Computerized Measurement Book No. 341 Page No.
51
1ST RA BILL
Work Order No./Dt.: R&B/Tender/Work/Vashi/37 Dt:- 07/10/2024
Start Date: 07-10-2024
Stip. End Date: 06-04-2025
Dt. Of Record: 09-03-2025
Item No.- 03 Providing and laying granular sub-base Grade- I C.B.R. not less than 30% by
providing coarse graded materials, consisting of B.T. crushed stone aggregates
53 mm to 26.5mm @ 35%, 26.5mm to 4.75mm @ 45%, 2.36 mm to below @
20% coarse sand combination and stone dust/grit spreading in uniform
layers with motor grader on prepared surface, mixing by mix in place method
with rotovator at O.M.C. to required dry density including filling the
depressions which occred during the process using vibratory roller 8-T to 10-T
complete as per Clause-401.
Qty as per TMB Pg. No. 31 1549.360 Cum
Total 1549.360 Cum
Item No.- 04 Supplying and stacking of crushed stone aggregates,chippings of 40 to
63mm size of hard stone free of disintegrated pieces deletarious and
organic matter ( for W.B.M. etc.) and grading as per [Link] including
filling the measure boxes with an all lead and
[Link] per TMB
Qty Pg. No. 32 610.500 Cum
Qty as per TMB Pg. No. 35 424.500 Cum
Qty as per TMB Pg. No. 39 424.500 Cum
Total 1459.500 Cum
Item No.- 05 Supplying and stacking of crushed stone aggregates,chippings Type-B of
hard stone free of disintegrated pieces deletarious and organic matter (for
WBM) and grading as per [Link] including filling the measure boxes
with an all lead and lift.
Qty as per TMB Pg. No. 33 130.500 Cum
Qty as per TMB Pg. No. 36 91.500 Cum
Qty as per TMB Pg. No. 40 91.500 Cum
Total 313.500 Cum
Item No.- 06 Supplying and stacking of Stonedust/ binding materials on road site including
filling the measure boxes with an all lead and lift.
Qty as per TMB Pg. No. 34 64.500 Cum
Qty as per TMB Pg. No. 37 45.000 Cum
Qty as per TMB Pg. No. 41 45.000 Cum
Total 154.500 Cum
Measured by Me:-
A R Suva
Shree Swastik Builders - Upleta
Computerized Measurement Book No. 341 Page No.52
Item No.- 07 Spreading the stone aggregates for soiling and W.B.M. including filling the
interstices forming the surface to required camber and gradient
Qty as per TMB Pg. No. 34 741.000 Cum
Qty as per TMB Pg. No. 37 516.000 Cum
Qty as per TMB Pg. No. 41 516.000 Cum
Total 1773.000 Cum
Item No.- 08 Spreading blindage or road crust filling the gaps in metal and leveling to
camber and gradient as directed ( i ) Stonedust
Qty as per TMB Pg. No. 34 64.500 Cum
Qty as per TMB Pg. No. 37 45.000 Cum
Qty as per TMB Pg. No. 41 45.000 Cum
Total 154.500 Cum
Item No.- 09 Rolling and consolidation using vibratory Road Roller 8-10 tonne capacity
(including watering) of (C) water bound macadam ( Layer not exceeding 100 mm
thickness )
Qty as per TMB Pg. No. 34 610.500 Cum
Qty as per TMB Pg. No. 37 424.500 Cum
Qty as per TMB Pg. No. 41 424.500 Cum
Total 1459.500 Cum
Item No.- 10 Providing and applying primer coat with bitumen emulsion on prepared
surface of granular base including cleaning of road surface and spraying
primer @ rate of 0.60Kg./Sq.M. using mechanical means.
Qty as per TMB Pg. No. 45 5627.660 Sqmt
Total 5627.660 Sqmt
Item No.- 11 Providing and laying 37.50 mm thick Built up spray grout in one layer using
black crushed stone aggregate as per gradation and specification
including using bitumen for tackcoat at the rate of 2.5 Kg./10 [Link] BT
surface by mechanical sprayer and bitumen of 80-100 grade mixing at the rate
of 19.90 Kg./ [Link] weight of total mix ( i.e.1.99 % ) including heating and
mixing the aggregate and bitumen by continuous batching drum mix plant,
transporting the mix and spreading the same by paver finisher and
consolidation with vibratory roller including cost of all materials, fuel,
labours,tools and plants. using contractor's own drum mix plant and
machineries etc. complete.
Qty as per TMB Pg. No. 46 49.910 MT
Qty as per TMB Pg. No. 48 372.160 MT
Total 422.070 MT
Measured by Me:-
A R Suva
Shree Swastik Builders - Upleta
Computerized Measurement Book No. 341 Page No.53
Item No.- 12 Providing, laying and rolling of 25 mm thick open graded premix bitumenous
carpet with B.T. aggregate as specified and using bitumen for tackcoat at the rate
of 2.5 Kg./10 Sqmt. on BT surface and using bitumen for mixing with aggregate at
the rate of 3.36 % i.e. 33.60 Kg./ M.T. of total mix including heating and mixing in
drum mix plant, spreading the same with paver finisher and consolidation with
vibratory roller including necessary fire wood, oil, lubricants, labour
charges etc. using contractor's own drum mix plant and
equipment, tools etc. completed in accordance with the requirement of
specification.
Qty as per TMB Pg. No. 49 295.450 MT
Total 295.450 MT
Item No.- 13 Providing and laying seal coat with B.T. aggregate as specified using
aggregate at the rate of 0.18 Cum/ 10 [Link] bitumen for mixing with
aggregate at the rate of 4.5 % i.e. 45.00 Kg./M.T. of total mix including heating
and mixing in drum mix plant and spreading the same by paver finisher and
consolidation with vibratory roller including necessary fire wood, oil,
lubricants, labour charges using contractor's own drum mix plant,
machinaries and equipment, tools etc. complete in accordance with
the requirement of specification.
Qty as per TMB Pg. No. 50 153.320 MT
Total 153.320 MT
Item No.- 15 Providing and filling in foundation with ordinary Cement Concrete M-
100 mix and providing necessary vertical pin headers including
formwork vibrating ramming and curing complete .
Qty as per TMB Pg. No. 42 45.420 Cum
Total 45.420 Cum
Item No.- 16 Providing and casting in situ controlled cement concrete M-250 for average
150mm thick wearing coat laid as directed including tamping,
vibrating,finishing,curing and filling in joints with bitumen complete.
Qty as per TMB Pg. No. 44 90.850 Cum
Total 90.850 Cum
Item No.- 17 Providing Thermo Mechanical Treated Bars ( T.M.T. Bars ) as per I.S. Standard F.E.
415 for temperature reinforcement for Mass concrete Pier / Abutment /
Returns including cutting, bending and tying as required complete.
Qty as per TMB Pg. No. 38 1.895 MT
Qty as per TMB Pg. No. 43 3.044 MT
Total 4.939 MT
Measured by Me:-
A R Suva
Shree Swastik Builders - Upleta
Computerized Measurement Book No. 341 Page No.54
Item No.- 25 Providing and casting in situ Ordinary cement concrete M-200 for average
100mm thick wearing coat laid as directed including tamping, vibrating,
finishing, curing and filling in joints with bitumen complete.
Qty as per TMB Pg. No. 40 37.500 Cum
Total 37.500 Cum
Deputy Executive Engineer
Panchayat (R&B) Sub Division
Dhoraji
Measured by Me:-
A R Suva
Shree Swastik Builders - Upleta