 40000 tonne 42000 tonne 42000
M-061 Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling holes, sqm 1500 sqm 5500 sqm input
nuts, bolts [Link] signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 200 nos 240 nos input
M-064 Bearing (Cost of parts) nos 20000 nos input nos 8000
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 40000 nos 3000 nos 80000
M-066 Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the 12000 10000 12000
process of vulcanisation,) nos nos nos
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 60000 nos 80000 nos 100000
M-068 Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel 100000 60000 85000
mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all comp nos nos nos
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 25000 nos 20000 nos 32000
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 25000 nos 20000 nos 25000
M-071 Bentonite kg 15 kg 3 kg 12
M-073 Bitumen ( Cationic Emulsion ) tonne 25000 tonne 28143 tonne 27514
M-074 Bitumen (60-70 grade) tonne 31679 tonne 30140 tonne 31615
M-075 Bitumen (80-100 grade ) tonne 30714 tonne 29205 tonne 30682
M-078 Bitumen (modified graded) CRMB-60 tonne 34538 tonne 32240 tonne 34451
M-082 Cold twisted bars (HYSD Bars) tonne 34500 tonne 37000 tonne 32000
M-084 Compressible Fibre Board(20mm thick) sqm 425 sqm 260 sqm 500
M-087 Corrosion resistant Structural steel tonne 35800 tonne 26000 tonne 38000
M-089 Credit for excavated rock found suitable for use cum 150 cum 50 cum 150
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 400 each 250 each 350
M-092 Earth Cost or compensation for earth taken from private land cum 45 cum 10 cum 10
M-093 Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 8000 10000 12000
915.1 of IRC: 83 (part II), metre metre metre
Page 7 of 563
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 500 100 nos 500 100 nos 600
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 300 kg 1000 kg 450
M-098 Epoxy resin-hardner mix for prime coat kg 300 kg 500 kg 200
M-099 Flag of red color cloth 600 x 600 mm each 15 each 15 each 12
M-101 Galvanised MS flat clamp nos 250 nos 250 nos 260
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 200 sqm 150 sqm 210
M-109 Geotextile filter fabric sqm 250 sqm input sqm 350
M-111 Grouting pump with agitator hour 300 hour 300 hour 300
M-115 HDPE pipes 90mm dia metre 100 metre input metre 160
M-117 Helical pipes 600mm diameter metre 750 metre 70 metre input
M-118 Hot applied thermoplastic compound litre 150 litre 170 litre 170
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 30 sqm 30 sqm 20
M-126 Mild Steel bars tonne 30000 tonne 32000 tonne 32000
M-127 Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly metre 7000 metre 50 metre 6500
comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel
Page 8 of 563
M-128 Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly metre 8000 metre 50 metre 8800
containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and
M-132 Pavement Marking Paint litre 150 litre 185 litre 180
M-134 Perforated geosynthetic pipe 150 mm dia metre 200 metre 200 metre input
M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 200 metre 200 metre 35
M-137 Pipes 200 mm dia, 2.5 m long for drainage AC metre 30 metre 5 metre 40
M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 60 sqm 2 sqm input
M-139 Plastic tubes 50 cm dia, 1.2 m high nos 320 nos 320 nos input
M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 210 sqm 430 sqm 220
M-142 Pre-coated stone chips of 13.2 mm nominal size cum 900 cum 425 cum 75
M-143 Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for the 146 50 80
full length of a joint to ensure water tightness. metre metre metre
M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 300 kg 300 kg 400
M-148 Random Rubble Stone cum 300 cum 300 cum 300
M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 4000 metre 3500 metre 3700
M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 4500 metre 4700 metre 5500
M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 800 metre 400 metre 550
M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 240 metre input metre 200
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 155 metre input metre 80
M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 140 metre input metre 70
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 250 metre input metre 95
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 200 metre input metre 35
M-159 Sand bags (Cost of sand and Empty cement bag) nos 6 nos 5 nos 10
M-161 Scrap tyres of size 900 x 20 nos 100 nos 60 nos 110
Page 9 of 563
M-162 Seeds kg 60 kg 1000 kg 52
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 15 sqm 2 sqm 17
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 250 cum 150 cum 270
M-168 Sodium vapour lamp each 550 each input each 700
M-169 Square Rubble Coursed Stone cum 4000 cum 1250 cum 365
M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 5750 each input each 5000
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 8000 each input each 7000
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 200 nos 130 nos 120
M-173 Steel helmet and cushion block on top of pile head during driving. kg 45 kg 34 kg 47
M-174 Steel pipe 25 mm external dia as per IS:1239 metre 75 metre 15 metre 85
M-175 Steel pipe 50 mm external dia as per IS:1239 metre 200 metre 31 metre 150
M-178 Strip seal expansion join metre 7000 metre 50 metre 850
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 350 sqm input sqm input
M-183 Tie rods 20mm diameter nos 275 nos input nos 150
M-184 Tiles size 300 x 300 mm and 25 mm thick each 8 each 6 each 9
M-186 Traffic cones with 150 mm reflective sleeve (Plastic) nos 400 nos input nos 450
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 1000 nos 25 nos 27
M-189 Water KL 50 KL 50 KL 22
M-193 Wooden ballies 2" Dia for bracing each 2 each 1 each 80
M-194 Wooden ballies 8" Dia and 9 m long each 10 each 5 each 120
M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 10 each 1 each 40
Page 10 of 563
M-197 Bitumen PMB-40 MT 38925
M-198 RCC pipe NP-4 Heavyduty Non-pressure pipe 600mm dia Rm 1300
M-199 RCC pipe NP-4 Heavyduty Non-pressure pipe 900mm dia Rm 2,900.00
Overheads for Bridge Works 10 % for input of Overheads or Contractors profit please type in collum C as like below
Overheads for Bridge Works (Rehabilitation) 10 % Type symble of apostrope(') then input value then one space then symble of
percentage (%) for example '08 %
Lead from Mixing Plant to working site 20 km 1 Km for Chapter 1 to 5 and 20 for other Chapter.
Page 11 of 563
Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate Unit Rate Unit Rate
Item 8.3 per cm height 0.50 per cmletter
height per 0.40 perper
cm height 0.00
Printing new letter and figures of any shade (ii) English Roman per letter letter
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 64.00 sqm 0.00 sqm 0.00
Item 8.9 Painting angle iron post two coats sqm 53.00 sqm 31.00 sqm 0.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 4,615.00 cum 2,773.00 cum 0.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 3,788.00 cum 2,219.00 cum 0.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 2,647.00 cum 1,457.00 cum 0.00
Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 3,899.00 cum 2,353.00 cum 0.00
Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 2,868.00 cum 0.00 cum 0.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 3,879.00 cum 2,419.00 cum 0.00
Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,083.00 cum 1,923.00 cum 0.00
Item 12.8 (B) PCC PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,441.00 cum 2,137.00 cum 0.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,466.00 cum 2,229.00 cum 0.00
Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 3,922.00 cum 2,631.00 cum 0.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,117.00 cum 2,091.00 cum 0.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,751.00 cum 2,336.00 cum 0.00
Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 4,274.00 cum 2,605.00 cum 0.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,405.00 cum 2,076.00 cum 0.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,779.00 cum 2,364.00 cum 0.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,535.00 cum 2,107.00 cum 0.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,785.00 cum 2,358.00 cum 0.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,435.00 cum 2,095.00 cum 0.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,798.00 cum 2,376.00 cum 0.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,450.00 cum 2,104.00 cum 0.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,884.00 cum 2,431.00 cum 0.00
Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 3,754.00 cum 2,241.00 cum 0.00
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 4,543.00 cum 2,711.00 cum 0.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,646.00 cum 2,176.00 cum 0.00
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,790.00 cum 2,334.00 cum 0.00
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,325.00 cum 1,984.00 cum 0.00
Batching Plant
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,967.00 cum 2,441.00 cum 0.00
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,501.00 cum 2,091.00 cum 0.00
Batching Plant
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4,001.00 cum 2,463.00 cum 0.00
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,536.00 cum 2,114.00 cum 0.00
Batching Plant
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4,079.00 cum 2,513.00 cum 0.00
Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 4,565.00 cum 2,732.00 cum 0.00
Page 12 of 563
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by cum 3,613.00 cum 2,163.00 cum 0.00
Batching Plant
Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 4,406.00 cum 2,690.00 cum 0.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 229.00 cum 129.00 cum 0.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 30.00 cum 21.00 cum 0.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 4,475.00 cum 2,711.00 cum 0.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 0.00 cum 3,018.00 cum 0.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5,446.32 cum 0.00 cum 0.00
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 4,143.00 cum 0.00 cum 0.00
Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 3,452.00 cum 0.00 cum 0.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 56,932.00 tonne 0.00 tonne 0.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 67,899.00 tonne 0.00 tonne 0.00
Item 5.17 Fog Seal sqm 41.00 sqm 28.00 sqm 0.00
Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 63.00 sqm 41.00 sqm 0.00
Item 5.21 Case-II Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 75.00 sqm 50.00 sqm 0.00
Item 5.21 Case-IV Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area sqm 101.00 sqm 66.00 sqm 0.00
above 50 %
Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 503.00 sqm #VALUE! sqm 0.00
Item 5.15 Case-I Slurry Seal Case-I 5 mm thickness sqm 67.00 sqm 45.00 sqm 0.00
Item 5.15 Case-II Slurry Seal Case-II 3 mm thickness sqm 46.00 sqm 31.00 sqm 0.00
Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 27.00 sqm 19.00 sqm 0.00
Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 87.00 sqm 55.00 sqm 0.00
Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 72.00 sqm 45.00 sqm 0.00
365.00
Page 13 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-1
CARRIAGE OF MATERIALS
Loading and unloading of stone boulder / stone aggregates / sand / kanker /
moorum. (Placing tipper at loading point, loading with front end loader, dumping, turning
1.1 for return trip, excluding time for haulage and return trip) cum 74.00 64.00 15.63
1.2 Loading and Unloading of Boulders by Manual Means cum 86.00 51.00 68.63
1.3 Loading and Unloading of Cement or Steel by Manual Means and stacking. tonne 111.00 70.00 58.57
1.4 Cost of Haulage Excluding Loading and Unloading
(i) Surfaced Road [Link] 2.10 1.50 40.00
(ii) Unsurfaced Gravelled Road [Link] 2.50 1.90 31.58
(iii) Katcha Track and Track in river bed / nallah bed and choe bed. [Link] 5.10 3.70 37.84
Hand Broken Stone Aggregates 63 mm nominal size (Supply of quarried stone, hand
breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained on 50
1.5 mm sieve) and stacking as directed) cum 879.00 492.00 78.66
CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of
trees, including cutting of trunks, branches and removal of stumps, roots, stacking of
2.1 serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the
depression/pit.)
Page 14 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
A Lime Concrete, cement concrete grade M-10 and below cum 280.00 142.00 97.18
B Cement Concrete Grade M-15 & M-20 cum 337.00 167.00 101.80
C Prestressed / Reinforced cement concrete grade M-20 & above cum 941.00 436.00 115.83
II By Mechanical Means for items No. 202( b) & ( c)
A Cement Concrete Grade M-15 & M-20 cum 341.00 193.00 76.68
B Prestressed / Reinforced cement concrete grade M-20 & above cum 610.00 329.00 85.41
(ii) Dismantling Brick / Tile work
A In lime mortar cum 165.00 91.00 81.32
B In cement mortar cum 223.00 116.00 92.24
C In mud mortar cum 142.00 80.00 77.50
D Dry brick pitching or brick soling cum 131.00 75.00 74.67
(iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar cum 188.00 101.00 86.14
B Rubble stone masonry in cement mortar. cum 223.00 116.00 92.24
C Rubble Stone Masonry in mud mortar. cum 165.00 91.00 81.32
D Dry rubble masonry cum 154.00 85.00 81.18
E Dismantling stone pitching/ dry stone spalls. cum 142.00 80.00 77.50
Dismantling boulders laid in wire crates including opening of crates and
F stacking dismantled materials. cum 165.00 91.00 81.32
Wood work wrought framed and fixed in frames of trusses upto a height of 5 m
(iv) above plinth level cum 455.00 217.00 109.68
Steel work in all types of sections upto a height of 5 m above plinth level
(v) excluding cutting of rivet.
I By Manual Means
A Bituminous courses cum 519.00 261.00 98.85
B Granular courses cum 364.00 188.00 93.62
II By Mechanical Means
A Bituminous course cum 179.00 111.00 61.26
Dismantling of Cement Concrete Pavement (Dismantling of cement concrete
pavement by mechanical means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at designated locations and disposal of
2.6 dismantled materials up to a lead of 1000 metres, stacking serviceable and cum 930.00 574.00 62.02
unserviceable materials separately)
Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable
2.7 materials and unserviceable materials separately.) metre 55.00 28.00 96.43
Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of
2.8 dismantled material with all lifts and up to a lead of 1000 metre) metre 9.00 6.00 50.00
Page 15 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means
and disposal of dismantled material with all lifts and up to a lead of 1000 metre)
2.9 metre 14.00 8.00 75.00
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia
including disposal with all lifts and lead upto 1000 metres and stacking of serviceable
2.12 material and unserviceable material separately under supervision of concerned metre 93.00 50.00 86.00
department)
Page 16 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual
means including loading in truck for carrying of cut earth to embankment site with all lifts
3.1 and lead upto1000 metres.) cum 130.00 67.00 94.03
Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in
soil by mechanical means including cutting and pushing the earth to site of embankment
upto a distance of 100 metres (average lead50 metres), including trimming bottom and
3.3 side slopes in accordance with requirements of lines, grades and cross sections.) cum 99.00 82.00 20.73
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for
roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing the
cut earth to site of embankment upto a distance of 100 metres ( average lead 50 metres
3.4 ), trimming bottom and side slopes in accordance with the requirements of lines, grades cum 167.00 138.00 21.01
and cross sections.)
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres
(Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and
breaking, trimming of bottom and side slopes in accordance with requirements of lines,
3.5 grades and cross sections, loading and disposal of cut road with in all lifts and leads cum 103.00 94.00 9.57
upto 1000 metres )
Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock
(blasting prohibited) with rock breakers including breaking rock, loading in tippers and
3.8 disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)
Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and loading in tippers and disposal
3.10 with in all lifts and lead upto 1000 metres, trimming of bottom and side slopes in cum 38.00 28.00 35.71
accordance with requirements of lines, grades and cross sections.)
Page 17 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Case-II :Compacting original ground supporting embankment cum 26.00 21.00 23.81
Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m
internal and re-application on embankment slopes, cut slopes and other areas in
3.20 localities where the available embankment material is not conducive to plant growth) cum 172.00 88.00 95.45
Stripping, storing and re-laying top soil from borrow areas in agriculture fields.
(Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable
place, spreading and re-laying after taking the borrow earth to maintain fertility of the
3.21 agricultural field, finishing it to the required levels and satisfaction of the farmer.) cum 59.00 49.00 20.41
Page 18 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass
on embankment slope, verges or other locations shown on the drawing or as directed by
3.22 the engineer including preparation of ground, fetching of rods and watering) sqm 24.00 16.00 50.00
Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing
and placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the
3.23 rate of0.23 litres per sqm and laying and fixing jute netting, including watering for 3 sqm 117.00 83.00 40.96
months all as per clause 308)
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with
perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon
size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm
3.27 cushion above the pipe, cross section of excavation 450 x 550 mm. Excavated material 449.00 325.00 38.15
to be utilised in roadway at site )
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm
x 450 mm with aggregates conforming to table 300-4, excavated material to be utilised
3.28 in roadway ) metre 91.00 51.00 78.43
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area
by mechanical means including cutting and trimming of side slopes and disposing of
3.32 excavated earth with all lifts and lead upto 1000 metres) cum 108.00 89.00 21.35
Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas
in hard rock requiring blasting, by mechanical means including trimming of slopes and
3.34 disposal of cut material with all lifts and lead upto 1000 metres.) cum 217.00 175.00 24.00
Work in Urban Roads (The cost of earth work in urban roads inhabited area will be
3.35 comparatively higher due to following reasons:)
Page 19 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Embankment Construction with Fly ash/Pond ash available from coal or lignite
burning Thermal Plants as waste material. (Construction of embankment with fly ash
conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal
power stations as waste material, spread and compacted in layer of 200mm thickness
3.36 each at OMC, all as specified in IRC: SP: 58-2001 and as per approved plans.) cum 112.00 88.00 27.27
Page 20 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a
prepared sub grade, pulverising, adding the designed quantity of cement to the spread
soil, mixing in place with rotavator, grading with the motor grader and compacting with
4.5 the road roller at OMC to achieve the desired unconfined compressive strength and to cum 666.00 510.00 30.59
form a layer of sub-base/base.)
Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base (Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread Material, mixing in place
with rotavator, grading with the motor grader and compacting with the road roller at
4.6 OMC to achieve the desired unconfined compressive strength and to form a layer of
sub-base/base.)
Page 21 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
A By Manual Means
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1157.00 812.00 42.49
(b) Using Screening Type-A (13.2mm Agg.) cum 1324.09 940.86 40.73
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1258.00 877.00 43.44
(b) Using Screening Type-A (13.2mm Agg.) cum 1337.00 940.00 42.23
(c) Using Screening Type-B (11.2mm Agg.) cum 1402.00 989.00 41.76
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1258.00 906.00 38.85
(b) Using Screening Type-B (11.2mm Agg.) cum 1402.00 1018.00 37.72
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1011.00 757.00 33.55
(b) Using Screening Type-A (13.2mm Agg.) cum 1177.54 886.18 32.88
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1112.00 822.00 35.28
(b) Using Screening Type-A (13.2mm Agg.) cum 1191.00 886.00 34.42
(c) Using Screening Type-B (11.2mm Agg.) cum 1256.00 934.00 34.48
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1112.00 852.00 30.52
(b) Using Screening Type-B (11.2mm Agg.) cum 1256.00 963.00 30.43
Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material
obtained by breaking damaged cement concrete slabs to size range not exceeding 75
mm as specified in table 400.7 transporting the aggregates obtained from breaking of
cement concrete slabs at a lead of L km., laying and compacting the same as sub base/
4.10 base course, constructed as WBM to clause 404 except the use of screening or binding cum 267.00 210.00 27.14
Material.)
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of
bitumen over cleaned dry surface of crushed cement concrete base at the rate of 25 kg
per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at the rate of
4.11 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause sqm 17.00 13.00 30.77
506.3.8)
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material with water
at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in
4.12 uniform layers with paver in sub- base / base course on well prepared surface and cum 1261.00 913.00 38.12
compacting with vibratory roller to achieve the desired density.)
Construction of Median and Island with Soil Taken from Roadway Cutting
(Construction of Median and Island above road level with approved material deposited
4.13 at site from roadway cutting and excavation for drain and foundation of other structures, cum 129.00 86.00 50.00
spread, graded and compacted as per clause 407)
Construction of Median and Island with Soil Taken from Borrow Areas
(Construction of median and Island above road level with approved material brought
4.14 from borrow pits, spread, sloped and compacted as per clause 407) cum 218.00 155.00 40.65
Page 22 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Page 23 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared
surface of granular Base including clearing of road surface and spraying primer at the
5.1 rate of 0.60 kg/sqm using mechanical means.) sqm 31.00 17.00 82.35
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading premixed with bituminous binder, transported to site,
laid over a previously prepared surface with paver finisher to the required grade, level
5.3 and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired
compaction)
Page 24 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6
% of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per
5.8 MORTH specification clause No. 509 complete in all respects)
Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid
5.12 to the specified levels, grade and cross fall using Type A and B seal coats)
Page 25 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with
paving grade bitumen meeting the requirements given in table 500-29, prepared by
using mastic cooker and laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated fine-grained hard stone
chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to center in both directions, pressed into surface
5.14 when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over sqm 548.00 365.00 50.14
mastic surface, all complete as per clause 515.)
Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates,
portland cement filler, bituminous emulsion and water on a road surface including
5.15 cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface)
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of
bituminous cold mix on prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type
5.18 and capacity, transporting, laying, compacting and finishing to specified grades and
levels.)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate cum 10478.00 5857.00 78.90
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 10474.00 5865.00 78.58
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 7409.00 5421.00 36.67
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 7390.00 5418.00 36.40
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder on a prepared sub-grade or sub-
base to the lines, levels, grades and cross sections as per the drawings including mixing
5.19 in a plant of suitable type and capacity, transporting, laying, compacting and finishing.) cum 6477.00 5322.00 21.70
Modified Binder (Supply of modified binder produced by mixing bitumen with modifier
such as natural rubber or crumb rubber or any other polymer found compatible with
bitumen and which allows properties given in clause 521.3 and IRC: SP: 53 blending of
modifier with bitumen to be done either at the refinery or at the site plant capable of
producing the modified binder to be delivered in drums which shall be agitated in melted
5.20 condition using suitable device before use to ensure uniform dispersion.) tonne
Page 26 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area
above 50 % (Providing and laying a single coat of a stress absorbing membrane
over a cracked road surface, with crack width above 9 mm and cracked area above
50 % after cleaning with a mechanical broom, using modified binder complying with
clause 521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed
stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread
(iii) of aggregates and surface finished to conform to clause 902.) sqm 122.00 74.00 64.86
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by
5.22 paver finisher, rolled with a pneumatic tyred roller initially and finished with a smooth
steel wheel roller, all as per clause 519.3)
Page 27 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete
Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS:
383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to
exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7 days,
6.1 mixed in a batching plant, transported to site, laid with a paver with electronic sensor, cum 2151.00 1634.00 31.64
compacting with 8-10 tonnes vibratory roller, finishing and curing.)
Rolled Cement Concrete Base (Construction of rolled cement concrete base course
with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not
exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement
content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending,
mixing in batching plant at optimum moisture content, transporting to site, laying with a
paver with electronic sensor, compacting with 8-10 tonnes smooth wheeled vibratory
6.3 roller to achieve, the designed flexural strength, finishing and curing.) cum 2491.00 1895.00 31.45
Transition section between rigid and flexible pavement (Due to change in the
properties of materials and type of construction, a gradual changeover from rigid
pavement to flexible pavement is desirable to avoid any damage at the butting joint.
After provision of an expansion joint in the cement concrete slab, the thickness of slab
should be tapered to 10 cm over a length of 3 m towards the flexible pavement. The
6.4 deficiency of thickness caused due to tapering of the slab should be made up by the
asphaltic layers.)
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Page 28 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia
using geotextiles treated with carbon black with physical properties as given in clause
702.2.3 formed in to a stable network and a planar geocomposite structure, joints
7.1 wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved metre 2676.00 2323.00 15.20
drawings including excavation and backfilling)
Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain
consisting of porous or perforated pipe laid in narrow trench surrounded by a geotextile
7.2 filter fabric, with a minimum of 450 mm overlap of fabric and installed as per clause metre 1063.00 734.00 44.82
702.3 and 309.3.5 including excavation and backfilling)
Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving
fabric with physical requirements as per table 704-2 over a tack coat of paving grade
Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned
and repaired surface to provide a water resistant membrane and crack retarding layer.
Paving fabric to be free of wrinkling and folding and to be laid before cooling of tack
7.3 coat, brooming and rolling of surface with pneumatic roller to maximise paving fabric sqm 306.00 232.00 31.90
contact with pavement surface)
Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main
components as under: a) Excavation for foundation, foundation concrete and cement
concrete grooved seating in the foundation for facing elements (facia material). b)
Facia material and its placement. c) Assembling, joining with facing elements and
7.5 laying of the reinforcing elements. d) Earthfill with granular material which is to be
retained by the wall.)
Page 29 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with
top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on
M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb
8.1 stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all
complete as per clause 408)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall cm height per
(i) be counted as half ) letter 0.80 0.50 60.00
Direction and Place Identification signs with size more than 0.9 sqm size board.
(Providing and erecting direction and place identification retro- reflectorised sign asper
IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm,
8.6 60 cm below ground level as per approved drawing) sqm 15007.00 5745.00 161.22
Page 30 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant
aluminium alloy sheet reflectorised with high intensity retro-reflective sheeting of
encapsulated lense type with vertical and lateral clearance given in clause 802.2 and
802.3 and installed as per clause 802.7 over a designed support system of aluminium
8.7 alloy or galvanised steel trestles and trusses of sections and type as per structural
design requirements and approved plans)
Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of surface to give an even
8.9 shade) sqm 56.00 37.00 51.35
Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of
approved brand on wood surface after through cleaning of surface to give an even
8.10 shade) sqm 62.00 42.00 47.62
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting
lines, dashes, arrows etc on roads in two coats on new work with ready mixed road
marking paint conforming to IS:164 on bituminous surface, including cleaning the
8.11 surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard
design as per IRC:8-1980, fixing in position including painting and printing etc)
8.14
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard
design as per IRC:25-1967, fixed in position including finishing and lettering but
8.16 excluding painting) each 412.00 265.00 55.47
Page 31 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI
barbed wire fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3
metres center to center founded in M15 grade cement concrete, 0.6 metre below ground
level, every 15th post, last but one end post and corner post shall be strutted on both
sides and end post on one side only and provided with 9 horizontal lines and 2
8.17 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc metre 269.00 184.00 46.20
complete as per clause 807 )
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI
barbed wire fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3
metres center to center founded in M15 grade cement concrete, 0.6 metre below ground
level, every 15th post, last but one end post and corner post shall be strutted on both
sides and end post on one side only and provided with 12 horizontal lines and 2
8.18 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc metre 451.00 309.00 45.95
complete as per clause 807 )
Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50
mm (Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on
medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above
8.20 ground, 2 m centre to centre, complete as per approved drawings) metre 1958.00 1439.00 36.07
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level
(Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on
precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes 50
8.21 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing) metre 1401.00 1058.00 32.42
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie"
metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75
x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all
steel parts and fitments to be galvanised by hot dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of
B channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810) metre 4069.00 2927.00 39.02
Page 32 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope
safety barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level,
split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x
450 mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and
anchored at terminal posts 15 m apart. Terminal post to be embedded in M 15
gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut
8.25 of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long metre 2402.00 1696.00 41.63
at the bottom, all embedded in foundation concrete as per approved design and
drawing, rate excluding excavation and cement concrete.)
Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and
rectangular vans (Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of one metre length and
1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x
300 mm at the middle, made out of steel sheet of 3 mm thickness, end vertical pipes
of the panel made larger for embedding in foundation concrete, applying 2 coats of
B paint on all exposed surfaces, all as per approved design and drawings.) metre 2648.00 2019.00 31.15
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting
anti - glare screen with rectangular vanes of size 750 x 500 mm made from MS
sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the
direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m
above ground level, vertical post firmly embedded in cement concrete foundation
C 0.60 m below ground level, applying 2 coats of paint on exposed faces, all complete metre 917.00 638.00 43.73
as per approved design and drawings)
Street Lighting (Providing and erecting street light mounted on a steel circular hollow
pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m
overhang on both sides if fixed in the median and on one side if fixed on the footpath,
8.27 fitted with sodium vapour lamp and fixed firmly in concrete foundation.)
Cable Duct Across the Road (Providing and laying of a reinforced cement concrete
pipe duct, 300 mm dia, across the road (new construction), extending from drain to drain
in cuts and toe of slope to toe of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and sides of RCC pipe as per
IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces,
outer to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in
8.29 case of double and triple row ducts, joints to be made leak proof, invert level of duct to
be above higher than ground level to prevent entry of water and dirt, all as per IRC: 98 -
1997 and approved drawings.)
(i) Single Row for one utility service metre 3103.00 1302.00 138.33
(ii) Double Row for two utility services metre 6008.00 2470.00 143.24
(iii) Triple Row for three utility services metre 8926.00 3644.00 144.95
Page 33 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post
8.30 every 50-60 km of the highway. )
Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The
items involved for underpass/ subway/ overhead bridge/ overhead foot bridge are
earthwork, plain cement concrete, plastering, painting, information sign etc. The rates
8.31 for these items are available in respective chapters which can be adopted for the
quantities derived from the approved designs and drawings)
Traffic Control System and Communication system (Providing a traffic control centre
and communication system including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central computer system These
are specialised item of telecommunication system and are the commercial products. The
designer is required to contact the manufacturers to ascertain market prices. In case of
civil works required to be executed for these installations, pricing may be done as per
8.32 rates in relevant chapters for quantities derived approved design and drawing.)
Gantry Mounted Variable Message Sign board (Providing and erecting gantry
mounted variable message sign board electronically operated capable of flashing the
desired message over a designed support system of aluminium alloy or galvanised
8.33 steel, erected as per approved design and drawings and with lateral clearance as per
clause 802.3)
Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic
impact attenuator at abutment/pier of flyovers bridges using plastic/steel barrels 0.60
B m dia and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire sqm 1039.00 777.00 33.72
rope as per approved design and drawings)
With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system,
water gets discharged from plastic tubes on impact over a pre-determined time, thus
C absorbing the energy)) sqm 2917.00 2448.00 19.16
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud
100x 100 mm, die cast in aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm
8.35 upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as each 445.00 269.00 65.43
per BS 873 part 4:1973)
Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made
of low density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm
8.36 and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873) each 674.00 485.00 38.97
Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of
parking areas may be done for the quantities of various items based on the approved
B dimensions and pavement design for a particular terrain and soil. Rates for items may
be from respective chapters.)
Page 34 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous
carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at
8.38 approved locations to control speed, marked with white strips of road marking paint.) sqm
High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high
mast pole lighting with 30 m high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part
3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal
lock, lantern carriage, suitable winching arrangement for safe working load of 750 kg
and high powered electrically driven power tools for raising and lowering of lantern
carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and
fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved
design and drawings This is a specialised work and is generally done by firms who
specialise in such jobs. The detailed designs and estimates are submitted by the firms
8.40 alongwith their tender for checks by the Department. The cost of this work is required to
be worked out based on approved design, drawings and estimate of the lowest tender.
A separate contract for this work is concluded as the contractors for road and bridge
works generally donot undertake such jobs.)
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken
into separate items of work as under based on the approved design and drawings:-)
8.41
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs
for limited period at suitable locations in construction zone comprising of warning zone,
approach transition zone, working zone and terminal transition zone with a minimum
distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from
the edge of the carriageway in case of un-kerbed roads, the bottom edge of the lowest
sign plate to be not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6
8.42 mm angle iron post, founded and installed as per approved design and drawings,
removed and disposed of after completion of construction work, all as per IRC:SP:55-
2001)
With Bricks (Construction of a permanent type barricade made with brick work in
mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar
C 1:6, painted with yellow and white strips) each 9408.00 7067.00 33.13
Page 35 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red
flag 600 x 600 mm securely fastened to a staff 1 m in length for guiding the traffic)
8.46 each 327.00 159.00 105.66
CHAPTER-9
PIPE CULVERTS
PCC [Link] in Foundation (Plain cement concrete [Link] mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed in foundation and
9.1 compacted by vibration including curing for 14 days.) cum 3373.00 2432.00 38.69
Page 36 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-10
MAINTENANCE OF ROADS
Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300 mm width, laying fresh
10.1 material in layers not exceeding 250 mm and compacting with plate compactor or power cum 113.00 71.00 59.15
rammers to restore the original alignment, levels and slopes)
Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/
irregularities on shoulder to the design level by adding fresh approved soil and
10.2 compacting it with appropriate equipment.) sqm 37.00 25.00 48.00
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from
the shoulder surface to achieve the approved level and compacting with plate
10.3 compactor) sqm 11.70 7.00 67.14
Repair of pot holes by Wet Mix Macadam material. Removal of all failed material,
trimming of completed excavation to provide firm vertical faces, cleaning of
surface, compacting base of excavation as per clause 503, back filling the pot
holes with wet mix macadam material by mannual means as per clause 406,
10.3.1 compacting with roller 8-10T, trimming and finishing the surface to form a smooth cum 1295.00 New item
continuous surface, all as per clause 3004.
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm.
(Removal of all failed material, trimming of completed excavation to provide firm vertical
faces, cleaning of surface, painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous material as per clause 511,
10.4 compacting, trimming and finishing the surface to form a smooth continuous surface, sqm 131.00 87.00 50.57
all as per clause 3004.2)
Filling Pot- holes and Patch Repairs with mix seal surfacing type "A:, 20mm
(Removal of all failed material, trimming of completed excavation to provide firm vertical
faces, cleaning of surface, painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous material as per clause 511,
10.4.1 compacting, trimming and finishing the surface to form a smooth continuous surface, sqm 158.00 New item
all as per clause 3004.2)
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm
followed by seal coat type "B". (Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on
the sides and base of excavation as per clause 503, back filling the pot holes with hot
bituminous material as per clause 511, compacting, trimming and finishing the surface
10.4.2 to form a smooth continuous surface, all as per clause 3004.2) sqm 174.00 New item
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm
followed by seal coat type "B". (Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the
sides and base of excavation as per clause 503, back filling the pot holes with emulsion
rapid setting as binder as per clause 511, compacting, trimming and finishing the
10.4.3 surface to form a smooth continuous surface, all as per clause 3004.2 sqm 158.00 New item
Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal
of all failed material, trimming of completed excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat on the sides and base of excavation as per
clause 503, back filling the pot holes with hot bituminous material as per clause 504,
10.5 compacting, trimming and finishing the surface to form a smooth continuous surface, all
as per clause 3004.2)
Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has
10.7 occurred.) sqm 0.80 0.67 19.40
10.8 A Fog Seal (ref item 5.17) sqm 41.00 23.00 78.26
Page 37 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Hill Side Drain Clearance (Removal of earth from the choked hill side drain and
10.11 disposing it on the valley side manually) metre 30.00 14.00 114.29
Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a
10.12 bull-dozer D 80 A-12, 180 HP and disposal of the same on the valley side) cum 51.00 42.00 21.43
Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard
rock requiring blasting for 50% of the boulders and disposal of the same on the valley
10.13 side.) cum 92.00 74.00 24.32
Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull-
10.14 dozer 165 Hp and disposing it on the valley side) cum 3.00 3.00 0.00
Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by
10.15 a snow blower and disposing on the valley side.) cum 1.00 1.00 0.00
Repair of iron sign board at road side including cutting welding and refixing as per
10.16 directions but excluding painting and lettering. Each 390.00 New item
Repair of road side cuts by earthen bags using empty gunny bag or cement bag
10.17 including filling by dry sandy soil or local dry soil, transporting and fixing properly Each 20.00 New item
at site as per directions by Engineer.
Supplying of survey sheets Plan, L section, Cross sections and calculation sheets
in two hard copies with soft copy (CD), including carrying out survey at 10m
interval with 1 mm staff in 30m width i.e.15 m on either side of centre of road,
submission of drawings Plan, L section and cross section including plane table
survey of populated area and calculation sheets of Earth work, GSB, WMM, BM
layer , SDBC layer and earthwork for side drain as required by engineer in charge.
10.18 Work includes making of Bench marks 0.45x0.45x0.75 m keeping 0.30m outside, Km 5729.00 New item
plaster thereon duly painted and marked at suitable interval or every 2Km and all
T&P and labour and material in all respect. Complete as per MoRTH
specifications.
Survey and Preparation of drawings for bridge work with supplying of survey
sheets Plan, L section, Cross sections and calculation sheets in two hard copies
with soft copy (CD), including carrying out survey of existing road in a length of
1000m on either side of bridge with marking of proposed road levels, ground
level, HFl etc. at suitable interval with 1 mm staff on either side of centre of road,
excavation of test pit and preparing soil log, submission of drawings of soil log,
Plan, L section and cross section, detail working drawings of proposed bridge
10.19 including drawings of Abutment, piers, wings, retaining wall, drains, RCC deck, Nos. 9395.00 New item
railibgs etc. as required by engineer in charge. Work includes making of Bench
marks 0.45x0.45x0.75 m keeping 0.30m outside, plaster thereon duly painted and
marked at both side of road and all T&P and labour and material in all respect.
Complete as per MoRTH specifications.
Page 38 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-11
HORTICULTURE
Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge
farm yard manure or/ and good earth in required thickness (cost of sludge, farm- yard
11.1 manure or/and good earth to be paid for separately)) cum 19.00 9.00 111.11
Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from
11.2 weeds and fit for moving including supplying good earth if needed)
Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns
with fine grassing including ploughing, dressing including breaking of clods, removal of
rubbish, dressing and supplying doobs grass roots at 10 cm apart, including supplying
11.5 and spreading of farm yard manure at rate of0.6 cum per 100 sqm) sqm 148.00 128.00 15.63
11.6 Maintenance of Lawns with Fine Grassing for the First Year sqm 114.00 80.00 42.50
a) Planting Permanent Hedges including Digging of Trenches (Planting
permanent hedges including digging of trenches, 60 cm wide and 45 cm deep, refilling
11.7 the excavated earth mixed with farmyard manure, supplied at the rate of 4.65 cum per metre 337.00 242.00 39.26
100 metres and supplying and planting hedge plants at 30 cm apart)
(b) Maintenance of Hedge for one year metre 160.00 94.00 70.21
11.8 a) Planting Flowering Plants and Shrubs in Central Verge km 64902.00 49634.00 30.76
Maintenance of Flowering Plants and Shrubs in Central Verge for one Year
(b) km 148143.00 78977.00 87.58
Planting of Trees and their Maintenance for one Year (Planting of trees by the road
side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil
11.9 with decayed farm yard/sludge mannure, planting the saplings, backfilling the trench, each 780.00 436.00 78.90
watering, fixing the tree guard and maintaining the plants for one year)
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with
Forked Soil (Renovation lawns including, weeding, forking the ground, top dressing
with forked soil, watering and maintenance the lawns, for 30 days or more, till the
grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish
11.10 as directed, including supplying good earth, if needed but excluding the cost of well sqm 12.00 6.00 100.00
decayed farm yard manure)
Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed
farm yard manure, from any available source, approved by the engineer in charge
11.11 including screening and stacking) cum
Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store-
11.12 deoiled neem cake duly packed in used gunny bags) quintal
11.13 Supplying Sludge (Supplying sludge duly stacked at site/ store) cum
Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres,
and height 1.2 metres, above ground and 0.20 metre below ground (Half brick
circular tree guard, in 2nd class brick, internal diametre 1.25 metres, and height 1.2
metres, above ground and 0.20 metre below ground, bottom two courses laid dry, and
top three courses in cement mortar 1:6 ( 1 cement 6 sand) and the intermediate
11.14 courses being in dry honey comb masonry, as per design complete) each 1135.00 868.00 30.76
Page 39 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks,
laid dry lengthwise, including excavation, refilling, consolidation, with a hand
11.15 packing and spreading nearly surplus earth within a lead of 50 metres) metre 22.00 17.00 29.41
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen
drum (Making tree guard 53 cm dia and 1.3 m high as per design from empty bitumen
drum, slit suitably to permit sun and air, (supplied by the department at stock issue rate)
11.16 including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, each 469.00 336.00 39.58
complete in all respect)
Making Tree Guard 53 cm dia and 2 metres high as per design from empty
bitumen drums (Making tree guard 53 cm dia and 2 metres high as per design from
empty bitumen drums, slit suitably to permit sun and air, ( supplied by the department
at stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 mm
11.17 MS riveted to tree guard and providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with each 804.00 576.00 39.58
rivets complete in all respects)
Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded
work) (using angles, square bars, tees and channel grills, grating frames, gates and
tree guards of any size and design etc. including cost of screens and welding rods or
11.18 bolts and nuts complete fixed in position but without the cost of excavation and concrete quintal 8455.00 5473.00 54.49
for fixing which will be paid separately)
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm)
vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8
11.19 mm dia and 30 mm long bolts including painting two coats with paint of approved brand each tree 2085.00 1408.00 48.08
over a coat of priming, complete in all respects.) guard
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60
metre square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron
11.20 25 x 3 mm and steel wire3 mm dia welded and fabricated as per design in two halves each tree 3725.00 1936.00 92.41
bolted together) guard
Page 40 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out, construction of shoring and
12.1 bracing, removal of stumps and other deleterious matter, dressing of sides and bottom
and backfilling with approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 100.00 45.00 122.22
(ii) 3 m to 6 m depth cum 129.00 58.00 122.41
(iii) Above 6 m depth cum 172.00 77.00 123.38
B Mechanical Means
(i) Depth upto 3 m cum 37.00 25.00 48.00
(ii) Depth 3 m to 6 m cum 43.00 29.00 48.28
(iii) Depth above 6m cum 53.00 35.00 51.43
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 143.00 64.00 123.44
B Mechanical Means cum 46.00 33.00 39.39
III Hard rock ( requiring blasting )
A Manual Means cum 344.00 186.00 84.95
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 340.00 173.00 96.53
V Marshy soil
(i) upto 3 m depth
A Manual means cum 349.00 177.00 97.18
B Mechanical Means cum 90.00 50.00 80.00
VI Back Filling in Marshy Foundation Pits cum 221.00 125.00 76.80
Filling Annular Space Around Footing in Rock (Lean cement concrete [Link] nominal
12.2 mix. Rate may be taken as per items 13.4.)
PCC [Link] in Foundation (Plain cement concrete [Link] nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation
12.4 and compacted by vibration including curing for 14 days.) cum 3384.00 2458.00 37.67
(a) Square Rubble Coursed rubble masonry( first sort ) cum 3899.00 2753.00 41.63
(b) Random Rubble Masonry cum 3296.00 2295.00 43.62
Plain/Reinforced cement concrete in open foundation complete as per drawing
12.8 and technical specifications
Page 41 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4556.00 3450.00 32.06
F PCC Grade M30
Case I Using Concrete Mixer cum 4739.00 3462.00 36.89
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4302.00 3279.00 31.20
G RCC Grade M30
Case I Using Concrete Mixer cum 4756.00 3476.00 36.82
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4320.00 3295.00 31.11
H RCC Grade M35
Case I Using Concrete Mixer cum 4840.00 3542.00 36.65
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4406.00 3361.00 31.09
Providing and constructing temporary island 16 m diameter for construction of
12.9 well foundation for 8m dia. Well.
A Assuming depth of water 1.0 m and height of island to be 1.25m. each 41513.00 33413.00 24.24
B Assuming depth of water 4.0 m and height of island 4.5 m. each 194024.00 146181.00 32.73
Providing and constructing one span service road to reach island location
C from one pier location to another pier location metre 2092.00 1886.00 10.92
Providing and laying cutting edge of mild steel weighing 40 kg per metre for well
12.10 foundation complete as per drawing and technical specification. tonne 85691.00 56874.00 50.67
A Well curb
(i) RCC M20 Grade
Case I Using concrete mixer cum 5033.00 3660.00 37.51
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4526.00 3450.00 31.19
(ii) RCC M25 Grade
Case I Using concrete mixer cum 5487.00 4010.00 36.83
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5133.00 3916.00 31.08
(iii) RCC M35 Grade
Case I Using concrete mixer cum 5640.00 4127.00 36.66
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5294.00 4039.00 31.07
B Well steining
(I) PCC M15 Grade cum 4103.00 2999.00 36.81
(ii) PCC M20 Grade cum 4580.00 3329.00 37.58
(iii) RCC M20 Grade
Case I Using concrete mixer cum 4613.00 3355.00 37.50
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4149.00 3162.00 31.21
(iv) PCC M25 Grade
Case I Using concrete mixer cum 4993.00 3646.00 36.94
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4532.00 3455.00 31.17
(v) RCC M25 Grade
Case I Using concrete mixer cum 5030.00 3676.00 36.83
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4705.00 3590.00 31.06
(vi) PCC M30 Grade
Case I Using concrete mixer cum 5038.00 3680.00 36.90
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4572.00 3486.00 31.15
(vii) RCC M30 Grade
Case I Using concrete mixer cum 5055.00 3695.00 36.81
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4592.00 3502.00 31.13
(viii) RCC M35 Grade
Case I Using concrete mixer cum 5170.00 3783.00 36.66
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4853.00 3703.00 31.06
(ix) RCC M40 Grade 4914.00 3749.00 31.07
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 4792.00 3495.00 37.11
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4199.00 3201.00 31.18
(ii) PCC Grade M25
Page 42 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 3672.00 2841.00 29.25
(ii) Beyond 3m upto 10m depth metre 5286.00 4150.00 27.37
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 6981.00 5482.00 27.34
Page 43 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . 15711.00 12339.00 27.33
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . metre 37326.00 29314.00 27.33
b Add 5% of cost for dewatering of the cost, if required metre 37019.00 29134.00 27.06
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 35256.00 27747.00 27.06
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 0.00 0.00
(ii) Beyond 3m upto 10m depth metre 7595.00 6058.00 25.37
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 10032.00 8001.00 25.38
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour) . metre 22580.00 18011.00 25.37
Add 20% of cost for Kentledge including supports, loading arrangement, and
b Labour etc. metre 53648.00 42792.00 25.37
Page 44 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
b Add 5% of cost for dewatering on the cost, if required metre 35667.00 28614.00 24.65
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 33968.00 27252.00 24.64
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 6899.00 5460.00 26.36
(ii) Beyond 3m upto 10m depth metre 8527.00 6776.00 25.84
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 11262.00 8950.00 25.83
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . metre 25349.00 20148.00 25.81
Add 20% of cost for Kentledge including supports, loading arrangement, and
b Labour etc. metre 8911.00 7083.00 25.81
b Add 5% of cost for dewatering on the cost, if required metre 38500.00 30553.00 26.01
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 36667.00 29098.00 26.01
Page 45 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 6971.00 5498.00 26.79
(ii) Beyond 3m upto 10m depth metre 9366.00 7451.00 25.70
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 12370.00 9841.00 25.70
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . metre 27846.00 22151.00 25.71
Add 20% of cost for Kentledge including supports, loading arrangement, and
b Labour etc. metre 66158.00 52628.00 25.71
b Add 5% of cost for dewatering on the cost, if required metre 41548.00 33019.00 25.83
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 39570.00 31447.00 25.83
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 8434.00 6734.00 25.25
(ii) Beyond 3m upto 10m depth metre 9872.00 7827.00 26.13
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 13037.00 10339.00 26.10
Page 46 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Add 7.5% for every additional meter depth of sinking over the rate of sinking
a for the previous meter metre 24454.00 19393.00 26.10
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . metre 29345.00 23271.00 26.10
Add 20% of cost for Kentledge including supports, loading arrangement, and
b Labour etc. metre 69720.00 55290.00 26.10
'b Add 5% of cost for dewatering on the cost, if required metre 40618.00 31830.00 27.61
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 38684.00 30314.00 27.61
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 19548.00 15809.00 23.65
(ii) Beyond 3m upto 10m depth metre 20583.00 16330.00 26.04
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 27184.00 21566.00 26.05
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . metre 61190.00 48543.00 26.05
Add 20% of cost for Kentledge including supports, loading arrangement, and
b Labour etc. metre 145376.00 115330.00 26.05
Page 47 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 33870.00 26361.00 28.49
b Add 5% of cost for dewatering on the cost, if required metre 83384.00 64896.00 28.49
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 79413.00 61806.00 28.49
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 40174.00 32164.00 24.90
(ii) Beyond 3m upto 10m depth metre 44898.00 35504.00 26.46
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 59296.00 46889.00 26.46
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . metre 133467.00 105541.00 26.46
Add 20% of cost for Kentledge including supports, loading arrangement, and
b Labour etc. metre 317096.00 250750.00 26.46
b Add 5% of cost for dewatering on the cost, if required metre 212320.00 168204.00 26.23
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 202210.00 160194.00 26.23
Page 48 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Add 20% of cost for Kentledge including supports, loading arrangement and
c Labour). metre 461204.00 365374.00 26.23
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 9122.00 7336.00 24.35
(ii) Beyond 3m upto 10m depth metre 9830.00 7879.00 24.76
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for
a the previous meter metre 12983.00 10405.00 24.78
Add 20% of cost for Kentledge including supports, loading arrangement and
b Labour . metre 29223.00 23420.00 24.78
Add 20% of cost for Kentledge including supports, loading arrangement, and
b Labour etc. metre 69429.00 55641.00 24.78
b Add 5% of cost for dewatering on the cost, if required metre 45047.00 35351.00 27.43
Add 25% of cost for Kentledge including supports, loading arrangement and
c Labour ). metre 42902.00 33668.00 27.43
Page 49 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
12.21 Sand filling in wells complete as per drawing and technical specifications cum 884.00 619.00 42.81
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells
12.22 including fabricating and setting out as per detailed drawing tonne 78678.00 52243.00 50.60
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
drawing and technical specifications and removal of excavated earth with all lifts
12.23 and lead upto 1000 m. (Pile diameter-750 mm) metre 4567.00 3654.00 24.99
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
drawing and technical specifications and removal of excavated earth with all lifts
12.24 and lead upto 1000 m. (Pile diameter-1000 mm) metre 7547.00 6017.00 25.43
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
drawing and technical specifications and removal of excavated earth with all lifts
12.25 and lead upto 1000 m. (Pile diameter-1200 mm) metre 9677.00 7672.00 26.13
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete
as per drawing and & Technical Specification (Pile Diameter=500 mm)
12.29 metre 1457.00 1097.00 32.82
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete
as per drawing and & Technical Specification (Pile Diameter=750 mm)
12.30 metre 2545.00 1930.00 31.87
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete
as per drawing and & Technical Specification (Pile Diameter=1000 mm)
12.31 metre 4319.00 3273.00 31.96
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete
as per drawing and & Technical Specification (Size of pile - 300 mm x 300 mm)
12.32 metre 956.00 714.00 33.89
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete
as per drawing and & Technical Specification (Size of pile - 500 mm x 500 mm)
12.33 metre 1669.00 1260.00 32.46
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete
as per drawing and & Technical Specification (Size of pile - 750 mm x 750 mm)
12.34 metre 3204.00 2428.00 31.96
Driven vertical steel piles complete as per drawing and & Technical Specification
(Section of the pile - H Section steel column 400 x 250 mm (ISHB Series) )
12.35 metre 5529.00 3872.00 42.79
Driven vertical steel piles complete as per drawing and & Technical Specification
(Section of the pile - H Section steel column 450 x 250 mm (ISHB Series) )
12.36 metre 6234.00 4365.00 42.82
Page 50 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
12.37 Pile load test on single vertical pile in accordance with IS:2911(Part-IV)
Cement concrete for reinforced concrete in pile cap complete as per drawing and
12.38 Technical Specification
Page 51 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-13
SUB-STRUCTURE
Brick masonry work in 1:3 in sub-structure complete excluding pointing and
13.1 plastering, as per drawing and technical specifications cum 3732.00 2799.00 33.33
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical
13.2 specifications sqm 500.00 319.00 56.74
Stone masonry work in cement mortar 1:3 for substructure complete as per
13.4 drawing and Technical Specifications
Page 52 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Back filling behind abutment, wing wall and return wall complete as per drawing
13.9 and Technical specification
Supplying, fitting and fixing in position true to line and level cast steel rocker
bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH
13.11 specifications complete including all accessories as per drawing and Technical tonne capacity 238.00 196.00 21.43
Specifications.
Supplying, fitting and fixing in position true to line and level forged steel roller
bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH
13.12 specifications complete including all accessories as per drawing and Technical tonne capacity 363.00 294.00 23.47
Specifications.
Supplying, fitting and fixing in position true to line and level sliding plate bearing
with PTFE surface sliding on stainless steel complete including all accessories as
13.13 per drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for tonne capacity 468.00 384.00 21.88
PTFE) and clause 2004 of MoRTH Specifications.
Supplying, fitting and fixing in position true to line and level elastomeric bearing
conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH
13.14 specifications complete including all accessories as per drawing and Technical cubic 0.90 0.80 12.50
Specifications. centimetre
Page 53 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Supplying, fitting and fixing in position true to line and level sliding plate bearing
with stainless steel plate sliding on stainless steel plate with mild steel matrix
13.15 complete including all accessories as per drawing and Technical Specifications. tonne capacity 475.00 384.00 23.70
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing
consisting of a metal piston supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, completre assembly to be of cast
steel/fabricated structural steel, metal and elastomer elements to be as per IRC:
83 part-I & II respectively and other parts conforming to BS: 5400, section 9.1 &
13.16 9.2 and clause 2006 of MoRTH Specifications complete asper drawing and tonne capacity 605.00 490.00 23.47
approved technical specifications.
Page 54 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-
14.1 structure as per drawing and Technical Specification
Page 55 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Page 56 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
High tensile steel wires/strands including all accessories for stressing, stressing
operations and grouting complete as per drawing and Technical Specifications
14.3 tonne 123655.00 93194.00 32.69
Providing and laying Cement concrete wearing coat M-30 grade including
14.4 reinforcement complete as per drawing and Technical Specifications cum 8414.00 6994.00 20.30
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top
of deck slab excluding prime coat with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and laid to required level and
slope after cleaning the surface, including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both
14.5 directions, pressed into surface when the temperature of surfaces not less than 100 sqm 280.00 179.00 56.42
deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)
Page 57 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding
12 mm, true to line and grade, tolurence of vertical RCC post not to exceed 1 in
500, centre to centre spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion, complete as per
14.6 approved drawings and technical specifications. metre 1696.00 1250.00 35.68
Providing, fitting and fixing mild steel railing complete as per drawing and
14.8 Technical Specification metre 3096.00 2119.00 46.11
14.9 Drainage Spouts complete as per drawing and Technical specification each 1451.00 1062.00 36.63
PCC M15 Grade leveling course below approach slab complete as per drawing
14.10 and Technical specification cum 3730.00 2726.00 36.83
14.14 Providing and fixing Helical pipes in voided concrete slabs metre 1722.00 1337.00 28.80
Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete,
semi-rigid crash barrier with metal beam and flexible crash barrier with wire ropes have
14.15 been made and included in chapter-8 on Traffic and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil,
14.16 grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. ) metre 42.00 31.00 35.48
Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20
mm, covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel
plate as per IS: 2062, placed symmetrical to centre line of the joint, resting freely over
the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised
14.17 nails spaced 300 mm c/c along the centre line of the plate, all as specified in clause metre 1152.00 974.00 18.28
2604.)
Providing and filling joint sealing compound as per drawings and technical
(iv) specifications with coarse sand and 6% bitumen by weight metre 20.00 10.00 100.00
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint varying
from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic direction),
covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming to
IS: 2062, asphaltic plug to consist of polymer modified bitumen binder, carefully
selected single size aggregate of 12.5 mm nominal size and a heat resistant foam
14.19 caulking/backer rod, all as per approved drawings and specifications.) metre 1118.00 808.00 38.37
Page 58 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab
steel expansion joint, catering to right or skew (less than 20 deg., moderately curved
with maximum horizontal movement upto 50 mm, complete as per approved drawings
and standard specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the manufacturer's instructions for
14.20 installation and clause 2606 of MoRTH specifications for road & bridge works.) metre 13576.00 10181.00 33.35
Compression Seal Joint (Providing and laying of compression seal joint consisting of
steel armoured nosing at two edges of the joint gap suitably anchored to the deck
concrete and a preformed chloroprene elastomer or closed cell foam joint sealer
14.21 compressed and fixed into the joint gap with special adhesive binder to cater for a metre 2847.00 2078.00 37.01
horizontal movement upto 40 mm and vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm, complete as per approved
drawings and standard specifications to be installed by the manufacturer/supplier or
14.22 their authorised representative ensuring compliance to the manufacturer's instructions metre 11385.00 8908.00 27.81
for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel
expansion joint including anchorage catering to a horizontal movement beyond 70 mm
and upto 140mm, complete as per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised representative ensuring
14.23 compliance to the manufacturer's instructions for installation.) metre 10847.00 8485.00 27.84
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal
expansion joint catering to a horizontal movement beyond 140mm and upto 210mm,
complete as per approved drawings and standard specifications to be installed by the
14.24 manufacturer/supplier or their authorised representative ensuring compliance to the metre 12511.00 9699.00 28.99
manufacturer's instructions for installation.)
Page 59 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection against scour
with stone boulders weighing not less than 40 kg each complete as per drawing
15.1 and Technical specification.
A Boulder laid dry without wire crates. cum 1076.00 676.00 59.17
Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire
crates made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm
15.2 mesh (weaved diagonally) including 10% extra for laps and joints laid with stone cum 2100.00 1523.00 37.89
boulders weighing not less than 40 kg each.)
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with
cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of
15.3 M-15 grade cement concrete with a minimum cement content of 250 kg/cum as per IRC: cum 3957.00 2892.00 36.83
21-2000.)
Providing and laying Pitching on slopes laid over prepared filter media including
boulder apron laid dry in front of toe of embankment complete as per drawing and
15.4 Technical specifications
Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes
on which pitching is laid to prevent escape of the embankment material through the
15.6 voids of the stone pitching/cement concrete blocks as well as to allow free movement of sqm 530.00 471.00 12.53
water without creating any uplift head on the pitching.)
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case
of dry rubble pitching or pitching with stones in wire crates or it can be in PCC M15
nominal mix if cement concrete block have been used for pitching . Rates for toe wall
can be adopted from respective clauses depending upon approved design. The rate for
15.7 excavation for foundation, dry rubble masonry and PCC M15 have been analysed and
given in respective chapters.)
A Rubble stone laid in cement mortar 1:3 cum 3911.00 2684.00 45.72
B Cement Concrete blocks Grade M15 cum 5211.00 3808.00 36.84
15.9 Dry rubble Flooring cum 1372.00 826.00 66.10
15.10 Curtain wall complete as per drawing and Technical specification
A Stone masonry in cement mortar (1:3) cum 3899.00 2753.00 41.63
B Cement concrete Grade M15 cum 3879.00 2835.00 36.83
Flexible Apron :Construction of flexible apron 1 m thick comprising of loose
15.11 stone boulders weighing not less than 40 kg beyond curtain wall. cum 1116.00 684.00 63.16
Page 60 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Gabian Structure for Erosion Control, River Training Works and Protection works
(Providing and constructing gabain structures for erosion control, river training works
and protection works with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m
compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10
sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double twist, mesh size not
15.13 exceeding 100 mm x 100 mm, filled with boulders with least dimension of 200 mm, all cum 4080.00 3170.00 28.71
loose ends to be securely tied with 4 mm galvanised steel wire.)
Page 61 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
CHAPTER-16
REPAIR AND REHABILITATION
Removal of existing cement concrete wearing coat including its disposal
complete as per Technical specification without causing any detrimental effect to
16.1 any part of the bridge structure and removal of dismantled material with all lifts sqm 295.00 40.00 637.50
and lead upto 1000m(Thickness 75 mm)
Guniting concrete surface with cement mortar applied with compressor after
cleaning surface and spraying with epoxy complete as per Technical specification
16.3 sqm 1435.00 555.00 158.56
Providing and inserting nipples with approved fixing compound after drilling
holes for grouting as per Technical specifications including subsequent
16.4 cutting/removal and sealing of the hole as necessary of nipples after completion each 104.00 59.00 76.27
of grouting with Cement/Epoxy
Sealing of crack / porous concrete with Epoxy Grout by injection through nipples
16.7 complete as per clause 2803.1. kg 1288.00 463.00 178.19
Applying epoxy mortar over leached, honey combed and spalled concrete
surface and exposed steel reinforcement complete as per Technical specification
16.8 sqm 434.00 250.00 73.60
16.11 Eproxy bonding of new concrete to old concrete sqm 584.00 313.00 86.58
Providing external prestressing with high tensile steel wires/strands including
drilling for passage of prestessing steel, all accessories for stressing and
16.12 stressing operation and grouting complete as per drawing and Technical tonne 296906.00 210828.00 40.83
specification
Page 62 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
Replacement of sliding plate bearing with mild steel matrix complete as per
Technical Specification including Lifting of superstructure span by jacking up
from below i.e. by placing the jacks on pier/abutment caps for all span length,
Supplying, fitting and fixing in position true to line and level sliding plate bearing
with stainless steel plate sliding on stainless steel plate with mild steel matrix
16.15.5 complete including all accessories as per drawing and Technical Specifications. tonne capacity 535.00 New item
16.16 Rectification of bearings as per Technical specifications each 35498.00 28651.00 23.90
16.17 Replacement of Expansion Joints complete as per drawings metre 2512.00 1507.00 66.69
16.18 Replacement of damaged concrete railing. metre 167.00 82.00 103.66
16.19 Replacement of crash barrier. metre 310.00 146.00 112.33
16.20 Replacement of damaged mild steel railing metre 138.00 69.00 100.00
Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30
grade by cutting and trimming the damaged portion to a regular shape, cleaning the
16.21 area to be repaired thoroughly, applying cement concrete after erection of proper form metre 153.00 108.00 41.67
work.)
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original
16.22 shape.) metre 121.00 88.00 37.50
Page 63 of 563
Summary of Rate Analysis
Descriptions
Rate as per % Increase in
Item No. Unit proposed in BSR Rate as per BSR Rates
June 2010 over BSR
June 2012 June 2010
16.23 Repair of steel Railing (Repair of steel railing to bring it to the original shape) metre 276.00 190.00 45.26
Page 64 of 563