## Foundation Calculations
1. **Excavation (Volume):**
- 230mm walls: 19.55 m³ = Length x Width x Depth
- 115mm walls: 2.34 m³ = Length x Width x Depth
2. **Concrete for Footings (Volume):**
- 230mm walls: 19.55 m³ = Length x Width x Depth
- 115mm walls: 2.34 m³ = Length x Width x Depth
3. **Sand Blinding (150mm thick):**
- 230mm walls: 4.89 m³ = Length x Width x Thickness
- 115mm walls: 0.59 m³ = Length x Width x Thickness
## Superstructure Wall Calculations
1. **Net Wall Area:**
- 230mm walls: 111.93 m² = (Length x Height) - Openings
- 115mm walls: 23.43 m² = (Length x Height) - Openings
2. **Plastering:**
- Internal/External Areas: 135.36 m² = Net wall area x 2 sides (less openings)
3. **Painting:**
- Internal/External Areas: 135.36 m² (three coats applied to plastered surfaces).
## Flooring Calculations
1. **Concrete Slab Volume:**
- 14.37 m³ = Area x Thickness (150mm)
2. **Cement Screed Volume:**
- 2.40 m³ = Area x Thickness (25mm)
3. **Tiling Area:**
- 95.8 m² = Sum of room areas.
## Roofing Calculations
1. **Roof Area:**
- 92 m² = Base Area / cos(Pitch Angle)
2. **Timber Truss Volume:**
- 0.45 m³ based on standard spacing (900mm c/c).
3. **Gutters and Downpipes Length:**
- 25 m based on roof perimeter.
## Doors and Windows Calculations
1. **Doors:**
- D01: 1 unit
- D02: 4 units
- D08: 1 unit
2. **Windows:**
- GW05: 1 unit
- GW08: 1 unit
- GW11: 4 units
- GW13: 1 unit
## Site Works Calculations
1. **Sewer Line Length:**
- 20 m based on site plan.
2. **Pergola Area:**
- 4.5 m² based on site plan.
---
## Material Breakdown (Detailed Calculations)
1. **Bricks:**
- Total Bricks = (Wall Surface Area / Brick Size) + Wastage
- Approximate Total: 8,000 pcs
2. **Cement:**
- Cement Bags = (Concrete Volume + Plaster Volume + Screed Volume) / Mix Ratio
- Approximate Total: 200 bags
3. **Sand and Aggregate:**
- Sand: 17.05 m³ (mortar, plaster, concrete)
- Aggregate: 16.43 m³ (foundation and slab concrete)
4. **Roofing Materials:**
- Chromadek Sheets: 92 pcs
- Timber Truss: 0.45 m³
---
## Notes:
- The calculations consider a standard wastage percentage (5-10%) for materials.
- Adjustments may be required on-site based on practical conditions.