You are on page 1of 4

REBUILDING OF COKE OVEN BATTERY NO.

2 TECHNICAL SPECIFICATION FOR


DSP

(PACKAGE NO: COB2/EXPN/SE-60)


Annexure I Sheet 1 of 3

QUENCHING SYSTEM

FORMAT FOR QUOTATION Technical Part Only


1. 2. Enquiry No. : Offer No. : dated dated

We agree to supply the items indicated hereinafter in sheet-2 of the annexure as per delivery schedule indicated. We agree to all clauses indicated in the technical specification no. ..... and reference drawings listed in the specification including details of inspection excepting those mentioned under deviation/exclusions hereunder. We confirm that commercial part of the tender has been submitted separately. We confirm that unit price and total prices for each of the items mentioned above has been indicated separately as Price part and submitted under a sealed cover. We confirm to furnish the required documentation.

Signature with company stamp Name: Designation: Companys name: Date:

T.S.No. MEC/S/9172/A/10/C1/0619

2011 MECON LIMITED. ALL RIGHTS RESERVED

REBUILDING OF COKE OVEN BATTERY NO. 2 TECHNICAL SPECIFICATION FOR


DSP

(PACKAGE NO: COB2/EXPN/SE-60)


Annexure I Sheet 2 of 3 Scope of Supply and delivery schedule

QUENCHING SYSTEM

Sl. No

Item Descript ion

Qty. quoted for

Unit Wt.

Total Wt.

Drg. Nos.

Delivery 1st Offer lot (Qty. to of sample be indicated in no. of days from sample approval) 7 8

Monthly Total rate of delivery supply period

Remarks

10

11

T.S.No. MEC/S/9172/A/10/C1/0619

2011 MECON LIMITED. ALL RIGHTS RESERVED

REBUILDING OF COKE OVEN BATTERY NO. 2 TECHNICAL SPECIFICATION FOR


DSP

(PACKAGE NO: COB2/EXPN/SE-60)


Annexure I Sheet 3 of 3 Vendor Confirmation

QUENCHING SYSTEM

Bid / offer without this confirmation sheet duly signed & with company seal shall be treated as incomplete offer and shall not be considered for technical / commercial evaluation Description Sl. (B) No (A) 1 Scope of work as per clause nos. 01.04, 04.03, 04.04, 04.05, 04.06, 04.07 & 04.08. 2. Tenderer has visited the DSP site for study of existing Quenching tower # 2, its pump house & Breeze pond for COB#2,before submission of offer. 3. Confirm to supply as per scope under clause no.04.04, 04.05, 04.06, 04.07 & 04.08 4 Confirm to give training on PLC related control system,as per clause no.04.07.3.31 5 Delivery schedule as per clause no. 01.08 8 Submission of drgs. as per scope in clause 03.11, 03.12, 03.13 & 03.14 9 QAP (Quality Assurance Plan) Annexure-III as per clause no. 02.04. 10 Inspection as per clause no. 02.05 12 Acceptance/ confirmation of clauses of TS . Confirmation (C) Alternative proposal by Vendor (D)

Continued.

T.S.No. MEC/S/9172/A/10/C1/0619

2011 MECON LIMITED. ALL RIGHTS RESERVED

REBUILDING OF COKE OVEN BATTERY NO. 2 TECHNICAL SPECIFICATION FOR


DSP Notes: a) b) c)

(PACKAGE NO: COB2/EXPN/SE-60)


Vendor shall fill up column C with word either Agreed or Not agreed as a mark of their confirmation which shall be implemented during execution period. Tenderer may indicate any alternative proposal in column D, if desire. But it is prerogative of MECON / DSP to accept or reject alternate proposal from vendor without providing any reason to vendor. Once the vendor confirmation sheet is filled up & signed by the tenderer, it will be assumed that clauses in this specification are clearly understood by the tenderer. Signature with company stamp Name: Designation: Companys name:

QUENCHING SYSTEM

Date:

T.S.No. MEC/S/9172/A/10/C1/0619

2011 MECON LIMITED. ALL RIGHTS RESERVED